Tata Motors Supplier Quality Manual
Tata Motors Supplier Quality Manual
Version 1.0
©Copyright 2014 Tata Motors Ltd.
This document belongs to Tata Motors Ltd. and is of confidential nature. Reproduction, circulation or distribution of this
document in part or whole in any form without permission is prohibited.
TABLE OF CONTENTS
1. FOREWORD 1
2. TATA MOTORS POLICIES 2
2.1. Mission, Vision and Values 2
2.2. Quality Policy 3
2.3. Environment Policy 4
2.4. Safety and Health Policy 5
3. HOW TO USE THIS MANUAL 6
3.1. Document Access 6
3.2. AIAG Documents 6
3.3. Supplier Feedback 6
4. INTRODUCTION 7
4.1. Purpose 7
4.2. Scope 7
4.3. Responsibility 7
4.4. Records 7
4.5. General Requirements 7
4.5.1. Quality Requirements 7
4.5.2. Applicable Statutory and Regulatory Requirements 8
4.5.3. Product Safety 8
4.5.4. Laboratory Requirements 8
4.5.5. Specific Requirements 8
4.5.6. Tata Code of Conduct 8
5. TATA MOTORS PROCESS OF SUPPLIER QUALITY 9
5.1. Advance Quality 10
5.1.1. Potential Supplier Assessment 10
5.1.2. Sourcing Decision 14
5.1.3. Advanced Product Quality Planning 16
5.1.4. Pre-Production Meeting 18
5.1.5. World Class Supplier Quality 20
5.1.6. Production Part Approval Process-PPAP 21
5.1.7. Run at Rate 31
5.1.8. Early Production Containment 33
5.2. Current Quality 35
5.2.1. Continuous Improvement 35
5.2.2. Quality Workshop 36
5.2.3. SQ Process & Measures 37
5.2.4. Level I – Controlled Shipping (CS I) 40
5.2.5. Level II – Controlled Shipping (CS II) 41
5.2.6. Performance Monitoring 42
5.2.7. Improvement Meeting 43
5.2.8. Re-Sourcing 44
6. APPLICABLE DOCUMENTS 45
7. GLOSSARY OF TERMS 46
1
1. FOREWORD
We at Tata Motors have built our governance model on the principle of ACES –
Accountability, Customer & Product Focus, Excellence and Speed. The major focus, in
future, for our suppliers will be on quality of parts delivered to Tata Motors and customer,
robust manufacturing processes and comprehensive adherence to the APQP process
leading to WORLD CLASS QUALITY. To facilitate Supplier Engagement effectively we have
upgraded our existing 16 Step Supplier Quality Process and have prepared this common
Supplier Quality Manual.
Going forward we need to focus on: Flawless Product Launches & Continual Quality
Improvement. To address these objectives in a holistic manner we will deploy the 16 Step
Supplier Quality Process for New Part Development. The first 8 steps are the Advance
Quality phase. The objective of Advance Quality is to achieve robust product development.
Each of these steps shall be further cascaded into individual tasks. Steps 9 through 16 are
the Current Quality phase. The objective of Current Quality is to reduce variability and
improve process stability. We have internally trained all the Supplier Quality Engineers on
this process. This process will now become a way of life for our end to end Supplier
Management.
The Advanced Product Quality Planning process defines the steps that are necessary to
ensure that the PRODUCT and PROCESS meet Tata Motors requirement. Adherence to
APQP is required for all new parts. Suppliers Top Management support is critical to the
Success of APQP process. Establishing robust Quality Management Systems as well as
Product and Process Validations are equally critical to the Success of APQP process. We
are sure that you as an Automotive Supplier must be aware of these tools and processes
and many of you would already be practicing these.
Together we have to overcome many challenges. Suppliers have a vital role in reducing the
warranty failure rate, warranty costs and incoming PPM. Thus, suppliers have a key role to
play in improving our current position and overall Customer Satisfaction. This needs to be
addressed on topmost priority to enable us to achieve better results. We have to do it right,
first time and every time. We need to be mindful of our speed of responses. Innovation will
be the Key to our Sustainability & we at Tata Motors have a firm belief that “Together We
Can Do It”.
We look forward to your support in implementing these requirements and partnering with us
in our journey towards Process Excellence.
Warm Regards
Dilip Huddar
Head - Supplier Quality
SQMS
2
SQMS
3
SQMS
4
SQMS
5
SQMS
6
All our Supplier related transactions are through SAP, single server environment across all
the plants of Tata Motors in India.
Suppliers have been provided access through our intranet services called SRM. This is
compatible with SAP and suppliers can view Purchase Order details, schedules, status of
their quality acceptance of supplies, payments etc. along with other initiatives like quarterly
feedback on Supplier rating, rejection, warranty information and Tata Motors Standards
required by them at their premises.
The latest valid version of this Supplier Quality Manual is posted on the Tata Motors SRM
portal. [Link]
To access the manual, log on to the SRM portal using your Admin ID (Vendor code) and
password. After logging on, go to the “Supplier Manual” folder using the following path: Home
> Documents > Tatamotors > Message > SupplierQuality > Supplier Manual
SQMS
7
4. INTRODUCTION
The Tata Motors Supplier Quality Manual has been developed to document the quality
requirements with the following objectives:
Ensure flawless new part development
Assure that quality tools are utilized by suppliers in the development of and revisions
to their products, processes, and services
Provide a framework for sustaining and improving the quality of supplier products,
processes, and services
4.1. Purpose
The purpose of this document is to communicate to our suppliers the expectations of Tata
Motors and meet quality management systems requirements.
