Contractor's Manpower (Including Subcontractors) Plant/Equipment

SCHHOL S03
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
48 views2 pages

Contractor's Manpower (Including Subcontractors) Plant/Equipment

SCHHOL S03
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Project name EDUCATIONAL BUILDINGS CONSTRUCTION IN RIYADH Project no.

RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng / Shehzad khanzada
Consultant name AECOM Data Date 14-May-17
To the Engineer Report no. S03/701
School Name PRINCE MUSHARY ELEMENTARY SCHOOL- BOYS School Code S03
Temperature Max : 34°C Min : 20°C Site Hand-Over Day 17-Feb-15
Weather Sunny Cloudy Rainy Humidity High Medium Low

Contractor's Manpower (including Subcontractors)* Plant/Equipment*

Status (Idle
Staff No. Direct Labor No Type Qty. Location
or Repair)
Projt. MGR. 1 Supervisor/Foreman 3 Excavator/ Poclain/ Excavator 0
Tech. Team 1 Precast Man 0 Shovel/ Loader/ Grader 0
Contract MGR. 1 Equipment Optr. 0 BOBCAT 1
Precast Manager 1 Carpenter 0 Dump Truck 0
Const. Manager 1 Welder 0 Roller/ Compactor 1
Project Control Team 1 Steelfixer 0 Portable Generator 0
QA/QC 1 E/M 0 Mobile Crane 1
Tech. Support 1 Mason 0 Tower Crane 0
Purch & Procurement 1 Painter Loabor 8 Pick up 0
Set. Manager 1 Plastering man 0 Water Tanker 1
Site Engineer 1 labor 32 Welding Machine 0
General Fork Lift
Safety/ HSE 1 1
Contractor JCB
Timekeeper 1 0
Electro Mechanical Engrs 1 Water Pump 0
Surveyor & Survayor Assistant 1 Bulldozer 0
Guard 0 Levelling Machine 0
Total station 0
Container 1
Water Tank 3
Portacabin 1
Temporary Genset 0

