Jan - 2024 - BS Power Ministry

The Broad Status Report for January 2024 details the progress of thermal power projects under construction in India, highlighting a total thermal capacity addition of 2,624 MW during the fiscal year 2023-24. The report outlines the achievements against targets set for various sectors, including central, state, and private, and provides insights into the challenges faced by these projects. Additionally, it includes a comprehensive overview of installed capacities and future targets for thermal power generation in the country.

Uploaded by

sahil.joshie
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
211 views56 pages

Jan - 2024 - BS Power Ministry

The Broad Status Report for January 2024 details the progress of thermal power projects under construction in India, highlighting a total thermal capacity addition of 2,624 MW during the fiscal year 2023-24. The report outlines the achievements against targets set for various sectors, including central, state, and private, and provides insights into the challenges faced by these projects. Additionally, it includes a comprehensive overview of installed capacities and future targets for thermal power generation in the country.

Uploaded by

sahil.joshie
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

BROAD STATUS REPORT

OF
UNDER CONSTRUCTION
THERMAL POWER PROJECTS
(JANUARY, 2024)
Monthly Thermal Capacity Addition achievement (MW) during FY :2023-24
3000
2624
2500
2000
MW

1500
874 800 800
1000
500 150
0 0 0 0 0 0
0
Apr'23 May'23 Jun'23 Jul'23 Aug'23 Sep'23 Oct'23 Nov'23 Dec'23 Jan'24 Total
Month

Thermal Capacity Addition Program for FY 2023-24


15000 14700
Target Achievement

10000
7820
6880
MW

5000
2624
1460
800 364
0
0
Central State Private Total

Thermal Project Monitoring Division


Central Electricity Authority
New Delhi
Ministry of Power
Government of India
[Link]
FOREWORD

As per clause 73(f) of the Electricity Act 2003, Central Electricity Authority is to
“promote and assist in the timely completion of schemes and projects”. The Thermal
Project Monitoring (TPM) Division of CEA is entrusted with the responsibility of
monitoring the progress of construction/erection activities of all the thermal power
projects in the country till the units are commissioned. Visits are also made by CEA
officers to the sites for assessing the on the spot progress of works and rendering the
advice/assistance in solving the problems being faced by the project authorities, thereby
helping the project authorities to avoid / minimize the time and cost overrunsof the
thermal power projects.

In this context, Thermal Project Monitoring Division, Central Electricity Authority


has been bringing out the monthly report titled “Broad Status of Thermal Power Projects
in the Country”. This report gives year-wise details of thermal power projects
commissioned during the last five years. Further, the Report includes up-to- date
information on thermal power projects under construction in the country wherein the
details regarding name of the Project, capacity, location, implementing agency,
commissioning schedule, type of fuel, estimated cost, physical and financial progress,
the milestones achieved as on date etc. are available. The critical issues requiring
immediate attention of concerned authorities in the implementation of these thermal
power projects have also been highlighted.

The Broad Status Report is being brought out regularly by TPM Division on the
basis of the data forwarded by various project authorities, visits made by CEA officers
to various power projects, discussions held with the executing agencies and suppliers
of equipment from time to time.

CEA welcomes feedback for further improvement in the Broad Status Report.

Chief Engineer (TPM)

This report is based on the details received from various project authorities & other organizations / agencies
associated with the projects and is for information and non-commercial use only. CEA is not responsible for the
contents or reliability of other websites to which CEA provides a link and do not necessarily endorse the views
expressed by them.
CONTENTS
Sl. No. Description Page No.
Executive Summary 3-4
1.1 Tentative Thermal Capacity Addition Program for FY 2023-24 5
1.2 Thermal Power Projects under construction in the country 6
1.3 Under construction TPPs where work is on hold / not likely to be commissioned 7-8
BROAD STATUS OF CENTRAL SECTOR PROJECTS
A NATIONAL THERMAL POWER CORPORATION LTD. (NTPC Ltd.)
Barh STPP St-I, Distt.- Patna, Bihar 9-10
North Karanpura STPP, Distt.- Chatra, Jharkhand 11-12
Telangana TPP (Ph-I), Distt.- Karim Nagar, Telangana 13-14
Patratu TPS, Distt.- Ramgarh, Jharkhand. [PVUNL (JV of NTPC & Govt. of Jharkhand)] 15-16
Talcher Thermal Power Project, Distt. – Angul, Odisha 17-18
Lara Super Thermal Power Project, Distt.- Raigarh, Chhattisgarh 19-20
B NEYVELI LIGNITE CORPORATION LIMITED (NLC Ltd.)
Ghatampur TPP, Distt. -Kanpur [NUPPL (JV of NLC & UPRVUNL)] 21-22
NLC TALABIRA TPP, Distt.- Sambalpur, Odisha 23-24
C TEHRI HYDRO DEVELOPMENT CORPORATION LIMITED (THDC Ltd.)
Khurja STPP, Distt. -Bulandshahr, U.P. 25-26
D SATLAJ JAL VIDHUT NIGAM LIMITED (SJVN Ltd)
Buxar TPP, Distt. -Buxar, Bihar. 27-28
BROAD STATUS OF STATE & PRIVATE SECTOR PROJECTS

E Uttar Pradesh
Obra-C TPP, Distt.- Sonebhadra, [UPRVUNL] 29-30
Jawaharpur STPP, Distt.- Etah, [JVUNL (A 100% subsidiary of UPRVUNL)]. 31-32
Panki TPS Ext, Distt. -Kanpur, [UPRVUNL] 33-34

F Tamil Nadu
Ennore SEZ SCTPP, Distt. -Thiruvallur, [TANGEDCO] 35-36
North Chennai TPP St-III, Distt.-Thiruvallur, [TANGEDCO] 37-38
Udangudi STPP, Distt.-Thoothukudi, [TANGEDCO] 39-40

G Telangana
Yadadri TPS (TSGENCO), Distt.- Nalgonda, [TSGENCO] 41-43

H Maharashtra
Bhusawal TPP, Distt. -Jalgaon, [MAHAGENCO] 44-45

I West Bengal
Sagardighi TPP, Distt.-Murshidabad, [WBPDCL] 46-47

J Madhya Pradesh
Mahan Ultra Supercritical TPP, Distt. Singrauli, Madhya Pradesh [Mahan Energen Ltd] 48-49
K On Hold Under-Construction TPPs
Yelahanka Combined Cycle Power plant, Distt.- Bangalore, [KPCL]. 50-51
Uppur SCTPP, Distt. -Ramanathapuram, [TANGEDCO] 52-53
Ennore Exp. TPP (1x660 MW), Distt- Thiruvallur, [TANGEDCO] 54
EXECUTIVE SUMMARY
I. All India Installed Capacity (MW)*
Thermal Grand
Nuclear Hydro RES
Sector Coal Lignite Gas Diesel Total total
State 68118 1150 7012 280 76560 0 27254 2527 106341
Private 73512 1830 10788 309 86439 0 3931 130957 221328
Central 66560 3640 7238 0 77438 7480 15743 1632 102293
Total 208189 6620 25038 589 240437 7480 46928 135116 429961
% of Grand Total 48.42% 1.54% 5.82% 0.14% 55.92% 1.74% 10.91% 31.43% 100.00%
*Compiled from Installed Capacity Report on CEA’s website (as on 31.01.2024).
II. Tentative Year-wise Target of Thermal Capacity to be included into National Capacity :
(as on 31.01.2024)
FY 2023-24 2024-25 2025-26 2026-27 2027-28 2028-29 2029-30 Total
(MW)
Central 3580 6880 800 660 1460 2400 800 16580
State 3580 7160 2120 0 0 0 0 12860
Private 0 0 0 800 800 0 0 1600
Total 7160 14040 2920 1460 2260 2400 800 31040*
*Yelahanka CCPP (370 MW), Uppur SCTPP (2x800 MW) and Ennore Exp TPP (1x660 MW) have not been included in this capacity.

III. Details of Technology wise Under Construction TPPs (excluding stressed TPPs ) in the country:
(as on 31.01.2024)
Super Critical # Sub-Critical Total
Sector No. of Projects Capacity No. of Projects Capacity No. of Projects Capacity
[Units] (MW) [Units] (MW) [Units] (MW)
Central 10 [21] 15120 0 0 10 [21] 15120
State 11 [20] 14320 1 [1] 370 12 [21] 14690
Private 1 [2] 1600 0 0 1 [2] 1600
Total 22 [43] 31040 1 [1] 370 23 [44] 31410
# Out of the 22 Supercritical TPPs, 9 projects (19 units) of total capacity 14080 MW are based on Ultra Super critical technology.
[ 6 projects (13 units) in Central sector of capacity 9840 MW,
[ 2 projects (4 units) in State sector of capacity 2640 MW and
[ 1 project (2 units) in Private sector of capacity 1600 MW]. The details of these projects are given in Table 1.2

IV. Sector-wise Thermal Capacity Addition during last five years :


FY:2018 -19 FY:2019-20 FY:2020-21 FY:2021-22 FY:2022-23
Achieve- Achieve- Achieve- Achieve- Achieve-
Sector Target Target Target Target Target
ment ment ment ment ment
Central 2760 1960 6040 3940 5790 4080 5400 2370 3580 660
State 4506 2850 4256 2780 4276 846 4360 1590 2770 800
Private Nil 972 Nil 45 525 0 525 525 0 0
Total 7266 5782 10296 6765 10591 4926 10285 4485 6350 1460

V.(a) Thermal Capacity Addition Program & Achievement for FY 2023-24 ( as on 31-01-2024):
Thermal Capacity Addition Program viz-a viz Achievement for FY 2023-24
16000 14700
Target Achievement
14000
12000
10000
7820
MW

8000 6880
6000
4000 2624
1460
2000 800 364
0
0
Central State Private Total

3
V.(b) Month-wise Thermal Capacity Addition upto January-2024 (FY 2023-24):

Month-wise Thermal Capacity Addition (MW) during FY 2023-24


3000
2624
2500

2000
MW

1500

1000 874 800 800

500
150
0 0 0 0 0 0
0

Month

4
1.1 Tentative Thermal Capacity Addition Program and Actual Achievement for FY 2023-24:
(as on 31.01.2024)
Trial Run Actual
Boiler (SG) & Targeted Anticipated Capacity
S. Project Implementing Unit Assessment as Date of
State Turbine(TG) Capacity Trial Run (as on per latest Achieved
No. Name Agency No 01-04-2023) Capacity
Make (MW) review by CEA (MW)
Addition
CENTRAL SECTOR
Barh STPP, SG-TPE/DPSI | TG-
1 NTPC Bihar U-2 660 Apr-2023 Jun-2023 660 30.06.2023
St-I Power Machines
Telangana U-1 800 Jun-2023 Sep-2023 800 05.09.2023
2 NTPC Telangana SG-BHEL | TG-GE
STPP, St- I U-2 800 Jul-2023 Feb-2024
North
SG-BHEL (EPC) |
3 Karanpura NTPC Jharkhand U-2 660 Nov-2023 Feb-2024
TG-BHEL (EPC)
STPP
SG-L&T (EPC) | U-1 660 Dec-2023 Jun-2024
4 Buxar TPP SJVN Bihar
TG-L&T (EPC) U-2 660 Mar-2024 Sep-2024
U-1 660 Jul-2023 Mar-2024
Ghatampur Uttar SG-L&T-MHI | TG-
5 NUPPL U-2 660 Oct-2023 July-2024
TPP Pradesh GE
U-3 660 Dec-2023 Oct-2024
Khurja Uttar SG-L&T-MHI | TG-
6 THDC U-1 660 Feb-2024 Jun-2024
SCTPP Pradesh BHEL
Total (Central Sector) No. of Units : 10 6880 6880 (10) 3580 (5) 1460 (2)
STATE SECTOR
Dr. Narla Tata
Andhra SG-BHEL | TG-
7 Rao TPS, St- APGENCO U-8 800 Jun-2023 Dec-2023 800 20.12.2023
Pradesh BHEL
V
Jawaharpur Uttar SG-DPSI (EPC) | U-1 660 Jun-2023 Feb-2024
8 UPRVUNL
STPP Pradesh TG-DPSI (EPC) U-2 660 Dec-2023 Apr-2024
Uttar SG-DPSI (EPC) | U-1 660 Jun-2023 Feb-2024
9 Obra-C STPP UPRVUNL
Pradesh TG-DPSI (EPC) U-2 660 Jan-2024 Jun-2024
Panki TPS Uttar SG-BHEL (EPC) |
10 UPRVUNL U-1 660 Jan-2024 Sep-2024
Extn. Pradesh TG-BHEL (EPC)
North Chennai SG-BHEL | TG-
11 TANGEDCO Tamil Nadu U-1 800 Sep-2023 Mar-2024
TPP, St-III BHEL
Udangudi SG-BHEL (EPC) |
12 TANGEDCO Tamil Nadu U-1 660 Mar-2024 Sept-2024
STPP, St-I TG-BHEL (EPC)
SG-BHEL (EPC) | U-1 800 Dec-2023 Dec-2024
13 Yadadri TPS TSGENCO Telangana
TG-BHEL (EPC) U-2 800 Dec-2023 Dec-2024
SG-BHEL (EPC) |
14 Bhusawal TPS MAHAGENCO Maharashtra U-6 660 Jul-2023 Mar-2024
TG-BHEL (EPC)
Total (State Sector) No. of Units : 11 7820 7820 (11) 3580 (5) 800 (1)
Total Targeted Capacity No. of Units : 21 14700* 14700 (21) 7160 (10) 2260 (3)
*Yelahanka CCPP (KPCL) (370 MW) has not been included in this capacity. It has been constructed and its trial run is pending due to non-availability of gas from M/s
GAIL (Anticipated in Feb.-2024)

Anticipated Trial Run Actual


Boiler (SG) & Targeted Capacity
S. Project Implementing Unit Trial Run (In Assessment as Date of
State Turbine(TG) Capacity the beginning per latest Achieved
No. Name Agency No Capacity
Make (MW) of FY 2023-24) review by CEA (MW)
Addition
ADDITIONAL CAPACITY (PRIVATE SECTOR)
GTG - GE, France |
STG - Hang Zhou
Kashipur
1 M/s SEPL Uttarakhand Steam Turbine Co. Mod-2 225 - - 214 13.06.2023
CCPP, Ph-II
Ltd., China | HRSG
- Greens Power, UK
SG-BHEL | TG-
2 Shirpur TPP M/s JPL Maharashtra U-2 150 - - 150 22.11.2023
BHEL
Total (State Sector) No. of Units : 2 375 - - 364 (2)

5
1.2 Under Construction Thermal Power Projects in the Country:
(as on 31.01.2024)
Antici-pated Physica Financia
Org Original Latest Total
S.N Implementing Unit Cap. Trial Run l l
Project Name State Boiler Turbine Technology LOA Date Trial Cost Cost Exp.
o. Agency No (MW) (as per Progres progress
Run (cr) (cr) (cr)
CEA) s (%) (%)
CENTRAL SECTOR
Power
1 Barh STPP St-I Bihar NTPC Doosan Machine Supercritical Mar-05 U-3 660 Oct-11 Aug-24 89% 8693 22078 22078 100%
Russia
U-1 660 May-23 Jun-24 89%
2 Buxar TPP Bihar SJVN L&T L&T Supercritical Jun-19 10439 10439 8861 85%
U-2 660 Sep-23 Sep-24 80%
North Karanpura U-2 660 Dec-18 Feb-24 97%
3 Jharkhand NTPC BHEL BHEL Supercritical Feb-14 14367 16243 15181 93%
STPP U-3 660 Jun-19 Sep-24 85%
U-1 800 Jan-22 Sep-24 69%
Ultra-
4 Patratu STPP Jharkhand PVUNL BHEL BHEL Mar-18 U-2 800 Jul-22 Mar-25 64% 17112 18668 12527 67%
Supercritical
U-3 800 Jan-23 Sep-25 48%
Ultra- U-1 660 Nov-26 Nov-26 20%
5 Talcher TPP St-III Odisha NTPC BHEL BHEL Sep-22 11844 11844 1057 9%
Supercritical U-2 660 May-27 May-27 15%
Ultra- U-1 800 Dec-27 Dec-27 0%
6 Lara STPP St-II Chhattisgarh NTPC BHEL BHEL Aug-23 15530 15530 588 4%
Supercritical U-2 800 Jun-28 Jun-28 0%
GE U-1 660 May-20 Mar-24 91%
Uttar L&T
7 Ghatampur TPP NUPPL Power Supercritical Aug-16 U-2 660 Nov-20 Jul-24 80% 17238 19406 16732 86%
Pradesh MHPS
system U-3 660 May-21 Oct-24 74%
May-28 May-28
U-1 800 (Tentati (Tentative) 0%
ve)
Nov-28 Nov-28
NLC TALABIRA Ultra-
8 Odisha NLC BHEL BHEL Jan-2024 U-2 800 (Tentati (Tentative) 0% 19422 27212 813.28 2.98%
TPP Supercritical
ve)
May-29 May-29
U-3 800 (Tentati (Tentative) 0%
ve)
Uttar Ultra- U-1 660 Jul-23 Jun-24 86%
9 Khurja SCTPP THDC L&T MHI BHEL Aug-19 11089 11089 9428 85%
Pradesh Supercritical U-2 660 Jan-24 Sep-24 70%
GE
Telangana STPP Ultra-
10 Telangana NTPC BHEL Power Feb-16 U-2 800 Nov-20 Feb-24 99% 10599 14000 11573 83%
St- I Supercritical
system
Total Central Sector 15120 136333 166509 98839
STATE SECTOR
Uttar Ultra- U-1 660 Dec-20 Feb-24 96%
1 Jawaharpur STPP UPRVUNL Doosan Doosan Dec-16 10566 12320 11877 96%
Pradesh Supercritical U-2 660 Apr-21 Apr-24 92%
Doosan U-1 660 Dec-20 Feb-24 97%
Uttar Doosan Ultra-
2 Obra-C STPP UPRVUNL India Dec-16 8778 11706 10282 88%
Pradesh India Supercritical U-2 660 Apr-21 Jun-24 87%
(GE)
Uttar
3 Panki TPS Extn. UPRVUNL BHEL BHEL Supercritical Mar-18 U-1 660 Sep-21 Sep-24 82% 5817 6729 5363 80%
Pradesh
U-1 660 Jan-18 Apr-25 69%
4 Ennore SCTPP Tamil Nadu TANGEDCO BHEL BHEL Supercritical Sep-14 9800 9800 5439 55%
U-2 660 Mar-18 Jul-25 68%
North Chennai
5 Tamil Nadu TANGEDCO BHEL BHEL Supercritical Jan-16 U-1 800 Oct-19 Mar-24 95% 6376 8723 8544 98%
TPP St-III
Udangudi STPP U-1 660 Jun-21 Sep-24 81%
6 Tamil Nadu TANGEDCO BHEL BHEL Supercritical Dec-17 13077 13077 9392 72%
St-I U-2 660 Jun-21 Jan-25 78%
7 Bhusawal TPS Maharashtra MAHAGENCO BHEL BHEL Supercritical Jan-18 U-6 660 May-22 Mar-24 95% 4548 4551 4083 90%
Sagardighi TPP
8 West Bengal WBPDCL BHEL BHEL Supercritical Dec-18 U-5 660 Jan-24 Jan-25 69% 3863 4567 1900 42%
St-III
U-1 800 Oct-21 Dec-24 89%
U-2 800 Oct-21 Dec-24 90%
9 Yadadri TPS Telangana TSGENCO BHEL BHEL Supercritical Oct-17 U-3 800 Jun-22 Mar-25 84% 25099 34543 24827 72%
U-4 800 Jun-22 Feb-25 85%
U-5 800 Oct-22 Oct-25 81%
GT
10 Yelahanka CCPP Karnataka KPCL BHEL BHEL Subcritical Nov-15 370 Feb-18 Feb-24 100% 1571 2335 2335 100%
+ST
Uppur Super U-1 800 Nov-20 On Hold 6%
11 Tamil Nadu TANGEDCO BHEL BHEL Supercritical Feb-16 12778 12778 3282 26%
Critical TPP U-2 800 Nov-20 On Hold 5%
LITL/B
12 Ennore Exp TPP Tamil Nadu TANGEDCO LITL/BGR Supercritical Jul-14 U-1 660 On Hold 4956 7093 791 11%
GR
Total State Sector 14690 107229 128222 88114
PRIVATE SECTOR
Madhya Mahan Energen BHEL BHEL Ultra- U-1 800 Nov-26 Dec-26 0%
1 Mahan STPP Aug-23 12439 12439 661 5%
Pradesh Ltd (Supply) (Supply) Supercritical U-2 800 May-27 May-27 0%
Total Private Sector 1600 12439 12439 661
Grand Total 31410 256001 307170 187614

6
1.3 Under construction TPPs where work is on hold / not likely to be commissioned (As on 31.01.2024)

LOA
S. Project Name / Impl. Original Latest Exp Till
Date/ Org. Present Status/Remarks
No State Agency/ EPC or BTG Cost Cost (cr) Exp. (cr) Date
ordered Unit No Cap. (MW) Comm.
date Sched.
CENTRAL SECTOR
Project was held up due to withdrawal of PPA by DISCOM (Rajasthan), due to
Barsingar TPP land issue in linked mines and consequently higher tariff. On 04-08-2022, a
1 Rajasthan ext/NLC/Reliance Nov-16 U-1 250 May-20 meeting was held (Additional Secretary-Coal, GoI along with NLCIL Directors 2112.59 2112.59 158.25 Jan- 21
Infra/Chinese met Chief Secretary-GoR and Principal Secretary-Energy) and it was jointly
decided not to pursue with the Barsingsar TPS Extension project (1X250 MW)
along with Hadla Mine.
Project was held up due to withdrawal of PPA by DISCOM(Rajasthan) due to
increased project cost and time over run. On 04-08-2022 a meeting was held
Bithnok TPP
2 Rajasthan Nov-16 U-1 250 May-20 (Additional Secretary-Coal, GoI along with NLCIL Directors met Chief 2196.3 2196.3 173.82 Jan- 21
/NLC/Reliance Infra/ Chinese Secretary-GoR and Principal Secretary-Energy) to revive the Bithnok TPS.
Based on the decision, a consultant was appointed to prepare feasibility. Further,
as per the discussions held with Rajasthan government officials, it has been
agreed that NLC and GoR will jointly work to revive the Bithnok Thermal
Power Project along with Bithnok Mines. The consultant has prepared the
feasibility report for revival of the project and the same is under “scrutiny and
approval”.
TOTAL CENTRAL SECTOR [No. of Projects: 2, No. of Units: 2] 500
PRIVATE SECTOR
Liquidation Order date 22/04/2019. Liquidator has partially sold the
Sep-09 U-1 660 Oct-13 assets(P&M) of the company on a standalone basis through e-auction. Further,
Bhavanapadu TPP Ph-I / East
Andhra the liquidator has also sold the Land including buildings at the Plant Site on 9th
1 Coast Energy Ltd. / BTG DEC 6571.94 9343.15 3785.6 Jan- 16
Pradesh Feb 2023.
china
Sep-09 U-2 660 Mar-14

Vedanta Ltd. Has bought this plant under NCLT route.


