Guidelines For Preparation of DPR
Guidelines For Preparation of DPR
PREPARED BY
MOHD. MAHBOOB HUSSAIN, [Link].,
EXECUTIVE ENGINEER,
Irrigation & CAD DEPARTMENT, GOVT. OF TELANGANA,
HYDERABAD-82
2016
Copyright © 2012 Author Name
All rights reserved.
ISBN:
ISBN-13:
Government of Telangana
Irrigation & CAD Department
GUIDELINES
FOR PREPARATION OF PRELIMINARY INVESTIGATION REPORT (PIR),
DETAILED SURVEY & PREPARATION OF DETAILED PROJECT REPORT
(DPR) OF NEW MINOR IRRIGATION SCHEME AND REHABILITATION OF
EXISTING MINOR IRRIGATION SCHEME
PREPARED BY
MOHD. MAHBOOB HUSSAIN, [Link].,
EXECUTIVE ENGINEER,
Irrigation & CAD DEPARTMENT,
GOVERNMENT OF TELANGANA,
HYDERABAD-82
2016
Government of Telangana
Irrigation & CAD Department
GUIDE LINES
(I) FOR FIELD INVESTIGATION AND METHOD OF PREPARATION OF
PRELIMINARY INVESTIGATION REPORT (PIR) OF MINOR
IRRIGATION SCHEMES
(II) FOR TAKING UP DETAILED SURVEY, DESIGN AND METHOD OF
PREPARATION OF DETAILED ESTIMATE / DPR OF MINOR
IRRIGATION SCHEMES
(III) FOR TAKING UP DETAILED SURVEY AND PREPARATION OF
DETAILED ESTIMATE OF RRR OF WATER BODIES AS PER GoI
NORMS AND REHABILITATION OF M.I. TANKS UNDER ―MISSION
KAKATIYA‖
PREPARED BY
MOHD. MAHBOOB HUSSAIN, [Link].,
EXECUTIVE ENGINEER,
Irrigation & CAD DEPARTMENT
GOVT. OF TELANGANA, HYDERABAD-82
T. HARISH RAO Room No. 151, Ground
Minister for Floor, D Block, T.
Irrigation, Secretariat, Hyderabad.
Marketing & OFFICE 040-23453220
Legislative Affairs Fax . 040-23450872
Bungalow : No. 7, Road No.
12,
Ministers Quarters,
Banjarahills.
RES 040-23324504
08457-222222
Cell 9440471409
Email
harishrao1116@[Link]
FOREWORD
FOREWORD
Date:26-08-2016
FOREWORD
Date: 24-08-2016
FOREWORD
I am sure that this booklet will be very useful for guidance to newly
recruited irrigation engineers and in-service irrigation engineers of this
department for preparation of PIR, estimates of new Minor Irrigation
schemes and also for rehabilitation of M. I. tanks. With these guidelines
all estimates of M.l. tanks received from the field officer will be in a
uniform pattern. I appreciate his keen interest in preparation of above
guidelines.
PREFACE
I hope that the guidelines will be useful to Irrigation Engineers of Irrigation &
CAD Department, Telangana State in Minor Irrigation Sector.
1.4 Case – d:- Where there are no U.R.R. tanks but L.R.R. tanks 13
1.5 Sample Index Map 24
*************************************************
2.1 L.S. of Bund 30
2.2 Survey Plan of M.I. tank 31
2.3 Net levels 34
2.4 Sample of L.S. of canal 37
2.5 Canal alignment (i.e.,Survey Plan) of L.F. Canal 38
2.6 Quarry Map 39
2.7 L.S. of Bund 40
2.8 25 Years 24 Hours ISOPLUVIAL Map (mm) 56
2.9 50 Years 24 Hours ISOPLUVIAL Map (mm) 57
2.10 Cross Section of F.O.F. Weir 58
2.11 Typical Cross Section of H.C. Weir 59
2.12 Cross Section of H.C. Weir when B.C. soils are met within the 59
foundation
2.13 L.S. of H.C. Weir 61
2.14 Plan & Cross-Section of H.C. Weir 62
2.15 Plan of F.O.F. Weir 63
2.16 Different parts of H.C. Weir 64
2.17 Abutment & Returns Section along 'AA' 65
2.18 Weir section when Water up to crest level on U/s side and no 68
water on D/s side
2.19 Weir section when Water on upstream side up to M.W.L. 69
2.20 Section of Abutment 70
2.21 Head Sluice drawing (copy issued by CE/M.I.) 78
2.22 L.S. and Half Plan-Half Section of head sluice 79
2.23 Cross section at Ch. (-) 0.20 82
2.24 Cross section at Ch. 1.50 83
2.25 Cross section at Ch. 6.25 83
2.26 Cross section at Ch. 10.00 84
2.27 Section of L.F. Canal 84
2.28 Plan of surplus course at weir 85
2.29 Cross Section of Canal 86
2.30 Cross section at Ch. 0.00 87
2.31 Cross section at Ch. 1.00 87
2.32 Cross section at Ch. 2.00 88
2.33 Cross section at Ch. 3.00 88
2.34 Cross section at Ch. 4.00 89
2.35 Cross section at Ch. 5.00 89
2.36 Cross section at Ch. 6.00 90
2.37 Drop of Canal (0.90 m) 93
2.38 Plan & L.S. of RCC Hume Pipe Culvert 95
2.39 Plan, L.S & section of RCC Hume pipe Super-passage 97
2.40 L.S & Section of the RCC rectangular Trough Aqueduct 100
2.41 Plan, L.S. & section of Drop cum Pipe Culvert 101
2.42 RCC Hume Pipe Aqueduct proposed for canal crossing a stream 102
2.43 Inlet-weir for canal crossing local Nala/small stream 103
2.44 Sample Index Map 118
*************************************************
3.1 Profile of bund section over the existing bund section 154
3.2 Fuel-Operated Compactor for Sub-grade Compaction 156
3.3 Typical Construction of Skin Wall 158
3.4 Open cut embankment for repairs of sluice barrel 160
3.5 Details of Joint in C.C. Lining (Placed in alternate panels) 162
3.6 C.C. Guide Wall Section for canal 162
ACKNOWLEDGEMENTS
I am indebted to Sri. Kondapally Venugopal Rao, Chief Engineer (Rtd.) and Sri.
Sridhar Rao Deshpande garu, Officer on Special Duty to Hon‘ble Minister for
Irrigation for their constant encouragement, guidance & support during the
compilation of these guidelines. Without their help, it would not have been
possible to complete this task.
I am grateful to Sri. S. Narasimha Rao Garu, Chief Engineer, Inter State & Water
Resources, I & CAD Department, Government of Telangana, Hyderabad for his
timely advice and encouragement in writing of this book.
Thanks are due to Sri. B. Nagender Rao Garu, Chief Engineer, Minor Irrigation
(Godavari River Basin), I & CAD Department, Government of Telangana,
Hyderabad for giving inputs and his personal experiences which were quite
useful in compiling this book.
I would be failing in my duty if I do not thank Sri. K. Suresh Kumar Garu, Chief
Engineer, Minor Irrigation (Krishna River Basin), I & CAD Department,
Government of Telangana, Hyderabad for his encouragement in bringing out this
book.
I am also thankful to Sri. L. Narayan Reddy Garu, Director General,
WALAMTARI, Hyderabad for all efforts to publish this book.
The Data Processing Officer, IS&WR Unit, I & CAD Department, Government of
Telangana, Hyderabad also deserve a word of praise for drawing all figures in
Auto CAD.
1
GUIDE LINES
I) FOR FIELD INVESTIGATION AND METHOD OF
PREPARATION OF PRELIMINARY INVESTIGATION REPORT
(PIR) OF MINOR IRRIGATION SCHEMES
PREPARED BY
MOHD. MAHBOOB HUSSAIN, [Link].,
EXECUTIVE ENGINEER,
I & CAD DEPARTMENT,
GOVRNMENT OF TELANGANA ,
HYDERABAD-82
2016
2
I) FIELD INVESTIGATION AND PREPARATION OF PRELIMINARY
INVESTIGATION REPORT
In view of its small size, a tank and its irrigated area are commonly
associated with a single village or more, and form an integral part of its socio-
economic structure.
Even before the element of a project can be visualized, the area must be
thoroughly reconnoitered. However, before the reconnaissance, it is necessary to
thoroughly understand the need, extent and limitation of the project. The
beginning should thus be made from the basic factors.
4
Site Selection criteria:
5
these tanks have to be inspected and located in the Topo sheet, if they
are not found in Topo sheet.
f) Similarly, enquiry should be made about the existing irrigation tanks on
the downstream side of the proposed M.I. tank site. After that, inspection
of these tanks should be carried out and locate in the Topo sheet, if they
are not found in Topo Sheet.
g) Utilization / settled ayacut and irrigated ayacut of such tanks from
Revenue records should be procured.
17
To Total yield available @75% Dep.
18 Proposed utilization under this proposed
M.I. tank / scheme
19 Balance yield available in sub-group as per
Master Plan record.
6
20 Ayacut proposed to be benefited :
22 Suitability of site :
26 Report:
After field inspection and collection of field data, one has to work out the
following calculations for preparation of P.I.R:-
(1) Work out the Global co-ordinates of the proposed site of MI tank from
Topo sheet.
(2) Find out sub-basin and sub-group in which the proposed schemes fall from
sub- group map and M.P. record available.
(3) Mark the catchment area with pencil, both free and intercepted, of the
proposed M.I. tank and find out free C.A., and intercepted C.A., with the
help of Plane-meter / graph sheet.
(4) With the help of Thiesen‘s Polygon map available, find out, which rain
gauge station (R.G.S) is influencing the catchment area of proposed M.I.
Tank.
(5) Sometimes the catchment area is also influenced by two or more rain
gauge stations, for which the yield is to be worked out using weighted
rainfall value.
(6) Note down the yearly rainfall data of the influencing rain gauge station for
the last 40 years and find out the average annual rainfall.
(7) Note down the monthly rainfall data of the influencing R.G.S., for the last
40 years Monsoon period (June to October). Find out average monsoon
rainfall by dividing total monsoon rainfall by 40. Now arrange the
monsoon rainfall data in descending order. The 30th year value gives you
75% Dep. rainfall. 26th year value gives you 65% Dep. rainfall.
(8) Using the Strange‘s table, work out yield / Sq. Mile for 50%,65% and
75% Dependable rainfall for ―Good‖ and ―Average‖ catchment. To obtain
yield of ―½ Good + ½ Average‖ catchment just average the values for
Good and Average catchment areas and tabulate as follows:
7
[Link]. Nature of Catchment 50% Dep. 65%Dep 75% Dep.
1. Good
2. ½ Good + ½ Average
3. Average
(9) Calculate total yield available at 65% Dep. at the proposed site by just
multiplying the catchment area to yield per Sq. Mile at 65% Dep. for
influencing only one rain gauge station.
(10) Calculate total yield available at 75% Dep. at the proposed site by just
multiplying the catchment area to yield per Sq. Mile at 75% Dep. for
influencing only one rain gauge station.
(11) Calculate the net yield available at site by deducting the yield utilization of
upper sources if any. Then propose the yield utilization for the proposed
M.I. tank only up to 60% of the net yield available.
(12) For computation of 75% Dep. Yield for any catchment under the influence
of two or more RGS, the following procedure should be adopted:
i) Latest and continuous rainfall data of 40 years for all the rain gauge
stations having influence on catchment may be gathered.
ii) Year wise yield for each RGS influencing area (as per Strange‘s table and
Thiessen Polygon method) may be calculated.
iii) The above year wise yield of two or more RGS may be summed up to
obtain the total yield of the entire catchment in each year.
iv) Yields obtained above may be arranged in descending order and then
75% dependable yield may be considered as the yield from the
catchment.
(13) Calculate the net yield available at site by deducting the yield utilization of
upper sources if any. Then propose the yield utilization for MI scheme in
question such that some yield is let down stream side, depending upon
demand under L.R.R tank if any.
(14) Discuss fully the effect of U.R.R. and U.R.R. tanks.
(15) Report should cover following points:
(i) Distance and direction of proposed site from village.
(ii) Mention who has represented for this scheme.
(iii) If there is any balance yield in the sub group for proposed minor
irrigation tank.
(iv) Suitability of site for construction of M.I. tank for irrigation purpose.
(v) Whether the scheme is feasible or not.
(vi) Any other special information regarding the proposed M.I. tank based
on local site conditions.
(vii) Request for according Hydrological Clearance for the minor irrigation
tank.
8
5) PROCEDURE FOR DISCUSSING L.R.R. AND U.R.R.
Based on the Minor Irrigation guidelines, U.R.R and L.R.R tank yield utilization
may be calculated as indicated below using duty given in Table-1.1:
(A) For irrigated wet crops (khariff)
Table – 1.1 – Giving Details of Duty for calculation of Yield utilization
(i) Above 15‖ monsoon rain fall 3 ½ Acre/Mcft
(ii) Above 15‖ & up to 20‖ monsoon rainfall 4 --do—
(iii) Above 20‖ & up to 25‖ monsoon rain fall 4 ½ --do---
(iv) Above 25‖ & up to 30‖ monsoon rainfall 5 --do---
(v) Above 30‖ & up to 32.50‖ monsoon 5 ½ --do---
rainfall
(vi) Above 32.50‖ & up to 35‖ monsoon 6 --do---
rainfall
(vii) Above 35‖ & up to 37.50‖ monsoon 7 --do---
rainfall
(viii) Above 37.50‖ & up to 40‖ monsoon 7 ½ --do---
rainfall
(ix) Above 40‖ & above 8 --do---
(B) For irrigated dry crops (Khariff) up to 25‖ monsoon R.F……15 Acre/Mcft
(C) For irrigated dry crops (Khariff) above 25‖ monsoon R.F…..20Acre/Mcft
(Note:- Monsoon rainfall relates to rainfall occurring between June to
December both months inclusive).
Lower riparian right (L.R.R) are to be worked out up to tail end if there are
direct drawls. If there are series of lower down tanks, the L.R.R is to be checked
up to lowest tank, till its surplus meet with the main river on which the medium
and major projects are constructed.
The following four cases of L.R.R and U.R.R are discussed as detailed
below:
Case(a): Where there are no URR tanks and also no LRR tanks.
Case(b): Where there is URR tank and no LRR tank.
Case(c): Where there is URR tank and LRR tank in d/s of proposed site.
Case(d): Where there are no URR tanks but there are LRR tanks.
9
Case a: Where there are no URR tanks and no LRR tanks
Fig. 1.1 – Case – a:- Where there are no U.R.R. tanks no L.R.R. tanks
U.R.R.: - There are no schemes / tanks on the upstream side of the proposed
new tank. Since it is proposed in free catchment area, U.R.R. will not
be affected.
10
Case b: Where there is URR tank and no LRR tanks
Fig. 1.2 – Case – b:- Where there is U.R.R. tank and no L.R.R. tanks
U.R.R.: - There is a tank on the upstream side of the proposed site by name
Chinna Cheruv with settled ayacut of 41 acres Paddy. The C.A. of
U.R.R. tank is 0.69 [Link]. The yield per square mile at 75%
dependability is 12.389 Mcft. Hence the total yield available at URR
tank is 0.69 * 12.389 = 8.548 Mcft. Yield required for 41 acres ayacut
of URR tank = 41/6 = 6.833 Mcft. Hence the balance yield available at
U.R.R. tank is 8.548-6.833=1.715 Mcft. Hence U.R.R. will not be
affected.
L.R.R.: - There are no tanks on this stream in the downstream of proposed site
up to a distance of nearly 10 km. Moreover this stream joins another
big stream on which also there are no tanks. Hence L.R.R. will not be
affected.
11
Case C: Where there is URR tanks in U/S and LRR tanks in D/S of the
proposed site.
Fig. 1.3 – Case – c:- Where there is U.R.R. tanks in U/s and L.R.R.
tanks in D/s of the proposed site
U.R.R.: - There is a U.R.R. tank by name Mallamma Cheruvu with settled ayacut
of 55 acres wet. The C.A of the U.R.R. tank is 1.139 [Link]. The
yield at 75% dependability is 11.45 Mcft per [Link]. The total yield
available at URR tank is 1.139 * 11.45 =13.04 Mcft. Yield required for
the U.R.R. tank =55/6=9.16 Mcft. Hence surplus yield available at
URR tank is 13.04-9.16=3.88 Mcft. Hence U.R.R. will not be affected.
L.R.R.: - There is a tank in L.R.R. by name Pedda Cheruvu with settled ayacut of
140 acres wet. The total C.A of LRR tank is 4.615 [Link]. The total
yield available at L.R.R. tank = 4.615 * 11.45 = 52.84 Mcft. The
proposed utilization for new tank is 10 Mcft. The total utilization of
LRR tanks = 140/6 = 23.33 Mcft. The surplus yield available at L.R.R.
tanks = 52.84 - 9.16 - 23.33 = 10.35 Mcft. Hence L.R.R. will not be
affected.
12
Case d: Where there are no URR tanks but L.R.R. tanks
Fig. 1.4 – Case – d:- Where there are no U.R.R. tanks but L.R.R. tanks
U.R.R. :- There are no schemes / tanks on the upstream side of the proposed
site since it is proposed in free catchment. Hence U.R.R. will not be
affected.
