MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
PAPER PRESENTATION
ON
MATERIAL SCHEDULE- A USEFUL TOOL FOR EFFECTIVE
MANGEMENT OF BUILDING PROJECT
BY QS CHIJIOKE MICHAEL IWUAGWU
AT THE OCCASION OF THE
NIQS WORKSHOP ON IMPORTANCE OF RESOURCE SCHEDULE FOR
INCLUSIVE DEVELOPMENT OF THE CONSTRUCTION INDUSTRY
ON 29TH -30TH OF MARCH, 2021
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
1.0 INTRODUCTION TO MATERIAL SCHEDULE
1.1. BACKGROUND
Material schedule is often produced after the project design and details have been defined, and
provides the overview of the general materials requirement of a construction project, identifying
the various materials specifications and quantities necessary to achieve the project objective.
Various studies indicated that materials and other subcomponents in building projects account
for over 70% of the total cost of building projects, and effectively managing the cost of materials
in building construction leads to greater cost and time savings; making material scheduling an
effective management tool in building production process.
Direct Work- Labour 23% 23%
Direct Work- Plant 5% 5%
Direct Work- Materials 28%
72%
Domestic Subcontracts 44%
A typical material schedule developed from the project drawings and specification presents the
individual makeup substance of the project- like the material type, quantity, sizes, specification/
quality and prices which summarizes the project scope in form of standard market units. Material
schedule is clearly distinct from priced bill of quantities which shows description of the work
items, their specification and prices, expressed in units and forms which are not easily obtainable
in the construction market. Material schedule assists to show the various types and extent of
construction resources needed in performance of the project, offering a useful way to narrow
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
down from the composite attributes that makes the project into basic components of resources
needed to achieve the product- similar to what is witnessed in other manufacturing processes.
1.2. BENEFITS OF MATERIAL SCHEDULE IN BUILDING PROJECTS
Some of the benefits of using Material Schedule in informal building construction process
includes client’s participation in procurement process, cost control, material management,
procurement planning, work planning and resource management.
1.2.1 CLIENT PARTICIPATION IN PROCUREMENT PROCESS
Material schedule enables the active participation of client in the procurement process of
materials and components. the material list provides the client a shopping list representing the
full project components, creating opportunity for the client to participate take critical decision in
issues like material quality, source, purchased price and other associated logistics.
1.2.2 COST AND QUALITY CONTROL
Material Schedule provide a flexible tool for both cost and quality control suitable in formal and
informal procurement settings. The material costs and quantities derivable from the primary
quantity of work items are adopted as basis of cost and quality control during project execution.
Initial projected specification and quantities of material are closely used as baseline for cost
projections, enabling the project stakeholders to budget and program cashflow and other
arrangements based on material schedule quantities.
1.2.3 MATERIAL MANAGEMENT
Material schedule provide a useful tool for implementing material management which helps to
ensure that the overall cost content or projection for materials are maintained or superseded.
Plans regarding material purchase, storage and utilization plan can be seamlessly executed based
on information in the material schedule such that indirect cost of materials are adequately
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
controlled. Some of the cost saving benefits accruable from this includes discounts on bulk
purchase or pre-ordering of materials, wastage control, materials storage conditions and
handling, equipment and labour planning can be adequately prepared for well ahead of time
before the work activities are due thereby leading to great time saving too.
1.2.4 CASHFLOW PLANNING AND BUDGETING
Typical material schedule serves as an instrument that enables easy cashflow and budgeting for
both the project promoter and the contractor. From the quantity of materials involved, the project
employer can determine the capital involved required at every particular stage of the work, and
as well, the contractor can also plan adequately for the best construction method suitable to
efficiently execute the works in time and cost. The material quantities, type, size and prices
therefore form the basis for budgeting the construction cost.
