Best of - Cartoon Booklet May 2024
Best of - Cartoon Booklet May 2024
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Contact
photo Naser Shaheen
Performance Stakes Solution
Energy Efficiency Due to the relative low and stable power consumption,
the most feasible option is if the rig can receive power from
the host platform.
Context
This will involve a dedicate shore power converter
(50Hz to 60Hz) to allow equalizing the expected power
The project is divided on three phases: and frequency diffrenrences to the rig.
Phase one – The project will install power
inverters on the accommodation rigs, setup the Outcome
power supply from the host installation.
Phase two - The accommodation rigs will shut
down diesel generators and switch to shore Emission ‘‘CO2 and GHG’’ reduction to zero while positioned
supply from the gas turbine at host installation / connnected to a host installation. Cost Saving of 2,4 mil
Phase three – only when rig move is expected, USD while on the same location. Possible long-term saving
then power supply will be reinstated via own of logistics, transport and bunkering of diesel adding up to
diesel generators total of 3,4 mil USD a year while contracted to the affiliate.
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Ziad Fallah
M-C Alboussiere
Performance Stakes Solution Head of Production &
Integrity - Manager
Continuous production To perform rig and barge moves with continuous production
by assessing the level of risk associated by not depressurizing
topside facilities and subsea facilities, and with wells in
production:
Context
• Simplification of operations (reduced shutdown and
startup operations)
In 2017 shortfalls related to rig move operations • Reduction in oil shortfalls
accounted for 153 kbbl equivalent to 7.6 M$ loss
of revenues for Al Khalij asset (@ 50$/bbl). Outcome
Estimated Savings : ~20 kbbls i.e., 330k$ for 2020 for TEPQ
(40%) @ 40$/bbl
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Aden Waberi
Performance Stakes Solution
Outcome
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Fuel Gas consumption reduction Different initiatives have been put in place to reduce Fuel
Gas consumption (turning off 1 main compressor A,
adjusting the parameters of the compression chain, reducing
Context the regeneration time of molecular sieves, …).
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Contact
photo Stuart Brice
Performance Stakes Solution
Context Outcome
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Top riser inspection Thanks to the implementation of drone inspection for top
riser, it will minimize the cost of the rope access mission.
Outcome
PCI RM+#: - Ref: - Country: BRAZIL Asset: LAPA (MV27 FPSO) 2023
Operations Fit for purpose
Field operations
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Context Outcome
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Per Thygesen
Performance Stakes Solution
Inspection and paint maintenance • This will minimise the use of scaffolding for inspection
and painting
• The set-up will cover Piping UT scanning/radiography,
NDT examination of welds, Structural inspection and
Outcome
Paint Maintenance on critical hot spots
• Site Inspector supervision
An overall saving of 27,945 hours • Using rope access should give an expected increase in
> 2,7 M$ per year when fully implemented efficiency:
• OIE supervision
• Multi-skilled independent team
• Flexible and agile execution (find & fix)
• Effective use of resources by cross collaboration
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Hassan Seghosime
Performance Stakes Solution
Turbo generator’s overhaul time extension Move to Conditional Based Maintenance (CMB):
• Overhaul not done as per OEM strict strategy
• Negotiated overhaul rate for a non-damaged Engine with
Context an ISP (Independant Service Provider)
• Regular Boroscope of engine, vibration survey and Lube oil
Until 2016, overhauls were done based on OEM • analysis done
recommendations. Every year 2 units were
removed from their berth and sent to an approved Outcome
repair and maintenance workshop.
2019 Savings: $2.2M
The yearly budget for this operation was $4M at
early life of the field and going to move to up to
$5M with the aging of the facility.