L.R.R. : - There is an LRR tank by name Pedda Cheru, Rudraram (V) with settled
ayacut of 110 Ac on this stream before it joins main stream. The
catchment area of L.R.R. tank is 6.18 [Link]. The yield per [Link]
@75% dependability of influencing R.G.S is 10.58 Mcft. The yield
available at L.R.R. tank is 10.58 * 6.18 = 65.384 Mcft. Further, there
are two tanks in this catchment area above L.R.R. tank and below the
proposed site by name Chinna Cheruvu, Gollapalli village and Oora
cheruvu, Pilaram village with settled ayacut of 30 acres and 55 acres
respectively. Proposed utilization of new scheme is 10 Mcft.
Yield required for LRR and other two tanks = (110+30+55)/6 = 32.50 Mcft.
The balance yield available at L.R.R. tank after deducting U.R.R utilization and
proposed utilization = 65.384 – 32.5 -10.0 = 22.884 Mcft.
A sample P.I.R of one of the M.I. tank is given below for guidance:
16
8) PRELIMINARY INVESTIGATION REPORT
26. U.R.R.:-There are three tanks in the upstream side of proposed site. The
immediate U.R.R tank is Appaiah Kunta of Banda Elka Charla(V). The catchment
17
area of Appaiah Kunta is 0.936 [Link]. The total yield available at Appaiah
Kunta is 0.936*14.149= 13.24 MCft.
The three tanks are
(1) Puslod Kunta of Banda Elka Cherla –-- 2 acre- 27 Guntas.
(2) Marri Kunta of Banda Elka cherla ---- 7 acre- 05 Guntas
(3) Appaiah Kunta of Banda Elkacherla ---- 12 acre- 20 Guntas
The yield required for above three tanks considering wet cultivation is
22.33/6= 3.72 Mcft. The balance yield available at U.R.R tank= 13.24 – 3.72 =
9.52 MCft.
27. L.R.R:- The immediate L.R.R. tank is Mothkul Kunta of Gundal(V), Doma
(M), Ranga Reddy Disrict and its C.A is 6.523 Sq. Miles. The yield available at
L.R.R. tank = 6.523* 14.149 = 92.29 MCft.
The tanks in catchment area of L.R.R tank and below Oora Cheru, Chellapur (V),
Kulkacherla (M), R R Dist. Are as follows:
The balance yield available at L.R.R. tank after deducting U.R.R. utilizations, 5
no. L.R.R. tanks utilization, Oora Cheru utilization and proposed new utilization
of Oora Cheru= 92.29 – 3.72 – 29.50 – 14.28 – 11.00 = 33.79 MCft.
Since the proposed new utilization of 11.00 MCft. is less than the balance yield
available at L.R.R tank, L.R.R. will not be affected.
28. Report:- This tank is situated adjacent to and North side of Chellapur
village, Kulkacherla mandal of Ranga Reddy district. This tank belongs to
Panchayat Raj department with registered ayacut of 85 acres- 28 Guntas as per
10 years Revenue Statement of M.R.O, Kulkacherla mandal, Ranga Reddy
district. The Sarpanch and Ryots of Chellapur village have requested for raising
18
F.T.L of Oora cheru. This scheme falls in IV-4 sub- group of K-7 Lower Krishna
sub- basin.
The scheme is irrigating its full ayacut as per local enquiry and 10
Revenue Statement. As land is available to irrigate about another 100 acres, the
villagers have requested for raising F.T.L of Oora Cheru, Chellapur (V). The
U.R.R and L.R.R. is discussed above in detail. Patta privte lands will come under
submergence due to raising F.T.L.
There is a chance of raising F.T.L of about 0.80 meter, since the flanks on
either side are not so high. Only after detailed surveys the possibility of raising
F.T.L can be fully examined. Moreover this tank has to be handed over to
Irrigation Department from Panchayath Raj Department.
Copy of Strange‘s table is given below in Table-1.4 for calculation of yield from
catchment.
Table of total monsoon rainfall and estimated run-off and yield per square mile
from catchment area (Strange‘s Table).
Percentage of run-off to
Percentage of run-off to
Percentage of run-off to
Depth of run-off due to
rainfall in inches
rainfall in inches
inches
in Mcft.
in Mcft.
rainfall
rainfall
rainfall
in Mcft
1 2 3 4 5 6 7 8 9 10
1 0.1 0.001 0.002 0.1 0.001 0.001 0.05 0.005 0.001
2 0.2 0.004 0.009 0.10 0.003 0.006 0.1 0.002 0.004
3 0.4 0.012 0.028 0.3 0.000 0.021 0.2 0.006 0.014
4 0.7 0.028 0.065 0.5 0.021 0.048 0.3 0.047 0.032
5 1.0 0.050 0.116 0.7 0.037 0.087 0.5 0.025 0.058
6 1.5 0.080 0.209 1.1 0.007 0.156 0.7 0.040 0.104
7 2.1 0.147 0.341 1.5 0.110 0.235 1.0 0.073 0.170
8 2.8 0.224 0.520 2.1 0.108 0.390 1.4 0.112 0.260
9 3.5 0.316 0.732 2.0 0.230 0.549 1.7 0.157 0.366
10 4.3 0.430 0.999 3.2 0.322 0.749 2.1 0.215 0.499
11 5.2 0.720 1.329 3.0 0.420 0.996 2.6 0.280 0.664
12 6.2 0.744 1.728 4.0 0.568 1.296 3.1 0.372 0.864
19
13 7.2 0.938 2.174 6.4 0.702 1.630 3.6 0.468 1.087
14 8.3 1.162 2.699 6.2 0.871 2.024 4.1 0.581 1.349
15 9.4 1.110 3.276 7.0 1.057 2.457 4.7 0.705 1.638
16 10.5 1.080 3.903 7.8 1.200 2.927 5.2 0.840 1.951
17 11.6 1.092 4.581 8.7 1.470 3.435 5.8 0.980 2.290
18 12.8 2.304 5.353 9.0 1.728 4.014 6.4 1.102 2.676
19 13.9 2.041 6.135 10.4 1.080 4.601 6.4 1.320 3.067
20 15.0 3.00 6.970 11.25 2.260 5.227 7.5 1.500 3.485
21 15.1 3.081 7.855 12.0 2.036 5.891 8.0 1.660 3.927
22 17.3 3.800 8.842 12.0 2.804 6.631 8.0 1.003 4.421
23 18.4 4.232 9.832 13.8 3.174 7.374 9.2 2.110 4.916
24 19.5 4.080 10.873 14.0 3.010 8.154 9.7 2.340 5.436
25 20.0 5.150 11.964 15.4 3.802 8.973 10.3 2.575 5.982
26 21.8 5.008 13.168 16.3 4.201 9.876 10.9 2.834 6.584
27 23.0 6.183 14.364 17.1 4.037 10.773 11.4 3.081 7.182
28 24.0 6.720 15.612 18.0 5.040 11.709 12.0 3.300 7.806
29 25.1 7.279 16.911 18.8 5.450 12.683 12.5 3.030 8.455
30 26.3 7.800 18.330 19.7 5.017 13.747 13.1 3.045 9.165
31 27.4 8.404 19.733 20.0 6.370 14.799 13.1 4.247 9.866
32 28.6 9.120 21.188 21.3 6.840 15.891 14.2 4.500 10.594
33 29.8 9.708 22.693 22.2 7.320 17.019 14.3 4.884 11.346
34 30.8 10.472 24.329 23.1 7.854 18.246 15.4 5.234 12.164
35 31.9 11.165 25.939 23.0 8.313 19.454 16.0 5.682 12.969
36 33.0 11.880 27.600 24.7 8.010 20.700 16.5 5.040 13.800
37 34.1 12.817 29.312 25.5 9.402 21.984 17.0 5.308 14.656
38 35.3 13.414 31.163 26.4 10.000 23.372 17.0 6.707 15.581
39 36.4 14.100 32.980 27.3 10.047 24.735 18.2 7.098 16.490
40 37.5 15.000 34.848 28.1 11.200 26.136 18.7 7.600 17.424
41 38.5 15.820 36.767 28.0 11.809 27.575 19.3 7.013 18.383
42 38.8 16.710 38.835 29.8 12.537 29.126 19.6 8.38 19.417
43 40.9 17.687 40.858 30.0 13.100 30.643 20.4 8.708 20.429
44 42.0 18.180 42.933 31.6 13.800 32.199 21.4 10.240 21.466
45 43.1 19.395 45.058 32.3 14.546 33.793 21.5 9.697 22.529
46 44.3 20.378 47.342 33.2 15.283 35.506 22.1 10.180 23.671
47 45.4 21.338 49.572 34.0 16.003 37.179 22.7 10.639 24.786
48 46.5 22.320 51.854 34.8 17.740 38.890 23.2 11.160 25.927
49 47.6 23.324 54.186 35.7 18.493 40.639 23.8 11.562 27.093
50 48.8 24.400 56.686 36.6 18.300 42.514 24.4 12.200 28.343
51 49.9 25.449 59.123 37.4 19.086 44.342 24.9 12.724 29.561
52 51.0 26.520 61.611 38.2 19.880 46.208 25.5 13.260 30.805
53 52.1 27.618 64.151 39.0 20.700 48.113 26.0 13.806 32.075
54 53.3 28.782 66.866 39.9 21.388 50.149 26.8 14.391 33.433
55 54.4 29.920 69.510 40.8 22.440 52.132 27.2 14.960 34.755
56 55.5 21.080 72.205 41.6 23.310 54.153 27.7 15.540 36.102
57 56.6 32.262 74.951 42.4 24.196 56.213 28.3 16.131 37.475
58 57.8 33.524 77.883 43.3 25.143 58.412 28.9 16.762 38.941
59 58.9 34.751 80.734 44.4 26.063 60.550 29.4 17.375 40.367
20
60 60.0 36.000 83.635 45.0 27.000 62.726 30.0 18.000 41.817
22
11) Table: 1.5 - PROFORMA OF AYACUT STATEMENT
Name of the scheme:
S. Name of the Cast of Surve Total Ayacut Name of
No ayacutdar/beneficiar beneficiary y no. extent likely to village/Rem
y in Acre be arks
irrigated
23
12) A sample index map is shown below:
24
13) List of enclosures to the P.I.R
25
GUIDE LINES
PREPARED BY
MOHD. MAHBOOB HUSSAIN, [Link].,
EXECUTIVE ENGINEER,
I & CAD DEPARTMENT,
GOVERNMENT OF TELANGANA ,
HYDERABAD-82
2016
26
II) Detailed Survey & Method of Preparation of estimate/ DPR
14) Purpose of M.I. Tank: - The main purpose of minor irrigation tank is to
provide irrigation facilities to local irrigable lands in upland areas where either
major or medium irrigation projects canals are not available.
A. SELECTION OF SITES:
DESIGN-CRITERIA:
The utilization of yield for all the minor irrigation tanks in a basin should
be restricted to 60% to 70% of the total available yield in the basin area.
Preliminary Investigation:-
27
15) Detailed survey, Capacity and Surplus Course Survey:
Chain & compass survey has to be conducted. This is required to prepare survey
plan of tank and to know the total length of M.I. tank. Chain survey for the
entire length of proposed earthen bund of M.I. tank should be conducted duly
fixing chainage for every 20 to 25 m. Whole circle bearing for the entire length
of earthen bund should be taken. The survey plan of minor irrigation tank should
now be drawn with reference to North direction.
1) First conduct the Double Check Bench Mark(DCBM) survey to bring the
G.T.S benchmark to site, or fix a Temporary Bench Mark (TBM) on a
nearby rock or permanent structure as value +100.00.
2) Take levels at each and every chainage of 20 to 25mt interval along the
length of bund. This is used for drawing L. S. of bund, which shows the
existing ground profile along bund line.
3) Take cross-section levels at every chainage at 3 to 5 m interval for about
5 m to 30 m tentatively on either side of centre line of bund depending up
on bottom width of earthen bund.
4) Work out average ground levels at each chainage from cross section
levels, so that height of bund can be calculated. From this height of bund
the areas of each item of bund can be picked up from ready reckoner
table given in M.I. guidelines booklet.
B) Capacity Survey:-
There are various methods for conducting capacity survey of tank. Generally we
conduct following types of survey:
i) Contour survey (Stadia or Tachometry survey)
ii) Block level survey
Before taking up capacity survey, fix Lowest Bed Level (L.B.L) at a lowest
point on upstream side of bund line such that it is about 10m to 15m distance
from upstream toe of the bund, where capacity of tank is supposed to be zero.
28
Generally 1m interval contours are surveyed for minor irrigation tanks. Number
of contours to be surveyed are decided based on the gross capacity required,
which is again based on the hydrological clearance accorded and number of
fillings adopted as per M.I. guidelines.
(i) Contour Survey:-Contour survey is taken up from a point along bund line
on left flank and picking up points of that level upstream side (i.e., bed side)
and closing contour point on the bund line on right flank, as shown in figure
below. Again for next higher level contour the above procedure should be
followed. One extra contour is surveyed to be on safer side to get the
required gross capacity.
(ii) Block Leveling:-If the bed side of the proposed tank is uniformly sloping
then 10mx10m block leveling can also be taken up for the entire foreshore
area of tank. After block levels, 1 meter interval contours can be drawn by
interpolation method.
Draw the survey plan of earthen bund and contours on upstream side of
bund line to scale. Work out the area of each contour enclosing to bund line. By
knowing the contour level and its area, capacity table can be prepared. The
proforma of capacity table is given below for ready reference.
Total
Capacity Capacity in
SL. R.L in Area in cumulative Remark
√A C = H/3 Mcft
No. meter [Link]. capacity in s
(A1+A2+√A1*A2) (6)x35.314
[Link]
1 2 3 4 5 6 7 8
L.S of the M.I. tank can now be drawn. A sample L.S of bund is shown
below for ready reference. Cross-sections of the bund at each chainage as per
M.I guidelines should be drawn. The earthen bund sections for different height of
bunds are given in M.I. Guidelines booklet.
C) Survey for surplus course:
Chain & Compass survey is to be conducted for surplus course. LS & CS levels
are also to be taken for surplus course till it joins stream. This is required for
design of drops along surplus course for smooth disposal of flood water.
Scale for L.S drawing be 1 cm = 20 m (horizontal) & 1cm= 1 m (vertical)
Scale for Survey Plan of bund & contour drawing be 1 cm= 20 m
(horizontal/vertical)
29
16) Sample Survey Plan & L.S. of Bund is shown below fig-2.1:
30
Fig. 2.2 – Survey Plan of M.I. tank
31
17) Table – 2.1 - A sample capacity table of M.I. tank is shown below:
Total
Area in Capacity Capacity in
SL. R.L in cumulative Remar
[Link]. √A C = H/3 Mcft
No. meter capacity in ks
A (A1+A2+√A1*A2) (6)x35.314
[Link]
1 2 3 4 5 6 7 8
Capacity= H*(A1+A2+√A1*A2)
3
32
18) Survey of Block levels/ Net levels on u/s & d/s of bund on either
flanks for O. R. removal:
Block levels / Net levels are to be taken on both the flanks on upstream and
downstream side of bund line for distance of the length of weir designed, because
weir can be proposed on any one of flank. Block levels are used for working out
Obstruction Removal (O.R) quantity on upstream and downstream side of the
proposed weir portion. These block levels are taken for 10mx 10m when ground
levels are uniform without undulations and 5mx5m when ground undulations are
more. The obstruction removal is required up to apron level on downstream side of
weir and 0.22 m below the crest of High coefficient weir on upstream side, so that
the maximum flood discharge is disposed off safely into the stream. L.S & C.S
levels are to be taken up along the surplus course from the weir till it joins stream
on the downstream side of the weir.
Sample net levels vide fig-2.3 and O.R. calculations are shown below:
33
Fig. 2.3 – Net levels
34
Obstruction Removal (O.R) Calculations:
Upstream O.R is nil, since the ground levels u/s of weir are well below the
crest of weir.
Average G.L =
(100.575+100.025+101.075+100.535+101.080+100.605+100.145+101.2
05+100.765+100.44+101.265+100.875+100.43)/13= 1309.02/13=
100.693
= [(6+4.80)/2]*2 = 10.80 Sq cm
= [(4.80+3.35)]*2= 8.15 Sq cm
= [(3.35+2.5)/2]*2= 2.92 Sq cm
= (0.50*2.5*1.50)= 1.87 Sq cm
Total= 36.29 Sq cm
= 100.693 – 100.00
= 0.693 m
= 628.72 Cum.
35
19) DETAILED SURVEY FOR CANALS:
The detailed survey for canals can be taken up once Sill Level of sluice is
fixed.
The sluice position should be fixed in such a way that entire RCC Hume pipe
is buried below natural ground level across the earthen bund both on left
flank and right flank. Moreover, canal survey should be taken up in such a
manner that canal bed levels are minimum 1 meter below ground level. This
is because canals are safe in cutting.
Canal alignment has to be fixed first by tracing the points of ground levels
with one meter cutting below Ground Level (G L) duly taking fly levels.
Chain & Compass survey should then be taken up. The chain survey is done
by taking 1 chain=20m to 25 m starting from sluice point along the bund till
the proposed ayacut is covered by canal. Once the alignment is fixed, we
have to take whole circle bearing with the help of Prismatic Compass for
entire length of canal from all Apex points along the alignment.
