Project name EDUCATIONAL BUILDINGS CONSTRUCTION IN RIYADH Project no.
RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng / Shehzad khanzada
Consultant name AECOM Data Date 14-May-17
To the Engineer Report no. S03/701
School Name PRINCE MUSHARY ELEMENTARY SCHOOL- BOYS School Code S03
Temperature Max : 34°C Min : 20°C Site Hand-Over Day 17-Feb-15
Weather Sunny Cloudy Rainy Humidity High Medium Low
Contractor's Manpower (including Subcontractors)* Plant/Equipment*
Status (Idle
Staff No. Direct Labor No Type Qty. Location
or Repair)
Projt. MGR. 1 Supervisor/Foreman 3 Excavator/ Poclain/ Excavator 0
Tech. Team 1 Precast Man 0 Shovel/ Loader/ Grader 0
Contract MGR. 1 Equipment Optr. 0 BOBCAT 1
Precast Manager 1 Carpenter 0 Dump Truck 0
Const. Manager 1 Welder 0 Roller/ Compactor 1
Project Control Team 1 Steelfixer 0 Portable Generator 0
QA/QC 1 E/M 0 Mobile Crane 1
Tech. Support 1 Mason 0 Tower Crane 0
Purch & Procurement 1 Painter Loabor 8 Pick up 0
Set. Manager 1 Plastering man 0 Water Tanker 1
Site Engineer 1 labor 32 Welding Machine 0
General Fork Lift
Safety/ HSE 1 1
Contractor JCB
Timekeeper 1 0
Electro Mechanical Engrs 1 Water Pump 0
Surveyor & Survayor Assistant 1 Bulldozer 0
Guard 0 Levelling Machine 0
Total station 0
Container 1
Water Tank 3
Portacabin 1
Temporary Genset 0
Sub Total/Main 15 43 5
Sub-contractors
Sub Total/Subcon 0 0 0
Grand Total 15 43 5
Activities and Tasks*
COMPLETED ACTIVITIES ON-GOING ACTIVITIES
Percentage
Type of Work Building Name Start Date Finish Date Type of Work Building Name Activity name Start Date Finish Date
Complete
Excavation Main Building - GF 23-Mar-15 4-Apr-15 Backfilling Site layout Backfilling Level Work ( Landscape ) 80.00% 2-Mar-17
Multi-purpose hall 14-Apr-16 24-Jul-16 Submit & Install Base Coarse 80.00% 1-Apr-17
Electric Room 2-May-16 28-May-16 Mechanical Main Building - GF Electric Water Heaters & Testing 90.00% 6-Feb-17
Canteen 9-May-16 24-Jul-16 Ventilation Fans & Testing 90.00% 2-Jan-17
Guard House 2-May-16 28-May-16 Diffusers & Grills 40.00% 22-Dec-16
Gate Work 25-Aug-16 10-Sep-16 Split Units & Testing 65.00% 1-Jan-17
Site layout 10-Mar-15 24-Jul-16 HVAC Duct & Testing 85.00% 27-Jul-16
Water Tank 10-May-16 29-May-16 Main Building - FF Fire Extingushers 70.00% 5-Jan-17
Boundary Wall 31-May-16 17-Jul-16 HVAC Duct & Testing 80.00% 27-Jul-16
Earth Works Site layout 1-Mar-15 24-Jul-16 Air Distribution System & Testing 80.00% 3-Dec-16
Sub Structure Main Building - GF 16-Aug-15 29-Feb-16 Ventilation Fans & Testing 30.00% 15-Dec-16
Multi-purpose hall 30-Apr-16 24-Jul-16 Diffusers & Grills 30.00% 21-Dec-16
Electric Room 2-Jul-16 1-Nov-16 Split Units & Testing 30.00% 2-Jan-17
Canteen 17-May-16 20-Aug-16 Electric Water Heaters & Testing 90.00% 10-Mar-17
