Addis Ababa Mixed-Use Project Plan
Addis Ababa Mixed-Use Project Plan
12 Facilitate the transfer of the land holding 1 day Wed 1/31/24 Wed 8
certificate for the development.
1/31/24
13 Provide all necessary licenses, including 2 days Thu 2/1/24 Fri 2/2/24 12
building permits, construction permits, access
road permits, utility line permits, and other
required documents to the Project Company.
14 Expedite the process for obtaining certificates 1 day Mon 2/5/24 Mon 13
and licenses required by the Project Company
2/5/24
15 Field Visit and Assessment of the Existing 1 day Tue 2/6/24 Tue 14
Situation
2/6/24
Page 1
ID Task Name DurationStart Finish
1st Half Predecessors 1st Half
1st Quarter 1st Quarter 1st Quarter 1st Quarter
Mar Aug Jan Jun Nov Apr Sep
16 Collaboration with the Subcity/Woreda to 1 day Wed 2/7/24 Wed 15
Make a survey of existing utility services and
2/7/24
liaise closely with authorities concerned on
the proposed relocation of such services. The
17 Approach relevant authorities to connect 1 day Wed 2/7/24 Wed 15
water, power supply, and communication
2/7/24
facilities to the enclosing wall of the PPP
Projects before project commencement.
18 Approach city governoment of addis ababa 1 day Wed 2/7/24 Wed 15
water and sewarage authoritiesand facilitate
2/7/24
the connection of water for the construction
19 Approach Ethiopian electric light & power 1 day Wed 2/7/24 Wed 15
authority (EELPA) and facilitate the connection
2/7/24
of power supply for the purpose of
construction
20 Approach City Government of Addis Ababa 1 day Wed 2/7/24 Wed 15
Roads authority and facilitate the construction
2/7/24
of any needed road for the construction
purpose upto the periphery of the
21 Techinical 12 days Thu 2/8/24 Fri 2/23/24
22 Issue the Contractor with all the necessary 2 days Thu 2/8/24 Fri 2/9/24 20
copies of the Works Contract Documents,
including Contract Agreement, Conditions of
23 Give a consent on the Appointment of 1 day Mon 2/12/24 Mon 22
Subcontractors
2/12/24
24 Supervise the activities of the Contractor in 1 day Tue 2/13/24 Tue 23
accordance with the Contract between the
2/13/24
Contractor and the Employer .
25 Organize a formal joint Monthly Progress 1 day Wed 2/14/24 Wed 24
Meeting to be attended by the Contractor,
2/14/24
Consultant and Employer.
Page 2
ID Task Name DurationStart Finish
1st Half Predecessors 1st Half
1st Quarter 1st Quarter 1st Quarter 1st Quarter
Mar Aug Jan Jun Nov Apr Sep
26 Check and verify the validity of all 1 day Mon 2/12/24 Mon 22
insurance/guarantees/performance bonds and
2/12/24
proof of payment of premiums which the
Contractor is obliged to have in place.
27 Delegate appropriate duties to members of 1 day Thu 2/15/24 Thu 25
the supervision team by preparing a
2/15/24
Construction Supervision manual.
28 Continuously monitor the Contractor’s 1 day Fri 2/16/24 Fri 27
progress against programme and his method
2/16/24
of working in respect of each construction
29 Review the Contractor’s proposed working 1 day Mon 2/19/24 Mon 28
drawing/plans and associated calculations.
2/19/24
Approve or reject the proposals accordingly
30 Review and analyze all the Contractor’s 1 day Mon 2/19/24 Mon 28
applications for extensions of time or claims
2/19/24
for additional time and furnish the Employer
31 Advice the Contractor on any design changes 1 day Mon 2/19/24 Mon 28
that may be necessary or advisable during
2/19/24
construction. Review, verify and approve
design changes and amendments carried out
32 Any Employer's Representative Instructions 1 day Mon 2/19/24 Mon 28
(EI) and variation orders (VO) proposal shall be
2/19/24
assessed with the required time extension, if
there is any, whilst advising the Employer of
such EI’s and VO’s and of the associated
implications.
Page 3
ID Task Name DurationStart Finish
1st Half Predecessors 1st Half
1st Quarter 1st Quarter 1st Quarter 1st Quarter
Mar Aug Jan Jun Nov Apr Sep
38 The Consultant will establish a database for the1important
day Wed project
2/21/24
records.
WedThe database
33 should include but not limited to; records of challenges and solutions, reports, claim related data, correspo
2/21/24
39 Allow inspection by the Employer on request of1allday
site correspondence
Thu 2/22/24 Thu
and2/22/24
records,3etc
8
40 Provide on-the-job training to not more than 3 junior
1 day professionals/graduates
Fri 2/23/24 Fri 2/23/2439
at a time (furnished by the Employer) in the various aspects of construction supervision and application of the Works
41 Quality Control 37 days Mon 2/26/24 Tue 4/16/24
42 Approval and Monitoring of Construction Materials/both
1 day Mon developed
2/26/24onMon
site and imported
40 to site
2/26/24
43 Quality Tests and Approval of Material Sources 1 day Mon 2/26/24 Mon 2/26/24
40
44 Carry out monitoring and/or auditing of the Construction
1 day Mon through
2/26/24
performance monitoring
Mon 2/26/2440 mechanisms and procedures and quality assurance procedures
45 Topographic Survey verification 1 day Tue 2/27/24 Tue 2/27/2444
46 Approval of Contractor’s Setting out Of Works 1 day Wed 2/28/24 Wed 2/28/24
45
47 Conduct close full time construction supervision1of
dayall activity
Thu 2/29/24
to assureThu
the 2/29/24
works are46
executed in strict conformity with the contract documents, specification, and drawings.