Center levels at all chainages should be taken up along the canal alignment.
This is called longitudinal section levels which depicts the ground profile
along canal alignment.
Cross section levels at all chainages of canal alignment should also be taken
up which is used for drawing cross sections of canal at each and every chain,
so that earthwork excavation and banking quantities of canal can be worked
out.
Apart from above block levels/ net levels should be taken up at canal
crossing cart track, road or stream or for proposed Drops etc., for design and
estimate preparation of CD & CM structures across canal.
20) A sample L.S. of canal is shown below in fig-2.4 and canal alignment
(i.e., survey plan) vide fig-2.5:
36
37
Fig. 2.4 – Sample of L.S. of canal
Fig. 2.5 – Canal alignment (i.e.,Survey Plan) of L.F. Canal
38
21) Leads of material to be used for proposed Minor Irrigation Tank :
Enquiries should be made about the availability of RCC Hume pipes for sluice
of the scheme.
Quarry map can now be prepared not to scale and appended to the detailed
estimate.
39
22) Trial Pits:- Trial pits should be got excavated to know the soil strata for
formation of bund.
i) Trial pits along bund line is to be taken at minimum 100m intervals and at
close intervals where the terrain steeply changes or where soil strata are
suddenly varying.
ii) The purpose of trial pits is to ascertain the strata up to ½ F.T.L depth.
Trial pits along canal is to be taken at minimum 100m intervals and at close
intervals where the terrain steeply changes or where soil strata are suddenly
varying.
d) The trial pit size normally should be 1.25mx 1.25m for a depth of 2 to 2.5
meters. This position of trial pits and trial pits classification details are to be
marked both on L. S. of bund and foreshore area Maps, the weir plans and L.S
of canal. Sample L.S. of bund vide fig-2.7 is shown below:
40
23) Table – 2.2 - Number of fillings of M.I. tanks as per M.I. guidelines
Number of fillings
N.E. Monsoon in Chittoor, Nellore, Other areas
Average monsoon
[Link]. Prakasham, Krishna, Guntur, of Andhra
Rainfall range
[Link] & E. Godavari Pradesh.
districts.
1 Up to 15‖ 1 1
2 15‖ to 20‖ 1¼ 1¼
3 20‖ to 25‖ 1½ 1½
4 25‖ to 30‖ 1¾ 1¾
5 30‖ to 35‖ 2 2
6 35‖ to 40‖ 2 2½
7 Above 40‖ 2 3½
If the hydrological clearance is given for say 12.00 M cft & if the average
monsoon RF is more than 30‖ , then 2 filling is to be adopted as per M.I. guidelines
(from above table).
Generally 10% to 15% dead storage is provided which is meant for
sedimentation of M.I. tank, if life of the Minor Irrigation tank is taken as 25 years.
If life of the Minor Irrigation tank is taken as 50 years (i.e., for M.I. tanks
taken up with JICA assistance), 20% dead storage is to be provided.
Assuming 12% dead storage, the dead storage will be 6.00*12/100= 0.72 Mcft.
The level corresponding to 0.72 Mcft. storage capacity in capacity table is called Sill
level of sluice.
The Gross capacity= 6.00+0.72= 6.72 Mcft. The level corresponding to gross
storage capacity is called Full Tank Level (F.T.L).
If the sill capacity and F.T.L capacity are not directly available in Capacity
table, then it should be worked out by interpolation method to get the Sill level and
F.T.L. from capacity table.
L.R.R:- This stream joins Kagna River after traversing about 13 km and more over
there are no tanks in between proposed site and Kagna River, hence L.R.R. will not
be effected.
42
Fixing of F.T.L & SILL:-
Location of weir is proposed along bund line at such a point on either left or
right flank that the foundation of weir is buried below natural ground level. Top of
foundation level is taken as Apron level. Full tank level minus Apron level is the
height of weir body wall.
Location of Sluices is proposed along bund line on either side of stream such
that the 800mmØ RCC Hume pipe barrel portion of sluice is completely buried
below natural ground level.
A sample latest 40 years Annual Rainfall data, Monsoon Rainfall data &
Monthly Monsoon Rainfall data are given below which is used for working out yield,
Rainfall distribution, yield distribution & Rainfall distribution @ 50% dependability.
These are used for preparation of Demand Tables (both Khariff & Rabi crops) and
Regime Table.
43
HYDROLOGY OF M.I. TANK
44
ii) Table- 2.5 - Statement showing Monsoon Rainfall of Tandur „R.G.S‟ from
June to October
Monsoon Rain fall
Monsoon Rain Year of
Sl. No. Year in descending Remarks
fall in Inches occurrence
order in Inches
1 1961 35.39‗‘ 52.83‗‘ 1998
2 1962 42.87‗‘ 47.90‗‘ 1978
3 1963 77.12‗‘ 46.18‗‘ 1990
4 1964 25.59‗‘ 43.96‗‘ 1975
5 1965 26.13‗‘ 43.19‗‘ 1973
6 1966 19.41‗‘ 41.87‗‘ 1962
7 1967 26.39‗‘ 40.81‗‘ 1983
8 1968 25.68‗‘ 39.09‗‘ 1970
9 1969 26.94‗‘ 37.84‗‘ 1988
10 1970 39.09‗‘ 37.12‗‘ 1963
11 1971 18.06‗‘ 35.79‗‘ 1961
12 1972 17.87‗‘ 34.03‗‘ 1989
13 1973 43.19‗‘ 33.93‗‘ 2000
14 1974 33.46‗‘ 33.61‗‘ 1987
15 1975 43.96‗‘ 33.46‗‘ 1974
16 1976 28.55‗‘ 32.38‗‘ 1985
17 1977 18.93‗‘ 31.33‗‘ 1992
18 1978 47.90‗‘ 31.14‗‘ 1995
19 1979 23.04‗‘ 30.21‗‘ 1991
20 1980 25.61‗‘ 29.86‗‘ 1996 50% Dep.
21 1981 28.03‗‘ 29.59‗‘ 1964
22 1982 26.22‗‘ 28.55‗‘ 1976
23 1983 40.81‗‘ 28.03‗‘ 1981
24 1984 25.65‗‘ 27.45‗‘ 1993
25 1985 32.38‗‘ 26.94‗‘ 1969
26 1986 25.39‗‘ 26.40‗‘ 1999 65% Dep.
27 1987 33.61‗‘ 26.39‗‘ 1967
28 1988 37.84‗‘ 26.22‗‘ 1982
29 1989 34.03‗‘ 26.13‗‘ 1965
30 1990 46.18‗‘ 25.68‗‘ 1968 75% Dep.
31 1991 30.21‗‘ 25.65‗‘ 1984
32 1992 31.33‗‘ 25.52‗‘ 1997
33 1993 27.45‗‘ 25.39‗‘ 1986
34 1994 18.89‗‘ 23.04‗‘ 1979
35 1995 31.14‗‘ 20.97‗‘ 1980
45
36 1996 29.86‗‘ 19.41‗‘ 1966
37 1997 25.52‗‘ 18.93‗‘ 1977
38 1998 52.83‗‘ 18.89‗‘ 1994
39 1999 26.40‗‘ 18.08‗‘ 1971
40 2000 33.93‗‘ 17.87‗‘ 1972
iii) Table – 2.7 - Monthly Monsoon Rainfall of TADUR RGS Ranga Reddy
District Monsoon Rainfall from June to October (1961 – 2000)
Sl. Year June July August Septemb October Total Remar
No er ks
1 1961 214.70 300.30 124.10 85.20 184.80 909.10
2 1962 163.40 280.00 291.00 206.40 122.80 1063.60
3 1963 172.00 183.80 334.00 155.60 97.40 942.80
4 1964 82.00 256.80 113.60 293.80 5.30 751.50
5 1965 99.80 266.60 94.80 202.40 0.00 663.60
6 1966 85.00 15.70 101.10 268.00 23.30 493.10
7 1967 120.40 242.80 59.60 231.40 16.00 670.20
8 1968 77.40 164.20 45.20 268.00 97.50 652.30
9 1969 124.60 216.20 64.40 266.00 12.60 684.40
10 1970 65.20 208.80 507.40 172.20 39.30 992.90
11 1971 156.70 10.60 92.20 81.00 118.80 459.30
12 1972 148.00 95.40 14.00 106.00 90.60 454.00
13 1973 197.20 62.40 431.10 105.40 344.70 1097.00
14 1974 170.20 137.60 85.60 19.80 251.40 850.00
15 1975 191.40 227.20 259.40 346.10 269.30 1116.50
16 1976 143.50 204.40 271.20 271.80 0.60 725.10
17 1977 73.60 182.60 182.40 229.20 22.40 480.80
18 1978 82.00 282.30 407.40 337.50 98.80 1216.60
19 1979 119.90 120.40 313.00 199.80 41.80 585.20
20 1980 153.70 105.10 162.50 250.70 0.00 650.50
46
21 1981 94.40 107.40 120.70 127.00 51.90 711.90
22 1982 83.50 284.60 48.00 221.20 50.00 665.90
23 1983 103.80 165.80 413.90 136.00 102.40 1036.60
24 1984 44.60 219.60 180.00 104.80 80.40 651.60
25 1985 138.20 279.80 78.80 150.80 102.40 822.60
26 1986 66.40 182.60 238.20 200.40 21.800 645.00
27 1987 149.20 279.20 196.40 195.20 124.20 853.80
28 1988 96.90 334.70 317.90 71.80 6.80 961.10
29 1989 156.80 368.40 112.20 154.80 26.60 864.40
30 1990 191.80 215.00 352.40 124.20 218.60 1173.00
31 1991 205.40 352.60 90.60 54.60 47.00 767.40
June = 4998.30 mm
July = 7903.20 mm
August = 7724.20 mm
September =7116.60 mm
October = 3914.70 mm
Average Monsoon Rainfall calculations:
June = 4998.30 = 124.957 mm
40
July = 7903.20 = 197.58 mm
47
40
August = 7724.20 = 193.105 mm
40
September =7116.60 = 177.915 mm
40
October = 3914.70 =97.867 mm
40
50
vi) Table – 2.10 - Capacity Table
Capacity =
Cumulative Cumulative
Sl. Reduced level Contour Area H* [(A1+A2+
√Area √A1xA2 capacity in capacity in M Remarks
No in meter in M Sqm (A)
M Cum. Cft.
√A1XA2)]/3
1 +94.60 0.000000 0.000000 0.000000 0.000000 0.000000 0.000000 L.B.L.
2 +97.00 0.00286 0.05347896 0.0000000 0.0022880 0.0022880 0.08079843 S.C
3 +98.00 0.00668 0.08173126 0.004370903 0.004636967 0.006924967 0.24454828 S.C
4 +99.00 0.01708 0.13069047 0.010681497 0.011430499 0.018405466 0.64997062 S.C/Sill
5 +100.00 0.02697333 0.16423560 0.021464028 0.02183912 0.040244586 1.42119732 S.C
6 +101.00 0.4020000 0.20049937 0.032929135 0.033367489 0.073612615 2.5995368 S.C
7 +102.00 0.0554000 0.23537204 0.47191948 0.047597316 0.121209391 4.28038843 S.C
8 +102.10 0.05705445 0.23886075 0.056221143 0.00562252 0.126831911 4.4789421
9 +102.20 0.05873326 0.24234946 0.057887774 0.005789183 0.132621094 4.68338132
10 +102.30 0.06043640 0.24583817 0.059578748 0.00595828 0.138579874 4.87379203
11 +102.40 0.06216389 0.2493268 0.061294064 0.006129812 0.144709186 5.11026019
12 +102.50 0.06391572 0.25281558 0.063033722 0.006303777 0.151012963 5.33287180
13 +102.60 0.0656918 0.25630429 0.064797721 0.006480177 0.15749314 5.56171271
14 +102.70 0.06749240 0.25979300 0.066586063 0.006659012 0.164152152 5.79686909
15 +102.80 0.06931726 0.26328171 0.068398748 0.006840280 0.170992432 6.03842674 F.T.L
16
+102.90 0.07116645 0.26677042 0.070235774 0.007023983 0.178016415 6.28647168
17
+103.00 0.0730400 0.27025913 0.072097143 0.007210120 0.185226535 6.54018985 SC
52
27) Maximum flood discharge calculations by Rational method and
Dicken‟s formula.
A- Rational Method:-
27) Sample calculations of one of the M.I. tank are shown below:
Catchment area = 1.06 Sq. miles –or- 2.745 Sq km.
L = Length of stream= 2.15 Km
W= Width of catchment= 1.15 km
L / W= 2.15/1.15 =1.869: 1 < 4:1
Choosing of run-off curve. Table of run-off curve given at page 52 of M.I.
guidelines.
Table – 2.12 of Run-off curve number for hydrological soil group of Black soil
for this M.I. Tank.
Percentage Run-off curve Number line
[Link]. Land use area of number percentage
catchment
1 Cultivated crop 15 85 1275
2 Cultivated paddy Nil 95 0
3 Forest / Gardens 85 70 5950
4 Waste lands nil 90 0
Total 100 7225
Weighted curve number=7225/ 100= 72.25 or say 72
Hence adopt curve number 72.
The maximum one day rainfall is read from Isohyets map vide the CE, MI,
Hyderabad circular memo no. DCE(MI)/ OT1-T4/ 28556/ 65, dated 29-1-86 duly
locating the proposed M.I. Tank position in map with help of latitude and longitude.
The value of one day maximum rainfall read as 170 mm.
Note: Latest 25 years 24- hours Isopluvial map published by IMD, New
Delhi published in September, 2007 is given below. The maximum one day
rainfall can be interpolated and used for MFD calculation from this map. 50
years 24-hours Isopluvial map is also enclosed.
To find the value of Q (i.e., discharge), read Graph-II of Black soil (given in MI
guideline booklet) for curve number 72 at 170 mm maximum one day rainfall, the
value of Q read for this scheme is 99.
= 0.48*(2.745)0.28
Tp= 0.6368 hr,
MFD= q = (0.146*A*Q)/ Tp
q = (0.146*2.745*99)/ 0.6368
q = 62.30 Cumecs –or- 2200 Cusecs.
53
B- Dicken‟s fomula:
Q = C* M3/4 where Q= discharge in Cusecs.
C= Constant= 1000
M= C.A= 1.06 Sq miles
Q= 1000*(1.06)3/4 = 1000* 1.04467 = 1044.67 Cusecs –or- say 1045
Cusecs.
Hence adopt 2200 Cusecs MFD for design of weir.
28) Cover page of Atlas of ISOPLUVIAL maps given below at p-55.
54
55
Fig. 2.8 – 25 Years 24 Hours ISOPLUVIAL Map (mm)
56
Fig. 2.9 – 50 Years 24 Hours ISOPLUVIAL Map (mm)
57
31) The formula for calculating length of F.O.F weir is as follows:
Q= (10*L*H3/2)/3,
Where Q= MFD in cusecs.
L=Length of weir in ft.
H=head of discharge in ft. (We have to assume it)
Width of apron= 2*√F*H +H+3, where F=ht. of bund, H=head of discharge.
Thickness of apron= √F+H
Base width of body wall= (F+H)/√2.5
Top width of body wall= 2 ft. –or- 0.60 m. For small MFD‘s from small
catchment areas and head of discharge between 0.50 m to 0.90 m, we provide
F.O.F weir (Broad Crested weir).
Cross section of F.O.F weir vide fig-2.10 is shown below.
The formula for calculating length of High Coefficient (H.C.) weir is as follows:
Q=3.90*L*H3/2 for C.R.S masonry body wall;
Q=4.10*L*H3/2 for C.C body wall.
Where Q= MFD in cusecs.
L=Length of weir in ft.
H=head of discharge in ft. (We have to assume it)
58
32) Typical cross section of H.C. weir is as shown below fig. 2.11:
The following is the figure 2.12 showing H.C. weir when B.C. soils are met with in
foundation as per M.I. guidelines.
59
Fig. 2.12 – H.C. Weir when B.C. soils are met within the foundation
L=2200 / (3.90*5.071) =
Hence provide H.C. weir from ch. (-) 0.20 to ch. 1.50 (such that the foundation of
H.C. weir is below ground level) with ahead of discharge of 0.90 m
We have to provide/place H.C. weir along the bund line on either left flank or right
flank such that the foundation of weir is buried below natural ground level as shown
in the L.S. of Bund figure at page (60).
Top of the foundation level of H.C. weir is taken as apron level, such that the apron
C.C. is below ground level as shown in cross section of weir.
34) L. S., Plan & Cross Section of H.C. Weir are shown below:
Fig. 2.13- L.S. of H.C. Weir; Fig. 2.14- Plan & C.S of H.C. Weir
60
Fig. 2.13 – L.S. of H.C. Weir
35) Plan & Cross Section of H.C. Weir are shown below:
61
62
Fig. 2.14– Plan & Cross-Section of H.C. Weir
36) Sample drawing of F.O.F Weir
63
37) Plan showing different parts of H.C. Weir, Abutment, Upstream
Return, Downstream Return, Wings and Talus (Horizontal stone
pitching) vide fig. 2.16
64
38) Sample drawing of Section along Abutment, Wings & Return.
Now we know the F.T.L and apron level. Height of weir body wall is the difference
between F.T.L and apron level.
For this height of body wall and head of discharge designed above, we have to
choose the corresponding standards of different components of H.C. weir from table
at page 109 in MI guideline booklet.