1.2.5 WORK PLANNING
Material schedule also enables the project team to develop outline of work goals and processes
geared towards realization of the project objective. Decisions to procure concrete rather
stockpiling cement, sand and aggregates can be concluded owing to instructive findings from the
material schedule. Even the plan to adopt a particular methodology can be deducted from
decisions arising from the material schedule.
1.2.6 RESOURCE MANAGEMENT
Material schedule also provides a useful tool in resource management in construction works. The
material resource projection of material schedule enables the project stakeholders to adequately
project and utilized non-material resources required on the project. Things like equipment sizing
and capacity can be related to the volume of materials required to be worked upon, and more
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
economic decisions can be taken on such matter, and likewise Labour plan and projections can
be based on the quantity of materials required to be worked upon.
1.3. FACTORS TO CONSIDER IN PREPARING MATERIAL SCHEDULE
Some of the factors to consider in preparing a functional material schedule program includes
undertaking the following processes:
1.3.1 IDENTIFY AND ESTABLISH THE WORK QUANTITY
A major step towards preparing functional material schedule is the determination and calculation
of the project works quantities. This information can easily be gotten from the project drawings
showing the descriptions and dimensions of the building elements and components, calculated
net with no allowance for shrinkage, bulkage, wastages or laps. Work quantities are expressed in
standard units of meters (m), square meter (m2 of m 2), cubic meter (m3 or m3), kilogram (kg),
tonne (ton) or even number (nr). Materials like concrete (m 3), blockworks (m2) reinforcement
(ton or kg) etc. are expressed in their corresponding standard unity.
1.3.2 UNDERSTAND THE BUILDING/CONSTRUCTION PROCESS
Knowledge of building construction process assists in identifying the individual material
makeups of composite materials, including their proportioning sequence and forms. Knowledge
of composite materials like concrete, formwork, mortar, or even simple materials are useful in
calculating material quantities from work/element quantities. Such understanding empowers the
Quantity Surveyor to identify the various materials required in the construction process, and to
accurately abstract them out from the proposed building designs and drawings.
1.3.3 IDENTIFY WORK MATERIAL PROPORTION AND COMPONENTS
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
Understanding of material proportioning is relevant to the preparation of material schedule.
Composite materials like concrete are designed by proportioning of the various material
components, representing a part of cement, sand and coarse aggregates. Mortar for laying blocks/
brick and plaster for rendering are other examples of materials requiring proportioning. And the
knowledge of the various standard mixes and proportion would great enhance the functionality
and accuracy of the material schedule.
1.3.4 UNDERSTAND MATERIAL CONVERSION FACTORS AND CONSTANTS
The process of converting work quantities to corresponding material and quantities requires the
application of accurate conversion factors/ constants on the work quantities in order to transform
them into standard material units obtainable in the market. From a mere cubic meter of concrete,
the corresponding proportion of material makeups are related to usage conversion factors in
order to convert the works quantities to standard materials obtainable in the market.
1.3.5 ADJUSTMENTS TO COVER FOR WASTAGES
Before preparing a functional material schedule, there is need to account for wastages, bulkage
or shrinkage which are most likely to occur in the process of utilizing construction materials.
And depending on the material, factors like application waste, storage waste, transit waste,
bulkage, shrinkage, lapping etc. should be adequately provided for when preparing the material
schedule. Varying degree of these factors should be accommodated depending on the nature and
type of material. Materials over or under size to the standard market size would attract more
wastage than the one matching with standard market sizes.
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
2.0 MATERIAL SCHEDULE USING THE SMRS-1
The Standard Method of Resources Schedule (SMRS-1) as produced by the Nigerian Institute of
Quantity Surveyors (NIQS), supports uniformity in the preparation of construction resources
offers a brilliant way to present material schedule for building works. The SMRS-1 document
established a set of standards principles which covers the contract scope and accommodates
direct participation of the project client in the procurement process, thus enabling the preparation
and scheduling of all resources- materials, labour, equipment, capital etc. needed to complete a
building project. through its laid-out guidelines and principles, giving rise to preparation of
Construction Resources and Economy Schedule (CORES) which is the alternative to Bill of
Quantities applicable for informal procurement methods.
