NEBOSH IG2 Risk Assessment Report Sample

Ig 2 samples

Uploaded by

rtmjlryl2428
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views28 pages

NEBOSH IG2 Risk Assessment Report Sample

Ig 2 samples

Uploaded by

rtmjlryl2428
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Unit IG2: Risk assessment

Declaration: By submitting this assessment (Parts 1 – 4) for marking I declare that it is entirely my own work. I understand that falsely claiming that
the work is my own is malpractice and can lead to NEBOSH imposing severe penalties (see the NEBOSH Malpractice Policy for further information).

Important note: You must refer to the document ‘Unit IG2: risk assessment – Guidance and information for learners and Learning Partners’ while
completing all parts of this assessment. Your Learning Partner should provide you with a copy, but it can also be downloaded from the relevant
resources section for this qualification on the NEBOSH website.

Part 1: Background

You should aim to complete this section in 150 - 200 words.


Topic Comments
Name of organisation* Advent construction.
Site location* Industrial estate, Faridabad, Haryana, India
Number of workers 300
It is one of the leading and renowned company since 1985 in developing civil works and has delivered many
projects such as residential and commercial projects all across India. The company has only one branch. The
company right now developing a multiplex in 15000 square meter in Haryana where undertaking company
establish its set up by bringing and installing all its required necessities as per the projects ,Lately I have
conducted risk assessment for its undergoing projects where encountered with several malpractices
.Undertaken activities involved such as pile foundation, iron and steel works, fabrication, roof laying,
concrete pouring, electrical and fireworks, plumbing and painting works etc and using all work equipment
General description of the organisation
as per requirements and since projects tenure as a deadline has to be completed within 24 months since
the projects commencement , hence management instructed to work in 2 alternate shift.
The working schedule set for workers;
Working Days – From Monday to Saturday except on Sunday
Working Time- From 9.a.m to 5.p.m -5 [Link] 1.a.m in 2 alternate shift where 1 hrs meal break is included.
Office employee work timing is 6 days in a week from 9.a.m to 5.p.m and if required they could be called to
backend support and is rewarded OT.
Description of the area to be included in the
The entire work process and activities will be covered in risk assessment.
risk assessment
Any other relevant information Project Manager is responsible for managing Health and safety and environment at workplace.

Learner number: Learner name: Sample Report 1 Page 1 of 28


* If you’re worried about confidentiality, you can invent a false name and location for your organisation but, all other inform ation provided must be
factual.

You should aim to complete this section in 100 - 200 words.


Note: this section can be completed after you have competed your risk assessment.
Outline how the risk assessment was carried To complete risk assessment, I took reference from two preferred web pages [Link] and
out this should include: [Link] where collected relevant information that required for Health and safety in construction
 sources of information consulted; and also noted the recommended action to be taken as per the undertaken work activities.

 who you spoke to; and Having collected all information, it was needed to cross evaluate the process and activities by doing visual
 how you identified: inspection to examine whether the safe code of practice is in place or not or meeting all safety standard
- the hazards; with compliance or not , I then visited workplace, and observed the work process and activities and during
- what is already being done; and my inspection I came across with several unsafe act and unsafe conditions at workplace such as some
- any additional controls/actions that workers were doing their job at work height without wearing appropriate PPEs and working platform seems
may be required. to unstable since inspections was last carried out 2 months ago, seeing all I further spoken to some workers
and their supervisor just to know their knowledge regarding Health and safety and their answer didn’t
convince me appropriately as they said “working at height platform is not more than 10 feet hence we have
been working for 2 months and didn’t encounter with any injuries” their answer made me alert that that
there is lack of safety awareness.

Realising workers action I demanded company last risk assessment, current audit report, work equipment
inspection report, workers health reports, absenteeism record and accident/incident book from HSE
Manager to check if any accidents occurred in past and if occurred , were taken control measure for
preventing such reoccurrence and following accident book checking the type of incidents and frequency of
incidents occurred in past and if any of these incident were recuring and also checked the reason of
incident.

Following accident book, I noted and identified the existing hazard and reviewing all my collected
information from available resource, I could be able to asses workplace process and activities and realize
that these all action required additional control measured required to be adapted.

Learner number: Learner name: Sample Report 1 Page 2 of 28


Part 2: Risk Assessment

Organisation name: Advent Construction


Date of assessment: 04/11/2023
Scope of risk assessment: The entire work process and activities.

Hazard category and Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
hazard and how? required? further actions person’s job
to be title
completed
(within …)
1. SLIP AND TRIP Any workers or person Assigned housekeeping 1. All scattered building material such 2 Weeks Housekeeping
might be harmed supervisor is not competent. as parts of scaffold and ladder, cut Supervisor
Inappropriate workplace, whosoever exposed with piece of iron and steel, wires and
poor housekeeping, such inappropriate Workers are being given cables must be properly arranged or
Poor illumination all are workplace conditions. instruction to clean the stacked in place by assigning
source of causing slip trip workplace before leaving their housekeeping officer.
at workplace. Engaged workmen while workplace.
moving at workplace for all 2. Any spillage of oil, solvent and 1 Week Housekeeping
different workplace Spill kit is available but sealant and other lubricant product Supervisor
activities likely to expose workers are not trained about must be frequently removed from
with scattered building its use. workplace.
material such as parts of
scaffold and ladder, cut First aider is available for 3. Advised to provide designated 1 Month Project
piece of iron and steel , minor injured workers. walkway for pedestrian use. Manager
wires and cables, spillage
of oil and other lubricant 4. Advised to modify the workplace 2 Weeks Project
product due to poor ensuring no uneven floor, no obstacles Manager
housekeeping shall be in walkway.
management and
moreover uneven floor and 5. Advised to install proper illumination Electrical