Sub Total/Main 15 43 5

Sub-contractors

Sub Total/Subcon 0 0 0

Grand Total 15 43 5

Activities and Tasks*


COMPLETED ACTIVITIES ON-GOING ACTIVITIES
Percentage
Type of Work Building Name Start Date Finish Date Type of Work Building Name Activity name Start Date Finish Date
Complete
Excavation Main Building - GF 23-Mar-15 4-Apr-15 Backfilling Site layout Backfilling Level Work ( Landscape ) 80.00% 2-Mar-17
Multi-purpose hall 14-Apr-16 24-Jul-16 Submit & Install Base Coarse 80.00% 1-Apr-17
Electric Room 2-May-16 28-May-16 Mechanical Main Building - GF Electric Water Heaters & Testing 90.00% 6-Feb-17
Canteen 9-May-16 24-Jul-16 Ventilation Fans & Testing 90.00% 2-Jan-17
Guard House 2-May-16 28-May-16 Diffusers & Grills 40.00% 22-Dec-16
Gate Work 25-Aug-16 10-Sep-16 Split Units & Testing 65.00% 1-Jan-17
Site layout 10-Mar-15 24-Jul-16 HVAC Duct & Testing 85.00% 27-Jul-16
Water Tank 10-May-16 29-May-16 Main Building - FF Fire Extingushers 70.00% 5-Jan-17
Boundary Wall 31-May-16 17-Jul-16 HVAC Duct & Testing 80.00% 27-Jul-16
Earth Works Site layout 1-Mar-15 24-Jul-16 Air Distribution System & Testing 80.00% 3-Dec-16
Sub Structure Main Building - GF 16-Aug-15 29-Feb-16 Ventilation Fans & Testing 30.00% 15-Dec-16
Multi-purpose hall 30-Apr-16 24-Jul-16 Diffusers & Grills 30.00% 21-Dec-16
Electric Room 2-Jul-16 1-Nov-16 Split Units & Testing 30.00% 2-Jan-17
Canteen 17-May-16 20-Aug-16 Electric Water Heaters & Testing 90.00% 10-Mar-17
Guard House 2-Jul-16 5-Sep-16 Main Building - SF HVAC Duct & Testing 80.00% 27-Jul-16
Gate Work 11-Sep-16 1-Dec-16 Electric Water Heaters & Testing 90.00% 10-Mar-17
Water Tank 29-Jun-16 6-Sep-16 Fire Extingushers 50.00% 5-Jan-17
Boundary Wall 31-May-16 20-Oct-16 Air Distribution System & Testing 80.00% 3-Dec-16
Backfilling Main Building - GF 27-Oct-15 15-Dec-15 Ventilation Fans & Testing 50.00% 1-Jan-17
Multi-purpose hall 5-Jun-16 24-Jul-16 Diffusers & Grills 30.00% 2-Jan-17
Electric Room 20-Aug-16 23-Sep-16 Split Units & Testing 50.00% 3-Jan-17
Canteen 26-May-16 25-Sep-16 Main Building - RF AHU Equipemnts & Testing 95.00% 10-Dec-16
Guard House 20-Aug-16 22-Sep-16 Multi-purpose hall Electric Water Heaters 90.00% 16-Apr-17
Gate Work 22-Oct-16 13-Dec-16 Canteen Roof Drain 50.00% 22-Feb-17
Boundary Wall 4-Oct-16 21-Oct-16 Guard House Roof Drain 90.00% 22-Mar-17
Slab On Grade Main Building - GF 13-Mar-16 20-Mar-16 Elevated Water Heaters 90.00% 21-Apr-17
Multi-purpose hall 23-Jul-16 30-Jul-16 Gate Work Roof Drain 90.00% 22-Mar-17
Electric Room 22-Sep-16 26-Nov-16 Elevated Water Heaters 90.00% 21-Apr-17
Canteen 24-Sep-16 6-Nov-16 Site layout Connection Water Network on General Network 95.00% 24-Apr-17
Guard House 1-Oct-16 26-Nov-16 Electrical Main Building - GF Data Communications System Third Fix (Fixtures ) 20.00% 2-Jan-17
Gate Work 24-Dec-16 28-Dec-16 IP Telephone System Third Fix (Fixtures ) 20.00% 2-Jan-17
Water Proofing Main Building - GF 18-Oct-15 8-Aug-16 Main Distribution Board 50.00% 2-Feb-17
Main Building - FF 9-Feb-17 21-Feb-17 Audio Communications Terminal Equipment 20.00% 2-Jan-17
Main Building - SF 9-Feb-17 21-Feb-17 Lighting System Third Fix (Fixtures ) 20.00% 2-Jan-17
Main Building - RF 12-Nov-16 24-Jan-17 Wiring Devices Third Fix (Fixtures ) 23.00% 2-Jan-17
Electric Room 8-Aug-16 29-Mar-17 Fire Alarm Third Fix (Fixtures ) 20.00% 2-Jan-17
Guard House 8-Aug-16 3-May-17 Main Building - FF Lighting System Third Fix (Fixtures ) 20.00% 2-Jan-17
Precast Main Building - GF 12-Nov-15 28-Dec-15 Wiring Devices Third Fix (Fixtures ) 22.00% 2-Jan-17
Main Building - FF 3-Dec-15 31-Jan-16 Fire Alarm Third Fix (Fixtures ) 20.00% 2-Jan-17
Main Building - SF 12-Dec-15 10-Jan-16 Data Communications System Third Fix (Fixtures ) 20.00% 2-Jan-17
Main Building - RF 7-Feb-16 5-Mar-16 Audio Communications Terminal Equipment 20.00% 2-Jan-17
Multi-purpose hall 6-Sep-16 2-Dec-16 IP Telephone System Third Fix (Fixtures ) 20.00% 2-Jan-17
Electric Room 10-Nov-16 21-Nov-16 Main Building - SF Fire Alarm Third Fix (Fixtures ) 20.00% 2-Jan-17
Canteen 12-Nov-16 27-Nov-16 Audio Communications Terminal Equipment 20.00% 2-Jan-17
Guard House 20-Oct-16 30-Nov-16 Lighting System Third Fix (Fixtures ) 20.00% 2-Jan-17
Gate Work 7-Dec-16 20-Dec-16 Wiring Devices Third Fix (Fixtures ) 30.00% 2-Jan-17
Boundary Wall 23-Oct-16 29-Dec-16 Data Communications System Third Fix (Fixtures ) 20.00% 2-Jan-17
Concrete Works Multi-purpose hall 16-Jan-17 17-Jan-17 IP Telephone System Third Fix (Fixtures ) 20.00% 2-Jan-17

