Addis Ababa Road Construction Challenges
Addis Ababa Road Construction Challenges
By
AYNALEM ABEBE
OCTOBER/ 2016
JIMMA, ETHIOPIA
JIMMA UNIVERSITY
BY
AYNALEM ABEBE
OCTOBER, 2016
JIMMA, ETHIOPIA
DECLARATION
I, the undersigned, declare that this thesis entitled “Assessmentof the major challenges
on ongoing road construction in Addis Ababa. is my original work, and has not been
presented by any other person for an award of a degree in this or any other University,
and all sources of material used for theses have been dually acknowledged.
Candidate:
AynalemAbebe
Signature______________________
As Master research Advisors, we hereby certify that we have read and evaluate this Msc
ACKNOWLEDGEMENT
First of all I would like to thank God and His Mother St. Mary for all my accomplishment
until now. And I would like to express my sincere and deepest gratitude to my advisor
Prof. Emer T. Quezon and my co-advisor Eng. GetachewKebede for all their limitless
efforts in guiding me through my work and for providing me useful reference materials.
Secondly, my deep hearted gratitude to Ethiopian Road Authority (ERA) and Jimma
University by giving me the opportunity to avail the scholarship program in pursuing my
master‟s degree in civil engineering (CEM).
And also I would like to thank to those client, contractors and consultants who have
sacrificed their important time for Answering, returning questionnaires and providing me
the necessary information during the development of the thesis work. I extend my thanks
for Addis Ababa City Roads Authority staffs, for their candid assistance and cooperation.
Finally, I am especially thankful to my mother for her continuous support and to all my
friends who shared their unselfish help and kind support in preparing my thesis,
especiallymy best friend TamratFikadu (Msc).
ABSTRACT
Road construction project is the challenging process which needs huge manpower,
machineries and technical as well as financial capacity. Construction projects in
crowded urban road have faced different challenge to implement the road construction
such as high-traffic volume, utility conflicts and relocations and complex right-of-way
challenges of urban area construction. Therefore,the main objective of this study was to
assess the major challenges of the selectedon ongoing road constructionprojects in the
case of Addis Ababa city.
Descriptive and explanatory study methods were carried for this research in order to
achieve the objective of the study. Firstly, Guide lines (checklist) for the case study were
prepared. It contains the basic information about the selected road construction projects
such as: identify the major challenges that observed during the construction
implementation process, determining the challenges that influence on road
construction.Secondly, the research was conducted by identification of the major
challenges through literature review, desk study and site observation on selected road
projects. Based on this, the questionnaires were developed and distributed to
respondents to collect data from the relevant population (i.e. Client, contractors
andconsultants). Thirdly, evaluate the perception of different stakeholders on the issues
of the challenges and ranking of the variables. Finally,evaluation of roads was done by
checking compliance with the existing construction standards. Upon obtaining the
desired data, checking and organization of data has been done. This was followed by
thorough discussions in order to draw a conclusion and to forward recommendations
based on the findings of the study.
The distributed questioners to respondents were 100% returnedeven though, 73% of the
questioners were only valid. From result that obtained, elevenmajor challenges (i.e.right
of way problem, utility conflict, schedule constraints, variation order and poor project
management, Scarcity of material and financial, high traffic problem, performance of
stakeholders, poor public awareness, Design/poor planning and Environmental
factors)were identified from the selected road projects by using checklist; however, the
highest major challenge was right of way problem. On other hand, Time over run, Budget
over run, Creating social problem, Reduce work motivation, Dispute between parties,
Project termination and Leadership removal were identified as the most common and
recurrent effects of the challenges on the on-going road construction projects. All most
all the selected on-going road projects were not compliance with the standard.
ABBREVIATIONS
UK United Kingdome
TABLE OF CONTENTS
ACKNOWLEDGEMENT ................................................................................................... i
ABSTRACT ........................................................................................................................ ii
ABBREVIATIONS ........................................................................................................... iii
TABLE OF CONTENTS ................................................................................................... iv
LIST OF TABLE .............................................................................................................. vii
LIST OF FIGURE............................................................................................................ viii
CHAPTER ONE ................................................................................................................. 1
INTRODUCTION .............................................................................................................. 1
1.1. Background .............................................................................................................. 1
1.2. Statement of the problem ......................................................................................... 2
1.3. Research questions ................................................................................................... 2
1.4. Objective .................................................................................................................. 3
1.4.1 General objective ................................................................................................ 3
1.4.2 Specific objective ............................................................................................... 3
1.5. Scope and limitation of the study ............................................................................. 3
1.6. Significance of the study .......................................................................................... 3
CHAPTER TWO ................................................................................................................ 4
LITERATURE REVIEWS ................................................................................................. 4
2.1. Introduction .............................................................................................................. 4
2.2. Classification of Construction Industry.................................................................... 4
2.3. Construction Projects ............................................................................................... 5
2.4. Road construction project......................................................................................... 5
2.4.1. Implementation of urban road construction project ......................................... 6
2.4.2. Challenges for implementation of urban road construction .................................. 6
2.4.2.1. Utility conflicts ............................................................................................... 6
2.4.2.2. ROW problem................................................................................................. 8
2.4.2.3 High-traffic problem (obstruction) during construction period ..................... 10
2.4.2.4 Performance of stakeholder issues ................................................................ 11
2.4.2.5. Schedule constraint ....................................................................................... 14
LIST OF TABLE
Table 4-1: Response rate by category ........................................................................................... 30
Table 4-2: Challenge affecting implementation was and still is a problem or not in Addis
Ababa road construction projects.................................................................................................. 32
Table 4-3: Physical performances of selected road projects ......................................................... 33
Table 4-4: Project Data for CMC Roundabout – Karalo .............................................................. 35
Table 4-5: Project data for CMC Roundabout – Karalo ............................................................... 37
Table 4-6: Project data for Yerergoro school- cmc at st. Michael church .................................... 39
Table 4-7: Project data for koyefeche condominium lot 1 and 2 asphalt ..................................... 41
Table 4-8: Project data for Radio beacon-kotebe Fisash mataria ................................................. 43
Table 4-9: Project Data for Augusta- Betel-Alembank Road Project........................................... 44
Table 4-10: Project data for Mexico - Amestegna police station Road project ............................ 45
Table 4-11: Project data for Kadisco paint factory to crown hotel ............................................... 46
Table 4-12: Project data for Meskel flower- gazebo- road project ............................................... 47
Table 4-13: Project data for Besrate Gebriel- Abo Roundabout................................................... 49
Table 4-14: The major identified challenges during assessment period ...................................... 51
Table 4-15: Major challenges of road construction projects ........................................................ 52
Table 4-16: Summary of spearman's rank correlation coefficients for identified
challenges….. ................................................................................................................................ 55
Table 4-17: RII and rank of all factors from contractors, consultants, client (AACRA),
and overall respondents‟ point of view from all categories. ......................................................... 57
Table 4-18: Rank effects of the challenges on road construction project from all
Respondents‟ point view ............................................................................................................... 59
Table 4-19: Summary of spearman's rank correlation coefficients for effects caused by
identified challenges ..................................................................................................................... 61
Table 4-20: Construction requirement for Right of way problem ................................................ 62
Table 4-21: Construction requirements for existing public utility................................................ 64
Table 4-22: compliance of Temporary traffic management plan standards ................................. 66
Table 4-23: Prepare Traffic management Approach .................................................................... 68
Table 4-24: organization working progress is within original schedule and cost estimate .......... 69
Table 4.25: lack of coordination of utility services ...................................................................... 69
LIST OF FIGURE
CHAPTER ONE
INTRODUCTION
1.1.Background
The construction industry everywhere faces problems and challenges;these difficulties
and challenges are present together with a general situation of socio-economic stress,
chronic resource shortages, institutional weaknesses and inability to deal with the key
issuesin the developing countries[1].
Therefore, in this research was made to assess the major challenges on ongoing road
construction in Addis Ababa City. These papers reports on identify the major challenges
and determine their effects on the ongoing road construction projects.In addition to this,
checkingthe existing road construction compliance with standards.Finally, to reduce the
road construction challenges in the study area, a number of recommendations have been
formulated.
Construction projects in congested urban corridors have been a challenge for many years.
High-traffic volume is just one of many concerns that need to be resolved. Adding
significant utility conflicts and relocations, complex right-of-way (ROW), a diverse
stakeholder makes normally difficult work even more complicated. Road construction
project is a complicated process which requires massive manpower, machineries and
technical as well as financial capacity [4].
Addis Ababa road construction projects frequently take longer construction time.
Amongthe challenging conditions, crowded working environment which decrease the
efficiency of machineries and complex right of way issues are observed. The everyday
construction method is currently bringing large interruptions because of extended period
of time and disturbance of adjacent businesses.
