Bridge Imp
Topics covered
Bridge Imp
Topics covered
➢ Stages in Investigation:-
1) Reconnaissance or technical feasibility study.
2) Preliminary or techno economic feasibility.
3) Detailed survey & project report.
➢ Subsurface investigation:-
Following methods are used.
1) Open pits (expensive), it gives complete picture.
2) Bore hole (100 – 150)m spacing.
3) By soundings – Suitable for pre investigation at shallow depth.
4) Geophysical methods – For quick preliminary investigation over large area.
➢ Thumb rule:- B.C of 20 times per m2 assumed at ground level for every one meter depth
increment of 1.5 tonnes per m2 is made.
Investigation depth may be about (1 – 2) times anticipated width of the foundation below the
depth of the foundation.
➢ Choice of bridge:-
1) Approaches
2) Availability of funds
a) Sufficient fund not available – Provide submersible.
b) Causeway bridge.
3) Climatic conditions.
4) Economy in construction.
If river is wide, construction is achieved by putting of roadcome rail bridge.
5) Foundation.
6) Navigation requirements.
7) Types of traffic (30 years record).
8) Specialized firm.
➢ Bridge Hydrology:-
1) Dicken’s formula:- used in north india.
3⁄
Q = Cd A (m3/sec)
4
A = area in km2.
Cd = 6 – 30
2) Ryve’s formula:- used in south india.
2⁄
Q = CR A 3(m3/sec)
A = area in km2.
CR = 6.8 – 10.2
3) Inglis formula:- used in western ghat of Maharashtra.
124A
Q=
√A+10.4
4) Khosla’s formula:-
➢ Determination of velocity:-
1) Float
a) Surface float. b) Sub – surface float.
c) Red floats. d) Twin floats.
2) Pressure instrument.
3) Current meter.
a) From bridge. b) From cable ways.
c) From boats. d) By wading.
➢ Measurement of width:-
1) Strip method:- Suitable upto width 150m.
2) Pivot point method:- If width > 150m.
➢ Empirical formulae for velocity determination:-
1) Manning’s formula:-
1
V = R2/3 S1/2
n
A
R = Hydraulic mean depth =
P
2) Chezy’s formula:-
V = C √RS
3) Lacy’s formula:-
V = 11 R2/3 S1/3
❖ Waterway:-
✓ The area through which the water flows under bridge support is known as waterway.
➢ Linear waterway / Artificial waterway:-
✓ Linear waterway is equal to the sum of all the clear spans.
➢ Natural waterway:-
✓ It is undisturbed area of the river or stream through which the water flows at the bridge
site.
➢ Following points considered during fixing of waterway:-
1) Freeboard for high level bridge ≮ 600mm.
2) Maximum water pass through the bridge.
3) Increasing velocity due to afflux should not exceed the permissible limit.
4) Clearance should be allowed according to navigational requirement.
Discharge (m3/sec) Minimum vertical clearance
(mm)
< 0.3 150
0.3 – 3 450
3.1 – 30 600
31 – 300 900
301 – 3000 1200
> 3000 1500
L = C √Q
➢ Economic Span:-
Overall cost depends upon:-
a) Cost of material.
b) Availability of skilled labour.
c) Span length.
d) Nature of stream.
e) Climatic conditions.
➢ Most economic span length is that, which satisfy the following equation.
➢ Assumptions:-
1) Bridge has equal span length.
2) Cost of superstructure varies as the square of the span length. (Cost ∝ Span2)
(Reason – Design of superstructure depends upon B.M & B.M varies with L2).
3) Cost of flooring & parapets varies directly as the span.
4) Cost of one pier & it’s foundation is constant.
5) Cost of abutment is constant.
➢ Total cost of bridge =
Cost of supporting system of superstructure + Cost of two abutments + Cost of (n – 1)
piers + Cost of approaches, railings & parapet.
P
Economic span (L) = √ or K √P (P = cost of pier)
a1
➢ Scour depth:-
✓ When the velocity of stream exceeds the limiting velocity which the erodible particle to
bed material can stand, the scour occurs.
1) The design discharge being greater than flood. (QD > QF)
2) Increases the velocity due to obstruction.
Case I – Linear waterway of the bridge is not less than the regime width.
In that case,
➢ Depth of foundation:-
✓ It depends upon safe bearing capacity of soil.
✓ According to rankine’s
P 1−Sinϕ 2
Df =
γsoil
(1+Sinϕ)
A) Cohesionless soil
Type of Soil S.B.C (t/m2)
1) Gravel, gravel & sand compact 45
& offering high resistance to
penetration
2) Coarse sand, compact & dry 45
3) Medium sand 25
4) Fine sand, silt 15
5) Loose gravel or sand gravel 25
6) Fine sand, loose & dry 10
B) Cohesive soil
2) Molesworth’s formula
V2 A 2
ha = [ + 0.015] (( ) − 1)
17⋅9 a
➢ Clearance:-
✓ It is a vertical distance between the springing level of earth or bottom of girder & highest
flood level.
