Co-Project Management Essentials
Co-Project Management Essentials
a. skills, analysis
b. tools, analysis
c. analysis, theories
d. skills, tools
e. skills, theories
Answer: d Ask his client to conduct an inspection on all of the completed project
deliverables
a. Pareto diagram
b. PERT chart
c. Control chart
d. HR personnel chart
e. Critical path
5. Once the project is approved and moves into the planning stage, what
happens in the next phase of the project life cycle?
6. Fill in the blank. Risk must be considered in the _____ phase and weighed
against the potential benefit of the project’s success in order to decide if the
project should be chosen.
a. completion
b. closeout
c. execution
d. planning
e. initiation
Answer: e initiation
8. Why does the creation of processes for developing teams, establishing
priorities, and distributing work and tasks require different sets of skills?
10. The project management office (PMO) handles all of the following
functions EXCEPT:
Answer: c assigning project managers from other departments but not procuring
contract project managers.
11. Under which of the following conditions would teams be more effective
than individuals?
a. Benchmarking
b. Expediting
c. Procurement
d. Delegation
e. Solicitation
Answer: d Delegation
13. Which of the following defines what tasks the project resources are
expected to accomplish and, just as importantly, what is not part of the
project team’s responsibilities?
a. Punch list
b. Check sheet
c. Project logic diagram
d. Checklist
e. Scope document
15. Fill in the blank. There is _______ correlation between project complexity
and project risk.
a. an unknown
b. a positive
c. no
d. a negative
e. a general
Answer: b a positive
Answer: b start to define and develop the stakeholder needs and requirements.
19. Fill in the blank. During the _________ of a project, the project manager
focuses on developing the project infrastructure needed to execute the project
and developing clarity around the project charter and scope.
a. completion
b. start-up
c. execution
d. evaluation
e. selection
Answer: b start-up
20. A project budget estimate that is developed with the least amount of
knowledge is known as which of the following?
23. Complete the following statement. As the project progresses into the
execution phase:
Answer: a risks need to be checked off on activities that have been performed.
25. Which of the following is typically a written document that defines what
work will be accomplished by the end of the project?
a. Scope of work (SOW)
b. Project logic diagram
c. Milestone schedule
d. Ballpark estimate
e. Work breakdown structure
26. What is considered to be the most useful skill for a project manager who
works in a matrix environment in order to achieve project goals?
a. Leadership skill
b. Influencing
c. Conflict management skill
d. Time management
e. Planning skill
Answer: b Influencing
27. Marco is an investor, and Jon is a project team member. Both have
intensive technical background for the project that you are managing.
However, recently they have disagreed on the next step to take for the project.
They both decide to defer to whoever has the authority to make this decision.
Who has the authority to decide which direction should be taken for the
project?
a. Project manager
b. Stakeholders
c. The project team
d. Investors
e. The board of trustees of this company
28. As a project manager, while Kathy was trying to categorize all potential
risks for her new construction project M based on levels of probability and
impact on the project, she identified a potential risk, regarding a schedule
conflict with another project to obtain critical equipment for a short time
period. Overall, because this risk is probable and might impact her project M,
Kathy wants to record this risk; however, she is confused about where she
should document this type of risk. According to the PMBOK guide, where
should Kathy document this risk?
a. Watch list
b. Risk management plan
c. Project management plan
d. WBS
e. Scope management plan
Answer: d WBS
29. Which of the following is a quality management system that gives titles to
specialists and requires a cost-benefit analysis?
a. Lean accounting
b. Business process re-engineering
c. Kaizen
d. Six Sigma
e. Total Quality Management
30. Which one of the following is the last step of project closings?
a. Objective credibility
b. Attribution of benevolence
c. Non-manipulative trust
d. High cost of lying
e. Acknowledgment of munificence
37. When a project manager starts to plan a new project budget, the cost of
which project management process group is expected to be lowest?
a. Initiating
b. Executing
c. Monitoring and controlling
d. Closing
e. Planning
Answer: d Closing
41. According to the Project Management Institute (PMI), the scope statement
should address all of the following issues EXCEPT:
a. project constraints.
b. project assumptions.s
c. project exclusions.
d. code of conduct for the team members working on the project.
e. project deliverables.
