Kingdom of Saudi Arabia
Client:
Water Transmission Co.
(WTCO)
Al Moghammas Reservoir
Transmission System.
(MRTS- Package-C)
PROJECT No. 21SWCG000523
Consultant:
Saudi Consolidated Engineering
Company SCEC
( KHATIB & ALAMI)
Contractor:
Alishar Contracting
Company.
Erection Clearance
Certificate (ECC)
N2-TIE IN STATION
CIVIL WORKS
WM & OM BUILDING
33-01-01-04-01-01
Volume No. 1 of 1
Kingdom of Saudi Arabia
Water Transmission and Technologies Co. (WTTCO)
Al Moghammas Reservoir Transmission System. (MRTS- Package-C)
PROJECT No. 21SWCG000523
Erection Clearance Certificate
(ECC)
ALMOGHAMMAS RESERVOIR TRANSMISSION SYSTEM PACKAGE-C
N2 -TIE IN STATION
CIVIL WORKS
WM & OM BUILDING
33-01-01-04-01-01
KINGDOM OF SAUDI ARABIA
WATER TRANSMISSION & TECHNOLGIES CO. (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM PACKAGE-C
PROJECT No. 21SWCG000523
Erection Clearance Certificate
(E C C)
ALMOGHAMMAS RESERVOIR TRANSMISSION SYSTEM
PACKAGE-C
N2 TIE IN STATION-CIVIL WORKS
WM & OM BUILDING
33-01-01-04-01-01
KINGDOM OF SAUDI ARABIA
WATER TRANSMISSION & TECHNOLGIES CO. (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM PACKAGE-C
PROJECT No. 21SWCG000523
GENERAL TABLE OF CONTENTS
ITEM # DESCRIPTION
1.0 ERECTION CLEARANCE CERTIFICATE INDEX SHEET
2.0 ERECTION CLEARANCE CERTIFICATE (ECC)
3.0 SCHEDULE OF DOCUMENTS FOR ECC
4.0 SCHEDULE OF TESTS & CHECKS FOR ECC
5.0 SCHEDULE OF MODIFICATIONS FOR ECC
6.0 SCHEDULE OF OUTSTANDING WORKS FOR ECC
7.0 ERECTION CHECK LIST
KINGDOMF SAUDI ARABIA
WATER TRANSMSSION AND TECHNOLGIES COMPANY (WTTCO)AL-
MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM-PACKAGE-C
PROJECT No. 21SWCG000523
__________________________________________________________________________________________________________________________
1.0
ERECTION CLEARANCE CERTIFICATE
INDEX SHEET
Document ID No : ASCC-QAQC-FARM-015
Water Transmission and Technologies Company Page: 1 of 1
Rev. No.: 0
Construction & Pre-Commissioning Procedure Date of Issue: 01-08-2024
__________________________________________________________________________________________________________________________
ERECTION CLEARANCE CERTIFICATE INDEX SHEET (ECC)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C
Consultant Contractor Site/Group
KHATIB & ALAMI ALISHAR CONTRACTING N2-TIE IN STATION –CIVIL WORKS
COMPANY (WM & OM BUILDING)
SYSTEM: AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C
KKS #......................................................................................................................
Included
No Record/ Documents Remarks
YES NO N/A
1. ECC Index Sheet
2. Erection Clearance Certificate
3. Schedule of Documents
4. Schedule of Tests & Checks for ECC
5. Schedule of modification for ECC
6. Schedule of Outstanding works for ECC
7. Erection Check List
Name Signature Date
Contractor ABDUL SATTAR 01-12-2024
Engineer
KINGDOMF SAUDI ARABIA
WATER TRANSMSSION AND TECHNOLGIES COMPANY (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM-PACKAGE-C
PROJECT No. 21SWCG000523
2.0
ERECTION CLEARANCE CERTIFICATE (ECC)
Document ID No : ASCC-QAQC-FARM-016
Water Transmission and Technologies Company
Page: 1 of 1
Rev. No.: 0
Construction & Pre-Commissioning Procedure Date of Issue: 01-08-2024
ERECTION CLEARANCE CERTIFICATE (ECC)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C
PROJECT No. 21SWCG000523
Consultant Contractor Site/Group
KHATIB & ALAMI ALISHAR CONTRACTING N2-TIE IN STATION –CIVIL WORKS
COMPANY (WM & OM BUILDING)
Date of Issue for ECC: 01-12-2024
As of 1000. Hours on 01-12-2024 for the plant item / system described below is in a sufficiently advanced
stage of erection for the said item / system to be issued with an Erection Clearance Certificate (ECC).
Responsibility for this area will remain with / transfer to Alishar Contracting Company of MRTS-MAKKAH
N2-TIE IN STATION.
