FABRICARES LIMITED
Building construction & textile manufacturer
Index no : C – 1046, Tell : +88028932440, +880248955266
Email : kspfl6666@[Link]
DETAILS MEASUREMENTOF CLASS-30 CASTING
Project :Construction of 97.326 m (2 × 30.488 m + 1 × 33.54 m) longP.C Girder Bridge
(Mahalia Bridge)at 5th km (Ch= 4 km + 923.50m N-105)
of Keranihat-Bandarban road (N-108)
TS Pay Item
SL No Description Unit Measurement Quantity
No
st
1 Span:
Deck slab : 31.198 × 10.25 × 0.25 × 1 = 79.945
Girder top: 31.198 × 1.10 × 0.025 × 5 = 4.290
Concrete class 30 (Deck slab, side wall, wheel guard,
1 5/01/03k Cum Parapet wall : 31.198 × 0.40 × 0.30 × 2 = 7.488 110.746
curb etc). (Batching plant)
: 31.198 × 0.585 × 0.30 × 2 = 10.950
Wheel guard : 31.198×{(0.275 + 0.25)/2} × 0.25 × 2 = 4.095
Footpath: 31.198 × 0.85 × 0.075 × 2 = 3.978
Total = 110.746
Project Engineer Project Engineer Project NCO Project JCO PO
Contractor 20 ECB 20 ECB 20 ECB 20 ECB
FABRICARES LIMITED
Building construction & textile manufacturer
Index no : C – 1046, Tell : +88028932440, +880248955266
Email : kspfl6666@[Link]
DETAILS MEASUREMENTOF WEARING COURSE
Project :Construction of 97.326 m (2 × 30.488 m + 1 × 33.54 m) longP.C Girder Bridge
(Mahalia Bridge)at 5th km (Ch= 4 km + 923.50m N-105)
of Keranihat-Bandarban road (N-108)
SL TS Pay
Description Unit Measurement Quantity
No Item No
st
1 Span:
1 5/01/03l Concrete class 35 (Wearing course) Cum 11.387
Wearing course: 31.198 × 7.30 × 0.05 = 11.387
Total = 11.387
Project Engineer Project Engineer Project NCO Project JCO PO
Contractor 20 ECB 20 ECB 20 ECB 20 ECB
FABRICARES LIMITED
Building construction & textile manufacturer
Index no : C – 1046, Tell : +88028932440, +880248955266
Email : kspfl6666@[Link]
DETAILS MEASUREMENTOF EXPANSION JOINT
Project :Construction of 97.326 m (2 × 30.488 m + 1 × 33.54 m) longP.C Girder Bridge
(Mahalia Bridge)at 5th km (Ch= 4 km + 923.50m N-105)
of Keranihat-Bandarban road (N-108)
SL TS Pay
Description Unit Measurement Quantity
No Item No
Expansion joint complete as detailed on the drawings in the location
1 5/8/01 described in the BOQ m Expansion joint: 7.5 × 1 = 7 .50 7.50
(Updated with new drawing)
Total = 7.50
Project Engineer Project Engineer Project NCO Project JCO PO
Contractor 20 ECB 20 ECB 20 ECB 20 ECB
FABRICARES LIMITED
Building construction & textile manufacturer
Index no : C – 1046, Tell : +88028932440, +880248955266
Email : kspfl6666@[Link]
DETAILS MEASUREMENTOF RAIN WATER DOWN PIPE
Project :Construction of 97.326 m (2 × 30.488 m + 1 × 33.54 m) longP.C Girder Bridge
(Mahalia Bridge)at 5th km (Ch= 4 km + 923.50m N-105)
of Keranihat-Bandarban road (N-108)
Ser no Ts pay item no Description of item Unit Measurement Quantity
1st Span Rain water down pipe
Deck slab = 12 × 1 × 2 = 24.00
1 SP-08 Rain water down pipe(62 mm dia UPVC) Nos 48.00
Wheel guard = 12 × 1 × 2 = 24.00
Total = 48.00
Project Engineer Project Engineer Project NCO Project JCO PO
Contractor 20 ECB 20 ECB 20 ECB 20 ECB