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Oil export rerouting Reroute Halfdan oil export to Dan. This will allow
decommissioning of separation and water treatment system
on Gorm and reduce flaring on Gorm:
• Less flaring on Gorm by 1.2 MMscfd
• Gas captured and exported from Dan as sales gas
> more production
• Decommissioning of equipment on Gorm
Outcome
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Bernard Reith
Performance Stakes Solution
Maintenance frequency
Outcome
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Avelino Tchama
Performance Stakes Solution Head of 2C&E project
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Dean Henderson
Performance Stakes Solution
Maintenance structure
Measuremen
Visual board Field Tour
t
Outcome
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Miguel Sanchez
Performance Stakes Solution
Contract negociation • Adapt the contract to the current activity level of the sites
• Working days are now 365 days a year versus 335 in the
past
• Stop the multiple billing for spare parts and have one
single billing
Outcome
Estimated savings :
~$18M of savings over 2015-2017
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Miguel Guerra
Performance Stakes Solution Digital engineer
FPSO Virtual visit Adopt technology based on the « 360° panoramic views » of
our FPSOs facilities.
Context Outcome
Due to POB constraint in our sites, some onshore Benefits/key results linked to objectives are:
personnel are often faced with several difficulties • Quality: by reducing the POB on the installations, allows
to prepare campaigns and preliminary surveys, better management of the personnel in case of an
be familiar with our offshore sites and undergo émergence.
immersive inductions • Cost savings: by avoiding Onshore personal mobility (up
to 2025 – 0,8 M$).
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Paulo PAULINO
Performance Stakes Solution Digital Project Leader
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Paulo PAULINO
Performance Stakes Solution Digital Project Leader
Data equipment The OneCBM is a digital platform that will consolidate equipment data
In order to provide an equipment health follow-up, failure detection and then
reduce the shortfall associated to the secondary equipment failures
Context This innovative digital platform gathers all relevant information regarding
rotating equipment’s all in one place. In addition, it helps CBM engineer by
automatically detecting abnormal behavior on secondary equipments.
The tool will enhance and facilitate day to day work and follow up for the
On FPSO, CBM engineer are performing a lot of Offshore and Onshore teams involved in maintaining these equipments.
regular taks that requires the consolidation and
analysis of multiple source data (xls, pdf, PI Outcome
dashboard…). The heavy workload on critical
equipment have them focus on other equipment
Levers: Reduce the shortfalls associated to secondary equipement (1% of the
than secondary equipment. Failures or lack of production of GIR as baseline with 10 to 20% of impact) Value: Girassol (YTD
anticipation and monitoring on these equipment Prod): 85,1 Kboepd Baseline (1%): 0,851 Kboepd Impact (10-20%): 0,085 –
lead to production and injection shortfalls 0,017 Kboepd
(280kbbl in 2025) Move from a dispersed and Value (95,4$/boepd & Half Year): 1,5M$ - 3,0M$ @100%
reactive CBM approach to consolidated and
proactive strategy
PCI RM+#: - Ref: - Country: ANGOLA Asset: B17 & DT 04/2023
Operations Digital
Field operations
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Paulo PAULINO
Context Solution Digital Project Leader
Initial Status: A product for maintenance & procurement team to provide visibility across
• Lack of visibility in all steps of the supply chain VS supply chain from the demand to the reception of materials leveraging SAP
Data.
planning operation. Spare parts criticality, work order
priority, work programs and campaigns, not visible to Achievements and Improvements:
ACT team. (due to poor communication between SAP • Tracking for work order • Management dashboard
PM and MM) • MRP Analysis • Details for Work order and Material
• Material requirement plan ‘’MRP’’ review and • Availability on Stock • Stock sizing & Statical lead time
validation are time consuming procedure (more than 5
Outcome Project
windows on SAP) and MS Excel to merge the
information image
o Too much time spend by methods team in This tool should improve the communication between technicians and support
order cross check information and find the teams. Increasing the visibility of all steps of the supply chain (from the work
historical data on SAP order until material arrival on site); Proposing valuable MRP recommendations
with potential savings, tracking the value on stock optimization (instead of doing
• SAP not so much user friendly, and difficult to find manually on excel). Ultimately value tracking will be reflected / synchronizing
information and sometimes with authorizations blocks with 3C RM+ tool for reporting
between SAP modules
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Joao Raulino
Performance Stakes Solution Quantum Coordinator
operational performance improvement and the absence • Progressive increase in number of users in following years leading to raise in In dollars* $654 K $2617 K $3571 K $4525 K
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Miguel Guerra
Performance Stakes Solution Digital engineer
Some risk analysis were necessary: Adopt technology based on the “Addictive manufacturing’.