Learner number: Learner name: Sample Report 1 Page 3 of 28


Hazard category and Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
hazard and how? required? further actions person’s job
to be title
completed
(within …)
poorly illuminated at workplace. 2 Weeks Supervisor
workplace where workers
encountered with several 6. A disciplinary action must be taken Project
personal injuries either by against breaching housekeeping rules. 1 Month Manager
tripping over or bump into
cause cuts/bruise/body 7. Advised to provided suitable and HSE Manager
parts fracture, head sufficient housekeeping training must 1 Month
injuries and could be more be given to all worker that include
worse depending the -5s a Japanese concept.
intensity of hitting by -Spill kit training
objects and may be death -Use of PPEs.
occur. 8. Advised to provide all mandatory HSE Manager
PPEs to all workmen that are present 1 Week
at workplace including anti friction
boots etc.
[Link] HANDLING Loaders, mason, helper, Competent and trained young 1. Advised to monitor that no any load 2 Weeks Project
nearby workers might be workers are being engaged in more than 25 kg must be in operation Manager
Inappropriate manual harmed. manual handling operation. by assigning competent person.
handling
technique/obstacles in Engaged loaders are Proper illumination is 2. In case of no such provision in 2 Weeks Site Supervisor
walkway/uneven carrying heavy load that installed. monitoring load exceed limit, all load
floor/heavy load more than contain pointed material, must be broken into smaller load to
25 kg in practice all are hot iron, glass material that First Aider is available. reduce the manual handling impact on
hazardous sources at possess more than 25 kg engaged loader.
workplace. weight for an extended
time period without taking 3. Advised to provide mechanical 2 Weeks Project
rest break, moreover assistance such as trolleys, mini trucks Manager
manual handling operation etc to completely eliminate the manual
is in practice with handling risk.

Learner number: Learner name: Sample Report 1 Page 4 of 28


Hazard category and Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
hazard and how? required? further actions person’s job
to be title
completed
(within …)
inappropriate manual
handling technique on 4. All provided mechanical assistance
uneven floor with obstacle must be inspected by competent 1 Week Project
in walkway person ensuring all are in good Engineer
where workers likely to conditions and meeting the standard
encounter with slip and load limit.
trip that results
cuts/bruise/body parts 5. Advised to give rest break to all
fracture/head engaged workers to avoid the 1 Week HSE Manager
injuries/sprain and stress maximum weight exposure limit on
and burns due to fall of hot worker.
material on foot and due
to heavy load impact on 6. Advised to modify all uneven floor
workers affect other ensuring no any carpentry works or 3 Weeks Project
musculoskeletal injuries. damage on floor to avoid slip trip Manager
It is more likely to hazard and reduce the associated risk
catastrophic results of injuries.
subjected to intensity of
hitting by objects. 7. Advised to ensure that obstacles free
walkway must be during manual 2 Weeks HSE Manager
handling operation with proper
barricading.

8. Advised to provide sufficient and


suitable training to all engaged workers 1 Month HSE Manager
that includes; -
- TILE Assessment- (Tile,
Individual, Load, Environment).
- SWL -Safe Working Load.

Learner number: Learner name: Sample Report 1 Page 5 of 28


Hazard category and Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
hazard and how? required? further actions person’s job
to be title
completed
(within …)
- SSW-Safe System of Work.
- Manual handling technique
- Correct use of PPEs.

[Link] to provide all mandatory


PPEs to all engaged workers such as
safety helmet, safety boots, gloves and 1 Week HSE Manager
reflective jacket.
[Link] Engaged hand held tools All work equipment that are in 1. Advised to eliminate all such 1 Month Project
operators and heavy-duty use are inspected. inappropriate or faulty machines Manager
High frequency noise machines and work causing high frequency noise.
generating from hand held equipment operators such Competent workers are only
tools and heavy-duty as welder, grinder man, allowed to work. 2. Advised to provide standard and 1 Month Project
machines and other work driller, carpenter and suitable work equipment and hand- Manager
equipment. Inappropriate heavy-duty machines Health cheek-up is set up for held tools and machines that shall
or faulty machines in use driver and it also might all workers. produce least noise and shall be as
causing high frequency harm nearby workers or reasonably as safe as practicable
noise. person and any one ensuring safe operation to eliminate
whosoever exposed with the high frequency noise impact.
high frequency noise
80+db. 3. All work equipment and hand-held 3 Weeks Project
tools and machines must be frequently Engineer
Workers likely to inspected ensuring all parts and
encounter with high components are good in conditions by
frequency noise affect competent person.
while using such high
frequency noise hand held 4. Advised to install sound level meter. 2 Weeks Project
tools and heavy duty Engineer
machines during all [Link] to install acoustic booth and 2 Weeks Project

Learner number: Learner name: Sample Report 1 Page 6 of 28


Hazard category and Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
hazard and how? required? further actions person’s job
to be title
completed
(within …)
different constructional guards, sound proof enclosure, Engineer
activities such as welding, acoustic booth, sound barriers by
drilling, grinding, carpentry competent person in noisy area or
works and excavation, workplace.
concrete mixing etc where
engaged workers are 6. Noise survey must be introduced and 3 Month Project
working for prolong period shall be in place and must adapt Manager
of time without taking rest required additional control measure as
break (since rest break is per survey.
not given) moreover
suitable hearing protection 7. Advised to provide rest break at 2 Week HSE Manager
is not worn where workers frequent interval of time by altering
likely to suffer from the job rotation to avoid prolong
temporary and permanent exposure of noise on workers.
hearing loss, NIHL, ringing
in ear, tinnitus, sleeping 8. A proper and suitable training must 1 Month HSE Manager
disorder and sometimes be given to all engaged workers that
cardiac arrest etc. includes;
- Impact of noise on individual
-Safe System of Work.
- Use of Hearing Protection -Aid and
proper maintenance.

[Link] to provide all suitable 2 Weeks HSE Manager


hearing protection aid such as ear plug,
ear defender etc with other mandatory
PPEs.