Stakeholders and the public believed that, the industry within the Public Sector has not
efficient and effective in projects deliveryin the Construction industry. This is evidenced
by the high number of delayed construction projects distributed all over the country.
There is high rate of non-completion of projects, budget overruns and extensions of
contract periods.
1.3.Research questions
1. What are the major challenges that affect the implementation of road construction
project in Addis Ababa?
2. Which challenges commonly affect the project implementation?
3. What are the effects ofthe challenges on the road construction in Addis Ababa?
4. What arethe existing conditions the selected road construction project in Addis
Ababa?
1.4.Objective
1.4.2 Specificobjective
To identify the major challenges thataffects the implementation of road
construction projects inAddis Ababa.
To examine and rank the major challenges that affect project implementation in
Addis Ababa road construction project.
To determine the effectsof thechallenges on road construction projects.
To check compliance of the existing road construction with standards
CHAPTER TWO
LITERATUREREVIEWS
2.1.Introduction
The construction industry, by nature, has many special problems and requirements. The
importance of taking measures to improve the performance of the construction industry
has now been recognized in several countries at various levels of socio-economic
development. Dedicated agencies have been formed in many countries to administer the
continuous improvement of the industry, although they have different objectives,
responsibilities and levels of authority. In the UK, the Construction Industry Board is an
industry initiative, whereas its counterpart institutions in developing countries are
government agencies. Considering the nature of the industry‟s needs and problems, and
in many developing countries, the resource constraints, formation of an agency does not
guarantee the success of construction industry development [1].
The construction industry is one of the main sectors that provide important ingredients
for the development of an economy. The construction industry is the tool through which a
society achieves its goals of urban and rural development. However it is becoming more
complex because of the sophistication of the construction process itself and the large
number of parties involved in the construction process, i.e., clients, users, designers,
regulators, contractors, suppliers, subcontractors, and consultants [5].
2.3.Construction Projects
A project is a unique process, consisting of a set of co-ordinate and controlled activities
with an assumed start and known finish dates, undertaken to achieve an objective
conforming to specific requirements including constraints of time, cost and resources [8].
Urban roads serve a variety of mobility needs including general public use, commercial,
merchandise, and emergency vehicle traffic. Maintaining traffic flow during construction
is an important issue.The number of complex projects in urban areas will likely continue
to increase in the future. Aging road infrastructures, right-of-way (ROW) constraints, and
increasing urban populations lead to difficulties for construction projects on existing,
congested, urban road projects.Overall system mobility must be considered in a
congested urban area undergoing construction [4].
Complexity is the key element when looking into the specifics of urban road construction
projects. Urban road projects are constructed in a physically constrained environment.
Existing road networks are dense and often intertwined with other infrastructures.
Scarcity of land in an urban setting implies high land acquisition costs this in turn makes
it very difficult to relocate those affected by the road project[11].
2.4.2.1.Utility conflicts
Utilities are the „conduits‟ or „technological systems‟ which support the rapid movement
of waste, water, energy and information up on which their integration together into
economic and social structure depends [13].
Urban corridors are not only congested with vehicles and people but also filled with
utilities, each one a potential conflict for the planned work. For many years, the natural
pattern has been to install utilities in streets and highways. It can take many forms,
whether aerial or underground. Some are privately owned and others owned by
municipalities, such as a local water company [4].
Urban utilities infrastructure accounts the water supply, sewerage facilities, drainage
systems, power distribution networks, communication transmissions and other related
underground, surface and overhead services and facilities [14].
In Addis Ababa, when utility companies (i.e. ETC, AAWSA, and EEPCO) needed to
install new lines or to improve the existing ones underneath the roads, they used to
apply to the Addis Ababa City Road Authority (AACRA) for permit to cut paved roads.
Very often permits were not granted promptly. Besides, the permits given were not
based on adequate information and database. The concerns of the utility company that
secured such a permit were limited only to laying its own utility lines. As a result such
developments often took place at the expense of the other utility lines that were already
in place. In fact this has resulted in the cutting and destruction of other infrastructure
lines that were otherwise functioning in good conditions. It has also resulted in delaying
in the implementation of projects thereby adversely affecting overall city infrastructure
and services provision[15].
From the perspective of utility companies, delays in ROW acquisition and frequent
changes to the design are the main reasons for delays in utility relocation. Past experience
with frequent design changes keep utility companies from getting involved earlier in the
project development process, for fear of wasting time, effort, and money on a relocation
that a project may no longer need after a design change[16].
Utility companies often lack accurate records on precise locations of underground utility
lines. In this case, they will not identify if utility lines are required to be moved,
especially in urban areas where utility lines have been installed years ago.In cases where
a utility conflict is anticipated, the problems should be studied with utility companies and
a contractor to come up with a best possible solution. The project design should be
revised and updated in order to expedite the construction and minimize the delays. A
delay mostly occurs when the prime contractor cannot work as a result of utility conflicts.
That is why it is important for the utility company and the contractor to establish good
cooperation between them during the actual construction of the project.Using some type
of utility locater is costly to use but it would be even more costly and time consuming if a
utility line is detected in the process of construction [17].
Since no proper records exist of the underground utilities like water supply, sewerage
lines, electrical and telephone cables etc., these utilities get identified as encumbrance
only during the implementation stage of the project. Similarly shifting of overhead
electrical and telephone lines (which are visible including poles) takes a long time. This
leads to delay as the shifting of these utilities brings in hardships to the general
population and suitable alternate arrangements are required to be made. There are
numerous government agencies involved from which clearances/approvals/permissions
are required to be obtained before the utilities can be shifted or relocated. This takes a
great deal of time. There are cumbersome procedures involved and sometimes the
relevant laws and regulations are also not very clear [18].
domain acquisition or have other inherent problems. Utilities with a history of slow
response in making adjustments should be aggressively managed. It should be noted that
ROW and utility adjustment issues may be of concern even in cases where the parcel or
utility is owned by a separate public entity. A strategy must be developed to address these
problematic parcels and/or utility adjustment [19].
In the context of Addis Ababa city road construction projects the ROW problem is related
to land acquisition issue from the community for the purpose of the infrastructure
development and relocating of utility facilities. The land required for these projects
includes the land to be used for the construction of the road which includes appropriate
ROW according to the requirements of the Addis Ababa city master plan standards and
other part of the land which will be used by the contractors as local material sources such
as quarry site, spoil area, and temporary land for material stock piling, pre-casting yards,
warehouse, workshops, parking lots, etc. ROW obstructions are one of the prevailing
risks hindering the progress of road construction in urban areas unless intensive
intervention measures are adopted [3].
Due to the construction time, land acquisition will occur .This will result in loss of
infrastructure; commercial activities and disturbance to people. The compensation for the
structures, plots, private and public properties etc. has to be made as per law[24].
publication (2012), the following are the major issues included under ROW:Delay in
clearance of ROW properties which includeswarehouses,fences,trees,Crops and grazing
lands [3].
Studies in Florida, USA, show the right of way costs for new or expanded roadways
exceed the cost for construction. The right of way acquisition process can begin after
60% of the design is completed; however, the process typically begins after 90% of the
design work is completed. The roadway design team leader is recommended to be
prepared with the backup documentation to support the design decisions made regarding
access management and to provide that information to the right of way team. The right of
way team often can consist of appraisers, land planners, engineers, accountants, and other
experts in the field. Their task is to estimate the fair market value of the property being
acquired. The right of way team will carefully review the work completed by the
roadway design team. This work will extend onto the property to address any secondary
problems that the driveway grade might create. Careful consideration and good, proactive
coordination in dealing with the secondary problems by the roadway design team during
the plans development phases can reduce the time and costs associated with the
acquisition process[22].
Due to the construction activities, proper traffic management may pose a challenge in the
project area. This may result in traffic jams and cause inconvenience to the people
passing through the project area due to movement of vehicles carrying construction
materials. It will also increase the traffic load on the existing road network, thus
deteriorating the existing condition of the road. Also, the movement of vehicles along the
haulage routes may cause soil compaction and alteration of percolation, and damage to
properties and utilities[24].