Answer: d code of conduct for the team members working on the project
42. Fill in the blank. The _____ is the difference between the additional money
spent on prevention and the corresponding reduction in the cost of failure.
a. cost-benefit analysis
b. implicit cost
c. cost of quality
d. variable cost
e. cost-utility analysis
43. Which of the following project baselines provides the basis for
measurement of the expected cash flow against requirements over time and is
often displayed as an S curve?
a. Schedule baseline
b. Cost performance baseline
c. Scope baseline
d. Plan baseline
e. Initiation baseline
44. The conceptual estimate is developed with the least amount of knowledge.
When more information is known, the project team can develop a:
a. Most flowcharts use one width of column to represent a category, while the
vertical axis represents the frequency of occurrence.
b. If a particular method is a standard of quality, you can compare your
organization’s quality plan to it by flowcharting.
c. A flowchart shows the ratio of cost of increasing quality to the resulting benefit.
d. If some of the functions of a project are repetitive, flowcharting can be used to
identify trends.
e. Flowcharting is useful for communicating responsibility for work processes.
47. During the project meeting, the project manager had to leave earlier due
to a family emergency. Afterwards, a few team members started to argue, so
the project meeting took very long without producing outcomes. What is the
possible reason that resulted in the inefficient project meeting in this
scenario?
50. Fill in the blanks. It is during the ______________ phase that the decision
should be made regarding whether the project should continue. During this
phase, ____________ must be considered and weighed against the potential
benefit of the project’s success.
a. completion, cost
b. closeout, resources
c. execution, performance
d. planning, timing
e. initiation, risk
Answer: e initiation, risk
51. What is the most critical aspect in developing a project plan that meets
project specifications within the timeframe and at the lowest costs?
Answer: e Developing a project execution plan that matches the complexity level
of the project
52. Fill in the blank. Risk represents the likelihood that an event will happen
during the life of the project that will negatively affect the ________________
of project goals.
a. scope creep
b. achievement
c. float
d. rough order of magnitude
e. slack
Answer: b achievement
53. What should be done by the project manager to ensure that all the work in
the project is included?
a. completion
b. start-up
c. execution
d. evaluation
e. selection
Answer: b start-up
a. Continue to increase the intensity of the project to achieve the next milestone.
b. Continue to follow the exact same project plan that helped the team achieve the
milestone.
c. Allow the team to reflect on finding new ways of approaching the project work.
d. Select an upcoming key event and designate it as the next milestone.
e. Stretch the goals of the project team, making them more tough and rigorous.
Answer: c Allow the team to reflect on finding new ways of approaching the
project work.
56. Once the project is approved and moves into the planning stage, what
happens in the next phase of the project life cycle?
58. Fill in the blank. Risk must be considered in the _____ phase and weighed
against the potential benefit of the project’s success in order to decide if the
project should be chosen.
a. completion
b. closeout
c. execution
d. planning
e. initiation
Answer: e initiation
60. Determining the policies that are needed for the smooth execution of a
project relates to which of the following agenda items of alignment sessions?
a. They are short meetings to develop a common understanding of what the short-
term priorities are for the project.
b. They focus on short-term activities, usually less than a week in duration.
c. They are purely fact-based meetings with a left-brain type focus.
d. They have very little dialogue except to ask clarification questions.
e. They are oriented toward developing plans, tracking progress of existing plans,
and making adjustments to plans in response to new information.
62. Do it because I said to” is the mantra for project managers who use _____
as the default approach to resolve conflict.
a. collaborating
b. compromising
c. accommodating
d. forcing
e. avoiding
Answer: d forcing
63. A(n) _ is a review of the quality plan, procedures, data collection, and
analysis by an outside group.
a. scope document
b. project appraisal
c. cost performance index
d. analogous estimate
e. quality audit
a. They are the filters through which project members screen information that is
shared.
b. They do not lend themselves to create an environment of trust.
c. The success of larger, more complex projects is more dependent on contracts
than on relationships of trust.
d. Without contracts, projects that are highly dependent on an information-rich
environment will suffer.
e. Contracts promote the growth of a trusting project culture.
a. communication planning.
b. key milestones.
c. work flow organization.
d. approval processes.
e. role boundary spanning processes.
70. Shauna has recently been appointed as a project manager for Project
SkyNorth, which is regarded as an important project in her organization.
During the project planning meeting, Shauna is capable of allocating key
resources and personnel that she needs for this project. Which organizational
structure is best for Shauna’s company?