4.2. Scope
This document covers the details of Tata Motors Supplier Quality Process. Tata Motors has
developed 16 Step Supplier Quality Process, under Process Excellence Initiative (Pro-X).
This process is applicable equally to all suppliers and affiliated organizations that supply
parts, materials for production, pre-production, and/or services to the customer.
4.3. Responsibility
Suppliers shall utilize the latest revision of this Quality Manual and seek clarification from
their Tata Motors contact when necessary for items that are not identified or completely clear
in the manual. Tata Motors will continually improve and revise the contents of this manual.
4.4. Records
Suppliers shall maintain records of all required documents of this manual and shall be made
available to Tata Motors Supplier Quality Engineer upon request.
Supplier shall inform Tata Motors about changes in their QMS registration status, such as
new certificate, suspension, revocation or switchover to another certification body. Tata
SQMS
8
Motors expects its Tier 1 suppliers to manage the quality of their supplier base. Tier 1
suppliers should also ensure that their supplier base meets Tata Motors requirements.
SQMS
9
SQMS
10
Scope
This step is applicable to all Suppliers of production parts, raw materials, service parts, and
sourced products.
Activities
The PSA is part of Tata Motors supplier approval process and has the following tasks:
Key Stakeholder Meeting
PSA
Technical Review
Process
This step formally starts off APQP process with program review and identification of key
strategies in the Purchasing Process, through the Key Stakeholder Meeting. A
comprehensive RFQ package based on SOR (from the concerned stakeholders) is prepared
to ensure that all information necessary to receive equivalent bids is present.
Potential Suppliers are identified and tabled into the Preliminary Bid List. The suppliers are
assessed either on the Past Performance or Initial Supplier Assessment.
Suppliers who pass the PSA (Potential Supplier Assessment) or have approved Supplier
Performance in Integrated Supplier Rating (Source-able Category) are eligible to receive
RFQ. On submission of RFQ response, the Technical Reviews are evaluated to ensure
suppliers are technically capable of producing parts as per parameters set by Tata Motors.
Suppliers who have passed the Technical review and who have cleared the risk assessment
(Step 2) are eligible to receive new business, depending on the acceptance of their bids by
the purchase officer.
SQMS
11
Process Flow
INPUTS:-
3. Alternate
Source
4. Project Details
Preliminary Bid
List
Potential Supplier
Exit Fail Supplier Rating Poor Exit
Assessment (PSA)
RFQ RFQ
Package Package
Pass Approved
Technical Review
Timeline
Prior to Sourcing decision, before PSA
Output
Timely release of RFQ package with appropriate supporting documents
Process
The buyer invites the key internal stakeholders and conducts the KSM meeting as per the
agenda (This meeting is conducted for reviewing the potential bidders list and contents of
the SOR).
SQMS
12
Timeline
Prior to Sourcing Decision, before Technical Review
Output
Risk assessment Status – Pass or Fail
Process
The SQE receives the potential bid list from the buyer.
In case, the Supplier has active business, the SQE reviews the Supplier Rating to
verify that supplier meets the required criteria before proceeding towards Technical
Review.
If the supplier is not engaged in active business, the SQE proceeds towards PSA.
The supplier supports the SQE in conducting the PSA by providing all
documents/necessary support in a timely manner.
If the supplier has achieved satisfactory Score in each of the 5 parameters, the
supplier is qualified for technical review.
SQMS
13
Timing
Prior to Sourcing Decision
Output
Identification of capable suppliers
Supplier Responsibilities:
Suppliers must review information in the SOR and produce upon information as requested
by the Tata Motors SQE:
Adherence to Tata Motors Quality Requirements, including but not limited to:
– Adherence to ISO/TS 16949 Systems.
– Adherence to requirements mentioned in AIAG documents
– WCSQ Requirements
– Production Support Requirements
– Continuous Quality Improvement
Preliminary Timing Charts
– Highlight concerns related to tooling, gages & fixtures, and/or testing that may
impact PPAP.
– Detailed list of (proposed) changes to the manufacturing facility, including
Greenfield and brownfield plans.
– Optimized and dedicated resource deployment to successfully complete the
APQP project; including competency mapping and training requisite to
complete the tasks.
Suppliers should have Preliminary process flow diagrams, PFMEA and Control Plan.
– The suppliers must specifically list down all information that is material,
including but not limited to special assembly techniques, test methods
(including EOL testing, functional and compliance testing), and containment
procedures deployed.
Capability Studies on similar parts (Commodity) and tolerances:
– Error Proofing systems, MSA studies, SPC, EPS mechanisms and their
record keeping is included.
– Plan to meet warranty targets (Review open PRRs, existing warranty action
plans and data on similar parts/aggregates)
Present process and resource plan for evaluation and management of sub-
contracted/tiered suppliers.
Respond to the assessment and observations and where applicable identifying
countermeasures to be taken.
Provide evidence of product experience or technical expertise relevant to the new
product.
SQMS
14
Scope:
All parts under development
Activities:
Risk Assessment
Process
To receive new business, the supplier’s manufacturing location must be aepproved on the
Tata Motors Preliminary Bid List for Quality in the specific commodity
Suppliers clearing the Technical Review and qualifying the risk evaluation criteria will be
eligible for consideration in the sourcing process.
