FMEA
FMEA
[Link] Part Code Part Name Photograph Qty Domain IS Standard 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Material CRC-DD
Aesthetics
Hardness
Brazing Area
Brazing
Perpendicularity (BP)
Front Plate Height (BP)
Acid Cleaning
Aesthetics
Buffing
Hardness
Stress Relieving
project:
Operation
Part name:
Description Product characteristics
Material tag
(Identification & Traceability)
Material as per requisition slip
Receiving Of Child
Qty as per Tag and requisition slip
Parts
Asthetics
(No Rust, No Dents, No Scratch)
Inner U Size
Middle Resizing
with Gauge
Aesthetics
Buffing
Transfer To Next
Operation
project:
Operation
Part name:
Description Product characteristics
Material tag
(Identification & Traceability)
Material as per requisition slip
Receiving Of Child
Qty as per Tag and requisition slip
Parts
Asthetics
(No Rust, No Dents, No Scratch)
Dimension #2
Both faces should Butt together
Dimension # 4 (On both sides)
Spot Welding
Spot Welding Nugget ( 6 Spots )
Maximum Displacement in Staple Guide Assy
Spot Welding
Transfer To Next
Operation
project:
Operation
Part name:
Description Product characteristics
Material tag
(Identification & Traceability)
Material as per requisition slip
Receiving Of Child
Qty as per Tag and requisition slip
Parts
Asthetics
(No Rust, No Dents, No Scratch)
Transfer To Next
Operation
project:
Operation
Part name:
Description Product characteristics
Material tag
(Identification & Traceability)
Material as per requisition slip
Receiving Of Child
Qty as per Tag and requisition slip
Parts
Asthetics
(No Rust, No Dents, No Scratch)
Aesthetics
Belt Grinding
Aesthetics
Surface Grinding
Blackening
Transfer To Next
Operation
PHT-150
Staple Guide + Front Plate Assy
Specification
SC
SC
SC
SC
0.1 mm BP SC
0.1 ± 0.05 BP SC
BP SC
0.1 mm BP SC
BP SC
BP SC
0.1|Z BP SC
0.1 ± 0.05 mm BP SC
No Precipitate Marks to be
there on part
36-45 HRC SC
0.1|Z BP SC
PHT-150
Middle + Tensioner Assy
Specification
SC
SC
SC
SC
2.8 mm BP SC
0.1 mm BP SC
17.85 + 0.1 mm BP SC
11 ± 0.1 mm
No Sharp Edges
PHT-150
Staple Guide Assy + Middle Assy
Specification
SC
SC
SC
SC
10.50 mm BP SC
0.3 mm BP SC
Ø 5.60 -0.00-0.05 BP SC
262.40 mm BP SC
Ø 4 mm BP SC
BP SC
20.20 ± 0.10 mm BP SC
20 % of Min Sheet Thickness ES SC
2 Welding Tacks
PHT-150
Middle Holder Assy + Middle Bracket
Specification
SC
SC
SC
SC
15.0 mm BP SC
12.0 mm BP SC
1.35 -0.00 -0.05 mm BP SC
11 ± 0.05 mm BP SC
0.05 mm BP SC
BP SC
BP SC
5.6 mm BP SC
20 % of Min Sheet Thickness ES SC
No Extra Welding On the Side
BP
Surfaces
Asthetics
Rusty/ Dent/ Scratch on material
(No Rust, No Dents, No Scratch)
20 Projection Welding
(Staple Guide + Front
Perpendicularity with respect to Z Front Plate Flatness Operator Skill Machine Condition Fixture Condition Height Gauge Accuracy
Plate )
Dimple Height
Dimension # 3 Slot Cut of Staple Guide Operator Skill Electrode Condition Height Gauge Accuracy
Position with respect to Y Front Plate Side Slot Over Size Fixture Condition
Air Pressure
Projection Welding Nugget Dimensions Staple Guide Dimple CD Machine Condition Air Pressure Vernier Calliper Accuracy
Current
Heat %
Hold Cycle
Weld Cycle
Off Cycle
Squeeze Cycle
Electrode Condition
Quenching Media
Flux
Perpendicularity (BP) NG Child Parts Operator Skill Torch Condition Fixture Condition Height Gauge Accuracy
Front Plate Height (BP) NG Child Parts Operator Skill Height Gauge Accuracy
40 Acid Cleaning /
Pickling
50 Buffing
No Precipitate Marks to be there on part Operator Skill Machine Condition Buffing Wheel Condition
60 Stress Relieving
Hardness Oily Material Machine Condition Relieving Temperature Hardness Tester Accuracy
Relieving Time
70 Surface Grinding
Perpendicularity with respect to Z (BP) Operator Skill Machine Condition Grain Size
Wheel Width
Transfer To Next
Operation
1. Stick Bin Tag
2. Handover The
Material
Kangaro Group of Companies (KGOC) Doc. No
Rev. No
FC/PE/TA-182.6A
01
Operation Characterstics
Machine Used Source of Incoming Variation Symbol
No. Description No. Product Process Class
Wrong requisition 10.01 Material Identification Tag …….