• Installation conditions of the machine (room, So, TEPA management decided to print some critical parts
HVAC) locally having as strategy to start on the 3D Polymer Printer.
• Isolation system against volatile organic
compounds released by printers
Context Outcome
The affiliate is faced with several difficulties due Benefits/key results linked to objectives is cost saving
to the Global Supply Chain Limitations and mainly on :
certain parts are no longer manufactured over the • Plant refurbishment: With gain Up to 2025 – 0,42 M$;
entire operating life of the facilities, which can • On demand: With gain Up to 2025 – 0,12 M$;
reach around forty years (the case of FPSO
Girassol and Dalia).
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Contact
photo Kim Rasmussen
Performance Stakes Solution
Outcome
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Vicky Mateso /
Contact
photo A. Carvalheira /
Performance Stakes Solution B. D. Bartolomeu
Long term mitigation measure Reason why this project has been undertaken stakeholders
involved or to be informed different steps to achieve the
Context initiative difficulties or attention points solutions found
Due to internal corrosion and erosion most of lines will lose the wall
thickness until it reaches a point where remaining wall thickness can
not withstand anymore the MAWP; in order to continue to operate
within design condition the line shall be replaced “TBR” or temporary Outcome
solution such as patch repair implemented.
Estimation has been done based on the data available from past
interventions, below is the cost comparison between TBR and Patch
Impacts:
repair: • Lower significantly the cost keeping an acceptable level of
safety and operational standard.
Line replacement “TBR” cost 45 kUSD (includes material
• Reduction in the material on stock at the affiliate
•
purchase, prefabrication and installation) ;
• Strategy to be applied mainly for FPSO
• Patch 2kUSD (includes prefabrication and installation). Savings : 1,0 mUSD/y
PCI RM+#: - Ref: - Country: ANGOLA Asset: GIRASSOL & DALIA MM/YYYY
DRAPEAU
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Contact
Nels M. Jeansen
photo
Performance Stakes Solution
Valve refurbishment • Manual Wing Valve and Methanol valves removed (Less maintenance
Offshore)
• HA6 Actuators replaced to type CH55 (Less spare parts required during
WHM)
• New spools and 6GR52R Saver subs installed (Simplified R/U during
intervention)
Context Outcome
• 71 ea. XMTs dismounted on Tyra East and West wellhead platforms. Manufacturing of new steel contra the refurbishment
44 ea. Xmas trees refurbished locally by UNITY in Esbjerg (WHM
•
Reduced C02 Emission (CO2e)
contract)
The Tyra Redevelopment Project comprises the reinstatement and New steel manufacturing ~ 1,9tons of C02 per ton of steel.
unsuspension of 44 resources wells (out of 72 wells). Refurbishing – less than 10% - only when manufacturing internal spares
Refurbishment cost per Xmas tree cost on average: DKK – 500.000,00 44 Xmas trees – 4 to 5 ton per tree = 200 tons of steel
(Good investment compared to new X-mas Tree valued +/- DKK
1,9 * 200 tones = approx. 380 tons of reduced C02 emission (new steel)
1.900.000,00 per tree)
Saving of approx. 1.4 MM DKK per tree. Our scope is 44 off Trees. - 10% = 380 – 38 = 342 tons
CAPEX cost saving of approx. 60 MM DKK ( ~ 10 MM USD)
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Context Outcome
Challenge: reduce the subsea lines length without compromising well • Combined cost of 3 lines (water and gas injection and
productivity.