2.1. THE RULES AND GUIDELINES
The SMRS-1 as a standard document provides the general guideline and supplementary rules
defining the works in order to achieve uniformity and consistency using this document. The rules
are grouped under16 headings, subheadings, and careful study of these headings and the
subheadings therein would ensure uniformity in the preparation of the Construction and
Economy Schedule (CORES).
2.2. WORK QUANTITIES
The Work/Element quantities shall be measured as gross or net depending on their placement on
the table. Net quantitates (nm, nm2, nm3, nkg,nt, nnr) of the works/cement shall be recorded for
each described work as fixed in place, and shall be the actual quantity of works/ material
required to achieve the work without any allowance for wastage, laps, shrinkage or bulkage.
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
Gross quantities (gm, gm2, gm3, gkg, gt, gnr) of the work shall be recorded for each material
issue required to achieve the full extent of the works described in the description column, with
adequate allowance made for wastage, shrinkage, bulkage, laps and other factors affecting the
material application method and process.
All dimensions used in working up for quantities shall be entered to the nearest 10mm, and
material quantities shall be rounded to whole unit, with the exception of materials expressed in
tonnage (ton), which shall be presented to the nearest two decimal places. Each work quantity
shall be measured according the relevant application rule, and the quantities so presented shall be
deemed sufficient to achieve the final work quantity and quality.
2.3. DESCRIPTIONS
Work descriptions shall be provided in the general form similar to the BESMM4 in the sequence
of length (L), width (W), or depth/ height (H). reference to drawings shall be stated to
sufficiently amplify the works description. The heading to schedules of resources shall be read as
part of the descriptions of the items to which the heading applies. Hyphens between two
dimensions in the schedule of resources shall indicate the range of dimension, from the lower
bracket to the higher bracket. Works sections in the schedule of resources shall begin stating the
nature and location of the works, unless evident from the drawn or other information required to
be provided by these rules. The Method Related statement shall describe and state the
contractor’s proposed methodology to executing the work, and the cost involved therein shall be
considered under the Method Related charge which is deemed to include:
a. Labour and incidental cost to it
b. Plant and all incidental cost to it
c. The cost of assembling, fitting and fixing of materials and goods in positions
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
d. Contractor’s establishment charges, overhead and profit
e. Consumable stores including jointing of materials not scheduled as material issue
under the employer’s responsibility.
Materials issued by the employer shall be defined to include the point of issue and method of
delivery to the contractor, and the method related charge shall include the cost for taking delivery
of the materials from the employer.
2.4. DRAWN INFORMATION
The project drawings shall sufficiently provide information to identify and define the expected
works from the building plans with relations to existing infrastructures, access road, and the
general layout of the site. The sections, the elevations, the outlines and the site plans of the
project shall provide sufficient information to enable accurate and reasonable assumptions
needed to draw-up quantities of the works.
The component drawings shall show the information necessary for manufacture and assembly of
the components
2.5. CATALOGUES OR STANDARD COMPONENTS
Reference to identified aspects of the works can be made through a catalogue which shall
establish the full extent of the works, and such shall suffice in place of normal item description
of the works as required in Rule 2.
2.6. WORK OF SPECIAL TYPES
Works of the following special types shall be so separately identified:
1 Works on existing building (under rule 13)
2 Works to be carried out and subsequently removed (other than temporary works)
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
3 Works outside the cartilage of the site
4 Works carried out in or under water shall be so described stating whether canal, river,
or seas water, and where applicable the main seasonal levels of high and low water
5 Works carried out in compressed air shall be so described stating the pressure and
method of entry and exit.
2.7. PROCEDURE WHERE THE DRAWN INFORMATION AND SPECIFICATION
REQUIRED BY THESE RULES IS NOT AVAILABLE
Where works can be described and given in items in accordance with these rules, but the
quantities of works required cannot be accurately determined, as estimate of the quantity shall be
given and identified as an approximate quantity.