Dimple Height 20.03 Front Plate Face should Butt with Staple Guide(BP) SC
Front Plate Blank Over Size 20.05 Projection Welding Nugget Dimensions(BP) SC
Burr at Staple Guide Face 20.06 Faces Should remain inside the the Staple Guide(BP) SC
20.12 Current
20.13 Heat %
30.08 O2 + LPG
30.09 Flux
40 Acid Cleaning / Pickling Manual Follow Acid Cleaning Process from Blackening PFC
Parts with Dust and Oil 70.01 Perpendicularity with respect to Z (BP) SC
Surface Grinder + 70.02 Grain Size
70 Surface Grinding
Vice
Surface Grinder +
70 Surface Grinding
Vice 70.03 Grinding Wheel Width
13 of 25
Revision History
Rev. No. Rev Date Revision Details Revised By Verified By Approved By
Kangaro Group of Companies (KGOC) Doc. No
Rev. No
PF/PE/TA-182.6A
01
Part Number 182.6 A Part Rev # 01 Plant Kanin india Type Origin Date 27-11-2021 14 of 25
Part Description Projection Welding (F Plate + S Guide) Section Welding Shop Proto Type Key Date
Project Number PHT-150 Mr. Arvind, Mr. Tariq, Mr. Jaskaran, Mr. [Link], Mr. Manpreet, Mr. Gian Pre Launch ### Cust App Date
CFT singh,
Project Description Stanely hammer tacker Production
Action Priority
Potential Current Process Current Process
Occurrence
Operation Action Results
Detection
Potential Causes Controls Controls Resp. &
Potential Recommended
Class
RPN
Requirement Failure Mode Effect(s) of Severity Actions Target
Failure Mechanism of Date
No Function Failure Prevention Detection Action Taken Sev Occ Det AP
20 Projection Perpendicularity Perpendicularity
Welding with respect to More
(Staple Z(BP) 1. Operator Skill
Guide + Evaluation (Type B)' 1. Manpower Skill Matrix
Front Plate ) Next Process: Monitoring Manpower Skill Matrix
8 Operator Skill No Control 10 6 480 H HR/ Prod. 8 3 5
100 % Reject [Link] Piece approval 2. Manpower Change and Change Point System
and Patrol Inspection Matrix
(Type B)
1. Preventive
Maintenance of Machine
Subsequent as per Schedule
Predictive Maintenance
Process : 1 Machine Condition No Control 10 (Type B) 6 480 H Maint. Predictive Maintenance 8 4 6
of Machine
NA 2. First Pueve Approval
and Patrol Inspection
(Type B)
8 SC
Preventive Maintenance Predictive maintenance
Customer (Plant): Predictive Maintenance
8 Fixture Condition No Control 10 of Fixture as per plan 6 480 H of Fixture to be Tool Room 8 4 6
100 % Reject as per Decided frequency
(Type B) implemented
Safety &
Daily Calibration with Scheduled Calibration
Regulatory: Height Gauge
1 Master 2 plan 6 96 M
No Discemible Accuracy
(Type A) (Type B)
effect
1. Operator Skill
Evaluation (Type B)' 1. Manpower Skill Matrix
Next Process: Monitoring Manpower Skill Matrix
8 Operator Skill No Control 10 6 480 H HR/ Prod. 8 3 5
100 % Reject [Link] Piece approval 2. Manpower Change and Change Point System
and Patrol Inspection Matrix
(Type B)
1. Preventive
Maintenance of Fixture
as per Plan
(Type B)
Subsequent 50 Strokes Dressing 2. First Piece Approval
Electrode and Patrol Inspection
Process : 1 Alarm 2 6 96 M
Condition (Type B)
NA (Type A)
Dimension More 8 SC
End User :
8
100 % Reject
1. Operator Skill
Evaluation (Type B)' 1. Manpower Skill Matrix
Next Process: Monitoring Manpower Skill Matrix
8 Operator Skill No Control 10 6 480 H HR/ Prod. 8 3 5
100 % Reject [Link] Piece approval 2. Manpower Change and Change Point System
and Patrol Inspection Matrix
(Type B)
1. Preventive
Subsequent 50 Strokes Dressing Maintenance of Fixture
Electrode as per Plan
Process : 1 Alarm 2 6 96 M
Condition (Type B)
NA (Type A)
2. First Piece Approval
and Patrol Inspection
Dimension Less 8 SC
Daily Calibration with Scheduled Calibration
Customer (Plant): Height Gauge
8 Master 2 plan 6 96 M
100 % Reject Accuracy
(Type A) (Type B)
End User :
Loss of Primary
8
Function
Safety &
Regulatory:
1
No Discemible
effect
Subsequent
Process : 1
NA
Front Plate Face
should Butt with No Butt 8 SC
Staple Guide(BP) Customer (Plant):
8
100 % Reject
End User :
Loss of Primary
8
Function
Safety &
Regulatory:
1
No Discemible