Timing
Prior to Sourcing Decision (Sourcing Recommendation Table)
Output
Completed APQP Supplier Assessment
Supplier Responsibilities:
Provide necessary information and support audit requests.
SQMS
15
Legend
R – Responsible; A – Approve; S – Support; I – Inform
Note: Unless otherwise specified, APQP will be supplier monitored.
SQMS
16
Scope:
All new parts under development
Activities:
APQP enlists 3 core activities within the step, namely:
APQP Project Plan
APQP Timing Chart
APQP Kick Off Check sheet1
Output
APQP Open Issues List
Updated APQP Timing Chart
Process
The APQP project plan is developed in accordance with the recommendation of AIAG APQP
manual, listing the various activities in line with Tata Motors NPI DR Gates /Milestones. The
type of Product, complexity and project expectations are considered in selecting the timing
elements that are planned and charted. Each event has a “start” & “completion” date along
with the actual point of progress recorded. APQP process is then formally kicked off (APQP
Kick Off) for the various projects.
The reviews are conducted by Tata Motors for all parts that are designated as
Customer monitored APQP during Step 2.
For supplier monitored APQP parts, the supplier reviews and updates the timing
charts and Open issue lists throughout the APQP Process. Supplier must update all
information pertaining to Product Quality and Timing to the concerned SQE.
Note:
The timing chart is developed in accordance with principles of Critical Path Method
(CPM), Gantt chart, and is driven by the principles of simultaneous engineering
performed by product and manufacturing engineering activities working concurrently.
Each project plan will be different depending on the project program and the part.
The APQP Timing chart will be continually referenced and reviewed throughout the
Product Development Cycle.
APQP project planning facilitates communication between the supplier and customer
(Tata Motors) to clarify requirements that translate into more detailed specifications.
1
APQP_KickOff.pdf
SQMS
17
Suppliers prepare component specific timing chart in line with the APQP Project Plan
(Master Timing Chart) considering development along the entire supply chain
(including Sub Contractor Development).
Supplier Responsibilities
Create an APQP Timing Chart or equivalent and track tasks to completion in line with
chart.
Suppliers should use APQP as a tool to support process development2:
– To develop and execute an APQP Plan for flawless product launch.
Launch of new components intended for regular production.
Development of new manufacturing processes
Significant changes to existing products or process
– Regularly update the progress of product development based on their APQP
plan and share the same with customer (Tata Motors) teams.
Suppliers are required to adhere to APQP Timing Chart.
– Create an APQP Open Issues and monitor the same throughout the program.
Utilize APQP Open Issues list to capture all issues requiring action.
– Update timing chart as timing changes occur and communicate any changes,
concerns and issues to SQE.
Develop recovery plans for issues impacting quality and timing and
drive the plan to maintain program timing
Any timing changes by the customer (Tata Motors) have to be
adequately communicated downstream.
– Sub-component (tier II) milestones shall be pulled ahead of the Supplier’s
assembly milestones to protect Tata Motors program timings.
Chart
Prototype Pilot / Pre-Launch Launch /
Planning Production
AIAG APQP Product Design and Development
PHASES Process Design and Development
Product and Process Validation
Feedback, Assessment and Corrective Action
PO+4w eek Alpha Build Beta build PO/PP PL SOP
GR-1
GR-2
GR-3
GR-4
Gate Sourcing
# APQP Task Reviews Activities
14 PPAP GR-4 o o
Plan Capacity Analysis Capacity Analysis Conduct Run@Rate
15 Run @ Rate GR-1,2,3,4 o o o o o o o
2
Refer AIAG APQP Manual
SQMS
18
Scope
All activities covered under the APQP process.
Activities
Pre-Production Meeting marks the start of activities which are conducted periodically
throughout the APQP cycle to evaluate progress of various activities in a structured manner.
Tata Motors SQE will be scheduling these Gate Reviews with Supplier.
Process
SQ Gate Reviews are conducted prior, preferably 1-2 weeks, to Project DR Gate
Reviews.
Pre-Production Meeting entails the first Gate Review (GR1) should be completed
within 4 weeks after the release of PO.
– Subsequent Gate Reviews are aligned with the vehicle built for each
component.
Completion of all activities as mentioned in the APQP Gate Review Chart, ensures
qualification to next level, else the progress takes a step back to a prior level.
Timeline
Completed prior, preferably 1-2 weeks, to Project DR Gate Reviews.
Output
Updated APQP Open Issues List
Progress of Project – Completed documents of all required activities
Gate Clearance Status
100 % Interim Saleable along with minimum 75 % Fully Approved PPAP Status at
time of pilot production.
100% WCSQ compliance before PPAP approval.
– WCSQ compliance will be considered as a pre-requisite for fully approved
PSW.
Minimum 90% Run @ Rate at SSF (Start of System Fill)
Supplier Responsibilities
Ensure completion of required activities as per APQP plan at various gates.
SQMS
19
Review the completion status of actions required for compliance to SQ SOR3 and
Part Specific SOR, Lessons learned.
Ensure lessons learned are captured adequately in the FMEAs or Control Plans.
Validate capability studies and RPN reduction plans to satisfy Tata Motors design
specifications and quality requirements.
Validate capacity/plan vs. capacity required by Tata Motors.
Identify and communicate key issues in adhering to the APQP timing chart to Tata
Motors management.
Co-ordinate the gate reviews after APQP kick-off. For Supplier monitored parts, the
supplier must conduct the APQP Gate reviews and periodically report the same to
Tata Motors SQE.