Springing level
Clearance Clearance
H.F.L
✓ Structure provided with metallic bearing clearance ≮ 500mm.
1 1
✓ Clearance = (Maximum depth of water) + (Rise of arch)
10 3
➢ Free board:-
✓ Vertical distance between the designed HFL allowing for afflux & level of the crown of
the bridge as it’s lowest point.
Note:- Clearance is associated with lowest point of support, where freeboard concerned with
approaches & bands.
➢ Grip length:-
✓ It is the depth of foundation below maximum scour depth called as grip length.
1
a) For road bridge:- Grip length = maximum scour depth.
3
1
b) For railway bridge:- Grip length = maximum scour depth.
2
Note:-
➢ Class of loading:-
1) Class A – 55.5 tonnes – Permanent bridge.
2) Class B – 33.2 tonnes – Temporary bridge.
3) Class AA – 20.0 tonnes 4) Class 70 R – 70.0 tonnes – (R – Revised)
✓ Wheeled vehicle (Truck, car) .Designed for class AA loading should be checked for class
A loading.
Note:- For class AA
1) The nose to tail spacing between two successive vehicles should not be less than 90m.
2) Maximum loads for the wheeled vehicle equal to 20 tonnes for single axle, 40 tonnes
for double axle spaced not more than 1.2m.
Note:-
1) The nose to tail distance between successive trains should be less than 18.4m.
2) No other L.L consider when a train of vehicle is crossing the bridge.
9
b) Steel Bridge (I) = Imax = 0.545
13.5+L
ii) L > 9m
0.088 L = 45m.
a) If depth of floor is more, impact will be less.
b) If span is more, impact will be less.
c) Speed increases, impact also increases but upto a certain limit.
d) Filling of arch, impact will be less.
e) Hammering action is more in case of railway.
f) Impact is the function of L.L.
0.154 L = 45m.
❖ Tramway:-
✓ No wind load consider when wind velocity > 130 km/hr.
K = 0.051 to 0.095
✓ When effect of WL & EL loads are consider SBC of soil is increased by 25%.
➢ Lateral Loads:-
✓ Force on railing & parapets (1m Height)
✓ H&V force 150 kg/m
✓ Not considered in the designed.
✓ Forces on kerb = 750 kg/m.
➢ Longitudinal forces:-
1) Breaking effect.
2) Frictional resistance offered to the movement of free bearing due to variation in
temperature.
3) Tractive effort:-
a) For single lane & two lane bridge:-
✓ 20% of 1st train load + 10% of the load in succeeding train.
✓ Where entire first train is not on the full span, the breaking force should be taken as
equal to 20% load.
b) For multilane bridge:-
✓ (a) + 5% load excess of two.
✓ These forces consider at height 1.2m.
➢ Centrifugal force:-
✓ Where a road bridge situated on a curve.
WV2
P=
127 R
P
….. a) Road = (1/4), b) Railway = (1/8)
W
S.F = x W
✓ In case of piers & abutments S.F assumed to be direction parallel to the current of flow.
✓ For support of bridge S.F due to L.L in the direction perpendicular to the traffic
consideration.
✓ The superstructure in zone IV & V should be anchored to the piers.
✓ If masonry arch bridge are designed in the zone III, IV & V span ≯ 10m.
➢ Water Pressure:-
V2
Pw = K.W. K = costant. V = velo. in m/s.W = unit wt. of water.g = acceleration due to gravity.
2g
Pw = 520 N/m2
➢ Temperature stresses:-
✓ Temperature stresses developed when free expansion is prevented.
✓ IRC recommendation,
a) Steel structure – Moderate climate – 18O C to 50O C
b)Concrete structure – Moderate climate – 17O C rise & 17O C fall.
Extreme climate – 25O C rise & 25O C fall.
➢ Deformation stresses:-
✓ D.S. considered only for steel bridges.
✓ Called as bending stress.
✓ D.S. ≮ 16 % of D.L & L.L.
➢ Secondary stresses:-
1) For R.C.C bridge –
a) Deformation of certain members. c)Movement of supports.
b) Shrinkage in concrete. d)Time yield in concrete.
2) Steel bridge –
a) Application of load at intermediate points in a panels.
b) Cross girder connected away from panel point.
c) Eccentricity of connection of floor & beam.
d) Effect of wind loads.
e) Movement of the supports.
➢ Railway bridges:-
a) Broad gauge = 1.676m.
b) Meter gauge = 1.000m.
c) Narrow gauge = 0.762m.
➢ Racking force:-
✓ Lateral bracing provided to resist racking force.
