0% found this document useful (0 votes)
40 views99 pages

IE325 Course Material For Week 3-4

Endüstri mühendisliği açıklamalarını kapsar

Uploaded by

snnrzdmr38
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
40 views99 pages

IE325 Course Material For Week 3-4

Endüstri mühendisliği açıklamalarını kapsar

Uploaded by

snnrzdmr38
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Project Management

Copyright © 2017 Pearson Education Ltd 3-1


Outline
► The Importance of Project
Management
► Project Planning
► Project Scheduling
► Project Controlling

Copyright © 2017 Pearson Education Ltd 3-2


Outline - Continued
► Project Management Techniques:
PERT and CPM
► Determining the Project Schedule
► Variability in Activity Times
► Cost-Time Trade-offs and Project
Crashing

Copyright © 2017 Pearson Education Ltd 3-3


Outline - Continued
► A Critique of PERT and CPM

Copyright © 2017 Pearson Education Ltd 3-4


Learning Objectives
When you complete this chapter you
should be able to:
3.1 Use a Gantt chart for scheduling
3.2 Draw AOA and AON networks
3.3 Complete forward and backward
passes for a project
3.4 Determine a critical path

Copyright © 2017 Pearson Education Ltd 3-5


Learning Objectives
When you complete this chapter you
should be able to:
3.5 Calculate the variance of
activity times
3.6 Crash a project

Copyright © 2017 Pearson Education Ltd 3-6


Examples of Projects
► Building Construction

► Research Project
Copyright © 2017 Pearson Education Ltd 3-7
Management of Projects
1. Planning - goal setting, defining the
project, team organization
2. Scheduling - relate people, money,
and supplies to specific activities and
activities to each other
3. Controlling - monitor resources, costs,
quality, and budgets; revise plans and
shift resources to meet time and cost
demands
Copyright © 2017 Pearson Education Ltd 3-8
Project Management Activities
► Planning
► Objectives ► Scheduling
► Resources ► Project
activities
► Work break-
down structure ► Start and end
times
► Organization
► Network

► Controlling
► Monitor, compare, revise, action
Copyright © 2017 Pearson Education Ltd 3-9
Project Planning,
Scheduling, and Controlling

Figure 3.1

Copyright © 2017 Pearson Education Ltd 3 - 10


Project Planning,
Scheduling, and Controlling

Figure 3.1

Copyright © 2017 Pearson Education Ltd 3 - 11


Project Planning,
Scheduling, and Controlling

Figure 3.1

Copyright © 2017 Pearson Education Ltd 3 - 12


Project Planning,
Scheduling, and Controlling

Figure 3.1

Copyright © 2017 Pearson Education Ltd 3 - 13


Project Time/cost
Planning,
Budgets
estimates

Scheduling, and Controlling


Engineering diagrams
Cash flow charts
Material availability details

Budgets
Delayed activities report
Slack activities report

CPM/PERT
Gantt charts
Milestone charts
Figure
Cash 3.1schedules
flow

Copyright © 2017 Pearson Education Ltd 3 - 14


Project Planning
► Establishing objectives
► Defining project
► Creating work
breakdown structure
► Determining
resources
► Forming organization

© 2014 Pearson Education, Inc. 3 - 15


Project Organization
► Often temporary structure
► Uses specialists from entire company
► Headed by project manager
► Coordinates activities
► Monitors schedule
and costs

© 2014 Pearson Education, Inc. 3 - 16


Project Organization
Most Helpful When:
1. Work can be defined with a specific goal
and deadline
2. The job is unique or somewhat unfamiliar
to the existing organization
3. The work contains complex interrelated
tasks requiring specialized skills
4. The project is temporary but critical to the
organization
5. The project cuts across organizational
lines
Copyright © 2017 Pearson Education Ltd 3 - 17
A Sample Project
Organization
President

Human Quality
Resources Marketing Finance Design Production
Mgt

Project Project Mechanical Test


Technician
No. 1 Manager Engineer Engineer

Project Project Electrical Computer


Technician
No. 2 Manager Engineer Engineer

Figure 3.2

Copyright © 2017 Pearson Education Ltd 3 - 18


The Role of
the Project Manager
Highly visible
Responsible for making sure that:
1) All necessary activities are finished in order
and on time
2) The project comes in within budget
3) The project meets quality goals
4) The people assigned to the project receive
motivation, direction, and information
Copyright © 2017 Pearson Education Ltd 3 - 19
The Role of
the Project Manager
Highly visible Project managers should be:
Responsible for making sure that:
► Good coaches
1) All necessary activities
► Goodare finished in order
communicators
and on time ► Able to organize activities

