Sample Pipeline Project Timeline Overview

The Sample Pipeline Project outlines a detailed timeline for various activities from November 2024 to July 2025, including engineering, procurement, and construction tasks. Key phases include design submissions, internal reviews, and approvals, with specific tasks allocated to civil, mechanical, electrical, and telecom work. The project aims to ensure timely delivery and execution of pipeline infrastructure through a structured schedule of meetings, evaluations, and procurement processes.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
78 views8 pages

Sample Pipeline Project Timeline Overview

The Sample Pipeline Project outlines a detailed timeline for various activities from November 2024 to July 2025, including engineering, procurement, and construction tasks. Key phases include design submissions, internal reviews, and approvals, with specific tasks allocated to civil, mechanical, electrical, and telecom work. The project aims to ensure timely delivery and execution of pipeline infrastructure through a structured schedule of meetings, evaluations, and procurement processes.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Sample Pipeline Project Initiall Layout of PLP 10-Nov-24 23:49

# Activity ID Activity Name Original Start Finish Calendar 2024 2025


December January February
Duration W48 W49 W50 W51 W52 W1 W2 W3 W4 W5 W6 W7
1 Sample Pipeline Project 189 25-Nov-24 02-Jul-25

2 Engineering 23 25-Nov-24 21-Dec-24 My Calendar 21-Dec-24, Engineering


3 Basic Design 16 25-Nov-24 14-Dec-24 My Calendar 14-Dec-24, Basic Design
4 Civil Work 16 25-Nov-24 14-Dec-24 My Calendar 14-Dec-24, Civil Work
5 Mechanical Work 16 25-Nov-24 14-Dec-24 My Calendar 14-Dec-24, Mechanical Work
6 A1090 Meeting with contractors & Consultant 1 25-Nov-24 26-Nov-24 My Calendar Meeting with contractors & Consultant
7 A1100 Requirement Plan 3 26-Nov-24 28-Nov-24 My Calendar Requirement Plan
8 A1110 Site Survey 3 28-Nov-24 02-Dec-24 My Calendar Site Survey
9 A1120 data submission 1 02-Dec-24 03-Dec-24 My Calendar data submission
10 A1130 Design first submission 1 03-Dec-24 04-Dec-24 My Calendar Design first submission
11 A1140 Internal review 3 04-Dec-24 08-Dec-24 My Calendar Internal review
12 A1150 Design second Submission 3 08-Dec-24 10-Dec-24 My Calendar Design second Submission
13 A1160 Approved for DED 3 10-Dec-24 14-Dec-24 My Calendar Approved for DED
14 Electrical Work 16 25-Nov-24 14-Dec-24 My Calendar 14-Dec-24, Electrical Work
15 A1170 Meeting with contractors & Consultant 1 25-Nov-24 26-Nov-24 My Calendar Meeting with contractors & Consultant
16 A1180 Requirement Plan 3 26-Nov-24 28-Nov-24 My Calendar Requirement Plan
17 A1190 Site Survey 3 28-Nov-24 02-Dec-24 My Calendar Site Survey