effect
Customer (Plant):
8
100 % Reject
End User :
Loss of Primary
8
Function
Safety &
Regulatory:
1
No Discemible
effect
1. Preventive
Maintenance of Machine
as per Schedule
Next Process: Predictive Maintenance
4 Machine Condition No Control 10 (Type B) 6 0 H Maint. Predictive Maintenance 8 4 6
100 % Rework of Machine
2. First Pueve Approval
and Patrol Inspection
(Type B)
End User :
First Piece Approval and
Loss of Primary Panel Digital Controls
8 Heat % 2 Patrol Inspection 6 96 M
Function (Type A)
(Type B)
1. Preventive
Maintenance of Fixture
as per Plan
(Type B)
50 Strokes Dressing 2. First Piece Approval
Electrode and Patrol Inspection
Alarm 2 6 96 M
Condition (Type B)
(Type A)
Subsequent
Process : 1
NA
Faces Should
remain inside the
Faces not Inside 8 SC
the Staple
Guide(BP)
Customer (Plant):
8
100 % Reject
End User :
Loss of Primary
8
Function
Safety &
Regulatory:
1
No Discemible
effect
30 Brazing Aesthetics Degraded Function 1. Operator Skill
(Staple : Evaluation/ Matrix
Guide + Aesthetically Part 1. Manpower Skill Matrix
Record Sheet (Type B)'
Front Place not good due to Next Process: Monitoring
Sub over brazing 2. Manpower Change
No Discemible 1 Operator Skill No Control 10 [Link] Training 6 420 H HR/ Prod.
Assembly) Sheet
Effect (Type B)
3. Frequently Manpower 15 of 25
[Link] Sample
Training
(Type B)
Subsequent
Process :
Preventive Maintenance Predictive maintenance
Production may
7 Fixture Condition No Control 10 of Fixture as per plan 6 420 H of Fixture to be Tool Room
has to be sorted
(Type B) implemented
and less than
100% Scrap
7
Customer (Plant):
Sorting, Line
5
Shutdown for 1
hour
End User :
Very objectionable
4
appearence
Safety &
Regulatory:
1
No Discemible
effect
8 sc
1. First Piece Approval
Customer (Plant): Flow Gauges at Cylinder
5 O2 + LPG No Control 10 and Patrol Inspection 6 480 H Prod
Line Shut Down to Set and Calibrate
(Type B)
End User :
Loss of Primary
8
Function
Safety &
Regulatory:
1
No Discemible
effect
Subsequent
Preventive Maintenance Predictive maintenance
Process :
5 Fixture Condition No Control 10 of Fixture as per plan 6 420 H of Fixture to be Tool Room
Less than 100%
(Type B) implemented
rework
7
Customer (Plant):
6 Flux No Control 10 No Control 10 700 H Prod
Line Shut Down
End User :
Degradation of 7
primary Function
Safety &
Regulatory:
1
No Discemible
effect
8
Customer (Plant):
6 Flux No Control 10 No Control 10 800 H Prod
Line Shut Down
End User :
Loss of primary 8
Function
Safety &
Regulatory:
1
No Discemible
effect
Perpendicularity Perpendicularity
(BP) More
1. Operator Skill
Evaluation (Type B)' 1. Manpower Skill Matrix
Next Process:
Monitoring Manpower Skill Matrix
No Discemible 1 Operator Skill No Control 10 6 480 H HR/ Prod. 8 3 5
[Link] Piece approval 2. Manpower Change and Change Point System
Effect
and Patrol Inspection Matrix
(Type B)
1. Preventive
Maintenance of Machine
Subsequent as per Schedule
Predictive Maintenance
Process : 1 Torch Condition No Control 10 (Type B) 6 480 H Maint. Predictive Maintenance 8 4 6
of Machine
100 % Reject 2. First Pueve Approval
and Patrol Inspection
(Type B)
8 sc
Preventive Maintenance Predictive maintenance
Customer (Plant): Predictive Maintenance
8 Fixture Condition No Control 10 of Fixture as per plan 6 480 H of Fixture to be Tool Room 8 4 6
100 % Reject as per Decided frequency
(Type B) implemented
End User :
Timely Planned
Loss of Primary Gas Pressure Regulator Machine Set up Approval Regulator Installation at
8 Gas Flow Regulator 7 6 336 H Calibration of Gauges Maint. 8 3 6
Function (Type A) (Type B) place
and Regulators
Safety &
Daily Calibration with Scheduled Calibration
Regulatory: Height Gauge
1 Master 2 plan 6 96 M
No Discemible Accuracy
(Type A) (Type B)
effect
Subsequent
Process : 8
100 % Scrap
8 sc
Customer (Plant):
8
100 % Reject
End User :
Loss of Primary
8
Function
Safety &
Regulatory:
1
No Discemible
effect
1. Preventive
Maintenance of Machine
Subsequent
as per Schedule