Complete the gate reviews with sub-contractors (Tier II to Tata Motors), at least 6
weeks prior to Tata Motors gate reviews to protect Tata Motors project timing. Inform
Tata Motors SQE, in case of any discrepancy or non-conformation.
Protect Tata Motors program timing and objectives by adhering to the APQP charts.
– In case of deviation, prepare comprehensive recovery plans and submit the
same to Tata Motors SQE.
– Track all open APQP issues and report any concerns to Tata Motors SQE,
immediately.
Chart
3
Refer SQ_SOR.pdf
SQMS
20
Scope
WCSQ applies to all Suppliers partnering and/or engaged in business with Tata Motors.
Timeline
Gate 1 (Gap Analysis)
Gate 4 (Compliance, before PPAP)
Output
Action Plan for WCSQ compliance – Gate Review 1
Full Compliance with WCSQ audit – Gate Review 4
Activity
The activity has the following 10 key elements
1. Quick Response Teams
a. Quick Response Process
b. Problem Solving
c. Lessons Learned
2. Control of Non-Conforming Product
3. Quality Gate
4. Standardized Operations
5. Standardized Operator Training
6. Error Proofing
7. Layered Process Audits
8. RPN Risk Reduction (Reverse FMEA)
9. Contamination Control
10. Supply Chain Management
Supplier Responsibilities
At the WCSQ Gap Analysis audit, provide action plans with appropriate detail, timing,
ownership, etc.
Implement and verify effectiveness of all the action plan items before Supplier Gate
Review 4.
Keep the customer (Tata Motors) updated regarding implementation status and any
issues or concerns with implementation.
Note: WCSQ compliance is a compulsory requirement to qualify the eligibility criteria to
receive new business.
SQMS
21
Scope
Applies to all supplier sites supplying Production parts, service parts, production
materials or bulk materials.
o For bulk materials, refer to the Bulk Materials Checklist4.
Suppliers supplying standard catalogue parts (e.g. Bolts, nuts etc.) shall comply with
PPAP, unless otherwise specified by the authorized Tata Motors SQE.
PPAP Requirements5
Design Record
Authorized Engineering Changes
Customer Engineering Approval
Design FMEA
Process Flow Diagrams
Process FMEA
Control Plan
MSA Studies
Dimensional Results
Records of Material/Performance Test Results
Initial Process Studies
Qualified Laboratory Documentation
Appearance Approval Report
Sample Production Parts
Master Sample
Checking Aids
Customer Specific Requirements
Part Submission Warrant (PSW)
Timeline
Initial chart–prior to sourcing, reviewed at Gate 2 and Gate 3, and completed in PPAP.
Output
Process Flow Chart (depicting Sub component system)
4
AIAG PPAP Manual, Appendix F
5
Refer AIAG PPAP Manual, Section 2 – PPAP Process Requirements
6
Refer [Link]
SQMS
22
Supplier Responsibility
Create a preliminary process flow chart using a similar process as part of response to
RFQ package requirement.
Define a production flow chart once product design is released.
Document all items in the flow chart with the respective nomenclature (store, move,
inspect, correct, etc.)
Ensure the process flow chart is linked to the PFMEA and control plan
Update flow chart to reflect actual production process.
Communicate any changes on an ongoing-basis to SQE.
Timeline
As per APQP Project Plan
Output
Defined and measurable Classification of Characteristics (CTQ)
Appearance, performance and material testing specifications
Geometric Dimensioning & Tolerancing (GD&T)
Supplier Responsibility
Confirm the manufacturing process can achieve the specified tolerances on a
sustained basis.
Any recommendations / improvements to the design record are documented and
submitted to Tata Motors for approval.
Communicate any concerns related to the CTQ cascade Designators or GD&T
scheme and the manufacturability of the part. Document any open issues on the
APQP Open Issues List
Develop an understanding of the engineering change process with the Tata Motors
ERC Engineer. Refer Design Review Check sheet7 and address any open action
item.
Note: Where the design record is in electronic format, e.g., CAD/CAM, the Supplier
shall produce a hard copy.
7
Refer Design_Review_Chk.xlsx
SQMS
23
Output
DFMEA document8 and cascade DFMEA to sub-component level DFMEA.
Supplier Responsibilities:
The supplier needs to create and submit the DFMEA if it is design responsible.
The DFMEA document should be maintained throughout the life of the product and
updated and revised prior to any engineering changes. Changes in part level DFMEA
should be communicated to Tata Motors for updating system level DFMEA.
Supplier must address and identify all Tata Motors special characteristics as given in
TS11413 standard.
The DFMEA shall be ranked based on AIAG guidelines for Severity, Occurrence and
Detection Ratings.
Timeline
Starting at APQP Kick-Off Meeting and complete by PPAP.
Outputs
PFMEA9
RPN Reduction Summary
Supplier Responsibilities:
Review and update PFMEA each time a design change is made or a Process change
is implemented. All potential areas for failure are included in the PFMEA and
appropriate corrective actions are planned and implemented.
8
Refer [Link]
9
Refer [Link]
SQMS
24
Timeline
Starting at Tooling Kick off Meeting till PPAP approval
Outputs
Process capable Tooling and Equipment delivered on time as per APQP Project Plan.
Supplier Responsibilities:
The supplier should review and inform Tata Motors about any changes in the original
project timing.