Learner number: Learner name: Sample Report 1 Page 7 of 28


Hazard category and Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
hazard and how? required? further actions person’s job
to be title
completed
(within …)
[Link] Workers such as welder, Trained and competent 1. Advised to remove all such running 1 Month Project
Grinder man, driller, workers are being engaged on hand-held vibrating tools and work Manager
All running hand held carpenter, heavy duty all hand-held vibrating tools equipment and heavy-duty machines
vibrating tools and work machines operator, drivers and heavy-duty machines. that all causing high vibration impact
equipment and heavy-duty might be harmed. on workers to minimise associated risk.
machines generating high General Inspection and
extensive vibration impact Engaged workers while maintenance are done for all 2. Vibration transmission must be 1 Month Project
on workers’ health. performing several task work equipment. reduced by isolating workstation with manager
such as welding, grinding, shock absorbing pads.
drilling, carpentry work Quarterly health surveillance
with such inappropriate programme is set-up 3. Ergonomically designed workstation 2Weeks Project
hand-held vibrating tools and ergonomics seating arrangement Engineer
and work equipment and must be provided or use anti vibration
heavy-duty machines such Advised to use vibration seat to reduce the associated MSDs
as running bulldozer, isolation technique such as by risk.
concrete mixer that all isolating workstation with
producing extensive shock-absorbing pads to 5. Advised to provide standard 1 Month Project
vibration where workers reduce the vibration machines ensuring least vibration Manager
are operating such transmission to all engaged omission ensuring safe for operation to
machines for prolong workers avoid associated risk of injuries.
period of time without
taking rest break likely to 6. Inspection shall be done by 1 Month Project
encounter with several competent person in place for all Manager
personal injuries such as running hand-held tools and work
loss of sensation, loss of equipment ensuring
grip control in hand, white - No mechanical issues due to which
fingers, Carpel tunnel vibration generates
syndrome numbness, and - Check proper greasing,
hand shivering , and likely - No any loosen parts left

Learner number: Learner name: Sample Report 1 Page 8 of 28


Hazard category and Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
hazard and how? required? further actions person’s job
to be title
completed
(within …)
to suffer HAVs. - Loosen guards are appropriately
tightened before its use.

7. Advised to monitor that worker shall 15days HSE Manager


not spent maximum time on any
machines and tools and shall give rest
break by changing workers
shift/hour/rotation to avoid prolong
impact of vibration.

8. All mandatory PPEs must be provided 2 Weeks HSE Manager


such as warm clothing and anti-
vibration gloves and ensure workers to
must wear.
[Link] Engaged electrical Competent person is being 1. Faulty and inappropriate electrical 2 Weeks Project
supervisor, electrician, engaged in all electrical work tools, device and equipment, live wire Manager
Faulty and inappropriate service engineers, activities. and incorrect installation electrical
electrical tools, device and electrical tools and parts and components must be
equipment in use/damage equipment operators etc No electric work activities are removed from operation instantly to
electrical wire /live wire might be primarily harmed allowed in wet condition and avoid associated risk of electrical
/incompetent person but it might harm anyone strictly prohibited. injuries.
involvement/ incorrect who could expose with
installation electrical parts electricity such as other Warning safety signage as a 2. Advised to provide appropriate, 1 Month Project
and components all are workmen, person, office “DANGER ZONE” near standard and suitable electrical tools, Manager
hazardous factors cause employee etc. electrical control room and in device and equipment, wires and cable
electrical hazard. vicinity. ensuring no cuts and damage, double
Workers while doing insulated wires and cables, all electrical
several electrical works Electrical TBT -Tool Box Talk is spares and components must be
and hot work activities being conducted frequently provided to control the associated risk

Learner number: Learner name: Sample Report 1 Page 9 of 28


Hazard category and Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
hazard and how? required? further actions person’s job
to be title
completed
(within …)
with the provided faulty, prior to start the work. of injuries.
damage or inappropriate
electrical tools and devices All flammable and hazardous 3. Advised to inspect all provided 2 Weeks Electrical
and equipment , moreover, substances are frequently electrical tools, device and equipment, Engineer
at workplace there is removed by assigning all installation of spare and
incorrect installation of housekeeping person. components, supplied wires and cable
electrical parts and must be frequently in practice ensuring
components and live wire all are safe and reasonably-practicable
spread across the Rescue operation team along for safe operation.
workplace where some rescue operation team
incompetent workers are equipment - along with 4. Power cut-out system must be 2 Weeks Electrical
also involved in electrical competent first aider is installed. Engineer
installation where workers available with complete first
likely to encounter with aid kit for minor injured 5. LOTO (LOCK-OUT TAG-OUT) must be 1 Week Project
several personal injuries in place for all electrical work Engineer
depending on the amount, maintenance.
current and path of the
electrical exposure causes 6. Electrical PTW must be effectively in 1 Month Project
several injuries such as practice with compliance ensuring all Manager
electrocution, electric its checklist are meeting the standard.
burn, cardiac arrest and in
worse case death. There 7. Advised to conduct a suitable and 1 Month HSE Manager
could be more injuries if sufficient training for all engaged
electrical fire exposed with workers that includes
flammable substances - Electrical hazard identification
could cause maximum and its prevention.
number of fatalities, harm - Handling with electrical tools
property and environment. and equipment
- SSOW-Safe System of Work

Learner number: Learner name: Sample Report 1 Page 10 of 28


Hazard category and Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
hazard and how? required? further actions person’s job
to be title
completed
(within …)
- LOTO training
- Proper use of PPEs.

[Link] to provide all mandatory 1 Week HSE Manager


PPEs including rubber gloves and
insulated boots for engaged work.
[Link] EQUIPMENTS AND Engaged work machines Only trained workers are 1. Work equipment without safe 3 Weeks Project
MACHINERY operator working with being permitted in handling guard/without authority in operation Manager
inappropriate work with all such inappropriate or any poor selection of work
Work equipment without equipment such as grinder work equipment. equipment must be removed from
safe guard/without man, driller, welder, operation to reduce the risk of
authority in operation service engineer, mechanic A competent monitoring is in entanglement or break down of work
/poor selection of work in repair might be harmed. place to check that engaged equipment to avoid the risk of
equipment/incompetent workers shall not keep long associated injuries.
workers involvement etc. Engaged workers while hair, wear loosen clothing or
engaged with such take any alcohol so to 2. A suitable and standard work 3 Weeks Project
inappropriate work entanglement of these to equipment ensuring all its Manager
equipment such as welding work equipment could be manufacturing instruction meeting its
,drilling and grinding isolated. standard such as all work equipment
machine without installed are safely installed safe guard or with
safe guard and without A warning safety signage must authority must be provided for safe
authority while carrying be displayed on work operation.
welding, drilling and equipment such as “NO
grinding activities TEMPER WITH WORK 3. Advised to carry a periodic and 1 Month Mechanical
moreover incompetent EQUIPMENTS OR ANY OF ITS routine inspection by competent Engineer
workers are also in such PARTS". person for all work equipment
activities where there is ensuring no any mechanical issues
chance of entanglement of Inspection of running work such as no loosing parts, no any repair
work equipment or any of equipment was lastly done 3 to be done, and installed guards