73. Which of the following establishes key dates throughout the life of a
project that must be met for the project to finish on time?
a. Critical path
b. Ballpark estimate
c. Pert diagram
d. Slack chart
e. Milestone schedule
Answer: e Milestone schedule
a. Project risk focuses on identifying, assessing, and eliminating the risks on the
project.
b. Risk management is all about eliminating risk.
c. Project risk is an uncertain event that, even if it occurs, has no effect on project
objectives.
d. There are no risk-free projects.
e. Risk management involves identification, evaluation, and elevation of risk
a. To understand reports
b. To reflect new information
c. To begin planning the project
d. To teach team members what they need to know about their jobs
e. To establish a trusting project culture
76. Fill in the blank. Crashing refers to when the task duration’s are __ along
the critical path to meet the project completion date.
a. scope creep
b. floated
c. slack
d. compressed
e. expedited
Answer: d compressed
78. Which of the following is a form of trust that is built on the examination of
the person’s motives and the conclusion that he or she is not hostile?
a. Objective credibility
b. Attribution of benevolence
c. Non-manipulative trust
d. Unequivocal liberality
e. High cost of lying
80. Fill in the blank. A __ represents the sequence of the activities needed to
complete the project.
answer (D)
answer (B)
Q. Assembling project team and assigning their responsibilities are done during
which phase of a project management?
(A) Initiation
(B) Planning
(C) Execution
(D) Closure
answer (D)
answer (C)
answer (C)
answer (A)
2. Functional managers
3. The customer
4. Both a and b
Answer:D
(2)The decision to request an increase the resources for a project is the
responsibility of the:
1. Functional manager
2. Project manager
4. Customer
Answer: B
(3)In which of the following project phases is the project schedule developed?
1. Conceptual
2. Planning
3. Implementation
4. Design
Answer: B
(4)To crash a schedule you should:
2. Try to increase expenditures of time only those tasks that are behind
schedule.
3. Replace those worker that are not performing up to par with the busy.
4. Increase work efforts on those tasks that are on the critical path.
Answer:D
(5)The project scope statement furnishes the basis for:
Answer:A
(6)Which of the following is NOT one of the primary needs for good project
scheduling?
Answer: D
(7)The time necessary to complete a project is referred to as:
1. Implementation time
2. Life cycle
3. Operations cycle
4. Production cycle
Answer: B
(8)The successful project managers spend most of their time:
Answer: C
(9)Resource leveling attempts to :
3. Reduce the amount of resources so that they can be shared with on other
endeavors.
4. Increase the amount of the project manager's authority so that budget dollars
can be appropriated.
Answer: A
(10)A prerequisite of effective time management is:
1. Knowing the dictated project completion date
2. Having the most advanced software package for project planning, scheduling
and control
3. Having a good project WBS which identifies the major project deliverables
and tasks, and the person responsible for each of them
Answer: A
(1) Which type of project cost estimate is the most accurate?
1. Preliminary
2. Definitive
3. Order of magnitude
4. Conceptual
Answer:B
(2)Which of the following type of contracts is most preferable to the contractor
doing the project work?
1. Cost plus fixed fee
2. Fixed price
4. B and C
Answer: A
(5)Cost budgeting can be best described by which of the following?
1. The process of developing the future trends along with the assessment of
probabilities, uncertainties, and inflation that could occur during the project
2. The process of assembling and predicting costs of a project over its life cycle
Answer:C
(6)Which of the following is a direct project cost?
1. Lighting and heating for the corporate office
4. A and B
Answer: C
(7)Cost controls can be best described by which of the following?
1. The process of developing the future trends along with the assessment of
probabilities, uncertainties, and inflation that could occur during the project
2. The process of assembling and predicting costs of a project over its life cycle
3. The process of assembling and predicting costs of a project over its life cycle
Answer: D
(10)Life Cycle Costing is a term that is:
1. used when making decisions between alternatives
5. A and B
Answer: E
(1) Measured quality of a manufactured product is :
1. Always constant
2. Continually decreasing
4. Continually increasing
Answer:C
(2)The process control charts are used:
2. variables
3. attributes
4. properties
Answer: B
(4)Which of the following is the most efficient means of product quality
inspection?
1. Acceptance sampling
2. 100% inspection
3. Variable sampling
4. a and c
Answer:C
(5)The primary components of the quality management function are :
1. quality planning
3. quantitative measurement
5. a and b
Answer:E
(6)Setting the number of defects before the lot is rejected, is a direct
responsibility of :
1. a functional worker
2. the project manager
3. management
Answer: C
(7)Which of the following has the greatest effect on product's reliability and
maintenance characteristic?
1. conceptualization
2. product design
3. fabrication
4. a and b
Answer: D
(8)On a project the project manager should strive for a "Quality Level" that :
Answer: B
(9)Quality control in the final analysis is :
2. a production system
3. an inspection system
5.
Answer: A
(10)Quality costs include :
1. the total of all costs incurred to assure the production and delivery of
acceptable products and services.
3. Only the cost of scrap, rework due to defects, customer returns and warranty
costs.