The supplier must participate in Tata Motors design reviews to incorporate Tata
Motors requirements and special characteristics in the tooling or equipment.
Design, build and obtain certification of and validation of tooling and equipment as
per latest CAD data.
Participate in design reviews with Tata Motors and ensure GD&T, CTQ Cascade
requirements are included in the tooling, equipment and functional test design. Also
ensure tooling and equipment will produce parts consistently to meet process
capability requirements.
The supplier should inform Tata Motors about any design and process changes
regarding any new or modified tools, rearrangement of existing tooling or equipment,
any product or process changes impacting fit, form, function, performance and
durability of saleable product, any test/inspection methods and any new facilities.
Prior to tools being grained, dimensional verification is required by Tata Motors and
Grain Approval to be signed off.
10
Refer RPN_Red_Sum.xlsx
SQMS
25
Ensure PFMEA has been comprehended and incorporated into tooling and
equipment design.
Timeline
To be completed by PPAP Approval
Outputs
Approved Gage Prior to PPAP.
Supplier Responsibility
Identify gage requirement as per CTQ cascade mentioned on drawing.
Review timing to ensure compliance and inform Tata Motors SQE about any changes
from original project timing, any design and process changes, any new part math
data and/or GD&T changes, any test/inspection methods that include gages, any
new facilities that would house the gages.
Participate in design reviews, ensure GD&T scheme is released and relevant CTQ
cascade parameters are incorporated into final gage design.
Design, build, certify gage dimensionally (including a third party certification), perform
complete AIAG MSA (GR&R and Bias study) and meet all requirements as per Tata
Motors fixture standards.
The supplier shall conduct and document Gage R&R studies upon receipt of new or
repaired measuring equipment.
Timeline
Starts with Initial draft at APQP Kick Off, supplier shall update parallel PFMEA changes
prior to PPAP.
Output
Control Plan11
Individual Process Control Charts for all CTQ cascades (FMASOW)
11
Refer Control_Plan.xlsx
SQMS
26
Supplier Responsibilities:
Incorporate necessary inputs from PFD, PFMEA, Lessons learned, warranty data,
PRRs on similar parts and manufacturing process capability on similar parts.
Supplier should maintain the control plan throughout the life of the product.
The control plan must be approved by a cross functional team at supplier’s end. It
may be reviewed by Tata Motors depending upon the component.
The supplier must identify and address all Tata Motors special characteristics on the
control plan.
The supplier should communicate any changes in control plan to Tata Motors
The supplier should conduct frequent audits to check the implementation of controls
in the control plan.
Timeline
As per APQP timing Chart
Output
Completed PPAP documents, PSW
Submission Levels
The supplier shall submit the items and/or records specified in the level identified below:
SQMS
27
•PSW with product samples and complete supporting data reviewed at the
Level 5 supplier’s location.
Legend
S – Supplier shall submit to Tata Motors and retain a copy of records or documentation
items at appropriate location
R – Supplier shall retain at appropriate locations and make readily available to Tata Motors
upon request.
* – Supplier shall retain at appropriate locations, and submit to Tata Motors upon request.
Tata Motors will determine what is needed for submission.
SQMS
28
Full Approval
PSW signed off as approved and all open issues are closed13.
For Bulk Materials, supplier shall use the Bulk Materials Approval Form, AIAG PPAP
Manual, Appendix F.
For tires and Commercial Vehicles (truck industry), suppliers shall refer the AIAG
PPAP Manual, Appendix G and H respectively.
Interim Saleable
Permits shipment of parts for a given time or quantity, whichever is less.
Interim approval is granted when the supplier has prepared and submitted an
approved action plan to the Tata Motors SQE and is valid till POPP batch.
If the PPAP is not re-submitted within the time frame of Interim Saleable status
(unless otherwise specified by the Tata Motors SQE), PPAP is rejected.
– If the PPAP submission date is extended beyond the time frame, approval
from SQ Head and Design Engineering Head shall be taken.
Reject
PPAP submission does not meet Tata Motors defined requirements based on the
production lot and/or accompanying documentation.
Document submission and/or process correction is required.
Parts will not be shipped before submission of approved/Interim Saleable PPAP.
Process
PPAP activities (DFMEA, PFMEA, MSA studies etc.) are conducted concurrently, as per the
APQP timing charts. Evaluation of the significant production run is done after all issues
identified in EPC station (Step 8) are resolved.
For Production parts, product for PPAP shall be taken from a significant Production
Run. A significant production run is of at least 8 hours of continuous production or a
production quantity of at least 300 consecutive parts, unless otherwise specified and
approved by Tata Motors SQE.
– For bulk materials, supplier shall refer to AIAG PPAP Manual, Appendix F.
– For tires, unless otherwise specified by Tata Motors SQE, size of significant
production run is 30 tires. PPAP is derived from 8 hours of tire curing from the
approved production process as specified in the control plan.
– For parts developed for commercial vehicles (Truck Industry), guidelines as
referenced in Appendix H of AIAG PPAP Manual, are applicable, unless
otherwise stated by Tata Motors SQE.
– This production is conducted at the production site, at the production rate,
using the production tooling, process, materials and operators. Parts from
each production line e.g., duplicate assembly line and/or work cell, each
13
Refer APQP_OpenIssues.xlsx
SQMS
29
SQMS
30
Timeline
Throughout new part development
Output
DFMEA & PFMEA and other PPAP Documents updated with Lessons Learned
Part-Specific SOR for key commodities updated with Lessons Learned throughout
the APQP process.