2) The project comes from a variety


in within of disciplines
budget
3) The project meets quality goals
4) The people assigned to the project receive
motivation, direction, and information
Copyright © 2017 Pearson Education Ltd 3 - 20
Ethical Issues
► Project managers face many ethical decisions
on a daily basis
► The Project Management Institute has
established an ethical code to deal with
problems such as:
1) Offers of gifts from contractors
2) Pressure to alter status reports to mask delays
3) False reports for charges of time and expenses
4) Pressure to compromise quality to meet schedules

Copyright © 2017 Pearson Education Ltd 3 - 21


Work Breakdown Structure

Level
1. Project
2. Major tasks in the project
3. Subtasks in the major tasks
4. Activities (or “work packages”)
to be completed

Copyright © 2017 Pearson Education Ltd 3 - 22


Work Breakdown Structure
Develop Windows 8
Level 1 1.0
Operating System

Software Cost Management System


Level 2 1.1 1.2 1.3
Design Plan Testing

Develop Design Cost Module


Level 3 1.1.1 1.2.1 1.3.1
GUIs Tracking Reports Testing

Ensure Compatibility Develop Defect


with Earlier Versions 1.1.2 Cost/Schedule 1.2.2 Testing 1.3.2
Interface

Compatible with
Level 4 1.1.2.1
Windows 7
(Work packages)
Compatible with
1.1.2.2
Windows Vista

Compatible with Figure 3.3


Windows XP 1.1.2.3

Copyright © 2017 Pearson Education Ltd 3 - 23


Project Scheduling Techniques
1) Ensure that all activities
are planned for
2) Their order of
performance is
accounted for
3) The activity time
estimates are recorded
4) The overall project time is developed

Copyright © 2017 Pearson Education Ltd 3 - 24


Purposes of Project
Scheduling
1. Shows the relationship of each activity to
others and to the whole project
2. Identifies the precedence relationships
among activities
3. Encourages the setting of realistic time and
cost estimates for each activity
4. Helps make better use of people, money,
and material resources by identifying critical
bottlenecks in the project
Copyright © 2017 Pearson Education Ltd 3 - 25
Project Management
Techniques

► Gantt chart
► Critical Path Method (CPM)
► Program Evaluation and Review
Technique (PERT)

Copyright © 2017 Pearson Education Ltd 3 - 26


A Simple Gantt Chart

Time
J F M A M J J A S

Design
Prototype
Test
Revise
Production

Copyright © 2017 Pearson Education Ltd 3 - 27


Service For a Delta Jet
Deplaning
Passengers
Baggage claim
Baggage Container offload
Pumping
Fueling
Engine injection water
Cargo and mail Container offload
Main cabin door
Galley servicing
Aft cabin door
Lavatory servicing Aft, center, forward
Drinking water Loading
First-class section
Cabin cleaning
Economy section
Cargo and mail Container/bulk loading
Galley/cabin check
Flight services
Receive passengers
Operating crew Aircraft check
Baggage Loading
Passengers Boarding
0 10 20 30 40
Time, Minutes
Figure 3.4
Copyright © 2017 Pearson Education Ltd 3 - 28
Project Controlling
► Close monitoring of
resources, costs,
quality, budgets
► Feedback enables
revising the project plan
and shift resources
► Computerized tools
produce extensive
reports

© 2014 Pearson Education, Inc. 3 - 29


Project Management Software

► There are several popular


packages for managing projects
► Oracle Primavera
► MindView
► HP Project
► Fast Track
► Microsoft Project

Copyright © 2017 Pearson Education Ltd 3 - 30


Project Control Reports
1) Detailed cost breakdowns for each task
2) Labor requirements
3) Cost and hour summaries
4) Raw materials and expenditure forecasts
5) Variance reports
6) Time analysis reports
7) Work status reports

Copyright © 2017 Pearson Education Ltd 3 - 31


PERT and CPM
► Network techniques
► Developed in 1950s
► CPM by DuPont for chemical plants (1957)
► PERT by Booz, Allen & Hamilton with the U.S.
Navy, for Polaris missile (1958)
► Consider precedence relationships and
interdependencies
► Each uses a different estimate of activity
times