Process : Predictive Maintenance
Triggers Minor
3 Machine Condition No Control 10 (Type B) 6 180 M
of Machine
Maint. Predictive Maintenance 3 4 6 16 of 25
2. First Pueve Approval
reaction plan
and Patrol Inspection
(Type B)
3
Customer (Plant): First Piece Approval and
Buffing Wheel
Triggers Minor 3 No Control 10 Patrol Inspection 6 180 M
Condition
reaction plan (Type B )
End User :
Moderately
3
objectionalble
Safety &
Regulatory:
1
No Discemible
effect
Subsequent
Process :
First Piece Approval and
100 % of the Relieving Panel Digital Controls
6 2 Patrol Inspection 6 96 M
Production may Temperature (Type A)
(Type B)
Have to be
reworked
8 SC
First Piece Approval and
Customer (Plant): Panel Digital Controls
8 Relieving Time 2 Patrol Inspection 6 96 M
100 % Reject (Type A)
(Type B)
End User :
Daily Calibration with Scheduled Calibration
Loss of Primary Hardness Tester
8 Master 2 plan 6 96 M
Function Accuracy
(Type A) (Type B)
Safety &
Regulatory:
1
No Discemible
effect
Hardness Less
1. Preventive
Maintenance of Machine
Next Process: as per Schedule
Predictive Maintenance
No Discemible 1 Machine Condition No Control 10 (Type B) 6 420 H Maint. Predictive Maintenance 8 4 6
of Machine
Effect 2. First Pueve Approval
and Patrol Inspection
(Type B)
Subsequent
Process :
First Piece Approval and
100 % of the Relieving Panel Digital Controls
6 2 Patrol Inspection 6 84 M
Production may Temperature (Type A)
(Type B)
Have to be
reworked
7 SC
First Piece Approval and
Customer (Plant): Panel Digital Controls
6 Relieving Time 2 Patrol Inspection 6 84 M
100 % Rework (Type A)
(Type B)
End User :
Daily Calibration with Scheduled Calibration
Degradation of Hardness Tester
7 Master 2 plan 6 84 M
Primary Function Accuracy
(Type A) (Type B)
Safety &
Regulatory:
1
No Discemible
effect
1. Preventive
Maintenance of Machine
Subsequent as per Schedule
Predictive Maintenance
Process : 8 Machine Condition No Control 10 (Type B) 6 480 H Maint. Predictive Maintenance 8 4 6
of Machine
100 % Reject 2. First Pueve Approval
and Patrol Inspection
(Type B)
8 SC
Mentioned on Wheel First Piece Approval and
Customer (Plant):
8 Grain Size and Work Instruction 4 Patrol Inspection 6 192 M
100 % Reject
(Type B) (Type B)
End User :
Mentioned on Wheel First Piece Approval and
Loss of Primary
8 Wheel Width and Work Instruction 4 Patrol Inspection 6 192 M
Function
(Type B) (Type B)
Safety &
Regulatory:
1
No Discemible
effect
Revision History
Rev. No. Revision Date Revision Details Revised By Verified By Approved By
01 25-2-2022 Operation 50,60,70 Added Mr. Jaskaran Mr. Aditya Mr. Tariq
Kangaro Group of Companies (KGOC) Doc. No
Rev. No
CP/PE/TA-182.6A
01
Class
No Description No Product Process Specifications & Data Recording Responsibility
Method Size Freq Method
Tolerance
20 Projection Projection
Welding Welding Machine FPA
(Staple Guide + (PW-04) 2 (Start of Quality Inspector
Front Plate ) Shift)
Self
2 (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
2 (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
2 (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
2 (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
2 (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
2 (Every 15 operator
minutes)
1. Operator Skill
Evaluation (Type
B)'
Inform Production Supervisor ,Train
20.07 … Operator Skill Level 3 / Level 4 Operator Skill 1 As per Plan FORMAT Prod Supervisor the operator and Evaluate the
Matrix [Link] Piece
Performance as per Freezed system
approval and
Patrol Inspection
(Type B)
1. Preventive
Maintenance of
Machine as per
Inform Production Supervisor and
1. No Parameters FPA Schedule Machine Condition
20.08 Machine Condition Fluctuation Visual/Tactical 1 (Start of (Type B) check sheet Quality Inspector Quality Person follow " Process for
control of Non conforming
2. No Loose Parts Shift) 2. First Pueve FORMAT
products"
Approval and
Patrol Inspection
(Type B)
Welding fixture
Preventive Stop & ^Inform Production
