INVENTORY CONTROL
Inventory:- Any resource that has a certain
value and which can be used at a later time, when the demand for that item will arise. It is thus a stock of goods, which may be in the form of raw materials, semi-finished goods ( WIP) or finished product. An inventory system is the set of policies and controls that monitor levels of inventory and determines what levels should be maintained, when stock should be replenished, and how large orders should be Firms invest 25-35 percent of assets in inventory but many do not manage inventories well
To maintain independence of operations
Provide optimal amount of cushion between work
centers Ensure smooth work flow
To allow flexibility in production scheduling
To meet variation in product demand To provide a safeguard for variation in raw material or
parts delivery time
Protect against supply delivery problems (strikes, weather,
natural disasters, war, etc.)
To take advantage of economic purchase-order size Improve customer service
Raw Materials
Works in Process
Finished Goods
Finished Goods in Field
Raw Material Inventory
Direct Inventories
Types
Work in progress Inventories Finished goods inventories
Indirect inventories
1. Direct Inventories:- Items which form an integral part of the finished goods. 2. Indirect Inventories:- Stored items, which do not form an integral part of the finished product but are necessary for upkeep of the plant facilities like lubricants, coolants, office material, etc.
Holding (or carrying) costs.
Costs for capital, taxes, insurance, etc. (Dealing with
storage and handling)
Setup (or production change) costs. (manufacturing)
Costs for arranging specific equipment setups, etc.
Ordering costs (services & manufacturing)
Costs of someone placing an order, etc.
Shortage (backordering) costs.
Costs of canceling an order, customer goodwill, etc.
Total Inventory cost= Purchase cost + Inventory carrying
cost + ordering cost + shortage cost. Ordering cost=
Unit cost of placing an order = Co/q ( Co= cost of placing an order, q=
order quantity) S= annual requirement, Annual cost of ordering = C /q x S
o
Annual Carrying cost= Cu x i x q/2
unit purchase cost, i = interest rate and Cui= annual carrying cost per unit. Shortage cost= { cost of being short one unit in the inventory} x { Average number of units short in the inventory)
Average Number of units short = (Min. shortage in the inventory + Mx
Cu =
shortage/2) x Time for which shortage exist
Inventory Models
Static Inventory Models (Only one order is placed to fulfill demand)
Dynamic Inventory Models
Probabilistic models or Stochastic inventory model
Deterministic Inventory models
Based on assumptions that the demand as well as lead time of an item are
deterministic. Classification:
Single Product (item) Inventory models. Multi Product inventory models
Single Product inventory models: Deterministic inventory models with no shortages: Inventory model with uniform demand Inventory model with several production runs of unequal length Inventory models with finite replenishment (Production)
Inventory model with shortages: Inventory model with instantaneous production and variable order cycle. Inventory model with instantaneous production and fixed order cycle. Inventory models with finite replenishment (Production)
Inventory models when quantity discount is allowed: With one price break
More than one price break
Probabilistic models:- Take into account the variation in demand and lead time.
Basically 3 models comes under this category: Model 1:- Uniform Demand Rate, Infinite Production Rate Model 2:- Gradual replacement Model Model 3: EOQ model with shortages
Model 1 :- Uniform Demand Rate: Developed by Ford Harris in 1915, modified by R.H. Wilson in 1943 Mode for uniform demand rate and infinite production rate.
Salient Features:
Inventory is know with certainty. Demand rate is constant Single lot placement of order Quantity discount is not allowed. Thus, purchase cost per unit is fixed. Lead time is constant and it is independent of demand. Inventory is controlled form one point of the system i.e. in a stockroom or in a warehouse.
Notions used in this Model: D = Annual demand of parts in units Q = Quantity ordered each time
Q* = Optimum quantity of inventory ordered for min.
total cost C = Cost of inventory per unit CC= Carrying cost of per unit of individual item. CO= Ordering , set-up or procurement cost per order TC= Total annual cost TL= Lead time CS= Cost of shortages due to non-availability of inventory.
Assumes lead time is Zero.