Supplier Responsibility
Lessons Learned Update
– Review solutions to issues identified in the Kick-off meeting and new items
added to the list in various builds till launch.
– As solutions are identified, DFMEA, PFMEA, Flow Chart, and Control Plan
are reviewed and updated.
Contribute with additional lessons learned based on knowledge of the commodity.
Adhere to the updated SOR.
Place a formal process to update FMEA and control plans based on Lessons
Learned.
SQMS
31
Scope
All Suppliers of production parts, service parts, and sourced products that have PPAP
submission status as “saleable” or “fully approved”.
Timeline
Upon PPAP approved Status.
8 weeks prior to start of production.
Output
• Completed R@R Capacity Workbook and R@R for each part
• Supplier meets Daily Contract Capacity
Process
R@R is carried out once the PPAP has been submitted as mentioned in scope above. The
SQE verifies that Tata Motors Lean Capacity Requirement14< = Quoted Tool Capacity15
Supplier Responsibility
Develop a R@R plan and provide to the SQE at the Gate 1 APQP Kick-Off meeting.
Complete the Capacity Workbook (Manufacturing Flow Diagram, Shared Capacity
Sheet(s), and Manufacturing System Capacity Estimate) and submit to the SQE prior
to the Gate 3 APQP Review.
The capacity analysis must show satisfactory results prior to ordering tooling and
equipment.
Ensure understanding of the R@R “PASS” performance metrics.
Conduct preliminary R@Rs and/or simulations prior to the planned R@R to confirm
readiness. The PPAP run of parts will be one of the trial runs.
Complete verification for all subcontractors, and submit prior to the R@R.
Completely fill the R@R Hourly Count Sheet during the R@R for both the final
operation and the constraint operation.
Completely fill the Capacity Workbook for all R@Rs and forward to the SQE
14
Daily Production Requirement
15
QTC as mentioned in the Tata Motors Purchase Order
SQMS
32
Process Flow
Escalate any
Missing PO
information
GR 3 Meeting and
Is Run @ Rate
Yes R@R Kick off Meeting escalate any missing
Required
supplier information
No Supplier completes
PFD, Shared
Capacity Sheets.
Exemption
from SQ Head
Status:-
Exempt Supplier
TML or Supplier Conducts
TML
monitored APQP Prior R@R
Supplier
R@R
R@R Status?? Pass
Complete
Fail
Supplier updates
APQP Open Issues
List.
SQMS
33
Scope
EPC station is to be established for all parts that require PPAP approval from Tata Motors.
Timeline
EPC will start from first off tool sample to meet Product and Process Validation Phase
Output
EPC Control Plan audit
Supplier Responsibilities:
Supplier should demonstrate compliance to requirements mentioned in SQ-SOR for EPC but
not limited to the following:
Implement EPC with entry date, exit criteria, and exit date as defined by Tata Motors
SQE.
Establish EPC containment stations, which must be off-line, separate, and
independent check from the normal manufacturing process and located at end of
process.
Verification of the effectiveness of error proofing.
Immediate implementation of containment and irreversible corrective action when
non-conformances are discovered in the EPC containment area or at the receiving
location.
Exit Criteria
For a Supplier to exit from the EPC firewall, the manufacturing process should be error free
for 21 consecutive days after observation of the problem, subject to minimum 3 months of a
firewall stationed installed at the supplier end.
SQMS
34
Process Flow
No EPC
Is PPAP Required No
Required
Yes
Implement additional
Supplier develops EPC
checking provisions. Inform
plan
Tata Motors SQE
Timeline : minimum 3
months after SOP
No
Yes
EPC Exit
SQMS
35
Scope
Continuous Improvement applies to all suppliers of Tata Motors and is applicable even when
Tata Motors has not requested data and/or product characteristics have not been called out
in the design record.
Supplier Responsibility:
All suppliers are required to have quality systems in place that ensures parts shipped to Tata
Motors meet specification. Suppliers are also expected to have a system to:
Properly identify the root cause of non-conformities
Prevent recurrence of non-conformances across their operations.
Effective Problem Solving (EPS) process in place to identify the root cause on a
timely basis, and implement and validate the corrective actions.
Lessons Learned process: Suppliers are required to have a documented and
effective process in place to drive lessons learned into current and future application
of FMEAs and Control Plans.
SQMS
36
Scope
Proactive – All Suppliers of legacy parts; Enhance supplier’s QMS.
Reactive – Exit Criteria for all Controlled Shipping Process / Top Focus
Process
WCSQ is a 2 day workshop that develops and facilitates implementation of 10 basic
strategies of WCSQ16.
A WCSQ Audit will be conducted by the Tata Motors SQE to gage need for Quality
Workshop.
Supplier provides detailed time bound action plan to the Tata Motors SQE
highlighting the updates on a weekly basis.
16
Refer Step 5 of Pro-X SQ 16 Step Process
SQMS
37
Scope
This process is to be used for all pre-production, production, service and accessory part
requirements.
iii. Engineering
Engineering PRR’s may be issued to design responsible suppliers to document design
related concerns.
iv. Indirect
An Indirect PRR may be issued to document a supplier responsible problem caused by a
non-production supplier (tooling, equipment repair parts, capital equipment, etc.) at the
customer plant. This would include scheduled work activities that cannot be completed due
to the supplier’s failure to meet prior delivery commitments.