Thamminapatnam TPP, St-II / Dec-09 U-3 350 May-12
Meenakshi Energy Pvt. Ltd. The project is likely to be commissioned during 2024-25.
Andhra
2 SG-Cether vessels TG- Chinese (U#1: Sep-2024, U#2: Oct-2024) 5005 5414.4 5414.4 Feb- 19
Pradesh
Dec-09 U-4 350 Aug-12

Mar-11 U-1 660 Aug-14 Liquidation Order date 17.07.2020; The Enforcement directorate has attached the
Siriya TPP (Jas Infra. TPP) / assets of the corporate debtor and as a result of which the auction of the assets are
Mar-11 U-2 660 Dec-14
3 Bihar JICPL BTG-DEC kept on hold. 11120 11120 NA NA
China Mar-11 U-3 660 Apr-15

Mar-11 U-4 660 Aug-15

Akaltara TPP (Naiyara) / KSK Apr-09 U-4 600 Apr-13 CIRP commenced on 3rd October 2019 & currently under NCLT.
Mahandi Power Company Ltd./ Apr-09 U-5 600 Aug-13 PPL and REC have submitted EOI on 21-7-2023 and shortlisted as PRAs.
4 Chhattisgarh Boiler- SEPCO CHINA 16190 27080 18730 Dec- 16
(Shanhai china) / TG- SEPCO (
Apr-09 U-6 600 Dec-13
Dongfong china)

Binjkote TPP/ SKS Power Mar-11 U-3 300 Mar-14 Reworked bids (seven) received from the Resolution Applicants.
Generation (Chhattisgarh) Ltd. Voting is completed. Plan submitted by Sarda Energy & Minerals filed with
5 Chhattisgarh 5058 7940 3828 Jun- 15
Boiler-Cethar Vessels Mar-11 U-4 300 Jun-14 NCLT for approval has been sent back by NCLT for reconsideration by CoC. The
/Turbine-Harbin China plant is likely to be revived by 2030-31.

Lanco Amarkantak TPP- II/ Nov-09 U-3 660 Jan-12 Admitted to NCLT on 05.09.2019.
6 Chhattisgarh PFC-REC consortium was declared successful Resolution Applicant. LOI 6886 10815.24 9537.79 Dec- 16
LAP Pvt. Ltd. BTG-DEC china Nov-09 U-4 660 Mar-12
issued on 09-01-2023.
CoC approved plan submitted by RP for approval of NCLT on 14-02-2023.
Plant is likely to be revived by FY 2025-26
Singhitarai TPP / Athena Dec-09 U-1 600 Nov-14
Vedanta Ltd. has bought the power plant under liquidation. Plant is likely to be
7 Chhattisgarh Chhattisgarh Power Ltd. BTG 6200 8443.79 6408.47 May- 17
–DEC china Dec-09 U-2 600 Feb-15 revived by FY 2030-31
Salora TPP / Vandana Vidyut/
8 Chhattisgarh Boiler- Cether Vessles /TG Sep-09 U-2 135 Sep-11 The liquidator successfully sold the assets of corporate debtor as per provision 1458.44 2386.89 2386.89 Mar- 15
of IBC, 2016.
Harbin China

The liquidator has started the process of liquidating the company by selling the
Deveri (Visa) TPP / Visa assets of the Corporate Debtor on piecemeal basis. BHEL claims certain unpaid
9 Chhattisgarh Jun-10 U-1 600 Aug-13 2618.7 3930 2077.23 Nov- 15
Power Ltd. BTG-BHEL lien on the assets available at the site of the Corporate Debtor and in this regard
matter is still pending before the Supreme Court of India.

Matrishri Usha TPP, Ph-I Dec-09 U-1 270 Apr-12


10 Jharkhand / Corporate Power Ltd. 2900 3120 3120 Nov- 12
EPC- BHEL Dec-09 U-2 270 May-12
The liquidator is making endeavor to sell the company as per provision of IBC,
Matrishri Usha TPP, Ph-II Mar-11 U-3 270 Oct-12 2016 and the regulation laid there in.
11 Jharkhand / Corporate Power Ltd. 3182 3182 2207 Sep- 12
EPC- BHEL Mar-11 U-4 270 Jan-13

Tori TPP, Ph-I / Essar Aug-08 U-1 600 Jul-12


12 Jharkhand 5700 5700 4757.92 Jun- 17
PowerLtd. BTG- Harbin Aug-08 U-2 600 Sep-12 the Liquidator has initiated the e-auction process for realizing the assets of the
China Corporate Debtor and till date has sold around 15,000 MT of Fabricated Steel
Structure from the power plant
Tori TPP Ph-II / Essar Power
13 Jharkhand Feb-10 U-3 600 Dec-15 2500 2500 246.65 Mar- 15
Ltd./ BTG- Harbin China
Oct-10 U-1 270 Jul-14

7
LOA
S. Project Name / Impl. Original Latest Exp Till
Date/ Org. Present Status/Remarks
No State Agency/ EPC or BTG Cost Cost (cr) Exp. (cr) Date
ordered Unit No Cap. (MW) Comm.
date Sched.
Oct-10 U-2 270 Sep-14 Company has decided to drop Phase II due to following reasons:
a) no new Bids for Long Term PPAs have been coming up in the Market
Amravati TPP Ph-II / Ratan Oct-10 U-3 270 Nov-14 since the last 5 years.
14 Maharashtra India Power Pvt. Ltd. BTG- 6646 6646 763.8 Mar- 15
Oct-10 U-4 270 Jan-15 b) the revised emission norms under the Environment (Protection)
BHEL
Amendment Rules, 2015 revising, inter alia, emission norms for thermal power
Oct-10 U-5 270 Mar-15 plants., drastic changes in the design and equipment of Phase II was required to
be carried out.
Nov-09 U-1 270 Apr-13

Nov-09 U-2 270 Jun-13


Nasik TPP Ph-II / Ratan India
Maharashtra Nasik Power Pvt. Ltd. BTG- Nov-09 U-3 270 Aug-13
BHEL
15 Nov-09 U-4 270 Oct-13 6789 6789 711.81 Mar- 15
Nov-09 U-5 270 Dec-13
Lanco Vidarbha TPP / LVP Nov-09 U-1 660 Jul-14
Majority of Plant material has been auctioned and removed from site.
Pvt. Ltd. EPC-
16 Maharashtra 706 Acres of Land and approx. 4000 MT of material is yet to be auctioned as they 6936 10433 5338 Apr- 17
LANCO/ Boiler- Dongfong Nov-09 U-2 660 Nov-14 were under Litigation.
China / Turbine- Harbin china
Bijora Ghanmukh TPP / Sep-11 U-1 300 Dec-16
17 Maharashtra Jinbhuvish Power Generation The coal linkage matter for this project is sub judice and once it is resolved, 3189 3450 422.27 Mar- 15
Sep-11 U-2 300 Mar-17 developer will be looking for funding options and further process.
Pvt. Ltd.

Madhya Gorgi TPP / D.B. Power (MP) The company has requested a COD extension with GoMP, and a revival will be
18 Mar-11 U-1 660 Jun-13 3941 3941 475.79 Sep- 15
Pradesh Ltd. BTG- BHEL planned accordingly on the final permission.

Utkal TPP (Odisha) JSW Energy has bought the plant under NCLT route. U#2 is likely to be
19 Odisha / Ind Barath/BTG-Cethar May-09 U-2 350 Dec-11 commissioned in June-2024 (2024-25). 3150 4254 4254 Apr- 17
Vessels
Nov-09 U-1 350 Dec-11
20 KVK Nilanchal TPP/ KVK
Odisha Nilanchal Nov-09 U-2 350 Feb-12 Project sold to successful bidder M/s Padmaprabhu Commodity Trading Pvt Ltd 4990 6000 1708.36 Mar- 15
in the E-auction held on 26th August 2022
/ BTG-Harbin China
Nov-09 U-3 350 Feb-12
Lanco Babandh TPP / LBP Nov-09 U-1 660 Apr-13
Odisha Ltd./ BTG- DEC the Liquidator has partially sold the assets of the company on a standalone basis 6930 10430 7615 Mar- 17
21
Nov-09 U-2 660 Aug-13 through e-auction dated 27.08.2021
Chinese
Jun-10 U-1 525 Dec-12 Jindal Steel & Power has acquired the asset under liquidation;
Malibrahmani TPP /
22 Odisha Plant is likely to be revived by FY 2024-25 5093 6330 5329.75 Dec- 14
Monnet Power [Link]. / Jun-10 U-2 525 Feb-13
BTG-BHEL
Tuticorin TPP (Ind- Barath) /
23 Tamil Nadu IBPIL / BTG- Shangdong May-10 U-1 660 May-12 Successful bidder has been identified. However, the Liquidation process has been 3595 3595 2000 May- 15
stayed by the Hon’ble NCLAT.
China
Hiranmaye Energy Ltd.
24 (India Power corporation
West Bengal (Haldia) TPP / Haldia Sep-10 U-3 150 May-16 Project is currently under hold
Energy Ltd / EPC- MEIL / 2656 3307 3263.05 Oct- 17
BTG- BHEL.

TOTAL PRIVATE SECTOR [No. of Projects:24, No. of Units:51] 23055


GRAND TOTAL [No. of Projects: 26, No. of Units: 53] 23555

8
Status as on 31-01-2024
BARH STPP St-I, Unit# 1, 2 & 3 (3x660 MW) / NTPC (CENTRAL SECTOR)
NTPC Barh Super Thermal Power Station, Barh, Distt – Patna, Bihar – 803215
E-Gen Portal Registration No. (U#1 - 1200002610; U#2 - 1200002611; U#3 - 1200002612 )
Project Developer / Implementing Agency -
Main Plant Vendor : SG-Ms/TPE/DPSI, TG: Power Machines, Russia,
NTPC
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#1 Feb-2010 30-Oct-2021 (A)
Unit#2 Mar-2005 Dec-2010 30-Jun-2023 (A)
Unit#3 Oct-2011 Aug-2024
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal, Indigenous, Non-pit head ORIGINAL ESTIMATED COST
8693.00
COAL COMBUSTION OF THE PROJECT
Supercritical
TECHNOLOGY
LATEST ESTIMATED COST 21312.11
APPROVAL DATE / NTP Feb-2005
TG: Power Machines, Russia on 14.03.2005. Boiler: Awarded to TPE DATE OF FINANCIAL
21.02.2005
EPC/BTG/BoP Contractor on 14.03.2005, contract terminated on 14.01.2015; Balance work CLOSURE
Details (Package Wise) awarded to DPSI on 30.01.2016. Pressure Parts ordered partially
(replacement of DI 59 coils) to GE Power on 15.01.2018. YEAR WISE EXPENDITURE

2010-11 921.81

Bihar (incl. Home state share): 1025 MW, Jharkhand: 202 MW, 2011-12 1286.25
PPA
Orissa: 418 MW, Sikkim: 38 MW and unallocated: 297MW.
2012-13 1384.43
Letter of Assurance dtd. 18.11.2010 from CCL, securing 10 MMTPA
COAL LINKAGE/FSA coal for 03 Units. FSA of Unit-1 (3.333 MTPA) already signed with 2013-14 1581.22
CCL(all operative mines, G8-G10) as per MoC PD dtd. 17.07.2013.
FSA of Unit-2 & 3 to be signed after commissioning in terms of para 2014-15 568.49
1A(i)of SHAKTI-2017 policy.
2015-16 1143.46
START UP POWER Done with PGCIL on 27.01.2020 for 400 kV D/C LILO of
AGREEMENT Kahalgaon-Patna, Barh-Patna & Barh-Gorakhpur lines 2016-17 1410.21
Tx Line Developer PGCIL
2017-18 1389.43
Tx Line Name LILOing of Kahalgaon – Patna 400 kV D/C
POWER EVACUATION (Quad) line at Barh (NTPC) switchyard. 2018-19 1453.89
Tx Voltage Level
SYSTEM
2019-20 1502.47
Configuration of Tx Line
D/C
(S/C or D/C)
2020-21 1123.15
LAND POSSESSION Required – 3212 Acres, Under Possession – 3212 Acres
2021-22 1185.00
WATER ALLOCATION 100 Cusec from River Ganges
2022-23 2284.00
MOEF CLEARANCE 11.09.2001
EXPENDITURE OF JAN’2024 40.51
CIVIL AVIATION
09.08.2004
CLEARANCE TOTAL EXPENDITURE
22077.76
(upto 31.01.2024)
CPCB CLEARANCE Not Applicable

Consent to Operate (Emission & Discharge) Granted by SPCB on


SPCB CLEARANCE
04.07.2017, For Unit#1, and is Valid upto 30.09.2021

FOREST CLEARANCE Not Applicable

9
Status as on 31-01-2024
BARH STPP St-I, Unit# 1, 2 & 3 (3x660 MW)
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL ) STATUS OF MAIN PLANT PACKAGE (BTG) / SG - DPSI, TG - Power Machine, Russia
UNIT-01 UNIT-02 UNIT-03 UNIT-01 UNIT-02 UNIT-03
Sl. Packages AREA
Actual / Actual / Actual / % Completion % Completion % Completion
Original Anticipat Original Anticipat Original Anticipat ed CIVIL 94%
Sl. MILESTONE Date of ed Date Date of ed Date Date of Date of 100%
1 BOILER STRUCTURE 100% 82%
Completi of Completi of Completi Completion
on Completi on Completi on PRESSURE PARTS 98%
on on CIVIL 95%
1 COMPLETION OF BOILER FOUNDATION Complete Complete Complete 2 TG STRUCTURE 100% 100% 97%
2 START OF BOILER ERECTION May-06 Mar-11 Mar-07 Jul-11 Jan-08 Jan-12 TG ERECTION 80%
3 BOILER DRUM LIFTING (if sub-critical unit) NA NA NA 3 ESP UNDER PROGRESS 100% 100% 95%
4 BOILER CEILING GIRDER LIFTING COMPLETION Complete Complete Complete CIVIL WORK 26% 12% 14%
5 CONDENSER ERECTION START Jun-07 Nov-08 Apr-08 Jan-09 Feb-09 Nov-13 MATERIAL SUPPLY 35% 30% 26%
4 FGD
6 TG ERECTION START Aug-07 Aug-11 Jun-08 Sep-11 Apr-09 Mar-12 1%
ERECTION WORK Yet to start Yet to start
7 HP PIPING ERECTION START May-09 Oct-19 Mar-09 Sep-23
8 BOILER HYDRO TEST (DRAINABLE) COMPLETION Dec-07 Feb-13 Oct-08 Jan-21 Aug-09 Feb-24 STATUS OF BOPs
9 BOILER HYDRO TEST (NON-DRAINABLE) COMPLETION Feb-13 Oct-08 Jan-21 Aug-09 Apr-24 Anticipated/Ac
UNIT-01 UNIT-02 UNIT-03
Packages/ Linked Vendor/Contracting Scheduled Date
10 TG BOX UP Aug-08 Dec-13 Jun-09 Jan-15 Apr-10 May-24 Sl. Date of Award
of Completion
tual Date of
Project Milestones Agency (DPSI) Completion % Completion % Completion % Completion
11 HP PIPING ERECTION COMPLETION Aug-09 Jun-22 Jun-09 Feb-24
12 START OF OIL FLUSHING Jul-09 Dec-21 May-09 Jun-24 1 Chimney NBCC 20.12.2005 19.07.2009 Completed 100% 100% 100 %
13 BOILER LIGHT UP Aug-08 Aug-19 Jun-09 May-22 Apr-10 Apr-24 L&T (Conveyor package) 21.08.2009 U2-May’23(A); 100% 100% 68%
2 Coal Handling Plant 22.09.2005 U3- Feb’24
L&T (Wagon Tippler) 21.07.2009 Completed 100% 100 % 100 %
14 CHEMICAL CLEANING COMPLETION Jul-09 May-22 May-10 Feb-24 L&T(Stacker Reclaimer) 21.09.2009 Completed 100% 100 % 100 %
3 Ash Handling Plant Melco 15.04.2016 14.01.2019 U2-May’23(A);
U3-Feb’24
100% 100% 62%

Sep-09 Jul-22 Jul-10 Apr-24 4 Fuel Oil System Techno 07.05.2006 05.07.2009 U2-Completed
100% 100 % 78%
15 STEAM BLOWING START U3- Feb’24

5 Cooling Towers Paharpur 28.12.2005 27.08.2009 U2-Jun’23(A);


100% 100% 85%
U3- Feb’24

6 CW Pump house KBL 17.07.2006 16.01.2014 U3- Feb’24 100% 100 % 96%
16 STEAM BLOWING COMPLETION Jan-09 Jan-20 Nov-09 Oct-22 Sep-10 May-24
7 WPT Plant SPML 28.05.2007 27.11.2008 U3- Feb’24 100% 100 % 87%
8 DM Plant Driplex 24.03.2006 23.09.2008 Completed 100% 100 % 100 %
17 ROLLING & SYNC. Mar-09 Sep-20 Jan-10 Mar-23 Nov-10 Jul-24
9 Compressed Air System Power Machines 24.03.2005 29.10.2014 U3- Feb’24 100% 100% 96%
10 Fire Protection System Minimax 24.03.2006 23.07.2008 U2-Nov’22(A);
100% 100% 82%
18 FULL LOAD Jul-09 Apr-21 Apr-10 Jun-23 Mar-11 Jul-24 U3- Feb’24

11 Switch Yard BHEL 23.03.2006 06.11.2009 Completed 100% 100 % 100 %


12 Station Transformers ABB 10.10.2005 11.09.2008 U3- Feb’24 100% 100% 95%
19 TRIAL RUN Feb-10 Oct-21 Dec-10 Jun-23 Oct-11 Aug-24
13 Unit Transformers TRIL/BHEL/Kanohar 22.05.2006 21.01.2009 U3- Feb’24 100% 100% 95%
14 Railway Siding RITES 28.06.2006 27.12.2007 Line a/v 100% 100 % 100 %
20 COD Mar-10 Nov-21 Jan-11 Aug-23 Nov-11 Sep-24
15 Power Evacuation Lines PGCIL Line a/v 100% 100% 100%

CRITICAL ISSUES
 Supply of Stator from M/s Power Machines, Russia. There may be delay in manufacturing of Generator stator due to geo-political situation and sanctions imposed on Russian Federation. It is likely to supplied by March-2024.

REASONS OF DELAY
Inordinate delay by Main Plant (SG & Auxiliaries Package) vendor M/s TPE. Work started after 6 Years of award. Contract of M/s TPE was terminated in Jan’15 due to consistent failure of commitments and poor performance.
Contract for balance works re-awarded after 1 year in Jan’2016.
During Hydro Test of Boiler U#1, DI-59 Coils in PSH-IV, CSH & LPRH-II failed which were supplied by M/s TPE. Accordingly, change of material to SS304H was approved and contract was awarded to M/s GE on 15.01.2018 for
supply, Dismantling & Installation of Coils. Delayed project by approx. 2 years.
Due to unusual delay in project commissioning for Main plant vendors, revival of Balance Offsite Packages is taking considerable time.
Due to US sanction on Power Machines, Russia, balance TG/SG supplies and works got delayed. Due to ongoing war between Ukraine & Russia availability of experts from Ukraine is affected.
10
Status as on 31-01-2024
NORTH KARANPURA TPP, Unit# 1, 2 & 3 (3x660 MW) / NTPC (CENTRAL SECTOR)
NTPC, North Karanpura, Tandwa, Sub division – Simaria, Distt–Chatra – Jharkhand-825321
E-Gen Portal Registration No. (U#1 - 1200002378; U#2 - 1200002379; U#3 - 1200002380 )
Project Developer / Implementing Agency -
Main Plant Vendor - BHEL (EPC)
NTPC
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#1 Jun-2018 18-Jan-2023(A)
Unit#2 Feb-2014 Dec-2018 Feb-2024
Unit#3 Jun-2019 Sept-2024
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal, Pithead ORIGINAL ESTIMATED COST
14367.00
COAL COMBUSTION OF THE PROJECT
Supercritical
TECHNOLOGY
LATEST ESTIMATED COST 16243.00
APPROVAL DATE / NTP Feb-2014
DATE OF FINANCIAL
28.01.2014
CLOSURE
EPC/BTG/BoP Contractor
BTG (EPC) – BHEL YEAR WISE EXPENDITURE
Details (Package Wise)

2010-11 8.17

Jharkhand: 500 MW; Odisha: 396 MW; Bihar: 688 MW; WB: 99 2011-12 4.88
PPA
MW; Unallocated: 297 MW.
2012-13 5.75
Letter of Assurance dtd. 24.03.2015 from CCL, securing 7.039
2013-14 1362.18
MTPA coal (G7-G11) for 03 Units. FSA to be signed after
COAL LINKAGE/FSA
commissioning in terms of para 1A (i) of SHAKTI-2017 policy.
2014-15 527.92

2015-16 615.73
START UP POWER Through ATS – 400 KV NK Chandwa line. Line is under construction.
AGREEMENT Agreement yet to be done. 2016-17 2199.92
Tx Line Developer NKTL
2017-18 2044.46
Tx Line Name i) NKSTPP-Chandwa 400 KV, D/c line
POWER EVACUATION 2018-19 1747.91
Tx Voltage Level ii) NKSTPP-Gaya, 400 KV D/c line
SYSTEM
2019-20 1762.62
Configuration of Tx Line
D/C
(S/C or D/C)
2020-21 1243.28
LAND POSSESSION 2263/ 2293 Acres. 30 Acres pending for acquisition.
2021-22 1051.00
20 Cusec from Garhi River – Raw water drawl agreement signed with
WATER ALLOCATION
DVC on 18.09.2020.
2022-23 1590.38
MOEF CLEARANCE 29.11.2004
EXPENDITURE of Jan’ 2024 83
CIVIL AVIATION
13.02.2009
CLEARANCE TOTAL EXPENDITURE (upto
15180.85
31.01.2024)
CPCB CLEARANCE Not Applicable