And where the works cannot be described and given in items in accordance with these rules, it
shall be given as Provisional Sum and identified as either defined or undefined works
appropriately. Defined provisional sum shall be given for works or items whose information
about the nature and construction of works is provided, location of the works in the finished
project is defined, information about quantities of the works scope and extent is available, and
the contractor is deemed to have made adequate provisions for it in the programme, planning,
and pricing of the preliminaries required to execute the works.
Undefined provisional sum shall be for works and items whose information required to
determine the full extents of the works is not available, and the contractors is deemed not to have
made any allowance for the provision of the item or works in the planning, programme or pricing
of the works in the preliminaries. Provided
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
2.8. WORKS NOT COVERED
The rules of measurement adopted for works not covered by these rules shall be stated in the
schedule, and such rules shall as far as possible conform with those provided in the SMRS-1 for
similar works.
2.9. SYMBOLS AND ABBREVIATIONS
The following tabulated units and their symbols are recognized in the SMRS-1 for resources
scheduling:
NET WORKS /ELEMENT QTY GROSS MATERIALS QTY
Symbol Meaning Symbol Meaning
Nm net meter gm gross meter
nm2 or nm2 net square meter gm2 or gm2 gross square meter
nm3 or nm3 net cubic meter gm3 or gm3 gross cubic meter
Nr net number gr gross number
Nkg net kilogramme gkg gross kilogramme
Net net tonne get gross tonne
2.10. WORKS TO EXISTING BUILDINGS
General classifications for works to Existing Building shall be described as so, and such works
shall be defined as follows:
1. Works on or in or immediately under works existing before the current project
2. Additional information to be read in conjunction with the preceding rules in the
appropriate work sections
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
3. Full descriptions of the additional preliminaries / general conditions which are pertinent
to the works shall be given, drawing attention to any specific requirements due to the
nature of the works
2.11. GENERAL DEFINITIONS
Radius or curvature of a described work/ element of work shall be stated, and the so radius or
radii so provided shall be that measured to the centerline of the material or member.
2.12. MATERIALS ISSUE PROCEDURE
Materials under the issue of the Client’s responsibility shall be so stated, and the point of
delivery/ collection of the materials, including the delivery dated stated.
The Materials certification and identification shall also be provided, and the method of
protection, storage or any associated works required to keep the material in useable state
provided.
2.13. METHOD STATEMENT AND CHARGE
Method statements are details of the contractors work plan and methodology for accomplishing
the given work scope, but the contractor is not limited to following it during construction method
statement helps the contractor to adequately prepare and state the workplan: propose non-
material resource and processes required in executing the project, arrange logistics encountered
therein the workplan, as well as assign his profits and overhead. These financial costs included
here make up the method charges of the work for the contractor. And the contractor is not
expected to show details of this charges.
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
3.0 BUILDING WORKS CLASSIFICATION AND KEY ACTIVITIES
Building works are classified into several works’ categories involving the use of several natural
and composite materials in varying quantities and proportions to accomplish the works/elements
in building construction. The NIQS Standard method of Resources Schedule 1 (SMRS-1)
identified a group of 19 work classification encountered in building projects.
3.1. WORK CLASSIFICATIONFOR BUILDING WORKS
Some of the works classification encountered in typical building construction are listed herein,
and includes the following aspects: Preliminaries and General Items, Maintenance Works;
Demolitions and Alterations; Earthworks; Insitu and Precast Concrete; Formworks;
Reinforcement; Masonry Block Walling; Structural/ Carcassing Timber, Roof and Similar
Claddings; Waterproofing; Components; Fittings and Fixtures; Metal and Minor Steelworks;
Finishes; Glazing; Painting; Electrical Installation; Mechanical Installation; and External Works
Car Parking, Drives Pavement/ Planting.
