F-QM-AR-001
BLOCK WORKS PROJECT:
LOCATION:
INSTALLATION DATE PREPARED: CONTROL NO.:
CHECKLIST
AREA/FLOOR LEVEL: INSPECTION DATE/TIME:
GRIDLINE/AXES:
CHECK THAT THE FOLLOWING COMPLY WITH APPROVED SUBMITTALS , FOR CONSTRUCTION DRAWINGS AND
TECHNICAL SPECIFICATIONS : :
Complied
PARTICULARS REMARKS
Y N
A. WALL MASONRY WORKS
1 First Floor
a. CHB unit size and strength complying, with no cracks
b. Layout based on approved plan
c. Reinforcing bars size, specification, splicing & spacing checked
d. All cells fully grouted according to approved mix
e. Stiffener columns and lintel beams checked if required
f. Vertical & horizontal alignment checked
f. Joint fillers properly installed were required
g. Plaster mix and plumbness checked
h. Proper location of embedded pipes, conduits, sleeves & elec'l
boxes checked
i. Checked for wavy surface; bush hammered & replastered
2 Second & Suceeding Floors
a. CHB unit size and strength complying, with no cracks
b. Layout & coursing as per plan
c. Vertical & horizontal alignment checked
d. Reinforcing bars size, specification, splicing & spacing checked
e. All cells fully grouted according to approved mix
f. Joint fillers properly installed were required
g. Plaster mix and plumbness checked
h. Proper location of embedded pipes, conduits, sleeves and boxes
checked
i. Checked for wavy surface; bush hammered & replastered
j. Random dye penetrant tested for welded joints
k. For verge angles securely and tightly fits precast panels
REMARKS
NOTE : This form must be submitted to The OPERATIONS, duly accomplished and signed by the corresponding Contractor's
Personnel-in-Charge at least 24 hours before actual INSPECTION.
PREPARED BY: INSPECTED BY: APPROVED BY:
( SubCon QA/QC Engr.) (NIA Project-in-Charge) (NIA Architect/Designer)
DISTRIBUTION : Subcon NIA Document Control
Revision No. :000 (Nov.22, 2024)