Answer: A
(1)From HR perspective, the project manager's responsibility in the planning
role includes:
3. Forecasting
4. Feedback sessions
5. Both b and c
Answer:E
(2)Expert power is the power that comes from the amount of knowledge a person
has obtained in a specific area. This type of power is:
1. Critical to a project manager because the PM has to have as much or more
knowledge than any of the team members to make sure the project is completed
successfully
3. Important if the project manager wants to maintain the respect of the project
team
4. Used sparingly if at all by the PM because the PM cannot stay current on all
areas of expertise and also manage the project
Answer: D
4)To successfully manage a project, the PM must play both a manager and
leadership role. In the manager role the PM will do all but which of the following:
1. Develop procedures
2. Align people
5. Both b and d
Answer:B
(5)To be successful in a functional organization, the PM must rely on:
1. Referent power
2. Formal authority
5. Both a and c
Answer:E
(6)Which form of power is the LEAST effective from the project manager's
viewpoint in terms of influencing functional managers?
1. Formal power
2. Expert power
3. Penalty power
4. Referent power
Answer: C
(7)The Project manager should be able to fulfill the role of:
1. an integrator
2. a functional manager
3. a line manager
4. a sponsor
Answer: A
(8)The most successful project manager usually:
1. works their way up from assistants in the project office to full-fledged project
managers, supplementing that experience with formal education.
2. Comes right from Harvard's MBA program into managing very large
projects.
Answer: A
(9) Which of the following is an important action that must be taken by top
management when implementing project management in an organization?
5.
Answer: D
(10)The project manager has the most authority in the __________________ type
of organization.
1. Project expediter
2. Matrix
3. Projectized organization
4. Functional
Answer: C
(1)Which of the following can cause a communication barrier?
5. Resistance to change
Answer:F
(2)Most of the project manager's external communication links consist of:
1. Written documents
2. Oral communication
3. Tactile contact
4. Informal contact
1. Progress report
2. Project directive
3. Project manager
4. Customer
Answer: C
(4)Communication management:
2. Is not a big problem for people with normal speech, sight and hearing
3. Involves the originator, the message, the medium and the receiver
4. Preparing an agenda
Answer:C
(5) Truly effective communication:
2. Depends on selecting the right method for each message and avoiding
duplication, since everyone is overloaded with information
5. a, b and c
Answer:E
(6)Methods of transmitting include:
2. Non-verbal/ visual
Answer: D
(7)A project management information system consists of:
Answer: D
(8) The process of communication contains four major parts. Which part is the
vehicle or method used to convey the message?
1. Communicator
2. Message
3. Medium
4. Recipient
Answer: C
(9) The contemporary view of conflict is that:
1. Conflict is bad
Answer: D
(10)Approximately what percentage of the project manager's time is spent in
some form of communication, such as: conferences, meetings, writing memos,
reading and preparing reports, and talking with project team members, upper
management, and all other stalk holders?
1. 10-20%
2. 50-70%
3. 75-90%
4. 21-45%
Answer: C
(1)PMI states that there are two risk types : business and insurable. Which of
the following are considered insurable risks?
2. Opportunity costs
3. Sunken costs
5. A and D
Answer:F
(2) The Three attributes of project risk are _________, ___________ and
___________.
1. What might happen, who it happens to, and how much will it cost
Answer: E
(3)A risk is defined as what might happened to the ____________ of the project
1. assessment
2. detriment
3. schedule
4. cost
5. scope
Answer: B
(4)When is the project's amount at stake the lowest
1. conceptual
2. design
3. close-out
4. implementation
Answer:A
(5)A new project was initiated that involves new technology and subsequently has
never been done before. What type of contract would to owner want to issue to
reduce or eliminate as much risk as possible.
1. Firm fixed price
4. Lump sum
5. A and D
Answer:E
(6)What is the most accurate method of obtaining project information that can
reduce the amount of risk?
1. Observations on the current project
3. The use of historical data from previous projects that were similar in nature
4. Sensitivity analysis
5. Delphi technique.
Answer: C
(7)Which of the following fit the category of external risks?