3.2. KEY ACTIVITIES OF BUILDING WORKS FOR MATERIAL SCHEDULE
Some of the key activities encountered in building construction includes the followings:
3.2.1 EARTHWORKS
Earthwork activities in building works involves the removal of existing earth formation to make
way for introduction of new permanent structures as well as the replacement of removed earth
formation with materials obtained outside the environment. Excavations involved in earthworks
is a works related items, but the replacement or removed earth either to makeup level or to
replace unsuitable formation requires additional materials which would be considered during
preparation of the material schedule expressed in the material supply units- say “truck” or “trip”.
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
For the benefit of preparing the material schedule, the materials required in earthwork to makeup
level or replace unsuitable materials.
Material Schedule Quantity (MSQ)= Work Quantity (m3) / Capacity per Truck load (m3)
Example: for a work quantity of 108m3, using a 20ton truck (20ton / material weight- for sand
between 1.4ton/m3 ro 1.6ton/m3).
108 m 3
That is MSQ=
¿¿
Note also that this expression does not include bulkage or swell experienced with materials of
this nature.
3.2.2 CONCRETE WORKS
Concrete is an important composite material in building works. It requires the mixture of cement,
aggregates and water in a proportion mix to produce it. A concrete proportion of 1:2:4 signifies a
proportion of 1 part of cement : 2 part of sand (measured in the equivalent of cement) : 4 part of
coarse aggregate (measured in the equivalent of cement) and Concrete is used for different
purposes according to the desired strength and characteristics as plain concrete, mass concrete
and reinforced concrete. Plain concretes (typical mix ratio of 1:6:10 or above) are used in
blinding, mass concrete (typical mix ratio of 1:3:6 or above) in floors and non-load bearing
structures while reinforced concrete (typical mix ratio of 1:2:4 or above) are used load bearing
structure.
For a building slab having a work quantity of 125m 3, the quantity of the various material of
cement, sand and granite would be as calculated using know standard conversion factors derived
from the concrete mix ratios determined as follows:
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
For mix ratio of 1 cement : 2 sand : 4 granite = 7parts. Voids and Shrinkage in concrete account
for about 45% of the material volume, and water for mixing can be taken at between 0.3-0.5% of
cement content in mix.
1
For cement = ∗( voids+shrinkage )=0.143∗1.45=0.214 m 3
7
Being that cement is obtained in bags in the open market, and one bag of cement contains about
0.035m3 of material, therefore 0.214m3/0.035m3 = 6.11 bags/ m3
2
For sand = ∗( voids+shrinkage )=0.286∗1.45=0.415 m3
7
Being that sand is supplied using truck capable of hauling 20ton of material per trip, that is
20ton/1.6ton/m3 (weight of sand) = 12.5m3; 0.415m3/12.5m3 (per truck) = 0.0332 truck/ m3
4
For granite = ∗( voids+ shrinkage )=0.571∗1.45=0.828 m 3
7
Being that granite is supplied using truck capable of hauling 30ton of material per trip, that is
30ton/1.7ton/m3 (weight of granite) = 17.64m3; 0.828m3/17.64m3 (per truck) = 0.0469 truck/
m3
Cement = 125m3 x conversion factor for cement (say 6.11 bags)
Sand = 125m3 x conversion factor for sand (say 0.0332 truck using a truck capacity of 20ton).
Granite = 125m3 x conversion factor for granite (say 0.05 truck using a truck capacity of 30ton).
3.2.3 BLOCK/MASONRY WORK
Block and masonry works are important parts of a building structure. They are used to form
walls and demarcation in building. Blockworks are made of blocks obtained from the mixture of
cement and aggregates with little water. The most common type of blocks used around here is
sandcrete blocks- made from mixture of cement and sand, mixed with water and vibrated in steel
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
molds to form the block. Masonry blockworks are laid and jointed with cement-sand mortar to
achieve strong bonding among the walls forming wall.