✓ R.F = 600 kg/m
➢ Formation width:-
Type of Bridge Rodway Width (Formation
Width)
Single lane bridge 4.25m
Two lane bridge 7.50m
Multilane bridge 7.50m to 3.5m every lane
Pedestrian bridge 2.50m.
✓ L ≯ 45m.
➢ Substructure of timber bridges:-
1) Timber trestles.
2) Timber pile bents (4 piles driven).
3) Cribs (Timber sleepers).
4) Crates.
➢ Suspension bridge:-
✓ L = 500 to 2000 m.
1) Unstiffened – Load transfer by suspenders.
2) Stiffened – Load transfer to cable through medium to trusses.
❖ Culverts:-
✓ Small bridge, span < 6m.
✓ It is used when linear waterway ≯ 12m.
✓ L < 6m – Railway bridge.
✓ L < 5m – Road bridge.
1) Arch culvert:- 2 – 6m.
2) Box culvert:- H ≯ 3m, L = (1 – 4)m.
3) Pipe culvert:- D ≮ 300mm, Q = 10 m3/sec
4) Slab culvert:- L = 8m…Economical, Height of parapet = 750 mm
❖ Scupper:-
✓ Cheap type culvert.
✓ L = (0.9 – 1.0)m.
➢ Bridge superstructure, substructure & adjoining structure:-
1) Substructure:-
✓ The components of bridge upto the level of bearings.
a) Piers.
b) Abutments.
c) Wing wall.
d) Foundation.
2) Superstructure:-
✓ Components of bridge above the bearing.
a) Beam. d) Arch & cable.
b) Girder. e) Guard stone.
c) Parapet wall.
3) Adjoining structure:-
a) Approaches. e) Guide bunds.
b) Guard stone. f) Apron.
c) Bearing. g) Revement for slope at abutment.
d) Training work.
➢ Classification of Bridges:-
1) Arch bridge.
2) Suspension bridge.
3) S.S. bridge.
4) Truss & girder bridge.
1) Arch bridge:-
✓ Stone arch.
✓ Masonry arch.
a) R.C.C – 200m.
b) Steel – 500m.
2) Suspension bridge:-
✓ Suitable for long span (500 – 2000m).
✓ Monkey trains, overhanging branches.
✓ Rope bridge.
✓ Stiffened.
✓ Unstiffened.
✓ Simple suspension.
✓ Under spanned bridge.
✓ Self anchored suspension bridge.
3) Simply supported bridge:-
✓ Cantilever.
✓ Rigid frame.
4) Truss & girder bridge:-
5) Steel bridge:-
✓ Steel arch bridge = 500m.
✓ Steel bow bridge = 240m.
✓ Steel cable = 1200m.
✓ Steel plate girder = 30m.
✓ Steel rolled beam bridge = 10m.
✓ Steel truss bridge = 180m.
✓ Indian railway prefers steel bridge for span 25m.
➢ According to loading:-
a) Class A – 55.5 tonnes.
b) Class B – 33.2 tonnes.
c) Class AA – 20 tonnes.
d) Class 70R – 70 tonnes.
➢ According to alignment:-
✓ Straight / square crossing / right angle crossing.
✓ Skew alignment.
✓ Ѳ ≯ 30O.
➢ According to function:-
✓ Aqueduct.
✓ Viaduct (Bridge over valley, river).
✓ Pedestrian bridge.
✓ Highway bridge.
✓ Railway bridge.
✓ Road come railway bridge.
➢ According to floor:-
1) Deck bridge.
2) Through bridge.
1) Deck bridge:-
✓ Superstructure provided between (F.L & H.F.L).
✓ Floor is at the top of superstructure.
2) Through bridge:-
✓ Sometimes F.L & H.F.L is not sufficient to accommodate superstructure.
✓ Floor is at bottom of superstructure.
✓ Support provided above the F.L.
3) Semi – through bride:-
✓ Support provided partly above & below the F.L.
➢ Arch bridge:-
1) One hinge arch bridge.
2) Two hinge arch bridge
3) Thee hinge arch bridge.
4) Fixed arch (Unyielding).
➢ According to shape:-
✓ Semi – circular.
✓ Segmental.
✓ Pointed.
✓ Semi – elliptical.
✓ Multi – centered.
➢ According to width:-
✓ Barrel type.
✓ Rib type.
➢ According to length:-
✓ Culvert bridge < 6m.
✓ Minor bridge ≤ 30m.
✓ Major bridge > 30m.
✓ Long span bridge > 120m.
✓ Slab bridge (L = 8m).
✓ Girder bridge (L = 10 - 20)m.
➢ Truss:-
✓ N or Pratt truss.
✓ Warren truss.
✓ Bow – string truss.
✓ K truss.
➢ Suspension bridge:-
L L
h= to
10 16
Side span
= 0.17 to 0.50.
