Excavation and Earthworks: Bill No. 1 Element No. 1 SUBSTRUCTURE (All Provisional)
Excavation and Earthworks: Bill No. 1 Element No. 1 SUBSTRUCTURE (All Provisional)
ELEMENT NO. 1
SUBSTRUCTURE (All Provisional)
Excavation and Earthworks
C. Excavate for matt foundation not exceeding 3m depth 2012 CM 450 905,400.00
E.
G. Load and cart away excess excavations as directed 1128 CM 500 564,000.00
Filling
H. Approved imported hardcore filling rolled and
consolidated in layers not exceeding 300mm thick
1518 CM 1500 2,277,000.00
(300mm average)
I. 50mm thick murram blinding 820 SM 200 164,000.00
1/1
Project Name: Proposed BoQ for the Research and Training Hospital Kirnyaga University
Client: Kirinyaga University
By: Mutuse Richard Kituu, EE101/G/9848/20 . Bachelor of Technology Construction and Prpoerty Management (C.P.M)
Fabric mesh
I. Fabric mesh Ref. No. A142 (measured net) (No
allowance for laps) 2012 SM 800 1,609,600.00
M. Edges of slab between 75mm and 150mm high 315 LM 200 63,000.00
1/2
Project Name: Proposed BoQ for the Research and Training Hospital Kirnyaga University
Client: Kirinyaga University
By: Mutuse Richard Kituu, EE101/G/9848/20 . Bachelor of Technology Construction and Prpoerty Management (C.P.M)
ELEMENT NO. 2
SUPERSTRUCTURE CONCRETE
1/3
Project Name: Proposed BoQ for the Research and Training Hospital Kirnyaga University
Client: Kirinyaga University
By: Mutuse Richard Kituu, EE101/G/9848/20 . Bachelor of Technology Construction and Prpoerty Management (C.P.M)
Beam
E T 16 Bars 33780 KG 250 8,445,000.00
F T 8 Bars 7440 KG 250 1,860,000.00
Columns
G T 25 Bars 45789 KG 250 11,447,250.00
H T 8 Bars 2980 KG 250 745,000.00
Stair
T 10 Bars
Sawn formwork to:
Soffits of suspended slab 59 SM 650 38,350.00
I Sides and soffits of ring beams 413 SM 650 268,450.00
Soffits of stair 208 SM 650 135,200.00
J Sides of columns 304 SM 650 197,600.00
ELEMENT NO. 3
1/4
Project Name: Proposed BoQ for the Research and Training Hospital Kirnyaga University
Client: Kirinyaga University
By: Mutuse Richard Kituu, EE101/G/9848/20 . Bachelor of Technology Construction and Prpoerty Management (C.P.M)
walls
wall
C. 150mm thick wall on the ground floor partitions. 192 SM 2000 384,000.00
ELEMENT NO. 3
ROOF
Roof Covering
1/5
Project Name: Proposed BoQ for the Research and Training Hospital Kirnyaga University
Client: Kirinyaga University
By: Mutuse Richard Kituu, EE101/G/9848/20 . Bachelor of Technology Construction and Prpoerty Management (C.P.M)
B. Extra over for ridge and hip cap to match 72 LM 500 36,000.00
Eaves Finishes
Wrot celcured prime grade cypress in:
Metalwork
Rainwater goods
1/6
Project Name: Proposed BoQ for the Research and Training Hospital Kirnyaga University
Client: Kirinyaga University
By: Mutuse Richard Kituu, EE101/G/9848/20 . Bachelor of Technology Construction and Prpoerty Management (C.P.M)
COLLECTION
DOORS
1/7
Project Name: Proposed BoQ for the Research and Training Hospital Kirnyaga University
Client: Kirinyaga University
By: Mutuse Richard Kituu, EE101/G/9848/20 . Bachelor of Technology Construction and Prpoerty Management (C.P.M)
Touch up primer after fixing and apply three coats gloss oil
paint to metal
ELEMENT NO. 6
WINDOWS
1/8
Project Name: Proposed BoQ for the Research and Training Hospital Kirnyaga University
Client: Kirinyaga University
By: Mutuse Richard Kituu, EE101/G/9848/20 . Bachelor of Technology Construction and Prpoerty Management (C.P.M)
G.
Glazing
H. 4mm clear sheet glass and glazing with putty in panes of 414 SM 2500 1,035,000.00
A. tensile steel for shade purposes support trusses 156 LM 1500 234,000.00
1/9
Project Name: Proposed BoQ for the Research and Training Hospital Kirnyaga University
Client: Kirinyaga University
By: Mutuse Richard Kituu, EE101/G/9848/20 . Bachelor of Technology Construction and Prpoerty Management (C.P.M)
Knot, prime, stop and apply two undercoats and one gloss oil
coats finishing to wood
COLLECTION
1/10
Project Name: Proposed BoQ for the Research and Training Hospital Kirnyaga University
Client: Kirinyaga University
By: Mutuse Richard Kituu, EE101/G/9848/20 . Bachelor of Technology Construction and Prpoerty Management (C.P.M)
ELEMENT NO.7
FINISHES
External Wall Finishes
1/11
Project Name: Proposed BoQ for the Research and Training Hospital Kirnyaga University
Client: Kirinyaga University
By: Mutuse Richard Kituu, EE101/G/9848/20 . Bachelor of Technology Construction and Prpoerty Management (C.P.M)
Floor Finishes
Cement/sand (1:4) screed
Ceiling
Screed Ceiling
D. -
13,549,500.00
E. -
F. -
G. -
Carried to collection -
1/12
Project Name: Proposed BoQ for the Research and Training Hospital Kirnyaga University
Client: Kirinyaga University
By: Mutuse Richard Kituu, EE101/G/9848/20 . Bachelor of Technology Construction and Prpoerty Management (C.P.M)
COLLECTION
ELEMENT NO. 8
Externally
Internally
1/13
Project Name: Proposed BoQ for the Research and Training Hospital Kirnyaga University
Client: Kirinyaga University
By: Mutuse Richard Kituu, EE101/G/9848/20 . Bachelor of Technology Construction and Prpoerty Management (C.P.M)
F. 25 LM 40 1,000.00
SUMMARY
ELEMENT
1/14
Project Name: Proposed BoQ for the Research and Training Hospital Kirnyaga University
Client: Kirinyaga University
By: Mutuse Richard Kituu, EE101/G/9848/20 . Bachelor of Technology Construction and Prpoerty Management (C.P.M)
GRAND SUMMARY
1/15
Project Name: Proposed BoQ for the Research and Training Hospital Kirnyaga University
Client: Kirinyaga University
By: Mutuse Richard Kituu, EE101/G/9848/20 . Bachelor of Technology Construction and Prpoerty Management (C.P.M)
Address …...................................................................................................................
Date …..................................................................................................................
Descrption …...............................................................................................................
Address …...............................................................................................................
Date …...............................................................................................................
1/16