Learner number: Learner name: Sample Report 1 Page 11 of 28


Hazard category and Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
hazard and how? required? further actions person’s job
to be title
completed
(within …)
its parts or could broke months ago. meeting it exceed limit.
down the work equipment
where workers likely to For minor injury, first aider is 4. Proper illumination shall be installed 1 Week Electrical
encounter with several available with complete aid on each equipment and in vicinity Supervisor
personal injuries such as kit. both.
cuts/bruise/amputation
and in worse case other 5.A suitable and sufficient training 1 Month HSE Manager
series injuries could occur. must be given to all such as SSOW with
work equipment upon which workers
supposed to work, use of PPEs etc.

[Link] to provide all mandatory 1 Week HSE Manager


PPEs to all engaged workers.
[Link] Any worker such as Hot work permit is taken and 1. Advised to remove all electrical tools 1 Week Project
engaged work equipment in place. and equipment that are in operations Manager
Frequent hot work operator, lone workers, to avoid associated risk of injuries.
activities with the use of disabled workers, office “SMOKING IS PROHIBITED” as
damaged electrical tools employee or anyone might a warning signage is installed 2. Advised to either keep accumulated 2 Weeks House Keeping
and equipment/short be harmed whosoever at workplace. flammable and hazardous substances Supervisor
circuit/accumulated exposed with fire might be such as thinner, paints, lubricant
flammable material and harmed and it also harm Fire TBT is in practice but fire material etc in steel container or
hazardous substances/hot the property and mock drill was lastly remove from workplace to avoid
work activities in enclosed environment. conducted 3 months ago. catching fire and associated injuries.
room /smoking material etc
are hazardous source of Workers while performing Monitoring fire activities, 3. Advised to provide standard and 2 Weeks Project
causing fire outbreak at several hot work activities there is fire marshal available appropriate electrical tools and Manager
work place. such as welding, drilling, at workplace. equipment ensuring no damaged in
grinding and other suppled wire etc.
electrical work activities in First aider and rescue

Learner number: Learner name: Sample Report 1 Page 12 of 28


Hazard category and Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
hazard and how? required? further actions person’s job
to be title
completed
(within …)
enclosed room (where no operations team is available 4. Advised to install proper ventilation 3 Weeks Project
proper ventilation is for victim. for enclosed room where hot job Manager
installed ) with the activities are being carried out to avoid
maximum use of electrical prolong exposure of toxic gasses,
tools and equipment and smoke and fumes.
use of argon gas cylinder
where flammable material 5. Heat, smoke and fire detection 2 Weeks Project
are also present at devices along with fire alarm system Engineer
workplace and the flame must be installed to detect fire at its
and spark emission initial stage to control the risk of fire
through the activities outbreak and to minimise the injuries.
either due to faulty
equipment or short circuit 6. Advised to install firefighting system 2 Weeks Project
has high likelihood of and equipment such as portable fire Engineer
catching of fire and cause extinguisher, water sprinkler system,
several personal injuries fire ball, fire blanket etc.
depending on the what
level and duration of fire 7. Advised to carry frequent inspection 1 Month Project
exposed to workers results of all provided electrical tools and Manager
injuries such as burns, equipment, fire extinguisher, heat
asphyxiation due to detection device ensuring all are ready
prolong exposure of toxic to use and easy to access.
gas , smoke and fumes and
could be worse if person 8. Advised to provide sufficient and 1 Month HSE Manager
can’t be evacuated in time suitable training apart from Fire TBT
could occur death and such as, to conduct fire mock drill
moreover if fire where PASS theory must be explained
contaminates with other to all workers, to inform about
accumulated flammable emergency evacuation plan, fire exit,

Learner number: Learner name: Sample Report 1 Page 13 of 28


Hazard category and Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
hazard and how? required? further actions person’s job
to be title
completed
(within …)
and hazardous substances escape route and other emergency
turn the fire into fire procedure and services to inform
explosion which could be about emergency number and location
catastrophic results for of first aider and rescue team etc.
property and environment.
[Link] to provide all mandatory 1 Week HSE Manager
PPEs to all engaged workers and other
relevant PPEs such as fire retardant or
fire resistance clothes, approach suit
must be in place for fire fighters and
rescue team person in case of fire
outbreak at workplace.
[Link] AT HEIGHT Engaged workers on Only trained workers are 1. Advised to implement taken PTW 1 Month Project
working platform such as being allowed to work at work with compliance ensuring all adequate Manager
Working on open edges mason, helper, painter, at height platform. precaution have been taken and place.
and uninspected scaffold Plumber, grinder man,
and ladder/working driller, welder, supervisor, PTW is taken but effectively 2. Advised to remove uninspected 2 Weeks Project
without PPEs/poor Engineer and associated not in compliance. scaffold and ladder that is using as a Manager
illumination all are hazard workers and person below working platform.
at workplace. the working the platform Barricading is done where
etc might be harmed. work at height activities is 3. Advised to modify the unprotected 2 Weeks Site Supervisor
being carried. edge by installing safe guards, toe
All engaged workers likely bords and rail guards to minimise the
to encounter several “WORK IN PROGRESS “as risk of fall and control the risk of
injuries while working on prohibition warning signage is associated injuries.
such inappropriate working displayed.
platform without wearing 4. Advised to provide inspected scaffold 2 Weeks Project
suitable PPEs where PPEs are available in and ladder. Manager
working platform is insufficient number moreover