Managing the substantial volumes of traffic found in these urban corridors is, perhaps,
the most confusing problem for agencies. Sometimes alternative corridors exist to which
traffic can be diverted; traffic movement also can be facilitated by other means in spite of
the major impacts of actual construction [4].
complexity, the industry plays a major role in the development and achievement of
society‟s goals. It is one of the largest industries and contributes to about 10% of the
gross national product (GNP) in industrializedcountries, many local construction projects
report poor performance due to many evidential project-specific causes such as:
unavailability of materials; excessive amendments of design and drawings; poor
coordination among participants, ineffective monitoring and feedback, and lack of project
leadership skills. Project performance can be measured and evaluated using a large
number of performance indicators that could be related to various dimensions (groups)
such as time, cost, quality, client satisfaction, client changes, business performance,
health and safety. Many factors ashaving influence on project cost performance, these
include: project manager's competence, top management support, project manager's
coordinating and leadership skills, monitoring and feedback by the participants, decision-
making, coordination among project participants, owners' competence, social condition,
economic condition, and climatic condition. Coordination among project participants,
however, was identified as the most significant of all the factors, having maximum
influence on cost performance[26].
2.4.2.4.1Contractor capacity
Road contractor‟s performance problem appears in many aspects in developing countries.
Many road projects fail in time performance, others fail in cost performance and others
fail in other performance indicators. In the past there were many road projects which
finished with poor performance because of many evidential reasons such as: obstacles by
client, non-availability of materials, road closure, amendment of the design and drawing,
additional works, waiting the decision, handing over, variation order, amendments in Bill
of Quantity and delay of receiving drawings. There are other indicators for problems of
road contractor‟s performance in developing countries such as project management,
The major issues of concern during urban road construction are mentionedas follows:
2.4.2.4.2. Consultantcapacity
The major issues of concern during urban road construction are mentionedas follows[3].
2.4.2.4.3.Clientcapacity
The major issues of concern during urban road construction are mentionedas follows:
2.4.2.5. Scheduleconstraint
Road construction operations, rules governing the actions and interactions of the
resources should be identified, developed, classified and modeled through a
comprehensive analysis of several road construction projects. For every road construction
operations (activities), project templates in advance should be defined and developed.
Through the templates, which summarize productivity, factors influencing the
productivity of resources and the sequence of works, the basics towards complete
executions planning and scheduling are achieved [29].
Construction planning and scheduling tasks are fundamental and challenging activities in
the management of executing construction projects. It involves choice of construction
technologies, definition of work tasks, estimation of the required resources and durations
for individual tasks, and identification of any interactions or constraints among the
different tasks. A good construction plan is the basis for developing the project budget
and the schedule of work. Poor estimates or schedules can easily result in large
construction cost increases or delays[31].
movement and over all construction works. Since most parts of Ethiopia have three
months of rainy season each year, these times of the year are usually known to disturb
ongoing road constructions. rainy seasons are also known to have their own negative
impact on road delay of the construction Due to this, construction time is extended and
detour roads does not give the expected services resulting in inconvenience of
transport[32].
not resolved through a formalized variation management process, can become the major
source of contract disputes, which is a severe risk contributing to project failure[33].
These causes of construction delay were categorized into the following eight major
groups[36].
1. Client related factors: finance and payments of completed work, owner interference,
slow decision making and unrealistic contract duration imposed by owners.
2. Contractor related factors: delays caused by subcontractor, site management, improper
construction methods, improper planning and errors during construction, and inadequate
contractor experience.
3. Consultant related factors: contract management, preparation and approval of
drawings, quality assurance and waiting time for approval of test and inspection.
4. Material related factors: quality of material and shortage in material.
5. Labor and equipment related factors: labor supply, labor productivity and equipment
availability and failure.
6. Contract related factors: change orders and mistakes or discrepancies in contract
document.
7. Contract relationship related factors: major disputes and negotiations, inappropriate
overall organizational structure linking to the project and lack of communication between
the parties.
8. External factors: weather condition, regulatory changes, problem with neighbors and
unforeseen site condition
Client-related and contractor-related factors have impact on the time overrun. Factors
such as inadequate planning by the contractors, improper site management by the
contractors, inadequate project handling experience of contractors, and delay in the
payments for the work completed directly affect the completion of the project and cause
time overrun[36].
professionals, cost overrun implies inability to deliver value for money and could well
tarnish their reputations and result in loss of confidence reposed in them by clients. To
the contractor, it implies loss of profit for non-completion, and defamation that could
jeopardize his/her chances of winning further jobs, if at fault. To the industry as a whole,
cost overruns could bring about project abandonment and a drop in construction
activities, bad reputation, and inability to secure project finance or securing it at higher
costs due to added risks [38].
All these consequences undermine the viability and sustainability of the construction
industry. The effects of cost overrun are not confined to the construction industry but are
reflected in the state of the overall economy of a country. They state that delays and cost
overruns in construction projects prevent the planned increase in property and service
production from taking place, and this phenomenon in turn affects, in a negative way, the
rate of national growth[39].
foundations, fencing, walls, kerbs, old pavements, abandoned pipelines, disused public
utilities and any other obstructions which are not designated or permitted to remain,
except for the obstructions to be removed and disposed of under other items in the
contract[42].
As the planning dimension, the institutional dimension used to assess the partners‟
coordination as the main point of interest. The concept of institutional coordination is
used to express official inter and intra-sectoral relationships among the city
administration and utility infrastructure providing institutions in the course of the city‟s
utility infrastructures provision. The problem of the institutional dimension is
characterized in terms of: inefficient use of resources(financial, material, land, labor and
time resources), an expenditure of large amount of money for the relocation utilities
compensation, problem in access of the revised city plan, lack of institutional
coordination when one institution builds the other destroys, inconsistency in
compensation payment, cumbersome procedures during the process of utility
infrastructure relocation and during the work of the city redevelopment projects [37].
CHAPTER THREE
RESEARCH METHDOLOGY
3.1. Study area
The study of this research was carried out in Addis Ababa which is the capital city of
Ethiopia. Geographically, Addis Ababa is located at the center of the country. It is
located in the plateau of mountain ranges at an altitude of 2200 to 3000 m above mean
sea level and the topography ranges from rolling to hilly area with relative steep
gradients. The city administration extends over 540 square kilometers with 10 Sub-cities
and 116 Woredas for administrative purpose. In addition to this, the city is allocated 220
km2 for green area (i.e. Forests, Parks, River Buffers, and Urban Agriculture). Vegetation
cover of the city is 80km2, and dominant species is Eucalyptus trees and rich in rare but
diverse flora and fauna[44].
the major challenges of ongoing road construction and effect of the challenges on the
selected road construction projects.
The desk study was undertaken by the researcher to obtain actual data from the source
documents which included in the contract documents, supplementary agreements, progress
report and site visit as well as to have appropriate data about the selected Road project
that are found in Addis Ababa. The other instrument employed was to asking professional
opinion and relevant data through questionnaires.
The questionnaire survey was take place by distributed questionnaires to the selected
Client, contractors and consultant‟s whereas, the interviewconducted to some top
managers which involved in the road construction in Addis Ababa.
In this study, the questionnaire consist both closed and opened questions in order to
identification of the major challenges and their effects on selected on-going. The
participants were requested to allocate marks from 0 to 4 (a 5-point Likert‟s scale).It
employed the five point type Likert ordinal scale to measure level of usage by responding
firms from “Very low Challenge” to “Very highChallenge” that is, 1= Very
The basic tools of analysis for the collected data to achieve the objectives of this research
are summarized as follows
The Relative Importance Index method (RII) was used identify the major challenges of
ongoing construction and determine the effect of the challenges of road projects in the
city of Addis Ababa respectively. Therelative importance index can be computed by
applying the relationship as shown below[45].
RII
W
A * N ……………………Equestion-1
Where: W is the weight given to each factor by respondents and ranges from 1 to 5
W wi * xi ; Where: i= response category index
wi= the weight assigned to ithresponse = 1, 2, 3, 4, 5, respectively.
xi= frequency of the ithresponse of the total responses for each factors.
A is the highest weight = 5 N is the total number of respondents
Ranks of the identified challenges and effects of the challenges are calculated based on
relative importance index, as perceived by different parties are tested for correlation. The
purpose of a correlation test is to see if there is difference in ranking between two groups
of respondents and to avoid being deceived by chance of occurrences and impact as
ranked by single part. The tests also helped to evaluate whether agreement of opinions
exist among respondents
The Spearman‟s- rank correlation coefficient (rs) for agreement in ranking between the
two parties is given by the following formula [46].
6 d 2
rs 1
N(N 2 1 ) ………………………………… (Equation-2)
d =the difference in ranking between the contractors, consultants and clients and
N= is number of variables
The rank correlation coefficient is used for measuring the differences or agreement in
ranking between two groups of respondents scoring the various factors (i.e. clients versus
consultants, clients versus contractors and consultants versus contractors).
respondents and the data carefully. During the data analysisto obtain quality of data the
researcher would be assured by giving attention to the following points.
Before collecting data, all the source of population availability has to be checked
and respondents‟ daily work schedules have to be respected.