48 Undertake necessary sample test for materials and
1 day
custom
Fri 3/1/24
materials (ifFri
any) before arrival
3/1/24 47 on the site
49 Check utilization of proper skilled manpower equipment
2 days Mon
and workman
3/4/24 Tue
ship3/5/2448
to assure the intended project quality
50 Follow up timely and proper coordination and allocation
1 day Wed of resources
3/6/24 by all project
Wed 3/6/24 stakeholders
49 specialized subcontractor such as (Mechanical, Electrical, sanitary metal work etc.) for an economic
51 Review Preliminary Architectural Design 1 day Thu 3/7/24 Thu 3/7/2450
52 Consent or approve the preliminary designs overall
1 dayplanning,
Fri 3/8/24
layout, and
Fridesign
3/8/24scheme
51
53 Approach City Government of Addis Ababa construction
1 day Mon permit
3/11/24
and control
Mon authority
52and facilitate the permit for construction
3/11/24
54 Review Detail Design Requirement for Common1Services
day Tue 3/12/24 Tue 3/12/2453
55 Review organization of the blocks of the buildings
1 day
as well
Wed as3/13/24
other design
Wedcomponents
54 and its oritantion
3/13/24
56 Review the Detailed Engineering Design 5 days Thu 3/14/24 Wed 3/20/2455
57 Architectural design with all necessary details5 days Thu 3/21/24 Wed 3/27/2456
58 Landscape design with all necessarily detail 2 days Thu 3/28/24 Fri 3/29/2457
59 Structural design with all necessary details 14 days Thu 3/28/24 Tue 4/16/2457
60 Foundation design with all necessary details 3 days Thu 3/28/24 Mon 4/1/2457
61 Sanitary design with all necessary details 3 days Tue 4/2/24 Thu 4/4/2460
62 Electrical design with all necessary details 3 days Thu 3/28/24 Mon 4/1/2457
Page 4
ID Task Name DurationStart Finish
1st Half Predecessors 1st Half
1st Quarter 1st Quarter 1st Quarter 1st Quarter
Mar Aug Jan Jun Nov Apr Sep
63 Fire Fighting design will all necessarily details
1 day Thu 3/28/24 Thu 3/28/2457
64 ICT network infrastructure design with all necessary
1 day Thu
details
3/28/24 Thu 3/28/2457
65 Mechanical design with all necessary details 1 day Thu 3/28/24 Thu 3/28/24 57
66 Rigid pavement design for the compound, covered•1 day Fri and3/29/24
uncoveredFriwalkway.
3/29/2465 with all necessary drainage design details (road, electric power supply, water supply, tells, etc.)
67 Preparation of Cost Estimates 1 day Mon 4/1/24 Mon 4/1/2466
68 Health and Safety 3 days Tue 4/2/24 Thu 4/4/24
69 Ensure that the Contractor Follows international1 and
day specified
Tue 4/2/24
safe working practices in all operations
Tue 4/2/2467
70 Verify economic and proper utilization of Employer's
1 day Tue health,
4/2/24safety,
Tue 4/2/2467and input by the Contractor
resource,
71 Report and keep Records of all accidents on site.0 days Tue 4/2/24 Tue 4/2/2469 4/2
72 Ensure the Contractor has site personnel qualified
0 days
in firstTue
Aid4/2/24
and suitable
Tuefirst aid facilities are available.
4/2/2470 4/2
73 Environmental and Social 2 days Wed 4/3/24 Thu 4/4/24
74 Assessment of Environmental and Social Impact1 dayAssessment/SEIA/
Wed 4/3/24 Wed 4/3/2472
75 Monitor and Ensure that the Contractor follow1 day
Environmental
Thu 4/4/24 Management Plan(EMP)
Thu 4/4/2474
76 Measurement and Payment 2 days Fri 4/5/24 Mon 4/8/24
77 Works Payments 1 day Fri 4/5/24 Fri 4/5/24 75
78 Interim Certificate (client sikefil) 2 days Fri 4/5/24 Mon 4/8/2475
79 Release of Final Retention Amount 2 days Fri 4/5/24 Mon 4/8/2475
80 Finaization of Contrat 2 days Tue 4/9/24 Wed 4/10/24
81 Inspection of Works 1 day Tue 4/9/24 Tue 4/9/2479
82 Site Clearance 1 day Wed 4/10/24 Wed 4/10/24 81
83 Precomissioning Phase 1 day Thu 11/30/23 Thu 11/30/23