TC = Co x N + Cc x Qavg
EOQ = Q* = 2DCo/Cc
17-13
1. You receive an order quantity Q.
4. The cycle then repeats.
Number of units on hand
R
2. Your start using them up over time.
L
Time
L
3. When you reach down to a level of inventory of R, you place your next Q sized order.
R = Reorder point Q = Economic order quantity L = Lead time
By adding the item, holding, and ordering costs together, we determine the total cost curve, which in turn is used to find the Qoptimal (a.k.a. EOQ) inventory order point that minimizes total costs. Total Cost
C O S T
Minimum Total Annual Stocking cost
Holding Costs
Annual Cost of Items (DC)
Ordering Costs
(EOQ)QOPTIMAL Order Quantity (Q)
Optimum Ordering Interval (t*): EOQ = demand rate x optimum ordering interval
Q* = Dt* t* = ( 2 x setup cost) / ( Demand / carrying cost) t* = 2Co/ DCc
Given the information, what are the EOQ and reorder
point: Annual Demand= 1,00 units
Days per year considered in daily Demand = 365
Cost to place and order = $ 10
Holding cost per unit per year = $ 2.5
Lead time = 7 days
Cost per unit= $ 15
EOQ= 2DCo/Cc = 2 ( 1000)(10)/ 2.5 = 89.443 units or 90 units
Re order Point = dl= (1000/365) x 7 = 19.18 (20 units)
Also known as Production-Consumption Model
Instantaneous supply of delivery may not be possible.
Supplier continuously replenishes items at rate, which is more than
the consumption rate.
Because the time inventory is supplied the consumption also continues. The supply is gradual.
Notions:-
P = Production rate ( Unit Per day)
C = Consumption Rate ( Unit Per day)
D = Demand rate ( Unit per day)
Q = Size of lot ordered or produced
Tp= Procurement time TD= Depletion time
Supply is gradual for period Tp ( Procurement Time)
Inventory builds up at a rate ( P-C) and after Tp,
inventory depletes at rate C.
Tp= Q/P Maximum on-hand inventory :- Tp (P-C) i.e. Q/P (P-C) = Q (1-C/P) Depletion Time = TD=
Q (1- (C/P)/C)
( 1-C/P)
Average Inventory level QAVG= Q/2
Total Cost= D/ Q.CO + Q/2 ( 1- C/P)
= (Number of units placed in a year X Ordering Cost) + (Carrying cost per unit X Average Inventory Level during year)
EOQ = Q* = 2DCo/( 1-C/P)Cc
There is a stock- out situation, the customer demand is not
satisfied. In case of raw material/work in process shortages, the production get disrupted. Causes loss due to emergency purchase. Unsatisfied customer result in loss of goodwill and lostsale. Lost sale due to 2 reason: The customer may post-pose or drop the idea to purchase Customer may go to another producer f similar product or services.
Demand is deterministic and known
Shortages are allowed. Production rate is infinite
Lead time is zero.
Reordering is allowed.
EOQ = Q* = 2DCo/Cc X (Cs + Cc)/ Cs
Q*= Economic order quantity D = Demand rate
Co= Cost of ordering
Cc= Annual Cost of carrying one unit of inventory
Cs= Penalty for the shortage f one unit per year or shortage cost.
Maximum Inventory Level (S):-
Optimum Value of S = S* S* = 2D.Co/Cc X Cs/(Cs+Cc) Time between receipt of order, also gives when to order (t*):t*= Q*/D Optimal inventory cost: TC* = 2D.Co.Cc X Cs/(Cs+Cc)
Material are made available at most economical rate.
There is no shortage of raw material etc. at any stage of
production Material of required quality is procured in time. Production schedules are not disturbed. It helps in achieving the production targets in time. Purchasing the material in bulk reduces the unit cost and overheads.
Helps in segregating the items from one another.
Tells about the value of the item to the total value. It classify the inventories on the basis of cost and usage.
The inventories are classified on the basis of control: ABC Classification (Pareto Principle)
A Items: very tight control, complete and accurate records, frequent review
B Items: less tightly controlled, good records, regular review
C Items: simplest controls possible, minimal records, large inventories,
periodic review and reorder
These are high value, low-volume of inventories.
Their annual consumptions is very less. These are very costly items.
Despite needed in less quantity, their annual monetary value is quite
high, only a small percentage (10-20%) accounts for major percentage (say 70-80%) of total inventory monetary consumption.
ABC analysis recommends careful control of A-type
inventory. More periodic review is needed.
These are low value, high volume type of inventories.
Their annual consumption is high. These are not too costly items.
A high volume not constitutes more annual monetary
consumptions. Majority of items (60-70%) constitute only a minor fraction of the total annual monetary consumption (5-15%) in inventories. The control needed for these items may not to very stringent. These items may be under the supervision of lower level of management.
These are medium volume, medium value type inventories.
Their annual consumption is moderate These items constitutes medium cost.
The items other then type A and C constitutes 20-30% of
volume and 10 to 25% in value. Their control and supervision are moderate.