18 A1200 data submission 1 02-Dec-24 03-Dec-24 My Calendar data submission
19 A1210 Design first submission 1 03-Dec-24 04-Dec-24 My Calendar Design first submission
20 A1220 Internal review 3 04-Dec-24 08-Dec-24 My Calendar Internal review
21 A1230 Design second Submission 3 08-Dec-24 10-Dec-24 My Calendar Design second Submission
22 A1240 Approved for DED 3 10-Dec-24 14-Dec-24 My Calendar Approved for DED
23 Telecom Work 16 25-Nov-24 14-Dec-24 My Calendar 14-Dec-24, Telecom Work
24 A1250 Meeting with contractors & Consultant 1 25-Nov-24 26-Nov-24 My Calendar Meeting with contractors & Consultant
25 A1260 Requirement Plan 3 26-Nov-24 28-Nov-24 My Calendar Requirement Plan
26 A1270 Site Survey 3 28-Nov-24 02-Dec-24 My Calendar Site Survey
27 A1280 data submission 1 02-Dec-24 03-Dec-24 My Calendar data submission
28 A1290 Design first submission 1 03-Dec-24 04-Dec-24 My Calendar Design first submission
29 A1300 Internal review 3 04-Dec-24 08-Dec-24 My Calendar Internal review
30 A1310 Design second Submission 3 08-Dec-24 10-Dec-24 My Calendar Design second Submission
31 A1320 Approved for DED 3 10-Dec-24 14-Dec-24 My Calendar Approved for DED
32 Detailed Engineering Design 6 14-Dec-24 21-Dec-24 My Calendar 21-Dec-24, Detailed Engineering Design
33 Civil Work 6 14-Dec-24 21-Dec-24 My Calendar 21-Dec-24, Civil Work
34 A1330 Design submission 1 14-Dec-24 15-Dec-24 My Calendar Design submission
35 A1340 Issue For Construction 5 15-Dec-24 21-Dec-24 My Calendar Issue For Construction
36 Mechanical Work 6 14-Dec-24 21-Dec-24 My Calendar 21-Dec-24, Mechanical Work
37 A1350 Design submission 1 14-Dec-24 15-Dec-24 My Calendar Design submission
38 A1360 Issue For Construction 5 15-Dec-24 21-Dec-24 My Calendar Issue For Construction
39 Electrical Work 6 14-Dec-24 21-Dec-24 My Calendar 21-Dec-24, Electrical Work
40 A1370 Design submission 1 14-Dec-24 15-Dec-24 My Calendar Design submission
41 A1380 Issue For Construction 5 15-Dec-24 21-Dec-24 My Calendar Issue For Construction
42 Telecom Work 6 14-Dec-24 21-Dec-24 My Calendar 21-Dec-24, Telecom Work
43 A1390 Design submission 1 14-Dec-24 15-Dec-24 My Calendar Design submission
44 A1400 Issue For Construction 5 15-Dec-24 21-Dec-24 My Calendar Issue For Construction
45 Procurement 46 21-Dec-24 12-Feb-25 My Calendar 12-Feb-25, Procure
46 Bulk Item 30 21-Dec-24 25-Jan-25 My Calendar 25-Jan-25, Bulk Item
47 P.M(Pipes/wel rods/coupling/spools 30 21-Dec-24 25-Jan-25 My Calendar 25-Jan-25, P.M(Pipes/wel rods/couplin g/spools
48 A1410 RFQ 1 21-Dec-24 22-Dec-24 My Calendar RFQ
49 A1420 Bidding for Item 3 22-Dec-24 25-Dec-24 My Calendar Bidding for Item
50 A1430 Conference with contractors 1 25-Dec-24 26-Dec-24 My Calendar Conference with contractors
51 A1440 site visit 3 26-Dec-24 29-Dec-24 My Calendar site visit

