0% found this document useful (0 votes)
83 views114 pages

Construction Work Breakdown Summary

The document outlines detailed construction work including excavation, concrete work, masonry, and various other tasks with specific measurements and volumes. It includes sections on materials needed, areas covered, and total quantities for different construction elements. The document serves as a comprehensive guide for the construction project, detailing each phase and its requirements.

Uploaded by

mercyjohnhad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
83 views114 pages

Construction Work Breakdown Summary

The document outlines detailed construction work including excavation, concrete work, masonry, and various other tasks with specific measurements and volumes. It includes sections on materials needed, areas covered, and total quantities for different construction elements. The document serves as a comprehensive guide for the construction project, detailing each phase and its requirements.

Uploaded by

mercyjohnhad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Loundary Room

Cart awaye
1) Excavation & Earth Work
13.17 1.1) Site Clearing
1.1) Site Clearing
9.90 16.53 1.2) Bulk Excavation
6.65
34.81 1.3) Trench Excavation
65.84 Total area

1.2) Bulk Excavation 64.51 Total Volume

7.90
1 1 4.65 25cm Hard Core
0.45
3.55
16.53 Total Volume 1 2 2.03

1.3) Trench Excavation 105 cm 14.41

7.90 3.75
1 3 1.00 Axis A-C on 1,2'&2 1 2 2.03
1.05
15.23
24.89

3.15 29.64 Total area


1 3 1.00 Axis 1-2 on A,B &C
1.05

9.92

34.81 Total Volume

1.4) Back Fill

16.53 Bulk

34.81 Trench

51.34 Total

0.83 Concrte C-5 Under masonery

34.81 Masonery Wall

7.41 hard core

43.05 Total

8.29 Total Volume of Back Fill


2) Concrete Work b) 10cm Ground Slab

2.1) Lean Concrete 3.55


1 2 2.03
a) Under Masonery
14.41
7.90
1 3 0.50 Axis A-C on 1,2'& 2 3.75
1 2 2.03
11.85
15.23
3.15
1 3 0.50 Axis 1-2 on A,B&C
29.64 Total area
4.73

b) 10cm Ground Slab


16.58 Total area
3.55
1 2 2.03
2.2) Concrete -25
14.41
a) Gread Beam
3.75
7.70 Axis A-C on 1&2 1 2 2.03
1 2 0.35
0.20 15.23

1.08
29.64 Total area
7.70 Axis A-C on 2'
1 1 0.45
0.20 1.3) Form Work

0.69 a) Gread Beam

4.45 Axis 2-1 on A&C 7.70 Axis A-C on 1&2


1 2 0.35 2 2 0.35
0.20
10.78
0.62
7.70 Axis A-C on 2'
7.70 Axis 2-1 on B 1 2 0.45
1 2 0.35
0.20 6.93

1.08 4.45 Axis 2-1 on A&C


2 2 0.35

6.23
3.47 Total Volume
7.70 Axis 2-1 on B
2 2 0.35

10.78

34.72 Total area


1.3)Re- bar

87.50 a)8

b)10

58.96 c)12

d)14

53.09 e)16

f)20

3) Masonery Work

3.1) Under Masonery


7.90
1 3 1.00 Axis A-C on 1,2'&2
1.05

24.89

3.15
1 3 1.00 Axis 1-2 on A,B &C
1.05

9.92

34.81 Total Volume

3.2) 10mm Expanision Joint

1 1 41.38

41.38 Total ml
B) SUPER STRUCTURE b)Top Tie Beam

1) Concrete Work 7.70 Axis A-C on 1&2


2 2 0.30
a) Elevation Column
0.30 9.24
1 6 0.30
2.65 C1 7.70
2 1 0.20
1.43
3.08
0.30
1 6 0.30 4.50 Axis 2-1 on A,B &C
2.65 C2 3 2 0.3

1.43 8.1

4.50 Axis 2-1 on A,B &C


2.86 3 1 0.2

2.7
b)Top Tie Beam
7.00
1 2 0.30 Axis A-C on 1&2 23.12 Total area
0.20

0.84

5.20
1 3 0.30 Axis 2-1 on A,B &C
0.20

0.94

1.78 Total Volume

Form Work

a) Elevation Column
0.30
4 4 2.65 c1 1.3)Re- bar

12.72 77.26 a)8

0.30 b)10
2 4 2.65 c2
111.89 c)12
6.36
d)14

19.08 Total area 207.30 e)16

141.66 f)20
2)Block work 2.2) 10cm HCB

2.1) 20cm Block 4.6


0.5 2 2.65
3.55
1 2 2.65 12.19

18.82
1.62
1.55 1 1 2.65
1 2 2.65
4.29
8.22

1.63
1 1 2.65 16.48 Total area

4.32

0.85 3) Roofing Work


1 2 2.65
3.1) G -30
4.51 8.80
1 6.20
4.51
1 1 2.65 54.56 Total area

11.95

4.44
1 1 2.65

11.77

59.59 Total area

Ddt
1.00
1 1 0.6 W1

0.60

1.70
1 1 1.65 W2

2.81

3.15
1 1 1.95 W3

6.14

0.70
1 1 2.1 D1

1.47

11.02 Ddt area

48.57 Total Net area


4) Carpentery Work 7.1) Three Internal plastering

4.1)Dia 12 Upper & Lower 3.55


1 2 2.65
1 7 11.26
18.82
78.82 ml

0.85
4.2)Dia 10 Vertical & Diagonal 1 2 2.65

1 7 5.25 4.51

36.75 ml 4.51
1 1 2.65
4.3)7x5 Purlin
11.95
1 6 8.70
0.7
52.20 ml 1 1 2.65

1.86
4.4) Chip wood 1.62
5.83 1 2 0.65
1 4.35
2.11
25.36
1.05
1.62 1 2 0.65
1 1.05
1.37
1.70
3.77
1.62 1 1 0.65
1 3.17
2.45
5.14
1.62
1 2 2.65

32.20 Total area 8.59

5) Metal Work 3.17


1 2 2.65
5.1) LTZ Door 0.8mm Ribbed Sheet
16.80
1 a) D1 Size :- 70x210 cm

68.46

5.2) 28x28 Window

1 a) W1 Size :- 100 x 60 cm

1 b) W2 Size :- 170 x 65 cm

1 c) W3 Size :-3.15 x 162 cm


Ddt External Wall
1.00
1 1 0.6 W1 3.55
1 2 2.65
0.60
18.82
1.70
1 1 1.65 W2
0.85
2.81 1 2 2.65
3.15
1 1 1.95 W3 4.51

6.14 1.70
1 2 2.65
0.70
1 1 2.1 D1 9.01

1.47 4.25
1 1 2.65

11.02 Ddt area 11.26

57.44 Total Net area


43.60
Summary
Ddt
57.44 Internal wall 1.00
1 1 0.6 W1
19.08 Column
0.60
23.12 Top Tie beam
1.70
99.64 Total area Plastering 1 1 1.65 W2

2.81
3.15
1 1 1.95 W3
7.2) Two Internal plastering
Under Cramic Wall 6.14

1.62 0.70
1 2 2.00 1 1 2.1 D1

6.48 1.47

1.05
1 2 2.00 11.02 Ddt area

4.20
32.58 Total Net area
3.77
1 1 2.00

7.54

18.22 Total area of plastering


7.3) 50cm Cement Screed 5.7)10 cm Cramic Skirting

5.83 1 1 29.94
1 1 4.35
29.94 Total ml
25.36

1.62 7.8) Pavment


1 1 3.17 7.90
1 2 1.20
5.14
18.96

30.50 Total area 4.65


1 2 1.20

7.4) PVC celling 11.16

5.83
1 1 4.35 30.12 Total area

25.36

1.62 7.9) Curb Stone


1 1 1.05
1 1 25.20
1.70
25.20 Ml
1.62
1 1 3.17

5.14
7.10) Marble Window

32.20 Total area 1 1 1.00 W1

1.00
7.5)Cramic Floor Tile
1.62 1 1 1.70 W2
1 1 1.05
1.70
1.70 Total area
1 1 3.15 W3

7.6)Cramic Wall 3.15


1.62
1 2 2.00

6.48 5.85 Total Ml

1.05
1 2 2.00

4.20

3.77
1 1 2.00
7.54

18.22 Total area of Wall


8) Glazzing Work

8.1) 4mm cleer Glass

1.00
1 1 0.94 W1

0.94

1.70
1 1 1.65 W2

2.81

3.15
1 1 1.95 W3

6.14

0.70
1 1 0.4 D1

0.28

10.17 Total area


CONTRACTOR Page 1
OWNER
BLOCK Gread Beam & Ground Slab BAR SCHEDULE

Ref. Diam Length No of No of Total No Length


Bar shape No Location
(mm) (m) Bars Member of bar φ6 φ8 φ10 φ12 φ14 φ16 φ20 φ24 φ26 φ28
Axis A-C on 1&2 Top 12 8.55 2 2 34.20 0 - 0 34.20 0 0.00 0 0 0 0
Bottom 12 8.05 2 2 32.20 0 - 0 32.20 0 0.00 0 0 0 0
Strip 8 1.00 40 2 80.00 0 80.00 0 0.00 0 0.00 0 0 0 0
0.00 0 - 0.00 0.00 0 0.00 0 0 0 0
Axis A -C on 2 Top 16 8.75 2 1 17.50 0 - 0.00 0.00 0 17.50 0 0 0 0
Bottom 16 8.05 2 1 16.10 0 - 0.00 0.00 0 16.10 0 0 0 0
Strip 8 1.40 52 1 72.80 0 72.80 0.00 0.00 0 0.00 0 0 0 0
0.00
Axis 2-1 on A& C Top 16 5.30 3 2 31.80
Bottom 16 4.80 3 2 28.80
Strip 8 1.00 23 2 46.00 46.00
0.00
Axis 2-1 on B Top 16 5.30 5 1 26.50
Bottom 16 4.80 5 1 24.00
Strip 8 1.00 23 1 23.00
0.00
0.00
Ground Slab 8 3.55 2 1 7.10 7.10
8 2.03 2 1 4.06 4.06
8 3.75 2 1 7.50 7.50
8 2.03 2 1 4.06 4.06
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Total length 221.52 0.00 66.40 0.00 33.60 0.00 0.00
Weight kg/m 0.222 0.395 0.617 0.888 1.21 1.58 2.468 3.552
SAR BET SITE Page 15
Total weight kg 87.50 0.00 58.96 0.00 53.09 0.00 0.00