84 CONSTRUCTION PHASE(Block 1- Block 5) 491 daysFri 12/1/23 Fri 10/17/25
85 Contractor Mobilization 1 day Fri 12/1/23 Fri 12/1/2383
86 A. SUB STRUCTURE 137 daysMon 12/11/23Tue 6/18/24
87 SOIL INVESTIGATION & DESIGN PREPARATION 27 days Mon 12/4/23 Tue 1/9/24
Page 5
ID Task Name DurationStart Finish
1st Half Predecessors 1st Half
1st Quarter 1st Quarter 1st Quarter 1st Quarter
Mar Aug Jan Jun Nov Apr Sep
88 Soil Investigation 20 days Mon 12/4/23 Fri 12/29/23
85
89 Design Preparations 25 days Mon 1/1/24 Fri 2/2/24 88
90 1. EXCAVATION & EARTH WORK 137 daysWed 1/10/24 Thu 7/18/24
91 Top soil excavation 7 days Mon 2/5/24 Tue 2/13/2489
92 Bulk Excavation 30 days Wed 2/7/24 Tue 3/19/24 91SS+2 days
93 Back fill Work 35 days Mon 4/8/24 Fri 5/24/24
94 2. CONCRETE WORK 84 days Wed 1/10/24 Mon 5/6/24 87
95 Form work 38 days Fri 3/15/24 Tue 5/7/24
96 Mat foundation 10 days Fri 3/15/24 Thu 3/28/2492FS-3 days
97 Foundation Column & SW 15 days Fri 3/29/24 Thu 4/18/2496
98 Retaining wall 12 days Mon 4/22/24 Tue 5/7/24102FS-10 days
99 Rebar work 29 days Fri 3/29/24 Wed 5/8/24
100 Mat foundation 17 days Fri 3/29/24 Mon 4/22/2496
101 Foundation column & shear wall 12 days Tue 4/23/24 Wed 5/8/24100
102 Retaining wall 11 days Fri 4/19/24 Fri 5/3/24 97
103 Concrete work 88 days Wed 1/10/24 Fri 5/10/24
104 50 mm thick lean concrete under Mat 5Foundation
days Wed 1/10/24 Tue 1/16/24
105 Mat Foundation Concrete 10 days Fri 4/19/24 Thu 5/2/24100FS-2 days
106 Foundation Column & SW 14 days Wed 4/10/24 Mon 4/29/2497FS-7 days
107 Retaining wall 14 days Tue 4/23/24 Fri 5/10/2498FF+3 days
108 1ST BASEMENT 105 daysWed 1/10/24 Tue 6/4/24
109 Slab, Beam & Stair 19 days Tue 4/23/24 Fri 5/17/24
110 Form work 10 days Tue 4/23/24 Mon 5/6/24106FS-5 days
111 Rebar work 10 days Tue 4/30/24 Mon 5/13/24110SS+5 days
112 Concrete work 4 days Tue 5/14/24 Fri 5/17/24111
Page 6
ID Task Name DurationStart Finish
1st Half Predecessors 1st Half
1st Quarter 1st Quarter 1st Quarter 1st Quarter
Mar Aug Jan Jun Nov Apr Sep
113 Column, Shear wall & Retaining wall 15 days Wed 5/15/24 Tue 6/4/24
114 Rebar work 10 days Wed 5/15/24 Tue 5/28/24
112SS+1 day
115 Form work 12 days Wed 5/15/24 Thu 5/30/24
114FF+2 days
116 Concrete work 7 days Mon 5/27/24 Tue 6/4/24115FF+3 days
117 GROUND FLOOR 17 days Wed 1/10/24 Thu 2/1/24
118 SLAB, BEAM & STAIR 17 days Wed 1/10/24 Thu 2/1/24
119 Form work 10 days Wed 1/10/24 Tue 1/23/24
120 Rebar work 10 days Mon 1/15/24 Fri 1/26/24119SS+3 days
121 Concrete work 4 days Mon 1/29/24 Thu 2/1/24120
122 3. SUNDARY WORK 34 days Wed 1/10/24 Mon 2/26/24
123 Lay Upvc slotted pipe & Covering Geotextile
7 days Tue 4/30/24 Wed 5/8/24129
124 Lay Upvc for cleaning eyes 7 days Thu 5/9/24 Fri 5/17/24123
125 Fill 50-30 mm washed aggregate material5. days
.. Thu 5/23/24 Wed 5/29/24124,128FS+3 days
126 Covering by Geotextile of 1mm thickness 5 days Thu 5/23/24 Wed 5/29/24 125FF
127 Backfill imported 50cm depth washed redash
5 days . . . Thu 5/30/24 Wed 6/5/24125
128 Construct manhole for collecting manhole7 .days
.. Thu 5/9/24 Fri 5/17/24123
129 Install TESTUDO or equivalent 4mm thick 7. .days
. Fri 4/19/24 Mon 4/29/24105FF-3 days
130 B. SUPER STRUCTURE 449 daysTue 1/30/24 Fri 10/17/25
131 [Link] WORK 449 daysTue 1/30/24 Fri 10/17/25
132 GROUND FLOOR 11 days Tue 1/30/24 Tue 2/13/24
133 COLUMN & SHEAR WALL 11 days Tue 1/30/24 Tue 2/13/24
134 Rebar work 10 days Tue 1/30/24 Mon 2/12/24 121SS+1 day
135 Form work 10 days Wed 1/31/24 Tue 2/13/24 134SS+1 day
136 Concrete work 3 days Fri 2/9/24 Tue 2/13/24135FS-3 days
137 1st FLOOR 26 days Thu 2/8/24 Thu 3/14/24
Page 7