SQMS
38
v. Packaging
A Packaging PRR is issued when Tata Motors has verified that the supplier caused a
packaging non-conformance, which could result in part damage or affect the sale-ability of
the part.
vii. Shipping
A Shipping PRR should be issued when the customer has verified that a shipping or
scheduling-related nonconformity was caused by the supplier.
Supplier Responsibilities
Acknowledgement
The supplier shall acknowledge the PRR by an email reply and initiate initial response
(containment) within 24 hours.
Final Response
The supplier shall provide a final response within applicable number of days as mentioned in
SRM PRR portal. The final response shall include at a minimum:
Containment and preventive actions taken and evaluations/success of the results
thereof
Root cause of the problem, including methods used to identify the root cause.
SQMS
39
Major Disruption
Major Disruptions are tracked by the issuance of PRR’s.
A problem that affects multiple plants is considered one Major Disruption.
A problem that could be classified as more than one type of Major Disruption shall be
issued under one PRR with one type of Major Disruption.
PPM for a supplier code is calculated monthly using the following formula:
1. Total all the “actual quantity nonconforming” for all part numbers for that location
2. Divide by total receipts for that location
3. Multiply by 1,000,000.
Timeline
Throughout the line of the product
Output
PCPA Audit Summary
Supplier Responsibility
Extend full support for the PCPA audit.
Implement any immediate containment/addition process controls as directed.
Develop, document, and provide action plan with appropriate detail, timing,
ownership, etc.
Implements action plan on a timely basis.
SQMS
40
Scope
All Suppliers of production parts, raw materials, service parts, and sourced products with
below listed issues may fall under the purview of CS 1.
Repeat and/or non-conforming PRRs
Severity of the problem
Field Issues (Warranty, JD Power etc.)
Note: The above mentioned reasons are not exhaustive and the final decision will be taken
by Tata Motors.
Timeline
Suppliers may be placed in CS1, as per several criteria defined in the scope of the step
Output
Certified Material to the Customer facility.
Additional process controls to prevent future occurrences.
Corrective Action Report from Supplier
Supplier Responsibilities:
Establish a separate CS 1 area at the manufacturing location
Notify additional Tata Motors facilities that use the same part, inform them of the
nonconformance, and provide containment activities as necessary.
Mark individual parts, material, and containers, with CS 1 tags, to identify parts CS1
certified to be used in Tata Motors assembly/operations
The supplier, simultaneously, implements an Effective Problem Solving Process
(EPS), and isolates Tata Motors from the receipt of nonconforming parts/material.
Perform a redundant inspection of all suspected non-conforming products as per the
agreed upon process, and ensure defect free parts/material are delivered.
Develop, implement and validate the permanent corrective and/or preventive actions,
along with improved process controls
Meet the defined exit criteria as mentioned in the SRM portal.
SQMS
41
Scope
A CS2 may be raised due to any of the following parameters:
Repeat PRRs
Severity of the problem
Ineffective Level 1 Controlled Shipping
Field issues (Warranty, JD Power etc.)
Timeline
Suppliers may be placed in CS 2, as per several criteria defined in the scope of the step
Activities
Certified Material (with CS 1 tag) to the Tata Motors facility.
Problem solving capability to establish root cause.
– Documented and verified Corrective Action.
– Additional process controls to prevent future occurrences.
Supplier Responsibility
Supplier contacts a Controlled Shipping 3rd party provider.
o SQE should receive a copy of the same when appropriate.
Supplier performs a redundant inspection of all suspect nonconforming products as
per the agreed upon process to ensure defect free parts (CS1). CS1 is a separate
and independent inspection process from CS2
The 3rd Party Provider performs an additional redundant inspection of all suspect
non-conforming products as per the agreed upon process to ensure defect free parts
are delivered to Tata Motors.
SQMS
42
Scope
All Suppliers of production parts, raw materials, service parts, and sourced products.
Timeline
Every quarter for all suppliers
Output
Timely release of Supplier Performance rating
Process
The supplier is rated on certain parameters and his Quality Performance Reports are
generated. Similarly the sourcing metrics are generated classifying the supplier as approved
or low performing supplier. These reports will be available to the supplier via the SRM portal
and updated every quarter.
SQMS
43
Scope
All Suppliers of production parts, raw materials, service parts, and sourced products.
Activities
Top Focus
Timeline
Complete Product Life-cycle
Output
Process Control Plan Audit (PCPA)
Step Down Chart
Supplier Responsibilities
Commit resources and participates in Quality Workshop (as requested).
Performs a detailed analysis of the Supplier Performance Reports
Develop a Quality Improvement Plan
Track implementation of the initiatives and resulting quality improvements.
SQMS
44
5.2.8. Re-Sourcing
Purpose
Re-Sourcing step is included in Pro-X 16 Step SQ Process to protect and mitigate risk to
Tata Motors from engaging in business with poorly performing suppliers.
Scope
All Suppliers of production parts, raw materials, service parts, and sourced products with
poor performance
Process Flow
Resourcing /
Exit
No
New
Business
D/E Supplier Quality PRR Improvements
Hold
Yes
Process
Suppliers with continuous quality problems may be placed on New Business Hold (NBH) or
Tata Motors may proceed to resourcing if the following criteria are met:
Repeat of major disruptions: downtime, part shortage, tool/process change etc.
Lack of ISO/TS16949 certification
Continuous Poor performance
Continuous Customer Satisfaction PRR’s
SQMS
45
6. APPLICABLE DOCUMENTS
Document path:
Log on to [Link] using your Admin ID (Vendor Code) and password.