Copyright © 2017 Pearson Education Ltd 3 - 32


Six Steps PERT and CPM
1. Define the project and prepare the
work breakdown structure
2. Develop relationships among the
activities – decide which activities must
precede and which must follow others
3. Draw the network connecting all of the
activities

Copyright © 2017 Pearson Education Ltd 3 - 33


Six Steps PERT and CPM
4. Assign time and/or cost estimates to
each activity
5. Compute the longest time path through
the network – this is called the critical
path
6. Use the network to help plan,
schedule, monitor, and control the
project

Copyright © 2017 Pearson Education Ltd 3 - 34


Questions PERT and CPM
Can Answer
1. When will the entire project be completed?
2. What are the critical activities or tasks in the
project?
3. Which are the noncritical activities?
4. What is the probability the project will be
completed by a specific date?

Copyright © 2017 Pearson Education Ltd 3 - 35


Questions PERT and CPM
Can Answer
5. Is the project on schedule, behind schedule,
or ahead of schedule?
6. Is the money spent equal to, less than, or
greater than the budget?
7. Are there enough resources available to
finish the project on time?
8. If the project must be finished in a shorter
time, what is the way to accomplish this at
least cost?
Copyright © 2017 Pearson Education Ltd 3 - 36
A Comparison of AON and
AOA Network Conventions
Activity on Activity Activity on
Node (AON) Meaning Arrow (AOA)
A comes before
(a) A B C B, which comes
before C A B C
A A
A and B must both
(b) C be completed
before C can start C
B B
B
B and C cannot
(c) A begin until A is B
completed A
C C
Copyright © 2017 Pearson Education Ltd 3 - 37
A Comparison of AON and
AOA Network Conventions
Activity on Activity Activity on
Node (AON) Meaning Arrow (AOA)

C and D cannot
A C begin until both A C
(d) A and B are
completed
B D B D

C cannot begin until


both A and B are
A C completed A C
(e) D cannot begin until Dummy activity
B is completed
B D A dummy activity is
introduced in AOA B D
Copyright © 2017 Pearson Education Ltd 3 - 38
A Comparison of AON and
AOA Network Conventions
Activity on Activity Activity on
Node (AON) Meaning Arrow (AOA)

B and C cannot
begin until A is
completed
A B D D cannot begin A B D
until both B and C
(f) are completed Dummy
A dummy activity activity
C
C
is again
introduced in AOA

Copyright © 2017 Pearson Education Ltd 3 - 39


AON Example
Table 3.1 Milwaukee Paper Manufacturing’s Activities and Predecessors
IMMEDIATE
ACTIVITY DESCRIPTION PREDECESSORS
A Build internal components —
B Modify roof and floor —
C Construct collection stack A
D Pour concrete and install frame A, B
E Build high-temperature burner C
F Install pollution control system C
G Install air pollution device D, E
H Inspect and test F, G

© 2014 Pearson Education, Inc. 3 - 40


AON Network for
Milwaukee Paper

Activity A
A
(Build Internal Components)

Start

Activity B
Start B (Modify Roof and Floor)
Activity
Figure 3.5

Copyright © 2017 Pearson Education Ltd 3 - 41


AON Network for
Milwaukee Paper
Activity A Precedes Activity C

A C

Start

B D

Activities A and B Figure 3.6


Precede Activity D
Copyright © 2017 Pearson Education Ltd 3 - 42
AON Network for
Milwaukee Paper

F
A C

E
Start H

B D G

Arrows Show Precedence Figure 3.7


Relationships
Copyright © 2017 Pearson Education Ltd 3 - 43
AOA Network for
Milwaukee Paper
C
2 4
(Construct
Stack)

H
1 Dummy 6 7
Activity (Inspect/
Test)

D
3 5
(Pour Figure 3.8
Concrete/
Install Frame)
Copyright © 2017 Pearson Education Ltd 3 - 44
Example

Copyright © 2017 Pearson Education Ltd 3 - 45


Copyright © 2017 Pearson Education Ltd 3 - 46
Determining the Project Schedule

Perform a Critical Path Analysis


► The critical path is the longest path
through the network
► The critical path is the shortest time in
which the project can be completed
► Any delay in critical path activities delays
the project
► Critical path activities have no slack time