Remaining Work Milestone Page 1 of 8 TASK filter: All Activities


Critical Remaining Work summary © Oracle Corporation
Sample Pipeline Project Initiall Layout of PLP 10-Nov-24 23:49
2025
March April May June July
W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27
02-Jul-25, Sample P

12-Feb-25, Procurement

Remaining Work Milestone Page 2 of 8 TASK filter: All Activities


Critical Remaining Work summary © Oracle Corporation
Sample Pipeline Project Initiall Layout of PLP 10-Nov-24 23:49
# Activity ID Activity Name Original Start Finish Calendar 2024 2025
December January February
Duration W48 W49 W50 W51 W52 W1 W2 W3 W4 W5 W6 W7
52 A1450 Testing and evaluation 1 30-Dec-24 31-Dec-24 My Calendar Testing and evaluation
53 A1460 Approval for manufacuring 1 31-Dec-24 01-Jan-25 My Calendar Approval for manufacuring
54 A1470 Purchase order issue 1 01-Jan-25 02-Jan-25 My Calendar Purchase order issue
55 A1480 Delivery On site 19 02-Jan-25 25-Jan-25 My Calendar Delivery On site
56 Valves(gate/control valves) 30 21-Dec-24 25-Jan-25 My Calendar 25-Jan-25, Valves(gate/control valves)
57 A1490 RFQ 1 21-Dec-24 22-Dec-24 My Calendar RFQ
58 A1500 Bidding for Item 3 22-Dec-24 25-Dec-24 My Calendar Bidding for Item
59 A1510 Conference with contractors 1 25-Dec-24 26-Dec-24 My Calendar Conference with contractors
60 A1520 site visit 3 26-Dec-24 29-Dec-24 My Calendar site visit
61 A1530 Testing and evaluation 1 30-Dec-24 31-Dec-24 My Calendar Testing and evaluation
62 A1540 Approval for manufacuring 1 31-Dec-24 01-Jan-25 My Calendar Approval for manufacuring
63 A1550 Purchase order issue 1 01-Jan-25 02-Jan-25 My Calendar Purchase order issue
64 A1560 Delivery On site 19 02-Jan-25 25-Jan-25 My Calendar Delivery On site
65 Concerate(gravel/sand) 30 21-Dec-24 25-Jan-25 My Calendar 25-Jan-25, Concerate(gravel/sand)
66 A1570 RFQ 1 21-Dec-24 22-Dec-24 My Calendar RFQ
67 A1580 Bidding for Item 3 22-Dec-24 25-Dec-24 My Calendar Bidding for Item
68 A1590 Conference with contractors 1 25-Dec-24 26-Dec-24 My Calendar Conference with contractors
69 A1600 site visit 3 26-Dec-24 29-Dec-24 My Calendar site visit
70 A1610 Testing and evaluation 1 30-Dec-24 31-Dec-24 My Calendar Testing and evaluation
71 A1620 Approval for manufacuring 1 31-Dec-24 01-Jan-25 My Calendar Approval for manufacuring
72 A1630 Purchase order issue 1 01-Jan-25 02-Jan-25 My Calendar Purchase order issue
73 A1640 Delivery On site 19 02-Jan-25 25-Jan-25 My Calendar Delivery On site
74 Special Item 46 21-Dec-24 12-Feb-25 My Calendar 12-Feb-25, Special
75 High specification Valves 46 21-Dec-24 12-Feb-25 My Calendar 12-Feb-25, High sp
76 A1650 RFQ 1 21-Dec-24 22-Dec-24 My Calendar RFQ
77 A1660 Bidding for Item 3 22-Dec-24 25-Dec-24 My Calendar Bidding for Item
78 A1670 Conference with contractors 1 25-Dec-24 26-Dec-24 My Calendar Conference with contractors
79 A1680 site visit 3 26-Dec-24 29-Dec-24 My Calendar site visit
80 A1690 Testing and evaluation 1 30-Dec-24 31-Dec-24 My Calendar Testing and evaluation
81 A1700 Approval for manufacuring 1 31-Dec-24 01-Jan-25 My Calendar Approval for manufacuring
82 A1710 Purchase order issue 1 01-Jan-25 02-Jan-25 My Calendar Purchase order issue
83 A1720 Custom Clearnce 5 02-Jan-25 08-Jan-25 My Calendar Custom Clearnce
84 A1730 Delivery onsite 30 08-Jan-25 12-Feb-25 My Calendar Delivery onsite
85 Telecom and elec item 46 21-Dec-24 12-Feb-25 My Calendar 12-Feb-25, Telecom
86 A1740 RFQ 1 21-Dec-24 22-Dec-24 My Calendar RFQ
87 A1750 Bidding for Item 3 22-Dec-24 25-Dec-24 My Calendar Bidding for Item
88 A1760 Conference with contractors 1 25-Dec-24 26-Dec-24 My Calendar Conference with contractors
89 A1770 site visit 3 26-Dec-24 29-Dec-24 My Calendar site visit
90 A1780 Testing and evaluation 1 30-Dec-24 31-Dec-24 My Calendar Testing and evaluation
91 A1790 Approval for manufacuring 1 31-Dec-24 01-Jan-25 My Calendar Approval for manufacuring
92 A1800 Purchase order issue 1 01-Jan-25 02-Jan-25 My Calendar Purchase order issue
93 A1810 Custom Clearnce 5 02-Jan-25 08-Jan-25 My Calendar Custom Clearnce
94 A1820 Delivery onsite 30 08-Jan-25 12-Feb-25 My Calendar Delivery onsite
95 Testing equipment 46 21-Dec-24 12-Feb-25 My Calendar 12-Feb-25, Testin g
96 A1830 RFQ 1 21-Dec-24 22-Dec-24 My Calendar RFQ
97 A1840 Bidding for Item 3 22-Dec-24 25-Dec-24 My Calendar Bidding for Item
98 A1850 Conference with contractors 1 25-Dec-24 26-Dec-24 My Calendar Conference with contractors
99 A1860 site visit 3 26-Dec-24 29-Dec-24 My Calendar site visit
100 A1870 Testing and evaluation 1 30-Dec-24 31-Dec-24 My Calendar Testing and evaluation
101 A1880 Approval for manufacuring 1 31-Dec-24 01-Jan-25 My Calendar Approval for manufacuring
102 A1890 Purchase order issue 1 01-Jan-25 02-Jan-25 My Calendar Purchase order issue

Remaining Work Milestone Page 3 of 8 TASK filter: All Activities


Critical Remaining Work summary © Oracle Corporation
Sample Pipeline Project Initiall Layout of PLP 10-Nov-24 23:49
2025
March April May June July
W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27