Answer: B
(8)Decision trees are best used for :
1. Determining the interaction of the amount at stake and the expected value
4. A flow chart which determines the standard deviation of the risk event
Answer: C
(9)The total amount of risk that is calculated for a project is found by
1. Multiplying the sum of each the risk times the amount at stake
2. Calculating the cumulative sum of the probability for each risk and
multiplying this value times the consequence of occurrence of the risk events
Answer: B
(10)A situation in which one of two or more risk events will follow an act, but the
precise nature of these events may not be known and the probabilities of their
occurring cannot be objectively assigned, is the definition of
1. certainty
2. uncertainty
3. risk
4. risk adversity
Answer: B
(1)The fixed price contract is advantageous to the buyer because it:
Answer:C
(2)The contract administration function includes:
1. funding management
3. performance control
Answer: D
(3)The major type(s) of standard warranty(ies) that are used in the business
environment is(are):
1. express
2. implied
3. negotiated
4. a and b
Answer: D
(4)A Unit Price (UP) contract provides:
4. a fixed price where the supplier agrees to furnish goods and services at unit
rates and the final price is dependent on the quantities needed to carry out the
work.
Answer:D
(5)Which phase of the Acquisition Process Cycle does source qualifications
reside?
1. Pre-Award
2. Award
3. Post Award
4. Origination
Answer:B
(6)From a contract management perspective, the project manager must consider
the:
1. acquisition process
2. contract administration
3. ecological environment
5. a and b
Answer: E
(7) A performance bond should always provide what part of the contract value?
1. 10 percent
2. 25 percent
3. 50 percent
4. 100 percent
5. Normally a performance bond, depending upon the state, only stipulates that
the contractor will guarantee the work for a certain period of time.
Answer: D (8)Which contract type places the most risk on the seller?
Answer: E
(9)What are the types of express guarantees?
1. Design/ mechanical
2. Field workmanship
3. Common Work
4. Length of service
5. a and b
Answer: E
(10)What is the last item a project manager must do to finalize project close-out?
1. Reassign the team
2. Contract completion
Answer: B
(1) A planning method, which provides details of the work to accomplish, but
also provide some preliminary description of the work to be done in later phases is
called :
1. Progressive detailing
2. Rolling wave
3. Strategic
4. Operational
Answer:B
(2)Another name of strategic planning is:
1. Short term
2. Operational
3. Tactical
4. Top down
Answer: D
(3) The type of planning that is equated with more specific data or detailed in
nature is called:
1. Strategic
2. Operational
3. Short term
4. Tactical
Answer: D
(4) One of the initial project documents, issued by senior management, which
outlines the authority of the project manager, is called Project charter. As a seller,
what other document can be used in this place:
2. Project scope
3. Contract
4. Internal memo
Answer:C
(5) During the planning development process, at times it is necessary to make
certain assumptions to enhance the project plan when the data is not available. In
regard to making those assumptions, which one of the following is most true for
project planning purposes?
3. Project assumptions are based upon historical data used for the project.
Answer:A
(6)A project planning methodology is any structured approach used to guide the
project team during development of the project plan. What is an example of this
methodology?
4. Stakeholders skills
Answer: A
(7)The engineer of the project in the planning phase and makes a significant
contribution to the technical scope. This is an example of what type of skill and
knowledge?
1. Inherent
2. Stakeholder
3. Technical evaluation
4. Convergent thinking
Answer: B
(8)In a program or project plan, there are always revisions to account for new or
missing data. Which one of the following provides the best reason for performing a
revision of the plan?
1. A supplier has changed the way their product is delivered to your supplier
4. Historical data on a similar project suggests that risk events are not included
in the current plan.
Answer: B
(9) The project closing process is essential to overall project planning. What is
considered one of the most important steps in closing the project?
Answer: D
(10)Each project phase is marked by completion of one or more:
1. Tasks.
2. Milestones
3. Deliverables
4. Life cycles
Answer: C
(1)The Scope Statement should contain which of the following?
1. Project schedule
4. Project objectives
Answer:D
(2)The Scope Management Plan is included in which of the following
documents.
1. Project Plan
4. Project Specifications
Answer: C
(3) Project Scope:
3. Should be managed and controlled from the project concept through close-
out
4. is usually not a problem after the contract or other document authorizing the
project has been approved.
Answer: C
(4) The Project charter is created by:
2. Upper management
4. The customer
Answer:B
(5)The project scope statement furnishes the basis for:
Answer:A
(6) The Scope Baseline is:
Answer: B
(7)A Project control system:
1. Monitors and controls the project's schedule, costs, scope, budgets etc
Answer: A
(8)The PM distributed a document to the stakeholders, which described the
software to be developed, the functionality, the users it would serve and the
installation timeline. The document was an example of:
1. Product scope
2. Project scope
Answer: D
(9)Each item of the Work Breakdown Structure is assigned a unique identifier.
What is the name of this identifier?
1. Product ID number
2. Code of accounts
2. Cost/benefit analysis
3. Project deliverables
4. Measurable objectives
Answer: A