[Link] Wear / Tear, Fixture & Tool
20.09 Fixture Condition Visual & tactical start of production Maintenance of Quality Inspector Supervisor and Quality Person
Spatter on the fixture inspection check
Fixture as per plan follow " Process for control of Non
2. sheet
(Type B) conforming products"
1. Preventive
Maintenance of
Inspect the Instrument, If able to
Fixture as per Plan
Electrode Dressing calibrate then Dispatch for
20.11 Electrode Condition Flat from Tip Visual/Tactical 1 Every 50 (Type B) Quality Assurance calibration , otherwise discard the
Check sheet
(No Buljing) Strokes 2. First Piece
FORMAT Instrument from master list and
Approval and
scrap
Patrol Inspection
(Type B)
FPA
2 First Piece Quality Inspector
(Start of Stop & ^Inform Production
Approval
Vicker hardness Shift) Supervisor and Quality Person
30.02 Hardness sc 36-45 HRC FM/QA/05
testing m/C follow " Process for control of Non
Patrol conforming products" "
2 Patrol Inspection Quality Inspector
(Once/Shift)
FPA
2 First Piece Quality Inspector
(Start of
Approval
Shift)
[Link] at inside the FM/QA/05
both corner of front Stop & ^Inform Production
30.03 plate welded area Visual 2 Patrol Patrol Inspection Quality Inspector Supervisor and Quality Person
Brazing Area (Once/Shift) follow " Process for control of Non
2. Brazing should not
Visible from back side conforming products"
of staple guide
FPA
2 First Piece Quality Inspector
(Start of
Approval Stop & ^Inform Production
Shift)
30.04 Perpendicularity … sc 0.1|Z Height Gauge FM/QA/05 Supervisor and Quality Person
follow " Process for control of Non
Patrol conforming products"
2 Patrol Inspection Quality Inspector
(Once/Shift)
FPA
2 First Piece Quality Inspector
(Start of
Approval Stop & ^Inform Production
Shift)
30.05 Front plate height … sc 0.1 ± 0.05 mm Height Gauge FM/QA/05 Supervisor and Quality Person
follow " Process for control of Non
Patrol conforming products"
2 Patrol Inspection Quality Inspector
(Once/Shift)
1. Operator Skill
Evaluation (Type
B)'
Inform Production Supervisor ,Train
30.06 Operator Skill Level 3 / Level 4 Operator Skill .----- N Prod Supervisor the operator and Evaluate the
Matrix [Link] Piece
Performance as per Freezed system
approval and
Patrol Inspection
(Type B)
Process Control
30.09 Flux Borax Visual start of production Setup verification Check Sheet Quality Inspector
40 Acid Cleaning / Manual Follow Acid Cleaning Process from Blackening Control Plan
Pickling
Process Control
50.01 Aesthetics No Precipitate Marks Visual start of production Setup verification Check Sheet Quality Inspector
to be there on part Stop & ^Inform Production
50 Buffing Cylindrical Buffing Supervisor and Quality Person
Machine follow " Process for control of Non
conforming products"
50.02 Buffing Wheel Type Visual start of production Setup verification Process Control Quality Inspector
Cloth Buffing Wheel Check Sheet
FPA
2 First Piece Quality Inspector
(Start of Stop & ^Inform Production
Approval
Vicker hardness Shift) Supervisor and Quality Person
60.01 Hardness sc 36-45 HRC FM/QA/05
testing m/C follow " Process for control of Non
Patrol conforming products" "
2 Patrol Inspection Quality Inspector
(Once/Shift)
60 Stress Relieving Heating Furnace
60.02 Stress Relieving Furnace Display start of production Setup verification Process Control Quality Inspector
Temperature 250°C Check Sheet Stop & ^Inform Production
Supervisor and Quality Person
follow " Process for control of Non
Process Control conforming products"
60.03 Stress Relieving Time 30min Furnace Timer start of production Setup verification Quality Inspector
Check Sheet
FPA
2 First Piece Quality Inspector
(Start of
Approval Stop & ^Inform Production
Shift)
70.01 Perpendicularity with … sc 0.1|Z Height Gauge FM/QA/05 Supervisor and Quality Person
respect to Z (BP) follow " Process for control of Non
Patrol conforming products"
2 Patrol Inspection Quality Inspector
(Once/Shift)
CD - Centre