Learner number: Learner name: Sample Report 1 Page 14 of 28


Hazard category and Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
hazard and how? required? further actions person’s job
to be title
completed
(within …)
unprotected and scaffold workers are unaware its 5. Advised to inspect scaffold and 2 Weeks Scaffold
and ladder is using as availability. ladder ensuring all its parts and engineer and
working platform are not components are standard,meeting ladder
inspected and since excess TBT is frequently given. load stability, firm stability with ground inspector
mass movement of must be done prior to star work by
workers is throughout the First aider is available. competent person.
working platform that
could cause collapse of Health rescue team is also 6. Advised to install proper illumination 1 Week Electrical
working platform and available. at both working at height platform and supervisor
increase the risk of falling below the working platform.
of person off the height
either due unprotected 7. Advised to carry risk assessment and 1 Month HSE Manager
edge or collapse of working further act upon on risk finding by
platform cause injuries to taking appropriate control measure.
workers and injuries
depend on what height 8. Advised to encircle the fall arrestor. 1 Week HSE Manager
workers falls cause Project
cuts/bruise/body parts 9. Advised to assign a competent 2 Weeks Manager
fracture/severe head and person for monitoring work at height
spinal injuries/disability activities including no workers shall
and in worse case death work without wearing suitable PPEs.
occur.
10. Advised to provide an adequate
training to all engaged workers 1 Month HSE Manager
regarding Work at height hazard
identification and fall prevention, Safe
system of work, Correct use of PPEs
and FBH ensuring FBH must be 100%
tie off with strong stability with

Learner number: Learner name: Sample Report 1 Page 15 of 28


Hazard category and Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
hazard and how? required? further actions person’s job
to be title
completed
(within …)
anchorage point and proper
maintenance.

[Link] to provide inspected PPEs 1 Week HSE Manager


such as safety helmet, boot, gloves,
jacket etc including FBH in sufficient
number to all engaged workers
ensuring its use.

[Link] SUBSTANCES Engaged workers such as RPEs are available in 1. Advised to provide safe chemical 1 Month Project
mason, loader, painter, insufficient number, substances to minimise the injuries. Manager
Dust arising from all chemical handler, chemical moreover workers are
different construction store keeper, unaware its availability. 2. An effective housekeeping must be 2 Weeks Project
activities/toxic gas, smoke housekeeping officer, in place for removal of accumulated Manager
and fumes from hot job grinder man, driller, welder Only competent person is hazardous substances that are either
activities/accumulated might be primarily harmed permitted in all type chemical left after use or shall be kept in steel
hazardous substances but it also might harm the works. container with proper marking and
present at workplace all are other person, rarely visitor, labelling to avoid catching fire.
hazardous to workers surveyor, office employee Separate area is being
health. etc. allocated for all dusty works 3. Local dust extractor must be installed 2 Weeks Project
such as loading and unloading for enclosed room where hot work Manager
Workers while performing of cement bags/chips stone activities are being done to reduce
all different construction away from main workplace. airborne mist, vapour, smog, fumes
activities where workers Dismantling activities are and gasses and to minimise exposure.
likely to encounter with being done in quieter time.
several hazardous 4. Inspection must be done for installed 1 Week Project
exposure in the form of Welfare facility is given to local dust extractor of its ongoing Engineer
dusty particle arising from change overall and wash basin effect
loading and unloading of and its arrangement is there

Learner number: Learner name: Sample Report 1 Page 16 of 28


Hazard category and Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
hazard and how? required? further actions person’s job
to be title
completed
(within …)
cement bags and chips for all workers. 5. A competent person must ensure the 2 Weeks Project
stone, sanding works, dust level and other fumes, smoke and Manager
dismantling the structure Health check-up for all gases are controlled in enclosed space
etc and toxic gas, smoke workers is being quarterly by checking installed extractor ongoing
and fumes emitting from done. effectiveness.
hot work activities such
from welding, grinding, 6. COSHH must be assessed. 1 Month HSE
drilling and other hot job Manager
works, and in addition to 7. Introduced a process to change 1 Month HSE Manager
this several accumulated hazardous process to non-hazardous
hazardous substances such process such mechanical to electric,
as solvent and sealant, brushing rather spraying to reduce
thinner, adhesive paint and airborne mist and dust level down.
glue producing chemical
agent and workers since 8. Rest break must be given at frequent 1 Week HSE Manager
working for prolong period interval of time either by alternating
of time without taking rest the job.
break likely to suffer from
acute and chronic disease 9. Risk assessment must be done and 1 Month HSE Manager
either by touching, inhaling adapt additional control measure if
or eating causes required by identifying the potential
dermatitis,, conjunctivitis, risk and determining all preauction are
skin and eye allergy, in place.
several respiratory disease
or issues, lung infection, 10. Advised to provide a suitable and 1 Month HSE Manager
occupational asthma, proper training to all engaged workers
prolong lung infection regarding
could lead to lung cancer - General hygiene education’
and in worse case death -Keeping washing area and changing

Learner number: Learner name: Sample Report 1 Page 17 of 28


Hazard category and Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
hazard and how? required? further actions person’s job
to be title
completed
(within …)
occur. room clean
-How to safely use chemical
substances.
- SSOW.
-Correct use of PPE and RPEs and its
proper use and maintenance.

[Link] to provide non-respiratory 1 Week HSE Manager


protective equipment and Respiratory
protective equipment respirators, such
as face mask and breathing apparatus
such as SCBA Self Contained Breathing
Apparatus), gasmask and other
mandatory PPEs including separate
overalls and gloves to all engaged
workers.
[Link] SPACE All engaged workers in Evaluation, inspection and 1. Advised to remove all electrical, fire, 3 Weeks Project
confined space activities testing is already carried for mechanical, physical hazard and also Manager
Working in such as grinder man, where confined space remove exposure of accumulated toxic
tank/manhole/pipe line welder, electrician, electric activities are being initiated. gasses, flowing liquid and solid from
likely to encounter with engineer, associated the confined space by proper testing,
Oxygen deficiency/oxygen workmen, supervisor, and Authorised entrant is allowed evaluating and testing to avoid
enrichment/excessive entrant and rescue to enter in confined space. associated risk of injuries.
heat/ mechanical operation team might be
hazards/electrical harmed. Confined space TBT is 2. Evaluation of toxic gas concentration 1Week Project
hazards/poor frequently in practice. must be done ensuring that Manager
illumination/fire Workers while engaged in concentration shall not be exceed and
explosion/limited access pipe line/tank for repairing No monitoring is carried out oxygen content in atmosphere
and egress etc all are and maintenance activities from beginning and during the ensuring it shall meet the minimum

