Sample Bridge Hydrology
Sample Bridge Hydrology
907m
Input Data
Design Chainage = 184.907 km
Skew Angle = 0 degree
Catchment Area ,A = 3.000 km2
Proposed span details = 1 20.000 m
0 0.000 m
Pier /internal wall width = 0m
Abutment /External wall width = 1.20 m
Bed level = 346.189 m
A) Empirical Formula
Value of C adopted in the present case 19.000 10.000 (From Article-4 of IRC:SP:13-2004)
Catchment area (M) (Sq Km) 3.000 3.000
Discharge, Q (Cumecs) 43.311 20.801
B) By Rational Method
Area of catchment, A = 3.000 km2 1.158 Mile2
Length of longest stream, L = 2.257 km 1.402 Mile
The fall in level between source and bridge site, H = 15 m 0.009 Mile
Average grade-source to site (in percent) = (H/L)*100 = 0.665
R50(tc) = K x R50(1)
= 39.2 mm
I = 50 year rainfall intensity (mm/hr) lasting for tc hr. duration
= R50(tc)/tc
= 29.061 mm/hr.
Design Flood Discharge ,
Q = 0.278 x C I A
= 16.952 m3/sec
Longitudinal Section
346.700
346.650
346.550
Column M
Linear (Column M)
346.500
346.450
346.400
346.350
100 110 120 130 140 150 160 170 180 190 200
Average Bed Slope of River, S = 0.003200
Manning's Coefficient,n = 0.055 (Rugosity Co- efficient,n table 5.1 of IRC:SP:13-2004)
Discharge by
Chart Title
D) HFL Calculation
Design Discharge = 31.201 cumecs
349.000
348.500
348.000
347.500
347.000
346.500
346.000
345.500
0.000 2.000 4.000 6.000 8.000 10.000 12.000 14.000 16.000
Column D Column E
RL of Existing RL of Modified Area, a Wetted Depth, d
Distance (m) HFL (m)
GL (m) GL (m) (sqm) Perimeter,p (m) (m)
Area after construction,An1* (An1* calculated from RLs which we have considered in
= 22.500 sq m
between the Extream edges of the bridge cross section taken from the topo survey)
Annexure-1
Area, A = 56.37 sq km
Length of longest stream, L = 23.80 km
Height Above
Reduced Datum*
Reduced
Distance Starting Length of Each (Di)=Differenc
Level of (Di-1 + Di) Li x (Di-1 +
Sl No
(*) Reduced level of river bed at the point of study, i.e. 280m
Time from the center of Unit rainfall duration to the peak of Unit Hydrograph
tp = 0.583*[LLc / (S)^0.5]^(0.302)
= 2.287 hrs
say 2.30 hrs
Peak discharge of hydrograph per unit area
qp = 1.914*[tp]^(-0.753)
= 1.027 cumecs per sq km
Width of U. G. measured at 50% maximum discharge ordinate
W50 = 1.849*[qp]^(-0.976)
= 1.80 hrs
Width of U. G. measured at 75% maximum discharge ordinate
W75 = 0.955*[qp]^(-0.792)
= 0.94 hrs
Width of the rising side of U. G. measured at 50% of maximum discharge ordinate
WR50 = 0.738*[qp]^(-0.781)
= 0.72 hrs
Width of the rising side of U. G. measured at 75% of maximum discharge ordinate
WR75 = 0.438*[qp]^(-0.641)
= 0.43 hrs
Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100 Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on
DBFOT pattern under NHDP phase IV
TB = 7.042*[(tp)^(0.559)]
= 11.18 hrs
say 11.00 hrs
Time from start of rise to the peak of unit hydrograph
Tm = tp + tr/2
= 2.8 hrs
Peak discharge of Unit Hydrograph
Qp = qp * A
= 57.87 cumecs
say 58.00 cumecs
1-hr Synthetic
Time (in hrs)
U.G. ordinates 70.00
0.00 0.00
Qp
0.25 1.00
0.50 2.00 60.00
0.75 3.00
1.00 5.00
1.25 7.00
50.00
1.50 10.00
1.75 12.00 75% Qp
2.00 20.00
40.00
2.25 29.00 W75
2.50 43.50
2.75 50.00
50% of Qp
3.00 58.00 30.00
3.25 50.00 W50
3.50 43.50
3.75 35.00 20.00
4.00 31.00
4.25 29.00
4.50 24.00
10.00
4.75 22.00
5.00 19.00
5.25 17.00
0.00
5.50 15.00
0
10
11
12
13
5.75 13.50
6.00 12.50 Column C
6.25 11.50
6.50 10.50
6.75 9.50
7.00 8.50
7.25 7.50
7.50 6.50
7.75 5.50
8.00 4.00
8.25 3.00
8.50 2.00
8.75 1.25
9.00 0.75
9.25 0.50
9.50 0.25
9.75 0.25
10.00 0.25
10.25 0.25
10.50 0.25
10.75 0.25
11.00 0.25
11.25 0.25
11.50 0.25
11.75 0.25
12.00 0.00
Sum 156.38 cumecs ……1
Sum(Qi) = (A*d)/(tr*0.36)
= 156.59 cumecs ……2
Four Laning of jalgaon-Gujarat / Maharashtra Border Section of NH-6 from Km 442.100 Km 649.000 in the state of Maharashtra to be executed as BOT (Toll) projects on
DBFOT pattern under NHDP phase IV
Note: Design loss rate in this zone is recommended as 0.5 cm/hr as per part 3.6 of flood estimation report lower
Narmadha -Tapi sub zone -3b (revised)
Step : - 7 Estimation of base flow
1-hr
U.G. Ordinates effective Direct Runoff
(cumec) rainfall (cumecs)
(cm)
58.00 8.10 469.94
50.00 1.29 64.38
50.00 0.28 14.10
Input Data
A) Empirical Formula
Value of C adopted in the present case 12.000 8.500 (From Article-4 of IRC:SP:13-2004)
Catchment area (M) (Sq Km) 56.372 56.372
Discharge, Q (Cumecs) 246.876 124.967
Longitudinal Section
Avg bed
Cum level
272.500 RD (m) @ C/S (m)
0 272.185
272.000 136 271.015
f(x) = − 0.00328059576328944 x + 271.909224505046
253 270.941
271.500
326 270.925
271.000 433 270.903
605 269.710
270.500 717 269.583
Column I
270.000 Linear (Column I)
269.500
269.000
268.500
268.000
0 100 200 300 400 500 600 700 800
Discharge by
C har t T i tl e
D) HFL Calculation
Design Discharge = 339.454 cumecs
276.000
275.000
274.000
273.000
272.000
271.000
270.000
269.000
268.000
0.000 10.000 20.000 30.000 40.000 50.000 60.000
Column D Column E
E) Afflux calculations
Design Discharge = 216.017 Cumecs
Area of C/S at bridge location = 118.918 Sq.m
Velocity of Water V=Q/A = 1.817 m/sec
HFL = 274.263 m
Bed Level = 270.882 m
Effective Linear waterway provided (no of spans *length of each span
(i.e c/c of bearings))-(no. of piers * width of pier)-(Abutment width)
L provided = 49.250 m
I. Recommendation
Design Discharge, Q = 216.017 cumecs
Design Affluxed HFL = 274.325 m
Average Velocity, Vn2 = 2.080 m/sec
Required vertical clearance = 0.9 m
Minimu soffit level required = 275.225 m