Main span
➢ Bridge Bearing:-
Functions of bearings –
✓ Absorb movement of girder.
✓ Allow angular movement of girder due to δ.
✓ Allow longitudinal & transverse expansion due to temperature.
✓ Distribute load over large area.
✓ Keep compressive stresses within safe limit.
✓ To make movement of girder harmless.
✓ To rotate at support to accommodate the δ of S.S. girder.
✓ To make vertical movement due to sinking support.
✓ To transfer the horizontal forces developed due to application of breaks.
✓ Cost of bearing (10 – 15) % of total cost.
1) Fixed bearing:-
✓ It allows angular movement & does not permit longitudinal movement.
o Design of fixed bearing depends upon:-
a) Span.
b) Type of support.
c) Type of structure.
2) Free bearing:-
✓ Free to slide, roll, moves & it thus allow longitudinal movement of the girder.
➢ Types of bearings:-
1) Cement mortar pad:-
✓ Suitable for small span, 30mm thick cement.
✓ Dowel bar 25mm provided.
✓ Length of pad = Width of girder.
✓ Pressure on pad ≯ 18 N/mm2.
2) Expansion bearing:-
✓ It allows free angular as well as longitudinal movements.
✓ Suitable for small spans.
3) Knuckle bearing:- Only angular movement.
4) Rocker bearing (Heavy loading):- Allow angular movement, L > 20m.
5) Rubber bearing:- Life = 30 – 35 years.
6) Sliding bearing:-
✓ Sole plate is provided.
✓ Allows only longitudinal movement.
7) Shallow plate bearing:- L < 12m
8) Deep plate bearing:- L > 12m.
9) Roller bearing:- Allows longitudinal as wall as angular movement.
✓ Machanite bearing.
✓ Armoured steel bearing.
✓ Elastomeric bearing.
✓ Polytetra – fluoro - ethylene (PTFE)
➢ Joints in bridge:-
1) Construction joints.
2) Contraction joints.
3) Expansion joints – Full depth joints.
➢ Railing:-
✓ Minimum height is 1m.
✓ Railing designed to resist lateral & vertical force 150 kg/m.
✓ Joints in railings are provided at 8m interval.
➢ Bridge foundations:-
✓ Minimum grip length.
1
a) Road (LG) = scour depth.
3
1
b) Railway (LG) = scour depth.
2
➢ Inverted Arches:-
✓ Used in soft soil to reduce the depth of foundation.
4) Coffer dam:-
✓ Used for temporary purpose.
✓ Six types of coffer dam.
➢ Bridge substructure & approaches:-
✓ The allowable stresses for masonry & mass concrete are tabulated below.
➢ Bridge piers:-
✓ They are intermediate supports of the superstructure.
1) Solid pier.
2) Open pier:-
✓ Height of pier:- Difference between F.L & bed level.
(Height is above 1.5m above the H.F.L).
✓ Pier batter:- Side of pier may be vertical or batter.
✓ Pier Width:- Sufficient to accommodate the seats of two bearings.
✓ Top width = √Span
➢ Length of pier:-
1
✓ Generally a to times top width beyond centreline of outer trusses plus cut water &
2
ease water.
➢ Open Piers:-
1) Multiple bent or multiple column.
2) Pile bent.
3) Cylindrical piers.
4) Trestle piers.
➢ Abutments:-
✓ They are support of superstructure & Retaining earth on their back.
➢ Classification of abutment :-
A) Abutment with wing wall.
B) Abutment without wing wall.
A) Abutment with wing wall:-
a) Straight wing wall (Ѳ = 0O) – Small bridge.
b) Splayed wing wall (Ѳ = 45O)
c) Return wing wall (Ѳ = 90O)
B) Abutment without wing wall:-
a) Buried abutment.
b) Box abutment.
c) Tee abutment.
d) Arch abutment.
➢ Conditions of stability:-
1) Crushing.
2) Overturning.
3) Sliding.
➢ Batter on earth side:-
24 x h
1 in
Span
Types of approaches:-
a) Attracting spur:-
o Spur points downstream.
b) Deflecting spur:-
o Short length perpendicular to the river.
c) Repelling spur:-
o Spur points U/P.
➢ Erection of superstructure:-
Erection methods of steel girder:-
➢ Rolling:-
✓ For continuous bridges & for crossing a viaduct by providing necessary bearings on
the supports.
✓ It also referred incremental launching method.
✓ Suitable for span 90m to 120m.
➢ Staging:-
✓ Depth of water during the construction is shallow.
✓ Ht. of superstructure above the bed level should not be more.
✓ Suitable for S. S span.
➢ Following are the methods which are applied to workout safe bearing capacity.
1) Correlation method.
2) Load testing method.
3) Critical method.
4) Theoretical method.