SPCB CLEARANCE Available. 31.12.2001 for Bihar. 11.12.2014 for Jharkhand

FOREST CLEARANCE 03.11.2015

11
Status as on 31-01-2024
NORTH KARANPURA TPP, Unit# 1, 2 & 3 (3x660 MW) / NTPC (CENTRAL SECTOR)
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL ) STATUS OF MAIN PLANT PACKAGE (BTG) : BHEL
UNIT-01 UNIT-02 UNIT-03 UNIT-01 UNIT-02 UNIT-03
Sl. Packages AREA
Actual / Actual / Actual / % Completion % Completion % Completion
Original Anticipat Original Anticipat Original Anticipat CIVIL 100% 100% 89.00%
Sl. MILESTONE Date of ed Date Date of ed Date Date of ed Date
1 BOILER STRUCTURE 100% 100% 78.41%
Completi of Completi of Completi of
on Completi on Completi on Completi PRESSURE PARTS 100% 100% 64.94%
on on on CIVIL 100% 100% 99.25%
1 COMPLETION OF BOILER FOUNDATION Complete Complete Complete 2 TG STRUCTURE 100% 100% 99.25%
2 START OF BOILER ERECTION Aug-15 Apr-16 Feb-16 Jul-16 Aug-16 Jun-17 TG ERECTION NA NA NA
3 BOILER DRUM LIFTING (if sub-critical unit) NA NA NA 3 ESP UNDER PROGRESS 100% 100% 84.31%
4 BOILER CEILING GIRDER LIFTING COMPLETION Complete Complete Complete CIVIL WORK 100% 89% 40%
5 CONDENSER ERECTION START May-16 Nov-18 Nov-16 Jan-20 May-17 Jun-23 MATERIAL SUPPLY 58% 44% 42%
4 FGD
6 TG ERECTION START Jul-16 Nov-17 Jan-17 Jan-18 Jul-17 Mar-22
ERECTION WORK 27% 13% 9%
7 HP PIPING ERECTION START Jul-17 Nov-20 Jan-18 Jul-23 Jul-18 Dec-23
8 BOILER HYDRO TEST (DRAINABLE) COMPLETION Jan-17 Dec-18 Jul-17 Oct-19 Jan-18 Mar-24 STATUS OF BOPs
9 BOILER HYDRO TEST (NON-DRAINABLE) COMPLETION Mar-17 Jan-19 Jul-17 Oct-19 Jan-18 Apr-24 UNIT-01 UNIT-02 UNIT-03
Anticipated/Ac
Packages/ Linked Vendor/Contracting Scheduled Date
10 TG BOX UP Jun-17 Aug-19 Dec-17 Jan-22 Jun-18 Mar-24 Sl. Date of Award
of Completion
tual Date of
Project Milestones Agency Completion % Completion % Completion % Completion
11 HP PIPING ERECTION COMPLETION Sep-17 Jan-21 Mar-18 Sep-23 Sep-18 Mar-24
12 START OF OIL FLUSHING 1 Chimney M/s BHEL Feb-14 U#1-Dec-18 U#2-Oct-23 (A)
100% 100% 100%
Jul-17 Jul-20 Jan-18 Feb-23 Jul-18 May-24 U#2-Jun-19 U#3-Apr-23 (A)
U#3-Dec-20
M/s BHEL (Conveyor package) Feb-14 Dec-18 U#2-Feb-24
100% 90% 49%
13 BOILER LIGHT UP Aug-17 Dec-20 Feb-18 Jun-23 Aug-18 Jun-24 U#3-May-24
2 Coal Handling Plant M/s BHEL (Wagon Tripler) Feb-14 NA NA NA NA NA
M/s BHEL(Stacker Reclaimer) Feb-14 Dec-18 U#1-Nov-22 (A)
100% 82% 57%
14 CHEMICAL CLEANING COMPLETION U#2&3-Mar-24
Aug-17 Jan-21 Feb-18 Jun-23 Aug-18 Jun-24 3 Ash Handling Plant M/s BHEL Feb-14 Dec-18 U#1-Jan’23(A)
100% 90% 70%
U#2-Feb’24
U#3-Mar’24
4 Fuel Oil System M/s BHEL Feb-14 Dec-18 Completed 100% 100% 100%
15 STEAM BLOWING START
Sep-17 Jan-21 Mar-18 Jul-23 Sep-18 Jul-24 5 Cooling Towers M/s BHEL Feb-14 Dec-18 U#2 – Oct’23(A)
100% C-100%; M- C-100%; M-
U#3 – Apr’24
100% 12%
6 CW Pump house M/s BHEL Feb-14 NA NA NA NA NA
16 STEAM BLOWING COMPLETION Oct-17 Feb-21 Apr-18 Aug-23 Oct-18 Jul-24
7 WPT Plant M/s BHEL Feb-14 Dec-18 Completed 100 % 100 % 100 %
8 DM Plant M/s BHEL Feb-14 Dec-18 Completed 100% 100% 100%
17 ROLLING & SYNC. Dec-17 21.10.2022 Jun-18 09.11.23 Dec-18 Aug-24
9 Compressed Air System M/s BHEL Feb-14 Completed 100% 100% 100%
10 Fire Protection System M/s BHEL Feb-14 U#2-Feb’24
100% 75% 40%
18 FULL LOAD Feb-18 20.12.2022 Aug-18 19.01.24 Feb-19 Sept-24 U#3-Feb’24
11 Switch Yard BHEL-TBG/Arun Construction Feb-14 Dec-18 U#2-Sep’23(A)
100% 100% 100%
Technico India Pvt. Ltd. U#3-Feb’24

12 Station Transformers M/s BHEL Feb-14 Mar-18 U#2-Dec’23(A)


100% 100% 70%
19 TRIAL RUN U#3-Mar23 (A)
Jun-18 18.01.2023 Dec-18 Feb-24 Jun-19 Sept-24 13 Unit Transformers M/s BHEL Feb-14 Jul-18 U#2-Feb’24
U#3-Feb’24
100% 90% 37%
14 Railway Siding M/s BHEL Feb-14 NA NA NA NA NA
20 COD
- 01.03.2023 - Feb-24 - Oct-24 15 Power Evacuation Lines M/s BHEL May-16 Sep-19 NK-Chandwa line
: Oct’22 (A) 100% (Chandwa) 100% (Chandwa) 54% (Gaya)
NK-Gaya-June’24

CRITICAL ISSUES
- Delay in handing over of encumbrance free balance 40 acres land by CCL to NTPC for construction of external Coal Handling Plant.
- Delay in readiness of 400 KV, D/C, North Karanpura - Gaya transmission line.
- Slow progress in AHP/CHP packages by EPC contractor

REASONS OF DELAY
Main plant layout was changed to avoid GM land which Govt. was not in position to handover due to encroachments.
Delay in Award of Critical Packages by BHEL. Air Cooled Condenser (ACC) Mechanical Package awarded in Mar’17 with a delay of 31months; ACC civil package was awarded in May’17 with a delay of 27 months.
Delay due to slow work progress by EPC agency (M/s BHEL). Slow progress of Air Cooled Condenser works by M/s BHEL may affect the current commissioning target of project.
Agitation by villagers for demand of additional compensation against already acquired land (about 2200 Acres). Project Work was completely stopped by the agitators for about 40 days during Local Agitation again started on
23.02.2022

12
Status as on 31-01-2024
TELANGANA THERMAL POWER PROJECT, St-I, Unit# 1 & 2 (2X800 MW ) / NTPC (CENTRAL SECTOR)
NTPC, Telangana, PO Ramagundam (Sub Office), Karim Nagar, Telangana - 505208
E-Gen Portal Registration No. ( U#1 - 1200001966; U#2 - 1200001967 )
Project Developer / Implementing Agency -
Main Plant Vendor : SG-BHEL, TG- GE
NTPC
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#1 May-2020 05-Sep-2023
Feb-2016
Unit#2 Nov-2020 Feb-2024
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal, Indigenous, Non- pit head ORIGINAL ESTIMATED COST
10599.00
COAL COMBUSTION OF THE PROJECT
Ultra-supercritical
TECHNOLOGY
LATEST ESTIMATED COST 10997.70
APPROVAL DATE / NTP Jan-2016
DATE OF FINANCIAL
29.01.2016
CLOSURE
EPC/BTG/BoP Contractor
SG Island – BHEL – 05.02.2016; TG Island – GE – 05.02.2016 YEAR WISE EXPENDITURE
Details (Package Wise)

2015-16 6.34

1360 MW power has been allocated to Telangana. Balance 240 MW is 2016-17 798.21
PPA
unallocated.
2017-18 1062.65
Linked with Mandakini-B captive coal mine (PRC-20 MMTPA);
however, NTPC has approached MoC on 26.12.2020 for surrendering
2018-19 2535.67
the coal mine. Tapering linkage against the linked coal mine was
COAL LINKAGE/FSA
initially allocated from WCL cost-plus. In July’2020, the linkage has
been shifted to SCCL. FSA signed with SCCL on 23.09.2023 for 7.2 2019-20 2599.45
Million Metric Ton per Annum of coal.
2020-21 1308.35
START UP POWER Start up Power has been granted for Telangana STPP by SRLDC on
AGREEMENT 26-6-2020 through RSTPS-TeSTPP 400 KV D/C line 2021-22 828.00
Tx Line Developer TSTRANSCO
2022-23 1195.27
i) TeSTPP-Narsapur, 400 KV, D/C
Tx Line Name Line.
POWER EVACUATION ii) TeSTPP- Ramadugu ,400 KV, EXPENDITURE OF Jan’2024 0
Tx Voltage Level
SYSTEM D/C line.
TOTAL EXPENDITURE (upto 11,572.70
Configuration of Tx Line 31.01.2024)
D/C
(S/C or D/C)
Being accommodated within the land possessioned with NTPC
LAND POSSESSION
Ramagundam project. No new land acquired for the project.

WATER ALLOCATION 60 cusecs from Yellampally Barrage on Godavari river

MOEF CLEARANCE 20.01.2016, Valid upto 19.01.2024

CIVIL AVIATION
29.03.2011
CLEARANCE

CPCB CLEARANCE Not Applicable

SPCB CLEARANCE Extension for Stg-1 approved by TSPCB up to 19-01-2023

FOREST CLEARANCE Not Applicable

13
Status as on 31-01-2024
TELANGANA THERMAL POWER PROJECT, Unit# 1 & 2 (2X800 MW, St-I) / NTPC (CENTRAL SECTOR)
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL) STATUS OF MAIN PLANT PACKAGE (BTG) : SG - BHEL, TG - GE
UNIT-01 UNIT-02 UNIT-01 UNIT-02
Sl. Packages AREA
% %
Actual / Actual / Completion Completion
Sl. MILESTONE
Original Date Anticipated Original Date Anticipated CIVIL 100% 100%
Date Date
1 BOILER STRUCTURE 100% 99%

1 COMPLETION OF BOILER Complete Complete PRESSURE PARTS 100% 100%


FOUNDATION
2 START OF BOILER ERECTION Mar-17 Dec-17 Sep-17 Dec-17 CIVIL 100% 100%

3 BOILER DRUM LIFTING (if sub-critical NA NA 2 TG STRUCTURE 100% 100%


unit)
4 BOILER CEILING GIRDER LIFTING Complete Complete TG ERECTION 100% 100%
COMPLETION
5 CONDENSER ERECTION START Feb-18 Jul-18 Aug-18 Feb-19 3 ESP UNDER PROGRESS 100% 99%

6 TG ERECTION START May-18 Aug-18 Nov-18 Mar-19 CIVIL WORK 99% 99%

7 HP PIPING ERECTION START May-19 Jun-20 Nov-19 Oct-22 MATERIAL SUPPLY 100% 100%
4 FGD
8 BOILER HYDRO TEST (DRAINABLE) Nov-18 Nov-21 May-19 Apr-22
COMPLETION ERECTION WORK 100% 100%
9 BOILER HYDRO TEST (NON- May-22 Aug-22
DRAINABLE) COMPLETION
10 TG BOX UP Apr-19 Sep-19 Oct-18 May-20 STATUS OF BOPs
11 HP PIPING ERECTION COMPLETION Aug-19 Jul-22 Feb-19 May-23 Anticipated UNIT-01 UNIT-02
Packages/ Scheduled
Vendor/Contracting Date of /Actual
12 START OF OIL FLUSHING Complete Complete Sl. Linked Project Award
Date of
Date of % %
Agency Completion
13 BOILER LIGHT UP Jun-19 Jun-22 Dec-19 Dec-22 Milestones Completion Completion Completion

14 CHEMICAL CLEANING COMPLETION Jul-19 Jul-22 Jan-20 Dec-22 30.08.19 (U1)


05.02.16 28.02.20(U2) Completed
1 Chimney BHEL 100% 100%

15 STEAM BLOWING START Sep-19 Aug-22 Feb-20 May-23 Conveyor Package – Tata 10.01.17 10.03.20 U1-Jun23
2 Coal HandlingPlant Projects Ltd U2-Feb’24 100% 98%
Wagon Tippler – 10.01.17 10.03.20 Feb-24
Tata Projects Ltd 85%
16 Stacker Reclaimer - U1-Sep22;
STEAM BLOWING COMPLETION Sep-19 Nov-22 Mar-20 Jun-23 10.01.17 10.03.20
Tata Projects Ltd U2-Feb’24 100% 90%
3 Ash Handling BHEL 05.02.16 27.11.19 U1-May23
U2- Jan’24 100% 99%
4 Fuel Oil System TATA Projects 10.01.17 09.01.20 Completed
100% 100%
17 5 Cooling Towers 10.01.17 10.01.20 Completed
ROLLING & SYNC. Nov-19 Mar-23 May-20 Aug-23 TATA Projects
100% 100%
6 CW Pump 10.01.17 10.02.20 Completed
TATA Projects
100% 100%
7 WPT Plant 10.01.17 10.03.20 Completed 100%
TATA Projects
100%
18 8 DM Plant 10.01.17 23.09.08 Completed 100%
FULL LOAD Jan-20 Jul-23 Jul-20 Feb-24 TATA Projects
100%
9 Compressed Air 10.01.17 29.10.14 Completed 100%
TATA Projects
System 100%
10 Fire Protection TATA Projects 10.01.17 10.05.20 U1-Apr23 (A); 100% 99%
U2- Feb’24
System
19
TRIAL RUN May-20 Nov-20 11 Switch Yard 10.01.17 10.12.19 Completed 100% 100 %
Sep-23 Feb-24 TATA Projects
12 Station Txer TATA Projects
10.01.17 10.06.20 Completed 100% 100 %

13 Unit Txer 10.01.17 10.06.20 U2-Aug23 100% 100 %


TATA Projects
20 Jun-20 Sep-23 Dec-20 Feb-24 14 Railway Siding TATA Projects 10.01.17 10.03.20 Feb’24 88% 90%
COD
Ramadugu Line
15 Power evacuation TSTransco Apr-18; Narsapur
Dec-19 Aug21 100% 100%
Line Aug-17

CRITICAL ISSUES
 Unit#2- Due to malfunctioning of electronic card, problem of temperature rise in turbine bearing, delaying in trial run activities.

REASONS OF DELAY
 Delay in Boiler design due to new De-NOx & De-SOx norms (New Env. norms came after opening of Price Bid and were incorporated in the contract).
Accordingly, there was delay in Completion of Basic Engineering and Supply of Boiler / TG structures.
 Slow progress by BHEL sub-agency M/s B&R.
 Delay in Sand supply / Procurement at site (Due to restrictions by State Government of Telangana).
 Delay due to ongoing COVID-19 pandemic since Mar’20. Non-availability of Industrial oxygen during second wave.

14
Status as on 31-01-2024
PATRATU TPS, Unit# 1, 2 & 3 (3X800 MW) / PVUNL (CENTRAL SECTOR)
Patratu Vidyut Utpadan Nigam Limited, Patratu, PO: PTPS, Patratu, Distt. Ramgarh, Jharkhand , PIN – 829119
E-Gen Portal Registration No. ( U#1 - 1200002399; U#2 - 1200002400; U#3 - 1200002401 )
Project Developer / Implementing Agency -
Main Plant Vendor - M/S BHEL (EPC-08.03.2018)
PVUNL
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#1 Jan-22 Sept-2024
Unit#2 Mar-2018 Jul-22 Mar-2025
Unit#3 Jan-23 Sept-2025
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal, Pithead ORIGINAL ESTIMATED COST
17112.00
COAL COMBUSTION OF THE PROJECT
Ultra Supercritical
TECHNOLOGY
LATEST ESTIMATED COST 18668.00
APPROVAL DATE / NTP Nov-2017
DATE OF FINANCIAL
CLOSURE
EPC/BTG/BoP Contractor
EPC package awarded to BHEL on 08.03.2018. YEAR WISE EXPENDITURE
Details (Package Wise)
-----
2015-16
-----
85% allocated to Jharkhand, PPA signed on 30.03.2016. 15% of 2016-17
PPA
powerwill remain as unallocated quota at the disposal of GoI
2017-18 992.11
12 MTPA for Ph-I from Banhardih Coal Mine at a distance of about
110 km. Banhardi Coal Mine transferred to PVUNL vide deed of
adherence signed on 02.06.2017. 2018-19 601.86
COAL LINKAGE/FSA
Bridge allocation granted by SLC(LT) upto 24-06-2024; Allocation 2019-20 695.09
from CCL; Coal quantity quantified is 9.17 MTPA.
2020-21 1228.66
START UP POWER Through 7.5 kms Transmission line : Patratu-Patratu (Main Plant to
AGREEMENT Katia Substation) D/C Line 2021-22 1846.48
Tx Line Developer JUSNL
2022-23 2849.76
i)Patratu (PVUNL) –Patratu, 400 kV
Tx Line Name D/C line (7.5 km).
POWER EVACUATION
Tx Voltage Level ii) Patratu STPP-Koderma, 400 KV D/c EXPENDITURE OF Jan’24 308.65
SYSTEM Line (160 Km). TOTAL EXPENDITURE
iii) Patratu STPP-Chandil, 400 KV D/c 12489.65
(upto 31.01.24)
Line (150 Km).
Configuration of Tx Line
D/C
(S/C or D/C)
Correction of 268.92 acres of land in the records of forest department
LAND POSSESSION
in favour of PVUNL and also change of nature of land as non-forest
Project is envisaged with Air Cooled Condenser Technology. In
WATER ALLOCATION principle commitment for 27 cusecs water available from Nalkari
DamReservoir vide agreement dt 25.01.2016 with GoJ.
EAC recommended for grant of EC for the project on EAC meeting
MOEF CLEARANCE held on 25.09.17. EC letter received on 07.11.17. Validity till
06.11.24.
CIVIL AVIATION
Received on 03.06.2016.
CLEARANCE
CPCB CLEARANCE Not Applicable

SPCB CLEARANCE SPCB Clearance: CTE received on 19.10.2018. Validity till 06.11.24.

FOREST CLEARANCE No forest land in the main plant area.

15
Status as on 31-01-2024
PATRATU TPS, Unit# 1, 2 & 3 (3X800 MW) / PVUNL (CENTRAL SECTOR)
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL ) STATUS OF MAIN PLANT PACKAGE (BTG) : M/S BHEL
UNIT-01 UNIT-02 UNIT-03 UNIT-01 UNIT-02 UNIT-03
Sl. Packages AREA
Original Anticipate Original Anticipate Original Anticipate % Completion % Completion % Completion
Sl. MILESTONE Date of d / Actual Date of d / Actual Date of d / Actual
Completio Date of Completio Date of Completio Date of CIVIL 81% 76% 70%
Completio Completio Completio
n
n
n
n
n
n
1 BOILER STRUCTURE 82% 81% 67%
1 COMPLETION OF BOILER FOUNDATION May-19 Apr-19 Nov-19 Dec-19 May-20 Jan-21 PRESSURE PARTS 97% 88% 52%
2 START OF BOILER ERECTION May-19 Aug-19 Nov-19 Dec-19 May-20 Jan-21 CIVIL 72% 54% 32%
3 BOILER DRUM LIFTING (if sub-critical unit) NA NA NA 2 TG STRUCTURE 100% 100% 29%
4 BOILER CEILING GIRDER LIFTING COMPLETION Feb-20 Mar-21 Aug-20 May-21 Feb-21 Jan-22
5 CONDENSER ERECTION START Feb-20 Sep-23 Aug-20 Apr-24 Feb-21 Jul-24 3 ESP UNDER PROGRESS 84% 88% 67%
6 TG ERECTION START Jun-20 Mar-22 Dec-20 Oct-22 Jun-21 May-24 CIVIL WORK 70% 71% 58%
7 HP PIPING ERECTION START Jul-20 Sept-22 Jan-21 Jun-23 Jul-21 Jun-24 MATERIAL SUPPLY 83% 57% 45%
4 FGD
8 BOILER HYDRO TEST (DRAINABLE) COMPLETION Jan-21 Mar-23 Jul-21 Aug-23 Jan-22 Oct-24
ERECTION WORK 32% 0% 0%
9 BOILER HYDRO TEST (NON-DRAINABLE) COMPLETION Jun-21 Apr-24 Dec-21 Aug-24 Jun-22 Apr-25
10 TG BOX UP May-21 Mar-23 Nov-21 Mar-24 May-22 Dec-24 STATUS OF BOPs (BHEL - EPC)
Anticipated/ UNIT-01 UNIT-02 UNIT-03
Scheduled
11 HP PIPING ERECTION COMPLETION May-21 Apr-24 Nov-21 Oct-24 May-22 May-25 Packages/ Linked Vendor/Contracting Date of Actual Date
Sl. Award
Date of
of
Project Milestones Agency Completion % Completion % Completion % Completion
Completion
12 START OF OIL FLUSHING Apr-21 18.11.23 Oct-22 Jul-24 Apr-22 Feb-25
U1-21.07.18; U2- U1-05.03.21; U2-
1 Chimney BHEL PSWR 26.07.18; U3-31.01.20 05.09.21; U3-05.03.22 Feb-25 88% 70% 49%
BHEL PSWR 12.01.2020 08.08.2021 Feb-25
13 BOILER LIGHT UP Jun-21 May-24 Dec-21 Aug-24 Jun-22 May-25 BHEL PSWR – Wagon Tippler 15.10.2020 27.07.2021 Feb-25
2 Coal Handling Plant 73% RCC complete
BHEL PSWR – Stacker 09.06.2021 23.06.2022 Feb-25 87.7% Structure complete
14 CHEMICAL CLEANING COMPLETION Jul-21 May-24 Jan-22 Oct-24 Jul-22 May-25 Reclaimer
3 Ash Handling Plant BHEL PSWR 15.10.2019 08.12.2021 Feb-25 73% RCC complete; 38.2% Structure complete
4 Fuel Oil System BHEL PSWR 07.10.2020 08.06.2021 Feb-25
15 STEAM BLOWING START Jul-21 May-24 Jan-22 Oct-24 Jul-22 May-25 70% civil works
5 ACC BHEL 08.04.2022 14.10.2021 Feb-25 56.20% 26.88% 29.04%
6 CW Pump house NA (ACC is envisaged) (Air Cooled Condenser)
16 STEAM BLOWING COMPLETION Sep-21 Jun-24 Mar-22 Nov-24 Sep-21 Jun-25
7 WPT Plant BHEL PSWR 14.01.2021 20.03.2021 Feb-25 55.0% RCC complete
8 DM Plant BHEL PSWR 27.03.2021 Feb-25
17 ROLLING & SYNC. Nov-21 Jul-24 May-22 Dec-24 Nov-22 Jul-25 55.0% RCC complete
9 Compressed Air System BHEL PSWR 04.07.2020 03.02.2021 Feb-25 96.2% Structure erection completed
10 Fire Protection System BHEL-PESD, Hyderabad 25.05.2021 18.05.2021 Feb-25
18 FULL LOAD Dec-21 Aug-24 Jun-22 Jan-25 Dec-22 Aug-25 98% RCC civil works
11 Switch Yard BHEL-TBG 01.05.2020 08.10.2021 Feb-25 90% RCC complete
12 Station Transformers BHEL-Bhopal 18.02.2021 Feb-25
19 TRIAL RUN Jan-22 Sept-24 Jul-22 Mar-25 Jan-23 Sept-25 30%
13 Unit Transformers BHEL Jhansi 17.02.2021 Feb-25 0%
14 Railway Siding PMC Contractor-M/s RITES 02.12.2019 01.04.22 Dec-23
20 COD Mar-22 Sept-24 Sep-22 Mar-25 Mar-23 Sept-25 28% (Award of sub pkg yet to be done)
15 Power Evacuation Lines JUSNL 08.10.2021 Feb-25 Patratu-Patratu Line – Civil:30%; Patratu-Koderma Line-Civil:0%

CRITICAL ISSUES
 Associated Transmission System: 03 nos. transmission lines are to be constructed by M/s JUSNL under State funding.
i) Patratu - Patratu (Plant to Katia Substation) 400 KV D/C Line (7.5 Kms) - Foundation and tower erection work is in progress. For work in forest area, Stage-I clearance is awaited from District Authority;
ii) Patratu STPP - Koderma (JUSNL) 400 kV D/C line (~160 km) – LOA issued in July’23 with completion schedule of 24 months. Detail survey work completed. Land Schedule verification under progress.
iii) Patratu STPP - Chandil 400 kV D/C line (~150 km)- LOA issued in July’23 with completion schedule of 24 months. Detail survey work in progress (130/141KM), balance is expected to be completed soon. Readiness of lines
(by JUSNL) are required for evacuation of power from the project.
 ACC works (BHEL) needs to be expedited.