SAR BET SITE Page 16


φ30 φ32 Remark
0 0
0 0
0 0
0 0
0 0
0 0
0 0

SAR BET SITE Page 17


SAR BET SITE Page 18
CONTRACTOR Page 2
OWNER
BLOCK Elevation Column & Top Tie Beam BAR SCHEDULE

Ref. Diam Length No of No of Total No Length


Bar shape No Location
(mm) (m) Bars Member of bar φ6 φ8 φ10 φ12 φ14 φ16 φ20 φ24 Remark
C1 16 4.10 8 4 131.20 0 - 0 0 0 131.20 0 0
8 0.70 14 4 39.20 0 39.20 0 0 0 0.00 0 0
0.00 0 - 0 0 0 0.00 0 0
C2 20 4.10 7 2 57.40 0 - 0 0 0 0.00 57.4 0
8 0.70 14 2 19.60 0 19.60 0 0 0 0.00 0
0.00 0 - 0 0 0 0.00 0
T.B Axis A-C on 1&2 Top 12 8.45 2 2 33.80 0 - 0 33.8 0 0.00 0
Bottom 12 8.05 2 2 32.20 0 - 0 32.2 0 0.00 0
Strip 8 0.90 40 2 72.00 0 72.00 0 0 0 0.00 0
0.00 0 - 0 0 0 0.00 0
T.B Axis A-C on A,B&C Top 12 5.20 2 3 31.20 0 - 0 31.2 0 0.00 0
Bottom 12 4.80 2 3 28.80 0 - 0 28.8 0 0.00 0
Strip 8 0.90 24 3 64.80 0 64.80 0 0 0 0.00 0
0.00 0 - 0 0 0 0.00 0
0.00 0 - 0 0 0 0.00 0
0.00 0 - 0 0 0 0.00 0
0.00 0 - 0 0 0 0.00 0
0.00 0 - 0 0 0 0.00 0
0.00 0 - 0 0 0 0.00
0.00 0 - 0 0 0 0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00 0 - 0 0 0 0.00 0 0
0.00 0 - 0 0 0 0.00 0 0
0.00 0 - 0 0 0 0.00 0 0
0.00 0 - 0 0 0 0.00 0
0.00 0 - 0 0 0 0.00 0
0.00 0 - 0 0 0 0.00 0
0 - 0 0 0 0.00 0
Total length 195.60 0.00 126.00 0.00 131.20 57.40 0.00
Weight kg/m 0.222 0.395 0.617 0.888 1.21 1.58 2.468 3.552
Total weight kg 77.26 0.00 111.89 0.00 207.30 141.66 0.00

SAR BET SITE Page 19


Slauter House

SUMMARY

[Link]-STRUCTURE

1.0 EXCAVATION & EARTH WORK ETH .BIRR -

2.0 CONCRETE WORK ETH .BIRR -

3.0 MASONARY WORK ETH .BIRR -

SUB-TOTAL A -

[Link] STRUCTURE

1.0 CONCRETE WORK ETH .BIRR -

2.0 BLOCK WORK ETH .BIRR -

3.0 ROOFING & WATER PROOFING ETH .BIRR -

4.0 CARPENTARY & JOINERY ETH .BIRR -

5.0 METAL WORK ETH .BIRR -

6.0 FINISHING WORK ETH .BIRR -

7.0 PAINTING WORK ETH .BIRR -

8.0 SANITARY INSTALLATION ETH .BIRR -

9.0 ELECTRICALL INSTALLATION ETH .BIRR -

SUB-TOTAL B -

TOTAL A+B -

Slauter House Page 60


Slauter House Page 61
Project:--
Block : - Site Work
Work Item :-Slauter House
Client:- MoND
Consultant: -DCDE
Location:-

NO DESCRIPTION UNIT QTY RATE AMOUNT

A. SUB-STRUCTURE

1. EXCAVATION & EARTH WORK

1.1 Clear area from top organic soil and


vegetation to an average depth of 20 cm.
M2 62.08 -
-
1.2 Bulk excavation in ordinary soil from the
natural ground level to a depth not exceeding
45cm. M3 15.52 -
-
1.3 Trench excavation in ordinary soil from
reduced level to a depth of not exceeding
105cm . M3 27.27 -
1.4 Ditto Item 1.3 in soft rock M3 10.91 -
-
1.5 Ditto Item 1.3 in hard rock M3 10.91 -
-
1.6 Back fill around foundation column, masonry,
footing & under Hard Core with selected
material brought from out side and well ram
in layers not exceeding 20cm .
M3 23.80 -
-
1.7
Cart away all surplus excavated materials and
deposited to a distance not exceeding 5 km
from site.
M3 55.21 -
-
1.8 250mm thick basaltic stone hardcore well
rolled, consolidated and blinded with crushed
stone . M2 29.00 -

Total Carried To Summary Eth Birr -

Slauter House Page 62


Project:--
Block : - Site Work
Work Item :-Slauter House
Client:- MoND
Consultant: -DCDE
Location:-

NO DESCRIPTION UNIT QTY RATE AMOUNT


2. CONCRETE WORKS

2.1 Provide and form 5 cm thick lean concrete


class C-5, with a minimum cement content of
150 kg cement/M3 :-

a) Under Masonry wall M2 13.63 -


-
2.2 Provide and form Reinforced concrete C-25,
with minimum cement content of 360kg
cement/M3 filled into form work and vibrated
around reinforcement bar. Steel and
formwork measured separately:-
-
a) In Grade beam M3 2.04 -
-
b) In 10 cm thick Ground Slab M2 30.45 -
-
2.3 Provide, cut and fix in position sawn zigba
wood form work to :-
-
a)To Grade beam M 2
22.79 -
-
2.4 Steel reinforcement according to structural
drawing price includes cutting, bending,
placing in position bar spacer and tying wires.

-
-
a)Ø 8mm deformed bar kg 118.58 -
-
b) Ø 10mm deformed bar kg 0.00 -
-
c) Ø 12mm deformed bar kg 50.72 -
-
d) Ø 14mm deformed bar kg 88.43 -
-
e) Ø 16mm deformed bar kg 0.00 -

Total Carried To Summary Eth Birr -

Slauter House Page 63


Project:--
Block : - Site Work
Work Item :-Slauter House
Client:- MoND
Consultant: -DCDE
Location:-

NO DESCRIPTION UNIT QTY RATE AMOUNT

Slauter House Page 64


Project:--
Block : - Site Work
Work Item :-Slauter House
Client:- MoND
Consultant: -DCDE
Location:-

NO DESCRIPTION UNIT QTY RATE AMOUNT

3. MASONRY WORKS

3.1 500mm thick hard Trachitic roughly dressed


stone masonry foundation wall below ground
level bedded in cement mortar mix ratio (1:3).

M3 20.45 -

3.2 10mm Styrofoam expansion joint between


floor slab & grade beam . Ml 33.18 -

Total Carried To Summary Eth Birr -

Sub Total (A) carried to summary Birr -

B. SUPER STRUCTURE

1. CONCRETE WORKS

1.1 Reinforced concrete in C-25, with minimum


cement content of 360kg cement/M 3 filled into
form work and vibrated around
reinforcement bar. Steel and formwork
measured separately:-

a )In Elevation column M3 0.67 -


-
b)In Top tie Beams M3 1.75 -
-
1.2 Provide, cut and fix in position sawn zigba
wood form work to :- -
-
a )To Elevation column M2 13.36 -
-
b)To Top tie Beams M2 26.04 -
-

Slauter House Page 65


Project:--
Block : - Site Work
Work Item :-Slauter House
Client:- MoND
Consultant: -DCDE
Location:-

NO DESCRIPTION UNIT QTY RATE AMOUNT


1.3 Steel reinforcement according to structural
drawing price includes cutting, bending,
placing in position bar spacer and tying wires.

-
-
a)Ø 8mm deformed bar kg 94.19 -
-
b) Ø 10mm deformed bar kg 0.00 -
-
c) Ø 12mm deformed bar kg 81.40 -
-
d) Ø 14mm deformed bar kg 0.00 -
-
e) Ø 16mm deformed bar kg 199.08 -
-

Total Carried To Summary Eth Birr -

2. BLOCK WORK

2.1 20 cm thick class B hollow concrete block


wall beded in cement mortar (1:3) . Both sides
left for plastering. M2 2.82 -

2.2 10cm thick Class C Hollow Concrte Block wall


beded in cement mortar (1:3) . Both sides left
for plastering.
M2 0.57 -

Total Carried To Summary Eth Birr -

3. ROOFING & WATER PROOFING

3.1 Supply and fix G-30 CIS roof cover. Unit


price shall include all the necessary
accessories,(Roofing is measured in horizontal
projection).
M2 46.87 -

Total Carried To Summary Eth Birr -

Slauter House Page 66


Project:--
Block : - Site Work
Work Item :-Slauter House
Client:- MoND
Consultant: -DCDE
Location:-

NO DESCRIPTION UNIT QTY RATE AMOUNT

Slauter House Page 67


Project:--
Block : - Site Work
Work Item :-Slauter House
Client:- MoND
Consultant: -DCDE
Location:-

NO DESCRIPTION UNIT QTY RATE AMOUNT


4. CARPENTARY & JOINERY

4.1 Supply and erect Wooden roof structure all


according to size and shape specified on the
detail drawing .

a) Truss Ø12 Eqlptus tree upper & lower


Member. Ml 74.92 -
-
b) Truss Ø10 Eqlptus tree vertical & diagonal
Member. Ml 58.91 -
-
c) Zigba wood Purlin (5X7cm). Ml 45.36 -

Total Carried To Summary Eth Birr -

Slauter House Page 68


Project:--
Block : - Site Work
Work Item :-Slauter House
Client:- MoND
Consultant: -DCDE
Location:-

NO DESCRIPTION UNIT QTY RATE AMOUNT


[Link] WORK

5.1 Supply and fix steel door size:- Main frame


made of 40*40*3mm RHS, work includes
ornamental metals, 20x30x2 RHS
vertical ,Bracings & necessary accessories .
Unit Price includes approved types of hinges,
locks, latches, handle stoppers& antirust
painting . as shown on Architectural
drawings. Shop drawing Should be provided
for Approval .

SD 1 Size :- 190 x 208cm No 1.00 -


5.2 Supply and fix 38x38mm black iron LTZ
section steel profile frame metal window with
0.8mm thick wire mesh . Unit price includes
one coat of anti-rust & two coats of oil paint all
according to detail drawing. Window sample
and workshop drawing has to be approved by
the consultant or Architect before mass
production. Windows shall be in accordance
with the technical specification , Architect
Engineer's preference and approval.

a)SW1 Size :- 140 x 70cm No 4 -

5.3 Supply and fix Steel Grail Size :-150x40cm.


Main RHS frame 40x40x3mm RHS for oppen
ditch cover c/c 5cm welded horizontally, Dia 8
weld internal bracing . Price shall include
anti-rust, electrode and all other necessary
civil works. According to AR Detail Drawing .