ID Task Name DurationStart Finish
1st Half Predecessors 1st Half
1st Quarter 1st Quarter 1st Quarter 1st Quarter
Mar Aug Jan Jun Nov Apr Sep
138 SLAB, BEAM & STAIR 15 days Thu 2/8/24 Wed 2/28/24
139 Form work 10 days Thu 2/15/24 Wed 2/28/24136FS+1 day
140 Rebar work 10 days Thu 2/8/24 Wed 2/21/24 139SS-5 days
141 Concrete work 4 days Thu 2/22/24 Tue 2/27/24 140
142 COLUMN & SHEAR WALL 14 days Mon 2/26/24 Thu 3/14/24
143 Rebar work 10 days Mon 2/26/24 Fri 3/8/24 141FS-2 days
144 Form work 10 days Tue 2/27/24 Mon 3/11/24143SS+1 day
145 Concrete work 3 days Tue 3/12/24 Thu 3/14/24 144
146 2nd FLOOR 26 days Mon 3/11/24 Mon 4/15/24
147 SLAB, BEAM & STAIR 15 days Mon 3/11/24 Fri 3/29/24
148 Form work 10 days Mon 3/18/24 Fri 3/29/24145FS+1 day
149 Rebar work 10 days Mon 3/11/24 Fri 3/22/24148SS-5 days
150 Concrete work 4 days Mon 3/25/24 Thu 3/28/24 149
151 COLUMN & SHEAR WALL 14 days Wed 3/27/24 Mon 4/15/24
152 Rebar work 10 days Wed 3/27/24 Tue 4/9/24150FS-2 days
153 Form work 10 days Thu 3/28/24 Wed 4/10/24152SS+1 day
154 Concrete work 3 days Thu 4/11/24 Mon 4/15/24 153
155 3rd FLOOR 26 days Wed 4/10/24 Wed 5/15/24
156 SLAB, BEAM & STAIR 15 days Wed 4/10/24 Tue 4/30/24
157 Form work 10 days Wed 4/17/24 Tue 4/30/24154FS+1 day
158 Rebar work 10 days Wed 4/10/24 Tue 4/23/24157SS-5 days
159 Concrete work 4 days Wed 4/24/24 Mon 4/29/24 158
160 COLUMN & SHEAR WALL 14 days Fri 4/26/24 Wed 5/15/24
161 Rebar work 10 days Fri 4/26/24 Thu 5/9/24159FS-2 days
162 Form work 10 days Mon 4/29/24 Fri 5/10/24161SS+1 day
Page 8
ID Task Name DurationStart Finish
1st Half Predecessors 1st Half
1st Quarter 1st Quarter 1st Quarter 1st Quarter
Mar Aug Jan Jun Nov Apr Sep
163 Concrete work 3 days Mon 5/13/24 Wed 5/15/24
162
164 4th FLOOR 26 days Fri 5/10/24Fri 6/14/24
165 SLAB, BEAM & STAIR 15 days Fri 5/10/24Thu 5/30/24
166 Form work 10 days Fri 5/17/24 Thu 5/30/24163FS+1 day
167 Rebar work 10 days Fri 5/10/24 Thu 5/23/24166SS-5 days
168 Concrete work 4 days Fri 5/24/24 Wed 5/29/24 167
169 COLUMN & SHEAR WALL 14 days Tue 5/28/24 Fri 6/14/24
170 Rebar work 10 days Tue 5/28/24 Mon 6/10/24168FS-2 days
171 Form work 10 days Wed 5/29/24 Tue 6/11/24170SS+1 day
172 Concrete work 3 days Wed 6/12/24 Fri 6/14/24171
173 5th - Roof All 5 Blocks Construction Simultaniously
349 daysTue 6/18/24 Fri 10/17/25
174 5th FLOOR 17 days Tue 6/18/24 Wed 7/10/24
175 SLAB, BEAM & STAIR 7 days Tue 6/18/24 Wed 6/26/24
176 Form work 5 days Tue 6/18/24 Mon 6/24/24 172FS+1 day
177 Rebar work 5 days Wed 6/19/24 Tue 6/25/24 176SS+1 day
178 Concrete work 1 day Wed 6/26/24 Wed 6/26/24 177
179 COLUMN & SHEAR WALL 12 days Tue 6/25/24 Wed 7/10/24
180 Rebar work 4 days Tue 6/25/24 Fri 6/28/24178FS-2 days
181 Form work 4 days Wed 6/26/24 Mon 7/1/24180SS+1 day
182 Concrete work 1 day Wed 7/10/24 Wed 7/10/24 185FS-1 day
183 6th FLOOR 13 days Thu 7/4/24 Mon 7/22/24
184 SLAB, BEAM & STAIR 7 days Thu 7/4/24 Fri 7/12/24
185 Form work 5 days Thu 7/4/24 Wed 7/10/24 181FS+2 days
186 Rebar work 5 days Fri 7/5/24 Thu 7/11/24185SS+1 day
187 Concrete work 1 day Fri 7/12/24 Fri 7/12/24186
Page 9
ID Task Name DurationStart Finish
1st Half Predecessors 1st Half
1st Quarter 1st Quarter 1st Quarter 1st Quarter
Mar Aug Jan Jun Nov Apr Sep
188 COLUMN & SHEAR WALL 6 days Mon 7/15/24 Mon 7/22/24
189 Rebar work 4 days Mon 7/15/24 Thu 7/18/24
187
190 Form work 4 days Tue 7/16/24 Fri 7/19/24189SS+1 day
191 Concrete work 1 day Mon 7/22/24 Mon 7/22/24
190
192 7th FLOOR 13 days Tue 7/23/24 Thu 8/8/24
193 SLAB, BEAM & STAIR 7 days Tue 7/23/24 Wed 7/31/24
194 Form work 5 days Tue 7/23/24 Mon 7/29/24 191
195 Rebar work 5 days Wed 7/24/24 Tue 7/30/24 194SS+1 day
