0% found this document useful (0 votes)
44 views19 pages

Saudi Reservoir Transmission ECC

Uploaded by

fiverr101010
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
44 views19 pages

Saudi Reservoir Transmission ECC

Uploaded by

fiverr101010
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Kingdom of Saudi Arabia

Client:

Water Transmission Co.


(WTCO)

Al Moghammas Reservoir
Transmission System.
(MRTS- Package-C)
PROJECT No. 21SWCG000523
Consultant:

Saudi Consolidated Engineering


Company SCEC
( KHATIB & ALAMI)
Contractor:

Alishar Contracting
Company.
Erection Clearance
Certificate (ECC)

N2-TIE IN STATION
CIVIL WORKS

WM & OM BUILDING

33-01-01-04-01-01

Volume No. 1 of 1
Kingdom of Saudi Arabia
Water Transmission and Technologies Co. (WTTCO)
Al Moghammas Reservoir Transmission System. (MRTS- Package-C)
PROJECT No. 21SWCG000523

Erection Clearance Certificate


(ECC)
ALMOGHAMMAS RESERVOIR TRANSMISSION SYSTEM PACKAGE-C

N2 -TIE IN STATION
CIVIL WORKS

WM & OM BUILDING

33-01-01-04-01-01
KINGDOM OF SAUDI ARABIA
WATER TRANSMISSION & TECHNOLGIES CO. (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM PACKAGE-C
PROJECT No. 21SWCG000523

Erection Clearance Certificate


(E C C)

ALMOGHAMMAS RESERVOIR TRANSMISSION SYSTEM


PACKAGE-C

N2 TIE IN STATION-CIVIL WORKS

WM & OM BUILDING

33-01-01-04-01-01
KINGDOM OF SAUDI ARABIA
WATER TRANSMISSION & TECHNOLGIES CO. (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM PACKAGE-C
PROJECT No. 21SWCG000523

GENERAL TABLE OF CONTENTS

ITEM # DESCRIPTION
1.0 ERECTION CLEARANCE CERTIFICATE INDEX SHEET
2.0 ERECTION CLEARANCE CERTIFICATE (ECC)
3.0 SCHEDULE OF DOCUMENTS FOR ECC
4.0 SCHEDULE OF TESTS & CHECKS FOR ECC
5.0 SCHEDULE OF MODIFICATIONS FOR ECC
6.0 SCHEDULE OF OUTSTANDING WORKS FOR ECC
7.0 ERECTION CHECK LIST
KINGDOMF SAUDI ARABIA
WATER TRANSMSSION AND TECHNOLGIES COMPANY (WTTCO)AL-
MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM-PACKAGE-C
PROJECT No. 21SWCG000523
__________________________________________________________________________________________________________________________

1.0

ERECTION CLEARANCE CERTIFICATE


INDEX SHEET
Document ID No : ASCC-QAQC-FARM-015
Water Transmission and Technologies Company Page: 1 of 1
Rev. No.: 0
Construction & Pre-Commissioning Procedure Date of Issue: 01-08-2024

__________________________________________________________________________________________________________________________

ERECTION CLEARANCE CERTIFICATE INDEX SHEET (ECC)

AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C


Consultant Contractor Site/Group
KHATIB & ALAMI ALISHAR CONTRACTING N2-TIE IN STATION –CIVIL WORKS
COMPANY (WM & OM BUILDING)

SYSTEM: AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C

KKS #......................................................................................................................

Included
No Record/ Documents Remarks
YES NO N/A
1. ECC Index Sheet
2. Erection Clearance Certificate
3. Schedule of Documents
4. Schedule of Tests & Checks for ECC
5. Schedule of modification for ECC
6. Schedule of Outstanding works for ECC
7. Erection Check List

Name Signature Date

Contractor ABDUL SATTAR 01-12-2024

Engineer
KINGDOMF SAUDI ARABIA
WATER TRANSMSSION AND TECHNOLGIES COMPANY (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM-PACKAGE-C
PROJECT No. 21SWCG000523

2.0

ERECTION CLEARANCE CERTIFICATE (ECC)


Document ID No : ASCC-QAQC-FARM-016
Water Transmission and Technologies Company
Page: 1 of 1
Rev. No.: 0
Construction & Pre-Commissioning Procedure Date of Issue: 01-08-2024

ERECTION CLEARANCE CERTIFICATE (ECC)

AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C


PROJECT No. 21SWCG000523
Consultant Contractor Site/Group
KHATIB & ALAMI ALISHAR CONTRACTING N2-TIE IN STATION –CIVIL WORKS
COMPANY (WM & OM BUILDING)

Date of Issue for ECC: 01-12-2024

As of 1000. Hours on 01-12-2024 for the plant item / system described below is in a sufficiently advanced
stage of erection for the said item / system to be issued with an Erection Clearance Certificate (ECC).

Responsibility for this area will remain with / transfer to Alishar Contracting Company of MRTS-MAKKAH
N2-TIE IN STATION.

