0% found this document useful (0 votes)
87 views2 pages

PERT CPM 2 Storey Residential Building

The document outlines a detailed project supervision plan for construction activities, including procurement of materials and consumables. It specifies various activities, their respective manpower, equipment, productivity rates, and durations. Key activities include mobilization, earthworks, structural works, and installations related to plumbing and electrical systems.

Uploaded by

Pro Basher
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
87 views2 pages

PERT CPM 2 Storey Residential Building

The document outlines a detailed project supervision plan for construction activities, including procurement of materials and consumables. It specifies various activities, their respective manpower, equipment, productivity rates, and durations. Key activities include mobilization, earthworks, structural works, and installations related to plumbing and electrical systems.

Uploaded by

Pro Basher
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69

MATERIALS, CONSUMABLES PROCUREMENT & PURCHASE

0 64
64 0 64
F 0 0
W 24 40
16 33 49
F 9 9
23 24

M 30 45 X 45 60
V 21 24 15 34 49 15 49 64
3 26 29 F 4 4 F 4 4
F 5 5
14 25
E 29 30
1 29 30 Y 56 60
F 0 0 4 60 64
F 4 4
H 36 37 I 37 40 K 40 41
F 30 36 1 36 37 3 37 40 1 40 41 O 52 56 R 56 64 Z 64 67
6 30 36 F 0 0 F 0 0 F 0 0 4 52 56 8 56 64 3 64 67
F 0 0 F 0 0 F 0 0 F 0 0
1 2 3 4 5 6 7 9 10 12 13 16 19 26
A 0 3 B 3 21 C 21 25 D 25 29
3 0 3 18 3 21 4 21 25 4 25 29 L 41 52
F 0 0 F 0 0 F 0 0 F 0 0 11 41 52
F 0 0

G 30 35
5 32 37
F 2 2 8 11
S 21 28 J 35 38 P 47 52 Q 52 58
7 25 32 3 37 40 N 30 47 5 53 58 6 58 64
F 4 4 F 2 2 17 36 53 F 6 6 F 6 6
F 6 6
15 18

T 28 44 U 44 51
16 41 57 7 57 64
F 13 13 F 13 13
20 21 22

AA 0 67
67 0 67
F 0 0

PROJECT SUPERVISION
Nodes Activity Code Activities ES LS EF LF FLOAT No. of Manpower No. of Equipment Productivity Rate Quantity Duration,days
1 2 A Mobilization 0 0 3 3 0 3
2 3 B Earthworks 3 3 21 21 0
Excavation 4-Laborer 1 cu.m./m-d 37.46 cu.m. 10
Backfill 4-Laborer 1.5 cu.m./m-d 32.11 cu.m. 6
Gravel Bedding & Compaction 2-Laborer 1-Tamping Rammer 1.0 cu.m./m-d 3.81 cu.m. 2
Structural Works
3 4 C Substructure Rebars 21 21 25 25 0 3-Steelfixer
100 kgs/m-d 2028.76 kgs. 4
3-Laborer
4 5 D Substructure Formworks 25 25 29 29 0 4-Carpenter
3 sq.m./m-d 47.52 sq.m. 4
4-Laborer
5 6 E Substructure Concrete Casting 29 29 30 30 0 2-Mason 1-One Bagger Mixer
0.65 cu.m./m-d 14.81 cu.m. 1
6-Laborer
6 7 F Superstructure Formworks - Grnd Flr 36 30 36 36 0 4-Carpenter
3 sq.m./m-d 126.42 sq.m. 6
4-Laborer
6 8 G Superstructure Rebar - Grnd Flr 30 32 35 37 2 3-Steelfixer
100 kgs/m-d 2743.46 kgs. 5
3-Laborer
7 9 H Superstructure Concrete Casting -Grnd Flr 36 36 30 30 0 2-Mason 1-One Bagger Mixer
0.65 cu.m./m-d 14.31 cu.m. 1
6-Laborer
9 10 I Superstructure Formworks -2nd Flr 37 37 40 40 0 4-Carpenter
3 sq.m./m-d 62.54 cu.m. 3
4-Laborer
8 11 J Superstructure Rebar -2nd Flr 35 37 38 40 2 3-Steelfixer
100 kgs/m-d 1638.27 kgs. 3
3-Laborer
10 12 K Superstructure Concrete Casting 40 40 41 41 0 2-Mason 1-One Bagger Mixer
0.65 cu.m./m-d 6.23 cu.m. 1
6-Laborer
12 13 L Steel Works 41 41 52 52 0 2-Welder 1-Welding Machine
40 kgs./m-d 848.80 kgs. 11
2-Laborer 1- Cut-Off Machine
6 14 M CHB Laying 30 34 45 49 4 2-Mason
6 sq./m-d 168.72 sq.m. 15
2-Laborer
6 15 N Plastering 30 36 47 53 6 2-Mason
8 sq./m-d 337.44 sq.m. 22
2-Laborer
13 16 O Tinsmithry 52 52 56 56 0 2-Installer
15 ln.m./m-d 106.34 ln.m. 4
2-Laborer
15 18 P Fenestration 47 53 52 58 6 2-Carpenter
1 lot 6
2-Installer
18 19 Q Tileworks 52 58 58 64 6 2-Tile Installer
8 sq.m./m-d 88.11 sq.m. 6
2-Laborer
16 19 R Painting 56 56 64 64 0 4-Painter
18 sq.m./m-d 518.55 sq.m. 8
4-Laborer
3 20 S Plumbing Utilities includes septic tank 21 25 28 32 4 2-Carpenter
and roughing-ins 1- Plumber 1 lot 7
2- Helpers
20 21 T Installation of Sanitary Pipes 28 41 44 57 13 2-Plumbers
1 lot 16
and clean water lines
21 22 U Installation of Plumbing 44 57 51 64 13 2-Plumbers
1 lot 7
fixtures and accessories
3 23 V Installation of Electrical roughing-ins 21 26 24 29 5 1-Electrician
1 lot 3
1-Laborer
23 24 W Installation of Electrical Conduit 24 33 40 49 9 1-Electrician
1 lot 3
1-Laborer
14 25 X Installation of Electrical Wires and Fixtures 45 49 60 64 4 1-Electrician
1 lot 9
1-Laborer
16 25 Y Installation of Ceiling Frame & Board 56 60 60 64 4 2-Installers
20 sq.m./m-d 120.96 sq.m. 4
3-Laborers
25 26 Z Turn-Over 64 64 67 67 0
3