Disannce "@ " marked F- Critical
UTS - Ultimate HV - Vicker Hardness (Unit of TDS - Total RG-Receiving gauge
(Hole to pH - measurement of acidity or dimension to be for Function MTS :Material
^Abbreviation Hole, Hole
Tensile Strength DVC-DigitaL
alkanity, measurement of hydrogen
Hardness given by the Test Dissolve Solids SP-Standard Pin
observe nd A: Critical
VMS: Vision
Technical " * "Parameter to be
used to
(Stress at which Vernier Calliper
ion concenteration of a solution
known as Vicker Pyramid (any mineral, salt, PG-Plug gauge
update after for
Measuring System
Specification validate in Production lot
material Breaks Number) metal) HG- Height Guge
Functional validation in trials Assembly
Edge)
Revision History
Rev. No. Revision Date Revision Details Revised By Verified By Approved By
01 25-2-2022 Added operation 60 & 70 Mr. Jaskaran Mr. Aditya Mr. Tariq
Kangaro Group of Companies (KGOC) Doc. No CP/PE/TA-182.11A
Rev. No 01
Class
No Description No Product Process Specifications & Data Recording Responsibility
Method Size Freq Method
Tolerance
20 Spot Welding Projection Weld
(Middle + Machine FPA
Tensioner) (PW-04) 2 (Start of Quality Inspector
Shift)
Self
2 (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
2 (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
2 (Every 15 operator
minutes)
1. Operator Skill
Evaluation (Type
B)'
Inform Production Supervisor ,Train
20.04 …. Operator Skill Level 3 / Level 4 Operator Skill 1 As per Plan FORMAT Prod Supervisor the operator and Evaluate the
Matrix [Link] Piece
Performance as per Freezed system
approval and
Patrol Inspection
(Type B)
1. Preventive
Maintenance of
Machine as per
Inform Production Supervisor and
1. No Parameters FPA Schedule Machine Condition
20.05 Machine Condition Fluctuation Visual/Tactical 1 (Start of (Type B) check sheet Quality Inspector Quality Person follow " Process for
control of Non conforming
2. No Loose Parts Shift) 2. First Pueve FORMAT
products"
Approval and
Patrol Inspection
(Type B)
1. Preventive
Maintenance of
Inspect the Instrument, If able to
Fixture as per Plan
Electrode Dressing calibrate then Dispatch for
20.14 Electrode Condition Flat from Tip Visual/Tactical 1 Every 50 (Type B) Quality Assurance calibration , otherwise discard the
Check sheet
(No Buljing) Strokes 2. First Piece
FORMAT Instrument from master list and
Approval and
scrap
Patrol Inspection
(Type B)
operator
1. Operator Skill
Evaluation (Type
B)'
Inform Production Supervisor ,Train
30.02 Operator Awareness Level 3 / Level 4 Operator Skill 1 As per Plan FORMAT Prod Supervisor the operator and Evaluate the
Matrix [Link] Piece
Performance as per Freezed system
approval and
Patrol Inspection
(Type B)
Process Control
40.01 Aesthetics No Sharp Edges Visual/ Feel start of production Setup verification Check Sheet Quality Inspector
Stop & ^Inform Production
40 Buffing Cylindrical Buffing Supervisor and Quality Person
Machine follow " Process for control of Non
conforming products"
40.02 Buffing Wheel Type Visual start of production Setup verification Process Control Quality Inspector
Cloth Buffing Wheel Check Sheet
Revision History
Rev. No. Revision Date Revision Details Revised By Verified By Approved By
01 25-2-2022 Added Operation 30 Mr. Jaskaran Mr. Aditya Mr. Tariq
Part Number 182.3A Part Rev # 00 Plant Kanin india Type Origin Date 15-11-2021
Part Description Spot Weld (Middle + Staple Guide Assy Section Welding Shop Proto Type Key Date
Project Number PHT-150 Mr. Arvind, Mr. Tariq, Mr. Jaskaran, Mr. [Link], Mr. Manpreet, Mr. Gian Pre Launch P Cust App Date
CFT
Project Description Stanely hammer tacker singh, Production
Characteristic Class: CC-Critical ; SC- Significant
Operation/Process Characteristics Method
Equipment Product/Process Sample Size Reaction Plan
Measuring Control
Class
Self
2 (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
2 (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
2 (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