For sample design of above H.C. weir body wall height 2.80 m and head of
discharge of 0.90 m,
the standards of H.C. weir as per M.I. guideline table at page 109 are as follows:
H= Height of weir body wall =2.80 m
W=Base width of body wall = 3.05 m
T1=Thickness of solid apron = 1.10 m
T2=Thickness of solid apron = 0.85 m
L1=Length of solid apron = 5.50 m
L2=Length of solid apron = 5.00 m
D1=Depth of upstream cut-off wall = 1.80 m
D=Depth of downstream cut-off wall = 2.20 m
L3=Length of Talus = 3.30 m
65
= 1.35* 1.188 = 1.603 m < 2.20 m proposed.
The formulas used for design of Abutment, Wings & Returns are as follows:
Design of Abutment:
Upstream Return:-
Downstream Return:-
66
(iii) Sample design of Abutment, Wings & Returns for one of the M.I. tank:
Design of Abutment:
Height of abutment = H = TBL – apron level
H = 105.20- 100.00
H = 5.20 m
Top width of abutment = 0.60 m
Bottom width of abutment = 0.4 x H = 0.40 * 5.20 +0.60
= 2.68 m -or- say 2.70 m
Length of abutment = same as top width of bund = 3.00 m
Upstream Return:-
Height of U/s return = equal to height of abutment = 5.20 m
Top width of return = 0.60 m
Bottom width of return = 0.4 x H = 0.40 * 5.20 +0.60
= 2.68 m -or- say 2.70 m
Length of U/s return = 2xH+0.60 = 2* 5.20 + 0.60
= 11.00 m
Downstream Return:-
Height of downstream return = TWD+0.30 = 1.17 + 0.30 = 1.47 m.
Top width of return = 0.60 m
Bottom width of return = 0.4xH +0.60 =0.40* 1.50 +0.60 = 1.20 m
Length of return = 2(TWL-Apron level) +0.30
= 2*(1.1017 – 100.00) + 0.30
=2.64 m -or- say 2.70 m
67
40) Sample Stability calculations for H. C. Weir
Case I: Where there is water upto crest level on U/s side and no water on D/s side
69
41) STABILITY CALCULATIONS FOR ABUTMENT:
2
5 Ph 0.1585*2.10*(4.80) (-)7.668 0.40*4.80=1.92 (-)14.722
70
Preparation of detailed estimate of earthen bund:
The detailed estimate of earthen bund is prepared with the help of following Earth
Work statement duly taking area of stripping, toe wall, toe drain, COT, hearting
zone, casing zone, revetment, rock toe, toe drain etc., from ready reckoner of ―
Statement of quantities for standard sections for minor irrigation tank‖ from page
95 to 100 in M.I. guidelines booklet.
EWE for toe wall & toe drain EWE for key trench EWE for cut-off trench
300mm thick gravel Rock toe 150mm thick Trimming on u/s & d/s
under revetment gravel on bund slopes to bund
Area Mean Qty. Area Mean Qty. Area Mean Qty. Area Mean Qty.
Area Area Area Area
28 29 30 31 32 33 34 35 36 37 38 39
Suppose the sill of the sluice is +97.45, G.L. is +98.50 & TBL is +104.45,
71
Height of bund at sluice point=104.45-98.50=5.95 m. For this height of bund, the
quantities of different items of sluice can be taken from ready reckoner table given
by the Engineer-in- Chief, Minor Irrigation, Hyderabad vide circular memo no. DCE
(MI)/OT4-T1/84023/86, dated.25-3-1987 (Copy given below for ready reference).
72
GOVERNMENT OF ANDHRA PRADESH
IRRIGATION & CAD DEPARTMENT
Office of the Engineer-in-Chief,
Minor Irrigation, Errum manzil,
Andhra Pradesh, Hyderabad.
43) Circular Memo [Link](MI)/OT4-T1/84023/86 Dated: 25-03-1987
Sub :Minor Irrigation –Type Design for head sluice– Ready Reckoner table –Reg
Ref :[Link] Memo No. DCE (MI)/OT4-T1/84023/86, dt.12.12.1986.
In continuation of this office circular memo cited, the Ready Reckoner Tables
for dimension of structures and quantities of work are enclosed for quick computing
the items of work involved and estimating. These standards are issued for the
purpose of estimation only. The Executive Engineers are requested to ensure the
safety of head wall based on the soils met with in the foundations and other field
conditions.
The following alterations are made to the type design already circulated.
1. Top width of earthen approach embankment (from bund to head wall) is
increased from 1 M to 2M to bring it in line with abutment of head wall and
also for consolidation with power roller up to top level.
2. Grouting and pointing of revetment for approach embankment is deleted as it
is considered not necessary.
3. The length of the barrel (pipe line) is fixed so as, to get the number of pipes
to the nearest half pipe length, as indicated in the enclosed statement.
The revised type design of head sluice is also enclosed for ready reference.
//TRUE COPY//
ground level
ground level
of head wall
No. of pipes
bund above
length each
Base width
(MWL plus
of 2.5 mts
meters at
head wall
in meters
in meters
Length of
Height of
Height of
Remarks
in meter
Width of
barrel in
bund in
0.30M)
meters
collars
No. of
Sl No.
above
1 2 3 4 5 6 7 8 9
1 2.8 14.2 1.6 0.90 13.75 5½ 5
2 3.0 15.0 1.8 0.90 15.00 6 5
3 3.2 15.8 2.0 1.00 16.25 6½ 6
4 3.4 16.6 2.2 1.10 16.25 6½ 6
5 3.6 17.5 2.4 1.20 17.50 7 6
6 3.8 18.3 2.6 1.30 18.75 7½ 7
7 4.0 19.1 2.8 1.40 18.75 7½ 7
8 4.2 19.9 3.0 1.50 20.00 8 7
9 4.4 20.7 3.2 1.60 21.25 8½ 8
10 4.6 21.5 3.4 1.70 21.25 8½ 8
11 4.8 22.3 3.6 1.80 22.50 9 8
12 5.0 23.1 3.8 1.90 23.75 9½ 8
13 5.2 23.9 4.0 2.00 23.75 9½ 8
14 5.4 24.7 4.2 2.10 25.00 10 9
15 5.6 25.5 4.4 2.20 25.00 10 9
16 5.8 26.3 4.6 2.30 26.25 10 ½ 9
17 6.0 27.1 4.8 2.40 27.50 11 10
18 6.2 27.9 5.0 2.50 27.50 11 10
19 6.4 28.7 5.2 2.60 28.75 11 ½ 10
20 6.6 29.5 5.4 2.70 30.00 12 11
21 6.8 30.3 5.6 2.80 30.00 12 11
22 7.0 31.1 5.8 2.90 31.25 12 ½ 11
23 7.2 31.9 6.0 3.00 32.50 13 11
24 7.4 32.7 6.2 3.10 32.50 13 11
25 7.6 33.5 6.4 3.20 33.75 13 ½ 12
26 7.8 34.3 6.6 3.30 35.00 14 12
27 8.0 35.1 6.8 3.40 35.00 14 12
28 8.2 35.9 7.0 3.50 36.25 14 ½ 13
29 8.4 36.3 7.2 3.60 36.25 14 ½ 13
30 8.6 37.5 7.4 3.70 37.50 15 13
31 8.8 38.3 7.6 3.80 38.75 15 ½ 14
32 9.0 39.1 7.8 4.00 38.75 15 ½ 14
33 9.2 39.9 8.0 4.30 40.00 16 14
34 9.4 40.70 8.2 4.60 41.25 16 ½ 15
35 9.6 41.5 8.4 4.60 41.25 16 ½ 15
36 9.8 42.3 8.6 4.90 42.50 17 16
37 10.00 43.1 8.8 5.00 43.75 17 ½ 16
74
45) Table – 2.17 - Statement showing the ready reckoner of quantities for
head wall, foundations, approach embankment etc., for 800 mm Ø NP3
class RCC hume pipe sluice for Minor Irrigation Tanks.
Approach embankment
Concrete ([Link])
([Link]) in Cum
cement morter
Height of bund
RR masonry in
above ground
Rebetment in
Earth work in
excavation in
foundation in
Pre-cast RCC
(1:6) in Cum
Puddle clay
Earth work
800 mm Ø
backing in
NP3 class
Concrete
concrete
Cement
Cement
block in
cement
in Cum
in cum
Gravel
Sl No.
level
Cum
cum
cum
cum
pipe
1 2 3 4 5 6 7 8 9 10 11 12
1 2.8 52.07 10.07 8.65 17.41 1.86 1.78 0.04 13.75 5.40 0.68
2 3.0 54.63 10.61 8.86 18.40 2.42 3.28 1.05 15.00 6.00 0.68
3 3.2 58.13 12.00 9.27 20.05 3.76 4.03 1.46 16.25 6.61 0.68
4 3.4 59.33 11.96 9.69 21.84 6.32 4.84 1.94 16.25 6.61 0.68
5 3.6 53.17 12.46 10.11 23.08 8.31 5.73 2.49 17.50 7.22 0.68
6 3.8 67.42 13.57 10.62 26.11 9.71 6.77 3.18 18.75 7.39 0.68
7 4.0 67.54 13.82 11.16 29.62 12.00 7.69 3.79 18.75 7.39 0.68
8 4.2 70.36 14.19 11.72 29.93 15.66 8.78 4.54 20.00 8.00 0.68
9 4.4 75.42 15.70 12.30 34.36 19.46 9.98 5.36 21.25 8.61 0.68
10 4.6 77.21 15.66 12.91 37.57 24.38 11.15 6.24 21.25 8.61 0.68
11 4.8 80.95 16.12 13.53 41.00 28.63 12.44 7.95 22.50 8.78 0.68
12 5.0 84.78 16.16 14.18 45.52 35.11 14.30 8.22 23.75 8.78 0.68
13 5.2 86.78 16.61 14.86 48.63 42.22 15.22 9.31 23.75 9.39 0.68
14 5.4 91.20 16.82 15.55 52.62 48.66 16.71 10.46 25.00 10.00 0.68
15 5.6 93.34 17.97 16.28 57.32 56.44 18.25 11.70 25.00 10.00 0.68
16 5.8 97.47 18.48 17.02 61.81 64.90 19.89 12.99 26.25 10.18 0.68
17 6.0 98.93 19.87 17.79 67.11 74.68 21.51 14.35 27.50 10.79 0.68
18 6.2 104.50 19.82 18.58 72.22 85.08 23.35 15.78 27.50 10.79 0.68
19 6.4 108.83 20.32 19.39 78.07 96.36 25.20 17.28 28.75 11.40 0.68
20 6.6 113.70 21.18 20.22 83.99 108.68 27.08 18.85 30.00 11.57 0.68
21 6.8 115.93 21.69 21.09 90.25 121.94 29.04 20.48 30.00 11.57 0.68
75
22 7.0 120.86 22.19 21.96 96.82 135.72 31.30 22.18 31.25 12.18 0.68
23 7.2 125.48 22.68 22.87 103.38 151.63 33.19 23.95 32.50 12.79 0.68
24 7.4 128.30 22.64 23.80 110.21 168.09 35.36 25.79 32.50 12.79 0.68
25 7.6 132.21 24.03 24.74 118.55 185.71 37.60 27.69 33.75 12.96 0.68
26 7.8 138.40 24.54 25.72 126.49 204.53 39.91 29.67 35.00 13.57 0.68
27 8.0 141.44 24.49 26.71 134.00 224.54 42.20 31.71 35.00 13.57 0.68
28 8.2 146.90 25.88 27.73 143.44 245.99 44.45 33.82 36.25 14.18 0.68
29 8.4 150.08 25.84 28.78 152.48 268.40 47.24 35.99 36.25 14.18 0.68
30 8.6 155.17 26.33 29.84 161.90 292.32 49.82 38.24 37.50 14.35 0.68
31 8.8 159.52 27.74 30.93 171.52 317.64 52.26 40.54 38.75 14.96 0.68
32 9.0 172.19 27.66 33.59 184.57 342.085 55.18 42.93 39.25 14.96 0.68
33 9.2 180.04 28.07 34.20 200.81 365.265 57.96 45.38 40.50 15.57 0.68
34 9.4 188.51 29.38 36.21 217.83 389.661 60.81 47.89 41.25 15.74 0.68
35 9.6 193.67 29.30 37.80 232.56 417.771 63.73 50.48 41.25 15.74 0.68
36 9.8 199.71 29.80 38.90 242.38 451.143 66.71 51.79 42.50 16.35 0.68
37 10.00 207.30 31.18 40.55 259.65 483.405 69.77 55.85 43.75 16.52 0.68
Sd/-
for Chief Engineer, Minor Irrigation
//True copy//
76
46) A sample detailed estimate of Head Sluice is given below:
Name of work: Formation of Minor Irrigation Tanks a/c Batti Vagu, Indur (V), Peddamul (M),
Ranga Reddy dist.
Table – 2.18 - Detailed Estimate of Head Sluice @ ch 11. 00
[Link]. Particulars of Item No. L B D Quantity
Quantities of each item of work of sluice as per CE/MI, Hyd. circular memo no.
DCE(MI)/OT4-T1/84023/86, dt: 25-03-1987 ready reckoner table.
Height of bund above G.L. at sluice point = T.B.L-G.L = 105.20-100.19=5.01 mt
a) Earth work excavation for foundation
I in ordinary soils up to stone matrix and - - - 84.78 Cum
depositing spoil away etc.
(3.38+1)x1.19+0)
b) E.W.E. for approach channel 2__________ x40 52.12 Cum
2
136.90 Cum
Filling foundation under the pipes on
II sluice with C.C ([Link]) using 40 mm - - - 16.12 Cum
metal
Filling foundation with C.C ([Link]) using
III - - - 14.18 Cum
40 mm metal
77
47) Type drawing of head sluice given by the Chief Engineer, Minor
Irrigation is show below vide fig.2.21 for ready reference:
78
48) Copy of actual drawing of Head sluice of one of M.I. Tank given
below at page 79.
Fig. 2.22 – L.S & Half Plan Half Section of head sluice
79
49) Name of work: Formation of Minor Irrigation Tanks a/c Batti Vagu,
Indur (V), Peddamul (M), Ranga Reddy District.
The statement of ready reckoner of quantities for H.C. weir components is available in
M.I guidelines booklet at page 110.
Table – 2.19 - Detailed Estimate of prop. H.C. weir from ch(-) 0.20 to ch 1.50 (34 mt.
long)
Sl.
Particulars of Item No. L B D Quantity
No.
Earth work excavation in ordinary soils
1 up to stone matrix for O.R. &
foundations of
i) O.R. (as per net levels sheet
- - - 628.72 Cum
enclosed.)
ii) Foundation of weir body wall
{(101.265+100.875+100.43+99.935)/ 1 34 3.05 1.47 152.43 Cum
4 -99.15=1.47}
xiii) D/S return right side 1 2.85 1.5 0.535 2.28 Cum
(2.85+1.45)
xiv) Wing wall left side 1 8 x 2.00 34.40 Cum
2
(2.85+1.45)
xv) Wing wall right side 1 8 x 0.535 9.20 Cum
2
1400=79
Total
Cum
80
2 Filling
foundation with
CC([Link])
i)Weir body wall 1 34 3.05 0.85 88.14
ii) U/S cut-off 1 34 0.30 1.80 18.36
wall
iii)Solid apron L1 1 (34+35.6)/2 4.1 1.00 142.68
iv)Solid apron L2 1 (35.6+37.6)/2 4.5 0.85 139.99
v)D/s cut-off 1 37.60 0.50 2.20 41.36
vi)Below 2 3.80 2.85 0.60 12.99
abutment
vii)U/s Return 2 8.30 3.00 0.60 29.88
Viii)D/s Return 2 2.85 1.50 0.60 5.13
ix)Wing walls 2 8.00 (2.85+1.45)/2 0.60 20.64
Total 499.17
3 Laying wearing 1 (34+35.6)/2 4.10 0.10 14.26
coat with
([Link]) using 20
mm metal
4 Construction of 1 34*1/2*1.4*2.8 - - 66.64
C.R.S masonry 1 34*(2.8+2.58)/2 0.45 - 41.15
2nd sort in 1 34*1/2*1.2 2.58 - 52.63
CM(1:5)
proportion for
Weir body wall
Total 160.42
5 Construction of
CRS masonry 2nd
sort in CM (1:6)
proportion for
i) 2 3.05 (2.70+0.60)/2 5.20 62.63
ii)U/s Returns 2 8.30 (2.70+0.60)/2 5.20 142.42
iii)D/s Return 2 2.70 (0.60+1.20)/2 1.50 7.29
iv) 2 8.0*[(2.7+0.6)/2+(1.2+0.6)/2]/2*(5.2+1.5)/2 68.34
Total 280.68
6 300 mm thick 1 37.60 3.30 0.90 111.67
rough stone
pitching for
Talus
81
Name of the Work: Formation of M.I. Tank a/c Batti vagu, Indur (V),
Peddemul (M), R.R. District.
Fig. 2.23
Fig. – Cross
2.23 section
– Cross at at
section Ch. (-)(-)0.
Ch. 0.2020
b) At Ch 1.50, the height = (105.20-99.935) + 0.30 = 5.565 Mt.
82
Base width = 2*5.565*2+3 = 25.26 Mt.