Guard House 2-Jul-16 5-Sep-16 Main Building - SF HVAC Duct & Testing 80.00% 27-Jul-16
Gate Work 11-Sep-16 1-Dec-16 Electric Water Heaters & Testing 90.00% 10-Mar-17
Water Tank 29-Jun-16 6-Sep-16 Fire Extingushers 50.00% 5-Jan-17
Boundary Wall 31-May-16 20-Oct-16 Air Distribution System & Testing 80.00% 3-Dec-16
Backfilling Main Building - GF 27-Oct-15 15-Dec-15 Ventilation Fans & Testing 50.00% 1-Jan-17
Multi-purpose hall 5-Jun-16 24-Jul-16 Diffusers & Grills 30.00% 2-Jan-17
Electric Room 20-Aug-16 23-Sep-16 Split Units & Testing 50.00% 3-Jan-17
Canteen 26-May-16 25-Sep-16 Main Building - RF AHU Equipemnts & Testing 95.00% 10-Dec-16
Guard House 20-Aug-16 22-Sep-16 Multi-purpose hall Electric Water Heaters 90.00% 16-Apr-17
Gate Work 22-Oct-16 13-Dec-16 Canteen Roof Drain 50.00% 22-Feb-17
Boundary Wall 4-Oct-16 21-Oct-16 Guard House Roof Drain 90.00% 22-Mar-17
Slab On Grade Main Building - GF 13-Mar-16 20-Mar-16 Elevated Water Heaters 90.00% 21-Apr-17
Multi-purpose hall 23-Jul-16 30-Jul-16 Gate Work Roof Drain 90.00% 22-Mar-17
Electric Room 22-Sep-16 26-Nov-16 Elevated Water Heaters 90.00% 21-Apr-17
Canteen 24-Sep-16 6-Nov-16 Site layout Connection Water Network on General Network 95.00% 24-Apr-17
Guard House 1-Oct-16 26-Nov-16 Electrical Main Building - GF Data Communications System Third Fix (Fixtures ) 20.00% 2-Jan-17
Gate Work 24-Dec-16 28-Dec-16 IP Telephone System Third Fix (Fixtures ) 20.00% 2-Jan-17
Water Proofing Main Building - GF 18-Oct-15 8-Aug-16 Main Distribution Board 50.00% 2-Feb-17
Main Building - FF 9-Feb-17 21-Feb-17 Audio Communications Terminal Equipment 20.00% 2-Jan-17
Main Building - SF 9-Feb-17 21-Feb-17 Lighting System Third Fix (Fixtures ) 20.00% 2-Jan-17
Main Building - RF 12-Nov-16 24-Jan-17 Wiring Devices Third Fix (Fixtures ) 23.00% 2-Jan-17
Electric Room 8-Aug-16 29-Mar-17 Fire Alarm Third Fix (Fixtures ) 20.00% 2-Jan-17
Guard House 8-Aug-16 3-May-17 Main Building - FF Lighting System Third Fix (Fixtures ) 20.00% 2-Jan-17
Precast Main Building - GF 12-Nov-15 28-Dec-15 Wiring Devices Third Fix (Fixtures ) 22.00% 2-Jan-17
Main Building - FF 3-Dec-15 31-Jan-16 Fire Alarm Third Fix (Fixtures ) 20.00% 2-Jan-17
Main Building - SF 12-Dec-15 10-Jan-16 Data Communications System Third Fix (Fixtures ) 20.00% 2-Jan-17
Main Building - RF 7-Feb-16 5-Mar-16 Audio Communications Terminal Equipment 20.00% 2-Jan-17
Multi-purpose hall 6-Sep-16 2-Dec-16 IP Telephone System Third Fix (Fixtures ) 20.00% 2-Jan-17
Electric Room 10-Nov-16 21-Nov-16 Main Building - SF Fire Alarm Third Fix (Fixtures ) 20.00% 2-Jan-17
Canteen 12-Nov-16 27-Nov-16 Audio Communications Terminal Equipment 20.00% 2-Jan-17
Guard House 20-Oct-16 30-Nov-16 Lighting System Third Fix (Fixtures ) 20.00% 2-Jan-17
Gate Work 7-Dec-16 20-Dec-16 Wiring Devices Third Fix (Fixtures ) 30.00% 2-Jan-17