Copyright © 2017 Pearson Education Ltd 3 - 47


Determining the Project Schedule

Table 3.2 Time Estimates for Milwaukee Paper Manufacturing


ACTIVITY DESCRIPTION TIME (WEEKS)
A Build internal components 2
B Modify roof and floor 3
C Construct collection stack 2
D Pour concrete and install frame 4
E Build high-temperature burner 4
F Install pollution control system 3
G Install air pollution device 5
H Inspect and test 2
Total time (weeks) 25

Copyright © 2017 Pearson Education Ltd 3 - 48


Determining the Project Schedule
Perform a Critical Path Analysis
Earliest start (ES) = earliest time at which an activity can
start, assuming all predecessors have
been completed
Earliest finish (EF) = earliest time at which an activity can be
finished
Latest start (LS) = latest time at which an activity can start
so as to not delay the completion time of
the entire project
Latest finish (LF) = latest time by which an activity has to be
finished so as to not delay the
completion time of the entire project

Copyright © 2017 Pearson Education Ltd 3 - 49


Determining the Project Schedule

Activity Format Figure 3.9

Activity Name
or Symbol
A Earliest
Earliest ES EF Finish
Start

Latest LS LF Latest
Start 2 Finish

Activity Duration
Copyright © 2017 Pearson Education Ltd 3 - 50
Forward Pass
Begin at starting event and work forward

Earliest Start Time Rule:

► If an activity has only a single immediate


predecessor, its ES equals the EF of the
predecessor
► If an activity has multiple immediate
predecessors, its ES is the maximum of all
the EF values of its predecessors

ES = Max {EF of all immediate predecessors}

Copyright © 2017 Pearson Education Ltd 3 - 51


Forward Pass
Begin at starting event and work forward

Earliest Finish Time Rule:

► The earliest finish time (EF) of an activity is


the sum of its earliest start time (ES) and its
activity time

EF = ES + Activity time

Copyright © 2017 Pearson Education Ltd 3 - 52


ES/EF Network for Milwaukee
Paper

ES EF = ES + Activity time
Start
0 0

Copyright © 2017 Pearson Education Ltd 3 - 53


ES/EF Network for Milwaukee
Paper
EF of A =
ES ES of A + 2
of A
A
Start 0 2
0 0

Copyright © 2017 Pearson Education Ltd 3 - 54


ES/EF Network for Milwaukee
Paper
A
0 2

2 EF of B =
ES ES of B + 3
0
Start
0 of B
B
0 0 3

3
Copyright © 2017 Pearson Education Ltd 3 - 55
ES/EF Network for Milwaukee
Paper
A C
0 2 2 4

2 2

Start
0 0

B
0 3

Copyright © 2017 Pearson Education Ltd 3 - 56


ES/EF Network for Milwaukee
Paper
A C
0 2 2 4

2 2

Start
0 0
= Max (2, 3) D
0
3 7
B
0 3

3
4
Copyright © 2017 Pearson Education Ltd 3 - 57
ES/EF Network for Milwaukee
Paper
A C
0 2 2 4

2 2

Start
0 0

B D
0 3 3 7

3 4

Copyright © 2017 Pearson Education Ltd 3 - 58


ES/EF Network for Milwaukee
Paper
A C F
0 2 2 4 4 7

2 2 3

Start E H
0 0 4 8 13 15

0 4 2

B D G
0 3 3 7 8 13

3 4 5
Figure 3.10
Copyright © 2017 Pearson Education Ltd 3 - 59
Backward Pass
Begin with the last event and work backwards
Latest Finish Time Rule:

► If an activity is an immediate predecessor for


just a single activity, its LF equals the LS of the
activity that immediately follows it
► If an activity is an immediate predecessor to
more than one activity, its LF is the minimum
of all LS values of all activities that
immediately follow it
LF = Min {LS of all immediate following activities}
Copyright © 2017 Pearson Education Ltd 3 - 60
Backward Pass
Begin with the last event and work backwards
Latest Start Time Rule:

► The latest start time (LS) of an activity is the


difference of its latest finish time (LF) and its
activity time

LS = LF – Activity time

Copyright © 2017 Pearson Education Ltd 3 - 61


LS/LF Times for
Milwaukee Paper
A C F
0 2 2 4 4 7

2 2 3

Start E H
0 0 4 8 13 15
13 15
0 4 2

B D – Activity timeG
LS = LF
0 3 3 7 8 13

3 4 5 LF = EF
of Project
Copyright © 2017 Pearson Education Ltd 3 - 62
LS/LF Times for
Milwaukee Paper
A C F
0 2 2 4 4 7