83
Base width = 2* 6.385X2+3 = 28.54 Mt.
Area of Land required for L.F. Canal= 11.70X110 = 128.70 Sq. Mt or 3.18 Acres
84
(b) R.F. Canal:
Length of H.C. weir is 34 meter. Hence width of surplus course is 34+4=38 mt.
(4 m is for retaining wall on either side of drop.)
Length of surplus course is 72 meter till it joins the stream on d/s side of bund,
as shown in figure below:
85
51) DESIGN OF CANAL: Sample design of canal is given below.
Left side canal ayacut=104 acres
Discharge required for 2‖ depth of water in khariff season for 4days in a
week
= 104x4840x2‖x9___ = 2.1847 C/s
4x24x60x60x12
Add 10% losses = 0.2184
Total = 2.4031 C/s
Proposed canal section……2‘-0‖x1‘-0
86
52) Sample calculations of earth work excavation and earth work
embankment of canal (canal in full cutting, canal in partial cutting &
partial banking and canal in full banking above ground level) are given
below for guidance:
Avg. GL =+100.190
CBL = +99.00
EWE in all soil = [(2.98+1.60)/ 2]* 0.69 = 1.58 [Link].
EWE in HDR = [(1.60+0.60)/2]* 0.500 = 0.55 [Link].
Avg. GL =+100.110
CBL = +98.992
EWE in all soil = [(2.836+1.60)/ 2]* 0.618 = 1.371 [Link].
EWE in HDR = [(1.60+0.60)/2]* 0.500 = 0.550 [Link].
87
Fig. 2.32 – Cross section at Ch. 2.00
Avg. GL =+99.830
CBL = +98.984
EWE in all soil = [(2.292+1.292)/ 2]* 0.500 = 0.896 [Link].
EWE in HDR = [(1.292+0.60)/2]* 0.346 = 0.327 [Link].
Avg. GL + 99.800
CBL = +98.976
EWE in all soil = [(2.248+1.248)/ 2]* 0.500 = 0.874 [Link].
EWE in HDR = [(1.248+0.60)/2]* 0.324 = 0.300 [Link].
88
Fig. 2.34 – Cross section at Ch. 4.00
Avg. GL =+99.605
CBL = +98.968
Stripping under bank = 2* 1.689*0.15 = 0.507 [Link].
EWE in all soil = [(1.874+0.60)/ 2]* 0.637 = 0.788 [Link].
EW embankment=2*[(0.90+1.689)/2]*0.269= 0.696 [Link].
Avg. GL =+99.560
CBL = +98.960
Stripping under bank = 2* 1.80*0.15 = 0.540 [Link].
EWE in all soil = [(1.80+0.60)/ 2]* 0.60 = 0.720 [Link].
EW embankment= 2*[(0.90+1.80)/2]*0.30= 0.81 [Link].
89
Fig. 2.36 – Cross section at Ch. 6.00
Avg. GL =+98.910
CBL = +98.952
Stripping under bank = 7.668*0.15 = 1.398 [Link].
EWE in all soil = nil
EWE in HDR = Nil
EW embankment= 2*[(0.90+3.15)/2]* 0.75+ [(6.90+7.668)/2]*0.192=
4.435 [Link].
Now we can prepare the earth work statement of Left and Right canal. This
will give earth work excavation for stripping, EW for canal excavation in
ordinary soils, excavation in HDR if any and earth work formation of canal
embankment.
90
53) DESIGN OF CD & CM STRUCTURES OF CANAL
(1) Top width of drop wall = √d1 + H , where d1 = height of drop in feet
H = FSD of canal in feet
(2) Bottom width of drop wall = (H+ d1)/ √ℓ ,
where d1 = height of drop in m.
H = FSD of canal in m.
ℓ = unit wt. of masonry=2.25
91
54) Sample design of 1.00 meter drop/fall is given below
Drop= d1 = 1.00 meter –or- 3.28 ft. ; FSD= H =0.30 m. –or- 1 ft.
1) Top width of drop = √d1 + H,
where d1 = 3.28 ft.
H = 1 ft.
= √3.28+ 1 = 2.06 ft. –or- 0.628 m. say 0.65 m.
2) Bottom width of drop wall = (H+ d1)/ √ℓ,
where, d1 = 3.28 ft.
H = 1 ft.
ℓ = unit wt. of masonry=2.25
= (0.30+1) / √2.25 =0.866 m. say 0.90 m.
3) Length of solid apron = 2* d1 + 2* √ d1*H
= 2* 1.00 + 2* √1*0.30
= 2+1.09
= 3.09 m. say 3.10 m.
4) Thickness of apron = ½ *(√d1 + H)
= ½ * (√1 +0.30) =0.57 m –or- say 0.60 m.
5) Length of d/s revetment = 4* (d1 + H) = 4* (1.00+0.30) = 5.20 m.
6) Length of u/s revetment = 3* d1 = 3* 1.00 = 3.00 m.
7) Length of drop wall = Top width of canal section +1m + 1m
= 1+3.90+1
= 5.90 m.
92
Sample drawing of the 0.90 m. drop of canal vide fig. 2.37 is shown below:
93
55) Sample deign of RCC Hume pipe culvert for canal crossing the
Cart Track at ch. Of canal
Discharge of canal = Q= 2.31 Cusecs
Velocity of water in canal = V = 0.854 ft/ sec.
Q= A* V
d2 = 2.2964
Hence provide minimum 600 mm Ø RCC Hume pipe for culvert, so that
it is not silted up. More over we have to provide higher diameter pipe
than the diameter obtained above to make flow as open channel flow.
Length of H.P. culvert proposed for Cart Track is 7.50 m. Length of each
pipe=2.50mt
Hence provide 3 no‘s RCC Hume pipes of 600 mm diameter from ch.
To ch. for canal crossing Cart Track.
94
56) A sample drawing of the RCC Hume pipe culvert is shown
below vide fig. 2.38:
95
57) Sample design of RCC Hume pipe Super-Passage for canal
crossing the surplus course:
Q= A* V
d2 = 3.309
Hence provide 800 mm Ø [Link] Hume pipe for super-passage, so that it is not
silted up. Moreover we have to provide higher diameter pipe than the diameter
obtained above to make flow as open channel flow.
96
58) Sample drawing of a RCC Hume pipe super-passage proposed
is given below vide fig. 2.39:
Fig. 2.39 – Plan, L.S. & C.S of RCC Hume pipe Super-passage
97
59) Design of Rectangular R.C.C Trough aqueduct for canal crossing
motorable track at ch.
Design discharge of canal = Q = 2.403 Cusecs
Velocity of water in canal = V = 0.8656 ft / sec
Design of rectangular section;
Q=A*V
A = Q / V = 2.403 / 0.8656 = 2.776 Sq ft.
We know FSD of canal = 1 ft., length of rectangular section will be,
A = L * Depth
2.776 = L * 1
L = 2.776/1 = 2.776 ft.
Hence provide 3 ft width of rectangular section.
Design of R.C.C. Trough slab:-
Clear span = 4.00 m.
Maximum depth of water = 0.30 m.
Unit weight of water = 1000 Kg/cum
Thickness of wearing coat = 2.50 cm.
Unit Weight of RCC slab = 2403 Kg/cum
Considering 1 meter length of slab,
Weight of water = 1000*0.30 = 300 Kg/[Link].
Assuming 12.50 cm slab thickness plus 2.50 wearing coat = 12.50+2.50
=15.00cm.
Weight of RCC slab = (15 * 2403)/100 = 360.45 Kg/[Link].
Weight of wearing coat = (2.50*2403)/100 = 60.07 Kg/[Link].
Total weight = 300+360.45+60.07 = 720.47 Kg/sq m
Hence adopt 750 Kg/ [Link] load for design for safer side.
Effective span = clear span + ½ of effective depth of slab
= 4.00 + ½ *(12.50/100)
= 4.062 m.
i) Maximum +ve B.M at mid span=W l2 / 12 = 750*(4.062)2 / 12
=1031.24 Kg-m.
2
ii) Maximum -ve B.M at support =W l / 16 = 750*(4.062)2 / 16
= 773.43 Kg-m.
iii) Effective depth = d= √(1031.24*100)/(11.50*100)
d= 9.469 cm.
Assuming 12mm Ø bars are used,
Overall depth = D= d + 0.60 + 2.50
= 9.469 + 0.60 + 2.50
= 12.569 cm < 15 cm
Hence O.K.
98
Main reinforcement:
Area of steel required at mid span;
Ast = (1031.24*100)/ 843.70*0.823*9.469)
Ast = 15.680 sq Cm
Providing 12 mm Ø Tor rods,
No. of rods = 15.68/ (╥/4*(1.20)2) = 13.87 rods say 14 number rods.
Spacing of 12 mm Ø rods= (8‘/3.28)/14 = 17 cm c/c
Area of steel required at support;
Asc = (773.43*100) / (843.70*0.82*9.469) = 11.76 [Link].
Providing 12mm Ø Tor rods;
No. of rods =11.76 / (╥/4*(1.20)2) = 10.39 say 11 numbers
Spacing = (8‘/3.28)/11 = 0.221 m c/c say 22 cm c/c
Distribution steel required = 20% of main reinforcement
= 15.68*20/100 = 3.136 [Link].
Providing 8 mm Ø tor steel rods.
No. of bars per meter= 3.136 / (╥/4*(0.80)2) = 6.238 say 7 rods/meter.
99
60) Drawing showing plan, L.S., and section of the RCC rectangular Trough
aqueduct is shown below vide fig. 2.40:
Fig. 2.40– L.S, Plan & Section of the RCC rectangular Trough Aqueduct
100
61) Sample drawing of a Drop-cum-Pipe Culvert proposed is given below
vide fig. 2.41:
Fig. 2.41– Plan , L.S. & section of Drop cum Pipe Culvert
Fig. 2.42–RCC Hume Pipe Aqueduct proposed for canal crossing a stream
102
63) Sample design of an Inlet-weir for canal crossing local
Nala/small stream:
An Inlet weir of CC ([Link]) proportion is proposed from ch. to ch. as the
G.L is just 0.30m below the proposed Canal Bed Level (CBL). Height of Inlet weir
will be d1=FSD+0.10m=0.35+0.10= 0.45m. Inlet weir is proposed on left side of
canal bank so that the water flowing from right side will join the canal water up to
0.45m depth, then after that level, excess water will on left side of inlet weir, for
which solid apron and loose apron are designed as follows:
After design and drawing of the Cross Masonry (CM) & Cross Drainage (CD)
structures like Drop, RCC Hume Pipe Culvert, R.C.C Deck Slab Culvert, super
103
passage, R.C.C Trough aqueduct, measuring devises etc., along left and right canal,
we can prepare the detailed estimates accordingly.
64) Preparation of Data: Readymade revised standard data published by the
State I&CAD Department (i.e., Superintending Engineer, Irrigation Circle, Ranga
Reddy district, Red Hills, Hyderabad) every year is available which can be used for
preparation of abstract estimates.
This data is prepared with basic rates of material without any lead & lift etc.,
Lead statement should be prepared, through which the final rate of material with
lead, lift, seigniorage charges etc., can be arrived.
This final rate can be replaced in the standard data to get the finished item rate
per cum or sq m or R m depending upon the type of item.
1 2 3 4 5 6 7 8 9
10 11 12 13
After arriving at total cost of material, the standard data of each item can be
use and final finished item rate can be calculated. This finished item rate is to be
used to prepare the abstract cost of earthen bund, weir, surplus course, canals, C.D
& C.M structures etc.,
104
65) Table – 2.20 - CROP WISE EXPENDITURE FOR THE YEAR 2001-2002 IN RANGA REDDY DISTRICT
Sl Crop Rainfe Expenditure Average value of gross yield of crops
No. d/ Cash Kind Aver Averag Value Value Toal Net
Irrigat age e price of of income
ed yield per gross fodde inco
per quintal yield r me
Cost of labour Other inputs
acre (Rs.) per
/quin acre
tal (Rs.)
Ploughin Operatio Harvesti Seed Fertil Pestic Total
g/ ns other ng izer ides
cultivatio than
n harvesti
ng
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 Paddy Irrigat
2640 1000 1100 260 1200 700 7000 2500 560 14000 1500 15500 8500
ed
2 Jowar Hybrid
/ HYW 600 450 550 200 400 300 2500 1000 550 5500 1000 6500 4000
ID
Local
rain 550 450 550 90 150 0 1790 500 550 2750 1000 3750 1960
fed
3 Groun Rain
600 700 900 1800 4000 400 5400 500 1500 7500 500 8000 2000
d nut fed
ID 1050
800 900 900 1800 1500 600 6500 1100 1500 16500 500 17000
0
Sd/-
JOINT DIRECTOR OF AGRICULTURE
RANGA REDDY DISTRICT
105
1
1
[Link].
2
Rainfed Groundnut Name of crop
3
246 Ayacut in acre
4
5.00
quintal
Gross yeild in quintal
5
1230.00
(3x4)
6
1500.00 Cost per quintal
Value of produce
7
1845000.00
Name of Work: Formation of M.I tank a/c
(5x6)
Rs.500/ Acre Fodder
66) VALUE OF PRODUCE BEFORE IRRIGATION
500.00
receipt
Value of Fodder
9
123000.00
receipt
Gross value produce
1968000.00
10
106
(7+9)
@Rs. 1800/Ac Cost
442800.00
11
of Seed
@Rs. 1000/Ac Cost
246000.00
12
of fertiliser
@Rs. 400/Ac Cost
98400.00
13
of pesticide
of mannual labour
Total input
1328400.00
15
66) Table – 2.21 - VALUE OF PRODUCE BEFORE IRRIGATION
(11+12+13+14)
(10-15)
JD of
R Dist.
Remarks
17
crop wise
Rain-fed Khariff Groundnut 246 Acres
As per the
2002 of R.R
statement of
Agriculture, R
dist. Issued by
the year 2001-
expenditure for
.
1
1
[Link].
2
I.D Groundnut Name of crop
3
246 Ayacut in acre
4
11.00
quintal
Gross yeild in quintal
5
2706.00
(3x4)
6
1500.00 Cost per quintal
Value of produce
7
4059000.00
(5x6)
@Rs. 500/Acre
Name of Work: Formation of M.I tank a/c
500.00 8
67) VALUE OF PRODUCE AFTER IRRIGATION
Fodder receipt
Value of Fodder
9
123000.00
receipt
Gross value of
4182000.00
10
produce (7+9)
107
@Rs. 1800/Ac Cost
442800.00
11
of Seed
@Rs. 1500/Ac Cost
369000.00
12
of fertiliser
@Rs. 600/Ac Cost
147600.00
13
of pesticide
of mannual labour
Total input
1599000.00
15
(11+12+13+14)
67) Table- 2.22 - VALUE OF PRODUCE AFTER IRRIGATION
2583000.00
16
(10-15)
Remarks
17
1
1
[Link].
2
HYV Jawar Name of crop
IRRIGATION
3
66.7 Ayacut in acre
4
10.00
quintal
Gross yeild in quintal
5
667.00
(3x4)
6
68) VALUE OF PRODUCE AFTER
Value of produce
7
366850.00
(5x6)
8 Rs.1000/Acre Per
Name of Work: Formation of M.I tank a/c
1000.00
Acre Fodder receipt
Value of Fodder
9
66700.00
receipt
Gross value produce
433550.00
10
108
(7+9)
@Rs. 200/Ac Cost of
13340.00
11
Seed
@Rs. 400/Ac Cost of
26680.00
12
fertiliser
@Rs. 300/Ac Cost of
20010.00
13
pesticide
@Rs. 1600/Ac Cost
106720.00
14
of mannual labour
Total input
166750.00
15
(11+12+13+14)
68) Table – 2.23 - VALUE OF PRODUCE AFTERE IRRIGATION
266800.00
16
(10-15)
Remarks
17
69) Table-2.24 - Sample B.C. ratio calculations are shown below:
Name of work: Formation of Minor Irrigation tank across Batti vagu near Indur
(V), Peddemul, (M), [Link]
BENEFIT COST RATIO
A
Benefit
Before Irrigation
Amount in Rs.
I(a) Estimated value of agriculture produce 1728000
(b) Cost of cultivation to the economy 1166400
('C) Net value of Agriculture produce (a-b) 561600
After Irrigation
At 10% At 5%
(i) Interest on capital outlay 807100 403550
109
70) Certificates:- Certificates to be enclosed to the estimate are as follows:
Lead certificate.
Seiniorage charges certificate.
L.R.R. & U.R.R certificate.
Certificate for check measure of levels.
Certificate of inspection of site by the EE. (Copy of inspection report to be
enclosed).
Certificate of blasting.
Certified that the Seigniorage charges are provided in the data of the estimate vide
[Link]. No. 198, Industries & Commerce Department, Dated 13-08-2009.
…………………………………..
“Counter Signed”
110
Name of work:- Formation of minor irrigation tanks across
…………………………………..
“Counter Signed”
………………………………..
111
Name of work: - Formation of minor irrigation tanks across
………………………………..
Certified that I have inspected the quarries of all material to be used for construction
of this M.I. tank on dt. ………………..and verified the availability, adequacy and
leads (distance) of the material provided in the estimate and found correct.
Certified that the minor irrigation tank proposal under consideration duly involving
utilization of …………M cft. shall not effect lower riparian right and upper riparian
rights.
