PRE-COMMISSIONING CHECKLIST
PROJECT NAME: JOB NO:
SYSTEM/ZONE:
CONTRACTOR:
VARIABLE AIR VOLUME UNIT
SYSTEM ITEM/TASK YES NO N/A
UNIT CHECK
Visual inspection, no apparent damage
Free of dirt and debris
DUCTWORK
Ductwork complete and leak tested
Duct joint sealant properly installed (gaskets, cleats, sealants bands)
All protective plastic removed from duct openings
All second fix outlets installed
All manual balancing dampers installed and locked 100% open
Flexible ductwork length <3m, minimum 1.5 x diameter bends
Outside air ductwork installed (if applicable)
PIPEWORK
Flushing, venting and chemical treatment complete
Pipework insulated and adequately supported
Correct control valve installed on return, direction correct and operational
Strainer installed and cleaned (c/w test port each side of strainer)
Flow/return isolating valves installed on each coil and set in operational position
High point air vents and low point drains installed on CHW/HHW pipework
Test point installed across coil
Regulating valve open to 100% or flow limiting valve cartridges installed
Flushing loop by-pass valves installed and closed
ELECTRICAL
All power and control wiring completed as per circuit diagram
All connections tight
Controls point to point checks completed
OTHERS
Temperature sensor/controller installed
Ceiling access provided to dampers, valves, actuators, controls, filters etc.
COMMENTS
COMPLETION
Signed Date