In order to prepare the material schedule for materials involved in a block wall construction, the
masonry structure is broken into component main component parts- Block and Mortar.
Block- blockworks come in standard sizes (LxWxH) depending on what is obtainable in the
environment. A typical block size available in our environment would include: 450 x225x225,
popularly refered to as 9 inches block, 450x150x225- also called 6 inches block. The area of 1
1 m2
block is the equivalent of 0.10125m2, meaning that 1 m2 = =9.87∨10 blocks
0.10125 m2
Mortar- sand used for joining block can be made from the mixture of binder and aggregate
proportion in ratio that achieve the best bond between the blocks. A typical mixture for mortar
would be in the proportion of 1:6 representing 1 part of cement and 6 part of sand, or 1 part of
lime and 6 part of sand, or a combination of both given as 1:1:6 representing 1 part of cement, 1
part of lime and 6 part of sand.
For a mortar mix of 1:6 = 7m3,
1
For cement = ∗( voids+shrinkage )=0.143∗1.35=0.193 m3
7
Being that cement is obtained in bags in the open market, and one bag of cement contains about
0.035m3 of material, therefore 0.193m3/0.035m3 = 5.51 bags/ m3
6
For sand = ∗( voids+shrinkage )=0.857∗1.35=1.157 m3
7
Being that sand is supplied using truck capable of hauling 20ton of material per trip, that is
20ton/1.6ton/m3 (weight of sand) = 12.5m3; 1.157m3/12.5m3 (per truck) = 0.093 truck/ m3
To prepare materials scheduled to cover 100m2 of 225mm sandcrete blockwork would be as
follows:
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
Mortar: assume a mortar volume of 4 cubic meter obtained from calculating the volume of
mortar used in jointing.
Block= 100m2 x 10 blocks/m2 = 1000 blocks
Cement = 4m3 x 5.51 bags = 22.04 bags
Sand = 4m3 x 0.093 truck = 0.372 trips of 20ton truck.
3.2.4 FORMWORK
Formwork are temporary or permanent molds used to support fresh concrete or similar materials
to achieve desired shape, form and strength to carry itself. Material for making formworks
include steel, timber and plastic. Formworks are measured according to the exposed surface in
contact with the permanent works.
Woods/ timber materials for formworks are available in standard sizes (LxWxTH):
Marine Board - 2400 x 1200 x 25 (mm) Timber–3000-5400 x 75-100 x 75-100(mm)
Plank – 3600 x 250-300 x 25 (mm) Timber–3000-5400 x 75-50 x 75-50(mm)
Plywood – 2400 x 1200 x 6 (mm) Timber–3000-5400 x 250 x 75-50(mm)
To accurately estimate the materials in formwork first determine the area of material in contact
with the finished works, the calculate the quantity of materials used to achieve supports and hold
the formworks in place. For slab formwork of say 700m2, the materials in formworks would be
as follows:
700
1. Marine Board (2400x1200) = =244 nrs of boards∨0.348 baords per m 2
(2.4∗1.2)
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
700
2. Horizontal support (using 75x75 timber) @ 600mm center to center = =1167m ,
0.6
1167
amounting to =325 lengths∨0.464 length per m2
3.6
3. Prop supports (using 100x100 timber) @ 600mm center to center
700
=1945 nrs of timber∨2.78 nrs per m2
(0.6∗0.6)
4. Nails/bolts & nuts in wooden formwork is estimated at an average ratio of 0.1kg/m2;
or 700*0.1kg=70kg.
Thus this constant can be used on other slab formworks quantities 150m2.
Marine board: 150m2 x 0.348 board/m2 = 53 boards; horizontal supports: 150m2 x 0.464
length/m2 = 70 lengths; prop supports: 150m2 x 2.78 nrs = 417 nrs.
The same approach can be taken to calculate materials in steel formworks, but care must be
taken to remember that steel formworks have higher re-usable value than wooden formworks.