No 2.00 -

Total Carried To Summary Eth Birr -

Slauter House Page 69


Project:--
Block : - Site Work
Work Item :-Slauter House
Client:- MoND
Consultant: -DCDE
Location:-

NO DESCRIPTION UNIT QTY RATE AMOUNT


6. FINISHING WORK

6.1 Apply three coats of plaster in cement sand


mortar ratio of (1:3) to iternal HCB wall .
Price includes exposed concrete beams&
columns with edge works and which quality
approved with engineer.
M2 114.91 -
-
6.2 Apply two coats of plaster in cement sand
mortar ratio of (1:3) to external HCB wall .
Price includes edge works and the quality is
approved by the engineer.
M2 79.98 -
-
6.3
50 mm thick cement sand screed smoothly
finished flooring in mortar mix (1:3).
M2 31.71 -
-
6.4 Supply and fix in place 10 cm high non-slipery
ceramic tile skirting to wall bended in cement
sand mortar (mix 1:3)
Ml 33.18 -
-
6.5 280x30mm approved type white marble
window sill cut to appropriate size, weathered
and mounted on & including 20mm thick
cement mortar (1:3) bedding. Price includes
bull nosing and making water drip as shown
on the detail drawing
Ml 6.05 -
-

Slauter House Page 70


Project:--
Block : - Site Work
Work Item :-Slauter House
Client:- MoND
Consultant: -DCDE
Location:-

NO DESCRIPTION UNIT QTY RATE AMOUNT


6.6 120 x100 x 8cm cast on site C-20 mass
concrete pavement around the building Unit
price shall included 150mm thick red ash and
300mm compacted fill selected material or
equivalent bedding materia .( the concrete
cast on site)
M2 29.74 -
-
6.7 200x400mm Cast Insitu non reinforced
concrete curb of Class C-20. Ml 26.46 -

Total Carried To Summary Eth Birr -

7. PAINTING

7.1 Apply three coats of approved type plastic


paint to all internal wall surface including
exposed concrete beams & columns.
M2 114.91 -

7.2 Apply Qrtiz paint for External Wall.


M2 79.98 -

Total Carried To Summary Eth Birr -

Slauter House Page 71


Project:--
Block : - Site Work
Work Item :-Slauter House
Client:- MoND
Consultant: -DCDE
Location:-

NO DESCRIPTION UNIT QTY RATE AMOUNT


[Link] INSTALLATION

8.1 SANITARY FIXTURES


All fixtures and pipes which are specified
below shall subject to the Consultants or
Owner's approval based on samples,
brochures and catalogues presented by the
contractor. Unit Price shall include all the
necessary fixing brackets or hooks and all
assistance civil works such as chiseling of
walls, floors, beams etc… In the specification
"or equivalent" refers to equal quality with the
specified on the specification or above.

8.2 WATER SUPPLY PIPES AND VALVES

8.2.1 Supply, lay install and commission approved


quality PPR pressure pipes (PN20),for hot & cold
water distribution system to sanitary fixtures. The
pipes shall be complete with all the necessary
connecting pieces such as bends,Ys, Ts, reducers,
nipples, unions, hangers & supported with
compatible clips all as per manufacturer's
recommendation to the walls, floors, slabs,beams,
ceilings, etc…Unit price shall include, disinfection
of the pipes with Chlorine and all the necessary
assistance to the installation works. The
installation shall be tested at a pressure of
10kg/cm2 at the expense of the contractor. The
pipes and fittings shall conform to
BS3505/DIN8062 or equivalent [Link]
PPR pipe shall be UV resistant at the exposed
areas. Pipe sizes are external.

-
-
" 25 " Ml 4.00 -
-

Slauter House Page 72


Project:--
Block : - Site Work
Work Item :-Slauter House
Client:- MoND
Consultant: -DCDE
Location:-

NO DESCRIPTION UNIT QTY RATE AMOUNT


" 32 " Ml 5.00 -
-
8.2.2 Supply and fix PPR ball Valves of approved
standard,on water supply distribution lines
where shown on the drawing The valves shall
be compatable with PPR pipes and complete
with adaptors,unions, elastic water proofing ,
hand wheels of normal quality and all other
necessary accessories.

-
-
Diameter 25mm No 1.00 -
-
Diameter 32mm No 2.00 -
-
8.3 WASTEWATER PIPES AND ACCESSORIES -
All domestic waste, vent and storm water pipe
lines shall be uPVC pipes and shall be
provided with a minimum slope as indicated
on the drawing towards the outlet unless
specified. All uPVC pipes and necessary
fittings shall be standard quality and be free
from damage during storage, transportation,
construction etc. Unit price shall include all
the necessary assistance civil works, such as
excavation cartaway, fixing or hanging to
walls, beams or slabs. etc., necessary fittings
such as bends, Y, T, etc. Storm water PVC pipes
shall resist the external temperature and the
quality shall meet the purpose.

-
-

Slauter House Page 73


Project:--
Block : - Site Work
Work Item :-Slauter House
Client:- MoND
Consultant: -DCDE
Location:-

NO DESCRIPTION UNIT QTY RATE AMOUNT


8.3.1 Providing, laying and jointing of internal uPVC
PN-6 waste pipes with all uPVC pipe fittings
including jointing with solvent cement joints
and testing of joints etc. according to where
shown on the drawings. Complete with all the
necessary fittings. Provide cleaning detail for
all waste water riser pipes as per the detail
drawing.

-
-
a) Diameter 80 mm Ml 1.00 -
-
b) Diameter 110 mm Ml 5.00 -
-
8.3.2 Supply and fix floor drains made of polished
steel of approved quality, complete with P-
smell trap and all other necessary fittings and
accessories. Type & model shall be approved
by the consultant prior to installation.
-
-
Size:- Dia. 110 mm No 2.00 -
-
8.3.3 Floor gully -
-
Supply and lay 400mm width Aco drain line
drainage system, B125, with locking slot,
tongue / groove connection system, stainless
steel edge rails etc. The secure edge
protection through integral cast in edge
rail .Thedrainage system, accessories,fittings
and welding shall comply with the
requirement of DIN EN 1433 or equivalent
Institution. Unit price shall include all the
necessary assistance to the installation
[Link] depth up to 0.3m. drainage
line should be laid with slope as indicated
on the drawing.

M 3.00 -

Slauter House Page 74


Project:--
Block : - Site Work
Work Item :-Slauter House
Client:- MoND
Consultant: -DCDE
Location:-

NO DESCRIPTION UNIT QTY RATE AMOUNT


-
8.4 Supply, install, test and commission faucet /
tap including accessories,all as specified
and/or shown on the [Link] work shall
be carried out in accordance with the
technical specification and drawings.

No 3.00 -
-
8.5 ROOF RUNOFF DRAINAGE SYSTEM -
8.5.1 Supply and fix uPVC(PN 6) Downpipes min.
wall thickness 3.2mm,with mass concrete
support at ground level and complete with
basket strainer at inlet, galvanized clips at
every elbows,joints and at every 1m interval
complete with all [Link] pipes,
accessories, fittings & method of welding shall
comply with the requirement of BS 4514or
equivalent Institution. Unit price shall include
all the necessary assistances to the
installation works.

-
-
. a) Size: - Dia.110mm Ml 16.00 -
-
8.6 WATER PROOF -
8.6.1 Apply cementious water proofing material for
toilet room floors & to a height of 300mm on
walls and columns as per the manufacturer's
instruction. The cost shall include cleaning of
all dirts, trace of grease, oil and loose
particles. The work shall be done on
subcontractual bases with the supplier of the
material which will give material &
construction gurantee to the client.

M2 30.00 -

Total Carried To Summary Eth. Birr -

Slauter House Page 75


Project:--
Block : - Site Work
Work Item :-Slauter House
Client:- MoND
Consultant: -DCDE
Location:-

NO DESCRIPTION UNIT QTY RATE AMOUNT


[Link] INSTALLATION
9.1 All distribution boards , breakers , switches,
accessories etc should be genuine Legrand ,
ABB, Siemens or approved equivalents
complying with IEC standards. Distribution
boards should be made of sheet metal and
have separate neutral and ground
busbars/phase [Link] units in the
distribution boards should should be labled to
give the reference and duty of the unit.

9.1.1 Flush mounted sub distribution board SDB-TR


with lockable door, phase-bar rating of
32A/1ph and with all its accessories
consisting of :-

1 pc m.c.b. of 25A/1ph

1 pcs m.c.b. of 16A/1ph

1 pcs m.c.b. of 10A/1ph


and with 20% reserve space. No 1.00 -
- -
9.2 Light point fed through PVC insulated copper
conductors of 2x2.5 [Link] in thermoplastic
conduit of minimum diameter 13.5 mm in/or
under surface including junction box with
cover and screw type insulating connectors
and flush mounted switches.
No 4.00 -
- -

Slauter House Page 76


Project:--
Block : - Site Work
Work Item :-Slauter House
Client:- MoND
Consultant: -DCDE
Location:-

NO DESCRIPTION UNIT QTY RATE AMOUNT


-
9.3.1 PHILIPS TCW 216/236 IC PI with 2x'TL' D
36W/830 lamps. No 4.00 -
- -
9.4 Flush mounted socket outlets of 10A/1ph fed
through PVC conductors of 3x2.5 [Link] in
thermoplastic conduit of minimum f 13.5mm
in/under surface including junction box with
cover and screw type insulating connectors.
No 1.00 -

Total Carried To Summary Eth. Birr -

Sub Total (B) carried to summary Birr

Slauter House Page 77


Slauter Room
1.5)Cart awaye
1) Excavation & Earth Work
12.42 Site Clearing
1.1) Site Clearing
8.40 15.52 Bulk
7.39
27.27 Trench
62.08 Total area
55.21 Total Volume Of Cart awaye