All the questions has to be put in simple & clear ways
All the system for quality control /assurance of data collection has to be worked
out effectively
CHAPTER FOUR
RESULTS AND DISCUSSION
4.1. Basic information on respondents
This section is mainly designed to provide general information about
respondent‟spositionand experience in road construction projects. Thirty (30)
questionnaires were distributed to the respondents as follows: ten to client (AACRA)
employees, ten to consulting firms and ten to contractor organizations. The
comprehensive analysis of total respondent‟s was (73%)valid responses were collected.
Table 4-1: Response rate by category
Contractor 10 10 100 7 70
Consultant 10 10 100 7 70
Client 10 10 100 8 80
Total 30 30 100 7 73
The survey was conducted by visiting the ten (10) selected ongoing road projects and
gathering necessary information from each site by preparing checklist for each site.
Distribution of questioners was done mainly through personal networking with
construction professionals, and by assigning data collector. Moreover, respondents were
contacted both in person by participation on the site for the distribution and frequently
contacted through phone calls.
Figure 4.1was illustrated that , 7% of the respondents where at Project manager position,
20% of the respondents where site engineers, 27% project coordinator,30% Resident
engineer and 16% of the respondents where others who work in the organization.
60%
Percent
Table 4-2: Challenge affecting implementation was and still is a problem or not in Addis Ababa
road construction projects.
Are there Challengesthat Client Contractor Consultant
affect implementation in
Addis Ababa road projects? Frequency % Frequency % Frequency %
YES 10 100 10 100 10 100
NO 0 0 0 0 0 0
Total 10 100 10 100 10 100
Table above shows, From the Selected Road Projects100 % of the respondents for this
research have recognized that there are challenges thatare being a problem for the
implementation of road construction in Addis Ababa city.
The above table illustrated thatthe physical progress of the selected road projects such
as:CMC-roundabout up to Karalo junction 84.68%,2nd police station-Kideste Mariam
30.13%,Yerergoro–CMCmichaelchurch 63.15%,Koyefeche condominium lot 1& lot 2
62.08%, Radiobecon- Kotebefisashmatari50%,Agusta–betel-alembank 1.9%,Mexico-
amestegna police 5%,Kadisco paint factory-Crown hotel 2.4%,Gazebo-Meskel flower
52.6% and BiserateGebriel-aboround about 5.03%.The above physical progress was
estimated according to the engineer‟s evaluation which comes from the actual progress
sum of works in different categories such as earth works, pavement layers, drainage and
structures, incidental works, day works and utility.
The actual physical progress percentage was calculated from weighting average
percentage of the works categorized, but the engineer‟s evaluation differs from site to
site. The method of estimation was shown in appendix B.
The CMC Round About – Karalo Junction Asphalt Concrete Road Construction Project
is one of the road construction projects undertaken by the Addis Ababa City Roads
Authority .The road is mainly intended to serve as a link road to the two main roads
namely the Hayat -Megenagna and Megenagna- Kotebe roads.
Problemsobserved from the site were ; obstruction of fiber Cable and main water supply
line at Sta. 0+120 and the Septic tank of Sunshine real state at Sta. 1+100 on the
LHS.Utility relocation was still remaining which created discontinuity of the routine
earthwork, pavement and drainage works. It also affects the next activities and ultimately
the time of project completion and delivery.Delay in the construction of Sub base, Base
course, the Asphalt surfacing operations associated with the failure of the Contractor
regarding the timely delivery of the materials satisfying the project specifications, The
production of Base course material not sufficiently cover the total length of the project
which brings interruption of the work.
Due to the existence Row problem three houses from km 1+650 to end of project and no
solution have been given from YekaKifleketema about their removal because of this
reasonutility companiescould not mobilize to relocate their properties.
The construction work especially the outlet excavation work at km 0+963 box culvert
have been interrupted due to Unfavorable weather condition, Shortage of sub base
material has become a main problem to complete the pedestrian walkway due to this
challenges theproject delayed2 years from the contract completion period.
4.3.2.2. 2nd Police Station -Kidestemariam church- Minilik Hospital Asphalt Road
project
Client AACRA
Problems encountered on second project were; Non removal of right of way obstruction
house and fence, Utility not relocated at the appropriate time of the project such as
Copper and optical fibre cables crossing the road at km 0+420, 200mm , DCI (ductile
cast iron) pipe crossing the road at km 0+ 420, 100mm and water pipe line(km 0+420-km
0+460 & km 0+580 RHS) right hand side, Electric pole and wires(km 0+810-0+920
LHS) left hand side,electric and Tele-cables(at km 1+720)was shown in Appendix(Figure
7: Utility related ROW observation.)
Utility institutions (i.e. Tele, Electric and AAWSA) due to their lack of coordination may
causes of utilities are not to bedisconnected, relocate and install at the appropriate time of
the construction phase. Due to such reason the project face for different challenges.The
project was delayed 1year from the contract completion period.
Figure 4.5:2 N D police station- kidestemariam church- Minilik hospital asphalt road
Table 4-6: Project data for Yerergoro school- cmc at st. Michael church
Project tittle Yerergoro school- cmc at st. Michael Church –
Kotebewendyrad school Asphalt concrete road
project
Client AACRA
Figure 4.6: Yerergoro school- CMC at st. Michael Church –Kotebewendyrad School
Asphalt concrete road project.
Figure 4.7: km4+600 DCI pipe not relocated by EEU junction work.
It‟s noted that due to possession of the site as a result of delay in approval of master plan
and delays in removal of the obstruction in the Row limit, the contractor is guaranteed an
extension of time of a total of 634cal day.
The engineer representative has repeatedly reported about the ROW problems and
difficulties that will be faced on the on-goingworks. There is still unresolved right of way
issue basically on junctions and currently the situation is very critical as the contractor is
finalizing the major road way works of the remaining sections. The project delayed by 2
years.
The total length of the road is 5.89km and designed to be constructed to asphalt concrete
standard .The project has entirely 5 routes under two lots of different formation width.
The first contract(lot 1) include 3 route access road1, access road 2 & route 3 with road
length of 0.72 km,0.52 km,&1.30 km respectively.This lot has total road width of 40m
comprising 2* 7=14m dual carriageway,2*5=10m walk way,& 16m median for future
expansion. The second contract(lot 2) consists two parts namely route 1 and route 2 with
respective road length 2.63 km & 0.72km.unlike to the first contract lot 2 has total width
of 30m comprising 2*10=20m dual carriage way,2*4.5=9m walk way and 2m median.
`
Figure 4.8:Koyefeche road project
Farm land
Retaining wall
Problem encountered such as Houses and fences located in Row limit access road 1are
still remaining as obstructions. The late removal process of farm lands are identified at
route 3of lot 1 for the construction of retaining wall and junctions has been also
delayed.AndalsoFences and houses of Akaki-kality sub-city housing project office which
is located in Row limit of route 4 were not removed.The removal and/or relocation of
remaining obstructions is still one of the major causes of delay in progress of the project.
Late possession of the site for Row affected sections of the project road may result in
raising potential claims for time extension and additional payments for related problems
The project delayed by 1 year.
The project is located in Addis Ababa city bole sub city and it connects the ends of two
roads running from St. George church round about to end of summit condominium and
yerer round about to lemiIndustry Park.
Client AACRA
The road project is located in the western part of AddissAbaba city in the kolfekeraneyo
sub-city of the city administration.it starts at betel round about, passes through the betel
teaching general hospital and ends at alem bank round about.
Median 50cm
Client AACRA
Client AACRA
The road project is located in the southern part of Addis Ababacity in Akakikality sub-
c.ity. It starts at kadisco factory and ends at crown hotel. Over the last few years, the
A.ddis Ababa city administration has continued with a wide program of
construction,rehabilitation, and modernization of the road infrastructure network.
Table 4-11: Project data for Kadisco paint factory to crown hotel
Project title Kadisco paint factory to crown hotel
road project
Project width 25m
Carriage way 9.25m each side
Walk way 3.25m on both side
Funding Addis Ababa city administration
Client AACRA
Contractor AACRA own force
Consultant AACRA design department
Date of signining of contract Nov,2014
Commencement date Feb,2015
% financial accomplishment 72.65%
% physical progress 20%
The project kadisco-crown hotel road is 1.73km long road project. It shall have a width of
25m with a divided carriageway of 9.25m on each side.it also shall have a 3.25m wide
walkway on both sides.it has side drainage structures of reinforced concrete pipes run
both sides of the roadway along the entire length.Thecarriage shall be asphalt concrete
and walk ways on each side were planned tobe coble stone for pedestrian use.
Section from Meskel flower to Gazebo - has 25mts total carriage way width including
3.5mts walkway on each sides and 1m medians.