Subsea flexibles cost between 2100 to 6200 USD/metre (plus laying-out
service): 7900$/m, for a total reduction of 19.75MU$D
costs) • Estimated two weeks for deploying 2500m, with an
By repositioning the WH location, it was possible to reduce the lines associated cost of 4.2MU$D
length by 2500m in the two injection wells (1050m for LPA-NE-I2 and
1450m for LPA-NE-I3) • Added cost for deviating the wells (including added time and
For this purpose, both wells were redesigned to be J-deviated wells, material): 3.54MU$D
instead of vertical, with an estimated increase of 350m on the wells total Cost reduction: 20.4 M U$D (7.1MU$D Gshare)
length (each).
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Context Outcome
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
C-H de Lammerville
Contact
photo
Performance Stakes Solution
Integrated Contract Model The two main innovative aspects of the contract are as follow:
A fully integrated contract (rig unit + all associated services). One only interlocutor,
Lego Block Contract including civil works.
The contract model : scope of work was split into thirty individual tasks (also called ‘’lego
blocks”). For each given task the cost is pre-defined by lump-sums
A win-win contractual relationship by sharing risks and reward:
The drilling contractor bears the obligation of means and of results. He is intrinsically
driven for performance within each block to improve his revenue.
The operator drives the operational sequence, by deciding on way forward as made
necessary by the well condition and ‘’pilling-up’’ individual tasks as done with a ‘’lego
block’’
Context Outcome
Several contracts for drilling operations not The Lego Block contract is an excellent example of the
allowing optimisation and driving performance adaptability, inventiveness and cooperation between the
D&W and the C&P teams.
It lead to a cost reduction of 4 m$ out of an initial estimate
12 m$ campaign conducted by mid-2018 in onshore
Gabon
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Richard Oseme
Performance Stakes Solution
RIGLESS OPERATIONS Base case XTRT was modified and mini-IWOCS system designed to allow well
injectivity/stimulation operations to be done from OIMR vessel and not from the drilling rig
OIMR VESSELS WELL INJECTIVITY • CTR1 scope:
HPU container, controls umbilical, UTA, subsea power & communication skid and XTRT
• CTR2 scope:
chute, circulation umbilical, clamps, weak link system and connectors
Synergy: Interface engineering (e-room) was set up to resolve technical queries
between (Bourbon) OIMR vessel contractor and SPS CONTRACTOR (FMC)
Context Outcome
Use of OIMR vessels to avoid Rig mobilisation • Saving due to cost comparison for operations between
rig and OIMR vessel: 8 M$ (36 M$ versus 28 M$)
• Future cost savings when stimulation is performed
during life of field for wells with declining productivity
index: ~11 M$ /well based on FPSO results
PCI RM+#: - Ref: - Country: NIGERIA Asset: EGINA & AKPO 06/2016
Operations Fit for purpose
Drilling & Wells
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Stéphane Cambier
Performance Stakes Solution
Rigless Operations Base case XTRT was modified and mini-IWOCS system designed to allow well
Average time to
injectivity/stimulation operations to be done from OIMR vessel and not from the drilling rig
Oimr Vessels Well Injectivity • CTR1 scope: clean-up a well
HPU container, controls umbilical, UTA, subsea power & communication skid and XTRT
• CTR2 scope:
chute, circulation umbilical, clamps, weak link system and connectors
Synergy: Interface engineering (e-room) was set up to resolve technical queries
between (Bourbon) OIMR vessel contractor and SPS CONTRACTOR (FMC)
Context Outcome
Use the FPSO instead of Drilling rig cost
the rig for well clean-up savings
Use of OIMR vessels to avoid Rig mobilisation • Saving due to cost comparison for operations between $1.4MUSD/day
rig and OIMR vessel: 8 M$ (36 M$ versus 28 M$)
• Future cost savings when stimulation is performed
during life of field for wells with declining productivity
index: ~11 M$ /well based on Akpo results
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Steve Penot
Performance Stakes Solution
Batch Operation BATCH operations (30’’ CP and 17 ½’’ surface section) are main contributors of
Drilling Face Optimisation operation efficiency
Multi Well Optimisation First successful drilling fluid inhibition to prevent Gumbo attack on Torpille field
Most depleted reservoir ever drilled in Total Gabon
Innovative drilling bits and tools
First use of mechanical Casing Running Tool
Fast and safe learning curve despite new comer rig startup. Motivated and
proactive teams
Context Outcome
TRM campaign budgeted duration= 169 days* This initiative saved 9 days of rig time, which is
Actual situation: TRM campaign realized equivalent to 2 Million USD.