6.40 1.2) Bulk Excavation


5.39
0.45 1.6) 25 cm Hard Core

15.52 Total Volume 2.90


1 2 5.00

6.40 1.3)Trench Excavation 29.00 Total area


1 2 1.00
1.05 Axis A-C on 1&2

13.44

4.39
1 3 1.00 Axis 2-1 on A,B &C
1.05

13.8285

27.27 Total Volume

1.4) Back Fill

15.52 Bulk

27.27 Trench

42.79 Total

0.65 Concrte C-5 Under masonery

19.48 Masonery Wall

20.13 Total

22.66 Total Volume of Back Fill


2) Concrete Work 2.3)Re- bar

2.1) Lean Concrete 112.93 a)8

a)Under masonery b)10


6.40
1 2 0.50 Axis A-C on 1&2 48.31 c)12

6.40 84.22 d)14

4.39 e)16
1 3 0.50 Axis 2-1 on A,B &C
f)20
6.59

12.99 Total area 3) Masonery Wall

2.1)C-25 Concrete 3.1)Under Masonery

a)Gread Beam 6.40


6.10 1 2 0.50
1 2 0.35 Axis A-C on 1&2 1.5 Axis A-C on 1&2
0.20
9.6
0.85
4.39
1 3 0.50 Axis 2-1 on A,B &C
5.20 1.5
1 3 0.35 Axis 2-1 on A,B &C
0.20 9.88

1.09
19.48 Total Volume

1.94 Total Volume


3.2)10 mm Expanision Joint
b)10cm Ground Slab
1 1 31.60
2.90
1 2 5.00 31.60 Total Ml

29.00

29.00 Total area

2.2)Form work

a)Gread beam

6.20 Axis A-C on 1&2


2 2 0.35

8.68

6.20 Axis 2-1 on A,B &C


3 2 0.35

13.02

21.70 Total area


1.3)Re- bar
1) Concrete Work
89.70 a)8
a) Elevation Column
0.20 b)10
1 6 0.20
2.65 77.52 c)12

0.64 Total Volume d)14

b)Top Tie Beam 189.60 e)16


6.10
1 2 0.30 Axis A-C on 1&2 f)20
0.20

0.73 2)Block work

5.20 2.1) 20cm Block


1 3 0.30 Axis 2-1 on A,B &C
0.20 2.90
1 2 2.65
0.94
15.37

1.67 Total Volume 2.90


1 2 2.65
1.2) Form Work
15.37
0.20 a) Elevation Column
6 4 2.65 5.00
1 3 2.65
12.72
39.75
12.72 Total area

b)Top Tie Beam 70.49

6.20 Axis A-C on 1&2 Ddt


2 2 0.30 1.40
1 4 0.7 W1
7.44
3.92
6.20
2 1 0.20 1.90
1 1 2.08 D1
2.48
3.95
6.20 Axis 2-1 on A,B &C
3 2 0.3 3.15
1 1 1.95 opening
11.16
6.14
6.20 Axis 2-1 on A,B &C
3 1 0.2 14.01

3.72
56.48 net Total area

24.80 Total area


2.2) 10cm HCB
5) steel Work
6.00
0.5 2 1.00 5.1) Door

6.00 1 a) D1 Size :- 70x210 cm

5.40
1 1 1.00

5.40 Window

1 a) W1 Size :- 140 x 70cm

11.40 Total area

3) Roofing Work

3.1) G -30
7.20
1 6.20

44.64 Total area

4) Carpentery Work

4.1)Dia 12 Upper & Lower

1 5 14.27

71.35 ml

4.2)Dia 10 Vertical & Diagonal

1 5 11.22

56.10 ml

4.3)7x5 Purlin

1 6 7.20

43.20 ml

4.4) Chip wood


2.9
2 5

29.00

29.00 total area


7)Finishing Work

7.1) Three Internal plastering 7.1) Two Coat of External plastering

2.90 6.00
1 4 2.65 Axis A-C on 1&2 1 2 4.00 Axis A-C on 1&2

30.74 48.00

5.00 5.00
1 4 2.65 Axis 1-2 on A-C 1 2 4 Axis 1-2 on A-C

53.00 40.00

83.74 Total area 88.00 Total area

Ddt Ddt
1.40 1.40
1 4 0.70 W1 1 4 0.70 W1

3.92 3.92

1.90 1.90
1 1 2.08 D1 1 1 2.08 D1

3.95 3.95

1.90 1.90
1 1 2.08 opening 1 1 2.08 opening

3.95 3.95

11.82 11.82

71.92 Total area of plastering 76.18 Total area of plastering

Summary

71.92 Internal wall

12.72 Column

24.80 Top Tie beam

109.44 Total area Plastering


7.3) 50cm Cement Screed
7.9) Curb Stone
2.90
1 2 5.00 1 1 25.20

29.00 25.20 Ml

1.50
1 2 0.40
painting
1.20
109.44 Internal wall

30.20 76.18 External

5.7)10 cm cramic Skirting

1 1 31.6

31.6 Total ml

4 1.44 window sill

5.76

5.76

7.8) Pavment
6.40
1 2 1.20

15.36

5.40
1 2 1.20

12.96

28.32 Total area


CONTRACTOR Page 1
OWNER
BLOCK Gread Beam & Ground Slab BAR SCHEDULE

Ref. Diam Length No of No of Total No Length


Bar shape No Location
(mm) (m) Bars Member of bar φ6 φ8 φ10 φ12 φ14 φ16 φ20 φ24 φ26 φ28
Axis A-C on 1&2 Top 12 7.05 2 2 28.20 0 - 0 28.20 0 0.00 0 0 0 0
Bottom 12 6.55 2 2 26.20 0 - 0 26.20 0 0.00 0 0 0 0
Strip 8 0.90 32 2 57.60 0 57.60 0 0.00 0 0.00 0 0 0 0
0.00 0 - 0.00 0.00 0 0.00 0 0 0 0
Axis 2-1 on A,B&C Top 14 6.05 2 3 36.30 0 - 0.00 0.00 36.3 0.00 0 0 0 0
Bottom 14 5.55 2 3 33.30 0 - 0.00 0.00 33.3 0.00 0 0 0 0
Strip 8 0.90 27 3 72.90 0 72.90 0.00 0.00 0 0.00 0 0 0 0
0.00 0 - 0.00 0.00 0 0.00 0 0 0 0
Ground Slab 8 2.90 26 1 75.40 0 75.40 0.00 0.00 0 0.00 0 0 0 0
8 5.00 16 1 80.00 0 80.00 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0.00 0.00 0 0.00 0 0 0 0
0 - 0 0.00 0 0.00 0 0 0 0
Total length 285.90 0.00 54.40 69.60 0.00 0.00 0.00
Weight kg/m 0.222 0.395 0.617 0.888 1.21 1.58 2.468 3.552

SAR BET SITE Page 84


Total weight kg 112.93 0.00 48.31 84.22 0.00 0.00 0.00

SAR BET SITE Page 85


φ30 φ32 Remark
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0

SAR BET SITE Page 86


SAR BET SITE Page 87
CONTRACTOR Page 2
OWNER
BLOCK Elevation Column & Top Tie Beam BAR SCHEDULE

Ref. Diam Length No of No of Total No Length


Bar shape No Location
(mm) (m) Bars Member of bar φ6 φ8 φ10 φ12 φ14 φ16 φ20 φ24 φ26 φ28
C1 16 4.00 5 6 120.00 0 - 0 0 0 120.00 0 0 0 0
Strip 8 0.70 23 6 96.60 0 96.60 0 0 0 0.00 0 0 0 0
0.00 0 - 0 0 0 0.00 0 0 0 0
0.00 0 - 0 0 0 0.00 0 0 0 0
T.B Axis A-C on 1&2 Top 12 6.95 2 2 27.80 0 - 0 27.8 0 0.00 0 0 0 0
Bottom 12 6.55 2 2 26.20 0 - 0 26.2 0 0.00 0 0 0 0
Strip 8 0.90 32 2 57.60 0 57.60 0 0 0 0.00 0 0 0 0
0.00 0 - 0 0 0 0.00
T.B Axis A-C on A,B&C Top 12 5.95 2 3 35.70
Bottom 12 5.55 2 3 33.30 33.3
Strip 8 0.90 27 3 72.90 72.90 0
0
0
0
0
0
0
0
0
0

0 - 0 0 0 0.00 0 0 0 0
0 - 0 0 0 0.00 0 0 0 0
0 - 0 0 0 0.00 0 0 0 0
0 - 0 0 0 0.00 0
0 - 0 0 0 0.00 0
0 - 0 0 0 0.00 0
0 - 0 0 0 0.00 0
Total length 227.10 0.00 87.30 0.00 120.00 0.00 0.00
Weight kg/m 0.222 0.395 0.617 0.888 1.21 1.58 2.468 3.552
Total weight kg 89.70 0.00 77.52 0.00 189.60 0.00 0.00

SAR BET SITE Page 88


φ30 φ32 Remark
0 0
0 0
0 0
0 0
0 0
0 0
0 0

0 0
0 0
0 0

SAR BET SITE Page 89


Pump House ( 5.00x5.00m) 1.5) Cart awaye

1) Excavation & Earth Work 10.95 Site Clearing

1.1) Site Clearing 9.46 Bulk


7.40 9.40
7.40
29.81 Total Volume
54.76
2) Concrete Work
1.2) Bulk Excavation
5.20 2.1) Lean Concrete
5.20
0.35 a) Under masoner
18.80
9.46 0.50

1.3) Trench 50m 9.40 Total area


5.20
2 1.00 2.2)C-25 Concrete
0.50
a)Gerad Beam
5.2 5.20
4 0.20
4.20 0.20
2 1.00
0.50 0.83

4.2 b)15 cm Ground Slab

5.00
9.4 Total Volume 5.00

25.00 Total area


1.3) Back Fill
3.75 Total Volume
9.46 Bulk
2.3)Form Work
9.40 Trench
5.2 a)Gerad Beam
18.86 4 2 0.2

0.47 Lean concrete 8.32 Total area

6.25 hard core


Re -bar
7.52 masonery
150.73 a) 8
14.24
b)10
4.62
c) 12
5.00 1.4) Hard Core
5.00 106.19 d)14

25.00 e)16
3) Masonery
5.20
2 0.50
0.80

4.16

4.20
2 0.50
0.80

3.36

7.52 Total Volume


B) Super Structure 2)Block Wall
2.1) 20 HCB Wall
1) Concrete Work 5.00
1 2 2.80
1.1) Concrete C-25
28.00
a) Elevation Column
0.20 5.00
1 4 0.20 1 2 2.80
2.80
28.00
0.45 Total Volume
56.00 Total area
b) Top Tie Beam
5.00 Ddt
1 4 0.20 2.00
0.20 1 2 0.75 W1

0.80 Total Volume 3.00

1.30
1.2) Form Work 1 2 1.20 W2

a) Elevation Column 3.12


0.20
4 4 2.80 2.00
1 2 2.00 D1
8.96 Total area
8.00
b) Top Tie Beam
5.00
4 2 0.20 14.12