112
Name of work: - Formation of minor irrigation tanks across
………………………………..
CERTIFICATE OF BLASTING
Certified that the stone used for masonry and metal is to be provided by blasting.
113
71) List of drawings to be enclosed to the DPR/ Detailed estimate
of M.I. Tank:-
4) Drawings showing the plan, L.S and C.S of the alignment of the bund with
details of sub-soil strata available in trial pit and depth of C.O.T proposed.
8) L.S, Plans & C.S‘s of all C.D & C.M structures of L.F & R.F canals.
9) Block levels/ net levels on upstream & downstream of weir for obstruction
removal.
10) Quarry map showing the proposed M.I. tank with distance from borrow
area of material.
114
72) The DPR/Estimate of Minor Irrigation tank consists of the
following items:
2) General Abstract
A – Preliminaries ……………… Rs.
B – Land acquisition ………… Rs.
C – Works
(i)Earthen Bund ……… Rs.
(ii)Weir ……….. Rs.
(iii)Sluices ……….. Rs.
(iv) Canals ………. Rs. _______
Total ……….. Rs. _______ . ………Rs.
D- Miscellaneous items:
Sub-total Rs.
115
3) B.C. ratio calculations
4) Input & Output statements of crops.
5) Basic data of crop input & Output before & after irrigation which is
obtained from Agriculture Department.
6) Details of L.A. required for the scheme.
7) Abstract estimate of earthen bund
8) Abstract estimate of surplus weir including surplus course.
9) Abstract estimate of Head Sluices.
10) Consolidated abstract estimate of L.F. canal
11) Consolidated abstract estimate of R.F. canal
12) Proposal sheet
13) Statement of last 40 years annual rainfall data.
14) Statement of last 40 years Monsoon rainfall data.
15) Design of weir
16) Design of Head Sluices
17) Design of L.F. & R.F. canal
18) Design of C.D. & C.M. structures of L.F. & R.F. canals
19) Stability calculations for weir
20) Stability calculation for Abutment & Returns.
21) Monthly Monsoon data for last 40 years.
22) Yield distribution.
23) Capacity table
24) Demand/Crop water requirement tables
25) Regime table
26) Detailed estimate of earthen bund
27) Detailed estimate of surplus weir & Surplus arrangement.
28) Detailed estimate of Head sluices
29) Detailed estimate of R.F. canals and C.D & C.M structures
30) Detailed estimate of L.F. canals and C.D & C.M structures
31) Lead statement.
32) Datas
33) Certificates
34) Index map in Survey of India / Topo sheet
35) L.S. of bund
116
36) Survey plan of bund & capacity contours with Trial Pits details.
37) C.S. of earthen bund at different chainages.
38) L.S. and Plan of surplus weir
39) C.S. of weir
40) L.S, C.S. and Plan of Head Sluices
41) L.S, Plan & Cross section of all C.D & C.M structures of L.F & R.F canals.
42) Plan showing entire surplus course arrangements.
44) Quarry map showing quarry of each materials with distance.
45) Block levels / Net levels on U/S & D/S of weir for obstruction removal
required.
117
73) A sample Index Map vide fig. 2.44 is shown below:
118
74) The following check slips are to be filled up & enclosed to the
estimate.
CHECK LIST FOR APPRIASAL OF PROJECTS
1 Name of the Tank :
2 Location :
i)River :
ii)Village,Taluka,Dist & State :
:
3 Year of Completion :
4 Details of Ayacut: :
i) Gross Cornmand Area(Ha :
ii) Culturable Command Area Ha) :
iii)Annual Irrigation ( Ha) :
5 Type of Scheme: :
Natural/Man made Storage/Lift etc. :
6 Physical details :
A- Dam :
i)Height (m) :
ii) Length (m) :
iii) Type:(Gravity/Area/Rock fill/Earth Fill
:
etc.)
B-Surplusing Arrangement: :
i)Spillway Length (m) :
ii) Gate/Un-gated :
a)Size of Gates :
b)No of Gates :
c)Total discharging Capacity :
C-Storage: :
i)DSL (m) :
ii)DSL capacity (MCM) :
iii) FTL (m) :
iv)FTL Capacity (MCM) :
v)Water Spread Area IN Ha :
D-Distribution System :
Length Discharge Command
a) In case of Gravity :
in km Cumecs Area HA
I)Main Canal (feeding canal) :
II) Secondary system in m :
b) In case of Lift :
I )No & Capacity of the pump :
II )Conveyance system (Length & Capacity) :
E-Canal Structures (No.) :
I )Cross Drainage Works :
119
II )Road Bridges :
III )Falls :
IV )Outlets :
V )Cross Regulator :
VI )Head Regulator :
VII )Silt Excluder (if any) :
VIII )Others (inlet) :
7 Hydrology / Water Availability :
I) Average Annual Rainfall (mm) :
II) Net Catchment area ([Link]) :
III) Average annual runoff (Ha-m)
:
(Whether gauged or un-gauged)
IV) Monsoon Rainfall in mm :
V) Non Monsoon Rainfall in mm :
VI) Peak flood (cumecs)
for un-gauged catchment, method for small :
catchment may be used
Ground water availability and its
8 :
conjunctive use in
9 Types of soil in the command : Red soil
10 Cropping pattern (Existing) :
Name of
Name of the season Existing Proposed
Crop
Paddy
A Khariff
(Ha)
Maize
(Ha)
Name of
B Rabi Existing Proposed
Crop
Paddy
(Ha)
Maize
(Ha)
Adopted Crop Water Requirement (as
11 approved by dept. of Agriculture) for this :
project
Name of Crop : Water Requirement (Cum)
Paddy :
Maize :
12 Yield (qntl. / ha) :
Name of Crop : Existing Proposed
Paddy :
Maize :
120
Component cost(%) of tank capacity
13 :
enhancement to the total cost
14 Benefit Cost Ratio :
15 Details of existing / proposed WUA :
Whether the proposal has been approved
16 :
by the state
:
17 Maps :
I) Index maps showing the location of the
project, its catchment area and other :
existing
II) Project map showing project features,
:
command area and distributory system
121
75) Proforma Check List for technical sanction.
ANNEXURE
CHECK SLIP TO ACCOMPANY THE ESTIMATE FOR CIVIL WORKS
FOR TECHNICAL SANCTION
1 Name of work:
2 Cost of work
Provision in the Project Est.
3
A) Reference to Admn. Approval
4 Whether the following enclosures are sent
a) Report in the form as prescribed in Govt. Memo
No.1514/GI.1.79-1,Dt.21-11-1979
b) Abstract estimate as prescribed in
CE/G1/Circular
No.F4/7071/79-74,Dt.01-11-1979
c) General Index Plan (s) and typical Drawings
showing
the general features of the work.
Designation of highest officer who inspected and
5
the date of inspection.
a) Suitability of Site
b) Suitability of Foundations
c) Adequacy of design suiting local condition
d) Soils and materials qualitative and quantitative
and leads
e) Soils classification of trail pits Up to hard rock
level
f) Abnormal dewatering
g) Land acquisition
h) Forest clearance
i) Availability of funds
j) Any other vital characteristics
Whether the L.S. Provisions is in accordance with
6
CE/G1/Cir/F-4/7071/79-5,Dt.10-11-1979
Whether provision for LI & LA charges is shown
separately as Lump-sum as per GO
7
1624/PWY/Dept
Dt.2-11-1969
Whether provision for LS and contingencies is in
8
accordance with GO 385, Dt.25-10-1979
a) In case of embankment whether Provision for
consolidation by power Roller is made
9 Proposed date of commencement of works
10 Proposed date of completion of work
122
76) Scales of Drawings for Plans, Longitudinal Section (L.S), Cross
Section (C.S) and side views of different components of Minor
Irrigation tank should be drawn to following scale:
1) Bund:-
i) L.S. Horizontal: 1Cm = 20 m
Vertical : 1 Cm = 1 m
ii) C.S. Horizontal: 1Cm = 1 m
Vertical : 1 Cm = 1 m
iii) Foreshore Plan (contours) Horizontal} 1 Cm = 20 m
& Vertical}
2) Weir:-
i) Plan & L.S. Horizontal: 1Cm =
20 m
Vertical : 1 Cm = 1 m
3) Sluice:-
i) L.S , Plan , C.S & side view Horizontal} 1 Cm = 20 m
& Vertical}
4) Canals:-
i) L.S. Horizontal: 1Cm = 20 m
Vertical : 1 Cm = 1 m
123
77) Different types of surplus arrangements that can be provided
for Minor Irrigation tanks are as follows:
1) Free over fall weir:- This is located where the length of discharge is
restricted, foundations are good and fall of water is adequate.
2) Submerged weir:- This is suitable where sufficient length of discharge is
available, the country is gently sloping and soils are not hard.
3) Broad crested weir:- This is provided where head of discharge is
between 0.50 m to 0.90m.
4) High Coefficient weir:- This is provided where head of discharge is more
than 0.90 m.
5) Flush escape or Masonry Sill (MS) bye wash:- This is provided where
the length available is great and where hard soils (Strata) is available at
or above F.T.L.
I) The formula for calculating length of M.S. bye wash weir is as follows:
Q= 2.67* L* H3/2 where, Q= MFD in Cusecs
L= length in feet
H= head of discharge in feet
II) The formula for calculating length of F.O.F weir is as follows:
Q= 3.33*L*H3/2, Where Q= MFD in Cusecs.
L=Length of weir in ft.
H=head of discharge in ft. (We have to
assume it)
Width of apron= 2*√F*H +H+3, where F=ht. of bund, H=head of
discharge.
Thickness of apron= √F+H
Base width of body wall= (F+H)/√2.5
Top width of body wall= 2 ft. –or- 0.60 mt. For small MFD‘s from
small catchment areas and head of discharge between 0.50 m to 0.90
m we provide F.O.F weir (Broad Crested weir).
III) The formula for calculating length of High Coefficient (H.C.) weir is as
follows:
Q=3.90*L*H3/2 for CRS masonry body wall;
Q=4.10*L*H3/2 for CC body wall.
Where Q= MFD in Cusecs.
L=Length of weir in ft.
H=head of discharge in ft. (We have to
assume it)
IV) Submerged weir ( suitable in B.C soils):
Q= 3.11 * L* H3/2 Where Q= MFD in Cusecs.
L=Length of weir in ft.
H=head of discharge in ft. (We have to assume it)
124
78) Emperical formula for calculating Maximum Flood Discharge
from a catchment basin there are several formulas. The
formulas generally used are as follows:
2) Dicken‟s formula:
3) Ryve‟s formula:
5) Fanning‟s formula:
125
79) Design of an Anicut and Feeder Channel
a) Rivers and canals in earth below the average in fair order= 0.030
b) Rivers and canals in earth obstructed by detritus and in bad order and
regime=0.035
c) Rivers and canals in earth obstructed by detritus and in rock cutting =
0.035
d) Torrets encumbered with detritus =0.05
Number of flood days are calculated using Table-2.25 based on daily rainfall:
Table – 2.25 – No. of Flood days
Daily Rainfall in inches Number of flood days
½‖ to ¾‖ 1‖ flood day
¾‖ to 1‖ ½‖ flood day
1‖ and above 1‖ flood day
126
80) CONVERSION TABLE
I. Linear
1 inch = 25.40 millimeters
1 foot = 12 inches
= 304.80 millimeters
III. Volume
1 cubic foot = 0.0283 cubic meter
= 6.2288 gallons
127
1 cubic meter = 35.3147 cubic feet
= 219.969 gallons
= 1000 liters
128
GUIDE LINES
(III) FOR TAKING UP DETAILED SURVEY AND PREPARATION OF
DETAILED
ESTIMATE OF RRR OF WATER BODIES AS PER GoI NORMS AND
REHABILITATION OF M.I. TANKS UNDER ―MISSION KAKATIYA‖
PREPARED BY
MOHD. MAHBOOB HUSSAIN, [Link].,
EXECUTIVE ENGINEER,
I & CAD DEPARTMENT,
GOVERNMENT OF TELANGANA,
HYDERABAD-82
2016
129
81) BRIEF GUIDELINES FOR THE CONTINUATION OF SCHEME ON
REPAIR, RENOVATION & RESTORATION (RRR) OF WATER
BODIES IN XIIth PLAN EFFECTIVE FROM OCTOBER,2013
(These will change from time to time)
I. INTRODUCTION:
130
Plan. The remaining amount of Rs. 3765 crore is to be arranged by State
Governments themselves. The States would also be encouraged to seek
external assistance for funding of RRR of Water Bodies.
2. Main objectives of the scheme:
(i) Comprehensive improvement and restoration water bodies thereby
increasing tank storage capacity.
(ii) Ground Water Recharge.
(iii) Increased availability of drinking water.
(iv) Improvement in agriculture/horticulture productivity.
(v) Improvement of catchment areas of tank commands.
(vi) Environmental benefits through improved water use efficiency; by
promotion of conjunctive use of surface and ground water.
(vii) Community participation and self-supporting system for sustainable
management for each water body.
(viii) Capacity Building of communities, in better water management.
(ix) Development of tourism, cultural activities, etc.
(i) The central assistance will be in the form of grant which will be 90%
of project cost in case of Special Category States (North-Eastern
States including Sikkim, Himachal Pradesh, Jammu & Kashmir,
Uttarakhand and undivided Koraput, Bolangir and Kalahandi (KBK
districts of Orissa) as well as projects lying in desert development
programme(DDP),drought prone area/tribal area/Naxal affected
area and Central assistance of 25% of project cost in case of Non-
Special Category States/areas. The balance cost of the project as
State share (10% in case of Special Category States/areas and 75%
in case of Non-Special Category States/ areas) is to be arranged by
the State Governments themselves.
(ii) The works of RRR of water bodies spilling over from XIth Plan would
be funded as per XIth Plan guidelines.
(iii) The proposals which satisfy the following criteria should be eligible
for funding:
133
ix. Implementation schedule & corresponding requirement of funds; details
of arrangement for monitoring & evaluation and arrangement for use and
maintenance of the restored water bodies.
x. The checklist at Annexure I should be the part of DPR.
At the water body level, the Detailed Project Reports (DPRs) would be
prepared and works would be implemented by Water Users‘ Association (WUA) /
Local Panchayat / A government agency identified by the District Level
Implementing Agency (DLIA). The dispute related to implementation of water
body could be referred to DLIA for resolution. The implementation plan of the
project will be placed before the Gram Sabha and its Cooperation will be solicited
by timely completion of the project. The Activity Mapping in relation to the role
of Panchayat in the implementation of the scheme is at Annexure II. The WUA
would also earn revenues by charging for its services from its members and
build up a corpus for maintaining and managing the water bodies over time. The
Non-Government Organizations (NGOs) may also play a role in implementation,
planning and execution of the scheme subject to State Government‘s decision.
The MoWR will coordinate the programme at the central level through
Central Water Commission. The inclusion of the Water Bodies for assistance
under the Scheme would be approved by the Empowered Committee of MoWR
under the Chairmanship of Secretary/Special Secretary/Additional Secretary
(WR). Constitution of the Committee is at Annex.-III. A flow chart indicating
134
the implementation arrangement is at Annex.-IV. The role of the CWC / MoWR
will be to:
(i) At the water body level, the DPRs of the water bodies are to be prepared
by WUA / Local Panchayat / a Government agency identified by DLIA.
The Detailed Project Reports (DPRs) will then be forwarded to District
Level Implementation Agency (DLIA) for onward transmission to the
State Level Nodal Agency (SLNA).
(ii) The proposals received by DLIA would be scrutinized, included in
the District Plan and forwarded to State Level Nodal Agency (SLNA) for
putting up to State TAC.
(iii) After approval of the DPR by state TAC, the States will submit DPRs to
the field office of Central Water Commission, which in turn will take
further necessary action for release of funds under the scheme.
Note:- Check list as shown in Annexure-I is to be filled up and enclosed to the
DPR of RRR of water bodies under XIIth Plan of Government of India.
135
82) CHECK LIST FOR APPRAISAL OF PROJECTS
1 Name of the Tank :
2 Location
i) River :
ii) Village, Taluq, Dist., :
State
3 Year of completion :
4 Details of Ayacut:
i)Gross Command Area(Ha) :
ii)Culturable Command Area(Ha) :
iii)Annual Irrigation (Ha) :
5 Type of Scheme:
Natural/Man made storage/Lift :
etc.,
6 Physical details
A. Dam
i)Height (m) :
ii)Length (m) :
iii)Type:(Gravity/Rock fill/Earth fill :
etc.)
B. Surplusing Arrangement: :
i)Spillway length (m) :
ii)Gated/Un-gated :
a) Size of Gates :
b) No. of Gates :
c) Total discharging capacity :
C. Storage:
i)DSL (m) :
ii)DSL capacity(MCM) :
iii)F.T.L (m) :
iv)F.T.L capacity (MCM) :
v)Water Spread Area in Ha :
D. Distribution System
a)In case of Gravity : Length in Discharge Command
Km Cumecs Area Ha.