REASONS OF DELAY
 Poor performance of few sub-agencies of BHEL.

16
TALCHER THERMAL POWER PROJECT, Unit# 1 & 2 (2X660 MW, St-III) / NTPC (CENTRAL SECTOR)
TALCHER THERMAL POWER PROJECT, P.O.: TALCHER THERMAL, DIST- ANGUL, ODISHA- 759101
E-Gen Portal Registration No. (U#1 - 1200003198; U#2 - 1200003199)
Project Developer / Implementing Agency -
Main Plant Vendor : SG-BHEL, TG- BHEL
NTPC
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#1 Nov-2026 Nov-2026
Sep-2022
Unit#2 May-2027 May-2027
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal ORIGINAL ESTIMATED COST
11843.75
COAL COMBUSTION OF THE PROJECT
Ultra-supercritical
TECHNOLOGY
LATEST ESTIMATED COST 11843.75
APPROVAL DATE / NTP Investment Approval: 26.08.2022
DATE OF FINANCIAL
CLOSURE
EPC/BTG/BoP Contractor
EPC Package for TTPP St-III(2X660 MW) awarded to M/s BHEL on YEAR WISE EXPENDITURE
Details (Package Wise)
27.09.2022
2021-22 45.00

PPA signed; Odisha SEB: 50% (660 MW) on 02.08.2022; Tamil Nadu 2022-23 453.14
PPA
SEB: 35% (460 MW) on 26.09.2022; Unallocated- 15%
EXPENDITURE OF Jan’2024 45.5
Available : as per the MoM of the Standing Linkage Committee (LT)
dated 10.04.2018; FSA Agreement with MCL under process; Source: TOTAL EXPENDITURE
COAL LINKAGE/FSA Bhuwaneswari/Jagannath mines of MCL 1056.78
(upto 31.01.2024)
Pithead, Dist – 30km; Grade: G-12; Quantity: 5.854 MMTPA

START UP POWER Startup power to be drawn from 400 KV grid. Application for
AGREEMENT connectivity to STU has been submitted on 01/12/2022.
Application for CTU connectivity to be submitted.
Tx Line Developer Yet to be awarded

Tx Line Name
POWER EVACUATION (400 kV Gas Insulated Switchyard)
Tx Voltage Level
SYSTEM

Configuration of Tx Line
-
(S/C or D/C)
Total Land: 194.82 Acre(Main Plant-191 Acre, Railway
LAND POSSESSION
Siding-1.48 Acre; Make up water -2.34 Acre to be acquired)
ROU/ROW of Land- 77.63 for Make up water Corridor.
Approval under process.

WATER ALLOCATION Available, Source: Up Stream of Samal Barrage from Brahmani River
Qty: 39 Cusec

MOEF CLEARANCE Received on 12.09.2018 and it is valid upto 12.09.2025


CIVIL AVIATION
Renewed on 22.05.2022 and valid upto 22.05.2030
CLEARANCE
ADDITIONAL REMARKS
CPCB CLEARANCE Received on 12.09.2018 and it is valid upto 12.09.2025 Ash Disposal:
SPCB CLEARANCE CTE Application submitted on 06.11.2022 (Application No -4474906) 6.43 Mcum of Quarry IV of Jaganath Mine Void
of MCL allocated for TTPP Stage-III which will
FOREST CLEARANCE Make up water Pump House: 1st stage received, Application for 2nd cater for 03 Years of Ash Disposal. For allocation
stage under process; Make up Corridor: There was delay in submission
of balance 17 Cum capacity, matter has been
of online application due to non-availability of PARIVESH PORTAL.
Online application for Stage-I submitted on 13.11.2022 and under taken up with MCL.
process at PCCF Odisha.

17
Status as on 31-01-2024
TALCHER THERMAL POWER PROJECT, St-III, Unit# 1 & 2 (2X660 MW) / NTPC (CENTRAL SECTOR)
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL) STATUS OF MAIN PLANT PACKAGE (BTG) : SG - BHEL, TG - GE
UNIT-01 UNIT-02 UNIT-01 UNIT-02
Sl. Packages AREA
% %
Actual / Actual / Completion Completion
Sl. MILESTONE
Original Date Anticipated Original Date Anticipated CIVIL 93% 45%
Date Date
1 BOILER STRUCTURE 2.50% 0%

1 COMPLETION OF BOILER PRESSURE PARTS 0% 0%


25.09.2023 Jan-24 25.01.2024 May-24
FOUNDATION
2 START OF BOILER ERECTION 26.09.2023 Jan-24 26.01.2024 May-24 CIVIL 45% 20%

3 BOILER DRUM LIFTING (if sub-critical 2 TG STRUCTURE 0% 0%


NA NA
unit)
4 BOILER CEILING GIRDER LIFTING 25.07.2024 Sept-24 25.11.2024 Mar-25 TG ERECTION 0% 0%
COMPLETION
5 CONDENSER ERECTION START 31.07.2024 Oct-24 30.11.2024 Apr-25 3 ESP UNDER PROGRESS 40% 30%

6 TG ERECTION START 07.08.2024 Oct-24 07.12.2024 Apr-25 CIVIL WORK 3% 0%

7 HP PIPING ERECTION START 04.08.2024 Oct-24 04.12.2024 Apr-25 MATERIAL SUPPLY 0% 0%


4 FGD
8 BOILER HYDRO TEST (DRAINABLE)
COMPLETION 26.07.2025 Sept-25 26.11.2025 Mar-26
ERECTION WORK 0% 0%
9 BOILER HYDRO TEST (NON-
DRAINABLE) COMPLETION 29.11.2025 Feb-26 29.03.2026 Aug-26
10 TG BOX UP 25.09.2025 Nov-25 25.01.2026 May-26 STATUS OF BOPs
11 HP PIPING ERECTION COMPLETION 25.01.2026 Mar-26 25.05.2026 Sept-26 Packages/ Anticipated UNIT-01 UNIT-02
Scheduled
Vendor/Contracting Date of /Actual
12 START OF OIL FLUSHING 27.09.2025 Nov-25 27.01.2026 May-26 Sl. Linked Project Award
Date of
Date of % %
Agency Completion
13 BOILER LIGHT UP 13.01.2026 Mar-26 13.05.2026 Sept-26
Milestones Completion Completion Completion
Nov-25 (U1)
14 CHEMICAL CLEANING COMPLETION 26.01.2026 Mar-26 26.05.2026 Sept-26
1 Chimney BHEL Sep-22 Nov-25 Mar-26 (U2)
50%
15 STEAM BLOWING START Jan-26 Jan-26 (U1)
27.02.2026 Apr-26 27.06.2026 Oct-26 Conveyor Package - BHEL Sep-22 May-26 (U2) 2%
2 Coal HandlingPlant
Jan-26 (U1)
Track Hopper- BHEL Sep-22 NA
May-26 (U2) 5%
16 Jan-26 (U1)
STEAM BLOWING COMPLETION Stacker Reclaimer - BHEL Jan-26
26.03.2026 May-26 26.07.2026 Nov-26 Sep-22 May-26 (U2) 2%
3 Ash Handling BHEL Apr-26 Apr-26 (U1)
Sep-22
Aug-26 (U2) 5.40%
4 Fuel Oil System BHEL Nov-25 Nov-25 (U1)
Sep-22 20% 20%
Mar-26 (U2)
17 5 Cooling Towers Dec-25 Dec-25 (U1)
ROLLING & SYNC. BHEL Sep-22
26.05.2026 Jul-26 26.09.2026 Jan-27 Apr-26 (U2) 10% 10%
6 CW Pump House and Nov-25 Nov-25 (U1)
BHEL Sep-22
Piping Mar-26 (U2) 12% 12%
7 WPT Plant BHEL Sep-25 Sep-25 (U1)
Sep-22
Jan-26 (U2) 3% 3%
18 8 DM Plant Jul-25 Jul-25 (U1)
FULL LOAD 25.06.2025 Aug-26 25.10.2026 Feb-26 BHEL Sep-22 Nov-25 (U2) 10.80% 10.80%
9 Compressed Air Dec-25 Dec-25 (U1)
BHEL Sep-22 Apr-26 (U2) 0% 0%
System
10 Fire Protection BHEL Sep-22
Aug-26 Aug-26 (U1)
10% 10%
System Dec-26 (U2)
19 11 Switch Yard Mar-26 Mar-26 (U1)
TRIAL RUN 24.11.2026 24.11.2026 24.05.2027 24.05.2027 BHEL Sep-22 26%
Jul-26 (U2)
12 Station Txer Apr-25 Apr-25 (U1)
BHEL Sep-22 Aug-25 (U2) 0% 0%
13 Generator Txer Apr-26 Apr-26 (U1)
BHEL Sep-22 Aug-26 (U2) 0% 0%
14 Unit Txer Apr-26 Apr-26 (U1)
20
COD BHEL Sep-22 Aug-26 (U2) 0% 0%
24.12.2026 24.12.2026 24.06.2027 24.06.2027 15 Railway Siding Jun-25 Jun-25 (U1)
RITES Dec-22 Jun-25 (U2) 0% 0%
16 Power evacuation a. ISTS connectivity: Talcher Stage-III to ISTS Pandiabili [Power Grid] pooling station (App.
120kms); b. STU connectivity: Talcher stage-III to Meramundali-B [OPTCL] (App.12kms).

CRITICAL ISSUES
1. Closure of Anand Bazaar – Jaganathpur Road passing through Main Plant area is awaited. This is critical in view of Safety and Security in construction area. Alternate road
(Jaganathpur bypass road) has already been constructed by NTPC.

2. Relocation of Bi-weekly Haat (Anand Bazar): There is a bi-weekly market located near the entrance gate of TTPS through which trucks/ trailers carrying construction/ project
materials pass. Relocation of the haat is required from NTPC land as the area becomes very crowded and is a bottleneck for safe movement of materials and Safety of public.

REASONS OF DELAY
-NA-

18
Status as on 31-01-2024

LARA SUPER THERMAL POWER PROJECT, St-II, Unit# 1 & 2 (2X800 MW ) / NTPC (CENTRAL SECTOR)
Lara Super Thermal Power Project, Village - Chhapora, PO/PS- Pussore. Distt.-Raigarh(C.G.)-496440
E-Gen Portal Registration No. ( U#1 - 1200003870 ; U#2 - 1200003871 )
Project Developer / Implementing Agency -
Main Plant Vendor : SG-BHEL, TG- GE
NTPC
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#1 Dec-2027 Dec-2027
Aug-2023
Unit#2 Jun-2028 Jun-2028
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal Based ORIGINAL ESTIMATED COST
15530.00
COAL COMBUSTION OF THE PROJECT
Ultra-Supercritical
TECHNOLOGY
LATEST ESTIMATED COST 15530.00
APPROVAL DATE / NTP 29.08.23
DATE OF FINANCIAL
CLOSURE
EPC/BTG/BoP Contractor
BHEL-EPC YEAR WISE EXPENDITURE
Details (Package Wise)

Upto 2022-23 252

PPA signed. Consent from Beneficiaries available Chhattisgarh: 50%, EXPENDITURE OF Jan’2024 22.21
PPA Power allocation to following states as per MoP allocation:
Gujarat, Madhya Pradesh, Maharashtra, Goa, Daman & Diu, DNH TOTAL EXPENDITURE (upto 588.21
31.01.2024)
COAL LINKAGE/FSA 7 MMTPA coal from Talaipalli Coal block allocated to NTPC

START UP POWER To be finalised by CTU


AGREEMENT
Tx Line Developer To be finalised by CTU
 ISTS connectivity: Talcher Stage-
Tx Line Name III to ISTS Pandiabili [Power Grid]
POWER EVACUATION pooling station
Tx Voltage Level
SYSTEM  STU connectivity: Talcher stage-III
to Meramundali-B [OPTCL]
Configuration of Tx Line
To be finalised by CTU
(S/C or D/C)

LAND POSSESSION Available; Land available for Stage-II: ~ 520 acres

Available; 76 cusec for Stage-II; Source is Mahanadi River, from


WATER ALLOCATION
Saradih Barrage (38 kms from Plant).

MOEF CLEARANCE Available (issued on 17.07.23)

CIVIL AVIATION
Available Valid up to 17.05.2030
CLEARANCE

CPCB CLEARANCE Not applicable

SPCB CLEARANCE In Process

FOREST CLEARANCE Not applicable

19
Status as on 31-01-2024
LARA SUPER THERMAL POWER PROJECT, Unit# 1 & 2 (2X800 MW, St-II) / NTPC (CENTRAL SECTOR)
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL) STATUS OF MAIN PLANT PACKAGE (BTG) : SG - BHEL, TG - BHEL
UNIT-01 UNIT-02 UNIT-01 UNIT-02
Sl. Packages AREA
% %
Actual / Actual / Completion Completion
Sl. MILESTONE
Original Date Anticipated Original Date Anticipated CIVIL 0% 0%
(Tentative Dates)
Date Date
1 BOILER STRUCTURE 0% 0%

1 COMPLETION OF BOILER PRESSURE PARTS 0% 0%


FOUNDATION
2 START OF BOILER ERECTION Dec-2024 Dec-2024 Jun-2025 Jun-2025 CIVIL 0% 0%

3 BOILER DRUM LIFTING (if sub-critical 2 TG STRUCTURE 0% 0%


unit)
4 BOILER CEILING GIRDER LIFTING Jul-2025 Jul-2025 Jan-2026 Jan-2026 TG ERECTION 0% 0%
COMPLETION
5 CONDENSER ERECTION START Aug-2025 Aug-2025 Dec-2025 Dec-2025 3 ESP UNDER PROGRESS 0% 0%

6 TG ERECTION START Sep-2025 Sep-2025 Jan-2026 Jan-2026 CIVIL WORK 0% 0%

7 HP PIPING ERECTION START Jun-2026 Jun-2026 Dec-2026 Dec-2026 MATERIAL SUPPLY 0% 0%


4 FGD
8 BOILER HYDRO TEST (DRAINABLE) 0% 0%
COMPLETION ERECTION WORK
9 BOILER HYDRO TEST (NON- Oct-2026 Oct-2026 Feb-2027 Feb-2027
DRAINABLE) COMPLETION
10 TG BOX UP Jan-2027 Jan-2027 Jul-2027 Jul-2027 STATUS OF BOPs
11 HP PIPING ERECTION COMPLETION Feb-2027 Feb-2027 Aug-2027 Aug-2027 Packages/ Anticipated UNIT-01 UNIT-02
Scheduled
Vendor/Contracting Date of /Actual
12 START OF OIL FLUSHING Feb-2027 Feb-2027 Aug-2027 Aug-2027 Sl. Linked Project Award
Date of
Date of % %
Agency Completion
13 BOILER LIGHT UP Feb-2027 Feb-2027 Nov-2027 Nov-2027 Milestones Completion Completion Completion

14 CHEMICAL CLEANING COMPLETION Aug’23 U#1-Oct26 U#1-Oct26 0% 0%


Apr-2027 Apr-2027 Oct-2027 Oct-2027
1 Chimney BHEL U#2-Feb27 U#2-Feb27
Apr-2027 Apr-2027 Oct-2027 Oct-2027
15 STEAM BLOWING START Conveyor Package - Aug’23 U#1-Dec26 U#1-Dec26 0% 0%
2 Coal HandlingPlant U#2-Apr27 U#2-Apr27
Jun-2027 Jun-2027 Dec-2027 Jan-2028 Wagon Tippler – NA NA NA NA NA NA
Stacker Reclaimer - Aug’23 U#1-Dec26 U#1-Dec26 0% 0%
16 U#2-Apr27 U#2-Apr27
STEAM BLOWING COMPLETION
3 Ash Handling BHEL Aug’23 U#1-Feb27 U#1-Feb27 0% 0%
U#2-Jun27 U#2-Jun27
4 Fuel Oil System BHEL Aug’23 U#1-Oct26 U#1-Oct26 0% 0%
Sep-2027 Sep-2027 Feb-2028 Feb-2028
U#2-Feb27 U#2-Feb27
17
ROLLING & SYNC. 5 Cooling Towers BHEL Aug’23 U#1-Sep26 U#1-Sep26 0% 0%
U#2-Jan27 U#2-Jan27
6 CW Pump Aug’23 U#1-Sep26 U#1-Sep26 0% 0%
BHEL
U#2-Jan27 U#2-Jan27
7 WPT Plant Aug’23 U#1-Aug26 U#1-Aug26 0% 0%
Nov-2027 Nov-2027 May-2028 May-2028 BHEL
U#2-Dec26 U#2-Dec26
18
FULL LOAD 8 DM Plant Aug’23 U#1-Jun26 U#1-Jun26 0% 0%
BHEL
U#2-Oct26 U#2-Oct26
9 Compressed Air Aug’23 U#1-Sep26 U#1-Sep26 0% 0%
BHEL
System U#2-Jan27 U#2-Jan27
10 Fire Protection Aug’23 U#1-Jul27 U#1-Jul27 0% 0%
Dec-2027 Dec-2027 Jun-2028 Jun-2028 BHEL
System U#2-Nov27 U#2-Nov27
19
TRIAL RUN 11 Switch Yard Aug’23 U#1-Feb27 U#1-Feb27 0% 0%
BHEL
U#2-Jun27 U#2-Jun27
12 Station Txer Aug’23 U#1-Feb26 U#1-Feb26 0% 0%
BHEL
U#2-Jun26 U#2-Jun26
Jan-2028 Jan-2028 Jul-2028 Jul-2028 13 Unit Txer Aug’23 U#1-Apr27 U#1-Apr27 0% 0%
BHEL
U#2-Aug27 U#2-Aug27
20 0% 0%
COD 14 Railway Siding RITES Application filed to Railways for FR
approval
15 Power evacuation Application for connectivity submitted

CRITICAL ISSUES
---------

REASONS OF DELAY
-----------

20
Status as on 31-01-2024
GHATAMPUR THERMAL POWER PROJECT, Unit# 1, 2 & 3 (3x660 MW) / NUPPL (CENTRAL SECTOR)
Near Village Lahurimau-Kasimpur, Ghatampur Tehsil, P.O.: Samuhi-209206, Kanpur Nagar District, Uttar Pradesh
E-Gen Portal Registration No. (U#1 - 1200002439; U#2 - 1200002440; U#3 - 1200002441)
Project Developer / Implementing Agency -
Main Plant Vendor: SG- M/s L&T/MHI, TG- M/s GE
NUPPL
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#1 May-2020 Mar-2024
Unit#2 Aug-2016 Nov-2020 July-2024
Unit#3 May-2021 Oct-2024
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal, Indigenous ORIGINAL ESTIMATED COST
17237.80
COAL COMBUSTION OF THE PROJECT
Supercritical
TECHNOLOGY
LATEST ESTIMATED COST 19406.12
APPROVAL DATE / NTP GoI Sanction - 27.07.2016
Contractor Details: 1. SG Package (GA1)- L&T-MHI Power DATE OF FINANCIAL
22.06.2021
Boilers Pvt. Ltd/ LoA Date-02-08-2016 CLOSURE
EPC/BTG/BoP Contractor 2. TG Package (GA2)- GE Power Systems India Pvt. Ltd /LoA Date-
YEAR WISE EXPENDITURE
Details (Package Wise) 02-08-2016
3. BoP Package (GA3)- BGR Energy Systems Ltd / LoA Date-21-11-
2016 2016-17 927.76

75% PPA Signed with Uttar Pradesh Power Corporation 2017-18 1228.45
PPA
Ltd.(UPPCL). Balance 25% PPA signed with Assam PDCL.
2018-19 3517.83
Allocation Date- 03.10.2016. Allocated Mine (Source) - Pachwara
South Coal Block Grade - G10 Quantity- Net Geological Reserve
2019-20 3525.17
373.52 MT. Extractable reserve - 262.84MT; Pachwara South Coal
COAL LINKAGE/FSA Block will be fully functional by the end of Financial Year 2026-27 and
2020-21 2260.09
will be able to meet the coal requirement of NUPPL. Hence, NUPPL is
seeking coal under bridge linkage by the time Pachwara South Coal
Block will be fully functional. 2021-22 1901.77

There are four incoming lines for 132 KV Start-up power. Four lines
2022-23 1511.60
are from: 1. Sarh-1 to NUPPL, 2. Ghatampur to NUPPL, 3. Sarh-2 to
START UP POWER
NUPPL, 4. Hamirpur to NUPPL; Out of four two are connected and
AGREEMENT EXPENDITURE OF Jan’2024 179.95
we are availing power through two lines (Ghatampur to NUPPL &
Sarh-2 to NUPPL). TOTAL EXPENDITURE
16732.32
Tx Line Developer M/S GTL (upto 31.01.2024)
i)765 KV, S/C, Ghatampur-Agra line;
Tx Line Name ii) 765 KV, S/C, Ghatampur- Hapur
POWER EVACUATION
Tx Voltage Level Line;
SYSTEM
iii) 400 KV D/C,Ghatampur-Kanpur
line
Configuration of Tx Line Both
(S/C or D/C)
Total Pocket land-52.33 Ha. (As per initial approval); Total Pocket
LAND POSSESSION
land registered/ Acquired- 47.4790 Ha. (As per current reconciliation);
WATER ALLOCATION 80 cusec from UP Irrigation department (44.6 km from GTPP)
Clearance obtained date from concerned authority-: 17.06.2015
MOEF CLEARANCE
validity of it (If any).:- 7 Years
CIVIL AVIATION Clearance obtained date from concerned authority:- 13.12.2013
CLEARANCE Validity : - 5 Years, NUPPL had sent compliance to AAI regarding the
CPCB CLEARANCE NOT APPLICABLE
Clearance obtained date from concerned authority,:- 17.11.2017;
SPCB CLEARANCE
validity of it.- 5 Years
FOREST CLEARANCE NOT APPLICABLE

21
Status as on 31-01-2024
GHATAMPUR THERMAL POWER PROJECT, Unit# 1, 2 & 3 (3x660 MW) / NUPPL (CENTRAL SECTOR)
UNIT WISE MILESTONES ANTICIPATED / ACTUAL ) STATUS OF MAIN PLANT PACKAGE (BTG) : SG - L&T MHI, TG - GE
UNIT-01 UNIT-02 UNIT-03 UNIT-01 UNIT-02 UNIT-03
Anticipate Anticipate Original Date Anticipate
Sl. Packages AREA
Original Original % Completion % Completion % Completion
Sl. Date of d / Actual Date of d / Actual of d / Actual
Milestones Date of Date of Date of CIVIL 96% 92% 93%
Completio Completio Completion
n Completio n Completio Completio
n n n
1 BOILER STRUCTURE 99% 98% 97%
1 COMPLETION OF BOILER FOUNDATION 01.01.2017 17.03.2017 01.07.2017 21.10.2020 28.12.2017 29.01.2021 PRESSURE PARTS 100% 100% 100%
2 START OF BOILER ERECTION 01.09.2017 27.02.2018 01.03.2018 30.06.2018 28.08.2018 04.12.2018 CIVIL 100% 100% 99%
3 BOILER DRUM LIFTING (if sub-critical unit) NA NA NA 2 TG
STRUCTURE 100% 100% 100%
4 BOILER CEILING GIRDER LIFTING COMPLETION 01.05.2018 25.11.2018 01.11.2018 04.04.2019 01.05.2019 12.09.2019
5 CONDENSER ERECTION START 19.07.2018 09.03.2019 19.01.2019 03.01.2020 19.07.2019 02.03.2021 3 ESP UNDER PROGRESS 100% 100% 99%
6 TG ERECTION START 03.07.2018 08.02.2019 03.01.2019 29.02.2020 03.07.2019 30.04.2021 CIVIL WORK
7 HP PIPING ERECTION START 12.01.2019 30.10.2019 12.07.2019 21.02.2019 12.01.2019 30.06.2021 MATERIAL SUPPLY GA-3 Package material shifting from FGD area is
4 FGD under progress, 1900Mt of GA-3 material already
8 BOILER HYDRO TEST (DRAINABLE) NA NA NA
COMPLETION ERECTION WORK shifted.