12-Feb-25, Special Item


12-Feb-25, High specification Valves

Delivery onsite
12-Feb-25, Telecom and elec item

Delivery onsite
12-Feb-25, Testing equip ment

Remaining Work Milestone Page 4 of 8 TASK filter: All Activities


Critical Remaining Work summary © Oracle Corporation
Sample Pipeline Project Initiall Layout of PLP 10-Nov-24 23:49
# Activity ID Activity Name Original Start Finish Calendar 2024 2025
December January February
Duration W48 W49 W50 W51 W52 W1 W2 W3 W4 W5 W6 W7
103 A1900 Custom Clearnce 5 02-Jan-25 08-Jan-25 My Calendar Custom Clearnce
104 A1910 Delivery onsite 30 08-Jan-25 12-Feb-25 My Calendar Delivery onsite
105 Coating and insulation material 46 21-Dec-24 12-Feb-25 My Calendar 12-Feb-25, Coating
106 A1920 RFQ 1 21-Dec-24 22-Dec-24 My Calendar RFQ
107 A1930 Bidding for Item 3 22-Dec-24 25-Dec-24 My Calendar Bidding for Item
108 A1940 Conference with contractors 1 25-Dec-24 26-Dec-24 My Calendar Conference with contractors
109 A1950 site visit 3 26-Dec-24 29-Dec-24 My Calendar site visit
110 A1960 Testing and evaluation 1 30-Dec-24 31-Dec-24 My Calendar Testing and evaluation
111 A1970 Approval for manufacuring 1 31-Dec-24 01-Jan-25 My Calendar Approval for manufacuring
112 A1980 Purchase order issue 1 01-Jan-25 02-Jan-25 My Calendar Purchase order issue
113 A1990 Custom Clearnce 5 02-Jan-25 08-Jan-25 My Calendar Custom Clearnce
114 A2000 Delivery onsite 30 08-Jan-25 12-Feb-25 My Calendar Delivery onsite
115 Instrumentation and control 46 21-Dec-24 12-Feb-25 My Calendar 12-Feb-25, Instrume
116 A2010 RFQ 1 21-Dec-24 22-Dec-24 My Calendar RFQ
117 A2020 Bidding for Item 3 22-Dec-24 25-Dec-24 My Calendar Bidding for Item
118 A2030 Conference with contractors 1 25-Dec-24 26-Dec-24 My Calendar Conference with contractors
119 A2040 site visit 3 26-Dec-24 29-Dec-24 My Calendar site visit
120 A2050 Testing and evaluation 1 30-Dec-24 31-Dec-24 My Calendar Testing and evaluation
121 A2060 Approval for manufacuring 1 31-Dec-24 01-Jan-25 My Calendar Approval for manufacuring
122 A2070 Purchase order issue 1 01-Jan-25 02-Jan-25 My Calendar Purchase order issue
123 A2080 Custom Clearnce 5 02-Jan-25 08-Jan-25 My Calendar Custom Clearnce
124 A2090 Delivery onsite 30 08-Jan-25 12-Feb-25 My Calendar Delivery onsite
125 Construction 120 12-Feb-25 02-Jul-25 My Calendar
126 Civil Work 80 12-Feb-25 17-May-25 My Calendar
127 Trench Work 70 12-Feb-25 05-May-25 My Calendar
128 A2100 Trench Excavation 50 12-Feb-25 12-Apr-25 My Calendar
129 A2110 Trench Beddin g 40 24-Feb-25 12-Apr-25 My Calendar
130 A2120 Pre-Post Padding 20 12-Apr-25 05-May-25 My Calendar
131 Pipeline Work 20 12-Apr-25 05-May-25 My Calendar
132 A2130 Pipeline Lowering 10 12-Apr-25 23-Apr-25 My Calendar
133 A2140 Tie-in and Crossing 10 23-Apr-25 05-May-25 My Calendar
134 Telecom Repeared Tower 80 12-Feb-25 17-May-25 My Calendar
135 A2150 Earth work 50 12-Feb-25 12-Apr-25 My Calendar
136 A2160 Telecom Repeated Foundation 20 12-Apr-25 05-May-25 My Calendar
137 A2170 Solar Pannel Foundation 10 05-May-25 17-May-25 My Calendar
138 Mechanical Work 60 12-Apr-25 21-Jun-25 My Calendar
139 Pipe Welding 40 12-Apr-25 28-May-25 My Calendar
140 A2180 Pipe Welding 15 12-Apr-25 29-Apr-25 My Calendar
141 A2190 Welding of Spools 20 29-Apr-25 22-May-25 My Calendar
142 A2200 NDT Testing 5 22-May-25 28-May-25 My Calendar
143 Pipeline Testing 19 28-May-25 19-Jun-25 My Calendar
144 A2210 Hydrotest 4 28-May-25 02-Jun-25 My Calendar
145 A2220 Cleaning and guaging 5 02-Jun-25 08-Jun-25 My Calendar
146 A2230 Filling pressure test 5 08-Jun-25 14-Jun-25 My Calendar
147 A2240 Drying 5 14-Jun-25 19-Jun-25 My Calendar
148 BVS Interconnection 50 23-Apr-25 21-Jun-25 My Calendar
149 A2250 Interconnection of Pipes/Valves/spools 50 23-Apr-25 21-Jun-25 My Calendar
150 Electrical Work 65 12-Apr-25 26-Jun-25 My Calendar
151 A2260 Cable Pulling(earthening+grounding) 30 12-Apr-25 17-May-25 My Calendar
152 A2270 Installation of Solar Pannel 20 17-May-25 09-Jun-25 My Calendar
153 A2280 Installation of Battery 10 09-Jun-25 21-Jun-25 My Calendar