Client AACRA
The proposed road project is found in the Addis Ababa City Administration under
NefasilkLafto Sub city and the proposed route is Bisrate Gabriel Roundabout – ABO
Roundabout. The estimated total length of the road will be 1.441 km. Based on the
obtained data‟s from the site Bisrate Gabriel roundabout- Abo round about road is
residential areas.The project areas are among the densely populated and high traffic
loaded areas of the city. Moreover, these areas are major residential with highly
developed infrastructure networks and facilities.
The contractor started the work after the client approved consultnat traffic management
plan which was made jointly with the contractor. This plan include the safety of the all
road users including the workers at the site
Figure 4.15: The Construction Works for B/Gebriel - Abo roundabout asphalt road
project.
Urban projects are definitely affected by the acquisition of ROWs. Most common among
the impacts are cost over- runs and schedule implications. Owner expectations and the
Utility conflict has been ranked by the clients, contractor and consultants respondents‟ in
the second position with RII =3.8, RII = 4.2 and RII= 4.2 respectively. This problem can
also be considered as major challenge for road construction projects. Utility conflicts
occur at a high rate on most projects. In 2001, a similar survey to that of utility issues are
the main causes of construction delays. Transportation agencies, utility owners, and the
public will always have conflicts that must be addressed. Although these conflicts are
generally resolved before construction the financial impact on public agencies is
significant. In another NCHRP study effort, it was determined that in the United States up
to $120 million per year in contractor claims result from utility issues[4].
Scarcity of resources, materials has been ranked by both the clients and contractor
respondents‟ in the tenth and three position with RII =3.1and RII= 3.7 respectively. But it
has been ranked by consultant respondents‟ in the fifth position with RII=3.5. This
problem can be considered as an obstacle for implementation of projects. Contractors in
the city of Addis Ababa suffered from delay because of settlements around the city and
materials shortage [47].
Poor public awareness and design/poor planning was ranked on the seventh, and ninth
position respectively by all the respondents with having RII of3.5, 3.1 and 3.3, RII of 3.3,
3, and 3.2 from client, contractor and consultant respondents respectively, because it have
a little influence on the selectedroad projects.
Environmental factor was ranked on tenth place by the client with RII value of 3.1 and it
was ranked on eleventh place by both the contractor and consultant respondents with RII
value of 2.5, 2.6 respectively. Therefore this challenge has the least place on affecting
implementation of the selected road projects.
Challenges
overall RII
The figure abovesummarized rank of overall RII and the result shows the major
challenges Identified.according to their rank of overall RII results; right of way
(4.53),utility conflict(4.07),schedule constraints (3.65),variation order(3.53),poor
projectmanagement(3.5), Scarcity of material, financial (3.43),High
trafficproblem(3.33),performance of stake holders(3.3),poor public
awareness(3.28),Design/poor planning(3.16) and Environmental factors(2.73)
Were ranked respectively in descending order.Right of way problem has been ranked in
the first position by contractors, client & consultant.This result indicates that it have very
high challenge to complete the project on time. The right of way problem creates disputes
between the parties of project, and then the time of completion will be affected even
more.
4.3.1 Test for Agreements on the identified challenges that affecting implementation
of the selected road construction projects in Addis Ababa
This part of the study checks whether there is a significant degree of agreement among
the three parties (the client, contractors and consultants) in ranking challenges affecting
implementation of the selected road projects. Spearman rank correlation coefficient is
used as a measure of agreement among raters based on the relative importance index.
Using the formula given in equation 1of this research; degree of agreement between
client and consultant, contractor and consultant and client and contractor were checked
and presented in the Table below. Spearman‟s correlation works by calculating
correlation on the ranked values of this data. Using the aboveTable 4.15and equation 1,
Spearman correlation coefficients (rs) are calculated and tabulated as shown in Table 4.16
a significance association between the sets of ranks from calculated Spearman‟s rank
correlation coefficients (r s) is assessed, in order to see whether there is agreement
between two groups of respondents in ranking the factors; the level of significance 95%
(ρ = 0.05) is used. This allows verifying whether there is "agreement" between
respondents‟ response.
Table 4-16: Summary of spearman's rank correlation coefficients for identified challenges
Respondent Category Client Consultant Contractor
Client 1
Consultant 0.44 1
Contractor 0.45 0.9 1
Number of pairs of values in the data set n=11
For n=11& significance level of 95% (ρ = 0.05); Critical value of r s = 0.536 (appendix
D) Results of spearman‟s rank correlations revealed that the perception of stakeholders
(parties) vary greatly on the challenges affecting implementation in selected Road in
Addis Ababa road construction projects. The result in general indicated that there is a
weak correlation among parties as compared in ranking identified challenges. This could
In this result it is indicated that there is a strong correlation between contactor and
consultant with rs value of 0.9. The reason behind this is most of the consultants
supervise the contractors work thoroughly, so both the contractor and consultants have
exposure to the identified challenges that are affecting implementation of the road
projects.
From the correlation result in Table 4.16it can be seen that there was a very weak
correlation between consultants‟ and client‟s response as well as between contractors‟
and clients‟ responses. One of the reasons could be lack of exposure to the work by the
client and the stake holders.
4.3.2. Factors causes of the major Challenges that affect implementation in road
construction with their
This section focused on the identification of factor leading challenges thataffect
implementation on road construction projects in the city of Addis Ababa. For this
studybased on literature review, fifteen (15) indicators were considered and listed. The
factors were summarized and collected from progress reports and others were added from
literature.
The ranking of the factors shown in the Table below were done based on rate of
occurrence using relative importance index. The Relative Importance Index (RII) for each
potential factors influencing road projects during implementation period were calculated
using equation (1) − section 3of this thesis to rank the factors based on overall factors
Table 4-17: RII and rank of all factors from contractors, consultants, client (AACRA), and
overall respondents‟ point of viewfrom all categories.
Client contractor consultant OVER ALL
Factor RII Rank RII Rank RII Rank RII Rank
slow clearance of right of way 4.6 1 4.9 1 5 1 4.83 1
Lack of coordination of utility
services 4.5 2 4.7 2 4.5 2 4.57 2
Delay of compensation 3.8 7 4.5 3 4 3 4.10 3
Slow and decision making & tedious
project approval process 3.8 7 4 4 3.8 6 3.87 4
Relocation of utility services 3.9 4 3.8 6 3.8 6 3.83 5
Very loose coordination and
integration among stakeholders 3.6 9 4 4 3.9 4 3.83 5
Design change/ variation order 3.9 4 3.4 9 3.9 4 3.73 7
Design change of the utility services 4.2 3 3.5 8 3.2 12 3.63 8
management process system 3.6 9 3.6 7 3.5 9 3.57 9
Lack of public awareness 3.87 6 3.4 9 3.1 13 3.46 10
High traffic jam 3.4 11 3.1 11 3.6 8 3.37 11
Lack of alternative roads 3.2 12 3.1 11 3.3 10 3.20 12
Poor back ground in project
management 3.1 13 2.8 13 2.9 14 2.93 13
Slow movement of heavy
construction equipment‟s 3 14 2.3 14 3.3 10 2.87 14
Lack of flag man/coordination 1.9 15 2 15 2.6 15 2.17 15
This group contains 15 factorsfrom all categories of that are factors for the challenges of
road construction projects. The factors for the challenges of road project has been ranked
by the client‟s, contractors‟ and consultants respondents The result summarized as for the
challenges of road construction from the respondents rate of RII slow clearance of ROW
has been ranked by the clients, contractor and consultants respondents‟ in the first
position with RII =4.6,RII = 4.9 and RII= 5 respectively.All client, consultants and
contractors feel with thisslow clearance of ROW sensitive problem in their projects. Lack
of coordination of utility service was rankedby the clients, contractor and consultants
respondents‟ in the second position with RII=4.5,RII = 4.7 and RII= 4.5 respectively.
High traffic jam was ranked by the client and contractor in the 11th place and it was
ranked in 8th placeby the consultants. Lack of flag man /coordination was ranked by the
client, contractor and consultant respondents in the 15th place with RII 1.9, 2, 2.6
respectively. It have been ranked in the last place by all of the respondents because it
have the least influence as a factor, for the challenges on the selected ongoing road
projects.
5.00 4.83
4.57
4.50 4.10
overall Relative important index
2.50 2.17
2.00
1.50
1.00
0.50
0.00
The figure summarized rank of overall RII for the factors, the result shows challenges
Identified and listed below according to their rank of overall RII results in
descendingorder; slow clearance of right of way (4.83),lack of coordination of utility
service(4.57),delay of compensation (4.10),slow and decision making and tedious project
approval process(3.87),relocation of utility service(3.83),very loss coordination and
integration among stakeholders(3.83), design change or variation order(3.73),design
change of utility service(3.63),management process system(3.57),lack of public
awareness(3.46),high traffic jam(3.37),lack of alternative roads(3.2), poor background in
project(2.93) slow movement of heavy construction equipment(2.87) and lack of flag
man coordination(2.17).