196 Concrete work 1 day Wed 7/31/24 Wed 7/31/24 195
197 COLUMN & SHEAR WALL 6 days Thu 8/1/24 Thu 8/8/24
198 Rebar work 4 days Thu 8/1/24 Tue 8/6/24196
199 Form work 4 days Fri 8/2/24 Wed 8/7/24198SS+1 day
200 Concrete work 1 day Thu 8/8/24 Thu 8/8/24199
201 8th FLOOR 13 days Fri 8/9/24 Tue 8/27/24
202 SLAB, BEAM & STAIR 7 days Fri 8/9/24 Mon 8/19/24
203 Form work 5 days Fri 8/9/24 Thu 8/15/24200
204 Rebar work 5 days Mon 8/12/24 Fri 8/16/24203SS+1 day
205 Concrete work 1 day Mon 8/19/24 Mon 8/19/24 204
206 COLUMN & SHEAR WALL 6 days Tue 8/20/24 Tue 8/27/24
207 Rebar work 4 days Tue 8/20/24 Fri 8/23/24205
208 Form work 4 days Wed 8/21/24 Mon 8/26/24 207SS+1 day
209 Concrete work 1 day Tue 8/27/24 Tue 8/27/24 208
210 9th FLOOR 13 days Wed 8/28/24 Fri 9/13/24
211 SLAB, BEAM & STAIR 7 days Wed 8/28/24 Thu 9/5/24
212 Form work 5 days Wed 8/28/24 Tue 9/3/24209SS+1 day
Page 10
ID Task Name DurationStart Finish
1st Half Predecessors 1st Half
1st Quarter 1st Quarter 1st Quarter 1st Quarter
Mar Aug Jan Jun Nov Apr Sep
213 Rebar work 5 days Thu 8/29/24 Wed 9/4/24212SS+1 day
214 Concrete work 1 day Thu 9/5/24 Thu 9/5/24213
215 COLUMN & SHEAR WALL 6 days Fri 9/6/24 Fri 9/13/24
216 Rebar work 4 days Fri 9/6/24 Wed 9/11/24214
217 Form work 4 days Mon 9/9/24 Thu 9/12/24 216SS+1 day
218 Concrete work 1 day Fri 9/13/24 Fri 9/13/24217
219 10th FLOOR 11 days Mon 9/16/24 Mon 9/30/24
220 SLAB, BEAM & STAIR 7 days Mon 9/16/24 Tue 9/24/24
221 Form work 5 days Mon 9/16/24 Fri 9/20/24218
222 Rebar work 5 days Tue 9/17/24 Mon 9/23/24 221SS+1 day
223 Concrete work 1 day Tue 9/24/24 Tue 9/24/24 222
224 COLUMN & SHEAR WALL 6 days Mon 9/23/24 Mon 9/30/24
225 Rebar work 4 days Mon 9/23/24 Thu 9/26/24 223FS-2 days
226 Form work 4 days Tue 9/24/24 Fri 9/27/24225SS+1 day
227 Concrete work 1 day Mon 9/30/24 Mon 9/30/24 226
228 11th FLOOR 16 days Tue 10/1/24 Tue 10/22/24
229 SLAB, BEAM & STAIR 10 days Tue 10/1/24 Mon 10/14/24
230 Form work 7 days Tue 10/1/24 Wed 10/9/24 227SS+1 day
231 Rebar work 7 days Wed 10/2/24 Thu 10/10/24230SS+1 day
232 Concrete work 2 days Fri 10/11/24 Mon 10/14/24
231
233 COLUMN & SHEAR WALL 7 days Mon 10/14/24Tue 10/22/24
234 Rebar work 5 days Mon 10/14/24Fri 10/18/24232SS+1 day
235 Form work 5 days Tue 10/15/24 Mon 10/21/24
234SS+1 day
236 Concrete work 1 day Tue 10/22/24 Tue 10/22/24235
237 12th FLOOR 18 days Wed 10/23/24Fri 11/15/24
Page 11
ID Task Name DurationStart Finish
1st Half Predecessors 1st Half
1st Quarter 1st Quarter 1st Quarter 1st Quarter
Mar Aug Jan Jun Nov Apr Sep
238 SLAB, BEAM & STAIR 10 days Wed 10/23/24Tue 11/5/24
239 Form work 7 days Wed 10/23/24Thu 10/31/24
236
240 Rebar work 7 days Thu 10/24/24 Fri 11/1/24239SS+1 day
241 Concrete work 2 days Mon 11/4/24 Tue 11/5/24
240
242 COLUMN & SHEAR WALL 8 days Wed 11/6/24 Fri 11/15/24
243 Rebar work 5 days Wed 11/6/24 Tue 11/12/24
241
244 Form work 5 days Thu 11/7/24 Wed 11/13/24
243SS+1 day
245 Concrete work 2 days Thu 11/14/24 Fri 11/15/24
244
246 13th FLOOR 16 days Mon 11/18/24Mon 12/9/24
247 SLAB, BEAM & STAIR 10 days Mon 11/18/24Fri 11/29/24
248 Form work 7 days Mon 11/18/24Tue 11/26/24
245
249 Rebar work 7 days Tue 11/19/24 Wed 11/27/24
248SS+1 day
250 Concrete work 2 days Thu 11/28/24 Fri 11/29/24
249
251 COLUMN & SHEAR WALL 6 days Mon 12/2/24 Mon 12/9/24
252 Rebar work 5 days Mon 12/2/24 Fri 12/6/24250
253 Form work 5 days Tue 12/3/24 Mon 12/9/24
252SS+1 day
254 Concrete work 2 days Mon 12/2/24 Tue 12/3/24
253SS-1 day
255 14th FLOOR 17 days Fri 11/29/24 Mon 12/23/24
256 SLAB, BEAM & STAIR 10 days Fri 11/29/24 Thu 12/12/24