8.00
41.88 Net Total area
5.00
4 1 0.20 2.2) 15 HCB Wall
5.00
4.00 0.5 2 1.40

7.00
12.00 Total area
5.00
1 2 1.40

1.3) Re -bar 14.00

62.57 a) 8 21.00 Total area

b)10

c) 12 3)CIS 30 Roofing Work

169.11 d)14 6.70


1 1 6.40
e)16
42.88 Total area
6)Finishing Work
4)Carpentery Work
6.1) Internal wall
4.1) Dia 12 Upper & Lower
5.00
1 5 13.89 1 2 2.80

69.45 Ml 28.00

5.00
4.2) Dia 10 Diagonal &Vertical 1 2 2.80

1 5 13.89 28.00

69.45 Ml 56.00 Total area

Ddt
4.3) 25cm width 2.5 cm thick pine 2.00
wooden fascial board 1 2 0.75 W1
1 1 26.2
3.00
26.20 Ml
1.30
1 2 1.20 W2
5)Metal Work
3.12
5.1) 28x28 Ltz Door
2.00
2 a) Size :- W1 =200 x 75 cm 1 2 2.00 D1

3 b) Size :- W2 =130 x 120 cm 8.00

5.2) 28x28 Ltz Door 14.12

1 a) Size :- D1 =200 x 200 cm


41.88 Net Total area

Summary

41.88 Wall

8.96 Coloum

12.00 Top Tie Beam

62.84 Total area of plastering


7) Painting
6.2) External wall
7.1) Internal wall Painting
5.00
1 2 2.80 62.84 Net Total area

28.00
7.2) External wall Painting
5.00
1 2 2.80 62.88 Net Total area

28.00

5.00
0.5 2 1.40

7.00

5.00
1 2 1.40

14.00

77.00 Total area

Ddt
2.00
1 2 0.75 W1

3.00

1.30
1 2 1.20 W2

3.12

2.00
1 2 2.00 D1

8.00

14.12

62.88 Net Total area

6.3)3cm Cement Screed Work

5.00
1 1 5.00

25.00 Total area


CONTRACTOR Page 1
OWNER
BLOCK Sub BAR SCHEDULE

Ref. Diam Length No of No of Total No Length


Bar shape No Location
(mm) (m) Bars Member of bar φ6 φ8 φ10 φ12 φ14 φ16 φ20 φ24 φ26 φ28
Slab 8 5.20 27 1 140.40 0 140.40 0 0.00 0 0.00 0 0 0 0
8 5.20 27 1 140.40 0 140.40 0 0.00 0 0.00 0 0 0 0
0.00 - 0 0.00 0 0.00 0 0 0 0
Gread beam 14 5.62 2 2 22.48 - 0.00 0.00 22.48 0.00 0 0 0 0
14 5.35 2 2 21.40 - 0.00 0.00 21.4 0.00 0 0 0 0
8 0.90 28 2 50.40 50.40 0.00 0.00 0 0.00 0 0 0 0

Gread beam 14 5.62 2 2 22.48 22.48


14 5.35 2 2 21.40 21.4
8 0.90 28 2 50.40 50.40 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Total length 381.60 0.00 0.00 87.76 0.00 0.00 0.00
Weight kg/m 0.222 0.395 0.617 0.888 1.21 1.58 2.468 3.552
Total weight kg 150.73 0.00 0.00 106.19 0.00 0.00 0.00

SAR BET SITE Page 103


150.73 0.00 106.19 0.00

CONTRACTOR Page 1
OWNER
BLOCK Super BAR SCHEDULE

Ref. Diam Length No of No of Total No Length


Bar shape No Location
(mm) (m) Bars Member of bar φ6 φ8 φ10 φ12 φ14 φ16 φ20 φ24 φ26 φ28
Column 14 3.25 4 4 52.00 52
8 0.90 16 4 57.60 57.60 0
0
Tobeam 14 5.62 2 2 22.48 22.48
14 5.35 2 2 21.40 21.4
8 0.90 28 2 50.40 50.40 0
0.00 0
Topbeam 14 5.62 2 2 22.48 22.48
14 5.35 2 2 21.40 21.4
8 0.90 28 2 50.40 50.40 0
0.00 0
0.00 0
0.00 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Total length 158.40 0.00 0.00 139.76 0.00 0.00 0.00
Weight kg/m 0.222 0.395 0.617 0.888 1.21 1.58 2.468 3.552
Total weight kg 62.57 0.00 0.00 169.11 0.00 0.00 0.00

62.57 0.00 169.11 0.00

SAR BET SITE Page 104


φ30 φ32 Remark
0 0
0 0
0 0
0 0
0 0
0 0

SAR BET SITE Page 105


φ30 φ32 Remark

SAR BET SITE Page 106


Oil Separator ( 410x165)

A) SUB STRUCTURE 1.5) Cart awaye

1)Excavation & Earth Work


22.27 Item 1.1
1.1) Site Clearing 0.20

6.10 4.45
3.65
30.41 Item 1.2
22.27 Total area

1.2) Bulk Excavation


5.10 34.86 Total Volume
2.65
2.25

30.41 Total Volume

1.3) Back Fill

30.41 bulk

30.41

0.34 C-5

1.02 Concrete

1.36

29.05 Total Volume of back Fill


2) Concrete Work Brick Wall

2.1)Lean Concrete C-5 4.10 25cm


1 2 2.05
a) Under Slab
16.81
4.10
1 1.65 1.15
1 2 2.05
6.77
4.715
6.77 Total area

21.53 Total area


2.2)Concrete C-25
8mm thick weathered wooden buffle
4.10 a) 15 cm bottom 4.10
1.65 1.65

6.77 Total area 6.77 Total area

b) 20 cm at slab Plastering
4.10
1.65 Internal & external

6.77 Total area 4.10


1 2 2.05
Form Work
16.81

c)C_25 Manhole Cover

1 Size:- 70x70x10

b) 20 cm at slab 16.81 Total area


4.10
1 1 1.65 Apply 3cm thick cement sand screed
1.40
6.77 Total area 1 2 0.4

1.12 Total area


Rebar

4.42 Dia 8

193.96 Dia 10

2.90 Dia 14
Plastering

a)pad
12.20
1 4 0.25

12.20 Total area


CONTRACTOR Page 1
OWNER
BLOCK Bottom Slab BAR SCHEDULE

Ref. Diam Length No of No of Total No Length


Bar shape No Location
(mm) (m) Bars Member of bar φ6 φ8 φ10 φ12 φ14 φ16 φ20 φ24 φ26 φ28
Bottom Slab 10 4.07 12 1 48.84 0 - 48.84 0.00 0 0.00 0 0 0 0
10 1.35 7 2 18.90 0 - 18.9 0.00 0 0.00 0 0 0 0
10 3.05 15 2 91.50 91.5 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
Top Slab 10 4.07 12 1 48.84 48.84 0.00 0 0.00 0 0 0 0
10 1.33 7 2 18.62 18.62 0.00 0 0.00 0 0 0 0
10 0.80 12 1 9.60 9.60 0.00 0 0.00 0 0 0 0
10 2.78 12 1 33.36 33.36 0.00 0 0.00 0 0 0 0
10 2.98 15 1 44.70 44.70 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
Manhole 8 0.70 8 2 11.20 11.20 0.00 0.00 0 0.00 0 0 0 0
0.00 - 0.00 0.00 0 0.00 0 0 0 0
14 0.30 8 1 2.40 - 0.00 0.00 2.4 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
6.77 - 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
7.77 - 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
- 0.00 0.00 0 0.00 0 0 0 0
- 0 0.00 0 0.00 0 0 0 0
Total length 11.20 314.36 0.00 2.40 0.00 0.00 0.00
Weight kg/m 0.222 0.395 0.617 0.888 1.21 1.58 2.468 3.552

SAR BET SITE Page 110


Total weight kg 4.42 193.96 0.00 2.90 0.00 0.00 0.00

SAR BET SITE Page 111


φ30 φ32 Remark
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0

SAR BET SITE Page 112


SAR BET SITE Page 113
Ground Reservior Pad

A) SUB STRUCTURE 1.5) Cart awaye

1)Excavation & Earth Work


201.64 Item 1.1
1.1) Site Clearing 0.20

14.20 40.33
14.20
76.18 Item 1.2
201.64 Total area

1.2) Bulk Excavation


13.80 116.51 Total Volume
13.80
0.40 1.5) Hard Core
12.20
76.18 Total Volume 12.20

1.3) Back Fill 148.84 Total area

76.18 bulk

76.18

7.44 C-5

37.21 Concrete

44.65

31.53 Total Volume of back Fill


2) Concrete Work

2.1)Lean Concrete C-5

a) Under Hared Core

12.20
1 12.20

148.84

148.84 Total area

2.2)Concrete C-25

a) 25 cm pad
12.20
12.20
0.25

37.21 Total area

Form Work

a) pad
12.20
1 4 0.25

12.20 Total area

Rebar

587.92 Dia 8

Plastering

a)pad
12.20
1 4 0.25

12.20 Total area


CONTRACTOR Page 1
OWNER
BLOCK pad BAR SCHEDULE

Ref. Diam Length No of No of Total No Length


Bar shape No Location
(mm) (m) Bars Member of bar φ6 φ8 φ10 φ12 φ14 φ16 φ20 φ24 φ26 φ28
pad 8 12.20 61 1 744.20 0 744.20 0 0.00 0 0.00 0 0 0 0
8 12.20 61 1 744.20 0 744.20 0 0.00 0 0.00 0 0 0 0
0 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0.00 0.00 0 0.00 0 0 0 0
0 0.00 0 0.00 0 0 0 0
Total length 1,488.40 0.00 0.00 0.00 0.00 0.00 0.00
Weight kg/m 0.222 0.395 0.617 0.888 1.21 1.58 2.468 3.552

SAR BET SITE Page 116


Total weight kg 587.92 0.00 0.00 0.00 0.00 0.00 0.00

SAR BET SITE Page 117


φ30 φ32 Remark
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0

SAR BET SITE Page 118


SAR BET SITE Page 119
Septic Tank ( 16.40x10.60) 2)Concrete Work

1) Excavation & Earth Work 2.1) Lean Concrete


16.45
1.1) Site Clearing 10.65 a) Under Slab

18.40 175.19
12.60

231.84 Total area 2.2)Concrete 25

1.2) Bulk Excavation 00-150 7.00 a)Bottom Slab


16.40 2 4.85
10.60
1.50 67.90

260.76 4.80
2 4.85
1.3) Bulk Excavation 150-300
16.40 46.56
10.60
1.50 3.60
2 4.85
260.76
34.92