Description of Plant Items / System: AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C
Terminal Point… N2-TIE IN STATION –CIVIL WORKS (WM & OM BUILDING)
Amended schedule of Documents Ref. No: SD - 33-01-01-04-01-01
Amended schedule of Tests and Checks Ref. No: STC - 33-01-01-04-01-01
Amended schedule of Modifications Ref. No: SM - 33-01-01-04-01-01
Amended schedule of Outstanding Works Ref. No: SOW - 33-01-01-04-01-01
Name Signature Date
Contractor Marwan Khader 01-12-2024
Engineer
WTTCO
` KINGDOMF SAUDI ARABIA
WATER TRANSMSSION AND TECHNOLGIES COMPANY (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM-PACKAGE-C
PROJECT No. 21SWCG000523
______________________________________________________________________________________________________
3.0
SCHEDULE OF DOCUMENTS FOR ECC
KINGDOMF SAUDI ARABIA
WATER TRANSMSSION AND TECHNOLGIES COMPANY (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM-PACKAGE-C
PROJECT No. 21SWCG000523
4.0
SCHEDULE OF TESTS & CHECKS
FOR ECC
KINGDOMF SAUDI ARABIA
WATER TRANSMSSION AND TECHNOLGIES COMPANY (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM-PACKAGE-C
PROJECT No. 21SWCG000523
_____________________________________________________________________________
4.1
MRIRs for CONCRETE WORKS &
PRECAST ELEMENTS
KINGDOMF SAUDI ARABIA
WATER TRANSMSSION AND TECHNOLGIES COMPANY (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM-PACKAGE-C
PROJECT No. 21SWCG000523
_____________________________________________________________________________
4.2
RFIs for CONCRETE WORKS &
PRECAST ELEMENTS
Document ID No : ASCC-QAQC-FARM-018
Water Transmission and Technologies Company
Page: 1 of 1
Rev. No.: 0
Construction & Pre-Commissioning Procedure Date of Issue: 01-08-2024
SCHEDULE OF TESTS & CHECKS FOR ECC
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C
Consultant Contractor Site/Group
ALISHAR CONTRACTING N2-TIE IN STATION –CIVIL WORKS
KHATIB & ALAMI
COMPANY (WM & OM BUILDING)
System: AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C
KKS No.: ……………………………………………………………………………………….
No. Document No. Description
1. MRIRs For concrete and other materials
2. RFIs For Concrete and other works
Name Signature Date
Contractor ABDUL SATTAR 01-12-2024
Engineer
KINGDOMF SAUDI ARABIA
WATER TRANSMSSION AND TECHNOLGIES COMPANY (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM-PACKAGE-C
PROJECT No. 21SWCG000523
5.0
SCHEDULE OF MODIFICATIONS FOR ECC
Document ID No : ASCC-QAQC-FARM-019
Water Transmission and Technologies Company
Page: 1 of 1
Rev. No.: 0
Construction & Pre-Commissioning Procedure Date of Issue: 01-08-2024
SCHEDULE OF MODIFICATIONS FOR ECC
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C
Consultant Contractor Site/Group
ALISHAR CONTRACTING COMPANY N2-TIE IN STATION –CIVIL WORKS
KHATIB & ALAMI
(WM & OM BUILDING)
System: AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C
KKS No.: …………………………………………………………………………………………………..
No. Document Ref. Description
There is no modification for N2-TIE IN STATION –CIVIL WORKS (WM & OM BUILDING)
01
Name Signature Date
Contractor ABDUL SATTAR 01-12-2024
Engineer
KINGDOMF SAUDI ARABIA
WATER TRANSMSSION AND TECHNOLGIES COMPANY (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM-PACKAGE-C
PROJECT No. 21SWCG000523
6.0
SCHEDULE OF OUTSTANDING WORKS FOR
ECC
Document ID No : ASCC-QAQC-FARM-020
Water Transmission and Technologies Company
Page: 1 of 2
Rev. No.: 0
Construction & Pre-Commissioning Procedure Date of Issue: 01-08-2024
SCHEDULE OF OUTSTANDING WORKS FOR ECC
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C
Contractor Contractor Contractor
ALISHAR CONTRACTING N2-TIE IN STATION –CIVIL WORKS
KHATIB & ALAMI
COMPANY (WM & OM BUILDING)
System: AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C
KKS No.: …………………………………………………………………………………………………..
Outstanding Works Cleared
No. Outstanding Work/Details Category Action By WTCO
Engineer Technical
Committee
1 Finishing works are ongoitg B ASCC
Name Signature Date
Contractor ABDUL SATTAR 01-12-2024
Engineer
KINGDOMF SAUDI ARABIA
WATER TRANSMSSION AND TECHNOLGIES COMPANY (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM-PACKAGE-C
PROJECT No. 21SWCG000523
7.0
ERECTION CHECK LIST
Document ID No : ASCC-QAQC-FARM-021
Water Transmission and Technologies Company
Page: 1 of 1
Rev. No.: 0
Construction & Pre-Commissioning Procedure Date of Issue: 01-08-2024
ERECTION CHECK LIST
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C
Consultant Contractor Site/Group
N2-TIE IN STATION –CIVIL WORKS
KHATIB & ALAMI ALISHAR CONTRACTING COMPANY
(WM & OM BUILDING)
System: …………………………………… Ref. Drawing No.: ……………………………………
Civil Electrical Mechanical Instrumentation
KKS No.: …………………………………………………………………………………………………..
No. Job Description Remarks Witness Date
1. NA
Name Signature Date
Contractor ABDUL SATTAR 01-12-2024
Engineer