Therefore from the rank of overall RII for the factors, we can understand that slow
clearance of ROW problem was at the first place and lack of flag man coordination was
listed as the least factor from the selected 10 ongoing road project sites.
Table 4-18: Rank effects of the challenges on road construction project from all Respondents‟
point view
Time over run has been ranked by the client respondents in the first position with RII of
4.1 and has been ranked by contractors and consultant respondents also in the first
position with RII of 4.5 and 4.7 respectively. And also Budget overrun has been ranked
by the client and contractors,consultant respondents with RII of 4, 3.6 and 3.6 in second
position has been ranked by the respondents respectively.
However, this effect is highly influence on the implementation of road construction.In
construction delay could be defined as the time over run either beyond completion date
specified in a contract, or beyond the date that the parties agreed upon for delivery of a
project. It is a project slipping over its planned schedule and is considered as common
difficult in construction projects. To the owner, delay means loss of revenue through
4.5
4.0 3.7
3.5 3.2 3.3
2.9 3.0
3.0 2.5
2.5
2.0
1.5
1.0 Effects
0.5
0.0
Effects
The figure summarized rank of overall RII the result shows that effects are determined.
Listed below according to their rank of overall RII results; Time over run(4.4),Budget
over run(3.7),Creating social problem (3.3),Reduce work motivation(3.2),Dispute
between parties(3.0), Project termination (2.9),Leadership removal(2.5).The result shows
thatTime over run is Very high impact in AddisAbaba road construction projects from the
respondents rate .
Generally the respondents are observed that time and cost overrun is one of the major
effects on the Addis Ababa cityroad projects.Creating social problem, Reduce work
motivation disputes between parties, Terminate the project and Leadership removal are
also the effects on road construction.
For n=14& significance level of 95% (ρ = 0.05); Critical value of r s = 0.786 (appendix
D) Results of spearman‟s rank correlations revealed that the perception of stakeholders
(parties) vary greatly on ranking the determined effects caused by the identified
challenges on the implementation of road projects in Addis Ababa city.
In this result it is indicated that there is a strong correlation between contractor and
consultant with rs value of 0.79. The reason behind this is as mentioned for the identified
challenges i.e. most of the consultants supervise the contractors work thoroughly, so both
the contractor and consultants have exposure to the effects caused by the identified
challenges that are affecting implementation of the road projects.
From the correlation result in Table 4.19it can be seen that there was a very weak
correlation between consultants‟ and client‟s response as well as between contractors‟
and clients‟ responses. One of the reasons could be lack of exposure to the work by the
client and the stake holders.
-Existing structures and installations shall -The demolished structures All the selected
be demolished as described in the contract were not removed so they ten projects
such a way as to leave no obstruction to are being an obstruction to
the new works [43]. the work
-Existing houses on the
road way were not
demolished because the
government did not give
compensation for the house
holders in time.
Structures which are to be partially There are some structures -Cmc
demolished, shall be shored, braced and are not demolished roundabout
supported in such a manner that the completely in addition to
integrity of the structure shall be this, they are not shored, - 2nd police sta.
maintained. All supports should be kept braced and supported.
- Mexico
outside the right of way [43].
-Kadisco
-Gazebo
- Unless otherwise directed by the engineer Voids below the existing - 2nd police sta.
any voids below ground level in existing structure were not filled
structures or installations shall be filled appropriately. - Mexico
with natural sand or crushed fine aggregate
-Gazebo
[43].
Besrategebriel
- Latrine pits, septic tanks etc. shall be The waste coming from the -Gazebo
cleaned out and disinfected and the breakage of the septic
contents disposed of generally in tanks during construction,
accordance with the requirements for were not cleaned or
hazardous materials before the filling with disinfected
approved materials[43].
During the assessment period, the road mentioned in the above table shown not comply
the with standard requirement projects due to factors such as; partially demolished
structures remaining on the site were not removed so they are being an obstruction to the
work, Voids below the existing structure were not filled appropriately and the affected
existing houses on the road way were not demolished because the government did not
give compensation for the house holders (property owner) on time.
The arrangement is required to begin from -Narrow space for All selected
the sides of streets and then need to end on utility services during road projects
the side of individual property lines as in the the design stage.
order of: drainage line - electric power
distribution line- telecommunication -wrong arrangement of
transmission lines and then at the end the the utility lines
water supply distribution system with the
minimum required distances of 0.50-1.0
meters between two consecutive utility lines
[14].
400 mm DCI
pipe
Electric
TELECOM
Figure
4.23:Narrow space for utility services during the design stage and wrong
arrangement of the utility line ( 2nd police station–kidestemariam)
Figure 4.25slow clearance of Electric pole and Tele wire box (Kadiskopaint factory
– Crown Hotel, Meskel flower - Gazebo)
Figure 4.26: Bundles of underground optical fibers and copper cables at 0+420km
which crosses the road project (2nd police station – kideste Mariam)
From the site survey and check list (guide list) most of the selected roads did not comply
with the standards set by AACRA. The Addis Ababacity utility infrastructures providing
authorities as well as the city administration were not familiarized about the standards for
utility infrastructures arrangement and minimum horizontal distances between utilities.
Utilities Electric, communications, gas, water, and sewer lines will normally be located
within the ROW of highways. In order to prevent utility maintenance from interfering
with highway traffic, nounderground utilities should be located beneath any part of the
pavement, except where crossings are required. Where these underground utilities must
cross beneath highways, theyshould be so designed and constructed as to minimize future
repairs and consequent interference with traffic. Obstructions including signs and poles
for overhead utilities shall be located outside the limits of usable shoulder on highways
designed without barrier curbs. Generally, utility poles should not be located in medians
on divided highways [50].
-Install and maintain temporary traffic Temporary traffic control devices All
control devices adjacent to and within were not installed. selected
the project as required by the traffic projects
control plan[43].
-The safety of the travelling public There were not enough Traffic safety All
is of utmost important and every officers to control the site ways and selected
effort must be made to ensure that side tracks, the provision of traffic projects
all road signs, barricades, controllers, lights, barriers ,ramps,
delineators, flag men and speed signs, road markings ,fences ,detours,
controls are maintained and and anyother items required for the
effective and that courtesy is safe and easy passage of all public
extended to the public at all times traffic were not applied
[43].
As we can see from the figure above, Accident happened at chainage 1+100 for
inappropriate back movement without guidance from safety works. The selected roads
have High traffic volume, temporary road way signs are not available on the project
progress area and also there are no safety officers. Therefore, they do not comply with the
standards set by AACRA.
Based on the questioner survey 70% of the stakeholders prepare traffic management plan
and the rest 30% did not have a traffic management plan because the sites were located
where there is less traffic volume.
Proper traffic management plan will be needed to avoid traffic jams/public problem,
Movement of vehicles carrying construction materials should be restricted during the
daytime to reduce traffic load and problem to the local residents, Coordinated planning of
traffic diversions by the traffic police and the Transport Department in accordance with
the construction program with advance warnings to the affected residents and road users,
The executing agency is required to maintain cooperation between the Traffic Police,
travelers and the contractor to facilitate traffic movement during construction stage [51].
2. Organization working progress with in the original time schedule and cost
estimate
Table 4-24: organization working progress is within original schedule and cost estimate
Do you think Client Contractor Consultant
organization
working progress is
within original
schedule and cost
estimate? Frequency % Frequency % Frequency %
YES 0 0 0 0 0 0
NO 10 100 10 100 10 100
Total 10 100 10 100 10 100
From the questioner survey data the above table and chart shows 100% of the
respondents agree that the working progress is not within the original time schedule and
cost estimate due to the challenges that identified. The organization of working progress
is affected by numerous problems due to this reason the projects not moves forward with
in original schedule and cost estimate.
3. Utility services during design stage to avoid the utility conflict on Addis Ababa road
construction project and lack of coordination of utility services affect the organization
Based on the questioner survey the above table and chart shows 70% of the stakeholders
prepare utility service plan during design stage and the rest 30% doesn‟t prepare utility
service design due to lack of coordination between the stakeholders.
by, among others, lack/shortage of basic urban infrastructure and services. It is also
vividly observed that the existing scanty infrastructure and services in the urban centers
are deteriorating mainly as a result of poor design and installation practices and due to
lack of timely maintenance. On top of this, lack of coordinated and integrated
infrastructure and services planning and implementation has exacerbated the problems
observed in the infrastructure development effort of the country [53].