Page 1 of 2
Gate Work 19-Dec-16 28-Dec-16 Main Building - RF Sub Main Distribution Board 20.00% 27-Apr-17
Block Work Main Building - GF 2-May-16 7-Jun-16 Panelboards 40.00% 15-Apr-17
Main Building - FF 30-Apr-16 24-Jul-16 Lighting Units (all building ) 30.00% 27-Apr-17
Main Building - SF 2-May-16 24-Jul-16 Multi-purpose hall Public Address System Second Fix (Wires ) 90.00% 14-Feb-17
Multi-purpose hall 16-Jan-17 17-Jan-17 IP Telephone System Second Fix (Wires ) 90.00% 14-Feb-17
Canteen 12-Dec-16 26-Dec-16 Fire Alarm System Second Fix (Wires ) 85.00% 14-Feb-17
Guard House 12-Dec-16 26-Dec-16 Low-Voltage Electrical Power Conductors and Cables 60.00% 14-Feb-17
Gate Work 29-Dec-16 2-Jan-17 Lighting System Second Fix (Wires ) 90.00% 14-Feb-17
Water Tank 28-Jul-16 2-Aug-16 Wiring Devices Second Fix (Wires ) 90.00% 14-Feb-17
Plaster Main Building - GF 20-Jun-16 31-Dec-16 Panelboards 80.00% 14-Feb-17
Main Building - FF 16-Jul-16 8-Jan-17 Lighting Units 50.00% 27-Apr-17
Main Building - SF 26-Sep-16 12-Jan-17 Canteen Low-Voltage Electrical Power Conductors and Cables 70.00% 14-Feb-17
Multi-purpose hall 18-Dec-16 8-Feb-17 Panelboards 80.00% 14-Feb-17
Canteen 16-Jan-17 7-Feb-17 Guard House IP Telephone System Second Fix (Wires ) 80.00% 14-Feb-17
Guard House 16-Jan-17 8-Feb-17 Low-Voltage Electrical Power Conductors and Cables 70.00% 27-Apr-17
Gate Work 1-Feb-17 4-Feb-17 Panelboards 70.00% 14-Feb-17
Water Tank 3-Aug-16 9-Aug-16 Lighting Units 30.00% 27-Apr-17
Mechanical Electric Room 29-Dec-16 22-Feb-17 Gate Work Low-Voltage Electrical Power Conductors and Cables 40.00% 27-Apr-17
Elevator Main Building - RF 11-Dec-16 29-Mar-17 Panelboards 60.00% 14-Feb-17
Electrical Electric Room 29-Dec-16 10-Apr-17 Site layout Telephone -Low Current Cable 80.00% 22-Dec-16
Doors Electric Room 26-Jan-17 14-Feb-17 Data -Low Current Cable 80.00% 22-Dec-16
Windows Electric Room 31-Jan-17 13-Feb-17 Fire Alarm -Low Current Cable 80.00% 22-Dec-16
Canteen 31-Jan-17 8-May-17 Low Voltage Cables 80.00% 22-Dec-16
Guard House 27-Apr-17 10-May-17 SEC Testing, Connection 20.00% 22-Dec-16
Gate Work 27-Apr-17 6-May-17 Doors Main Building - GF Hollow Metal Doors 80.00% 2-Mar-17
Space Frame Multi-purpose hall 15-Nov-16 8-Dec-16 Main Building - FF Hollow Metal Doors 55.00% 2-Mar-17
Gate Work 2-Mar-17 30-Mar-17 Main Building - SF Hollow Metal Doors 60.00% 2-Mar-17
Tiling Main Building - GF 26-Oct-16 30-Mar-17 Main Building - RF Hollow Metal Frames 35.00% 13-Apr-17
Main Building - FF 1-Nov-16 3-Apr-17 Multi-purpose hall Hollow Metal Door Frames 95.00% 26-Jan-17
Main Building - SF 22-Nov-16 29-Mar-17 Hollow Metal Doors 35.00% 25-Mar-17