257 Form work 7 days Fri 11/29/24 Mon 12/9/24
254SS-1 day
258 Rebar work 7 days Mon 12/2/24 Tue 12/10/24
257SS+1 day
259 Concrete work 2 days Wed 12/11/24Thu 12/12/24
258
260 COLUMN & SHEAR WALL 8 days Thu 12/12/24Mon 12/23/24
261 Rebar work 5 days Thu 12/12/24 Wed 12/18/24
259FS-1 day
262 Form work 5 days Fri 12/13/24 Thu 12/19/24
261SS+1 day
Page 12
ID Task Name DurationStart Finish
1st Half Predecessors 1st Half
1st Quarter 1st Quarter 1st Quarter 1st Quarter
Mar Aug Jan Jun Nov Apr Sep
263 Concrete work 2 days Fri 12/20/24 Mon 12/23/24
262
264 15th FLOOR 16 days Thu 12/19/24Thu 1/9/25
265 SLAB, BEAM & STAIR 10 days Fri 12/20/24Thu 1/2/25
266 Form work 7 days Fri 12/20/24 Mon 12/30/24
263FS-2 days
267 Rebar work 7 days Mon 12/23/24Tue 12/31/24266SS+1 day
268 Concrete work 2 days Wed 1/1/25 Thu 1/2/25267
269 COLUMN & SHEAR WALL 16 days Thu 12/19/24Thu 1/9/25
270 Rebar work 5 days Thu 1/2/25 Wed 1/8/25268FS-1 day
271 Form work 5 days Fri 1/3/25 Thu 1/9/25270SS+1 day
272 Concrete work 2 days Thu 12/19/24 Fri 12/20/24
261
273 16th FLOOR 17 days Thu 12/19/24Fri 1/10/25
274 SLAB, BEAM & STAIR 10 days Thu 12/19/24Wed 1/1/25
275 Form work 7 days Thu 12/19/24 Fri 12/27/24
272FS-2 days
276 Rebar work 7 days Fri 12/20/24 Mon 12/30/24
275SS+1 day
277 Concrete work 2 days Tue 12/31/24 Wed 1/1/25276
278 COLUMN & SHEAR WALL 8 days Wed 1/1/25 Fri 1/10/25
279 Rebar work 5 days Wed 1/1/25 Tue 1/7/25277SS+1 day
280 Form work 5 days Thu 1/2/25 Wed 1/8/25279SS+1 day
281 Concrete work 2 days Thu 1/9/25 Fri 1/10/25280
282 17th FLOOR 15 days Fri 1/10/25 Thu 1/30/25
283 SLAB, BEAM & STAIR 10 days Fri 1/10/25 Thu 1/23/25
284 Form work 7 days Fri 1/10/25 Mon 1/20/25 281FS-1 day
285 Rebar work 7 days Mon 1/13/25 Tue 1/21/25 284SS+1 day
286 Concrete work 2 days Wed 1/22/25 Thu 1/23/25 285
287 COLUMN & SHEAR WALL 7 days Wed 1/22/25 Thu 1/30/25
Page 13
ID Task Name DurationStart Finish
1st Half Predecessors 1st Half
1st Quarter 1st Quarter 1st Quarter 1st Quarter
Mar Aug Jan Jun Nov Apr Sep
288 Rebar work 5 days Wed 1/22/25 Tue 1/28/25
286FS-2 days
289 Form work 5 days Thu 1/23/25 Wed 1/29/25
288SS+1 day
290 Concrete work 2 days Wed 1/29/25 Thu 1/30/25
289FS-1 day
291 18th FLOOR 17 days Thu 1/30/25 Fri 2/21/25
292 SLAB, BEAM & STAIR 10 days Thu 1/30/25 Wed 2/12/25
293 Form work 7 days Thu 1/30/25 Fri 2/7/25 290FS-1 day
294 Rebar work 7 days Fri 1/31/25 Mon 2/10/25 293SS+1 day
295 Concrete work 2 days Tue 2/11/25 Wed 2/12/25 294
296 COLUMN & SHEAR WALL 8 days Wed 2/12/25 Fri 2/21/25
297 Rebar work 5 days Wed 2/12/25 Tue 2/18/25 295SS+1 day
298 Form work 5 days Thu 2/13/25 Wed 2/19/25 297SS+1 day
299 Concrete work 2 days Thu 2/20/25 Fri 2/21/25298
300 19th FLOOR 16 days Fri 2/21/25 Fri 3/14/25
301 SLAB, BEAM & STAIR 9 days Fri 2/21/25 Wed 3/5/25
302 Form work 7 days Fri 2/21/25 Mon 3/3/25299FS-1 day
303 Rebar work 7 days Mon 2/24/25 Tue 3/4/25302SS+1 day
304 Concrete work 2 days Tue 3/4/25 Wed 3/5/25303FS-1 day
305 COLUMN& SHEAR WALL 8 days Wed 3/5/25 Fri 3/14/25
306 Rebar work 5 days Wed 3/5/25 Tue 3/11/25 304FS-1 day
307 Form work 5 days Thu 3/6/25 Wed 3/12/25 306SS+1 day
308 Concrete work 2 days Thu 3/13/25 Fri 3/14/25307
309 20th FLOOR 15 days Fri 3/14/25 Thu 4/3/25
310 SLAB, BEAM & STAIR 10 days Fri 3/14/25 Thu 3/27/25
311 Form work 7 days Fri 3/14/25 Mon 3/24/25 308FS-1 day
312 Rebar work 7 days Mon 3/17/25 Tue 3/25/25 311SS+1 day
Page 14
ID Task Name DurationStart Finish
1st Half Predecessors 1st Half
1st Quarter 1st Quarter 1st Quarter 1st Quarter
Mar Aug Jan Jun Nov Apr Sep
313 Concrete work 2 days Wed 3/26/25 Thu 3/27/25
312
314 COLUMN&SHEAR WALL 9 days Mon 3/24/25 Thu 4/3/25