Boundary Wall 23-Oct-16 29-Dec-16 Data Communications System Third Fix (Fixtures ) 20.00% 2-Jan-17
Concrete Works Multi-purpose hall 16-Jan-17 17-Jan-17 IP Telephone System Third Fix (Fixtures ) 20.00% 2-Jan-17
Page 1 of 2
Gate Work 19-Dec-16 28-Dec-16 Main Building - RF Sub Main Distribution Board 20.00% 27-Apr-17
Block Work Main Building - GF 2-May-16 7-Jun-16 Panelboards 40.00% 15-Apr-17
Main Building - FF 30-Apr-16 24-Jul-16 Lighting Units (all building ) 30.00% 27-Apr-17
Main Building - SF 2-May-16 24-Jul-16 Multi-purpose hall Public Address System Second Fix (Wires ) 90.00% 14-Feb-17
Multi-purpose hall 16-Jan-17 17-Jan-17 IP Telephone System Second Fix (Wires ) 90.00% 14-Feb-17
Canteen 12-Dec-16 26-Dec-16 Fire Alarm System Second Fix (Wires ) 85.00% 14-Feb-17
Guard House 12-Dec-16 26-Dec-16 Low-Voltage Electrical Power Conductors and Cables 60.00% 14-Feb-17
Gate Work 29-Dec-16 2-Jan-17 Lighting System Second Fix (Wires ) 90.00% 14-Feb-17
Water Tank 28-Jul-16 2-Aug-16 Wiring Devices Second Fix (Wires ) 90.00% 14-Feb-17
Plaster Main Building - GF 20-Jun-16 31-Dec-16 Panelboards 80.00% 14-Feb-17
Main Building - FF 16-Jul-16 8-Jan-17 Lighting Units 50.00% 27-Apr-17
Main Building - SF 26-Sep-16 12-Jan-17 Canteen Low-Voltage Electrical Power Conductors and Cables 70.00% 14-Feb-17
Multi-purpose hall 18-Dec-16 8-Feb-17 Panelboards 80.00% 14-Feb-17
Canteen 16-Jan-17 7-Feb-17 Guard House IP Telephone System Second Fix (Wires ) 80.00% 14-Feb-17
Guard House 16-Jan-17 8-Feb-17 Low-Voltage Electrical Power Conductors and Cables 70.00% 27-Apr-17
Gate Work 1-Feb-17 4-Feb-17 Panelboards 70.00% 14-Feb-17
Water Tank 3-Aug-16 9-Aug-16 Lighting Units 30.00% 27-Apr-17
Mechanical Electric Room 29-Dec-16 22-Feb-17 Gate Work Low-Voltage Electrical Power Conductors and Cables 40.00% 27-Apr-17
Elevator Main Building - RF 11-Dec-16 29-Mar-17 Panelboards 60.00% 14-Feb-17
Electrical Electric Room 29-Dec-16 10-Apr-17 Site layout Telephone -Low Current Cable 80.00% 22-Dec-16
Doors Electric Room 26-Jan-17 14-Feb-17 Data -Low Current Cable 80.00% 22-Dec-16
Windows Electric Room 31-Jan-17 13-Feb-17 Fire Alarm -Low Current Cable 80.00% 22-Dec-16
Canteen 31-Jan-17 8-May-17 Low Voltage Cables 80.00% 22-Dec-16
Guard House 27-Apr-17 10-May-17 SEC Testing, Connection 20.00% 22-Dec-16
Gate Work 27-Apr-17 6-May-17 Doors Main Building - GF Hollow Metal Doors 80.00% 2-Mar-17
Space Frame Multi-purpose hall 15-Nov-16 8-Dec-16 Main Building - FF Hollow Metal Doors 55.00% 2-Mar-17
Gate Work 2-Mar-17 30-Mar-17 Main Building - SF Hollow Metal Doors 60.00% 2-Mar-17
Tiling Main Building - GF 26-Oct-16 30-Mar-17 Main Building - RF Hollow Metal Frames 35.00% 13-Apr-17
Main Building - FF 1-Nov-16 3-Apr-17 Multi-purpose hall Hollow Metal Door Frames 95.00% 26-Jan-17
