SCAN TO BIM EXECUTION PLAN & CHECKLIST
NO. PROJECT DETAILS INFORMATION REMARKS
1 Project Name
2 Project Number
LOD 100 /
3 Project LOD LOD 200 / LOD 300 /
LOD 400 / LOD 500
Scope of Work (Trades to be
4
Included/Excluded)
5 Input File Format
6 Revit 3D or 2D CAD or Both
7 Recap Validation
Refurbishment/
8 Intended Use of Model Renovation/
Retrofit/Other
9 Final Deliverable Format
Ver9July2020
The Checklist provided here is offered strictly as a tool for your use. It is in no way meant to be construed as an all -
encompassing checklist nor as a replacement for other checklists that are required by any government bodies.
[email protected] 1 of 5
www.united-bim.com
Date : / /
SCAN TO BIM EXECUTION PLAN & CHECKLIST
COMPLY
NO. CHECKPOINT REMARKS
YES NO N/A
1 LEVEL OF EFFORT
1.1 Architectural
1.1.1 Establish Levels/Elevations
1.1.2 Establish Walls
1.1.3 Establish Doors
1.1.4 Establish Windows/Storefront
1.1.5 Establish Roofs
1.1.6 Establish Ceiling
1.1.7 Establish Plumbing Fixtures
1.1.8 Establish Millwork
1.1.9 Establish Furnitures
1.2 Structural
1.2.1 Establish Foundation/Footings
1.2.2 Establish Floors/Slabs
1.2.3 Establish Roofs
1.2.4 Establish Openings
1.2.5 Establish Columns
1.2.6 Establish Beams
1.2.7 Establish Braces
1.2.8 Establish Angles
1.2.9 Establish Concrete Walls
Ver9July2020
The Checklist provided here is offered strictly as a tool for your use. It is in no way meant to be construed as an all -
encompassing checklist nor as a replacement for other checklists that are required by any government bodies.
[email protected] 2 of 5
www.united-bim.com
Date : / /
SCAN TO BIM EXECUTION PLAN & CHECKLIST
COMPLY
NO. CHECKPOINT REMARKS
YES NO N/A
1.3 MEPFP
1.3.1 Mechanical
(i) Establish HVAC Panels
(ii) Establish Ducts
(iii) Establish Air Terminals
(iv) Establish Mechanical Equipment (Exhaust Fan,
Diffuser, Heaters, AC Units)
(v) Establish HVAC Piping
1.3.2 Electrical
(i) Establish Cable Trays
(ii) Establish Conduits
(iii) Establish Electrical Distribution Equipments
(iv) Establish Lighting Fixtures
(v) Establish Electrical Panel Board
(vi) Establish Electrical Transformers
1.3.3 Plumbing
(i) Establish Piping
(ii) Establish Plumbing Equipment
(iii) Establish Plumbing Fixtures
(iv) Establish Gas Piping
(v) Establish Roof Drain
(vi) Establish Down Spout
1.3.4 Fire Protection
(i) Establish Alarm
(ii) Establish Exit Lights
(iii) Establish Fire Sprinklers
Ver9July2020
(iv) Establish CCTV
The Checklist provided here is offered strictly as a tool for your use. It is in no way meant to be construed as an all -
encompassing checklist nor as a replacement for other checklists that are required by any government bodies.
[email protected] 3 of 5
www.united-bim.com
Date : / /
SCAN TO BIM EXECUTION PLAN & CHECKLIST
COMPLY
NO. CHECKPOINT REMARKS
YES NO N/A
2 MODEL SETUP
2.1 Project North
2.2 Assign View Template
2.3 Establish Working Views
2.4 File Naming Convention (As per BEP)
2.5 Verify Common Data Environment(CDE)
Requirements
2.6 Worksets Naming Convention
3 POINT CLOUD SCAN
3.1 Point Cloud Scan Format
3.2 Point Cloud Scan Linked
3.3 Geo-Image Referencing
3.4 Coordinates
3.5 Alignment Verification
3.5.1 Grids Alignment
3.5.2 Levels Alignment
3.5.3 Model Alignment
Ver9July2020
The Checklist provided here is offered strictly as a tool for your use. It is in no way meant to be construed as an all -
encompassing checklist nor as a replacement for other checklists that are required by any government bodies.
[email protected] 4 of 5
www.united-bim.com
Date : / /
SCAN TO BIM EXECUTION PLAN & CHECKLIST
COMPLY
NO. CHECKPOINT REMARKS
YES NO N/A
4 REVIT CHECK
4.1 Revit File Setup
4.1.1 Create a RVT File
4.1.2 Append RVT Models
4.1.3 Verify Correct Coordinates/Positioning
4.2 Viewpoints Generation
4.2.1 Create Folder with Date
4.2.2 Create All Viewpoints
4.2.3 Correct Models acc. to the Viewpoints
4.2.4 Update RVT Models
4.2.5 Rename the Viewpoints
4.3 Model Clean up
4.3.1 Open as an Individual File
4.3.2 Preserve AEC Worksets
4.3.3 Delete Outsource Worksets
4.3.4 Delete Unnecessary Views
4.3.5 Delete Unnecessary Planes
4.3.6 Delete Unnecessary Groups
4.3.7 Purge File
4.3.8 Audit File
Ver9July2020
The Checklist provided here is offered strictly as a tool for your use. It is in no way meant to be construed as an all -
encompassing checklist nor as a replacement for other checklists that are required by any government bodies.
[email protected] 5 of 5