315 Rebar work 5 days Thu 3/27/25 Wed 4/2/25313FS-1 day
316 Form work 5 days Fri 3/28/25 Thu 4/3/25315SS+1 day
317 Concrete work 2 days Mon 3/24/25 Wed 3/26/25 316SF-2 days
318 21st FLOOR 18 days Tue 3/25/25 Thu 4/17/25
319 SLAB, BEAM & STAIR 10 days Tue 3/25/25 Mon 4/7/25
320 Form work 7 days Tue 3/25/25 Wed 4/2/25317FS-1 day
321 Rebar work 7 days Wed 3/26/25 Thu 4/3/25320SS+1 day
322 Concrete work 2 days Fri 4/4/25 Mon 4/7/25321
323 COLUMN&SHEAR WALL 9 days Mon 4/7/25 Thu 4/17/25
324 Rebar work 5 days Mon 4/7/25 Fri 4/11/25322FS-1 day
325 Form work 5 days Wed 4/9/25 Tue 4/15/25 324SS+2 days
326 Concrete work 2 days Wed 4/16/25 Thu 4/17/25 325
327 22nd FLOOR 17 days Thu 4/17/25 Fri 5/9/25
328 SLAB, BEAM & STAIR 10 days Thu 4/17/25 Wed 4/30/25
329 Form work 7 days Thu 4/17/25 Fri 4/25/25326FS-1 day
330 Rebar work 7 days Fri 4/18/25 Mon 4/28/25 329SS+1 day
331 Concrete work 2 days Tue 4/29/25 Wed 4/30/25 330
332 COLUMN&SHEAR WALL 8 days Wed 4/30/25 Fri 5/9/25
333 Rebar work 5 days Wed 4/30/25 Tue 5/6/25331FS-1 day
334 Form work 5 days Thu 5/1/25 Wed 5/7/25333SS+1 day
335 Concrete work 2 days Thu 5/8/25 Fri 5/9/25 334
336 23rd FLOOR 15 days Fri 5/9/25 Thu 5/29/25
337 SLAB, BEAM & STAIR 10 days Fri 5/9/25 Thu 5/22/25
Page 15
ID Task Name DurationStart Finish
1st Half Predecessors 1st Half
1st Quarter 1st Quarter 1st Quarter 1st Quarter
Mar Aug Jan Jun Nov Apr Sep
338 Form work 7 days Fri 5/9/25 Mon 5/19/25
335FS-1 day
339 Rebar work 7 days Mon 5/12/25 Tue 5/20/25
338SS+1 day
340 Concrete work 2 days Wed 5/21/25 Thu 5/22/25
339
341 COLUMN&SHEAR WALL 7 days Wed 5/21/25 Thu 5/29/25
342 Rebar work 5 days Thu 5/22/25 Wed 5/28/25340SS+1 day
343 Form work 5 days Fri 5/23/25 Thu 5/29/25342SS+1 day
344 Concrete work 2 days Wed 5/21/25 Thu 5/22/25 343SS-2 days
345 24th FLOOR 15 days Thu 5/22/25 Wed 6/11/25
346 SLAB, BEAM & STAIR 10 days Thu 5/22/25 Wed 6/4/25
347 Form work 7 days Thu 5/22/25 Fri 5/30/25344FS-1 day
348 Rebar work 7 days Fri 5/23/25 Mon 6/2/25347SS+1 day
349 Concrete work 2 days Tue 6/3/25 Wed 6/4/25348
350 COLUMN&SHEAR WALL 6 days Wed 6/4/25 Wed 6/11/25
351 Rebar work 5 days Wed 6/4/25 Tue 6/10/25 349FS-1 day
352 Form work 5 days Thu 6/5/25 Wed 6/11/25 351SS+1 day
353 Concrete work 2 days Wed 6/4/25 Thu 6/5/25352SS-1 day
354 25th FLOOR 17 days Fri 6/6/25 Mon 6/30/25
355 SLAB, BEAM & STAIR 10 days Fri 6/6/25 Thu 6/19/25
356 Form work 7 days Fri 6/6/25 Mon 6/16/25353
357 Rebar work 7 days Mon 6/9/25 Tue 6/17/25 356SS+1 day
358 Concrete work 2 days Wed 6/18/25 Thu 6/19/25 357
359 COLUMN&SHEAR WALL 8 days Thu 6/19/25 Mon 6/30/25
360 Rebar work 5 days Thu 6/19/25 Wed 6/25/25 358FS-1 day
361 Form work 5 days Fri 6/20/25 Thu 6/26/25 360SS+1 day
362 Concrete work 2 days Fri 6/27/25 Mon 6/30/25 361
Page 16
ID Task Name DurationStart Finish
1st Half Predecessors 1st Half
1st Quarter 1st Quarter 1st Quarter 1st Quarter
Mar Aug Jan Jun Nov Apr Sep
363 26th FLOOR 17 days Thu 6/26/25 Fri 7/18/25
364 SLAB, BEAM & STAIR 10 days Thu 6/26/25 Wed 7/9/25
365 Form work 7 days Thu 6/26/25 Fri 7/4/25 361FS-1 day
366 Rebar work 7 days Fri 6/27/25 Mon 7/7/25365SS+1 day
367 Concrete work 2 days Tue 7/8/25 Wed 7/9/25366
368 COLUMN&SHEAR WALL 8 days Wed 7/9/25 Fri 7/18/25
369 Rebar work 5 days Wed 7/9/25 Tue 7/15/25 367FS-1 day
370 Form work 5 days Thu 7/10/25 Wed 7/16/25 369SS+1 day
371 Concrete work 2 days Thu 7/17/25 Fri 7/18/25370
372 27th FLOOR 17 days Fri 7/18/25 Mon 8/11/25
373 SLAB, BEAM & STAIR 10 days Fri 7/18/25 Thu 7/31/25
374 Form work 7 days Fri 7/18/25 Mon 7/28/25 371FS-1 day
375 Rebar work 7 days Mon 7/21/25 Tue 7/29/25 374SS+1 day
