IE325 Course Material For Week 3-4
IE325 Course Material For Week 3-4
► Research Project
Copyright © 2017 Pearson Education Ltd 3-7
Management of Projects
1. Planning - goal setting, defining the
project, team organization
2. Scheduling - relate people, money,
and supplies to specific activities and
activities to each other
3. Controlling - monitor resources, costs,
quality, and budgets; revise plans and
shift resources to meet time and cost
demands
Copyright © 2017 Pearson Education Ltd 3-8
Project Management Activities
► Planning
► Objectives ► Scheduling
► Resources ► Project
activities
► Work break-
down structure ► Start and end
times
► Organization
► Network
► Controlling
► Monitor, compare, revise, action
Copyright © 2017 Pearson Education Ltd 3-9
Project Planning,
Scheduling, and Controlling
Figure 3.1
Figure 3.1
Figure 3.1
Figure 3.1
Budgets
Delayed activities report
Slack activities report
CPM/PERT
Gantt charts
Milestone charts
Figure
Cash 3.1schedules
flow
Human Quality
Resources Marketing Finance Design Production
Mgt
Figure 3.2
Level
1. Project
2. Major tasks in the project
3. Subtasks in the major tasks
4. Activities (or “work packages”)
to be completed
Compatible with
Level 4 1.1.2.1
Windows 7
(Work packages)
Compatible with
1.1.2.2
Windows Vista
► Gantt chart
► Critical Path Method (CPM)
► Program Evaluation and Review
Technique (PERT)
Time
J F M A M J J A S
Design
Prototype
Test
Revise
Production
C and D cannot
A C begin until both A C
(d) A and B are
completed
B D B D
B and C cannot
begin until A is
completed
A B D D cannot begin A B D
until both B and C
(f) are completed Dummy
A dummy activity activity
C
C
is again
introduced in AOA
Activity A
A
(Build Internal Components)
Start
Activity B
Start B (Modify Roof and Floor)
Activity
Figure 3.5
A C
Start
B D
F
A C
E
Start H
B D G
H
1 Dummy 6 7
Activity (Inspect/
Test)
D
3 5
(Pour Figure 3.8
Concrete/
Install Frame)
Copyright © 2017 Pearson Education Ltd 3 - 44
Example
Activity Name
or Symbol
A Earliest
Earliest ES EF Finish
Start
Latest LS LF Latest
Start 2 Finish
Activity Duration
Copyright © 2017 Pearson Education Ltd 3 - 50
Forward Pass
Begin at starting event and work forward
EF = ES + Activity time
ES EF = ES + Activity time
Start
0 0
2 EF of B =
ES ES of B + 3
0
Start
0 of B
B
0 0 3
3
Copyright © 2017 Pearson Education Ltd 3 - 55
ES/EF Network for Milwaukee
Paper
A C
0 2 2 4
2 2
Start
0 0
B
0 3
2 2
Start
0 0
= Max (2, 3) D
0
3 7
B
0 3
3
4
Copyright © 2017 Pearson Education Ltd 3 - 57
ES/EF Network for Milwaukee
Paper
A C
0 2 2 4
2 2
Start
0 0
B D
0 3 3 7
3 4
2 2 3
Start E H
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
3 4 5
Figure 3.10
Copyright © 2017 Pearson Education Ltd 3 - 59
Backward Pass
Begin with the last event and work backwards
Latest Finish Time Rule:
LS = LF – Activity time
2 2 3
Start E H
0 0 4 8 13 15
13 15
0 4 2
B D – Activity timeG
LS = LF
0 3 3 7 8 13
3 4 5 LF = EF
of Project
Copyright © 2017 Pearson Education Ltd 3 - 62
LS/LF Times for
Milwaukee Paper
A C F
0 2 2 4 4 7
10 13
2 2 3
Start E H
0 0
LF 4= Min(LS
8 of 13 15
following activity) 13 15
0 4 2
B D G
0 3 3 7 8 13
3 4 5
2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
8 13
3 4 5
0 2 2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5
Slack = LS – ES or Slack = LF – EF
0 2 2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5
A Build internal
components
B Modify roof and floor
C Construct collection
stack
D Pour concrete and
install frame
E Build high-temperature
burner
F Install pollution control
system
G Install air pollution
device
H Inspect and test
A Build internal
components
B Modify roof and floor
C Construct collection
stack
D Pour concrete and
install frame
E Build high-temperature
burner
F Install pollution control
system
G Install air pollution
device
H Inspect and test
v =
Variance of activity completion[(b − a)/6]2Probability of 1 in 100
of >times:
b occurring
MOST
OPTIMISTIC LIKELY PESSIMISTIC EXPECTED TIME VARIANCE
ACTIVITY a m b t = (a + 4m + b)/6 [(b – a)/6]2
A 1 2 3 2 .11
B 2 3 4 3 .11
C 1 2 3 2 .11
D 2 4 6 4 .44
E 1 4 7 4 1.00
F 1 2 9 3 1.78
G 3 4 11 5 1.78
H 1 2 3 2 .11
15 Weeks
(Expected Completion Time)
.5 = due .69497
Z.69146 − expected.71566
date /s
.71904
p
date of completion
.6 .72575 .72907 .74857 .75175
= (16 wks − 15 wks)/1.76
15 16 Time
Weeks Weeks
Figure 3.13
Probability
of 0.01
2.33 Standard Z
From Appendix I deviations
0 2.33
Figure 3.14
$30,000 —
Normal
Normal —
Cost
| | |
1 2 3 Time (Weeks)
Figure 3.15
Crash Time Normal Time
Copyright © 2017 Pearson Education Ltd 3 - 95
Critical Path and Slack Times
for Milwaukee Paper
Figure 3.16
A C F
0 2 2 4 4 7
0 2 2 4 10 13
2 2 3
0 0 4 8 13 15
0 4 2
B D Slack = 0 G Slack = 0
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5