It provide the framework for the integration of
information, material and finance , right form the suppliers to the customers. It is a network of facilities and distribution options that performs the function of procurement of material, transformation of these materials into products to customers. It is the sequence of organizations - their facilities, functions, and activities - that are involved in producing and delivering a product or service.
As per Harland (1996), SCM is the management of a
network of interconnected business involved in the ultimate provision of product and service packages required by end customers. It spans all movement and storage of raw materials, work-in- process inventory and finished goods from the point of origin to point of consumption. As per APICS dictionary, Designing, planning, execution, control and monitoring of supply chain with the objective of creating net value, building a competitive infrastructure, leveraging worldwide logistics, synchronizing supply with demand and measuring performance globally.
Production
Distribution
Purchasing Receiving Storage Operations Storage
Logisti cs
Packag ing
SUPPLY CHAIN
Distrib ution
Consu mption
Supply Chain Structure
SUPPLIER FACTORY
DC
RDC
RETAILER
Raw Materials
Finished Goods
Information Flow
Plan
Source
Make
Deliver
Buy
Suppliers
Manufacturers
Warehouses & Distribution Centers
Customers
Material Costs
Transportation Transportation Costs Transportation Costs Manufacturing Costs Inventory Costs Costs
33
Plan
Source
Make
Deliver
Buy
A set of approaches used to efficiently integrate
Suppliers Manufacturers Warehouses Distribution centers
In the right quantities To the right locations And at the right time
So that the product is produced and distributed
System-wide costs are minimized and
Service level requirements are satisfied
Supply Chain Decision
Strategic
Operational
Location Decision
Production Decision
Inventory Decisions
Transportation ( Distributions) Decision
Location Decision:- Geographic placement of production
facilities, stocking points and sourcing points. Production Decision: Strategic decision include what products to produce and which plants
produce them, allocation of suppliers to plants, plants to DCs, and DCs to customer markets. It determines the exact paths through which a product flows to and from these facilities. Operational decision focused on detailed production scheduling. It include construction of master production schedules, scheduling production on machines and equipment maintenance.
Inventory Decisions: Means by which inventories are managed.
Primary purpose to buffer against any uncertainty.
Strategic in sense as top management set goals.
Transportation Decisions: The choice of mode is strategic decision.
The best choice of mode is often found by trading-off the cost of using
the particular mode of transport with the indirect cost of inventory associated with that mode. Shipment size, routing, scheduling of equipment are key factors. Choice of mode among airway, seaway, rail or road.
Reduce operating cost
Reduce inventory levels and production costs
Improved responsiveness and reduce cycle time.
Improve customer service.
Simplify operations
Improve quality Support significant volume growth improved return on capital Effectively support a growing or diverse customer base.
Effectively offer great variety of products
Focus on core competencies.
Extension of organizational control beyond firm boundaries.
Customer relationship management
Supplier relationship management
Product Development and commercialization
Customer service management
Manufacturing flow management
Returns management
Demand management
Order fulfillment
Plan
Source
Make
Deliver
Return
SCM It is the brain of the enterprises It is contained based and optimized
ERP It is the body of the enterprises It is linear and interactive
It provides capability to the enterprises Primary function of ERP is to generate so that it can make sense out of data to data. help to make decision.
It afford forecasting and the decision Excels in he transaction management. support system
It goes beyond the conventional Links process boundaries of the organization and span organization in the entire supply chain. only within the
SAP India
Mastek
Oracle India
People Soft
J.D. Edwards
IBM Global services Red Pepper Manugistics QAD
I1 Technologies
Numetrix
BaaN India
For dependent demand situations, normal reactive inventory
model i.e. EOQ is not suitable because it result in high inventory cost and unreliable delivery schedule. MRP is better suited for dependent demand items. MRP, simple system of calculating arithmetically the requirement of input materials at different point of times based on actual production plan. Also defined as scheduling system to meet time-phased material requirement for production operations. Tries to meet delivery schedule of end products as specified in master schedule.
Reduction in inventory cost.
Meeting delivery schedule Improved performance.
MATERIAL RESOURCE PLANNING SYSTEM
It provides answer for several questions : What items are required?
When are they required?
How many are required?
Applied to both items, purchased from outside from
suppliers and to sub-assemblies, produced internally.
Master production schedule
Bill of materials Inventory status file.
OUTPUTS OF MRP
Planned order receipts
Planned order release
Order rescheduling
Improved calculation of material requirements. Improved plant efficiency Improved productivity Improved production schedule Improved shipping performance Improved customer service Reduced inventory levels Reduced components shortages. Reduced purchasing cost Reduction in excess inventory Reduced freight cost Reduced manufacturing cost Less scrap and rework Simplified and accurate scheduling.