1.4) Bulk Excavation 300-4.20


16.40 149.38 Total area
10.60
1.20 29.88 Total Volume

208.61 7.00 b)Top Slab


2 4.85
1.5) Back Fill
67.90
961.97 total bulk
4.80
2 4.85

961.97 Total 46.56

3.60
87.60 2 4.85

29.88 34.92

28.15 149.38 Total area

145.63 1.20 ddt


6 1.20

816.34

1.6) Cart Awye


8.64
46.37 Site Clearing

730.13 Bulk Excavation 140.74 Net Total area


28.15 Net Total Volume
776.50 Total Volume

7.00 c)Shree Wall 2.3) Form Work


1 2 3.70
0.30 7.00 a)Top Slab
2 4.85
15.54
67.90
4.80
1 2 3.70 4.80
0.30 2 4.85

10.66 46.56

3.60 3.60
1 2 3.70 2 4.85
0.30
34.92
7.99
149.38 Total area
4.85
2 2 3.70 1.20 ddt
0.30 6 1.20

21.53 8.64

4.85
2 2 3.30 140.74 Net Total area
0.20

12.80

7.00
1 1 3.30
0.20

4.62

4.80
1 1 3.30
0.20

3.17

3.60
1 1 3.30
0.20

2.38

78.69
7.00 b)Shree Wall
2 2 3.70

103.60

4.80
2 2 3.70

71.04

3.60
2 2 3.70

53.28

4.85
4 2 3.70

143.56

4.85
2 2 3.30

64.02

7.00
2 1 3.30

46.20

4.80
2 1 3.30

31.68

3.60
2 1 3.30

23.76

537.14

2.4) Rebar

66.24 a)8

17.20 b)10

7,994.93 c)12

d)14
e)16

f)20

3) Finishing Work

3.1) one Coat Plastering


7.00
2 2 3.70

103.60

4.80
2 2 3.70

71.04

3.60
2 2 3.70

53.28

4.85
4 2 3.70

143.56

4.85
2 2 3.30

64.02

7.00
2 1 3.30

46.20

4.80
2 1 3.30

31.68

3.60
2 1 3.30

23.76

537.14
CONTRACTOR
OWNER
BLOCK Bottom Slab BAR SCHEDULE

Ref. Diam Length No of No of Total No Length


Bar shape No Location
(mm) (m) Bars Member of bar φ6 φ8 φ10 φ12 φ14 φ16 φ20 φ28 φ30 φ32
Axis 1-2 on CB 12 7.84 33 1 258.72 0 - 0 258.72 0 0.00 0 0 0 0
12 3.64 33 1 120.12 0 - 0 120.12 0 0.00 0 0 0 0
12 8.94 33 1 295.02 0 - 0 295.02 0 0.00 0 0 0 0
12 10.86 33 1 358.38 0 - 0.00 358.38 0 0.00 0 0 0 0
12 0.70 2 1 1.40 0 - 0.00 1.40 0 0.00 0 0 0 0

Axis 2-4 on CB 12 9.44 33 1 311.52 311.52


12 3.21 33 1 105.93 105.93
12 10.54 33 1 347.82 347.82
12 10.94 33 1 361.02 361.02
12 0.70 2 1 1.40 1.40

1-2 B-A 12 10.86 33 1 358.38 358.38


12 8.94 33 1 295.02 295.02
12 7.84 33 1 258.72 258.72
12 3.64 33 1 120.12 120.12
12 0.70 2 1 1.40 1.40
Axis 2-4 on BA 12 10.98 33 1 362.34 362.34
12 3.21 33 1 105.93 105.93
12 10.54 33 1 347.82 347.82
12 9.44 33 1 311.52 311.52
12 0.70 2 1 1.40 1.40

1-2 B-A 12 5.79 36 1 208.44 208.44


12 6.89 36 1 248.04 248.04

2-3 on B-A 12 7.23 25 1 180.75 180.75


12 6.89 25 1 172.25 172.25
12 3.57 25 1 89.25 89.25
3-4 on B-A 12 6.89 19 1 130.91 130.91
12 5.78 19 1 109.82 109.82
12 2.84 19 1 53.96 53.96
1-2 on B-A 12 5.79 36 1 208.44 208.44
12 6.89 36 1 248.04 248.04
12 3.10 36 1 111.60 111.60
0.00
Total length - 0.00 6085.48 0.00 0.00 0.00
Weight kg/m 0.222 0.395 0.617 0.888 1.21 1.58 2.468
Total weight kg - 0.00 5403.91 0.00 0.00 0.00
SAR BET SITE Page 125
CONTRACTOR
OWNER
BLOCK Bottom BAR SCHEDULE

Ref. Diam Length No of No of Total No Length


Bar shape No Location
(mm) (m) Bars Member of bar φ6 φ8 φ10 φ12 φ14 φ16 φ20 φ28 φ30 φ32
2-3 on B-A 12 7.23 25 1 180.75 180.75 0 0
12 6.89 25 1 172.25 172.25 0 0
3-4 on B-A 12 6.89 19 1 130.91 130.91 0 0
12 5.79 19 1 110.01 110.01 0 0
10 0.87 3 1 2.61 2.61 0.00
10 0.70 3 1 2.10 2.10 0.00
8 0.30 3 1 0.90 0.90 0.00

0 0
0 0
0 0
0 0
0 0

0 0
0 0
0 0
0 0
0 0

Total length 0.90 4.71 593.92


Weight kg/m 0.222 0.395 0.617 0.888 1.21 1.58 2.468
Total weight kg 0.36 2.91 527.40 0.00 0.00 0.00

0.36 527.40 0.00 0.00

SAR BET SITE Page 126


CONTRACTOR
OWNER
BLOCK sheer wall BAR SCHEDULE

Ref. Diam Length No of No of Total No Length


Bar shape No Location
(mm) (m) Bars Member of bar φ6 φ8 φ10 φ12 φ14 φ16 φ20 φ28 φ30 φ32
Shear wall 12 4.29 2 2 17.16 17.16 0 0
12 4.29 2 2 17.16 17.16 0 0
10 3.86 2 1 7.72 7.72 0.00 0 0
10 3.86 2 2 15.44 15.44 0.00 0 0
8 16.41 2 3 98.46 98.46 0.00
8 10.40 2 3 62.40 62.40 0.00 0 0

0 0
0 0
0 0
0 0

0 0
0 0
0 0
0 0
0 0

0 0
0 0
0 0
0 0
0 0

Total length 160.86 23.16 34.32


Weight kg/m 0.222 0.395 0.617 0.888 1.21 1.58 2.468
Total weight kg 63.54 14.29 30.48 0.00 0.00 0.00

63.54 30.48 0.00 0.00

SAR BET SITE Page 127


CONTRACTOR
OWNER
BLOCK Bottom Top BAR SCHEDULE

Ref. Diam Length No of No of Total No Length


Bar shape No Location
(mm) (m) Bars Member of bar φ6 φ8 φ10 φ12 φ14 φ16 φ20 φ28 φ30 φ32
Axis 1-2 on CB 12 7.84 33 1 258.72 0 - 0 258.72 0 0.00 0 0 0 0
12 3.64 33 1 120.12 0 - 0 120.12 0 0.00 0 0 0 0
12 8.94 33 1 295.02 0 - 0 295.02 0 0.00 0 0 0 0
12 10.86 33 1 358.38 0 - 0.00 358.38 0 0.00 0 0 0 0
- 0 0.00
12 0.70 2 1 1.40 - 1.40 0 0.00
Axis 2-4 on CB 12 9.44 33 1 311.52 - 311.52 0 0.00
12 3.21 33 1 105.93 - 105.93 0 0.00
12 10.54 33 1 347.82 - 347.82 0 0.00
12 10.94 33 1 361.02 - 361.02 0 0.00
12 0.70 2 1 1.40 - 1.40 0 0.00
- 0 0.00
1-2 B-A 12 10.86 33 1 358.38 - 358.38 0 0.00 0 0 0
12 8.94 33 1 295.02 - 295.02 0 0.00 0 0 0
12 7.84 33 1 258.72 - 258.72 0 0.00 0 0 0
12 3.64 33 1 120.12 - 120.12 0 0.00 0 0 0
12 0.70 2 1 1.40 - 1.40 0 0.00 0 0 0
- 0 0.00
Axis 2-4 on BA 12 10.98 33 1 362.34 - 362.34 0 0.00 0 0 0
12 3.21 33 1 105.93 - 105.93 0 0.00 0 0 0
12 10.54 33 1 347.82 - 347.82 0 0.00 0 0 0
12 9.44 33 1 311.52 - 311.52 0 0.00 0 0 0
12 0.70 2 1 1.40 - 1.40 0 0.00 0 0 0
Axis 3-4 12 0.89 19 1 16.91 - 16.91 0 0.00
12 5.79 19 1 110.01 - 110.01 0 0.00
16 1.41 4 1 5.64 - 0.00 0 5.64
8 0.60 4 1 2.40 2.40 0.00 0 0.00
8 0.88 4 1 3.52 3.52 0.00 0 0.00
- 0.00 0 0.00
- 0.00 0 0.00
- 0.00 0 0.00

Total length 5.92 0.00 2289.57 0.00 5.64 0.00


Weight kg/m 0.222 0.395 0.617 0.888 1.21 1.58 2.468
Total weight kg 2.34 0.00 2033.14 0.00 8.91 0.00

SAR BET SITE Page 128


2.34 2033.14 0.00 8.91

66.24 17.20 7994.93

SAR BET SITE Page 129


Remark

SAR BET SITE Page 130


Remark
0

SAR BET SITE Page 131


Remark
0

SAR BET SITE Page 132


Remark

SAR BET SITE Page 133


SUMMARY
Option 1 (Cobble Stone Road Surfaceing )
1 SERIOUS 2000 ETH .BIRR

2 SERIOUS 3000 " ''

3 SERIOUS 4000 " ''

3 SERIOUS 5000 " ''

4 SERIOUS 6000

5 SERIOUS 9000

Defense Construction Design Enterprise Page 134


Project:--Engineering Collage Compound Road & Related Site Works

Work Item :-Option 1 (Cobble Stone Road Surfaceing )

Client:- MoND

Consultant: -DCDE

Location:- Debrezeit

Spec.
Description Unit Quantity Rate Amount
Ref. No
2000 SITE CLEARANCE
2100 CLEARING AND GRUBBING
21.01 Clearing and Grabbing ha 3.10 32,834.19 101,785.99
Total Carried Summary 101,785.99
3000 DRAINAGE
31.01 Excavation for open drains
Excavating soft material situated within the following depth
(a)
ranges below the surface level:

(i) 0 m up to 1.5 m m3 4,621.48 83.43 385,570.08


(ii) Exceeding 1.5 m and up to3.0m m3 1,462.98 130.36 190,714.07

Overhaul for material hauled in excess of 1.5 km free-haul


31.15 m3 12,284.46 65.85 808,931.69
(normal overhaul)

i) Well compacted selected granular material under the bed of


31.16 m3 1,981.68 293.99 582,594.10
side, road crossing and open ditch, (see dwg)
Back fill on the back side of both open ditch wall with granular
31.17 material and compact in layers not exceeding 200mm thick. m3 492.00 293.99 144,643.08

Curbing, Channeling, Open Chutes, Downpipes, and


3300
Concrete Lining of Open Drains
33.01 Curbing
Class C-25 /19 concrete curbing type-1 (20*40cm) along the road
(a) ml 3,443.00 647.40 2,228,998.20
and parking, (see dwg)

Class C-25 /19 concrete curbing type-2 (12*35cm) along the


(b) ml 5,540.00 516.20 2,859,748.00
walkway, (see dwg)

i) 10cm thick cast insitu reinforced concrete quality C-20, 320kg


33.02 m3 14.30 2,300.00 32,890.00
of cement/m3 for road crossing ditch bedding (see dwg).

ii) 15cm thick cast insitu reinforced concrete quality C-25, 360kg
of cement/m3 for open ditch bedding, price includes formwork m3 405.90 3,611.15 1,465,765.79
(see dwg).