duration= 160 days*
Operations Performance
Drilling & Wells Management
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Mazen Badawi
Context Solution Lead Completion Engineer
During the engineering phase, the completion A dedicated data compiling reference cased hole CNS
team reviewed offset completion to fine tune completion activity has been created, to help future
upcoming activity. This step is crucial to define the completion engineer efficiently determining future well
best timing and therefore the future well cost. completion duration.
Without having reference document, it takes
around 5 days to evaluate the completion
duration for a well.
Outcome
With this database, this step took only 0.5 days now.
Assumption work for 2024 5 wells (CIA, WC, B1, G10Y, G6).
1000£/FTE = 4.5 (days)*3*1k£=22.5k£
PCI RM+#: - Ref: - Country: UNITED KINGDOM Asset: Central North Sea 2024
Operations Fit for purpose
Logistics
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Samuel Cunha
Performance Stakes Solution Ricardo Marquini
Gisele Mangifeste
Hybrid Vessel Start an R&D project to develop a cost-effective conversion model and
-1 m
Psv Hybride launch a start-up for mass conversions in Brazil.
Use the R&D levy from local regulations to cover all investment of a
Mgo Savings
project - 3.8 mUSD (forced investment). USD/yr
• Maximize OPEX & GHG benefits by using a long-term vessel from 40%
our fleet as the prototype to 1. benefit from fuel savings and 2. GHG
request rate discount from vessel owner.
• Start-up to use exclusively SAFT batteries as part of the
technology transfer - business development opportunity.
Context Outcome BIZ DEV
Opportunity
Battery packs for new build vessels optimize fuel GHG REDUCTION:
consumption by “peak shaving”. This reduces 5.5 KT CO2EQ/Y
OPEX REDUCTION :
GHG emissions and fuel costs. But the conversion $ 1M /Y
of existing vessels to hybrid battery power is $ 0.5 K / DAY – VESSEL CHARTER
$ 2.2 K / DAY – FUEL CONSUMPTION
today too expansive for industrial scale. BUSINESS DEVELOPMENT START-UP + SAFT
+300 VESSELS IN MARKET
INVESTMENT FULLY COVERED BY R&D LEVY (ANP)
BUILD ON MARINE INDUSTRY LEADERSHIP (CORP)
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Emmanuel OSIFO
Performance Stakes Solution Patrick SOMIARI
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Luiz PICONE
Cristina Marinho
Performance Stakes Solution Fernanda Schroder
Robson Costa
Hybrid Vessel • Negotiation with MGO supplier resulted in 3% discount on price, if we pay
Psv Hybride invoices within 15 days, instead of the standard 30 days. Standard - 30
Mgo Savings • Feasibility and cash impact were assessed by LSO, SC&LC, and Finance days
team, and the decision was to go for it.
Fast-track -
• Many interactions were made internally and with supplier, in order to 15 days
adjust UNISOL details (Contract/PO/Taxes) before the invoice is received.
Context Outcome
OPTIMIZATION
Project Team worked together to come up with a Volume of MGO received = 4000 m³
Strategy for the Aviation and Supply Base contracts that Discount of $14.8 per m³
reflected the LEAN concepts of MUDA elimination, Total savings = $ 59.2 k Opex = $ 14.8 k (25%)
considering the activity set and timing uncertaintites. Capex = $ 44.4 k (75%)
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
DW
- ktCO2e/y - kBOE/y 3.2 MUSD/y 2.8 MUSD - MUSD - MUSD
Luiz PICONE
Cristina Marinho
Performance Stakes Solution Fernanda Schroder
Robson Costa
WASTE of capacity
on each airframe.