Go to the “Documents” folder using the following path: Home > Documents > Tatamotors > Message
> SupplierQuality > Supplier Manual
SQMS
46
7. GLOSSARY OF TERMS
SQMS
Tata Motors facilitates access to its Supplier Quality Manual through its SRM portal, where the latest valid version is posted. The suppliers can access the manual by logging into the SRM portal using their Admin ID and password. The portal provides additional resources, such as Tata Motors' SQ Pro-X format references and links to AIAG documents, which suppliers can order for further details. These resources help suppliers understand and comply with Tata Motors’ requirements, ensuring they are adequately equipped to meet quality standards .
Tata Motors' Supplier Quality Manual organizes the process of achieving supplier excellence into two main phases: Advance Quality and Current Quality. Each phase is further divided into 8 steps, making a total of 16 steps. The Advance Quality phase aims to achieve robust product development and includes steps 1-8, which cover potential supplier assessment, sourcing decision, advanced product quality planning, pre-production meeting, and production part approval process among others. The Current Quality phase focuses on reducing variability and improving process stability, covering steps 9-16, such as continuous improvement, quality workshop, performance monitoring, and possibly re-sourcing .
Tata Motors integrates supplier feedback into its Supplier Quality Manual through a dedicated communication process that encourages suppliers to provide improvement suggestions. This feedback can be sent via email to a specified address. Incorporating supplier feedback is significant because it allows for continuous improvement of the Supplier Quality Manual, ensuring it remains relevant and effective and accommodates the practical experiences and needs of suppliers. This approach fosters a collaborative environment where suppliers feel involved and acknowledged, potentially leading to more efficient and effective supplier quality processes .
Innovation is a key pillar in Tata Motors' strategy, integral to their pursuit of process excellence and sustainable growth. In the context of supplier quality management, innovation drives the development of advanced processes and tools that enhance quality and efficiency. It encourages suppliers to implement forward-thinking solutions that address potential challenges before they arise, fostering a proactive approach to quality management. Tata Motors' emphasis on innovation aligns with their goal of flawless product launches and continuous improvement, ultimately improving customer satisfaction and reducing costs associated with warranty failures and defects .
Quality Gate is a crucial element in Tata Motors' Supplier Quality Management as it serves as a checkpoint that helps in evaluating the quality and compliance of a supplier's processes and products at different stages of production. It contributes to supplier performance by ensuring that any issues are identified and addressed early in the process, thus preventing defects from reaching the customer. This process involves standardized operations, controlling non-conforming products, and addressing risks through measures like root cause analysis and corrective actions. Quality Gates enforce a systematic approach to maintaining high quality, thereby enhancing supplier reliability and performance .
The Advanced Product Quality Planning (APQP) process is vital in Tata Motors' Supplier Quality Manual as it lays the foundation for ensuring that products and processes meet Tata Motors' requirements. It emphasizes robust Quality Management Systems, product and process validations, and the engagement of suppliers' top management. APQP aims to support flawless product launches and continuous quality improvement by involving suppliers in tasks like design reviews, FMEA, and process improvement activities. This process is essential for new parts, requiring adherence to specific quality practices and management strategies by suppliers .
Tata Motors ensures supplier adherence to statutory and regulatory requirements by mandating compliance as a part of their general quality requirements. Suppliers are expected to comply with all relevant regulations and laws governing their operations and products. Tata Motors conducts periodic assessments or audits of suppliers' Quality Systems to verify compliance and expects suppliers to take timely actions to address any identified non-compliance issues. Suppliers are also required to inform Tata Motors about any changes in their QMS registration status, including the acquisition of new certificates or changes in certification bodies .
Suppliers are responsible for creating a preliminary Process Flow Diagram (PFD) as part of the response to the RFQ package. They must develop a production flow chart once the product design is released, ensuring it is linked to the PFMEA and control plan. Additionally, suppliers are required to update the flow chart to reflect the actual production process, document all items in the chart, and communicate changes to Tata Motors' Supplier Quality Engineer. These responsibilities ensure that there is a clear and documented understanding of the manufacturing processes, which is crucial for maintaining quality standards and facilitating process improvements .
DFMEA is a significant component of Tata Motors' supplier quality process as it helps predict potential failures in product design, evaluate their effects, and implement mitigation plans to minimize risks. DFMEA aids in achieving product performance, reliability, and safety goals before manufacturing begins. Suppliers are responsible for creating and maintaining the DFMEA document throughout the product's life, updating it with any engineering changes, and communicating part-level DFMEA changes to Tata Motors. Suppliers must address Tata Motors' special characteristics as specified in the TS11413 standard and rank DFMEAs based on severity, occurrence, and detection ratings according to AIAG guidelines .
The Production Part Approval Process (PPAP) is crucial in Tata Motors' Supplier Quality Management as it provides evidence that the supplier understands Tata Motors' engineering design record and specification requirements. It ensures the manufacturing process can consistently produce conforming parts during actual production runs. Key components of PPAP include Design Record, Engineering Changes, Customer Engineering Approval, Design and Process FMEA, Control Plan, Measurement System Analysis (MSA) Studies, Dimensional Results, and a Part Submission Warrant (PSW) among others. The PPAP process applies to all supplier sites supplying production and service parts, and it includes additional documentation such as Process Flow Diagrams and Control Plans .