9 BOILER HYDRO TEST (NON-DRAINABLE) 01.05.2019 06.01.2020 01.11.2019 24.02.2021 01.05.2020 29.08.2021
COMPLETION
STATUS OF BOPs
Anticipated/ UNIT-01 UNIT-02 UNIT-03
Scheduled
10 TG BOX UP 02.07.2019 23.10.2019 02.01.2020 15.05.2021 02.07.2020 15.12.2022 Packages/ Linked Vendor/Contracting Date of Actual Date
Sl. Award
Date of
of
Project Milestones Agency(M/s Completion % Completion % Completion % Completion
Completion
11 HP PIPING ERECTION COMPLETION 10.06.2019 31.08.2021 10.06.2020 28.02.2023 12.06.2020 30.06.2023 BGR)
1 Chimney BGR Energy System Ltd. 21.11.2016 20.11.2019 U1-Feb 24; 99.25% 72.25% 36.36%
U2-May 24;
U3-July 24
Conveyor Pkg – BGR Energy 21.11.2016 20.07.2019 Feb24, Apr24, 70% 19% 9%
12 START OF OILFLUSHING 30.11.2019 27.10.2020 31.05.2020 07.11.2022 30.11.2020 05.04.2024 System Ltd. May24
2 Coal Handling Plant Wagon Tippler - BGR Energy 21.11.2016 U1-Jul19, U1-Mar24, 68% 0%
System Ltd. U2&3-Jan20 U2&3-Apr24
Stacker Reclaimer - BGR 21.11.2016 U1-Jun19, U1-Jun24, 27% 9%
13 BOILER LIGHT UP 30.11.2019 28.02.2022 30.05.2020 31.03.2024 30.11.2020 31.05.2024 Energy System Ltd. U2&3-Feb20 U2&3-Jul24
3 Ash Handling Plant BGR Energy System Ltd. 21.11.2016 Jul19, Mar20, Feb24, 67% 68% 56%
Feb20 May24, Jun24
4 Fuel Oil System L&T MHI Power Boilers Pvt 21.11.2016 24.10.2019 Mar-24 99%
30.10.2019 24.07.2021 30.04.2020 29.30.2024 30.10.2020 30.04.2024 Ltd
14 CHEMICAL CLEANING COMPLETION
5 Cooling Towers BGR Energy System Ltd. 21.11.2016 20.11.2020 Feb24, July24, Civil:90%, Mech.47% Civil:63%, Merch. 0% Civil:42.15%, Mech.
Oct24 0%
6 CW Pump house BGR Energy System Ltd. 21.11.2016 20.11.2020 Feb24, 99% 25% 20%
15 STEAM BLOWING START 15.12.2020 23.06.2022 30.05.2020 05.04.2024 30.11.2020 15.06.2024 Mar24,Aprr24
7 WPT Plant BGR Energy System Ltd. 21.11.2016 20.04.2019 Feb-24 96%
8 DM Plant BGR Energy System Ltd. 21.11.2016 20.04.2019 Feb-22 (A) 100%
16 STEAM BLOWING COMPLETION 30.01.2020 13.08.2022 15.06.2020 10.035.2023 15.12.2020 10.07.2024
9 Compressed Air System L&T MHI Power Boilers Pvt 02.08.2016 20.07.2019 Mar-23 (A) 100%
Ltd
10 Fire Protection System BGR Energy System Ltd. 21.11.2016 20.11.2020 Feb24, 69% 13% 3%
17 ROLLING & SYNC. 01.03.2020 04.11.2023 31.08.2020 31.05.2024 01.03.2021 31.07.2024 May24, Jul24
11 Switch Yard BGR Energy System Ltd. 21.11.2016 20.02.2020 Mar’24 400kV-59%, 765kV-96%, Outdoor Switchyard-80%
12 Station Transformers GE-Power Systems India Pvt. 02.08.2016 Apr19, Oct19, Feb21(A),
Ltd. 100.0% 100.0% 95.0%
18 FULL LOAD 01.04.2020 Mar-24 31.10.2020 20.07.2024 01.04.2021 20.10.2024 Apr20 Aug22(A),
Mar-24
13 Unit Transformers GE-Power Systems India Pvt. 02.08.2016 Apr19, Oct19, Jul22(A), 100.0% 100% 95.0%
Ltd. Dec22 (A),
Apr20
Mar-24
14 Railway Siding RITES 29.03.2019 28.03.2021 Jun-24 Civil work – 98.76% Electrical – 93%
19 TRIAL RUN 29.05.20 Mar-24 27.11.20 July-24 29.05.21 Oct-24
26.02.2020 17.05.2020(A) 400kV GTPS-Kanpur -100%
15 Power Evacuation Lines Ghatampur Transmission Ltd 12.06.2018 26.09.2020 27.03.2021(A) 765kV GTPS-Agra -100%
20 COD 01.06.20 Apr-24 30.11.20 July-24 01.06.21 Oct-24
26.03.2021 25.12.2021(A) 765kV GTPS-Hapur - 100%

CRITICAL ISSUES
- Slow work progress in BoP areas i.e. CHP, AHP.
- Delay in material supply in CHP (Wagon Tippler, S/R)
REASONS OF DELAY
Work of BoP areas had been put on hold in August 2021 site due to financial issues being faced by M/s BGR.
22
NLC TALABIRA TPP, Unit# 1, 2 & 3 (3X800 MW) / NLC (CENTRAL SECTOR)
Office of the CGM & Project Head, Talabira Thermal Power Project, NLC India Ltd, Ainthapalli, Sambalpur – 768001
E-Gen Portal Registration No. ( U#1 - 1200003602 ; U#2 - 1200003603 ; U#3 - 1200003604 )
Project Developer / Implementing Agency -NLCIL Main Plant Vendor - M/S BHEL (EPC, LoA -12.01.2024)
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#1 May-2028 (Tentative) May-2028 (Tentative)
Unit#2 12-01-2024 Nov-2028 (Tentative) Nov-2028 (Tentative)
Unit#3 May-2029 (Tentative) May-2029 (Tentative)

CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)


FUEL TYPE Coal, Pithead ORIGINAL ESTIMATED 19,422.44
COST OF THE PROJECT
COAL Ultra-Supercritical
LATEST ESTIMATED 27,212.96
COMBUSTION
COST
TECHNOLOGY
DATE OF FINANCIAL
APPROVAL DATE / NTP - Within 11 months from the date of submission
CLOSURE
NTP of price bid (29.12.2023)
YEAR WISE EXPENDITURE
PPA "100% PPA available.
2017-18 1.01
PPA signed with:
a) TANGEDCO for 1500 MW on 16.03.2022(62.50%) 2018-19 28.3
b) Puducherry Electricity Dept for 100 MW on 2019-20 2.82
09.05.2022 (4.17%) 2020-21 2.05
c) KSEBL for 400 MW on 19.10.2022 (16.67%) 2021-22 21.31
d) GRIDCO for 400 MW on 28.09.2023 (16.67%)" 2022-23 519.40
COAL Coal Linkage from Talabira II & III OCP 10.56
LINKAGE/FSA Million Tonnes of coal per annum. GCV of about 3700 2023-24 (Upto Jan’24) 238.39
kCal/kg. [Grade: G-12] TOTAL EXPENDITURE 813.28
(up to 31.01.24)
START UP POWER Start up power will be drawn from CTU network,
AGREEMENT planned at 36th month from the date of NTP. Start up
power agreement will be made with ERLDC as per
CERC guidelines and prior to 36th month.
POWER Out of 2400 MW project, the 2000 MW will be
EVACUATION connected at CTU substation, and 400 MW will be
SYSTEM connected at STU substation. The power required for
Interstate Transmission will be evacuated through 2
Nos. D/C 765 KV transmission lines (LILO) to
Jharsuguda (Sundargarh) Substation & Angul
Substation of PGCIL, which is at a distance of about 25
km. The power required for the state of Odisha will be
evacuated through 1 no. D/C 400 kV transmission line
to nearby OPTCL Substation (Lapanga).
LAND POSSESSION "Requirement- 1694.5 Ac.
Advance Posession: 692 Ac.
Land in Use: 0 Ac."
WATER The Govt. of Odisha has granted approval for 90
ALLOCATION cusecs for the Phase-I 3X 800 MW and Phase-II
1x800 MW project from Hirakud Reservoir.
MOEF "EC Obtained on 02.02.2021
CLEARANCE (Validity 7 years from 02.02.2021)"
CIVIL AVIATION Obtained on 18.07.2018 from AAI
CLEARANCE
CPCB Not Applicable
CLEARANCE
SPCB CLEARANCE Not Applicable

FOREST Not Applicable


CLEARANCE

23
Status as on 31-01-2024
NLC TALABIRA TPP, Unit# 1, 2 & 3 (3X800 MW) / NLC (CENTRAL SECTOR)
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL ) STATUS OF MAIN PLANT PACKAGE (BTG) / SG - DPSI, TG - Power Machine, Russia
UNIT-01 UNIT-02 UNIT-03 SI PACKAGE AREA UNIT-01 UNIT-02 UNIT-03
Original Actual / Original Actual / Original Actual / CIVIL
Date of Anticipat Date of Anticipat Date of Anticipat 1 BOILER STRUCTURE
SI. Milestone Completi ed Date Completi ed Date Completi ed Date PRESSURE PARTS
on of on of on of CIVIL
Completi Completi Completi 2 TG STRUCTURE
on on on TG ERECTION
1 Completion Of 3 ESP UNDER PROGRESS
Boiler CIVIL WORK
Foundation 4 FGD MATERIAL SUPPLY
2 Start Of Boiler ERECTION WORK
Erection
3 Boiler Ceiling STATUS OF BOPs
Girder Lifting Sl. Packages/ Vendor/Contra Date of Schedule Ant/
Completion Linked Project cting Agency Award d Date of Actual
4 Condenser Milestones (DPSI) Comp. Date of UNI UNI UNI
Erection Start Comp. T01 T02 T03
5 TG Erection
Start 1 Chimney
6 HP Piping
Erection Start Coal Handling
2
7 Boiler Hydro Plant
Test (Drainable) 3 Ash Handling
Completion Plant
8 Boiler Hydro 4 Fuel Oil
Test (Non- System
Drainable)
5 Cooling
Completion
Towers
9 TG BOX UP
6 CW Pump
10 HP Piping house
Erection
7 WPT Plant
Completion
8 DM Plant
11 Start Of Oil
9 Compressed
Flushing
Air System
12 Boiler Light Up
10 Fire Protection
13 Chemical System
Cleaning
11 Switch Yard
Completion
12 Station
14 Steam Blowing
Transformers
Start
13 Unit
15 Steam Blowing
Transformers
Completion
14 Railway Siding
16 Rolling & Sync.
15 Power
17 Full Load
Evacuation
18 Trial Run
Lines
19 COD

CRITICAL AREAS
-

REASONS OF DELAY
-

24
KHURJA STPP, Unit# 1 & 2 (2x660 MW) / THDC (CENTRAL SECTOR)
Khurja, Distt.-Bulandshahar, Uttar Pradesh -203 131
E-Gen Portal Registration No. (U#1 - 1200002023; U#2 - 1200002024 )
Project Developer / Implementing Agency - Main Plant Vendor: SG Pkg. - M/s L&T/MHI and TG Pkg.- BHEL
THDC
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#1 Jul-2023 Jun-2024
Aug-2019
Unit#2 Jan-2024 Sep-2024
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal, Indigenous ORIGINAL ESTIMATED COST
11089.42
COAL COMBUSTION OF THE PROJECT
Ultra Supercritical
TECHNOLOGY
LATEST ESTIMATED COST Not Revised
APPROVAL DATE / NTP 07.03.2019.
EPC/BTG/BoP Contractor Zero Date : 29.08.2019 (with respect to Award of Main Plant Package DATE OF FINANCIAL
Details (Package Wise) i.e. Steam Generator & Associated Packages) CLOSURE
PPAs for entire off take-off power to be generated from Khurja STPP YEAR WISE EXPENDITURE
have been signed by THCDIL prior to 05.01.2011 with Uttar Pradesh,
Uttrakhand, Rajasthan, Himachal Pradesh and Delhi. Out of 1320
PPA 2016-17 338.92
MW, 60% power (792 MW) is to be supplied to UP & balance 40%
power (528 MW) is to be supplied to other beneficiary states as per
allocation to be done by Ministry of Power. 2017-18 10.66

For Coal linkage, Ministry of Coal, GoI vide allotment order 2018-19 148.87
dtd.17.01.2017 has allotted Amelia Coal Mine in District Singraulli,
Madhya Pradesh to THDCIL to meet out fuel requirements of the
COAL LINKAGE/FSA 2019-20 439.95
project. Grade of Coal: G9 (Avg. GCV = 4746 Kcal/Kg). Net
Geological Reserve in Amelia Coal Mine is 162.05 Million Ton (OC)
out of this Extractable Coal Reserve is 139.48 Million Ton. 2020-21 789.69

Connectivity has been granted by CTU vide its letter 2021-22 2158.93
NoC/CTU/N/05/1200002404 dated.18.03.2020 for evacuation of 528
MW power from Khurja (2x660 MW) STPP to ISTS beneficiaries.
2022-23 2825.84
START UP POWER Signing of Connectivity agreement is under process. In line with the
AGREEMENT granted connectivity, power evacuation system is under
implementation through Power Grid Corporation Of India Limited and EXPENDITURE OF Jan’2024 208.30
is likely to completed by [Link] THDCIL will request TOTAL EXPENDITURE (upto
RLDC for availing start up power as per CERC Regulations. 9428.30
31.01.2024)
Tx Line Developer PGCIL and UPPTCL
i) Khurja STPP- Aligarh 400 KV, D/C
Tx Line Name line (PGCIL)
POWER EVACUATION ii) Aligarh-Shamli 400 KV line , D/C,
Tx Voltage Level
SYSTEM LILOing at Khurja STPP (UPPTCL).

Configuration of Tx Line D/C


(S/C or D/C)
Small Patches of land within the boundary of already acquired 1201
LAND POSSESSION
Acre land by UPSIDC and handed over to THDCIL .
Formal water commitment letter for providing 43 Cusec water for
Makeup Water System from Upper Ganga Canal at just 11 Km from
WATER ALLOCATION
Project site issued by Water Resource Department, GoUP on
12.06.2014.
Environmental Clearance has been accorded to Khurja STPP by
MOEF CLEARANCE
MOEF&CC on 30.03.2017 with validity upto 29.03.2024.
Clearance for construction of chimney for Khurja STPP has been
CIVIL AVIATION
obtained from Airport Authority of India (AAI) on 19.04.2018 with
CLEARANCE
validity up to 17.07.2023.
CPCB CLEARANCE NOT APPLICABLE
“Consent to Establish” has been granted by SPCB Uttar Pradesh on
SPCB CLEARANCE
13.06.2018 with validity upto 01.06.2023.
FOREST CLEARANCE NOT APPLICABLE
25
KHURJA SUPER STPP, Unit# 1 & 2 (2x660 MW) / THDC (CENTRAL SECTOR)
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL) STATUS OF MAIN PLANT PACKAGE (BTG) : M/s L&T MHI Power Boilers Pvt.
UNIT-01 UNIT-02 UNIT-01 UNIT-02
Sl. Packages AREA
% %
Sl. MILESTONE Actual / Actual /
Original Date Anticipated Original Date Anticipated CIVIL 100% 100%
Date Date
1 BOILER STRUCTURE 86.11% 56.27%

1 COMPLETION OF BOILER FOUNDATION 29.09.2020 20.01.2021 29.03.2021 15.11.2021 PRESSURE PARTS 100% 100%

2 START OF BOILER ERECTION 29.10.2020 20.02.2021 29.04.2021 17.08.2021 CIVIL 99.97% 99.60%

3 BOILER DRUM LIFTING (if sub-critical unit) NA NA 2 TG STRUCTURE 100% 100%


BOILER CEILING GIRDER LIFTING
4 28.05.2021 12.02.2022 28.11.2021 09.09.2022 PRESSURE PARTS 100% 5.00%
COMPLETION
5 CONDENSER ERECTION START 02.09.2021 25.03.2022 02.03.2022 19.01.2023 3 ESP UNDER PROGRESS 84.00% 12.46%

6 TG ERECTION START 03.09.2021 25.05.2022 03.03.2022 25.02.2023 100 % RCC 85%


CIVIL WORK completed
7 HP PIPING ERECTION START 28.06.2021 20.10.2022 28.12.2021 28.02.2023
4 FGD
BOILER HYDRO TEST (DRAINABLE)
8 COMPLETION 29.05.2022 15.03.2023 29.11.2022 02.11.2023 MATERIAL SUPPLY 92.00% 100%
BOILER HYDRO TEST (NON-DRAINABLE)
9 NA NA NA NA ERECTION WORK 57.00 % 49.51%
COMPLETION
10 TG BOX UP 04.08.2022 20.07.2023 04.02.2023
May-24 STATUS OF BOPs
11 HP PIPING ERECTION COMPLETION 26.10.2022 Feb-24 26.04.2023
Feb-24 Anticipated UNIT-01 UNIT-02
Scheduled
Packages/ Linked Vendor/Contracting Agency Date of /Actual
Sl. Date of % %
Project Milestones (EPC- BHEL) Award Date of
May-24 Completion
12 BOILER LIGHT UP 29.10.2022 Feb-24 29.04.2023 Completion Completion Completion

Unit-1: RCC- 100%; Unit-2:


1 Chimney L&T MHI Power Boilers Pvt. Ltd 27.09.2020 14.04.2023 U#1-Feb’24
U#2-Jun’24 RCC-100%

Apr-24
13 CHEMICAL CLEANING COMPLETION 29.10.2022 Mar-24 29.04.2023
Thyssenkrupp Industries India Pvt.
2 Coal Handling Plant 04.08.2021 04.12.2023 Apr.’24 66%
Ltd.

M/s L&T MHI Power Boilers Pvt.


3 Ash Handling Plant Ltd 11.06.2020 20.02.2023 Apr’24 100% of Piling and 88% of RCC
M/s L&T MHI Power Boilers Pvt.
14 OIL FLUSHING COMPLETION 03.11.2022 07.11.2023 03.05.2023 Jun-24 4 Fuel Oil System
Ltd
30.09.2021 08.10.2022 15,Dec-23 100% LDO tanks; 100% FOPH

U-1: 99% of U-2: 98% of


16.04.2021/ 14.06.2023/ Feb-24/
5 Cooling Towers M/s Paharpur Cooling Towers Ltd civil work civil work
13.10.2021 14.12.2023 Mar-24
completed completed

15 STEAM BLOWING START 29.11.2022 Mar-24 29.05.2023 Apr-24 95%


6 CW Pump house Flowmore Ltd. 01.10.2021 30.09.2023 Mar-24

7 WPT Plant 30.11.2021 25.09.2023 25-01-24 Civil : 100% Mech: 100%

Mar-24 May-24 8 DM Plant


16 STEAM BLOWING COMPLETION 29.12.2022 29.06.2023 Gaja Engineering Pvt. Ltd. 15.02-24
DM Water Transfer Pump 30.11.2021 30.09.2023 Civil : 100% Mech: 90%
9
House
M/s L&T MHI Power Boilers Pvt. 08.10.22 Civil Work: 100%
10 Compressed Air System 31-01-24
Ltd
Gaja Engineering Pvt. Ltd 31.08.23 Civil – 100%; Mech-74%
17 ROLLING & SYNC. 02.04.2023 Apr-24 02.10.2023 Jul-24 11 Fire Protection System Feb-24

25.03.2023/ U#1 – Feb-24


12 Switch Yard GET&D 16.09.2020 96.0%
25.09.2023 U#2 – Jun-24

18 FULL LOAD 02.06.2023 May-24 02.12.2023 Aug-24 13 Ash Dyke Package M/s JPW Infratech Pvt Ltd 11.03.2022 10.09.2024 10.09.2024 45.0%

04.02.2022/ 24.07.2023/
14 Station Transformers BHEL 09.08.2020 100% | 5%
30.07.2022 31.05.2024

19 TRIAL RUN 02.07.2023 Jun-24 02.01.2024 Sep-24 15 Unit Transformers BHEL 08.09.2020 15.07.2022 Feb-2024 Civil: 96% Mfg: 96%

M/s Jhajhariya Nirman Ltd; M/s


20 Railway Siding 13.11.2020 13.09.2022 Apr-24 94 %
ISC-CMIPL (JV)

20 COD 02.08.2023 Jul-24 02.02.2024 Oct-24


M/s Unitech Power Transmission
21 Power Evacuation Lines 02.03.2021 01.06.2022 24.12.2022(A) 100% Tx line work completed
M/s Hyosung India

CRITICAL ISSUES
 Slow progress in BoP areas –CHP, AHP, Chimney, Air Compressor plant.
 Slow progress by the Sub contractors of Main contractors due to some contractual issues and shortage of manpower.

REASONS OF DELAY
⬧ 6 Months Post Award delay due to COVID-19 Pandemic.
⬧ Slow work progress in some of the BoP areas i.e. CHP, AHP, DM Water Plant, WPT Plant. Air Compressor and Fire protection

26
BUXAR THERMAL POWER PROJECT, Unit# 1 & 2 (2x660 MW) / SJVN (CENTRAL SECTOR)
Village-Chausa, Tehsil-Chausa, Distt.-Buxar (Bihar), Pin- 802114
E-Gen Portal Registration No. (U#1 - 1200002481; U#2 - 1200002482)
Project Developer / Implementing Agency -
Main Plant Vendor - M/s L&T (EPC)
SJVN
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#1 May-2023 Jun-2024
Jun-2019
Unit#2 Sep-2023 Sep-2024
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal, Indigenous ORIGINAL ESTIMATED COST
10439.09
COAL COMBUSTION OF THE PROJECT
Supercritical
TECHNOLOGY
LATEST ESTIMATED COST Not Revised
APPROVAL DATE / NTP Investment Approval accorded by Govt. of India vide MoP
BTG/BoP Contractor Main Plant works has been awarded in single EPC package to M/s. DATE OF FINANCIAL
26.11.2020
Details (Package Wise) L&T on 22.06.2019. CLOSURE
YEAR WISE EXPENDITURE
PPA signed with Govt. of Bihar on 05.01.2011 and further
PPA 2013-14 46.68
reconfirmed on 09.01.2018.