Remaining Work Milestone Page 5 of 8 TASK filter: All Activities


Critical Remaining Work summary © Oracle Corporation
Sample Pipeline Project Initiall Layout of PLP 10-Nov-24 23:49
2025
March April May June July
W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27

Delivery onsite
12-Feb-25, Coating and insulation material

Delivery onsite
12-Feb-25, Instrumentation and control

Delivery onsite
02-Jul-25, Construct
17-May-25, Civil Work
05-May-25, Trench Work
Trench Excavation
Trench Beddin g
Pre-Post Padding
05-May-25, Pipeline Work
Pipeline Lowering
Tie-in and Crossing
17-May-25, Telecom Repeared Tower
Earth work
Telecom Repeated Foundation
Solar Pannel Foundation
21-Jun-25, Mechanical Work
28-May-25, Pipe Welding
Pipe Welding
Welding of Spools
NDT Testing
19-Jun-25, Pipeline Testing
Hydrotest
Cleaning and guaging
Filling pressure test
Drying
21-Jun-25, BVS Interconnection
Interconnection of Pipes/Valves/spools
26-Jun-25, Electrical Work
Cable Pulling(earthening+grounding)
Installation of Solar Pannel
Installation of Battery

Remaining Work Milestone Page 6 of 8 TASK filter: All Activities


Critical Remaining Work summary © Oracle Corporation
Sample Pipeline Project Initiall Layout of PLP 10-Nov-24 23:49
# Activity ID Activity Name Original Start Finish Calendar 2024 2025
December January February
Duration W48 W49 W50 W51 W52 W1 W2 W3 W4 W5 W6 W7
154 A2290 Cable Pulling(Power+Control) 5 21-Jun-25 26-Jun-25 My Calendar
155 Telecom Work 70 12-Apr-25 02-Jul-25 My Calendar
156 A2300 Installation of Telecom repeated Tower 20 12-Apr-25 05-May-25 My Calendar
157 A2310 Installation of Radio System Cabinet 10 05-May-25 17-May-25 My Calendar
158 A2320 FOC Cable Lying 10 17-May-25 28-May-25 My Calendar
159 A2330 Installation of telecom Manhole 5 28-May-25 03-Jun-25 My Calendar
160 A2340 Other Basic Setting 25 03-Jun-25 02-Jul-25 My Calendar
161 Finishing and Handover 0 02-Jul-25 02-Jul-25 5x10
162 A2350 Finish Milestones 0 02-Jul-25 5x10

Remaining Work Milestone Page 7 of 8 TASK filter: All Activities


Critical Remaining Work summary © Oracle Corporation
Sample Pipeline Project Initiall Layout of PLP 10-Nov-24 23:49
2025
March April May June July
W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27
Cable Pulling(Power+Control)
02-Jul-25, Telecom W
Installation of Telecom repeated Tower
Installation of Radio System Cabinet
FOC Cable Lying
Installation of telecom Manhole
Other Basic Setting
02-Jul-25, Finishing
Finish Milestones,

Remaining Work Milestone Page 8 of 8 TASK filter: All Activities


Critical Remaining Work summary © Oracle Corporation

You might also like