Guard House 4-Apr-17 2-May-17 Guard House Hollow Metal Doors 50.00% 1-May-17
Paint Main Building - RF 29-Dec-16 1-Feb-17 Windows Main Building - GF Aluminum Windows 95.00% 12-Nov-16
Electric Room 8-Dec-16 4-Jan-17 Main Building - FF Aluminum Windows 90.00% 12-Nov-16
Exposed Aggr. Main Building - RF 7-Feb-16 24-Feb-16 Main Building - SF Aluminum Windows 90.00% 9-Feb-17
Electric Room 11-Mar-17 11-Apr-17 Main Building - RF Aluminum Windows 53.00% 4-May-17
Canteen 7-Mar-17 1-May-17 Multi-purpose hall Aluminum Windows 23.00% 2-May-17
Guard House 1-Apr-17 3-May-17 Skylights Main Building - RF Roof Windows and Skylights 70.00% 27-Apr-17
Gate Work 1-Apr-17 2-May-17 Tiling Stair Granite Finishes 90.00% 11-Mar-17
No R_Type Of Work Electric Room 9-Feb-17 14-Feb-17 Multi-purpose hall Ceramic Tiels for Floor 90.00% 2-May-17
Gate Work 1-May-17 3-May-17 Wall Ceramic Tiels 90.00% 27-Apr-17
Porcelain Tiels 90.00% 30-Apr-17
Site layout Granit Tiles 70.00% 11-Mar-17
Ceiling Main Building - GF Acoustical Panel Ceilings 85.00% 15-May-16
Solid Gypsum Ceiling 75.00% 21-Jul-16
Main Building - FF Acoustical Panel Ceilings 80.00% 15-May-16
Solid Gypsum Ceiling 75.00% 24-Jul-16
Main Building - SF Acoustical Panel Ceilings 50.00% 2-May-17
Solid Gypsum Ceiling 68.00% 6-Dec-16
Paint Main Building - GF Final Coat Paint 50.00% 6-May-17
Main Building - FF Final Coat Paint 50.00% 6-May-17
Main Building - SF Final Coat Paint 50.00% 6-May-17
Multi-purpose hall Exterior Painting 90.00% 9-Feb-17
Handrail Main Building - GF Pipe and Tube Railings 85.00% 22-Feb-17
Main Building - FF Pipe and Tube Railings 95.00% 21-Feb-17
Main Building - SF Pipe and Tube Railings 90.00% 2-Mar-17
Exposed Aggr. Multi-purpose hall Colour Exposed Aggregate 90.00% 9-Feb-17
Site layout Exposed Color Aggregate 98.00% 25-Mar-17
Landscape Precast Concrete Curbs 80.00% 11-Mar-17
Furniture Main Building - GF Lockers 55.00% 25-Mar-17
Main Building - FF Lockers 55.00% 25-Mar-17
Main Building - SF Lockers 60.00% 25-Mar-17
Site layout Student Stands 50.00% 2-Mar-17
Waste Baskets 50.00% 11-Mar-17
No R_Type Of Work Main Building - RF Installation of glass 70.00% 3-May-17
Multi-purpose hall Porcelain Skirting 90.00% 3-May-17
Rubber Grains & Polyurethane Artificial Ground 20.00% 9-Feb-17

Materials delivered to Site*


Item Unit Qty. Approved submittal reference

Contractor's authorized signatory Engineer's authorized signatory


Name: Hesham Ahmad Name:
Signature: Signature:
Date: 14-May-17 Date: 14-May-17

* This form is to be used by the General Contractor to capture the above required information on a daily basis to report to the
Construction Supervisor (Engineer).

Page 2 of 2