2014-15 15.18
Allocated Mine - CCL, Magadh-Amrapali; Distance from mine - 465
km (non pithead). 2015-16 378.08
Letter of Assurance (LoA) for 4.976 MTPA of G9 to G14 grade coal
COAL LINKAGE/FSA issued by Central Coalfields Ltd. (CCL) on 10.12.2018. Coal may be 2016-17 23.96
supplied either from Amrapali coal block or Magadh coal block.
2017-18 21.73

2018-19 68.21
START UP POWER Start up power will be arranged through South Bihar Power
AGREEMENT Distribution company Ltd. (SBPDCL). 2019-20 344.50

2020-21 1100.05
Tx Line Developer BSPTCL, Govt. of Bihar
i) Buxar TPS- Naubatpur 400 KV,
D/C 2021-22 2691.06
Tx Line Name ii) Buxar TPS- Dumraon (New) 220
Tx Voltage Level KV, D/C 2022-23 2581.36
POWER EVACUATION
SYSTEM iii) Buxar TPS- Karmnasa (New) 220
KV, D/C EXPENDITURE OF JAN’2024 133.55
iv) Buxar TPS- Dehri 220 KV, D/C
TOTAL EXPENDITURE (upto
Configuration of Tx Line D/C 8861.42
31.01.2024)
(S/C or D/C)
Total Land Required-1283 Acre;1058.335 Acre (for Main Plant), 147
LAND POSSESSION acre (for Rail Corridor) and 78 acre (for Water Pipeline corridor &
intake etc.) land under possession.

MoU for utilization of 55 cusec of water signed between STPL and


WATER ALLOCATION
Water Resource Deptt., Govt. of Bihar on 29.08.2016.

MOEF CLEARANCE Accorded by MOEF&CC on 28.02.2017.(Validity- 27.02.2024)

CIVIL AVIATION Accorded by Airport Authority of India on 12.04.2017 (Fresh NOC


CLEARANCE issued on 18.11.2018). (Validity-17.11.2028)

CPCB CLEARANCE NOT APPLICABLE


“Consent to Establish” (NOC) granted by Bihar State Pollution
SPCB CLEARANCE
Control Board on 03.09.2019.
FOREST CLEARANCE NOT APPLICABLE

27
BUXAR THERMAL POWER PROJECT, Unit# 1 & 2 (2x660 MW) / SJVN (CENTRAL SECTOR)
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL) STATUS OF MAIN PLANT PACKAGE (BTG) : M/s L&T ltd
UNIT-01 UNIT-02 UNIT-01 UNIT-02
Sl. Packages AREA
% %
Actual / Actual / Completion Completion
Sl. MILESTONE 100% 92.33%
Original Date Anticipated Original Date Anticipated CIVIL
Date Date
1 BOILER STRUCTURE 96.12% 90.32%

PRESSURE PARTS 100% 86.26%


COMPLETION OF BOILER
1 [Link].20 [Link].21 [Link].20 [Link].21
FOUNDATION CIVIL 100% 85.43%

2 START OF BOILER ERECTION [Link].20 [Link].20 [Link].20 [Link].21 2 TG STRUCTURE 100% 92.12%

TG ERECTION 97.55% 71.44%


BOILER DRUM LIFTING (if sub-critical
3 NA NA
unit) 3 ESP UNDER PROGRESS 92.12% 74.27%

4 BOILER CEILING GIRDER LIFTING


COMPLETION [Link].21 [Link].22 [Link].21 [Link].22 CIVIL WORK 76.95% 60.48%

5 CONDENSER ERECTION START [Link].21 [Link].22 [Link].21 Feb-24 4 FGD MATERIAL SUPPLY 94.48% 94.59%

6 TG ERECTION START [Link].21 [Link].22 [Link].22 Apr-24 ERECTION WORK 26.19% 6.44%

7 HP PIPING ERECTION START [Link].21 [Link].22 [Link].22 Feb-24 STATUS OF BOPs


BOILER HYDRO TEST (DRAINABLE) Anticipated UNIT-01 UNIT-02
8 [Link].22 [Link].23 [Link].22 Mar-24 Scheduled
COMPLETION Packages/ Linked Vendor/Contracting Agency Date of /Actual
Sl. Date of % %
Project Milestones (EPC- L&T) Award Date of
Completion
BOILER HYDRO TEST (NON- Completion Completion Completion
9 NA NA
DRAINABLE) COMPLETION 1 Chimney L&T Limited (EPC) [Link].19 [Link].23 MAR.24 77.26%

10 TG BOX UP [Link].22 20-DEC-23 [Link].22 Jun-24 L&T (Conveyor pkg) [Link].19 [Link].22 APR.24 67.85%

11 HP PIPING ERECTION COMPLETION [Link].22 Feb-24 [Link].22 Jun-24 2 Coal Handling Plant L&T (Wagon tipler) [Link].19 [Link].22 APR.24 70.51%
L&T/ Thyssenkrup (Stacker
12 START OF OIL FLUSHING [Link].22 Mar-24 [Link].22 Jul-24 reclaimer)
[Link].19 [Link].22 APR.24 74.80%

13 BOILER LIGHT UP [Link].22 Mar-24 [Link].23 Jun-24 3 Ash Handling Plant L&T /Macawber Beekay Pvt ltd [Link].19 [Link].23 APR.24 71.90%
L&T/ Shalkoot Mechanique Pvt.
14 CHEMICAL CLEANING COMPLETION [Link].22 Mar-24 [Link].23 Jun-24 4 Fuel Oil System Ltd [Link].19 [Link].22 FEB.24 85.13%
L&T/ Paharpur Cooling Towers
15 STEAM BLOWING START [Link].22 Apr-24 [Link].23 Jul-24 5 Cooling Towers
Ltd [Link].19 [Link].23 FEB,24 83.95%
[Link].19 [Link].23 APR,24 55.32%
L&T/ Xylem Water Solutions India 85.30%
6 CW Pump house [Link].19 [Link].23 JAN,24 57.75%
Pvt Ltd
16 STEAM BLOWING COMPLETION [Link].22 [Link].23 [Link].19 [Link].23 APR,24
Apr-24 Jul-24 L&T/ Driplex Water Engineering
7 WPT Plant Pvt Ltd [Link].19 [Link].23 APR,24 94.23%
[Link].19 [Link].23 APR,24 66.23%
L&T/ Driplex Water Engineering
8 DM Plant [Link].19 [Link].23 [Link].23 100%
Pvt Ltd
17 ROLLING & SYNC. [Link].23 May-24 [Link].23 Aug-24
9 Compressed Air System L&T / L&T-MHPS Boilers Pvt. Ltd [Link].19 [Link].22 Feb,24 91.47%

10 Fire Protection System L&T/ Flowmore Limited [Link].19 [Link].23 FEB,24 70.82%
18 FULL LOAD [Link].23 Jun-24 [Link].23 Sep-24
L&T/ ABB Power Products &
11 Switch Yard Systems India Ltd [Link].19 [Link].22 Feb,24 98.58%
L&T/ ABB Power Products &
12 Station Transformers Systems India Ltd [Link].19 [Link].22 Feb,24 99%
19 TRIAL RUN [Link].23 [Link].23 [Link].19 [Link].22 MAR,24 80.92%
Jun-24 Sep-24 L&T/ ABB Power Products &
13 Unit Transformers [Link].19 [Link].23 FEB,24 54.64%
Systems India Ltd
[Link].19 [Link].23 MAR,24 50.23%

14 Railway Siding RITES Ltd. [Link].19 [Link].22 FEB,24 32.34%


20 COD [Link].23 Jul-24 [Link].24 Oct-24
15 Power Evacuation Lines BSPTCL, Govt. of Bihar [Link].21 [Link].22 Feb,24
99.86%

CRITICAL ISSUES
- Slow work progress in BoP areas i.e. AHP, CHP & Railway siding.
- Delay in readiness of Switchyard (Stringing & Cabling) and start-up power availability due to local agitation.
- Problem in land acquisition for railway siding and water intake pipeline corridor.

REASONS OF DELAY
BTG :
Covid-19 Pandemic and subsequent lockdowns; Non-availability of industrial Oxygen cylinders due to Covid-19; State government restriction for transportation of aggregates,
sand mining etc.; Agitation by locals on 10.01.2023 and unrest activity on 11.01.2023.

BoP:
Delayed acquisition of land for Water Corridor & Intake and Rail Corridor.; Covid-19 Pandemic and subsequent lockdowns. Non-availability of industrial Oxygen cylinders due
to Covid-19; State government restriction for transportation of aggregates, sand mining etc.; Agitation by locals on 10.01.2023 and unrest activity on 11.01.2023.

28
OBRA ‘C’ TPP, Unit# 1 & 2 (2x660 MW) / UPRVUNL (STATE SECTOR)
Village-Obra, Tehsil-Obra, District-Sonebhadra, Uttar Pradesh, Pin-231219
E-Gen Portal Registration No. (U#1 - 1200001696; U#2 - 1200001697)
Project Developer / Implementing Agency - UPRVUNL Main Plant Vendor - (BTG) : M/s. Doosan Power Systems India Pvt. Ltd.
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#1 Dec-2020 Feb-2024
Dec-2016
Unit#2 Apr-2021 Jun-2024
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal, Indigenous ORIGINAL ESTIMATED COST
8777.71
COAL COMBUSTION OF THE PROJECT
Ultra-Supercritical
TECHNOLOGY
LATEST ESTIMATED COST 11705.85
APPROVAL DATE / NTP Date of NTP or Approval Date: 22.12.2016
DATE OF FINANCIAL 13.11.2013; 30.05.2019
CLOSURE for additional amount.
BTG/BoP Contractor 22.12.2016. EPC contract awarded to M/s Doosan Power Systems
Details (Package Wise) India Pvt. Ltd., Gurugram(Haryana)
YEAR WISE EXPENDITURE
PPA signed with UP Power Corporation Ltd for 100% share to state of
PPA
UP
2015-16 7.24
Allocated Mine - Saharpur Jamarpani mines, Jharkhand; Distance from
2016-17 423.77
mine - 651 km (non pithead); Allocation Date: 13.08.2015. Grade of
COAL LINKAGE/FSA
Coal -G10
2017-18 277.83

2018-19 855.90
START UP POWER
Start up power from UPPTCL
AGREEMENT 2019-20 2175.96
Tx Line Developer UPPTCL
2020-21 1220.62
i) LILO of 765 kV Anpara’D’- Unnao
Tx Line Name
POWER EVACUATION S/C at Obra ‘C’ TPS; 2021-22 1826.42
Tx Voltage Level
SYSTEM ii) 400 kV D/C Jaunpur- Obra line (upto
LILO point of Obra‘B’ – Obra ‘C’ 2022-23 1460.40
Line).
EXPENDITURE OF Jan’2024 26.20
Configuration of Tx Line
(S/C or D/C) TOTAL EXPENDITURE (upto
10281.53
Brown Field project, therefore Land already in Possession. For ash 31.01.2024)
dyke construction, land acquisition of 113.42 Ha under progress.
LAND POSSESSION
Initially ash disposal of Obra 'C' will be made in existing obra 'B' Ash
Pond and in parallel land acquisition work for Obra'C' is in progress.

Water requirement to be fulfilled from return channel of Obra-B


WATER ALLOCATION plant. Additional requirement (if any) shall be met from the reservoir
of Rihand Dam.

MOEF CLEARANCE Clearance obtained date 21.06.2016

CIVIL AVIATION
Clearance obtained date : 12.07.2016 Valid upto 21.07.2021
CLEARANCE

CPCB CLEARANCE Not Applicable

SPCB CLEARANCE Not Applicable

FOREST CLEARANCE Wild life Clearance obtained date 07.06.2016

29
OBRA ‘C’ TPP, Unit# 1 & 2 (2x660 MW) / UPRVUNL (STATE SECTOR )
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL) STATUS OF MAIN PLANT PACKAGE (BTG) : Doosan Power Systems India Pvt.
UNIT-01 UNIT-02 UNIT-01 UNIT-02
Sl. Packages AREA
Anticipated / Anticipated / % % Completion
Sl. MILESTONE Original Date Original Date Completion
Actual Date Actual Date
of of CIVIL
of of
Completion Completion
Completion Completion
1 BOILER STRUCTURE 100% 90.15%

COMPLETION OF BOILER PRESSURE PARTS


1 11-Mar-18 15-Feb-19 16-Jun-18 21-Feb-19
FOUNDATION CIVIL

2 START OF BOILER ERECTION 22-Apr-18 28-May-18 22-Aug-18 21-Jan-19 2 TG STRUCTURE 100% 80.52%

PRESSURE PARTS
BOILER DRUM LIFTING (if sub-critical
3 NA NA
unit) 3 ESP PASS STATUS 98.75% 60.00%

BOILER CEILING GIRDER LIFTING CIVIL WORK 96.52% 75.32%


4 21-Sep-18 7-Mar-19 21-Jan-19 10-Nov-19
COMPLETION 94% 65.50%
MATERIAL SUPPLY
4 FGD
5 CONDENSER ERECTION START 23-Nov-18 17-Aug-20 23-Mar-19 2-Apr-22
ERECTION WORK 53.00% 18.14%
6 TG ERECTION START 22-Jan-19 2-Nov-20 23-May-19 May-23

7 HP PIPING ERECTION START 12-Jan-19 1-Mar-20 22-May-19 7-Oct-23 STATUS OF BOPs (DPSI-EPC)
BOILER HYDRO TEST (DRAINABLE) UNIT-01 UNIT-02
8 22-Sep-19 27-Sep-20 23-Jan-20 20-Apr-22 Scheduled Anticipated/
COMPLETION Packages/ Linked Project Vendor/Contracting Agency Date of
Sl. Date of Actual Date of
Milestones (EPC- Award
Completion Completion % % Completion
DPSI Completion
BOILER HYDRO TEST (NON-
9 22-Sep-19 27-Sep-20 23-Jan-20 20-Apr-22
DRAINABLE) COMPLETION 1 Chimney M/[Link] 27.11.2018 01.12.2019 31.12.2023 100%

10 TG BOX UP 22-Feb-20 15-Dec-21 20-Jun-20 Apr-24 KCC (Conveyor package) 19.05.2020 29.02.2024 99.00%

11 HP PIPING ERECTION COMPLETION 20-Mar-20 14-Mar-22 20-Jul-20 Mar-24 2 Coal Handling Plant Aneja (Wagon Tripler) 23.11.2018 23.02.2020 29.02.2024 99.00%

12 START OF OILFLUSHING 23-Feb-20 10-Mar-22 21-Jun-20 Apr-24 Aneja (Stacker Reclaimer) 02.05.2018 05.04.2020 31.10.2024 97.38%

13 BOILER LIGHT UP 21-Apr-20 26-Apr-22 19-Aug-20 Mar-24 3 Ash Handling Plant AKC, PNC 09.04.2018 29.06.2020 31.09.2024 80.26%

14 CHEMICAL CLEANING COMPLETION 25-Mar-20 16-Mar-22 25-Jul-20 Apr-24 4 Fuel Oil System AKC, Sangha, Singrauli, Jiwala 30.11.2018 04.05.2020 Dec,2023 100%

15 STEAM BLOWING START 22-May-20 07-Nov-22 19-Sep-20 Apr-24 01.08.2018(C 25.11.2019(C


T-01), T-01), Dec,2023
5 Cooling Towers PCTL 100% 75%
14.12.2018(C 26.03.2020(C 03.03.2024
16 STEAM BLOWING COMPLETION 22-Jun-20 09-Dec-22 19-Oct-20 May-24
T-02) T-02)

6 CW Pump house GDCL 06.06.2018 05.07.2020 02.04.2023 100%

17 ROLLING & SYNC. 30-Jul-20 25-Apr-23 27-Nov-20 May-24 Rajpati Vishwakarma, Sahil
7 WPT Plant 20.11.2018 13.09.2020 Apr,2023 100%
Kumar, KNIL, IEIL

Rajpati Vishwakarma, Sahil


8 DM Plant 03.10.2018 04.11.2019 Mar,2023 100%
Kumar, KNIL,IEIL
18 FULL LOAD 1-Sep-20 26-Dec-23 31-Dec-20 May-24

9 Compressed Air System GDCL 23.11.2018 04.05.2020 Mar,2023 100%

10 Fire Protection System Lloyd 08.04.2019 17.10.2019 14.04.2024 57.76%

19 TRIAL RUN 21-Dec-20 Feb-24 21-Apr-21 Jun-24 11 Switch Yard KNIL , GDCL, GET&D 01.08.2018 30.01.2020 Apr,2023 100%

12 Station Transformers GDCL. GET&D 10.11.2018 27.09.2019 28.06.2022 100.00%

13 Unit Transformers GDCL, GET&D 10.03.2019 06.02.2020 25.02.2024 98.67%


Civil Works:- Civil Works:- Civil Works:- 87%
20 COD 21-Dec-20 Feb-24 21-Apr-21 Jun-24 14 Railway Siding DPSI
23.05.2023
24.08.2019 23.02.2020
S&T Works-
21.12.2023

OHE works:-
Apr-
2024(Tentative)
100%
15 Power Evacuation Lines GET&D 08.11.2017 24.07.2020 12.04.2023

CRITICAL ISSUES
- Commissioning activities affected due to Boiler tube leakage
- Delay in readiness of AHP -M/s Indure

REASONS OF DELAY

- COVID-19 I & II wave.


- Steel Price Hike, Dispute between main contractor M/s DPSI and its sub-vendors,

30
JAWAHARPUR STPS, Unit# 1 & 2 (2X660 MW) / UPRVUNL (STATE SECTOR )
Jawaharpur STPS, Malawan, Distt.-Etah, U.P. – 207 001
E-Gen Portal Registration No. (U#1 - 1200002452; U#2 - 1200002496)
Project Developer / Implementing Agency - UPRVUNL Main Plant Vendor - M/S Doosan Power Systems India
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#1 Dec-2020 Feb-2024
Dec-2016
Unit#2 Apr-2021 Apr-2024
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal, Indigenous ORIGINAL ESTIMATED COST
8078.56
COAL COMBUSTION OF THE PROJECT
Ultra Super Critical
TECHNOLOGY
LATEST ESTIMATED COST 12320.43
Approval of DPR and Initial project cost by U. P. Government of
APPROVAL DATE / NTP
DPRVide letter dated 04.09.2015 DATE OF FINANCIAL
EPC/BTG/BoP Contractor 22.12.2016- date of Award to EPC Contractor M/s Doosan Power CLOSURE
Details (Package Wise) Systems India Power Limited - scope including BTG,BOP
YEAR WISE EXPENDITURE
Details of PPA signed or under process whichever is applicable with
PPA
defining share % if any.
2016-17 445.21
Allocated Mine - Saharpur Jamarpani mines, Jharkhand; Distance from
mine - 1190 km (non pithead) 2017-18 400.26
COAL LINKAGE/FSA
Bridge Linkage from CCL/ECL for 4.461 MTPA
2018-19 844.96

2019-20 2295.94
START UP POWER
For 220 KV signed with UPPTCL
AGREEMENT 2020-21 2034.08
Tx Line Developer PGCIL & UPPTCL
2021-22 2224.36
i) LILO of 765kV Mainpuri - Gr. Noida
Tx Line Name
POWER EVACUATION S/C at Jawaharpur TPS; 2022-23 1782.72
Tx Voltage Level
SYSTEM ii) Jawaharpur TPS-Firozabad 400kV
D/C line. EXPENDITURE OF JAN’2024 195.66
TOTAL EXPENDITURE
11877.04
Configuration of Tx Line (upto 31.01.2024)
(S/C or D/C)

LAND POSSESSION 765 Acre land for Power House under Possession

WATER ALLOCATION Lower Ganga Canal - 38 cusec

MOEF clearance granted in 63rd Meeting of the reconstituted EAC


MOEF CLEARANCE
(Thermal Power) was held on 29th & 30th August, 2016
CIVIL AVIATION
Chimney clearance from AAI vide letter dated 12.06.2015
CLEARANCE

CPCB CLEARANCE NA

Ref No- 58264/UPPCB/Aligarh(UPPCBRO)/CTE/ETAH/ 2019 dated


SPCB CLEARANCE
24.10.2019 valid up to 09.10.2024

FOREST CLEARANCE Clearance obtained vide letter no. 1904/14-1 dated 15.03.2016

31
JAWAHARPUR STPS, Unit# 1 & 2 (2X660 MW) / UPRVUNL (STATE SECTOR )
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL) STATUS OF MAIN PLANT PACKAGE (BTG) : M/S DPSI
UNIT-01 UNIT-02 UNIT-01 UNIT-02
Sl. Packages AREA
% Completion % Completion
Sl. MILESTONE Anticipated / Anticipated /
Original Date of Original Date of
Completion
Actual Date of
Completion
Actual Date of CIVIL 100 % 100%
Completion Completion
1 BOILER STRUCTURE 98.92 % 93.28%
1 COMPLETION OF BOILER FOUNDATION 31.12.2017 05.03.2019 03.05.2018 29.05.2019 PRESSURE PARTS 100% 100 %
2 START OF BOILER ERECTION 22.04.2018 20.08.2018 22.08.2018 20.11.2018 CIVIL 100 % 99.10%
3 BOILER DRUM LIFTING (if sub-critical unit) NA NA 2 TG
STRUCTURE 99.71 % 98.22%
BOILER CEILING GIRDER LIFTING
4 06.09.2018 14.06.2019 06.01.2019 14.11.2019
COMPLETION
3 ESP STRUCTURE 98.99% 68.91%
5 CONDENSER ERECTION START 22.01.2019 16.09.2020 22.05.2019 12.06.2021 CIVIL WORK 100% 100 %
6 TG ERECTION START 22.01.2019 23.11.2020 22.05.2019 25.02.2022 MATERIAL SUPPLY 100% 100%
4 FGD
7 HP PIPING ERECTION START 18.02.2019 01.11.2019 22.06.2019 15.02.2021
ERECTION WORK 96.99% 52.97%
BOILER HYDRO TEST (DRAINABLE)
8
COMPLETION
21.09.2019 10.11.2020 21.01.2020 30.11.2021 STATUS OF BOPs (DPSI-EPC)
UNIT-01 UNIT-02
BOILER HYDRO TEST (NON-DRAINABLE)
9 - - - - Scheduled Anticipated/A
COMPLETION Packages/ Linked Project Vendor/Contracting Agency (EPC- Date of
Sl. Date of ctual Date of
Milestones BHEL) Award
Completion Completion % Completion % Completion
10 TG BOX UP 22.02.2020 25.07.2022 20.06.2020 28.07.2023

11 HP PIPING ERECTION COMPLETION 23.08.2019 10.07.2022 23.12.2019 30.11.2022 1 Chimney Simplex 16.03.2017 05.11.2019 03.04.2024 82.44%
tkII/ NeoStructo(Conveyor
12 START OF OILFLUSHING 23.02.2020 12.02.2022 21.06.2020 01.08.2023 package) 10.10.2017 23.04.2020 02.03.2024 95.70%
02.03.2024
13 BOILER LIGHT UP 26.04.2020 27.05.2022 23.08.2020 02.11.2023 2 Coal Handling Plant tkII/ NeoStructo (Wagon Tripler) 10.10.2017 24.12.2019 98.36%
tkII/ NeoStructo (Stacker 02.03.2024
14 CHEMICAL CLEANING COMPLETION 15.03.2020 03.05.2022 13.07.2020 02.11.2023 10.10.2017 15.09.2019 98.84%
Reclaimer)
15 STEAM BLOWING START 26.05.2020 27.09.2022 21.09.2020 01.02.2024 3 Ash Handling Plant Main vendor/subcontractor 30.12.2016 26.09.2020 04.08.2024 85.03%

16 STEAM BLOWING COMPLETION 21.06.2020 02.12.2022 21.10.2020 27.02.2024 4 Fuel Oil System Main vendor/ 21.02.2017 10.04.2020 01.02.2024 99.90%
(Piping#2)

05.03.2018, 26.11.2019, 27.10.2023,


5 Cooling Towers Paharpur 100% 89.94%
10.09.2018 27.03.2020 11.03.2024
17 ROLLING & SYNC. 21.08.2020 29.04.2023 21.12.2020 15.03.2024

6 CW Pump house DPSI/ Jyoti 10.01.2017 05.12.2019 15.03.2024 98.62%

7 WPT Plant Civil : Tecknow 14.10.2018 06.09.2019 30.12.2023 100%

18 FULL LOAD 01.09.2020 19.01.2024 01.01.2021 28.03.2024 8 DM Plant EPC : Ion Exchange 21.08.2019 16.11.2019 31.01.2024 100%

9 Compressed Air System Atlas / Jyoti 13.03.2017 19.05.2020 02.03.2024 98.44%

10 Fire Protection System Lloyd 17.02.2017 05.04.2020 30.04.2024 64.80%

19 TRIAL RUN 20.12.2020 29.02.2024 20.04.2021 30.04.2024 11 Switch Yard GE T&D 17.01.2017 26.03.2020 08.07.2024 96.53%

12 Station Transformers Zagson 31.01.2019 03.09.2019 10.04.2024 82.42%

13 Unit Transformers Zagson 16.08.2019 23.09.2019 08.03.2024 85.96%


- Civil work 65%
20 COD 21.12.2020 29.02.2024 21.04.2021 01.04.2024 14 Railway Siding
100 % 100 %
15 Power Evacuation Lines DPSI 21.08.2020 29.04.2023

CRITICAL ISSUES
Commissioning activities affected due to some issues in LDO strainer & choking of guns
- Delay in readiness of Ash Handling plant ( M/s Indure)
- Delay in readiness of Wagon Tippler.