For the future, theinstitutions stated an objective to prepare (follow) procedures before
implementation of the road projects, exchange information andintegrate worksat each
stage. The necessities of utility institutional coordination are:
1. Institutional benefit: it will help the institutions for proper utilization of the yearly
budget; it reduces re work and time wastage
2. Urban level benefit: to satisfy the community need and to keep the future
development of the town.
CHAPTER FIVE
CONCLUSIONS AND RECOMMENDATIONS
5.1. Conclusions
Based on the data gathered from the desk study and the analysis obtained from
questionnaire survey,100%of express their agreement towards the issue that there
arechallenges affecting implementation of road construction in Addis Ababa city.
Results obtained from of the study showed that; Right of way ,utility conflict, schedule
constraints, variation order, poor project management, Scarcity of materials and finance,
high traffic problem, performance of stake holders, poor public awareness, Design/poor
planning, and Environmental factors were identified as major challenges affecting the
implementation of road construction. From these challenges,Right of way problem was
the first major challenge of the road construction projects based on the client, contractor
and consultant respondents with RII =4.4,RII = 4.6 and RII= 4.6 respectively. Utility
conflict wasthe second major challenge of the road project based on the clients,
contractor and consultants respondents‟ in position with RII =3.8, RII = 4.2 and RII= 4.2
respectively. Hence,these challenges have placed as the major‟s one that affecting
implementation of the selected construction road project.
This study obtained that, the effect of major challenges on the on-going construction road
projects were Time over run,Budget over run, Creating social problem, Reduce work
motivation, Dispute between parties, Project termination and Leadership removal with
4.4,3.7,3.3,3.2,3.0,2.9 and 2.5 RII value respectively. As ranked by frequency occurrence
of the relative importance index (RII) value the result shown that;Time over run was
Very high impact in AddisAbaba road construction projects.
The institutions are not familiar with the Addis Ababa city infrastructure standards so
theydid not complywiththe standards for utility infrastructures arrangement, ROW
requirements and traffic management approach.There is lack of coordination between the
institution (AACRA,AWSA,TELE and EEPCO /EEU)
5.2. Recommendation
In respect to this research finding, the following basic recommendations are expected to
be exercised by key role players of the construction industry, i.e,
Clients,ConsultantsContractors and utilityinstitutions in order to minimizechallenges on
ongoing Addis Ababa road construction projects. It is therefore forwarded the
recommendation to the following concerned parties
CLIENT/AACRA
An independent organization which has authority to coordinate all institutions that have a
role in the road construction should be established in order to minimize right of way and
utility conflict problems. In order to avoid time overrun and budget overrun, the client
shall properly evaluate the design submitted by consultants and bring the issue to a public
debate before awarding construction work. In this case the ultimate need of the client and
the public considerable variation and change of order will be avoided.
Before the construction starts, the client has to fulfill all the necessary requirements for
deliveringthe site. Failure to deliver the site will cause time and cost overrun.
Compensation must be given before the work starts for the property owner toreduce delay
of the construction work.In spite of this, Institutions and stake holders should be
instructed to comply with AACRA standard.
CONTRACTOR
The public should also be informed on the existence of road construction and alternative
routes must be made andshould have a strong accountability to minimize challenges that
cause delay on the road construction.
CONSULTANT
Detailed site investigation should be done at the design phase towards the actual field
data to minimize the challenges from occurring. They should also hold themselves
responsible for collection of accurate data and ideal solution during design work.
REFERENCE
[8] Keith L., James G . Project Management and project Network Techniques, Seventh
Edition of Critical Path Analysis and Other Project Network Techniques. 1996.
[9] Olateju, O. I., Abdul-Azeez I. A. &Alamutu, S. A. Project Management Practice in
Nigeria Public Sector an Empirical Study, Australian Journal of Business and
Management Research, 2011;Vol. 1(8), 01-07
[10] Assefa, A. Time – Cost Relationships for Public Road Construction Projects in
Ethiopia. Master Thesis, AAU, Ethiopia .2008.
[11] International road federation urban road network benefit of public private
partnership approach 2010.
[12] Collins, O.Factors Affecting Implementation of Community Projects: Case of
Kimira – Oluch Smallholder Farm Improvement Project in Homa Bay County, Universal
Journal of Management, Kenya,2013:111-118.
[13] Graham, S. , Marvin, S., „Managing Cities: The new Urban Context‟,Healey, P.ET
AL(eds.). More than Ducts and Wires: Post-Fordism Cities andUtility Networks. John
Wiley, London. 1994.
[14] Zegeye, y. The problem of urban utility infrastructure provision in ethiopia: the case
of BahirDar.July 2012.
[15] Mathewos consult integrated urban infrastructure and services planning manual
addisababaseptember, 2006.
[16] Edgar, K.Development of a utility conflict management tool, Texas Department of
Transportation Research and Technology Implementation Office.2007.
[18] H. L. Chawla, Consultant, World Bank Some Critical Issues pertaining to the Indian
Road Construction Industry September 2010.
[19] Bingham, E. Development of the Project Definition Rating Index (PDRI) for
Infrastructure Projects. MSc Thesis. Arizona State University, USA. 2010.
[20] Addis Ababa City Roads Authority, AACRA, Annual Publication, Addis Ababa,
Ethiopia.2012.
[21]Road Reconstruction in Post – Disaster Recovery; Challenges and Obstacles
EzriHayat ,DilanthiAmaratunga University of Salford
[22] Mark T. Llewellyn, P.E, Right Of Way Acquisition & Access Management Issues In
Florida. 2004.
[23] UnitedStatesDepartmentofTransportation.FederalHighwayAdministration.
[45] Cheung, S. O., Suen Henry C.H. and Cheung Kevin K.W. PPMS: A Web based
construction Project Performance Monitoring System, Automation in Construction, Vol.
13, PP. 361– 376.2004.
[46] Dowdy S,WeardenS.Statistics for research.2ndEd.NewYork:John Wiley &
Sons,1985. FOR CREELATION
[47]UNRWA .Projects completion reports, United Nations Relief and Works Agency,
Gaza2006.
[49]Arditi D., and F. Yasamis, Reasons for delays in public projects in Turkey, Journal
of Construction Management and Economics, 1997. Vol. 3, No.12, pp. 171-181.
[50] Department of the Army and the Air Force. General Provisions and Geometric
Design for Roads, Streets, Walks and Open Storage Areas., Washington DC, USA.1987.
[51] Anticipated Environmental Impacts and Mitigation Measures EIA of Construction of
Lahore Orange Line Metro Train Project May, 2015.
[52] Shehu.Z and Sommerville, J.Real time risk management approach to construction
projects, Glasgow Calonianuniversity, Glasgow, United Kingdom.2006.
[53] Pickering, D., park, J.M. & Bannister, D.B., „Urban Management and
Infrastructure‟: Utility mapping and Record Keeping for Infrastructure. World Bank,
Washington, DC 20433, USA. 1993
APPENDIX A
Sampled Questionnaires
The aim of this questionnaire is toassess the major challenges on ongoing road
constructionprojects in Addis Ababa. The research is conducted for fulfilling the
requirements for the degree of MSc in Construction Engineering and Management at
Jimma University. This questionnaire is required to be filled with exact relevant facts as
much as possible.
All information provided in this questionnaire will be treated with strict confidentiality
and allowed to serve only for the purpose of the academic research under consideration.
Interested participants of this study will be given feedback on the overall research results
after the completion of the research work.
Sincerely yours,
AynalemAbebe
PART ONE
A. General Information
Please put () and/or fill in the blanks as appropriate
1. Name of the project:________________________________________
2. Name of Organization:_____________________________________
3. Type of Organization:
Client Contractor Consultant
Other, Please specify: __________________________________
4. Current Job title in the organization/company:
Project Manager Site Engineer Project
Coordinator
Resident Engineer
Other, Please specify: ___________________________
5. Years of experience of the road construction Projects in Addis Ababa:
< 3years 3-8years > 8years
________________________________________________________________________
________________________________________________________________________
3. Does your organization propose any traffic management approaches to minimize the
problem during construction?
Yes No
4. Do you think enough planning work is done by utility services during design stage to
avoid the effect of utility conflict on urban road construction? Yes No
Why?___________________________________________________________________
________________________________________________________________________
________________________________________________________________________
__________________
5. How do you see the effect of traffic congestion in decreasing the efficiency of
machineries ordered by the contractor?