10 13
2 2 3

Start E H
0 0
LF 4= Min(LS
8 of 13 15
following activity) 13 15
0 4 2

B D G
0 3 3 7 8 13

3 4 5

Copyright © 2017 Pearson Education Ltd 3 - 63


LS/LF Times for
LF = Min(4, 10)
Milwaukee Paper
A C F
0 2 2 4 4 7

2 4 10 13
2 2 3

Start E H
0 0 4 8 13 15

4 8 13 15
0 4 2

B D G
0 3 3 7 8 13
8 13
3 4 5

Copyright © 2017 Pearson Education Ltd 3 - 64


LS/LF Times for
Milwaukee Paper
A C F
0 2 2 4 4 7

0 2 2 4 10 13
2 2 3

Start E H
0 0 4 8 13 15

0 0 4 8 13 15
0 4 2

B D G
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5

Copyright © 2017 Pearson Education Ltd 3 - 65


Computing Slack Time
After computing the ES, EF, LS, and LF times for
all activities, compute the slack or free time for
each activity

► Slack is the length of time an activity can be


delayed without delaying the entire project

Slack = LS – ES or Slack = LF – EF

Copyright © 2017 Pearson Education Ltd 3 - 66


Computing Slack Time
TABLE 3.3 Milwaukee Paper’s Schedule and Slack Times
EARLIEST EARLIEST LATEST LATEST ON
START FINISH START FINISH SLACK CRITICAL
ACTIVITY ES EF LS LF LS – ES PATH
A 0 2 0 2 0 Yes
B 0 3 1 4 1 No
C 2 4 2 4 0 Yes
D 3 7 4 8 1 No
E 4 8 4 8 0 Yes
F 4 7 10 13 6 No
G 8 13 8 13 0 Yes
H 13 15 13 15 0 Yes

Copyright © 2017 Pearson Education Ltd 3 - 67


Activities with zero slack are on the critical path. It:
Computing Slack Time
► Starts at the first activity in the project

► Terminates at the last activity in the project

► Includes only critical activities


TABLE 3.3 Milwaukee Paper’s Schedule and Slack Times
EARLIEST EARLIEST LATEST LATEST ON
START FINISH START FINISH SLACK CRITICAL
ACTIVITY ES EF LS LF LS – ES PATH
A 0 2 0 2 0 Yes
B 0 3 1 4 1 No
C 2 4 2 4 0 Yes
D 3 7 4 8 1 No
E 4 8 4 8 0 Yes
F 4 7 10 13 6 No
G 8 13 8 13 0 Yes
H 13 15 13 15 0 Yes

Copyright © 2017 Pearson Education Ltd 3 - 68


Critical Path for
Milwaukee Paper
A C F
0 2 2 4 4 7

0 2 2 4 10 13
2 2 3

Start E H
0 0 4 8 13 15

0 0 4 8 13 15
0 4 2

B D G
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5

Copyright © 2017 Pearson Education Ltd 3 - 69


ES – EF Gantt Chart
for Milwaukee Paper
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

A Build internal
components
B Modify roof and floor
C Construct collection
stack
D Pour concrete and
install frame
E Build high-temperature
burner
F Install pollution control
system
G Install air pollution
device
H Inspect and test

Copyright © 2017 Pearson Education Ltd 3 - 70


LS – LF Gantt Chart
for Milwaukee Paper
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

A Build internal
components
B Modify roof and floor
C Construct collection
stack
D Pour concrete and
install frame
E Build high-temperature
burner
F Install pollution control
system
G Install air pollution
device
H Inspect and test

Copyright © 2017 Pearson Education Ltd 3 - 71


Variability in Activity Times

► CPM assumes we know a fixed time


estimate for each activity and there is
no variability in activity times
► PERT uses a probability distribution for
activity times to allow for variability

Copyright © 2017 Pearson Education Ltd 3 - 72


Variability in Activity Times

► Three time estimates are required


► Optimistic time (a) – if everything goes
according to plan
► Pessimistic time (b) – assuming very
unfavorable conditions
► Most likely time (m) – most realistic
estimate

Copyright © 2017 Pearson Education Ltd 3 - 73


Variability in Activity Times
Estimate follows beta distribution
Expected activity time:
t = (a + 4m + b)/6
Variance of activity completion times:
v = [(b – a)/6]2