FABRICARES LIMITED
Building construction & textile manufacturer
Index no : C – 1046, Tell : +88028932440, +880248955266
Email : kspfl6666@[Link]
DETAILS MEASUREMENTOF REINFORCEMENT
Project :Construction of 97.326 m (2 × 30.488 m + 1 × 33.54 m) longP.C Girder Bridge
(Mahalia Bridge)at 5th km (Ch= 4 km + 923.50m N-105)
of Keranihat-Bandarban road (N-108)
SL TS Pay
Description Unit Measurement Quantity
No Item No
st st
1 Span deck slab reinforcement: 1 Span deck slab reinforcement:
Main bar length :(10.25 + 0.10 + 0.10) – (clear cover 0.05 × 2) = 10.35 M 12 mm Φ Main bar top & bottom = 10.35 × 312 ×2 × 0.89 = 5747.98
Main bar lapping length :(50 × 12)/1000 = 0.60 m 12 mm Φ Main bar top & bottom lapping = 0.60 × 312 × 2 × 2 × 0.89 = 599.04
Main bar spacing (31.098/ 0.10) + 1 = 312 Nos
10 mm Φ Binder bar = 31.098 × 106 × 1 × 0.62 = 2043.79
Binder bar length: (31.098 + 0.10 + 0.10) = 31.298 M
12 mm Φ Binder bar = 31.098 × 32 × 1 × 0.89 = 885.67
12 mm Φ Binder bar lapping length: (50 × 12)/1000 = 0.60 m
10 mm Φ Binder bar lapping length: (50 × 10)/1000 = 0.50 m 10 mm Φ Binder bar lapping = 0.50 × 106 × 1 × 0.62 = 32.86
12 mm Φ Binder bar lapping = 0.60 × 32 × 1 × 0.89 = 17.09
Parapet wall vertical bar: (0.75 + 1.035 + 0.15 + 1.035 + 0.35) = 3.326 M
Parapet wall bracket bar: 0.20 + 0.45 + 0.20 = 0.85 m 16 mm Φ Parapet wall vertical bar = 3.326 × 209 × 1 × 2 × 1.58 = 2196.62
Parapet wall bracket binder bar Spacing: 3.00 Nos 16 mm Φ Parapet wall bracket bar = 0.85 × 209 × 1 × 2 × 1.58 = 561.37
Parapet wall vertical & bracket bar spacing: (31.098 / 0.15) + 1 = 209 Nos 12 mm Φ Parapet wall bracket binder = 31.098 × 3 × 1 × 2 × 0.89 = 166.06
1 5/2/02 Parapet wall binder bar length: 0.15 + 31.098 + 0.15 = 31.398 m
12 mm Φ Parapet wall binder bar = 31.098 × 8 × 2 × 2 × 0.89 = 885.67
Parapet wall binder bar spacing: (1.035 / 0.15) + 1 = 8 Nos Ton
12 mm Φ pa rapet wall b inder bar lapping = 0.60 × 8 × 2 × 2 × 0.89 = 17.09
Wheel guard vertical bar length: 0.10 + 0.20 + 0.425 + 0.225 + 0.45 + 0.15 +
0.10 = 1.65 m 12 mm Φ Wheel guard vertical bar = 1.65 × 209 × 2 × 0.89 = 613.83
Wheel guard vertical bar spacing: (31.098 / 0.15) + 1 = 209 Nos 12 mm Φ Wheel guard binder bar= 31.098 × 6 × 2 × 0.89 = 332.13
Wheel guard binder bar: 0.15 + 31.098 + 0.15 = 31.398 m 12 mm Φ Wheel gua rd b inder bar lapping = 0.60 × 6 × 2 × 2 × 0.89 = 12.82
20 mm Φ Wheel guard binder bar= 31.098 × 2 × 2 × 2.47 = 307.25
Footpath main ba r: 0.80 m 20 mm Φ Wheel guard binder bar lapping = 1.00 × 2 × 2 × 2 × 0.89 = 3.56
Footpath spa cing: (31.098 / 0.125) + 1 = 250 Nos
Footpath binder: 31.098 m 10 mm Φ Footpa th main ba r = 0.80 × 250 × 1 × 2 × 0.62 = 248.00
Footpath binder spa cing: (0.80 / 0.125) + 1 = 8 Nos 10 mm Φ Footpa th binder= 31.098 × 8 × 1 × 2 × 0.62 = 308.49
Total (kg) = 14979.32
Total (ton) = 14979.32/1000 = 14.979 14.979
Project Engineer Project Engineer Project NCO Project JCO PO
Contractor 20 ECB 20 ECB 20 ECB 20 ECB