Context Outcome
3
MGO invoices were paid in 30 days average
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
DW
- ktCO2e/y - kBOE/y 2.1 MUSD/y - MUSD - MUSD - MUSD
Luiz PICONE
Cristina Marinho
Performance Stakes Solution Fernanda Schroder
Robson Costa
The overall cycle FPSO-Uruguay-FPSO is estimated at 21 voyage days. The objective is to reduce the voyage
CRUDE OIL TRANSPORTATION, days owing to the following:
1/ accurate lifting scheduling (vessel arriving on time, FPSO having the stock in tank)
LIFTING SCHEDULING, 2/ optimization of embarkment / desembarkment of independent inspectors and custom surveyors (avoiding
SHIP TO SHIP OPERATIONS idle time at night in a port for instance)
3/ accurate STS scheduling (vessel arriving on time in STS area, conventional tanker ready and STS provider
ready)
This will be complemented in 2019 by:
1/ another transportation contract with lower daily rate
2/ STS area in Brazil (Açu port facility and also offshore Santos Basin or Bahia) avoiding lengthy voyage to
Uruguay
In addition, smart co-loading of both qualities (Lapa/Mero) is avoiding deadfreight.
All together, this represents a saving of 0.5 $/bbl in 2018 and an additional saving of 0.20 $/bbl in 2019 (in
normal weather conditions)
Context Outcome
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
DW
- ktCO2e/y - kBOE/y -0.06 MUSD/y - MUSD - MUSD - MUSD
Sabtu JAMADULIN
David FLAJOLET
Solution Nigel ANG
• Alternative solution is to provide Onshore Electrical power to vessels directly at the Jetty
• Onshore Electrical supply will not only reduce cost but also eliminate associated emissions (Nox, Sox and CO2) by using more
efficient shore based facilities
• Following deployment of the Shore Base Electrical Power in Muara Logistic Base in April 2018, Fuel consumption at the jetty
was reduced to 0 and overall fuel consumption reduced by more than 20%
• The financial effect is significant as Electrical consumption is included in the current contract with the Base Operator
• Next step is to anticipate the future need when the fleet grows during drilling campaign in order to dimension adequately
power capacity at the Logistic Base
Saving expected at 65,000USD per year
Context Outcome
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
DW
- ktCO2e/y - kBOE/y -1.2 MUSD/y - MUSD - MUSD - MUSD
Laura REY
Solution
Sublet a supply vessel to neighbor operators during a TEP I will optimize my planning and go
Austral stand-by period of time to other operators to offer them a
sublet agreement
Outcome
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Guilherme Resende
Marcos Fernando Silva
Ballot to communicate to the
partners and requesting for
approval to proceed with the
material scrap process.
Stock Materials from
Let´s follow Lapa sold for scrap
the right
steps… Scrap BRL 271,124 Outcome
Dealer
(USD50,904)
LAPA The SCLC buyer initiates a BID
Expected Monthly Saving
The TADM is responsible to in search of the best offer to Benefits/key results linked to
sell the scrap items. Area R$/m2 Total Value
approve the list of dead stock
or damaged items to be sold as objectives is cost saving mainly on :
124 R$ 41.33 R$ 5,124.92
scrap.
• Plant refurbishment: With gain Up
I have these stock
materials in LAPA.
to 2025 – 0,42 M$;
• On demande : With gain Up to
We do! We can buy it
I need to do some Ballot to communicate the from you.
optimizations partners and requesting for
approval. 2025 – 0,12 M$;
Stock Materials from Lapa sold
to C-M-541
CM541
According to the SCLC stock
process, you can do a scrap BRL 739,073 (USD138,763)
sale for the damaged and
deadstock and a transfer for Communication to CM541
LAPA stock materials inspected
other projects you have for the partners about material
and ready to be transferred for
items in good conditions of use. transfer and payment from
another Project.
CM541 budget the to the
LAPA project.