Learner number: Learner name: Sample Report 1 Page 18 of 28


Hazard category and Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
hazard and how? required? further actions person’s job
to be title
completed
(within …)
hazardous to health. such as grinding and confined space work activities. standard volume at 19.5 %.
welding and electrical
work likely to expose with Emergency rescue team is in 3. Advised to install inspected 2 Weeks Project
oxygen deficient, oxygen place with all its rescue ventilation system to minimise the Engineer
enrichment and excessive operation equipment such as toxic gas, fumes and smoke exposure.
heat ,atmospheric and tri-pod crane, stretcher etc.
non-atmospheric 4. Advised to install proper illumination 15days Electrical
exposure, electrical , fire ensuring all source of lightening Supervisor
and mechanical hazard and through ELCB and shall be of 24 volts in
physical hazard and confined space.
exposure of accumulated
toxic gasses , flowing liquid 5. Ensure both confined space permit 1 Month Project
and solid can cause several system and hot work permit system Manager
injuries such as must be in place with compliance
Asphyxiation due to meeting all its checklist content are
prolong toxic gas and fulfilled and all adequate precaution
fumes exposure (since are in place.
proper ventilation is not
installed),headache, 6. Advised to provide safe means of 2 Weeks Project
Electrocution. burning, access to and egress from workplace to Manager
Heat exhaustion/slip trip ensure the workplace safety for the
due to poor illumination prevention against all potential risk.
cause cuts, bruise, fracture
of body parts and will be 7. An effective monitoring at workplace 2weeks HSE Manager
more worsen if person shall be in place by assigning entry
can’t be evacuated safely supervisor, hole watcher by ensuring
due to limited scope of below action
access and egress where
maximum number of -Safe entry shall be ensured by taking 2weeks HSE Manager

Learner number: Learner name: Sample Report 1 Page 19 of 28


Hazard category and Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
hazard and how? required? further actions person’s job
to be title
completed
(within …)
fatalities occur. all practicable preparation in place.
-All entrant is adequately trained in 2weeks Safety Officer
confined space entry conditions and
aware with hazard nature likely to
encounter
-Rescue operation team rescue 1week Safety Officer
procedure, protective clothing and
equipment is in place.
-In hazardous condition or unsafe job 1week Safety Officer
conditions in confined space where
worker shall be stopped.
-Name of the entrant and duration 1week HSE Manager
shall be recorded in attendance
register sheet by hole watcher.
-Communication system must be 1week HSE Manager
maintained with all confined space
entrant by safety watch.
-Awareness of emergency services and 1week HSE Manager
rescue equipment’s location must be
known by hole watcher.
-Rescue team must be physically fit 1 Week HSE Manger
and competent in rescuing inside and
outside the confined space and shall
be competent enough in giving
CPR/First aid.

8.A suitable and sufficient training 1 Month HSE Manager


must be given to all engage workers
including;

Learner number: Learner name: Sample Report 1 Page 20 of 28


Hazard category and Who might be harmed What are you already doing? What further controls/actions are Timescales for Responsible
hazard and how? required? further actions person’s job
to be title
completed
(within …)
- Confined space hazard
identification
- Nature of task and involved
risk.
- SSOW-Safe System of Work
- Confined pace entry conditions
- Safe entry tag
- Emergency evacuation
procedure
- Correct use of Provided PPEs
and RPEs.
- First Aid and CPR training.

[Link] to provide all type of 1 Week HSE Manager


mandatory PPEs and RPEs such as Self-
Contained Breathing apparatus -SCBA,
safety harness and life line etc in
sufficient number ensuring its proper
use while entering and working in
confined space.

Learner number: Learner name: Sample Report 1 Page 21 of 28


Part 3: Prioritise 3 actions with justification for the selection
Suggested word counts
Moral, general legal and financial arguments for all actions: 300 to 350 words
For EACH action:
Specific legal arguments: 100 to 150 words
Likelihood AND severity: 75 to 150 words
How effective the action is likely to be in controlling the risk: 100 to 150 words

Moral, general legal and financial arguments for ALL actions


Moral, general legal and financial Moral- Advent construction has also moral obligation to protect their workers by providing a safe and better
arguments workplace, equipment and environment along with competent training and supervision to prevent injuries
from all risk involved in workplace activities is also moral duty of undertaking employer to treat their workers
as their own family member because they work for them for employer growth and in return get small
monitory reward as a wage and workers expect where they work shall be safe and suitable without risk and
expect happy and safely return to home each day and runs their livelihood safely but not to put themselves
failing into risk of injuries but if during prolong work activities any injuries occurred to workers, it will not only
impact on victim health conditions but also impact on witness mental condition that could weaken the
morale of workers and force them to leave the organisation that led bad reputation which will impact on
business .Hence employer shall meet the workers expectation and to provide a safer and better workplace,
equipment and environment to give protection from any risk.
Legal: Failing to meet moral obligation is an act of contravening ILO standard and national laws and legislation
and if injuries occurred due to non-compliance where employer will be responsible for the injuries caused to
workers and in such case undertaking employer will have to face strict legal action against employer where
prohibition notice will be served to employer by the reinforcement agency in the forms of fines and penalties,
will be imposed persecution charges, trade licences will be cancelled, interfere of courts ,could have been
drag to court and subjected to crime , employer may have been sent to jail.
Financial: if any injuries took place, then the cost that incurred in form of direct cost and indirect cost and that
could be categorised in three category such as
1. Cost that incurred on injured workers as a sick pay compensation, hospital treatment
productivity lost, recruiting and training cost of newly joined workers.

Learner number: Learner name: Sample Report 1 Page 22 of 28


2. Cost that incurred on repairing and replacing of damaged equipment, infrastructure.
3. Cost that incurred in following accident investigation by engaging key personnel,
enforcement action costs and several legal costs and duties.
Apart from above incurred costs, some costs are insured and recoverable but there are some uninsured costs
that can’t be calculably returned such as OT cost for balancing down time, emergency supply cost, trained
person lost, loss of reputation, loss of morale, loss of contract etc that all will be devastating for undertaking
company’s finance.
Keeping all moral, legal and financial argument employer must ensure to meet all obligation to avoid bad
consequence that could fall on undertaking company.