I Main canal (feeding Canal) :
II Secondary system :
b) In case of Lift :
I No. and capacity of pumps :
II Conveyance system (Length & :
capacity)
E. Canal Structures (No.) :
I Cross Drainage Works :
136
II Road Bridges :
III Falls :
IV Outlets :
V Cross Regulators :
VI Head Regulator :
VII Silt Excluder :
VIII Others (Inlet) :
7 Hydrology / Water Availability
I Average Annual Rainfall (mm) :
II Net Catchment area (Sq. Km) :
III Average annual run-off (Ha-m) :
( Whether gauged or un-Gauged)
IV Monsoon Rainfall in mm :
V Non-Monsoon Rainfall in mm :
VI Peak flood (cumecs) for un- :
gauged catchment, method of
small catchment may be used
8 Ground water availability and its :
conjunctive use
9 Type of soil in the command :
10 Cropping pattern (Existing)
Name of the season Name of Existing Proposed
A Khariff crop
137
15 Details of existing/ proposed WUA :
16 Whether the proposal has been :
approved by state govt.
17 Maps
I) Index maps showing the :
location of the project, its
catchment area and other existing
II) Project map showing project :
features, command area and
distributor system.
138
Annexure- I
83) Check List for preparation of DPRs:
Sl. Item Yes
No. /No
1. Whether census of water bodies completed and assigned unique code
number?
2. Whether only water bodies having minimum water spread area of 5 hectare
in rural areas and water spread area of 2-10 hectare in urban areas
included?
3. Are private water bodies included in the DPR?
4. Whether Water Users‘ Associations and Panchayats have been associated
for selection of water bodies and capacity building?
5. Whether water bodies are included in the district plan?
6. Whether rain fall data for last 10 years, ground water level, land
use pattern, water quality situation in the water bodies and
adjoining areas have been included?
7. Whether details of original CCA / present CCA / CCA expected after
rejuvenation have been included?
8. Whether details of original storage capacity/present storage capacity and
storage capacity expected after rejuvenation have been included?
9. Whether maps of catchment and command are enclosed?
10. Whether latest SOR adopted for preparation of cost estimates?
11. Number of people benefitted
12. Number of farmers of SC/ST community benefitted
13. Whether benefit cost ratio has been incorporated?
14. Whether implementation schedule and corresponding requirement of funds,
details of arrangements for monitoring and evaluation has been included?
15. Whether convergence with IWMP or other schemes have been taken into
account?
16. Whether District Level Implementing Agency has been identified?
17. Whether State Level Nodal Agency has been identified by the State
government?
18. Whether Technical Advisory Committee has been constituted
with Members from Central Water Commission and Central Ground
Water Board?
19. Whether objective of the proposals is mentioned?
20. Whether details of present status of water bodies with reasons for
deterioration & likely benefits (creation of additional potential, increase in
agriculture) included?
21. Whether the categorization of Projects - Special Category/DP/DDP/TA/
DPA/ Naxal affected area or Non-Special Category is mentioned?
22. Whether detailed Work Programme & corresponding Detailed Financial
Programme attached?
23. Whether detailed calculation of B.C Ratio using latest authenticated
published data (Quantity and Rate of yield) from the Ministry of gricultures,
GoI has been considered?
24. Whether detailed of Proposed Programme of Monitoring & Evaluation (both
Physical & Financial Programme) is given?
139
84) Table – 3.1 - SAMPLE HYDROLOGICAL STUDIES UNDER THE
SCHEME “REPAIR, RENOVATION AND RESTORATION OF
WATER BODIES” AS PER CWC, NEW DELHI NORMS
140
27 2001 200.40 260.20 257.00 104.80 78.00 900.40 955.90
28 2002 197.00 86.20 430.40 36.40 72.80 822.80 955.10
29 2003 109.40 473.60 544.80 195.60 132.60 1456.00 945.60
30 2004 85.50 283.00 317.20 86.80 75.20 847.70 934.40
31 2005 148.40 431.80 150.40 448.20 66.00 1244.80 900.40
32 2006 89.60 280.00 414.60 281.00 5.00 1070.20 847.70
33 2007 121.80 251.20 195.00 173.40 82.60 824.00 824.00
34 2008 211.20 281.80 518.80 294.20 46.00 1352.00 822.80
35 2009 47.40 225.60 150.00 54.60 35.80 513.40 774.20
36 2010 411.20 345.20 371.20 306.00 115.60 1549.20 742.10
37 2011 139.60 328.00 157.20 88.80 60.60 774.20 668.20
38 2012 110.00 419.10 340.80 283.20 133.20 1286.30 578.80
39 2013 182.40 464.80 237.20 172.40 139.80 1196.60 540.20
40 2014 17.20 276.20 295.20 265.20 137.80 991.60 513.40
Total = 43184.70
Average monsoon rainfall= 43184.70/40= 1079.618
141
Table – 3.2 - Monsoon Rainfall data for month wise in descending order
Rainfall in mm
Rainfall in
S.
Year June July August Sept. Octo. Total Descending
No
order
1 1975 411.20 846.20 672.20 448.20 432.90 2810.70 2810.70
2 1976 394.40 527.30 554.10 356.00 185.00 2016.80 2016.80
3 1977 349.60 514.60 553.80 339.40 175.50 1932.90 1932.90
4 1978 329.30 503.00 544.80 325.00 161.30 1863.40 1863.40
5 1979 273.30 478.00 518.80 306.00 146.80 1722.90 1722.90
6 1980 261.00 473.60 479.10 294.20 139.80 1647.70 1647.70
7 1981 258.40 464.80 441.00 283.20 137.80 1585.20 1585.20
8 1982 249.30 438.80 430.40 281.00 133.20 1532.70 1532.70
9 1983 241.80 431.80 414.60 271.00 132.60 1491.80 1491.80
10 1984 211.20 419.10 408.40 265.20 131.10 1435.00 1435.00
11 1985 200.40 405.50 373.30 261.20 130.20 1370.60 1370.60
12 1986 197.00 392.90 371.20 237.70 115.60 1314.40 1314.40
13 1987 197.00 392.50 367.20 235.20 82.60 1274.50 1274.50
14 1988 195.30 365.80 358.30 205.60 81.20 1206.20 1206.20
15 1989 182.40 356.20 357.00 204.60 80.20 1180.40 1180.40
16 1990 160.20 351.70 347.60 204.30 78.00 1141.80 1141.80
17 1991 157.00 345.20 340.80 203.50 77.60 1124.10 1124.10
18 1992 150.60 328.00 335.70 195.60 77.40 1087.30 1087.30
19 1993 148.40 303.10 321.90 181.80 76.00 1031.20 1031.20
20 1994 144.50 286.50 317.20 178.90 76.00 1003.10 1003.10
21 1995 139.60 283.00 309.40 175.60 75.20 0982.80 982.80
22 1996 138.10 281.80 308.60 173.40 72.80 0974.70 974.70
23 1997 135.40 280.00 295.20 172.40 72.60 0955.60 955.60
24 1998 130.00 278.20 292.20 154.40 69.60 0924.40 924.40
25 1999 121.80 276.20 284.50 130.00 66.00 0878.50 878.50
26 2000 121.00 260.20 270.00 123.60 63.50 0838.30 838.30
142
27 2001 114.30 254.20 257.00 110.40 60.60 0796.50 796.50
28 2002 110.00 251.20 254.20 104.80 46.00 0766.20 766.20
29 2003 109.40 244.70 237.20 99.40 45.20 0735.90 735.90
30 2004 89.90 238.00 225.20 97.00 44.00 0694.10 694.10
31 2005 89.60 237.80 195.00 94.40 36.20 0653.00 653.00
32 2006 86.20 226.40 181.70 93.90 35.80 0624.00 624.00
33 2007 85.50 225.60 157.20 90.00 18.60 0576.90 576.90
34 2008 83.70 224.70 150.40 88.80 17.80 0565.40 565.40
35 2009 83.20 214.20 150.00 86.80 12.00 0546.20 546.20
36 2010 73.90 193.00 132.90 69.20 11.20 0480.20 480.20
37 2011 70.60 179.00 132.20 65.60 9.50 0456.90 456.90
38 2012 64.60 152.20 127.60 54.60 5.00 0404.00 404.00
39 2013 47.40 136.50 125.00 36.40 4.20 0349.50 349.50
40 2014 17.20 86.20 80.50 25.00 0.00 0208.90 208.90
Total = 43184.70
Average annual rainfall = 999.510
75% dependable year = 30th
75% dependable rainfall = 694.10
143
Table – 3.3 - Non -Monsoon Rainfall data for 2012-13 & 2013-14
Edulla Vagu Cheroo under the Scheme
"Repair, Renovation and Restoration of Water Bodies"
Rainfall in mm
S.
Year Nov Dec Jan Feb March April May
No
1 2012-13 196.20 0.00 0.00 21.80 0.00 17.80 12.20
2 2013-14 19.00 0.00 0.00 0.00 0.00 0.00 206.80
Calculation of Effective Rainfall 2012-13
S.
Description Nov Dec Jan Feb March April May
No
1 Rainfall in mm 196.20 0.00 0.00 21.80 0.00 17.80 12.20
2 Percentage rainfall 79.11.% 0.00.% 0.00.% 8.79.% 0.00.% 7.18.% 4.92.%
Disribution in
3 inches 7.72 0.00 0.00 0.86 0.00 0.70 0.48
(196.2/25.4=7.72)
Effective Rainfall
4 (75% Dep.) in 5.79 0.00 0.00 0.64 0.00 0.53 0.36
inches(7.72*0.75
Calculation of Runoff(2012-13) 8.25 Sq. Miles
S.
Description Nov Dec Jan Feb March April May
No
1 Rainfall in inches 7.72 0.00 0.00 0.86 0.00 0.70 0.48
Cumulative rainfall
2 7.72 7.72 7.72 8.58 8.58 9.28 9.76
in inches
Cumulative
3 yield/sq. mile in M 0.352 0.352 0.352 0.477 0.477 0.605 0.701
Cft
Cumulative
yield/sq. mile in M
4 2.904 2.904 2.904 3.935 3.935 4.991 5.783
Cft for entire
catchment Area
Monthly runoff in
5 0.082 0.082 0.082 0.111 0.111 0.141 0.164
M Cum (w)
144
Distribution in
3 0.75 0.00 0.00 0.00 0.00 0.00 8.14
inches
Effective Rainfall
4 (75% Dep.) in 0.56 0.00 0.00 0.00 0.00 0.00 6.11
inches
Calculation of Runoff 8.25 Sq. Miles
S.
Description Nov Dec Jan Feb March April May
No
1 Rainfall in inches 0.75 0.00 0.00 0.00 0.00 0.00 8.14
Cumulative rainfall
2 0.75 0.75 0.75 0.75 0.75 0.75 8.89
in inches
Cumulative yield
3 0.001 0.001 0.001 0.001 0.001 0.001 0.523
/sq. mile in M cft
Cumulative
yield/sq. mile in M
4 0.008 0.008 0.008 0.008 0.008 0.008 4.315
cft for entire
catchment Area
Monthly runoff in
5 0.0002 0.0002 0.0002 0.0002 0.0002 0.0002 0.1222
M Cum (w)
145
Inflow/ Runoff Calculations for
Edulla Vagu Cheroo Under The
Scheme "Repair Renovation and Restoration of Water Bodies"
146
85. a) Sample yield calculations are shown below:
Yield Calculation
1. Location of the scheme: ………………………………………..
2. Catchment Area Details:
Free catchment Area : 2.84 Sq Miles
Combined Catchment Area : 0 Sq Miles
Total Catchment Area : 2.84 Sq Miles
3. Rain Gauge Station data:
Influencing R.G.S : PINAPAKA
As per 40 years record from 1975 to 2014
Average Monsoon Rainfall : 1079.62 mm or 42.505‖
Rainfall @ 75 % Dependability: 934.40 mm or 36.787‖
4. Yield Particulars:
The yield per Sq miles for the C.A classified as ½Good + ½Average
for the rainfall @ 75% dependability as per Strange‘s Table :
Considered for yield calculation (Free C.A +½ of Combined C.A) = 2.84 Sq
miles
@ 75% dependable rainfall = 36.79‖
147
85. b)Sample M.F.D calculations are shown below:
Calculation of Maximum Flood Discharge (M.F.D)
Catchment area of the scheme= 2.84 Sq miles or 7.356 Sq km.
1. Maximum Flood Discharge as per Dicken‟s formula:
Discharge = Q = CM3/4 where, C= Constant ranging from 900 to 1200
Generally we adopt 1100 value for small catchments
¾
Q= 1000*(2.84) = 1100*2.1877 = 2406.47 Cusecs or 68.145 Cumecs.
Hydrological soil group is red soil.
2. M.F.D calculation as Rational Method:
Step-I
Length of stream (L) = 4300
Width of catchment area (W) = 2000
L / W = 4300/2000 = 2.150 2.15:1 < 4:1
Step-II
Time to reach peak (Tp) = 0.48* (A)0.28 = 0.48* (7.356) 0.28 = 0.839 hr.
Step-III
Table – 3.5 – Table of run-off curve number for hydrological soil group.
Land use pattern % C.A. Curve % C.A* Curve number
number
Cultivated crop 60 75 4500
Cultivated Paddy 10 95 950
Forest/ Garden 10 50 500
Waste Land 20 80 1600
Total 100 7550
Weighted Curve Number= 7550/ 100 = 75.50, Adopt 75 curve number.
Step-IV
Value of ―P‖ i.e., maximum rainfall in a day = 180 mm
The value of Q read from Graph for Red soil for P=180 mm & Curve
number 75 is 100.
Step-V
M.F.D is calculated using equation, q= 0.146*A*Q / Tp
= (0.146*7.356* 100)/0.839
= 128.00 Cumecs
Adopt higher M.F.D of 128.00 Cumecs for design of weir.
Now check the adequacy of the existing weir using M.F.D calculated
above.
148
86) Checking the adequacy of existing surplus weir
149
87) Fixing of dead storage level of M.I. tank:
Sample calculations:
Catchment Area : 1.10 Sq miles.
Lowest reservoir contour : 138.00 M.
Contour interval : 0.50 M.
Design life of the project in year : 50 years
(I) As per Inglis Formulae:
For silt accommodation: S = C* N * A3/4
23
Where, S = Total silt accumulation in acre-ft.
C = 1.70 a constant
N = Life of the project in years.
A = Catchment area in sq. miles.
Total silt accumulation S = 1.70*50*(1.10)3/4/23= 3.96 acre-ft. in
design life
= 0.172 M Cft.
150
NAME OF WORK: DPR OF PEDDA CHEROO
UNDER THE SCHEME "REPAIR RENOVATION AND
RESTORATION OF WATER BODIES"
88) Table – 3.6 Proforma for the calculation of Benefit Cost Ratio
(BCR) as per CWC norms.
Total Cost of Rs 93.70 Lakh
CCA 133.20 Ha
SI. Before After
Description
No. Modernization Modernization
A GROSS RECEIPTS
1)Gross value of farm produce 80.74 124.71
2)Dung receipts (as 30% of the fodder
3.63 3.74
expenditure)
3)Total (A): gross receipt (1+2) 84.37 128.45
B EXPENSES
1)Expenditure on seeds 1.59 2.47
2)Expenditure on manure etc., 16.46 26.48
3)Expenditure hire labour (Human and
14.52 23.99
bullock)
4)Fodder expenses (as per percentage of
12.11 12.47
gross value of produce 15%, 10% of A1)
5)Depreciation on implementation 2.7%
2.18 3.37
on item A. 2.7% on item A1
6)Share and cash rent 5% on item A1. 3%
4.04 3.74
item A1
7)Land revenue 2% on item A1 1.61 2.49
8)Total B: Expenses (1 to 7) 52.52 75.02
C NET VALUE OF PRODUCE
1)Total gross receipts (Total A3) 84.37 128.45
2)Minus total expenses (Total B8) 52.52 75.02
3)Net value with project [C] : (1-2) 31.86 53.43
D ANNUAL AGRICULTURAL BENEFITS
1)Net value with project (C3) 53.43
2)Minus net value without project (C3) 31.86
3)Net amount benefit (D) : (1-2) 21.58
151
Other net annual benefits due to aqua-
culture including pisiculture, drinking &
industrial water, hydro-power generation,
E animal husbandry, catchment are
treatment chargeable to project, canal
bank plantation, reservoir periphery
afforestation etc.,
F TOTAL NET ANNUAL BENEFITS 21.58
G ANNUAL COSTS
Interest on capital @ 4.5% (Estimated
1 cost of the project including cost of land 4.22
development @ Rs…………. per Ha)
Depreciation of the project @ 4% of cost
2 of 3.75
project for 25 years life of project.
Annual operation and maintenance
3 charges 1.57
@ Rs.1175 per Ha of CCA
Maintenance of head works @ 1% of its
4 0.00
cost(Rs 173.05 Lakh)
152
89) The works proposed under RRR of water bodies under XII th
plan and “Mission Kakatiya” are as follows:
a) De-silting of fore shore area (tank bed side) of Minor Irrigation tank.
b) Improvement to earthen bund to bring it to the M.I. standards.
c) Repairs to damaged Weir, Apron, Abutments, Wing wall and Returns as
per requirement.
d) Repairs to sluices of tank as per requirement.
e) Restoration of Feeder Channel to the tank
f) Improvements / repairs to canals and providing C.C. lining / Guide walls in
vulnerable reaches as per requirement. Repairs to CD & CM structures.
a) De-siltation
De-siltation is an important work to restore/increase the original capacity
of irrigation tank. This work is for removing accumulated silt in tank bed,
clearing foreshore area encroachments. To decide upon the quantum of
silt that can be removed from tank bed, the following procedure can be
adopted:
a. Preliminary investigation including collection of statistics regarding
tank bed level and other aspects are done.
b. Net levels at every 15m interval are to be taken in tank bed/foreshore
area to decide the quantum of silt that can be removed.
c. Trial pits up to impermeable layer of the tank bed may be taken at
required intervals to measure quantity of de-siltation.
d. The silt removed is to be got tested for its suitability to use in
agriculture farms to improve fertility.