2 (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
2 (Every 15 operator
minutes)
1. Operator Skill
Evaluation (Type
B)'
Inform Production Supervisor ,Train
20.06 … Operator Skill Level 3 / Level 4 Operator Skill 1 As per Plan FORMAT Prod Supervisor the operator and Evaluate the
Matrix [Link] Piece
Performance as per Freezed system 21 of 25
approval and
Patrol Inspection
(Type B)
1. Preventive
Maintenance of
Machine as per
Inform Production Supervisor and
1. No Parameters FPA Schedule Machine Condition
20.07 Machine Condition Fluctuation Visual/Tactical 1 (Start of (Type B) check sheet Quality Inspector Quality Person follow " Process for
control of Non conforming
2. No Loose Parts Shift) 2. First Pueve FORMAT
products"
Approval and
Patrol Inspection
(Type B)
1. Preventive
Maintenance of
Inspect the Instrument, If able to
Fixture as per Plan
Electrode Dressing calibrate then Dispatch for
20.08 Electrode Condition Flat from Tip Visual/Tactical 1 Every 50 (Type B) Quality Assurance calibration , otherwise discard the
Check sheet
(No Buljing) Strokes 2. First Piece
FORMAT Instrument from master list and
Approval and
scrap
Patrol Inspection
(Type B)
Welding fixture
Preventive Stop & ^Inform Production
[Link] Wear / Tear, Fixture & Tool
20.09 Fixture Condition Visual & tactical start of production Maintenance of Quality Inspector Supervisor and Quality Person
Spatter on the fixture inspection check
Fixture as per plan follow " Process for control of Non
2. sheet
(Type B) conforming products"
CD - Centre
Disannce "@ " marked F- Critical
UTS - Ultimate HV - Vicker Hardness (Unit of TDS - Total RG-Receiving gauge
(Hole to pH - measurement of acidity or dimension to be for Function MTS :Material
^Abbreviation Hole, Hole
Tensile Strength DVC-DigitaL
alkanity, measurement of hydrogen
Hardness given by the Test Dissolve Solids SP-Standard Pin
observe nd A: Critical
VMS: Vision
Technical " * "Parameter to be
used to
(Stress at which Vernier Calliper
ion concenteration of a solution
known as Vicker Pyramid (any mineral, salt, PG-Plug gauge
update after for
Measuring System
Specification validate in Production lot
material Breaks Number) metal) HG- Height Guge
Functional validation in trials Assembly
Edge)
Revision History
Rev. No. Revision Date Revision Details Revised By Verified By Approved By
Mr. Jaskaran Mr. Aditya Mr. Tariq
Self
2 (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
2 (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
2 (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
2 (Every 15 operator 22 of 25
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
2 (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
2 (Every 15 operator
minutes)
FPA
1 (Start of Quality Inspector
Shift)
Self
… (Every 15 operator
minutes)
1. Operator Skill
Evaluation (Type
B)'
Inform Production Supervisor ,Train
20.09 … Operator Skill Level 3 / Level 4 Operator Skill 1 As per Plan FORMAT Prod Supervisor the operator and Evaluate the
Matrix [Link] Piece
Performance as per Freezed system
approval and
Patrol Inspection
(Type B)
1. Preventive
Maintenance of
Machine as per
Inform Production Supervisor and
1. No Parameters FPA Schedule Machine Condition
20.10 … Mig Welding Set Visual/Tactical 1 Quality Inspector Quality Person follow " Process for
Fluctuation (Start of (Type B) check sheet
Condition control of Non conforming
2. No Loose Parts Shift) 2. First Pueve FORMAT
products"
Approval and
Patrol Inspection
(Type B)
1. Preventive
Maintenance of
Torch as per
Inform Production Supervisor and
FPA Schedule
20.11 … Torch Condition [Link] Spatter Inside the Visual 2 Quality Inspector Quality Person follow " Process for
(Start of (Type B)
Nozzle control of Non conforming
Shift) 2. First Piece
products"
Approval and
Patrol Inspection Process Control
(Type B) Check Sheet
FM/QA/05
1. Preventive
Maintenance as
per Schedule Inform Production Supervisor and