Copyright © 2017 Pearson Education Ltd 3 - 74


Variability in Activity Times
Estimate follows beta distribution
Figure 3.11
Expected activity time:
t = (a + 4m + b)/6
Probability of 1t in =
100 (a + 4m + b)/6
of < a occurring
Probability

v =
Variance of activity completion[(b − a)/6]2Probability of 1 in 100
of >times:
b occurring

v = [(b – a)/6]2 Activity


Time

Optimistic Most Likely Pessimistic


Time (a) Time (m) Time (b)

Copyright © 2017 Pearson Education Ltd 3 - 75


Computing Variance
TABLE 3.4 Time Estimates (in weeks) for Milwaukee Paper's Project

MOST
OPTIMISTIC LIKELY PESSIMISTIC EXPECTED TIME VARIANCE
ACTIVITY a m b t = (a + 4m + b)/6 [(b – a)/6]2
A 1 2 3 2 .11

B 2 3 4 3 .11

C 1 2 3 2 .11

D 2 4 6 4 .44

E 1 4 7 4 1.00

F 1 2 9 3 1.78

G 3 4 11 5 1.78

H 1 2 3 2 .11

Copyright © 2017 Pearson Education Ltd 3 - 76


Probability of Project
Completion
Project variance is computed by
summing the variances of critical
activities
sp2 = Project variance
= (variances of activities
on critical path)

Copyright © 2017 Pearson Education Ltd 3 - 77


Probability of Project
Completion
Project variance is computed by
summing the variances of critical
Project variance
activities
s2p = .11 + .11 + 1.00 + 1.78 + .11 = 3.11

Project standard deviation


sp = Project variance
= 3.11 = 1.76 weeks
Copyright © 2017 Pearson Education Ltd 3 - 78
Probability of Project
Completion
PERT makes two more assumptions:

► Total project completion times follow a


normal probability distribution
► Activity times are statistically independent

Copyright © 2017 Pearson Education Ltd 3 - 79


Probability of Project
Completion
Figure 3.12
Standard deviation = 1.76 weeks

15 Weeks
(Expected Completion Time)

Copyright © 2017 Pearson Education Ltd 3 - 80


Probability of Project
Completion
What is the probability this project can
be completed on or before the 16 week
deadline?

Z = Due – Expected date /sp


date of completion
= (16 weeks – 15 weeks)/1.76

= 0.57 Where Z is the number of


standard deviations the due
date or target date lies from the
mean or expected date
Copyright © 2017 Pearson Education Ltd 3 - 81
Probability of Project
Completion
From Appendix I
What is the probability
.00 .01 this project
.07 can
.08
be completed on or before the
.1 .50000 .50399
16 week
.52790 .53188
deadline?.2 .53983 .54380 .56749 .57142

.5 = due .69497
Z.69146 − expected.71566
date /s
.71904
p
date of completion
.6 .72575 .72907 .74857 .75175
= (16 wks − 15 wks)/1.76

= 0.57 Where Z is the number of


standard deviations the due
date or target date lies from the
mean or expected date
Copyright © 2017 Pearson Education Ltd 3 - 82
Probability of Project
Completion
0.57 Standard deviations
Probability
(T ≤ 16 weeks)
is 71.57%

15 16 Time
Weeks Weeks
Figure 3.13

Copyright © 2017 Pearson Education Ltd 3 - 83


Determining Project
Completion Time
Probability
of 0.99

Probability
of 0.01

2.33 Standard Z
From Appendix I deviations
0 2.33
Figure 3.14

Copyright © 2017 Pearson Education Ltd 3 - 84


Example

Copyright © 2017 Pearson Education Ltd 3 - 85


Solution
▶ To solve the problem using following formulas for each
activity.
Expected activity time:
t = (a + 4m + b)/6
Variance of activity completion times:
v = [(b – a)/6]2

Copyright © 2017 Pearson Education Ltd 3 - 86


Variability of Completion Time
for Noncritical Paths
► Variability of times for activities on
noncritical paths must be considered
when finding the probability of
finishing in a specified time
► Variation in noncritical activity may
cause change in critical path

Copyright © 2017 Pearson Education Ltd 3 - 87


What Project Management Has
Provided So Far
1. The project’s expected completion time is
15 weeks
2. There is a 71.57% chance the equipment
will be in place by the 16 week deadline
3. Five activities (A, C, E, G, and H) are on
the critical path
4. Three activities (B, D, F) are not on the
critical path and have slack time
5. A detailed schedule is available
Copyright © 2017 Pearson Education Ltd 3 - 88
Cost–Time Trade-Offs and Project
Crashing
It is not uncommon to face the
following situations:
► The project is behind schedule
► The completion time has been
moved forward