Defense Construction Design Enterprise Page 135


Spec.
Description Unit Quantity Rate Amount
Ref. No
iii) 10cm thick cast insitu mass concrete quality C-20, 320kg of
m3 222.82 2,223.47 495,433.59
cement/m3 for road side ditch bedding (see dwg).

33.03 Class C-25 confining concrete member at every 5m along the


road way, (size = 15x20x600cm).

a) For Road m3 64.85

b) For Parking m3 4.95


33.12 Steel reinforcement
Mild steel reinforcement according to structural drawings. Price
(a)
includes cutting, bending, placing in position, and tying wire.

i) Ø6 stirrup c/c 20cm, L=60cm kg 1,571.58 33.49 52,632.21


ii) Ø8 mm deformed bar kg 839.38 34.49 28,950.22
iii) Ø10 mm deformed bar kg 5,726.82 35.49 203,244.84

Defense Construction Design Enterprise Page 136


Spec.
Description Unit Quantity Rate Amount
Ref. No
iv) Dia 12 mm deformed bar kg 24,841.80 34.49 856,793.68
(b) i) Grill, Ø28 bar for road crossing ditch cover, c/c 20mm kg 1,596.87 39.50 63,076.37
ii) Grill, 600x54x2mm plate for side ditch cover, c/c 20mm (See
kg 44,465.75 34.49 1,533,623.72
dwg)
(c) Angle Iron (40x40x3mm) Pcs 1,218.00 623.31 759,191.58

PITCHING, STONEWORK, AND EROSION


3400 0.00
PROTECTION

34.03 Stone Masonry Walls 0.00


i) Trachytic roughly dressed and pointed, in all exposed surfaces,
(b) cement mortared stone walls for all ditchs bedded in cement sand m3 2,880.09 1,581.61 4,555,179.14
mortar 1:4
34.04 Concrete Pitching 0.00

5cm thick lean concrete quality C-5, with minimum cement content of
34.06 150kg/m3 of concrete for road crossing and side ditch (See dwg). m2 729.60 71.65 52,275.84

5cm thick lean concrete quality C-15, with minimum cement content of m2
34.07 200kg/m3 of concrete for open ditch (See dwg). 3,526.00 150.00 528,900.00

Cement sand mortar copping at the top of all masonry ditch walls m2
34.08 1,459.20
to the level of angle iron with cement sand mortar ratio 1:4.
Supply, cut and fix Ø100mm uPVC weep hole pipe 75cm long every
34.09 10m in masonry ditch wall (see dwg) ml 66.00 1,050.00 69,300.00

Total Carried Summary 17,898,456.20

4000 EARTH WORKS

4200 Roadway and Borrow Excavation


42.01 Cut & Borrow to fill including free-haul up to 1.5km:
(b) Material in compacted layer thickness exceeding 200mm:

i) Compacted to 93% of modified AASHTO density (imported


m3 386.50 293.99 113,627.14
material)

42.02 Selected borrow fill (capping layer) m3 7,539.87 166.52 1,255,539.15

Cut to spoil including free haul up to 1.5Km material


42.03
obtained from

a) Common(normal) excavation m3 6,596.46 142.26 938,412.40

Defense Construction Design Enterprise Page 137


Spec.
Description Unit Quantity Rate Amount
Ref. No
b) Intermediate excavation m3 2,198.82 148.63 326,810.62

c) Rock excavation m3 0.00


Overhaul for material hauled in excess of 1.5 km free-haul
d) m3 8,795.28 65.85 579,169.19
(normal overhaul)
Total Carried Summary 3,213,558.50
5000 BASE, SUB BASE AND GRAVEL WEARING COURSE

51.01 Sub-base layer constructed from gravel or Crushed stone:

(a) 200mm thick Gravel sub-base (unstabilized gravel) compacted to:

(i) 95% of modified AASHTO density for the main road and
m3 3,687.68 352.02 1,298,137.11
walkways.
Total Carried Summary 1,298,137.11
serious6000
64.02 Segmental Pavements
i) Segmental paving (road pavment) /cobble stone,
100x100x100mm in size, sound basaltic rock or equivalent as per
(a) engineer order including supply, placing or laying to the pattern m2 11371.92 488.98 5,560,641.44
shown as per the attachement or as may be agreed by the
engineer,compaction and filler material

ii) 300x300mm coloured concrete tiles of 50mm thick for walway m2 5540 403.53 2,235,556.20

(b) Bedding

70mm thick crushed aggregate bedding including transport


supply, laying, compaction and joint filling for both road & m2 16911.92 68.68 1,161,510.67
walkway

Total Carried to Summary 8,957,708.31


serious 9000
Greenery works for median exist between the two lanes roads, the
96.03 m2 15,761.70 220 3,467,574.00
price includes all necessary civil works.
Total Carried to Summary 3,467,574.00

Grand Total -

Defense Construction Design Enterprise Page 138


Compound Road

SUMMARY

ETH .BIRR

1 SERIOUS 2000 101,785.99

2 SERIOUS 3000 -

3 SERIOUS 4000 4,480,030.47

4 SERIOUS 5000 2,574,053.32

5 SERIOUS 6000 -

6 SERIOUS 9000 3,593,667.60

SUB TOTAL -

DZ Compound Road Page 110


Project:--Engineering Collage Compound Road & Related Site Works
Work Item :-Compound Road
Client:- MoND
Consultant: -DCDE
Location:- Debrezeit

Spec.
Description Unit Quantity Rate Amount
Ref. No
2000 SITE CLEARANCE
2100 CLEARING AND GRUBBING
21.01 Clearing and Grabbing
Ha 3.10 32,834.19 101,785.99
Total Carried Summary 101,785.99
3000 DRAINAGE

31.01 Excavation for open drains

Excavating soft material situated within


(a) the following depth ranges below the
surface level:

(i) 0 m up to 1.5 m M3 4,621.48 0.00 0.00

(ii) Exceeding 1.5 m and up to3.0m M3 1,462.98 0.00 0.00

Overhaul for material hauled in excess


31.15
of 1.5 km free-haul (normal overhaul)
M3 12,284.46 65.85 808,931.69

i) Well compacted selected granular


31.16 material under the bed of side, road
crossing and open ditch, (see dwg) M3 1,981.68 0.00 0.00

Back fill on the back side of both open ditch


31.17 wall with granular material and compact in
layers not exceeding 200mm thick.
M3 492.00 0.00 0.00
Total Carried Summary 0.00

DZ Compound Road Page 111


Project:--Engineering Collage Compound Road & Related Site Works
Work Item :-Compound Road
Client:- MoND
Consultant: -DCDE
Location:- Debrezeit

Spec.
Description Unit Quantity Rate Amount
Ref. No
Curbing, Channeling, Open Chutes,
3300 Downpipes, and Concrete Lining of
Open Drains
33.01 Curbing

Class C-25 /19 concrete curbing type-1


(a) (20*40cm) along the road and parking,
(see dwg) Ml 3,443.00 647.40 2,228,998.20

Class C-25 /19 concrete curbing type-2


(b) (12*35cm) along the walkway, (see
dwg) Ml 5,540.00 516.20 2,859,748.00

i) 10cm thick cast insitu reinforced


concrete quality C-20, 320kg of
33.02
cement/m3 for road crossing ditch
bedding (see dwg).
M3 14.30 0.00 0.00

ii) 15cm thick cast insitu reinforced


concrete quality C-25, 360kg of
cement/m3 for open ditch bedding,
price includes formwork (see dwg). M3 405.90 0.00 0.00

iii) 10cm thick cast insitu mass concrete


quality C-20, 320kg of cement/m3 for
road side ditch bedding (see dwg).

M3 222.82 0.00 0.00


33.12 Steel reinforcement

DZ Compound Road Page 112


Project:--Engineering Collage Compound Road & Related Site Works
Work Item :-Compound Road
Client:- MoND
Consultant: -DCDE
Location:- Debrezeit

Spec.
Description Unit Quantity Rate Amount
Ref. No
Mild steel reinforcement according to
structural drawings. Price includes
(a)
cutting, bending, placing in position,
and tying wire.

i) Dia 08 mm deformed bar kg 839.38 0.00 0.00

ii) Dia 12 mm deformed bar kg 24,841.80 0.00 0.00

i) Grill, Ø28 bar for road crossing ditch


(b) kg
cover, c/c 20mm 1,596.87 60.00 95,812.20
0.00
ii) Grill, 600x54x2mm plate for side
kg 60.00
ditch cover, c/c 20mm (See dwg) 44,465.75 2,667,945.00

(c) Angle Iron (40x40x3mm) Pcs 609.00 0.00 0.00

PITCHING, STONEWORK, AND


3400
EROSION PROTECTION

34.03 Stone Masonry Walls

i) Trachytic roughly dressed and


pointed, in all exposed surfaces, cement
(b)
mortared stone walls for all ditchs
bedded in cement sand mortar 1:4
M3 2,880.09 0.00 0.00
34.04 Concrete Pitching
5cm thick lean concrete quality C-5, with
minimum cement content of 150kg/m3 of
34.06
concrete for road crossing and side ditch
(See dwg). M2 729.60 0.00 0.00