FPA Machine Condition
20.13 … Wire Feed Rate To be smooth without 1 (Type B) Quality Inspector Quality Person follow " Process for
(Start of check sheet
Interuption 2. First Piece control of Non conforming
Shift) FORMAT
Approval and products"
Patrol Inspection
(Type B)
Self
2 (Every 15 operator
minutes)
1. Operator Skill
Evaluation (Type
B)'
Inform Production Supervisor ,Train
30.02 … Operator Skill Level 3 / Level 4 Operator Skill 1 As per Plan FORMAT Prod Supervisor the operator and Evaluate the
Matrix [Link] Piece
Performance as per Freezed system
approval and
Patrol Inspection
(Type B)
1. Preventive
Maintenance of
Machine as per
Inform Production Supervisor and
1. No Parameters FPA Schedule Machine Condition
30.03 … Mig Welding Set
Fluctuation Visual/Tactical 1 (Start of (Type B) check sheet Quality Inspector Quality Person follow " Process for 23 of 25
Condition control of Non conforming
2. No Loose Parts Shift) 2. First Pueve FORMAT
products"
Approval and
Patrol Inspection
(Type B)
CD - Centre
Disannce "@ " marked F- Critical
UTS - Ultimate HV - Vicker Hardness (Unit of TDS - Total RG-Receiving gauge
(Hole to pH - measurement of acidity or dimension to be for Function MTS :Material
^Abbreviation Hole, Hole
Tensile Strength DVC-DigitaL
alkanity, measurement of hydrogen
Hardness given by the Test Dissolve Solids SP-Standard Pin
observe nd A: Critical
VMS: Vision
Technical " * "Parameter to be
used to
(Stress at which Vernier Calliper
ion concenteration of a solution
known as Vicker Pyramid (any mineral, salt, PG-Plug gauge
update after for
Measuring System
Specification validate in Production lot
material Breaks Number) metal) HG- Height Guge
Functional validation in trials Assembly
Edge)
Revision History
Rev. No. Revision Date Revision Details Revised By Verified By Approved By
01 25-2-2022 Added Operation no. 30 Mr. Jaskaran Mr. Aditya Mr. Tariq
Self
… (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
2 (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
.. (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
… (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
… (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
2 (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
… (Every 15 operator
minutes)
FPA
2 (Start of Quality Inspector
Shift)
Self
… (Every 15 operator
minutes)
FPA
1 (Start of Quality Inspector
Shift)
Self
… (Every 15 operator 24 of 25
minutes)
First Piece
Inform Production Supervisor ,Train
20.10 … Operator Skill Level 3 / Level 4 Operator Skill 1 As per Plan Approval and FORMAT Prod Supervisor the operator and Evaluate the
Matrix Patrol Inspection
Performance as per Freezed system
(Type B)
Welding fixture
Preventive Stop & ^Inform Production
[Link] Wear / Tear, Fixture & Tool
20.13 … Fixture Conditon Visual & tactical start of production Maintenance of Quality Inspector Supervisor and Quality Person
Spatter on the fixture inspection check
Fixture as per plan follow " Process for control of Non
2. sheet
(Type B) conforming products"
FPA
2 First Piece Quality Inspector
(Start of
Approval Stop & ^Inform Production
After Grinding Max. 0.1 Shift)
40.01 Aesthetics … Visual FM/QA/05 Supervisor and Quality Person
mm above Middle
follow " Process for control of Non
Surface Self conforming products"
2 (Every 15 Patrol Inspection Operator
minutes)
40 Surface Grinding Surface Grinder +
Vice
40.02 Grain Size Mentioned on start of production Setup verification Process Control Quality Inspector
120 mm Wheel & Work instruction Check Sheet Stop & ^Inform Production
Supervisor and Quality Person
follow " Process for control of Non
Mentioned on Setup verification Process Control conforming products"
40.03 Grinding Wheel Width 13 mm start of production Quality Inspector
Wheel & Work instruction Check Sheet
Revision History
Rev. No. Revision Date Revision Details Revised By Verified By Approved By
01 22-5-2022 Added operation No. 40 Mr. Jaskaran Mr. Aditya Mr. Tariq