Shortening the duration of the


project is called project crashing
Copyright © 2017 Pearson Education Ltd 3 - 89
Factors to Consider When
Crashing a Project
► The amount by which an activity is
crashed is, in fact, permissible
► Taken together, the shortened activity
durations will enable us to finish the
project by the due date
► The total cost of crashing is as small as
possible

Copyright © 2017 Pearson Education Ltd 3 - 90


Steps in Project Crashing
Step 1: Compute the crash cost per time
period. If crash costs are linear over
time:
Crash cost (Crash cost – Normal cost)
per period = (Normal time – Crash time)

Step 2: Using current activity times, find the


critical path and identify the critical
activities

Copyright © 2017 Pearson Education Ltd 3 - 91


Steps in Project Crashing
Step 3: If there is only one critical path, then
select the activity on this critical path
that (a) can still be crashed, and (b) has
the smallest crash cost per period. If
there is more than one critical path,
then select one activity from each
critical path such that (a) each selected
activity can still be crashed, and (b) the
total crash cost of all selected activities
is the smallest. Note that the same
activity may be common to more than
one critical path.
Copyright © 2017 Pearson Education Ltd 3 - 92
Steps in Project Crashing
Step 4: Update all activity times. If the desired
due date has been reached, stop. If not,
return to Step 2.

Copyright © 2017 Pearson Education Ltd 3 - 93


Crashing The Project
TABLE 3.5 Normal and Crash Data for Milwaukee Paper Manufacturing

TIME (WEEKS) COST ($)


CRASH COST CRITICAL
ACTIVITY NORMAL CRASH NORMAL CRASH PER WEEK ($) PATH ?
A 2 1 22,000 22,750 750 Yes

B 3 1 30,000 34,000 2,000 No

C 2 1 26,000 27,000 1,000 Yes

D 4 3 48,000 49,000 1,000 No

E 4 2 56,000 58,000 1,000 Yes

F 3 2 30,000 30,500 500 No

G 5 2 80,000 84,500 1,500 Yes

H 2 1 16,000 19,000 3,000 Yes

Copyright © 2017 Pearson Education Ltd 3 - 94


Crash and Normal Times
and Costs for Activity B
Activity
Cost
Crash

$34,000 — Crash Cost – Normal Cost


Crash Cost/Wk =
Normal Time – Crash Time
Crash $33,000 — $34,000 – $30,000
Cost =
$32,000 —
3–1
$4,000
= = $2,000/Week
$31,000 — 2 Wks

$30,000 —
Normal
Normal —
Cost
| | |
1 2 3 Time (Weeks)
Figure 3.15
Crash Time Normal Time
Copyright © 2017 Pearson Education Ltd 3 - 95
Critical Path and Slack Times
for Milwaukee Paper
Figure 3.16

A C F
0 2 2 4 4 7

0 2 2 4 10 13
2 2 3

Start Slack = 0 Slack = 0 E Slack = 6 H


0 0 4 8 13 15

0 0 4 8 13 15
0 4 2

B D Slack = 0 G Slack = 0
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5

Slack = 1 Slack = 1 Slack = 0


Copyright © 2017 Pearson Education Ltd 3 - 96
Advantages of PERT/CPM
1. Especially useful when scheduling and
controlling large projects
2. Straightforward concept and not
mathematically complex
3. Graphical networks help highlight
relationships among project activities
4. Critical path and slack time analyses help
pinpoint activities that need to be closely
watched

Copyright © 2017 Pearson Education Ltd 3 - 97


Advantages of PERT/CPM
5. Project documentation and graphics point
out who is responsible for various activities
6. Applicable to a wide variety of projects
7. Useful in monitoring not only schedules but
costs as well

Copyright © 2017 Pearson Education Ltd 3 - 98


Limitations of PERT/CPM
1. Project activities have to be clearly defined,
independent, and stable in their
relationships
2. Precedence relationships must be specified
and networked together
3. Time estimates tend to be subjective and
are subject to fudging by managers
4. There is an inherent danger of too much
emphasis being placed on the longest, or
critical, path

Copyright © 2017 Pearson Education Ltd 3 - 99

You might also like