While as steel formworks can be reused upto 10 times (with adequate caretaking), wooden
formworks have a limited of upto 6 reusable times (given good caretaking).
3.2.5 REINFORCEMENT WORKS
Reinforcement are integral part of concretes in building works. The design for strength in
reinforced concrete follows a given ratio of concrete to steel for the sectional area of concrete.
Steel reinforcement bars are obtained in the market in standard sizes of 6, 8, 10, 12, 14, 16, 20,
25, 32 (mm) diameter and standard length of 12m.
To convert steel work/element quantity, first the bars are converted to weight per length (m)
using defined conversion factors as shown below:
32mm diameter bars= 6.318 kg/m 14mm diameter bars= 1.209 kg/m
25mm diameter bars= 3.856 kg/m 12mm diameter bars= 0.889 kg/m
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
20mm diameter bars= 2.468 kg/m 8mm diameter bars= 0.395 kg/m
16mm diameter bars= 1.578 kg/m 6mm diameter bars= 0.222 kg/m
To calculate material quantity in 256kg of 16mm reinforced concrete structure, divide the work
quantity (kg or ton) by weight of each length as shown below:
256 kg 256 kg
Qty (16 mm)= = =14 lengths
12∗1.58 kg/m 18.96 kg/nr
3.2.6 PLASTERING/ RENDERING WORKS
Plasters and rendering are wall finishes made from cement, sand and water mortar mixed in the
ratio of 1:3 to 1:6 depending on the purpose. Plasters are external wall finishes often having
thickness not less than 15mm with mortar mix not less than 1:4, while rendering are internal wall
finishes having thickness not less than 12mm thick.
To calculate the materials required to plaster a wall of 245m2 at ratio 1:4, first calculate the
volume of plaster mortar on the wall, then multiply by the conversion factor to derive the number
of cement and sand involved.
Therefore, mortar = 245m2 of wall * 25mm thickness = 6.125m3 of mortar.
For a mortar mix of 1:4 = 5m3,
For cement = 1/5* (voids+shrink)= 0.2*1.35=0.27m3, therefore 0.27m3/0.035m3 = 7.71bags/
m3
For sand = 4/5* (voids+shrink)= 0.80*1.35=1.08m3; using 20ton/1.6ton/m3 (weight of sand) =
12.5m3; 1.08m3/12.5m3 (per truck) = 0.0864 truck/ m3
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
The materials for plaster mortar of 6.125m3 would be as follows:
Cement = 6.125m3 x 7.71bags = 47.22 bags
Sand = 6.125m3 x 0.0864 truck = 0.529 trips of 20ton truck.
3.2.7 TILING WORKS
Tiling works are fashionable floor and wall finishes in building construction, requiring the fixing
of tiles (porcelain, vitrified, glazed etc.) with cement grout and adhesive. Materials involved in
tiling works include- tiles (often obtained in cartons or square meter), cement grout/ mortar for
backing or bedding, adhesive gum, waterproofing additive and tiles corner tape and strips.
To prepare material schedule for work quantity of 20m2 of floor finishing using 450x450x8mm
thick tiles laid on 40mm bed:
1 m2
Tiles = 1 carton = =4.94=5 pcs /carton, so for 20m2, 20 carton of tiles
( 0.45∗0.45 ) m2/tile
would be required.
For bedding, the mortar needed for 20m2 area = 20m2 x 0.04m = 0.8m3
Using ratio of 1:4 = 5m3,
For cement = 1/5* (voids+shrink)= 0.2*1.35=0.27m3, therefore 0.27m3/0.035m3 = 7.71bags/
m3
For sand = 4/5* (voids+shrink)= 0.80*1.35=1.08m3; using 20ton/1.6ton/m3 (weight of sand) =
12.5m3; 1.08m3/12.5m3 (per truck) = 0.0864 truck/ m3
The materials for mortar bed of 0.80m3 would be as follows:
Cement = 0.8m3 x 7.71bags = 6.16 bags
Sand = 0.8m3 x 0.0864 truck = 0.069 trips of 20ton truck.