Justification for action 1


Action (Taken from column 4 of risk “Advised to provide inspected PPEs such as safety helmet, boot, gloves, jacket etc including FBH in sufficient
assessment) number to all engaged workers ensuring its use.”

HAZARD CATEGORY-WORK AT HEIGHT.


Specific legal arguments C167 - Safety and Health in Construction Convention, 1988 (No. 167), Article -30

With the reference to above suitable convention where employer are advised to provide suitable and
protective clothing and equipment to protect workers against injury where workers are liable to work in
adverse conditions realising the type of work and its risk , its employer duty to provide such protective
clothing without cost to workers and shall train workers for the use of protective equipment individually and
ensure its proper use and maintenance as prescribed by country’s laws and legislation whereas workers shall
also use properly and take good care of provided protective clothing and equipment, but such suitable
protective clothing and protective equipment are not provided by the undertaking employer which is act of
contravention of ILO and prescribed country’s laws and legislation and during prolong risk activities any injuries
occurs caused harm to workers due to non-compliance of ILO standard , in such circumstances , undertaking
employer will be accountable for injuries caused to workers where a series of strict legal action will be taken
against him such as imposing several charges, legal duties will be imposed which could hamper ongoing
projects and upcoming projects and ultimately have to close the projects.
Consideration of likelihood AND severity The work at height activities has always possess high risk of injuries and here in advent construction most of
the activities are also being carried out at work at height where working platform is unprotected and
uninspected where there is High likelihood of falling of person from working at height platform either due to

Learner number: Learner name: Sample Report 1 Page 23 of 28


open edge or collapse of working platform and since PPEs are also not worn by the engaged workers where
there is Quite Very High likelihood of causing injuries to fallen workers and person below the working
platform.
The severity of injuries depend on what height workers falls and how intensely hitting by the objects such as
 types of injury or ill health cuts/bruise/body parts fracture/severe head and spinal injuries/disability and in worse case death occur.
43 Workers are at risk
 number of workers at risk
 how often the activity is carried The work at height activities is being carried out on an average of 7hrs/job/workers on daily basis for all
out different location in 2 shifts.
 how widespread the risk is
The risk is concentred within work at height premises and its circumference.

How effective the action is likely to be in


My advised action is likely to be controlling the risk by providing the suitable protective clothing ensuring it
controlling the risk. This should include:
must wear while working at height which will protect workers from injuries and will improve the safety of
 the intended impact of the action; workplace and also ensure the safety of all engaged workmen.

 justification for the timescale that I have given 1 week to complete action because only it required to check what number to be purchased and
you indicated in your risk after undergoing official formalities and after getting purchase approval, could be easily purchased from
assessment; and approved vendor which is now a days is easy to find. Management must not take more than 1 Week realising
high likelihood and catastrophic result. Hence 1 week is sufficient enough to complete the action.
 whether you think the action will My advised action will fully control the risk by wearing provided suitable protective clothing such as FBH
fully control the risk ensuring its 100% tie off with anchorage point with strong hook stability that will ensure to not let the workers
falls and control the risk of injuries, in addition to this other recommended control measures as advised must
be in place in right direction within given time scale.

Justification for action 2


Action (Taken from column 4 of risk “Heat, smoke and fire detection devices along with fire alarm system must be installed to detect fire at its initial
assessment) stage to control the risk of fire outbreak and to minimise the injuries”.
HAZARD CATEGORY -FIRE
C167-Safety and Health in construction Convention, 1988 (No.167), Article -29
Specific legal arguments
According to above mentioned specific convention where employer is advised to adapt all appropriate

Learner number: Learner name: Sample Report 1 Page 24 of 28


measure to avoid the risk of fire and shall take all required precautionary arrangement so to combat quickly
and efficiently any outbreak of fire and its also employer duty to bring about a quick and safe evacuation of
persons but in right now undertaking employer is not installed Heat, smoke and fire detection devices along
with fire alarm system to detect fire at its initial stage to control the risk of fire outbreak and to minimise the
injuries where employer neglects the compliance of standard ILO convention and breaching the ILO act and in
case of any injuries that occurred due to prolong high risk activities of hot work activities and causes injuries
to workers in such circumstances undertaking employer will be accountable for the injuries caused to worker
where employer will be treated as contravener and inconsequence , employer will have to face a series of
strict legal action against him that could series impact on its reputation, could be imposed several legal and
enforcement action and even punish for the non-compliance negligence and will hit a serious impact on
running projects. Hence its employer duty to meet all standard and fix the issue to avoid such bad
consequences.
There is High likelihood of fire occurrence as hot work activities is being carried out in enclosed room (where
Consideration of likelihood AND severity
no proper ventilation system is installed) with the maximum use of electrical tools and equipment and use of
argon gas cylinder in presence of flammable material at workplace and the flame and spark emission through
the activities either due to faulty equipment or short circuit has Quite Very High likelihood of catching and
spreading of fire could cause several personal injuries.

 types of injury or ill health Severity of injuries occurred to workers depending on the what level of fire and duration of fire exposed to
workers such as burns, asphyxiation due to prolong exposure of toxic gas, smoke and fumes and could be
worse if person can’t be evacuated in time could occur death and moreover if fire contaminates with other
accumulated flammable and hazardous substances turn the fire into fire explosion which could be
catastrophic results for property and environment.

 number of workers at risk Primarily 21 proactive engaged workers at high risk such as welder, grinder man, driller and electrical
supervisor etc but other person such as lone workers, disabled person and office employee are also at risk.
 how often the activity is carried The Hot work and electrical work activities are being frequently carried out on an average of daily basis
out 7hrs/job/workers in all 2 shifts for all different location at workplace.