Table – 3.7 - Sample calculation of silt quantity in bed of tank is shown below:
Sill level=139.20, Bed area= 15.92 Acre
[Link]. Level of Area in S Area in Avg. proposed Quantity in
Contour qm between depth of silt in Cum.
contours in S m.
qm.
1 139.20 6992 - - -
2 139.50 13444 6452 0.35 2258.20
3 140.00 16785 6341 0.30 1902.30
4 140.50 38772 18987 0.35 6645.45
Total 31780 Total Qty. 10805.95
1 0.15m depth 31780 0.15 4767.00
silt Qty. for
disposal as
un-use-full
with 1 Km
lead
2 Balance silt 6038.95
Qty.
153
b) Improvement/Rehabilitation of Earth bund/Dam
Detailed survey for existing earthen bund:
Fig. 3.1 – Profile of bund section over the existing bund section
154
(3) Capacity Survey:-
There are various methods for conducting capacity survey of tank. Generally the
following types of survey are conducted:
(a) Contour survey (Stadia or Tachometry survey)
(b) Block level survey
Before taking up capacity survey, Lowest Bed Level (L.B.L) has to be fixed
at a lowest point on upstream side of bund line such that it is about 10m to 15m
distance from upstream toe of the bund, where capacity of tank is supposed to
be zero. Generally 1m interval contours are surveyed for minor irrigation tanks.
Number of contours to be surveyed are till the F.T.L contour of M.I. tank is
arrived.
(b) Block Leveling:-If the bed side of the proposed tank is uniformly sloping
then 10mx10m block leveling can also be taken up for the entire
foreshore area of tank. After block levels, 1 meter interval contours can be
drawn by interpolation method.
Draw the survey plan of earthen bund and contours on upstream side of
bund line to scale. Work out the area of each contour enclosing to bund line.
After knowing the contour level and its area, capacity table can be prepared. The
proforma of capacity table is given below for ready reference.
Capacity Total
Area in Capacity in
SL. R.L in C = H/3 cumulative Remar
[Link] √A M Cft
No. meter *(A1+A2+√A1*A2 capacity in ks
. (6)x35.314
) [Link]
1 2 3 4 5 6 7 8
a. Preparation work:
For raising earthwork on the old embankment, care should be taken to
ensure proper bonding of the freshly laid soil with the old embankment.
Accordingly, all bushes, vegetation, root, trees etc., from the existing
portion of embankment proposed to be raised are to be removed.
The base should be stripped to a depth of 30 Cm.
The requisite slopes of existing embankment should be benched in steps
of 30 Cm or 45 Cm as shown in figure given below.
155
b. Placement of Earthwork and Compaction:
Being homogeneous section, proper types of soils (GC, GM, SC, SM, CL
soils) should be used. Accordingly, representative samples of soils
proposed to be used shall be got tested. Grain size analysis for
classification should be done to know the classification of soils proposed to
be placed in the embankment. This is very important.
Earth-fill should be laid in suitable layers not exceeding 30 cm for power
roller compaction. Clods should be broken to 7.50 cm. Any roots, grass
and rubbish material should be removed from the fill.
Cobbles/gravels/boulders of size more than 7.50 cm should also be
removed.
In case initial water content in the soil is less than the optimum moisture
content, water should be uniformly sprinkled over the freshly laid layer
before taking up compaction.
Compaction of earth-fill should be done by 8 – 10 Ton Power Roller. A
general acceptance criteria of minimum 95% of Proctor density at
Optimum Moisture Content (OMC) be adopted.
Where space is not sufficient for deployment of Power Roller for
compaction, earth-fill be laid in layers of 15 cm and compacted either by
the ―fuel-operated bed compactor‖ (as illustrated in photo shown below)
or by ―pneumatic tamper‖.
In-situ field density test of each layer should be taken.
Figure 3.2 shows sub-grade compaction using fuel-operated compactor.
In case the weir suffers from appreciable leakages from the body wall, it
may be appropriate to provide either external plastering or skin wall of concrete
to the upstream body wall of weir.
i) External plastering:
Roughening of surface of body wall should be done to improve the
bond of plaster.
The surface should be moistened sufficiently.
Plaster of 20 cm thickness and of specified grade shall then be
applied to the surface from top and worked down. The mortar shall
be stiff enough to cling to the surface and hold when laid.
When recommencing the work on next day, the edge of old plaster
shall be scrapped clean and wetted and treated with cement slurry.
Water curing of plastering should be done uninterruptedly for 14
days.
ii) Concrete Skin Wall:
Provision of concrete skin wall shall provide a watertight barrier and
stop all leakages through the weir. Typical construction of thin skin wall is
illustrated in the figure. 3.3 as shown below.
157
Fig. 3.3 – Typical Construction of Skin Wall
158
Grade of concrete : M15 (with 20mm maximum size of
aggregate)
Thickness of concrete : 200 mm(150mm for smaller heights,
say up to 1.50m)
Thickness of concrete : 300mm(200mm for smaller heights) at
bottom
Anchor bars : 16mm Ø (as shown in sketch)
The skin wall shall be anchored with top of weir by removing the top one
layer of existing stone. The wall is to be taken below upstream ground
level/apron level to a depth of 450 mm (or 600 mm) and width of 600 mm (or
900 mm) throughout the length of weir, depending upon the height of the weir.
The shape of crest shall not be changed.
Specifications:
C. Damage to apron:
In case damage to apron consists of only few pot holes and the rest of the
apron is generally alright, it shall be appropriate to clean the pot holes, chip the
sides where ever necessary and fill up with plain cement concrete of grade M 7.5
grade ([Link]).
159
d) Repairs to sluices of tank
Repairs to the damaged irrigation sluices and their improvement shall be
given ‗top priority‟. This shall also include replacement of existing plugs
with screw gear-operated steel shutters.
Design of proposed gangways/RCC platform or structure to facilitate easy
approach for operation of sluices shall be prepared and got approved
from CDO.
In case the situation is such that repairs to the whole of sluice barrel is
contemplated, it shall require ―open cut‖ of embankment/earthen dam on
either side of the barrel in order to expose the entire length of barrel.
Cutting shall be done in suitable benching at ½ : 1, or flatter slope if so
warranted (as illustrated in the sketch below).
After the repairs to damaged masonry sluice barrel have been carried out
and water cured for 14 days, the open cut portion of the embankment
shall be taken up for filling with approved soil. Layer of soil not more
than 15 cm thickness shall be laid, and compacted with either ‗fuel-
operated bed compactors‘ or ‗pneumatic tampers‘ to the specified density
of 95% at OMC.
Figure 3.4 shows open cut embankment for repairs of sluice barrel.
i) Earthen Sections:
Channels shall be restored to the designed earthen sections in optimum
possible reaches.
Where banking is involved, the earth-fill be appropriately compacted by
‗fuel operated bed compactor‘ or ‗pneumatic tamper‘ to impart stability
and durability to the banks.
It shall be appropriate to construct Model Sections in cement concrete at
suitable intervals, say one at every curve and at 50m to 75 m intervals in
straight reaches. This will be highly useful in maintaining the profile of the
earthen channels.
ii) Lined Sections:
Channels shall be lined only in vulnerable reaches where it becomes
essential as per site conditions duly following IS 9451: 1994 Code on ―guidelines
for lining of canals in expansive soils‖
i) Plain Cement Concrete Lining:
Thickness of lining. It shall be provided as per following table-3.8:-
161
Coping:- Horizontal concrete coping (i.e., Lug) or key shall be provided
at the top of lining.
Concrete placement:- Conventional concrete placement (i.e., manual
placement) shall be in alternate panels of up to 3 m in length.
Curing of lining:- Utmost importance shall be given to water curing of
lining. Bed lining be cured through ponding of water by providing small
earth ponds. For curing of side lining, gunny bags be placed on slopes
and kept wet. 28 days curing is to be done, but first 14 days of curing
must be ensured without any interruption whatsoever.
Note: Porous concrete plugs of 100 mm dia may be provided in each panel of 3
m width, as under drainage, wherever considered necessary.
Figure 3.5 shows details of joint in Cement concrete lining.
162
90) A copy of [Link]. No.44,I & CAD (REFORMS) DEPT. DT. 13-03-2015
is given below:
GOVERNMENT OF TELANGANA
ABSTRACT
Irrigation & CAD Department – Minor Irrigation – Restoration of Minor Irrigation
Tanks – ―Mission Kakatiya‖ – General Guidelines – Orders –Issued.
------------------------------------------------------------------------------------------
IRRIGATION & CAD (REFORMS) DEPARTMENT
[Link]. 44 Dated: 13-03-2015
Read the following:
From the Chief Engineer, Minor Irrigation, TS, Hyderabad, [Link]. DCE-II/
OT1/ TO2/Mission Kakatiya /2015, Dt: 05-03-2015.
****
1. In the reference read above, the Chief Engineer, Minor Irrigation, TS,
Hyderabad has informed that Tanks were the main source of irrigation in
Telangana for centuries. Over a period of time, due to lack of proper
maintenance and siltation, most of these tanks have either shrunk or become
defunct. Reduced availability of surface water has resulted in over stress on the
available groundwater resources. To bring back the past glory to tank irrigation,
the Government of Telangana State have launched the ―Mission Kakatiya‖ (Mana
Ooru – Mana Cheruvu) with community participation. The State is committed to
ensure restoration of all the irrigation tanks in the next five years in a phased
manner.
2. The Chief Engineer, Minor Irrigation, TS, Hyderabad has requested the
Government to accord permission to use the rate structure, Tender procedure to
be followed and guidelines for the de-siltation of Irrigation Sources.
I. GUIDELINES:
i. Prioritization of tanks:
d. The chain tanks in the mandal shall be identified in the 1st phase. Cost
estimates for each individual tank in the chain including repairs of its
feeder channel shall be prepared. The Continuation of chain into the next
mandal shall be identified at Division / Sub – Division level.
e. The Rural Development Department has taken up removal of silt and
certain restoration works in 18,369 tanks during the last five years under
MGNREGS. Estimation for these tanks under Mission Kakatiya shall be
prepared, considering the works already taken up so as to avoid
duplication of work. These tanks shall preferably be taken up in
subsequent years.
f. The process of prioritization shall be done in consultation with the District
Minister/ local MLA/MLC/other Public representatives.
g. The details of the tanks so identified to be taken up for restoration shall
be documented with their unique identification number, geographical
locations, hydraulic particulars along with the works proposed and cost
thereof.
h. Regular inspection and quality control checks shall be carried out as per
normal procedure.
i. Executive Engineer shall take photos before, during execution, and after
completion of work and upload on the website.
a. De-siltation.
b. Restoration of Feeder Channel to the tank.
c. Re-sectioning of Irrigation Channels & Repairs to CM & CD works.
d. Repairs to Bund, Weir & Sluices.
e. Raising of F.T.L, wherever possible
iii. Estimates:
The estimates shall be prepared based on the standard data and current
SSR and shall be realistic.
The works shall be sanctioned only after inspection of concerned officer as per
the norms given below (Table-3.9).
(Amount in Rs. Lakhs)
Task Powers delegated to Value
Executive Engineer Up to 100
Inspection before Superintending Engineer 100-500
technical sanction
Chief Engineer Above 500
Technical Sanction Executive Engineer Upto 50
Superintending Engineer 50 to 100
Chief Engineer Above 100
Executive Engineer Upto 50
Superintending Engineer Upto 100
Tender Approval
Chief Engineer 100 to 1000
Commissioner of Tenders Above 1000
165
vii. Bid Capacity:
The available bid capacity will be calculated as (2 x A x N – B) where A is
maximum value of civil engineering works executed in his name in any one
financial year during the last 10 financial years, B is updated value of all existing
commitments and N is number of years prescribed for completion of work for
works costing Rs. > 50.00Lakhs.
Maximum of 5 No. of works or works costing not more than 2.00 crores shall
be awarded to a Contractor in the category of works costing upto Rs. 50.00
lakhs where Single Cover System (i.e., Price Bid quotation only) followed. For
the works costing more than Rs. 50.00 lakhs where normal evaluation procedure
for qualification criteria i.e., 2AN-B > ECV there is no limitation in this category.
The estimate shall also include seignorage charges for the item of work of
strengthening of bund.
The defect liability period is 24 months from the date of completion of the work.
166
xi. Retention Money:
The department shall retain from each payment due to the contractor @
7.5% of the bill amount until completion of the whole of the works.
167
The balance silt is proposed with excavation rate only i.e. Rs. 40.10 /
Cum, assuming, farmers transport the silt to their fields at their own
cost.
The above rates shall be revised from time to time as per the
prevailing SSR.
Provision of transporting the silt to a dumping yard not more than 1
Km is to be provided in the estimate in case, the farmers do not come
forward for transportation of silt to their fields while execution of work.
This lead should not be included in the agreement. Depending on the
farmers willingness to transport silt, the situation shall be assessed for
taking further action.
If more lead is required, decision shall be taken by the competent
authority.
Suitable lands may be identified for dumping of spoil with the
involvement of local villagers.
The particulars of the Shikam submergence map to be developed by
Revenue & Irrigation Authorities and FTL contour maps are to be
prepared duly conducting net leveling and shall be made as
permanent record.
The cadastral maps along with Geo – referencing shall be prepared
for the ayacut coming under each tank.
i. Formation of Embankment:
All the tanks shall be restored to its original FTL by raising the weir where
they are disturbed or lowered.
The aspect of raising FTL wherever feasible economically shall be
examined in detail and proposed.
Jungle Clearance for Bund and bed shall be provided as per necessity.
The following procedure shall be adopted while considering raising the
FTL and foreshore patta lands, to avoid submergence and LA issues.
a. On the acceptance of foreshore patta farmers, FTL of the Tank shall
be raised and the bund shall be raised with de-silted useful soils from
tank bed.
b. The slope of raised bund at FTL contour shall be taken care against
rain gullies by providing revetment.
Get the top soil, vegetation and sand patches removed to complete depth
Scarify the ground and wet properly
Obtain Proctor‘s Density, Optimum Moisture Content from the lab for the
useful soils and borrow soils.
Provide Cut of Trenches according to height of bank
Raise embankment with uniform horizontal layer of 25cm thickness
168
Break clods, remove roots, big boulders, other materials larger than
80mm from the soils used in the embankment
Supplement deficit moisture whenever required
Provide extra offset on both sides of bank
Compaction with 8 to 10 tonnes power roller
Conduct field compaction tests and determine compaction co-efficiency
Check embankment profiles periodically
Ensure 8 minimum number of passes
Provide 10% allowance in setting profile of the embankment
ii. Weirs:
All the tank users who are directly or indirectly dependent on it such as
farmers, fishermen, livestock grazers and washer-men etc., shall be
the beneficiaries.
The importance of traditional practice of tank silt application,
maintaining assets of the restored tanks shall be propagated by
169
organizing Kalajathas and other media in all the tank villages.
In many villages, Gram Sabhas have passed resolutions expressing
their interest for active participation in tank restoration and application
of tank bed silt in their fields.
The project shall thus adopt a participatory implementation strategy.
Financial contributions by interested persons / groups for tank
restoration.
I. The Chief Engineer, Minor Irrigation, TS, Hyderabad shall take necessary
action in the matter.
TO
The Chief Engineer, Minor Irrigation, TS, Hyderabad
The Engineer-in-Chief (Irrigation Wing), I & CAD, Hyderabad.
All the Engineers-in-Chief & Chief Engineers of I&CAD Dept.
The Commissioner, Commissionerate of Tenders, Hyderabad
Copy to:
The P.S. to Hon‘ble Chief Minister
The [Link]. R&B Department
The Prl. Secy. PR&RD Department.
The Prl. Secy. MA&UD Department
The Engineer-in-Chief (R&B), Admn, Hyderabad.
The Engineer-in-Chief, Admn ,PR&RD Dept., Hyderabad
The Engineer-in-Chief, PH Dept, Hyderabad
The P.S. to Hon‘ble Minister, Irrigation
The P.S. to Hon‘ble Minister, R&B
The P.S. to Hon‘ble Minister, PR
The P.S. to Hon‘ble Minister, MA&UD
The P.S. to [Link]. I&CAD Department.
SF/SC
//FORWARDED::BY ORDER//
SECTION OFFICER
170
91) BIBLIOGRAPHY
171
About Author
Mohd. Mahboob Hussain, Executive Engineer the author of this book is B.E
(Civil) and M. Tech., who joined Irrigation & CAD Department on 9-11-1987 as
Assistant Executive Engineer. He worked in Minor Irrigation sector for one
decade. He was promoted as Deputy Executive Engineer and joined on 20-03-
2002. He has joined as Executive Engineer (i/c) on 12-04-2014. He is working in
office of the Chief Engineer, Inter State & Water Resources, Hyderabad,
Government of Telangana.
172