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
6. Do you think lack of coordination of utility services affect your organization? If say
yes, state your
reason__________________________________________________________________
________________________________________________________________________
7. Do you think your organization working progress within the original time schedule and
cost estimate? Yes No
If you say no
why?___________________________________________________________________
________________________________________________________________________
____________________________________________________________
8. What possible measures do you suggest in order to manage (reduce) the challenges of
ongoing road construction projects in Addis Ababa?
________________________________________________________________________
____________________________________________________________
PART TWO
Questions: From your experience in the sector, what are the Challenges that affecting
implementation in Addis Ababa road construction projects? Rank them in order of
frequency of occurrence?
Challenges Frequency/rate of occurrences
1 2 3 4 5
1 Utility conflict
2 ROW problem
3 High traffic problem
4 Performance of the stakeholder
5 Schedule constraint
6 Environmental factors
7 Poor project management
8 Variation order
9 Scarcity of financial ,material
10 Poor public awareness
11 Design/ poor planning
12 Others
Rate of occurrence
Challenges
(5)Very high
(1) Very low
(3) Medium
(4) High
(2) Low
A Utility Conflict
1 Lack of coordination of utility services
2 Design change of the utility location
3 Relocation of utility services
4 Management process system
B traffic problem
1 High traffic jam
2 Slow movement of heavy construction
equipment‟s
3 Lack of alternative roads
4 Lack of flag man/ coordination
5 Very loose coordination and integration
among stakeholders
6 Poor background in (project)
management
C Right of Way (ROW) problem
1 Slow clearance of ROW
2 Lack of public awareness
3 Delay of compensation
4 Slow and decision making & tedious
project approval process
5 Design change / Variation order
PART THREE
Determine Effects (impact) of the challenges on road construction projects.
Objective of the study: To determine theeffectsof the challenges on road construction
projects.
Please tick “” and scale each representing the following rating:
(5) Very High (4) High (3) Average (2) Minor (1) Never
Questions: From your experience,determine what are the effects of the challenges on
your road construction project? Rank them in order of frequency of occurrence?
PART FOUR
Interview Survey
Name of organization________________________________________
1. How technically your institution install the utility lines? Explain
- Both
_______________________________________________________________________
2. How did you keep the alignments to follow the street standards? Explain
- None
_______________________________________________________________________
3. How frequently communicate with utility, road, transport and land administration
Agencies to exchange information? Express in percentage
_______________________________________________________________________
None___________________________________________________________________
5. How do you communicate with other utility institutions to safe guard the existing
utility lines? Explain
- Informally
- Formally
- Both
- None
_______________________________________________________________________
Theinstitutional benefit:
__________________________________________________________
_______________________________________________________________________
Local(Urban)levelbenefit:
_____________________________________________________
_______________________________________________________________________
_______________________________________________________________________
8. Does your institute have future objectives for institutional coordination? Yes, No If
yes, state
______________________________________________________________________
9. State your opinion about the causes of utility conflict between the organizations?
Explain briefly
10. Do you think lack of coordination of utility services affect your organization? If say
yes state your reason.
_______________________________________________________________________
_____________________________________________________________________
11. Do you think there is relocation of utility problem? If say yes reason out
_______________________________________________________________________
______________________________________________________________________
12. In what reason the design change of the utility locations happens during construction
time?
_______________________________________________________________________
13. What possible measures do you suggest in order to manage (reduce) the challenges of
ongoing road construction projects in Addis Ababa? By considering the utility services
conflict?
_______________________________________________________________________
_______________________________________________________________________
APPENDIX B
Raw Data Collected by Questionnaire Survey from Respondents
Table AB1: Ranking the challenged of the selected on-going road projects
RANK
RANK
Rank
Rank
RII overa
RII
RII
Client Contractor Consultant ll RII
Challenges 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5
Utility
conflict 0 1 1 7 1 3.8 2 0 1 2 1 6 4.2 2 0 1 1 3 5 4.2 2 4.07 2
Right of
way
problem 1 0 1 0 8 4.4 1 1 0 0 0 9 4.6 1 1 0 0 0 9 4.6 1 4.53 1
High
traffic
problem 0 1 3 4 2 3.7 4 0 3 4 3 0 3 9 0 0 7 3 0 3.3 7 3.33 7
Complex
stakeholde
rs issue 0 1 3 3 3 3.8 2 0 2 6 1 1 3.1 7 0 2 7 0 1 3 10 3.3 8
Schedule 3.5
constraints 0 2 2 4 2 3.6 6 0 2 2 6 1 4 5 0 1 2 5 2 3.8 3 3.65 3
Environme
ntal
factors 1 0 6 3 0 3.1 10 1 5 2 2 0 2.5 11 2 2 4 2 0 2.6 11 2.73 11
Poor
project
manageme
nt 0 2 4 3 1 3.3 8 0 1 4 3 2 3.6 4 0 0 6 2 2 3.6 4 3.5 5
Variation
order 0 1 3 4 2 3.7 4 0 2 2 6 0 3.4 6 0 1 3 6 0 3.5 5 3.53 4
Scarcity of
financial,
material 1 1 5 2 1 3.1 10 0 0 5 3 2 3.7 3 1 0 3 5 1 3.5 5 3.43 6
Poor
public 3.4
awareness 0 1 5 4 1 5 7 1 2 2 5 0 3.1 7 0 2 3 5 0 3.3 7 3.28 9
Design/po
or 3.2
planning 0 1 3 5 1 7 9 2 0 4 2 1 3 9 1 0 6 2 1 3.2 9 3.16 10
Table AB2: Ranking the Effects of challenged of the selected on-going road projects
RANK
RANK
Rank
over A
RII
RII
RII
all N
Client contractor consultant RII K
Effects 1 2 3 4 5 1 2 3 4 5 1 2 3 4 5
Time over
run 1 0 2 1 6 4.1 1 0 0 2 1 7 4.5 1 0 0 1 1 8 4.7 1 4.43 1
budget
overrun 0 0 3 4 3 4 2 0 2 2 4 2 3.6 2 1 0 2 6 1 3.6 3 3.73 2
project
termination 0 2 3 2 3 3.6 4 4 3 1 1 1 2.2 6 1 3 4 1 1 2.8 7 2.87 6
dispute
between
parties 0 3 4 3 0 3 5 1 2 6 1 0 2.7 3 0 1 6 3 0 3.2 5 2.97 5
reduce
work
motivation 0 1 1 7 1 3.8 3 2 6 0 1 1 2.3 5 1 1 2 5 1 3.4 4 3.17 4
leadership
removal 1 3 5 1 0 2.6 7 4 4 1 1 0 1.9 7 1 1 4 4 0 3.1 6 2.53 7
creating
social
problems 0 1 4 2 3 3.7 6 3 3 2 1 1 2.4 4 0 1 2 5 2 3.8 2 3.3 3
Table AB3: Cmcround about – karalo junction asphalt concrete road construction
project physical progress according to the site engineer‟s evaluation
6. utility 1.32% 0
APPENDIX C
List of Name of Organizations
Clients
List of Contractors
1.YemaneGirmay General Contractor
2.Enyi General Contractor
List of Consultants
1. BEST Consulting Engineer‟s P.l.c
2. Classic consulting engineers plc
3. Eng. ZewdieEskinder&Co.plc
4. AACRA design department
5. Core Consulting Engineering P.L.C
6. Beza Consulting Engineers Plc
7. AACRA Design team
APPENDIX D
Critical Values of Spearman‟s Rank Correlation Coefficients
Note: when there is no exact number of subjects, use the next lowest number
APPENDIX E
JIMMA UNIVERSITY
JIMMA UNIVERSITY INSTITUTE OF TECHNOLOGY
CIVIL ENGINEERING DEPARTMENT
MSC PROGRAMME IN CONSTRUCTION ENGINEERING AND MANAGEMENT
Title…………………………………………………………………
Guide line for case study
Introduction
The construction industry everywhere faces problems and challenges. However, in the
developing countries, these difficulties and challenges are present alongside a general
situation of socio-economic stress, chronic resource shortages, institutional weaknesses
and a general inability to deal with the key issues. There is also evidence that the
problems have become greater in extent and severity in recent years [1].
Project name………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
……………………………………………………………………………………
3. Determine the effects of the challenges during the implementation period
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
4.Checking compliance with the existing construction standards on the selected road
construction projects
5
.conclusion:…………………………………………………………………………………
……………
APPENDIX F
Letters of the organizations
Figure 1: Construction works of the road Junction Km 0+000 tokm 0+030 of road (at
yereGoro)
Figure 2a: Severe delay in removal of utility lines (Electric and telephones poles) from
project Junction.
Figure 2a: Severe delay in removal of utility lines (Electric and telephones poles) from
project Junction.
Figure3: Profile data from km 1+660 to km 1+980 (Delay in approval of template design)