The risk of fire occurrence is throughout the workplace as hot work activities and electrical work activities are
 how widespread the risk is
being carried out all different locations at workplace.
How effective the action is likely to be in
My advised action is likely to minimise the risk of fire occurrence by installing heat, smoke and fire detections

Learner number: Learner name: Sample Report 1 Page 25 of 28


controlling the risk. This should include: devices along with interlinked fire alarm system which will improve the workplace safety and ensure the
safety of all engaged workers working at workplace.
 the intended impact of the action;
I have given 2-week time scale to complete releasing its high likelihood and catastrophic results occurrence
 justification for the timescale that and considering it urgency responsible person only required to identify what number to be installed and take
you indicated in your risk approval for its purchase and after undergoing some official purchase approval, these could be purchased
assessment; and from selected vendor and after its inspection can be installed by competent person who is available at
workplace. Hence all these processes shall be completed within 2 weeks easily.
 whether you think the action will My advised action will fully control the risk of fire occurrence by installing Heat, smoke and fire detection
fully control the risk devices along with fire alarm system because the functions of heat, smoke and fire detection devices is to
detect fire at its incipient stage and with installed interlinked fire alarm system that helps to alert any fire
outbreak and noticing such alarm fire could be easily extinguish with help of fire fighter by the installed fire
extinguisher and will not let fire to be caught and spread , in conjunction with these other recommended
control measure shall be in place in right direction withing their given time scale.

Justification for action 3


Action (Taken from column 4 of risk “Advised to monitor that no any load more than 25 kg must be in operation by assigning competent person”
assessment)
HAZARD CATEGORY-MANUAL HANDLING
Specific legal arguments C127 - Maximum Weight Convention, 1967 (No. 127), Article- 3
R128 - Maximum Weight Recommendation, 1967 (No. 128), VI.
Maximum Weight in Section A –Adult Male Workers.

In Undertaking company manual handling operation is done, where heavy load containing more than 25kg
and possessing hazardous material by individual is being carried out where likely to affect workers’ health by
means of its weight where employer is breaching above mentioned ILO conventions which specifically states
that no worker shall be engaged to manual handling or load transporting by means of its weight, workers likely
to jeopardize workers’ health or safety and during manual handling operation and also breaching countries
laws and legislation and if workers suffer from any injuries due to heavy load where employer is accountable
for injuries caused to workers due to non-compliance of ILO act and in such case employer will have to face
legal consequences that could serious hit on its business.
Consideration of likelihood AND severity Engaged loaders are carrying heavy load that contain pointed material, hot iron, glass material that possess
more than 25 kg weight for an extended time period without taking rest break, moreover manual handling

Learner number: Learner name: Sample Report 1 Page 26 of 28


operation is in practice with inappropriate manual handling technique on uneven floor with obstacle in
walkway where there is High likelihood of resulting inappropriate conditions, awkward positioning and off
movement occurrence where there is Quite Very High Likelihood of suffering from several personal injuries.
Severity of injuries that could cause due to slip and trip and other musculoskeletal injuries such as
 types of injury or ill health cuts/bruise/body parts fracture/head injuries/sprain and stress, spinal injuries, ligament and tissues, sciatic
pain and other MSDs and burns and in worse case death occur depending how intense hit by the objects and
fall.
10 Workers are primarily at risk.
 number of workers at risk
 how often the activity is carried Manual handling work activities is being done on an average of 7hrs/day/job in both shift on regular basis.
out Associated manual handling risk is concentred only during manual handling operation and where manual
 how widespread the risk is handling activities are being carried out in all different locations at workplace.
How effective the action is likely to be in My recommended action is likely to be controlling the associated risk of injuries of manual handling by reducing
controlling the risk. This should include: the weight which will ensure the workers’ health and safety and reduce and enable all engaged worker to
 the intended impact of the action; work safely without risk to harm to workers.

 justification for the timescale that I have given 2 Weeks’ time to complete the action because responsible person only required to assign a
you indicated in your risk competent person who kept monitoring of maximum load that shall not be in practice more than 25 kg where
assessment; and competent person can be easily assigned within 2 weeks.

 whether you think the action will My advised control measures will fully control the risk by assigning competent person because assigned person
fully control the risk will ensure that the maximum load is under controlled and maintained, ensuring no worker shall be engaged to
manual handling or load transporting by means of its weight, workers likely to jeopardize workers’ health or
safety and will not let cause injuries from manual handling operations, along with other control measures
shall be in place and effectively in compliance.

Part 4: Review, communicate and check


Suggested word counts for each section:
 Planned review date or period and reasoning for this: 50 - 100 words
 How the risk assessment findings will be communicated and who needs to know the information: 100 - 150 words
 Follow up on the risk assessment: 100 - 150 words.
Planned review date/ period with Review of risk assessment must be conducted annually as per the policy of undertaking company

Learner number: Learner name: Sample Report 1 Page 27 of 28


reasoning Therefore, I planned review date on 3rd November, 2024, under the following circumstances
4. If there is no change in working pattern and schedule
5. If there is no change in brought in work activities and process
6. If there is change in work equipment.
7. Upon introducing new substances and technology
8. If there is glitch in implementing HSE policy
9. If there is incident revealing hazards.
How the risk assessment findings will be To communicate my risk finding of completed risk assessment, I will first of all arrange a meeting and will
communicated AND who you need to tell invite all responsible person such as project manager, project engineer, HSE Manager and member from all
department and will discuss on my risk finding and get them agreed to implement my recommended control
measure within time scale. I will also email a soft copy to almost all department and safety committee
member team requesting to consider my risk assessment finding in Company upcoming TBT.I will also display
my risk finding on company notice board with proper warning sign so that workers could notice. I will also
meet all workers personally in their rest break time counselling workers to take precaution until the
recommended action is to be implemented.
How you will follow up on the risk Having communicated my risk finding, I will set reminder in my mobile and also note down in my dairy of all
assessment to check that the actions minutes of meeting and will be in touch with all of the responsible person whom I assigned the responsibility
have been carried out and when reaching closer to minimum time scale given. I will ask for the latest update for the action to be
taken and while on talking on mobile if I will find any glitch or discrepancies in their statement .I will plan to
revisit the workplace and will meet all concerned person and will ask the reason of delayed caused to
implement and would like to know the reason whether its lack of resources, manpower or any financial
concern .I will also meet the project manager who has responsibility for managing health and safety at work
place and request to fix the issues and I will also meet the Director along with project manager briefing all
hurdles encountering implanting issues and will request to director to solve immediately realising the bad
consequences of noncompliance of risk finding which could impact on business because it is act of
contravening ILO act.

Learner number: Learner name: Sample Report 1 Page 28 of 28