376 Concrete work 2 days Wed 7/30/25 Thu 7/31/25 375
377 COLUMN&SHEAR WALL 8 days Thu 7/31/25 Mon 8/11/25
378 Rebar work 5 days Thu 7/31/25 Wed 8/6/25376FS-1 day
379 Form work 5 days Fri 8/1/25 Thu 8/7/25378SS+1 day
380 Concrete work 2 days Fri 8/8/25 Mon 8/11/25379
381 28th FLOOR 15 days Fri 8/8/25 Thu 8/28/25
382 SLAB, BEAM & STAIR 10 days Fri 8/8/25 Thu 8/21/25
383 Form work 7 days Fri 8/8/25 Mon 8/18/25380FS-2 days
384 Rebar work 7 days Mon 8/11/25 Tue 8/19/25 383SS+1 day
385 Concrete work 2 days Wed 8/20/25 Thu 8/21/25 384
386 COLUMN&SHEAR WALL 6 days Thu 8/21/25 Thu 8/28/25
387 Rebar work 5 days Thu 8/21/25 Wed 8/27/25 385FS-1 day
Page 17
ID Task Name DurationStart Finish
1st Half Predecessors 1st Half
1st Quarter 1st Quarter 1st Quarter 1st Quarter
Mar Aug Jan Jun Nov Apr Sep
388 Form work 5 days Fri 8/22/25 Thu 8/28/25387SS+1 day
389 Concrete work 2 days Thu 8/21/25 Fri 8/22/25388SS-1 day
390 29th FLOOR 17 days Fri 8/22/25 Mon 9/15/25
391 SLAB, BEAM & STAIR 10 days Fri 8/22/25 Thu 9/4/25
392 Form work 7 days Fri 8/22/25 Mon 9/1/25389FS-1 day
393 Rebar work 7 days Mon 8/25/25 Tue 9/2/25392SS+1 day
394 Concrete work 2 days Wed 9/3/25 Thu 9/4/25393
395 COLUMN&SHEAR WALL 8 days Thu 9/4/25 Mon 9/15/25
396 Rebar work 5 days Thu 9/4/25 Wed 9/10/25 394FS-1 day
397 Form work 5 days Fri 9/5/25 Thu 9/11/25396SS+1 day
398 Concrete work 2 days Fri 9/12/25 Mon 9/15/25 397
399 30th FLOOR 20 days Mon 9/15/25 Fri 10/10/25
400 SLAB, BEAM & STAIR 10 days Mon 9/15/25 Fri 9/26/25
401 Form work 7 days Mon 9/15/25 Tue 9/23/25 398FS-1 day
402 Rebar work 7 days Tue 9/16/25 Wed 9/24/25 401SS+1 day
403 Concrete work 2 days Thu 9/25/25 Fri 9/26/25402
404 COLUMN&SHEAR WALL 11 days Fri 9/26/25 Fri 10/10/25
405 Rebar work 5 days Fri 9/26/25 Thu 10/2/25 403FS-1 day
406 Form work 5 days Mon 10/6/25 Fri 10/10/25405FS+1 day
407 Concrete work 2 days Fri 10/3/25 Mon 10/6/25 406SS-1 day
408 Roof + Top FLOOR 10 days Mon 10/6/25 Fri 10/17/25
409 SLAB, BEAM & STAIR 10 days Mon 10/6/25 Fri 10/17/25
410 Form work 7 days Mon 10/6/25 Tue 10/14/25407FS-1 day
411 Rebar work 7 days Tue 10/7/25 Wed 10/15/25410SS+1 day
412 Concrete work 2 days Thu 10/16/25 Fri 10/17/25
411
Page 18
ID Task Name DurationStart Finish
1st Half Predecessors 1st Half
1st Quarter 1st Quarter 1st Quarter 1st Quarter
Mar Aug Jan Jun Nov Apr Sep
413 FINISHING WORKS 1844 daysMon 10/20/25Thu 11/11/32
414 Block Work 120 daysMon 10/20/25Fri 4/3/26 412
415 Plastering Work 165 daysMon 4/6/26 Fri 11/20/26 414
416 Painting Work 135 daysMon 11/23/26Fri 5/28/27415
417 Floor & Wall Finishing Works 164 daysMon 5/31/27 Thu 1/13/28 416
418 CARPENTARY & JOINERY 60 days Fri 1/14/28 Thu 4/6/28417
419 METAL WORK 221 daysFri 4/7/28 Fri 2/9/29 418
420 WATER PROOFING WORKS 156 daysMon 2/12/29 Mon 9/17/29419
421 ELECTRICAL INSTALLATIONS 239 daysTue 9/18/29 Fri 8/16/30420
422 SANITARY WORKS 584 daysMon 8/19/30 Thu 11/11/32
423 Plumbing work 160 daysMon 8/19/30 Fri 3/28/31421
424 Site Sanitary works 281 daysMon 3/31/31 Mon 4/26/32 423
425 MECHANICAL WORKS 121 daysTue 4/27/32 Tue 10/12/32
426 LIFT WORK 120 daysTue 4/27/32 Mon 10/11/32 424
427 Fire fighting 1 day Tue 10/12/32 Tue 10/12/32 426
428 Land Scape Work (Greenery, Pavement, walk
22 way)
days Wed 10/13/32Thu 11/11/32
429 Pavement 15 days Wed 10/13/32Tue 11/2/32 427
430 walk way 5 days Wed 10/13/32Tue 10/19/32 427
431 Greenery 4 days Wed 10/13/32Mon 10/18/32
427
432 Fence work 7 days Wed 11/3/32 Thu 11/11/32 429
433 Other Activities 1 day Wed 10/20/32Wed 10/20/32 430
434 Guard House 4 days Wed 10/20/32Mon 10/25/32
430
435 Site Hand Over 3 days Wed 10/20/32Fri 10/22/32 430