Description of Plant Items / System: AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C

Terminal Point… N2-TIE IN STATION –CIVIL WORKS (WM & OM BUILDING)

Amended schedule of Documents Ref. No: SD - 33-01-01-04-01-01


Amended schedule of Tests and Checks Ref. No: STC - 33-01-01-04-01-01
Amended schedule of Modifications Ref. No: SM - 33-01-01-04-01-01
Amended schedule of Outstanding Works Ref. No: SOW - 33-01-01-04-01-01

Name Signature Date

Contractor Marwan Khader 01-12-2024

Engineer

WTTCO
` KINGDOMF SAUDI ARABIA
WATER TRANSMSSION AND TECHNOLGIES COMPANY (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM-PACKAGE-C
PROJECT No. 21SWCG000523
______________________________________________________________________________________________________

3.0

SCHEDULE OF DOCUMENTS FOR ECC


KINGDOMF SAUDI ARABIA
WATER TRANSMSSION AND TECHNOLGIES COMPANY (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM-PACKAGE-C
PROJECT No. 21SWCG000523

4.0

SCHEDULE OF TESTS & CHECKS


FOR ECC
KINGDOMF SAUDI ARABIA
WATER TRANSMSSION AND TECHNOLGIES COMPANY (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM-PACKAGE-C
PROJECT No. 21SWCG000523
_____________________________________________________________________________

4.1

MRIRs for CONCRETE WORKS &


PRECAST ELEMENTS
KINGDOMF SAUDI ARABIA
WATER TRANSMSSION AND TECHNOLGIES COMPANY (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM-PACKAGE-C
PROJECT No. 21SWCG000523

_____________________________________________________________________________

4.2

RFIs for CONCRETE WORKS &


PRECAST ELEMENTS
Document ID No : ASCC-QAQC-FARM-018
Water Transmission and Technologies Company
Page: 1 of 1
Rev. No.: 0
Construction & Pre-Commissioning Procedure Date of Issue: 01-08-2024

SCHEDULE OF TESTS & CHECKS FOR ECC

AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C


Consultant Contractor Site/Group
ALISHAR CONTRACTING N2-TIE IN STATION –CIVIL WORKS
KHATIB & ALAMI
COMPANY (WM & OM BUILDING)

System: AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C

KKS No.: ……………………………………………………………………………………….

No. Document No. Description

1. MRIRs For concrete and other materials

2. RFIs For Concrete and other works

Name Signature Date

Contractor ABDUL SATTAR 01-12-2024

Engineer
KINGDOMF SAUDI ARABIA
WATER TRANSMSSION AND TECHNOLGIES COMPANY (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM-PACKAGE-C
PROJECT No. 21SWCG000523

5.0

SCHEDULE OF MODIFICATIONS FOR ECC


Document ID No : ASCC-QAQC-FARM-019
Water Transmission and Technologies Company
Page: 1 of 1
Rev. No.: 0
Construction & Pre-Commissioning Procedure Date of Issue: 01-08-2024

SCHEDULE OF MODIFICATIONS FOR ECC

AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C


Consultant Contractor Site/Group
ALISHAR CONTRACTING COMPANY N2-TIE IN STATION –CIVIL WORKS
KHATIB & ALAMI
(WM & OM BUILDING)

System: AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C

KKS No.: …………………………………………………………………………………………………..

No. Document Ref. Description

There is no modification for N2-TIE IN STATION –CIVIL WORKS (WM & OM BUILDING)
01

Name Signature Date

Contractor ABDUL SATTAR 01-12-2024

Engineer
KINGDOMF SAUDI ARABIA
WATER TRANSMSSION AND TECHNOLGIES COMPANY (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM-PACKAGE-C
PROJECT No. 21SWCG000523

6.0

SCHEDULE OF OUTSTANDING WORKS FOR


ECC
Document ID No : ASCC-QAQC-FARM-020
Water Transmission and Technologies Company
Page: 1 of 2
Rev. No.: 0
Construction & Pre-Commissioning Procedure Date of Issue: 01-08-2024

SCHEDULE OF OUTSTANDING WORKS FOR ECC

AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C


Contractor Contractor Contractor
ALISHAR CONTRACTING N2-TIE IN STATION –CIVIL WORKS
KHATIB & ALAMI
COMPANY (WM & OM BUILDING)

System: AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C

KKS No.: …………………………………………………………………………………………………..

Outstanding Works Cleared

No. Outstanding Work/Details Category Action By WTCO


Engineer Technical
Committee
1 Finishing works are ongoitg B ASCC

Name Signature Date

Contractor ABDUL SATTAR 01-12-2024

Engineer
KINGDOMF SAUDI ARABIA
WATER TRANSMSSION AND TECHNOLGIES COMPANY (WTTCO)
AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM-PACKAGE-C
PROJECT No. 21SWCG000523

7.0

ERECTION CHECK LIST


Document ID No : ASCC-QAQC-FARM-021
Water Transmission and Technologies Company
Page: 1 of 1
Rev. No.: 0
Construction & Pre-Commissioning Procedure Date of Issue: 01-08-2024

ERECTION CHECK LIST

AL-MOGHAMMAS RESERVOIR TRANSMISSION SYSTEM- PACKAGE-C


Consultant Contractor Site/Group
N2-TIE IN STATION –CIVIL WORKS
KHATIB & ALAMI ALISHAR CONTRACTING COMPANY
(WM & OM BUILDING)

System: …………………………………… Ref. Drawing No.: ……………………………………

 Civil  Electrical  Mechanical  Instrumentation

KKS No.: …………………………………………………………………………………………………..

No. Job Description Remarks Witness Date

1. NA

Name Signature Date

Contractor ABDUL SATTAR 01-12-2024

Engineer

You might also like