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Contract
Procurement
& Procurement
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Wilfried VANDERSIPPE
Solution
Outcome
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Outcome
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Outcome
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Contact
photo Michel Javault
Performance Stakes Solution
Interbranch mutualization
E&P: “We refurbished our office building
E&P in Libreville. We have room available, why
not sharing it with the MS branch “
Outcome
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Laurent WOLFFSHEIM
Context Solution Managing Director at TEPQ
"QUWA" (which stands for "power" in Arabic), is Key Focus Areas to enhance the profitability, maintain the
a companywide project aimed at exploring new competitiveness and ensure that Al Khalij field is fit for the
operating models for Al Khalij with clear target future:
to improve the cash contribution for Total, while Enhance the safety and operational excellence by developing staff
maintaining the safety and operational excellence People competence and learning agility, and maintaining the highest safety
as the sole operator of Al Khalij field. standards.
Strengthen the operational efficiency by optimizing production/
Performance maintenance/inspection processes, costs, organization, and challenging
Outcome current model and standards.
Think out the box and promote initiatives towards technical innovations
Innovation
and digital, and ”make the difference”
A Lower Cost Operating model without compromising HSEQ
Objectives : Develop the ability to change mindset, working habits, behavior
Culture
• Additional Barels and increased productivity and to adapt to new model and to Company transformation
• Safe and sustainable low-cost operations
• A digital and leaner organisation
Estimated Savings : ~ 9.5M$ over 2019 - 2020
Disclaimer
This presentation may include forward-looking statement within the meaning of the Private Securities Litigation Reform Act of 1995 with
respect to the financial condition, results of operations, business, strategy and plans of TotalEnergies that are subject to risk factors and
uncertainties caused by changes in, without limitation, technological development and innovation, supply sources, legal framework, market
conditions, political or economic events.
TotalEnergies does not assume any obligation to update publicly any forward-looking statement, whether as a result of new information, future
events or otherwise. Further information on factors which could affect the company’s financial results is provided in documents filed by
TotalEnergies with the French Autorité des Marchés Financiers and the US Securities and Exchange Commission.
Accordingly, no reliance may be placed on the accuracy or correctness of any such statements.
Copyright
All rights are reserved and all material in this presentation may not be reproduced without the express written permission of TotalEnergies.
DRAPEAU
Production
GHG Reduction optimisation OPEX Cost Vigilance CAPEX Cost Vigilance Cash Optimisation Productivity * Asset Location
Please comment if a risk analysis was necessary Reason why this project has been undertaken
and its main outcomes. Link to it if necessary. Stakeholders involved or to be informed
X 6 lines max Different steps to achieve the initiative
X 6 lines max Difficulties or attention points
X 6 lines max Solutions found (main solution first 3 lines)
X 6 lines max
Project
Context Outcome
image
Initial situation. Benefits/key results linked to objectives.
Quick description of the environment and context. Change/improvements after implementation of the solution
Mention challenges. X 6 lines max
Area of Improvement and objectives. X 6 lines max
X 6 lines max X 6 lines max (* Productivity estimation based on xxxx)
X 6 lines max
Request For Modification All initiatives related to RFM process : discipline in selection of modifications, asset plan challenge
All initiatives related to contracting and purchasing contracting strategy; commercial negotiation;
Procurement
collaboration model with supplier; contract management
Mutualization & Sharing All initiatives related to optimization of means : mutualization of activities, equipment and staff,
Affiliate, operators between branches, affiliates and/or operators ; GPI synergies
All initiatives related to optimization of stock value : supply strategy; dead/non-moving stock
Stock Management
management
Integrated Planning All initiatives related to efficiency in activity planning and scheduling
Levers Definitions
All initiatives related to performance management & control : KPI & Dashboard monitoring;
Performance Management performance incentive; deviation analysis (NPT, consumables..); procedure compliance, budget
Objectives follow up, KPI
delegation, SAP process
R&D & Innovation All initiatives related to Research & Development projects
All initiatives related to support of TGP to Affiliates (C&P entities, incl. stock management) and
Assistance TGP
Headquarter
Lean
Processes optimization All initiatives related to optimization of processes : lean operations; lean office