5cm thick lean concrete quality C-15, with


34.07 minimum cement content of 200kg/m3 of
concrete for open ditch (See dwg).
M2 3,526.00 0.00 0.00
Supply, cut and fix Ø100mm uPVC weep
34.08 hole pipe 75cm long every 10m in masonry
ditch wall (see dwg) Ml 66.00 2,194.59 144,842.94
Total Carried Summary -

DZ Compound Road Page 113


Project:--Engineering Collage Compound Road & Related Site Works
Work Item :-Compound Road
Client:- MoND
Consultant: -DCDE
Location:- Debrezeit

Spec.
Description Unit Quantity Rate Amount
Ref. No
4000 EARTH WORKS

4200 Roadway and Borrow Excavation

Cut & Borrow to fill including free-haul


42.01
up to 1.5km:

Material in compacted layer thickness


(b)
exceeding 200mm:

i) Compacted to 93% of modified


M3
AASHTO density (imported material)
386.50 293.99 113,627.14

42.02 Selected borrow fill (capping layer) M3 7,539.87 334.49 2,522,011.12

Cut to spoil including free haul up to


42.03
1.5Km material obtained from

a) Common(normal) excavation M3 6,596.46 142.26 938,412.40

b) Intermediate excavation M3 2,198.82 148.63 326,810.62

c) Rock excavation M3 - 890.59

Overhaul for material hauled in excess


d) M3
of 1.5 km free-haul (normal overhaul)
8,795.28 65.85 579,169.19

Total Carried Summary 4,480,030.47


BASE, SUB BASE AND GRAVEL
5000
WEARING COURSE

Sub-base layer constructed from gravel


51.01
or Crushed stone:

DZ Compound Road Page 114


Project:--Engineering Collage Compound Road & Related Site Works
Work Item :-Compound Road
Client:- MoND
Consultant: -DCDE
Location:- Debrezeit

Spec.
Description Unit Quantity Rate Amount
Ref. No
200mm thick Gravel sub-base
(a)
(unstabilized gravel) compacted to:

(i) 95% of modified AASHTO density for


M3
the main road and walkways. 3,687.68 352.02 1,298,137.11

52.01 Base layer construction

(b) Crushed-stone base compacted to :

(i) 98% of modified AASHTO density of


M3
150mm thick for the asphalt road.
1,778.33 717.48 1,275,916.21

TOTAL 2,574,053.32
6000 BITUMINOUS SURFACINGS AND ROAD BASES
61.01 Prime coat:
(a) MC-30 cutback bitumen, (1Lit/m2) Lt 10,329.00 0.00 - pp

61.02 Asphalt Concrete Surfacing (50mm) M2 10,329.00 600.00 6,197,400.00 pp

Double Bituminous Surface


63C.01
Treatment Using

Double surface treatment

Double surface treatment using grade 1


chippings and 60/70 bitumnt binder
19mm and 9.5 mm chippings at
120m2/m3 per sq.m tendering and
actual application shall be as per
engineer order

DZ Compound Road Page 115


Project:--Engineering Collage Compound Road & Related Site Works
Work Item :-Compound Road
Client:- MoND
Consultant: -DCDE
Location:- Debrezeit

Spec.
Description Unit Quantity Rate Amount
Ref. No

i) Using 19.0mm aggregate for first


(b)
layer (0.013m3/m2)
M2 11,371.92 40.50 460,562.76

ii) Using 6.70mm aggregate for second


layer (0.005m3/m2) M2 11,371.92 36.18 411,436.07

i) Segmental paving (road pavment)


/cobble stone, 100x100x100mm in
size, sound basaltic rock or equivalent
as per engineer order including supply,
(c)
placing or laying to the pattern shown
as per the attachement or as may be
agreed by the engineer,compaction and
filler material
M2 11371.92 488.98 5,560,641.44

ii) 300x300mm coloured concrete tiles


2,235,556.20
of 50mm thick for walway M2 5540 403.53
Bedding (Cobble)

70mm thick crushed aggregate bedding


including transport supply, laying,
compaction and joint filling for both
road & walkway M2 16911.92 68.65 1,161,003.31
Total Carried to Summary -
96.03
Greenery works for median exist
between the two lanes roads, the price
includes all necessary civil works.
M2 15761.7 228 3,593,667.60 pp

Total Carried to Summary 3,593,667.60

Grand Total

DZ Compound Road Page 116


Project: 0 Location: 0 As per
Item no & activity: 1.10 Angle iron 40*40*3mm Daily out put: 15.00 pcs DCEE out
put

A . Material B. Manpower C. Equipment


Type Unit Qty Rate Cost per unit Type # U.F. Daily rate Daily cost (birr) # U.F. Rental rate Daily cost
(birr) (birr) (birr/hr) (birr)
angel iron pcs 1.05 0.00 0.00 Daily Laborer 1 1.000 0.00 52.00 Tools 1 8 0.00 0

Electrode & anti rust (20%) 0.50 Welder 1 1.000 0.00 135.20
forman 1 0.125 0.00 243.66

Total 'A' (birr) 0.00 Total 'B' (birr) 430.86 Total 'C' (birr) 0.00

1. Material Total "A" 0.00 2. Manpower Total "B" 28.72 3. Equipment Total "C" 0.00
Daily output Daily output
1. Direct cost (birr) = "1" + " 2 " + " 3 " 0.000
2. Profit and overhead cost (birr) = 30% 0.000

Total unit cost (birr) 0.00


engineering college compound road
Date
Page No.
ANALYSIS OF DIRECT COSTS

Item No. and Activity : Prime Mc-30 Daily output:

A. Material B. Manpower C. Equipment


Daily Cost
Type Unit * Qty Rate Cost per Unit Type No. U.F ** Indexed Daily Cost
(Birr)
Type No. Daily Hr

MC-30 liter 1.05 28.95 30.40 Daily Labour 8.00 1.00 0.00 0.00 asphalt distributer 1 8
Forman 1.00 0.25 0.00 0.00 stationary heater 1 8
0.00 Air compresser 1 8
water truck 4 8
hand tools 6 8

Total "B" 0.00 Total "C"

1. Material Total "A" 30.40 [Link] Total "B" Daily Output


0.00 [Link] Total "C"
Daily Output
1 Direct Cost ( Birr ) = "1"+"2"+"3" 0.00
2 Profit and Overhead Cost ( Birr ) = 30% 0.00
Total Unit Cost ( Birr ) 0.00
ANALYSIS OF DIRECT COSTS

Item No. and Activity : Asphalt production Daily output:

A. Material B. Manpower C. Equipment


Daily Cost
Type Unit * Qty Rate Cost per Unit Type No. U.F ** Indexed Daily Cost
(Birr)
Type No. Daily Hr

AC 80/100 lt 138 22.19 3062.22 batch plant Forman 1 0.50 0.00 0.00 Asphalt plant 1 8.00
Aggregate 02 m3 1.7 520.00 884.00 Labour 15 1.00 0.00 0.00 loader 1 8.00
Staionary heater 4 8.00
Welding machin 1 8.00

Total "B" 0.00 Total "C"

1. Material Total "A" 3946.22 [Link] Total "B" Daily Output


0.00 [Link] Total "C"
Daily Output

1 Direct Cost ( Birr ) = "1"+"2"+"3" 0.00

Item No. and Activity : Hauling Daily output:

A. Material B. Manpower C. Equipment


Daily Cost
Type Unit * Qty Rate Cost per Unit Type No. U.F ** Indexed Daily Cost
(Birr)
Type No. Daily Hr

Daily Labour 2.00 1.00 0.00 0.00 Loader 1 4


Dump track 4 8

Total "A" 0.00 Total "B" 0.00 Total "C"

1. Material Total "A" 0.00 [Link] Total "B" Daily Output 0.00 [Link] Total "C"
Daily Output
1 Direct Cost ( Birr ) = "1"+"2"+"3" 0.00

Average D/truck speed 30


Average hauling distance 30
Loading,unloading and manuovering 5
D/truck capacity 16
No. of trucks to be assigned 4.00
Efficiency factor 0.80
Time for one round trip 125.00
No. of trips per truck per hr 0.48
Material hauled per truck per hr 7.68
Total quantity of material to be hauled per day 196.61

Item No. and Activity : Placing Daily output:

A. Material B. Manpower C. Equipment


Daily Cost
Type Unit * Qty Rate Cost per Unit Type No. U.F ** Indexed Daily Cost
(Birr)
Type No. Daily Hr

Daily Labour 8.00 1.00 0.00 0.00 Asphalt paver 1.00 8.00
Pnuematic roller 1.00 8.00
Forman 1.00 1.00 0.00 0.00 wheel roller 3.00 8.00
level man 1.00 1.00 62.40 62.40 power broom 1.00 8.00
Water track 2.00 4.00

Total "B" 0.00 Total "C"

1. Material Total "A" 0.00 [Link] Total "B" Daily Output


0.00 [Link] Total "C"
Daily Output
1 Direct Cost ( Birr ) = "1"+"2"+"3" 0.00
hauling and borrow production 0.00
2 Profit and Overhead Cost ( Birr ) = 30% 0.00
Total Unit Cost ( Birr ) 0.00

0.00
4000 lit./day

Rental Rate Daily Cost


(Birr/hr) (Birr)

2201.02 17608.16
193.98 1551.84
401.80 3214.40
821.02 26272.64
2.00 96.00

48743.04

12.19
120 m3

Rental Rate Daily Cost


(Birr/hr) (Birr)

15802.41 126419.28
0.00 0.00
193.98 6207.36
0.00 0.00

0.00

0.00

196.61 m3

Rental Rate Daily Cost


(Birr/hr) (Birr)

0.00 0.00
- 0.00

0.00

0.00

km/hr
km
min.
m3

min.

m3
m3/day

3000 m2

Rental Rate Daily Cost


(Birr/hr) (Birr)

2,260.40 18,083.20
1,647.20 13,177.60
1,060.40 25,449.60
401.80 3,214.40
821.02 6,568.16

66,492.96

22.16
doubl brick manhole (1000×750 with the depeth of 1m)
MATERIAL TYPE UNIT QTY RATE TOTAL COST
25 cm thick brick m 2
8.4 612.26 5142.98
pit excavation m3 10.85 96.54 1047.46
lean concrete m2 0.75 71.9 53.93
back fill m3 9.27 100.79 934.32
cart away m3 1.58 77.17 121.93
10 cm ground floor m2 0.10 2352.18 235.22
formwork for pad m2 3.00 283.22 849.66
reinforcement kg 22 33.05 727.10
plastering m2 3 38.74 116.22
cover slabconcret m2 0.10 2352.18 235.22
TOTAL BIRR 9464.04
5.714286
51
187.5
0.342282

You might also like