REASONS OF DELAY
1st and 2nd wave of COVID‐19 pandemic have caused delay in project.

32
PANKI THERMAL POWER PROJECT, Unit# 1 (1X660MW) / UPRVUNL (STATE SECTOR )
Panki TPP, Distt.-Kanpur, U. P., Pincode-208020
E-Gen Portal Registration No. (U#1 - 1200001768)
Project Developer / Implementing Agency - UPRVUNL Main Plant Vendor - M/s BHEL
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#1 Mar-2018 Sep-2021 Sep-2024
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal, Indigenous ORIGINAL ESTIMATED COST
5816.70
COAL COMBUSTION OF THE PROJECT
Super Critical
TECHNOLOGY
LATEST ESTIMATED COST Not Revised
APPROVAL DATE / NTP 20.03.2018
DATE OF FINANCIAL
22.06.2018
EPC/BTG/BoP Contractor CLOSURE
BHEL, LOA: 31.03.2018
Details (Package Wise)
YEAR WISE EXPENDITURE
PPA Signed on 17.01.2017
2018-19 543.29

Allocated Mine - Saharpur Jamarpani mines, Jharkhand; Distance from 2019-20 837.26
COAL LINKAGE/FSA mine - 896 km (non pithead). Expected grade of coal is G-10.
2020-21 1131.48
FSA on 30.01.2017

2021-22 951.81
START UP POWER
20.10.2020
AGREEMENT 2022-23 1243.57

EXPENDITURE OF Jan’2024 140.95


Tx Line Developer UPPTCL TOTAL EXPENDITURE (upto
5363.26
31.01.2024)
Tx Line Name
POWER EVACUATION
Tx Voltage Level
SYSTEM Panki TPS - Panki , 400 KV, D/C line
(UPPTCL)
Configuration of Tx Line
(S/C or D/C)

LAND POSSESSION It is extension project. Hence Land is available

WATER ALLOCATION Lower Ganga Canal and Tertiary Treatment Plant, Bingawan (Kanpur)

Clearance obtained vide letter no. J-13012/35/2013-IA- I(T) dated :-


MOEF CLEARANCE
29.06.2017
CIVIL AVIATION Clearance obtained vide letter no. AAI/NOC/2012/453/104-106
CLEARANCE dated:- 18.01.2013

CPCB CLEARANCE MOEF clearance obtained on 29.06.2017

Clearance obtained vide letter no. 24271/UPPCB/Kanpur


SPCB CLEARANCE
Nagar(UPPCBRO)/CTE/Kanpur Nagar/2018 dated : 25.06.2018

FOREST CLEARANCE Clearance obtained vide letter no. 484/14-1 dated:- 11.08.2015

33
Status as on 31-01-2024
PANKI THERMAL POWER PROJECT, Unit# 1 (1X660MW) / UPRVUNL (STATE SECTOR )
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL) STATUS OF MAIN PLANT PACKAGE (BTG) : M/s BHEL
UNIT-01 UNIT-01
Sl. Packages AREA
% Completion
Sl. MILESTONE
Anticipated / Actual Date of
Original Date of Completion
Completion
CIVIL 90.00%
1 BOILER STRUCTURE WORKS 84.50%
1 COMPLETION OF BOILER FOUNDATION 29.04.2019 13.01.2020 PRESSURE PARTS 99.0
0%
2 START OF BOILER ERECTION 30.04.2019 24.04.2019 CIVIL 82.00%
NA NA
3 BOILER DRUM LIFTING (if sub-critical unit) 2 TG STRUCTURE WORKS 82.00%
BOILER CEILING GIRDER LIFTING 20.11.2019 23.02.2020
4
COMPLETION TG AUX 80.00%
5 CONDENSER ERECTION START 30.04.2020 28.08.2021 3 ESP PASS STATUS 94.00%
6 TG ERECTION START 30.04.2020 04.10.2021 CIVIL WORK 50.00%
7 HP PIPING ERECTION START 03.11.2019 30.11.2020 4 FGD MATERIAL SUPPLY 53.00%
8 BOILER HYDRO TEST (DRAINABLE) 30.09.2020 17.12.2021 ERECTION WORK 12.00%
COMPLETION

9
BOILER HYDRO TEST (NON-DRAINABLE)
22.02.2021 30.09.2023
STATUS OF BOPs
COMPLETION
UNIT-01
Scheduled Anticipated/Act
Packages/ Linked Project Date of
Sl. Vendor/Contracting Agency Date of ual Date of
Milestones Award
10 TG BOX UP 31.01.2021 30.03.2024 Completion Completion % Completion

1 Chimney Bygging 27.11.2018 01.12.2019 May’24 99.69%


11 HP PIPING ERECTION COMPLETION 29.08.2020 15.04.2024
Thyseen Krupp & RVPR (Conveyor Package) 19.05.2020 Mar’24

Thyseen Krupp & Kanwar (Wagon Tripler) 23.11.2018 23.02.2020 Mar’24


12 START OF OILFLUSHING 30.01.2021 30.04.2024 67.84
2 Coal Handling Plant
Thyseen Krupp & Kanwar (Stacker Reclaimer) 02.05.2018 05.04.2020 Mar’24
13 BOILER LIGHT UP 28.02.2021 18.11.2023
3 Ash Handling Plant Indure/ Kanwar 09.04.2018 29.06.2020 Mar’24 56.66%
14 CHEMICAL CLEANING COMPLETION 10.03.2021 15.12.2023
4 Fuel Oil System GMW/ Simplex 30.11.2018 04.05.2020 Mar’24 70%

May’24
01.08.2018, 25.11.2019,
15 STEAM BLOWING START 09.04.2021 31.03.2024 5 Cooling Towers Paharpur 95%
14.12.2018 26.03.2020

6 CW Pump house MHI/ Simplex 06.06.2018 05.07.2020 Feb’24 70%


16 STEAM BLOWING COMPLETION 30.04.2021 15.05.2024
7 WPT Plant GDCL 20.11.2018 13.09.2020 Feb’24 67%

8 DM Plant BGR & Simplex 03.10.2018 04.11.2019 Feb’24 54%


17 ROLLING & SYNC. 31.05.2021 30.06.2024
9 Compressed Air System ATLAS COPCO 23.11.2018 04.05.2020 May’24 76.5%

10 Fire Protection System BHEL 08.04.2019 17.10.2019 May’24 39%


18 FULL LOAD 30.06.2021 30.07.2024
11 Switch Yard JSPPL 01.08.2018 30.01.2020 31.01.2024 99%

12 Station Transformers BHEL 10.11.2018 27.09.2019 Feb’24 80%


19 TRIAL RUN 30.09.2021 30.09.2024
13 Unit Transformers BHEL 10.03.2019 06.02.2020 Mar’24 80%
05-10-2020 Mar’24
14 Railway Siding RITES 85%
20 COD 30.09.2021 01.10.2024
15 Power Evacuation Lines UPPTCL 08.11.2017 24.07.2020 Apr’23 100%

CRITICAL ISSUES
- Delay in completion of CWPH, ACW system, Raw water intake system
- Delay in execution of AHP, CHP, power cycle piping works &DM Plant
- Inadequate manpower at site (BHEL).

REASONS OF DELAY
Due to COVID 19 outbreak and its consequences.

34
Status as on 31-01-2024
ENNORE SEZ STPP, Unit# 1 & 2 (2X660 MW) / TANGEDCO (STATE SECTOR)
Village-Voyalur, Minjur, Distt-Thiruvallur (Tamil Nadu)-601203
E-Gen Portal Registration No. (U#No - 1200001984, U#2 No - 1200001985)
Project Developer / Implementing Agency - TANGEDCO Main Plant Vendor - M/s BHEL (EPC)
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#1 27.01.18 Apr-2025
Sep-2014
Unit#2 27.03.18 Jul-2025
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal, Indigenous & Imported ORIGINAL ESTIMATED COST
9800.00
COAL COMBUSTION OF THE PROJECT
Supercritical
TECHNOLOGY
LATEST ESTIMATED COST 9800.00
APPROVAL DATE / NTP 27.09.2014
DATE OF FINANCIAL
EPC/BTG/BoP Contractor CLOSURE
M/s BHEL (EPC), LoA: 27.09.2014
Details (Package Wise)
YEAR WISE EXPENDITURE
State sector project. Hence entire 100% power from this project will be
PPA
utilized by TAMILNADU
2016-17 558.04
Allocated Mine - Chandrabila Coal Block, Odisha; Distance from mine
- 1300 km (non pithead); Total requirement is 5.95MTPA, comprising of 2017-18 2276.51
indigenous 3.68 MTPA & imported 2.26 MTPA respectively
MoU has already been signed between MMTC & TANGEDCO on 25.06.2012 2018-19 4688.11
for the supply of Import coal for this project.
Bridge Linkage with SCCL available for indigenous coal. 2019-20 1550.04

2020-21 750.13
COAL LINKAGE/FSA
2021-22 260.14
2022-23 410.67
EXPENDITURE OF JAN’2024 301.20
TOTAL EXPENDITURE (upto
9429.59
31.01.2024)
START UP POWER
By TAGEDCO
AGREEMENT (Tripartite agreement between TANGEDCO, M/s
Tx Line Developer TANGEDCO BHEL (EPC contractor), PFC (Lender) signed on
Tx Line Name Ennore SEZ SCTPP - North Chennai 21.11.2016 and Loan agreement between PFC
POWER EVACUATION (765KV PS), 400 KV, D/C line
Tx Voltage Level andTANGEDCO signed on 18.01.2017.)
SYSTEM
Configuration of Tx.
Line (S/C or D/C)
Acquisition of Land does not arise since own Land of TANGEDCO
LAND POSSESSION (Out of 1100 acres available at Ash Dyke of NCTPS , only 500 Acres
of ash dyke is utilized for the development of the subject project)
Supply of 4 MGD water from CMWSSB obtained. However
WATER ALLOCATION
desalination plant is envisaged in the project.
MOEF Letter No. J 13012 / 36/[Link](T) dt.07.01.2014. Validity
MOEF CLEARANCE
extended upto 31.12.2023 as per MoEF lr. Dt.09.04.2021
Airport Authority has been addressed to issue NOC vide Letter No:
Se/C/P&E/EE/EMC/AEE/C/[Link]-SEZTPP/D768 dt 17.4.2010. No
Objection certificate issued by Airport Authority of India for the
CIVIL AVIATION
construction of chimney for the proposed Ennore SEZ TPP- 2X800
CLEARANCE MW Project vide [Link]:AAI/SR/NOC/dt 13.5.2010-validity 7 years
available. Validity extended upto 13.5.2022 vide their letter dt
19.5.2017.
CPCB CLEARANCE Not applicable
Consent to establish under Air and water Acts issued by TNPCB vide
SPCB CLEARANCE order 2002229941522 Dt.26.11.2020 extended the validity upto
06.01.2021. Extension of validity upto 31.12.2023 is under process.
FOREST CLEARANCE Not applicable

35
Status as on 31-10-2023
ENNORE SEZ STPP, Unit# 1 & 2 (2X660 MW) / TANGEDCO (STATE SECTOR )
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL) STATUS OF MAIN PLANT PACKAGE (BTG) : M/S BHEL
UNIT-01 UNIT-02 UNIT-01 UNIT-02
Sl. Packages AREA
Actual / Actual /
% Completion % Completion
Sl. MILESTONE
Original Date Anticipated Original Date Anticipated CIVIL 100.00% 90.00%
Date Date
1 BOILER STRUCTURE 97.49% 93.60%
COMPLETION OF BOILER PRESSURE PARTS 97.49% 93.60%
1 13.08.15 14.09.17 13.10.15 07.06.18
FOUNDATION CIVIL 64.80% 87.00%
2 START OF BOILER ERECTION 25.08.15 15.09.17 28.10.15 08.06.18 2 TG STRUCTURE 64.80% 87.00%
Civil work is under progress
BOILER DRUM LIFTING (if sub-critical TG ERECTION Yet to start
3 NA NA
unit) 3 ESP UNDER PROGRESS 79.12% 73.16%
BOILER CEILING GIRDER LIFTING CIVIL WORK
4 28.01.16 30.11.18 28.03.16 16.05.19 Specification under finalization.
COMPLETION MATERIAL SUPPLY
4 FGD
5 CONDENSER ERECTION START 27.04.17 Feb-24 20.06.17 20.06.22
ERECTION WORK
6 TG ERECTION START 10.06.17 March-24 10.08.17 Feb-24

7 HP PIPING ERECTION START 27.04.16 16.09.21 27.06.16 16.11.21 STATUS OF BOPs (BHEL-EPC)
BOILER HYDRO TEST (DRAINABLE) UNIT-01 UNIT-02
8 28.12.16 15.02.20 27.02.17 29.03.21 Scheduled Anticipated/
COMPLETION Packages/ Linked Project Vendor/Contracting Agency (EPC- Date of
Sl. Date of Actual Date of
Milestones BHEL) Award
Completion Completion % Completion % Completion
BOILER HYDRO TEST (NON-
9 28.04.17 30.08.24 28.06.17 30.11.24
DRAINABLE) COMPLETION 1 Chimney M/s Simplex 30.01.17 28.03.17 Aug,24 100 % (Civil) 100 % (Civil)

10 TG BOX UP 27.09.17 30.09.24 27.11.17 30.12.24 Contractor for erection M/s Promac 09.02.17 27.10.17 Feb,24 100 % (Civil), 30% (Mech)
M/[Link] (Conveyor package Feb,24
2 Coal Handling Plant supply), M/[Link]- Pipe 18.03.17 27.10.17 48.55 % (Civil)
11 HP PIPING ERECTION COMPLETION 27.05.17 30.09.24 27.07.16 30.12.24
M/[Link] : Stacker Reclaimer Feb,24
supply, M/[Link] : Vibrating 09.02.17 27.10.17 40 %
M/[Link] (for supply and erection
12 START OF OILFLUSHING 27.10.17 05.10.24 27.12.17 10.01.25 for mechanical packages) ,
M/[Link] Engineers for Sluury
3 Ash Handling Plant disposal pipes supply M/[Link] for 14.09.17 27.10.17 Sept,24 51.96%
Slurry pumps supply, M/[Link]
13 BOILER LIGHT UP 30.05.17 30.09.24 29.09.17 30.12.24 Copco& M/[Link] for
Compressor supply M/[Link]

4 Fuel Oil System M/[Link] Fire Engineers Pvt ltd. 13.06.17 30.03.17 Jul,24 60.29%
14 CHEMICAL CLEANING COMPLETION 10.06.17 10.10.24 10.08.17 10.02.25
Sept,24 (U-1)
5 Cooling Towers M/[Link] (Design – Paharpur) 30.01.17 29.04.17 Dec,24 (U-2) 79.11% 25.59%
CW Pump House - M/s
15 STEAM BLOWING START 20.06.17 05.12.24 20.08.17 01.04.25 6 CW Pump house Cornerstone ( De- scoped from 27.12.19 29.04.22 Aug,24 38.17%
M/[Link]),CW Piping: BHEL /
M/s Vijay Gowtham- ( De-scoped
M/[Link] Global business
7 WPT Plant 18.01.18 30.03.17 Aug,24 56.48%
services for supply and erection
16 STEAM BLOWING COMPLETION 15.07.17 05.01.25 15.09.17 30.04.25
M/s Cornerstone (De-scoped from
8 DM Plant 27.09.14 30.03.17 Aug,24 55.93%
M/[Link])
9 Compressed Air System M/[Link] Equipments Ltd. 27.11.17 30.03.17 Jul,24 99.13%
17 ROLLING & SYNC. 27.11.17 28.02.25 27.01.18 30.05.25
10 Fire Protection System BHEL- PE&SD July,18 30.03.17 Aug,24 5%
BHEL-TBG ( Awarded to Sakthi
18 FULL LOAD 27.10.17 30.03.25 27.12.17 30.06.25 11 Switch Yard Kanna Construction Ltd & 27.09.14 30.03.17 Mar,24
M/[Link] Gowtham- De-scoped 88.87%
from M/[Link])
12 Station Transformers M/s Cornerstone 19.11.19 30.03.17 Jul,24
19 TRIAL RUN 27.11.17 30.04.25 27.01.18 30.07.25 73.12%
13 Unit Transformers M/s Cornerstone 19.11.19 30.08.17 Jul,24

14 Railway Siding NA NA NA NA NA NA
20 COD (TRIAL RUN) 27.01.18 30.04.25 27.03.18 31.07.25 Mar.,2023 Power will be evacuated
15 Power Evacuation Lines TANGEDCO Ennore SEZ SCTPP- through DC 400 KV TL, i.e. 2
North Chennai(765 KV PS), 400 KV, nos 400 KV lines to 765 KV
pooling station and 2 nos 400
D/C line KV lines to ETPS – work under
progress.

CRITICAL ISSUES
- In External coal handling plant area, erection of structure for a portion is held up due to NGT order. Getting amendment in EC from MoEF & CC is in
process.
- Inadequate manpower by BHEL.
- Slow progress in NDCT –II, APH, CCR and CHP, AHP
-
REASONS OF DELAY.

- Zero date is 27.09.2014, Works commenced at Site on 09.10.2016. Project works temporarily suspended from 07.09.2015 to 18.10. 2016 due to litigation. Original completion schedule is March 2018.
Work resumed at Site from 19.10.2016. Completion schedule re-fixed to 06.05.2019 (without levy of LD & penalty) due to time loss of 407 day due to court case. Time extension granted from
06.05.2019 to upto 31.08.2020 for U#1 and 31.10.2020 for Unit 2 without prejudice to levy of LD & Penalty clauses.
- Entire project civil works were awarded to M/s. Simplex. Wherever slow progress of work noticed, BHEL has de scoped the certain works from M/s. Simplex based on TANGEDCO’s request, but still
the progress is very poor from M/s. Simplex.
- Project activities became slow since 24th March 2020 due to lock down enforced by GOI in view of COVID-19 outbreak. Permission accorded by Distt Collector (Thiruvalur) for resumption of work at
site with only 600 manpower on [Link] resumed by BHEL from 18.05.2020

36
Status as on 31-01-2024
NORTH CHENNAI STPP St - III, Unit# 1 (1X800 MW) / TANGEDCO (STATE SECTOR )
Athipattu village, Ponneri Tk, Distt.-Thiruvallur, Chennai (T.N.) - 600 120.
E-Gen Portal Registration No. (U#1 - 1200002174 )
Project Developer / Implementing Agency - TANGEDCO Main Plant Vendor - M/s BHEL (BTG)
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#1 Jan-2016 Apr-2019 Mar-2024
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal, Indigenous & Imported(MMTC) ORIGINAL ESTIMATED COST
6376.00
COAL COMBUSTION OF THE PROJECT
Super critical
TECHNOLOGY
LATEST ESTIMATED COST 8722.86
BTG : SE/E/T & H (P)/ OT No. 02/2015-16 ; BOP : SE/E/T & H (P)
APPROVAL DATE / NTP
OT No.04/2015-16 DATE OF FINANCIAL
28.1.2017
EPC/BTG/BoP Contractor CLOSURE
BTG contractor-BHEL(LoA: 29.01.2016), BOP contractor-M/s
Details (Package Wise)
BGR(LoA: 28.10.2016) YEAR WISE EXPENDITURE
PPA NOT APPLICABLE. State sector project.
2012-13 0.21
Allocated Mine - SCCL; Distance from mine - 606 km (non pithead);.
Ministry of Coal recommended for longterm coal linkage for 1.971
2013-14 0.40
MTPA Indigenous coal to SCCL. FSA Executed between
COAL LINKAGE/FSA
TANGEDCO and SCCL for indigenous coal. MoU has been entered
with M/s. MMTC for supply of Imported coal of 1.450 MTPA on 2014-15 0.13
25.05.2015.
2015-16 0.25
Start up Power Arrangement is through 220 KV level by LILO of
START UP POWER
NCTPS-1 to Ennore Feeder. Station Transformer was charged on
AGREEMENT 05.09.2020. 2016-17 198.08
Tx Line Developer TANTRANSCO
2017-18 929.75
Tx Line Name
POWER EVACUATION 2018-19 2243.52
Tx Voltage Level NCTPS St-III -North Chennai (PS), 765
SYSTEM
KV, D/C line
2019-20 2090.62
Configuration of Tx Line
(S/C or D/C)
2020-21 928.95
The proposed site is within the existing NCTPS complex and land is
LAND POSSESSION
already under possession of TANGEDCO.
2021-22 760.29
The raw water requirement for this project will be met from existing
cooling water fore-bay of NCTPS, Stage-II. The make-up water for
2022-23 694.13
cooling water, boiler make up and other sweet water requirements are
WATER ALLOCATION
to be met from desalination plant under construction for this project.
Construction water from M/s. CMWSSB available to the contractor EXPENDITURE OF JAN’2024 54.98
from 07.01.2017. TOTAL EXPENDITURE(upto
8,543.53
31.01.2024)
(In-principal approval for financial assistance of
Environmental clearance issued by MoEF on 20.01.2016 valid for a Rs.5006.992 crores with Debt : Equity ratio of 80
MOEF CLEARANCE
period of seven years. : 20 for setting up of 1 x 800 MW Supercritical
CIVIL AVIATION Chimney constructed for full height and the same was informed to Thermal Power Plant in Tiruvallur District of
CLEARANCE Airports Authority of India. Tamil Nadu has been received from M/s. REC on
05.08.2016. Loan has been sanctioned on
CPCB CLEARANCE NOT APPLICABLE. State sector project.
22.11.2016. Loan Agreement was signed on
28.01.2017.)
SPCB CLEARANCE Approval has been obtained on 13.04.2017.