20 kg
Tile gum = 20kg per bag for 8m2 coverage; =2.5 kg /m2∨0.125 bag /m 2
8 m2
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
Gum for 20m2 = 20m2 x 0.125 bag = 2.5 or 3 bag.
3.2.8 PAINTING
Painting is the application of paint, pigment, colour or other medium to final surfaces of building
material or component like blockworks, ceiling, concrete or metal works. Painting activity in
building works some preparatory steps required to prepare the surface to receive the final paint
coating. To prepare a simple material schedule for paint work on wall or metal surface of 200m2,
consider the following:
Surface Preparation:
Surface preparation varies depending on the type of surface been prepared and the material used.
Some surface preparatory materials and process are putty, floating/screeding etc. involving the
use of filler materials to fill cracks and unevenness on the surface to be painted.
Determine the coverage of POP screeding paint used- say 40m2/ drum (20 litres)
Screed material required = 20L / 40m2 = 0.5L/m2; for 200m2 = 200m2 x 0.5L/m2 = 100L
Qty required of 20L = 100L / 20L = 5 Drums or 0.025drum per m2
Application of Paint is calculated in number of coats- first, second, third etc.
Using a paint material that has a coverage capacity of 8m 2/L, and assuming 75% efficiency on
the coverage of the first coat, 85% efficiency on the coverage of the second coat and 100%
efficiency on the coverage of the third coat as calculated in the table below:
First coat @ 75% 6m2/L
Second coat @ 85% 6.8m2/L
Third coat @ 100% 8m2/L
Average coverage 6.93m2/L
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
Therefore, 200m2 / 6.93m2 = 28.86 L / 20L per drum = 1.44 drums or 0.0072 drum per m2
Other materials involved in painting can be calculated like this, using their coverage capacity and
unit content as available in the market. Some of the standard unit content of paint materials are:
Drum = equivalent of 20 liters
Gallon= equivalent of 5 liters
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU
MATERIAL SCHEDULE-A USEFUL TOOL FOR EFFECTIVE MANAGEMENT OF BUILDING PROJECTS
4.0 CONCLUSION
As a wise man once said, counting the cost is an important aspect of building decision, and
material schedule assists the construction promoters to count the material costs which never the
less represents about 70% of the building cost. Understanding the project composition therefore
is an asset to the project stakeholders, and material schedule offers a useful insight in presenting
the material composition of the project which are used for critical project decisions like material
purchases, cashflow planning and projection, quality control, work plan etc.
A functional material schedule helps in effective management of the building process, affording
the construction promoter chance to participate directly in the final decisions in procurement
process of materials, cost, quality and time from the beginning to the end of the project.
As professional quantity surveyors, it is our responsibility to ensure that the cost upon which a
Wiseman’s decision to build is founded upon is both accurate and as well as practicable in order
to protect the success of the project.
References
Brook Martin Estimating and Tendering for Construction Works [Book]. - [s.l.] : Butterworth-Heinemann,
2008. - 3rd Edition. - 978-0-7506-5864-5.
Frank R. Walker Compny Walker's Building Estimator's Reference Book [Book]. - [s.l.] : Frank R. Walker
Company, 1996. - 23rd Edition. - 0-911592-23-7.
Nigerian Institute of Quantity Surveyors (NIQS) Standard Method of Resources Scheduling 1 [Book]. -
Abuja : Nigerian Institute of Quantity Surveyors (NIQS), 2006. - 1st Edition. - 978-36754-8-6.
Peurifoy Robert L and Oberlender Garold D Esimating Construction Costs [Book]. - [s.l.] : MCGraw-Hill,
2005. - 5th Edition. - 978-0-07-243580-1.
NIGERIAN INSTITUTE OF QUANTITY SURVEYORS (NIQS). PRESENTED BY QS CHIJIOKE MICHAEL, IWUAGWU