Main Building - SF 22-Nov-16 29-Mar-17 Hollow Metal Doors 35.00% 25-Mar-17
Guard House 4-Apr-17 2-May-17 Guard House Hollow Metal Doors 50.00% 1-May-17
Paint Main Building - RF 29-Dec-16 1-Feb-17 Windows Main Building - GF Aluminum Windows 95.00% 12-Nov-16
Electric Room 8-Dec-16 4-Jan-17 Main Building - FF Aluminum Windows 90.00% 12-Nov-16
Exposed Aggr. Main Building - RF 7-Feb-16 24-Feb-16 Main Building - SF Aluminum Windows 90.00% 9-Feb-17
Electric Room 11-Mar-17 11-Apr-17 Main Building - RF Aluminum Windows 53.00% 4-May-17
Canteen 7-Mar-17 1-May-17 Multi-purpose hall Aluminum Windows 23.00% 2-May-17
Guard House 1-Apr-17 3-May-17 Skylights Main Building - RF Roof Windows and Skylights 70.00% 27-Apr-17
Gate Work 1-Apr-17 2-May-17 Tiling Stair Granite Finishes 90.00% 11-Mar-17
No R_Type Of Work Electric Room 9-Feb-17 14-Feb-17 Multi-purpose hall Ceramic Tiels for Floor 90.00% 2-May-17
Gate Work 1-May-17 3-May-17 Wall Ceramic Tiels 90.00% 27-Apr-17
Porcelain Tiels 90.00% 30-Apr-17
Site layout Granit Tiles 70.00% 11-Mar-17
Ceiling Main Building - GF Acoustical Panel Ceilings 85.00% 15-May-16
Solid Gypsum Ceiling 75.00% 21-Jul-16
Main Building - FF Acoustical Panel Ceilings 80.00% 15-May-16
Solid Gypsum Ceiling 75.00% 24-Jul-16
Main Building - SF Acoustical Panel Ceilings 50.00% 2-May-17
Solid Gypsum Ceiling 68.00% 6-Dec-16
Paint Main Building - GF Final Coat Paint 50.00% 6-May-17
Main Building - FF Final Coat Paint 50.00% 6-May-17
Main Building - SF Final Coat Paint 50.00% 6-May-17
Multi-purpose hall Exterior Painting 90.00% 9-Feb-17
Handrail Main Building - GF Pipe and Tube Railings 85.00% 22-Feb-17
Main Building - FF Pipe and Tube Railings 95.00% 21-Feb-17
Main Building - SF Pipe and Tube Railings 90.00% 2-Mar-17
Exposed Aggr. Multi-purpose hall Colour Exposed Aggregate 90.00% 9-Feb-17
Site layout Exposed Color Aggregate 98.00% 25-Mar-17
Landscape Precast Concrete Curbs 80.00% 11-Mar-17
Furniture Main Building - GF Lockers 55.00% 25-Mar-17
Main Building - FF Lockers 55.00% 25-Mar-17
Main Building - SF Lockers 60.00% 25-Mar-17
Site layout Student Stands 50.00% 2-Mar-17
Waste Baskets 50.00% 11-Mar-17
No R_Type Of Work Main Building - RF Installation of glass 70.00% 3-May-17
Multi-purpose hall Porcelain Skirting 90.00% 3-May-17
Rubber Grains & Polyurethane Artificial Ground 20.00% 9-Feb-17
Materials delivered to Site*
Item Unit Qty. Approved submittal reference
Contractor's authorized signatory Engineer's authorized signatory
Name: Hesham Ahmad Name:
Signature: Signature:
Date: 14-May-17 Date: 14-May-17
* This form is to be used by the General Contractor to capture the above required information on a daily basis to report to the
Construction Supervisor (Engineer).
Page 2 of 2