FOREST CLEARANCE Not applicable, since the site is not coming under Forest area.

37
Status as on 31-01-2024
NORTH CHENNAI STPP, St - III, Unit# 1 (1X800 MW) / TANGEDCO (STATE SECTOR )
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL) STATUS OF MAIN PLANT PACKAGE (BTG)
UNIT-01 UNIT-01
Sl. Packages AREA
% Completion
Sl. MILESTONE Original Date of
Anticipated / Actual Date
Completion
of Completion
CIVIL 100%
1 BOILER STRUCTURE 100%
COMPLETION OF BOILER PRESSURE PARTS 100%
1 31.10.2016 14.06.18
FOUNDATION CIVIL 100%
2 START OF BOILER ERECTION 29.11.16 30.08.17 2 TG STRUCTURE 100%
BOILER DRUM LIFTING (if sub-critical TG ERECTION 100%
3 NA NA
unit) 3 ESP UNDER PROGRESS 99.5%
BOILER CEILING GIRDER LIFTING CIVIL WORK
4 11.05.17 31.07.18 M/s BHEL – FGD Civil
COMPLETION MATERIAL SUPPLY Piping and Pipe cap works
4 FGD are in progress.
5 CONDENSER ERECTION START 29.08.17 02.01.19
ERECTION WORK
6 TG ERECTION START 28.10.17 25.02.19

7 HP PIPING ERECTION START 24.10.17 25.03.18 STATUS OF BOPs - BGRESL/Chennai


BOILER HYDRO TEST (DRAINABLE) Packages/ Scheduled
Anticipated UNIT-01
8 28.02.18 31.12.19 Vendor/Contracting Date of /Actual
COMPLETION Sl. Linked Project Award
Date of
Date of
% Completion
Agency Completion
BOILER HYDRO TEST (NON-
Milestones Completion
9 26.09.18 07.12.22
DRAINABLE) COMPLETION 1 Chimney 10.03.17 25.06.19 15.01.2024 100%

10 TG BOX UP 07.11.18 Aug-23

11 HP PIPING ERECTION COMPLETION 13.04.19 30.11.22 2 Coal Handling Plant 21.07.17 25.07.19 15.02.2024 93.33%

14 START OF OILFLUSHING 29.11.18 03.11.20

12 BOILER LIGHT UP 29.10.18 May-23 3 Ash Handling Plant 25.11.17 28.07.19 15.02.2024 80%

13 CHEMICAL CLEANING COMPLETION 27.02.19 22-06-23 4 Fuel Oil System 27.07.17 28.06.19 15.02.2024 99%

15 STEAM BLOWING START 31.12.18 23-09-23 5 Cooling Towers M/s. BGR ESL 16.05.17 21.09.19 10.02.2024 92.5%

6 CW Pump house 09.01.18 28.05.19 15.02.2024 97%


16 STEAM BLOWING COMPLETION 29.01.19 24-11-23 15.02.2024
7 WPT Plant 16.06.17 17.05.19 93%
15.02.2024
8 DM Plant 06.10.17 28.05.19 93%
17 ROLLING & SYNC. 28.02.19 14-01-24
9 Compressed Air System 10.12.17 28.08.19 31.01.2022 100%

10 Fire Protection System 01.07.17 14.05.19 10.02.2024 90.5%


18 FULL LOAD 28.03.19 Mar-24
11 Switch Yard 19.08.17 26.10.19 05.02.2024 99%

12 Station Transformers BHEL 24.07.18 28.04.19 05.09.2020 100%


19 TRIAL RUN 28.04.19 Mar-24
13 Unit Transformers BHEL 06.03.18 27.02.19 31.01.2023 100%

14 Railway Siding NA NA NA NA NA
20 COD
28.07.19 Mar-24 15 Power Evacuation Lines TANTRANSCO, NCTPS St-III 12.01.18 11.11.19 Nov-2023 100%
-North Chennai (PS), 765 KV,
D/C line

CRITICAL ISSUES
-Delay in AHP Readiness - mechanical works are still in progress. 2 passes ready and 4 passes will be made ready by 3 rd week of Feb’2024.
- Delay in CHP Readiness: Alternate arrangement for ECHS is made from NCTPS, St-I.

REASONS OF DELAY
Due to COVID Lock down in 2020 & 2021 and non-availability of Industrial Oxygen in 2020 & 21, Delay in CW pipe line readiness.

38
Status as on 31-01-2024
UDANGUDI STPP, St-I, Unit# 1 & 2 (2x660 MW) / TANGEDCO (STATE SECTOR )
Distt.- Thoothukudi, Tamil Nadu
E-Gen Portal Registration No. (. Unit-1: 1200002175, Unit -2: 1200002176 )
Project Developer / Implementing Agency – TANGEDCO Main Plant Vendor – M/s BHEL (EPC)
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#1 Jan-2021 Sep-2024
Unit#2 Dec-2017 Mar-2021 Jan –2025
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal, Indigenous & Imported (Indonesia) ORIGINAL ESTIMATED COST
13076.71
COAL COMBUSTION OF THE PROJECT
Supercritical
TECHNOLOGY
LATEST ESTIMATED COST 13076.71
BGT-SE/E/T & H(P)/OT No. 01/ 2015-16.
APPROVAL DATE / NTP BOP-SE/E/T&H(P)/[Link].1/2020-21. DATE OF FINANCIAL Financial tie up with
SWIOP-SE/C/TP/[Link].2/2016-17. CLOSURE M/s. PFC

EPC/BTG/BoP Contractor
Awarded to BHEL as EPC contractor on 07.12.2017 YEAR WISE EXPENDITURE
Details (Package Wise)

PPA NOT APPLICABLE. State sector project. 2017-18 118.93


Allocated Mine – Chandrabila Coal Block for indigenous coal of G13 Grade
for 3.647 MTPA and MDO selection is under process. Distance from mine 2018-19 336.43
COAL LINKAGE/FSA (appx) : Railway distance for movement of coal through Rail-cum-Sea route
via Paradip port is 200 km.(Chandrabila to Paradip port), from Paradip port to 2019-20 654.76
Udangudi captive Port, sea distance is 1224 Nautical Miles. Total requirement
is 5.893 MTPA with Indigenous coal of 3.647 MTPA and import coal of
2.246 MTPA. Import coal (2.246 MTPA) will be procured to the requirements.
Bridge Linkage with SCCL available for indigenous coal

START UP POWER 2020-21 1778.54


230/11 KV Karaigudi Feeder
AGREEMENT
2021-22 1711.00
Tx Line Developer

2022-23 2817.92
POWER EVACUATION
Tx Line Name
SYSTEM
Tx Voltage Level EXPENDITURE OF JAN’2024 49.53
Udangudi STPP – Ottapidaram, 400 KV,
D/C line (BHEL/L&T) TOTAL EXPENDITURE (upto
9392.414
31.01.2024)
Configuration of Tx Line
(S/C or D/C)
Land required for the project is under TANGEDCO Possession. EPC
Contracts awarded to M/s. BHEL & M/S L&T has been suspended as
LAND POSSESSION per the NGT(SZ), Chennai Judgment dated 17.03.2021, delivered on
Appeal No. 144 of 2016(SZ) filed in the designated court for a period
of six months or until further orders.

Tamil Nadu Maritime Board has issued NOC for construction of Jetty
WATER ALLOCATION
for drawal and discharge of cooling water, vide 27.4.2015.

Ministry of Environment and Forest has accorded clearance for the


MOEF CLEARANCE
above Project on 18.05.2016.
CIVIL AVIATION Clearance expired on 21.11.2019. Clearance further extended up to
CLEARANCE 21.11.2024.

CPCB CLEARANCE NOT APPLICABLE. State sector project.

CRZ committee of MOEF recommended the Project on 28.1.16 and


SPCB CLEARANCE
MOM published in web site on 8.2.2016.

FOREST CLEARANCE NOT APPLICABLE

39
Status as on 31-01-2024
UDANGUDI STPP, St-I, Unit# 1 & 2 (2x660 MW) / TANGEDCO (STATE SECTOR )
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL) STATUS OF MAIN PLANT PACKAGE (BTG) : M/S BHEL
UNIT-01 UNIT-02 UNIT-01 UNIT-02
Sl. Packages AREA
Actual / Actual / % Completion % Completion
Sl. MILESTONE
Original Date Anticipated Original Date Anticipated CIVIL 91.26% 93.00%
Date Date
1 BOILER
STRUCTURE 85.72% 89.75%
COMPLETION OF BOILER PRESSURE PARTS 96.11% 97.13%
1 12.09.18 10.04.21 12.11.18 21.04.21
FOUNDATION CIVIL 99.13% 92.23%
2 TG STRUCTURE 84.86% 78.775%
2 START OF BOILER ERECTION 27.09.18 20.09.19 27.11.18 16.09.19
TG ERECTION 44.25% 52.26%
BOILER DRUM LIFTING (if sub-critical 3 ESP UNDER PROGRESS 95.50% 95.86%
3 - - - -
unit) CIVIL WORK
BOILER CEILING GIRDER LIFTING MATERIAL SUPPLY
4
COMPLETION
09.02.19 26.06.21 09.04.19 18.06.21 4 FGD Work yet to be awarded
ERECTION WORK
5 CONDENSER ERECTION START 15.08.19 28.12.22 15.10.19 01.04.23

6 TG ERECTION START 12.09.19 01.02.23 12.11.19 30.03.23 STATUS OF BOPs (BHEL-EPC)


7 HP PIPING ERECTION START 30.10.19 16.04.23 30.10.19 15.05.23 Packages/ Vendor/Contracting Anticipated UNIT-01 UNIT-02
Scheduled
Date of /Actual
BOILER HYDRO TEST (DRAINABLE) Sl. Linked Project Agency (EPC- Award
Date of
Date of % %
8 27.02.20 15.12.22 27.04.2020 20.12.22 Completion
COMPLETION Milestones BHEL) Completion Completion Completion
M/[Link]/ M/s Bygging- Civil
BOILER HYDRO TEST (NON- Structural Erection 26.10.19 20.02.24 99.46%
9 02.07.20 30.04.24 02.09.20 30.06.24 1 Chimney 08.10.18
DRAINABLE) COMPLETION 03.12.20 25.05.24 93.92%

M/s. BHEL/ M/s Kanwar/ M/s


10 TG BOX UP 30.07.20 30.05.24 30.09.20 31.07.24 01.03.22 25.06.20 23.05.24 78.94%
Priya- Civil
2 Coal Handling Plant M/s. BHEL/ M/[Link] /URC 15.07.19 25.06.20 15.04.24 36.30%
11 HP PIPING ERECTION COMPLETION 06.08.20 02.07.24 06.10.20 02.11.24
Structural Erection

M/s. BHEL/IGG 09.05.19 - 15.12.24 -

12 START OF OILFLUSHING 30.07.20 08.04.24 30.09.20 08.08.24 M/[Link]/ RPP/Srinic- Civil


11.05.20 25.06.20 23.05.24 54.60%
M/[Link]/ M/[Link]/URC-
3 Ash Handling Plant 15.07.19 25.06.20 15.03.24 -
Structural Erection
13 BOILER LIGHT UP 09.07.20 31.03.24 09.09.20 31.07.24 15.03.19 30.11.20 15.04.24 -
M/s. BHEL Mechanical Equipment
15.12.24

4 Fuel Oil System M/[Link]/ M/[Link] Civil 25.07.19 22.01.20 29.02.24 96.72%
14 CHEMICAL CLEANING COMPLETION 30.07.20 18.04.24 30.09.20 18.08.24
M/[Link]/ M/[Link] 31.08.24
5 Cooling Towers 16.12.2019 22.10.20 69.87% 25.68%
15.11.24

M/[Link]/ M/s.B&B; M/[Link]/


15 STEAM BLOWING START 13.08.20 20.05.24 13.11.20 20.09.24 6 CW Pump house 04.06.19 17.01.20 20.04.24 78.73%
M/[Link] Techno 09.03.24 75.65%

7 WPT Plant M/[Link]/ M/s.B&B 04.06.19 07.02.20 25.04.24 82.46%


16 STEAM BLOWING COMPLETION 03.09.20 30.06.24 03.11.20 31.10.24
8 DM Plant M/[Link]/ M/[Link] 25.07.19 12.10.19 25.04.24 74.09%

9 Compressed Air System M/[Link] / M/[Link] Mech 07.01.22 01.11.20 25.05.24 97.40%
17 ROLLING & SYNC. 12.11.20 31.07.24 12.01.21 30.11.24
10 Fire Protection System M/s. BHEL - 22.10.20 25.05.24 -

11 Switch Yard M/s. BHEL/ M/s. RB Electrical 25.06.21 23.05.19 29.02.24 96.70%
18 FULL LOAD 31.12.20 31.08.24 28.02.21 31.12.24
12 Station Transformers

13 Generator Transformers M/[Link] / M/s Power Mech 30.12.21 15.06.20 30.04.24 98.67%
19 TRIAL RUN 07.01.21 Sep-24 07.03.21 Jan-25
14 Unit Transformers

15 Railway Siding NA NA NA NA NA
20 COD 25.02.21 Sep-24 25.04.21 Jan-25
16 Power Evacuation Lines Udangudi STPP – Ottapidaram, 27.01.20 11.10.20 29.02.24 100%
400 KV, D/C line (BHEL/L&T)

CRITICAL ISSUES
- Slow progress in execution of works by M/s BHEL for BLU in areas viz. DM Water system, Sea water system
- The slow GIS switchyard progress will impact start up power requirement by Feb 24 .
- Slow progress in NDCTs and critical piping erection
- FGD work is yet to be awarded.( by TANGEDCO)

REASONS OF DELAY
COVID 19, Labor shortage / Vendor Mobilization delay by Contractor, Fishermen issue at Coal Jetty

40
Status as on 31-01-2024

YADADRI TPS, Unit# 1, 2, 3, 4 & 5 (5x800 MW) / TSGENCO (STATE SECTOR )


Veerlapalem village, Damercharla Mandal,Nalgonda, Telangana -508208
E-Gen Portal Registration No. (U#1-1200001092; U#2-1200001093; U#3-1200001094; U#4-1200001095; U#5-1200001096)
Project Developer / Implementing Agency - TSGENCO Main Plant Vendor - BHEL (EPC)
Unit No. LOA Original Trial Run Date Anticipated / Actual COD Date
Unit#1 Oct-2021 Dec-2024
Unit#2 Oct-2021 Dec-2024
Unit#3 Oct-2017 Jun-2022 Mar-2025
Unit#4 Jun-2022 Feb-2025
Unit#5 Oct-2022 Oct-2025
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal, Indigenous ORIGINAL ESTIMATED COST
29965.48
COAL COMBUSTION OF THE PROJECT
Supercritical
TECHNOLOGY
LATEST ESTIMATED COST 34542.95
APPROVAL DATE / NTP 04.10.2014 (MoU entered with BHEL)
DATE OF FINANCIAL
*
LOI was issued to M/s BHEL as EPC contractor (BTG & BOP) on CLOSURE
EPC/BTG/BoP Contractor
01.06.2015 . Revised LOI issued on Dt:17.10.2017 for considering
Details (Package Wise) YEAR WISE EXPENDITURE
new norms & impact of GST with zero date as 17.10.2017.

PPA Power purchase Agreement entered on 11.03.2020 with TSDISCOMS 2015-16 499.46
Allocated Mine - SCCL; Distance from mine - 270 km (non pithead);
2016-17 59.29
Ministry of Coal vide File No.23014/1/2018-CLD, Dt:15-02-2018 has
COAL LINKAGE/FSA
granted coal linkage from SCCL for supply of 14 MTPA of coal
(grade-G9). 2017-18 941.44

As per clause no.2.2 of PPA , TSDISCOMS shall provide electrical 2018-19 2129.24
START UP POWER
energy to TSGENCO for construction, start up and maintenance, also
AGREEMENT
for commissioning of the project. 2019-20 2935.56
Tx Line Developer TSTRANSCO
2020-21 4427.54
i) YTPS –Dindi, 400 KV, D/C line;
Tx Line Name
POWER EVACUATION ii) YTPS-Choutuppal,400 KV, D/C line; 2021-22 3582.33
Tx Voltage Level
SYSTEM iii) YTPS-Damarcherla, 400 KV,
D/C line; 2022-23 5703.27
iv) YTPS-Janagaon, 400 KV, D/C line.
EXPENDITURE OF Jan’2024 92.18
Configuration of Tx Line
(S/C or D/C) TOTAL EXPENDITURE (upto
24,827.39
LAND POSSESSION (Details about land area still to be acquired). Ac.5459.39 Gts 31.01.2024)
Water Source from river Krishna Qty- 208cuses(i.e.6.60 TMC per
WATER ALLOCATION
year) allotted vide [Link].13, Dt:30.01.2015 * M/s REC Ltd vide Lr dt 11-08-2015. M/s PFC Ltd vide Lr
EC obtained from MoEF&CC vide [Link].J-13012/18/2015-IA.I(T), dt 19-07-2015
MOEF CLEARANCE Dt.29- 06-2017 with a validity of 7 years from the date of issue of
MoEF clearance(i.e upto 29.06.2024)
[Link]:NADI/SOUTH/B/071216/149982,Dt:26.07.2016.
CIVIL AVIATION
[Link]:NADI/SOUTH/B/071216/149984,Dt:26.07.2016.
CLEARANCE
[Link]:NADI/SOUTH/B/071216/149988,Dt:26.07.2016.
CPCB CLEARANCE Not Applicable
Consent for Establishment (CFE) received from TSPCB vide Order
SPCB CLEARANCE
No.10/TSPCB/CFE/RO-NLG/HO/2017, Dt.25-07-2017.
Approval was accorded by Central Govt. Ministry of Environment,
Forest, Climate Change, MoEF &CC, GOI, FC Section, New Delhi for
diversion of forest land to an extent of 1892.35 hectares vide
FOREST CLEARANCE
[Link].8.07/2015-FC dt.07-07-2015 Subsequent G.O. was issued
by Govt. of Telangana vide [Link].38,dt.30-07-2015 by EFS & T
(For) Department.

41
Status as on 31-01-2024
YADADRI TPS, Unit# 1, 2, 3, 4 & 5 (5x800 MW) / TSGENCO (STATE SECTOR )
STATUS OF BTG WORKS
UNIT-01 UNIT-02 UNIT-03 UNIT-04 UNIT-05
Sl. Packages AREA
% Completion % Completion % Completion % Completion % Completion
CIVIL 100.00% 100.00% 100.00% 100.00% 100.00%
1 BOILER STRUCTURE 84.79% 92.71% 76.62% 87.38% 79.04%
PRESSURE PARTS 99.31% 100.00% 92.30% 99.69% 99.28%
CIVIL 98.50% 98.50% 98.00% 97.00% 96.00%
2 TG STRUCTURE 99.63% 99.27% 97.77% 97.72% 90.96%
TG ERECTION 91.00% 93.05% 67.00% 69.05% 65.00%
3 ESP UNDER PROGRESS 96.28% 96.97% 92.21% 94.40% 88.13%
CIVIL WORK 21.00 21.00 21.00 21.00 21.00
MATERIAL SUPPLY 72.00 72.00 60.00 72.00 72.00
4 FGD
ERECTION WORK
0.00 0.00 0.00 0.00 0.00
UNIT WISE MILESTONES (ANTICIPATED / ACTUAL )
UNIT-01 UNIT-02 UNIT-03 UNIT-04 UNIT-05

Sl. MILESTONE Actual / Actual / Actual / Actual / Actual /


Original Date Anticipated Original Date Anticipated Original Date Anticipated Original Date Anticipated Original Date Anticipated
Date Date Date Date Date

1 COMPLETION OF BOILER FOUNDATION 08.01.20 08.01.20 29.12.19 29.12.19 11.02.20 11.02.20 16.02.20 16.02.20 23.03.20 23.03.20
2 START OF BOILER ERECTION 18.02.20 18.02.20 30.07.20 30.07.20 18.03.20 18.03.20 30.07.20 30.07.20 14.08.20 14.08.20
3 BOILER DRUM LIFTING (if sub-critical unit) NA NA NA NA NA
4 BOILER CEILING GIRDER LIFTING COMPLETION 31.01.21- 20.03.21 31.03.21 31.03.21 11.04.21 11.04.21 09.06.21 09.06.21 07.09.21 07.09.21
5 CONDENSER ERECTION START 31.03.21 20.10.21 31.05.21 03.01.22 30.05.21 13.12.22 31.07.21 24.10.22 15.10.21 09.10.22
6 TG ERECTION START 03.05.21 20.12.21 30.06.21 31.01.22 31.08.21 21.12.22 30.10.21 25.10.22 30.11.21 20.10.22
7 HP PIPING ERECTION START 01.04.21 16.09.21 01.05.21 01.01.22 01.06.21 15.07.22 01.07.21 31.07.22 01.08.21 31.07.22
8 BOILER HYDRO TEST (DRAINABLE) COMPLETION 31.01.22 31.07.22 31.03.22 21.06.22 31.05.22 26.05.23 31.07.22 15.09.22 30.09.22 26.05.23
9 BOILER HYDRO TEST (NON-DRAINABLE) 15.07.22 15.03.23 15.09.22 15.02.23 15.11.22 01.08.23 15.01.23 10.07.23 15.03.23 15.08.23
COMPLETION
10 TG BOX UP 31.05.22 30.03.23 31.07.22 05.02.23 31.08.22 30.04.24 30.10.22 30.06.24 30.11.22 31.05.24
11 HP PIPING ERECTION COMPLETION 13.10.22 31.03.24 13.11.22 28.02.24 13.12.22 28.11.24 13.01.23 15.10.24 13.02.23 15.10.24
12 START OF OIL FLUSHING 30.04.22 09.06.23 31.05.22 23.03.23 31.07.22 31.05.24 30.09.22 31.03.24 30.10.22 30.06.24
13 BOILER LIGHT UP 31.07.22 08.05.24 30.09.22 08.05.24 30.11.22 31.07.24 31.01.23 31.05.24 31.03.23 31.08.24
14 CHEMICAL CLEANING COMPLETION 05.09.22 20.05.24 29.09.22 20.05.24 29.10.22 31.08.24 29.11.22 15.06.24 29.12.22 30.09.24
15 STEAM BLOWING START 14.09.22 30.06.24 14.10.22 30.06.24 14.11.22 30.11.24 14.12.22 31.08.24 14.01.23 30.09.24
16 STEAM BLOWING COMPLETION 14.10.22 30.07.24 14.11.22 30.07.24 14.12.22 31.12.24 14.01.23 30.09.24 14.02.23 30.11.24

17 ROLLING & SYNC. 30.10.22 30.10.24 31.12.22 05.11.24 31.01.23 10.02.25 31.03.23 30.11.24 30.06.23 30.08.25
18 FULL LOAD 12.02.23 15.12.24 15.03.23 20.11.24 15.04.23 20.02.25 15.05.23 15.12.24 15.06.23 01.10.25
19 TRIAL RUN Feb’23 Dec-24 Mar’23 Dec-24 Apr’23 Mar-25 May’23 Feb-25 Jun’23 Oct-25

20 COD

42
Status as on 31-01-2024
YADADRI TPS, Unit# 1, 2, 3, 4 & 5 (5x800 MW) / TSGENCO (STATE SECTOR )
STATUS OF BOPs
Vendor/Contracting Agency Anticipated/Act
UNIT-01 UNIT-02 UNIT-03 UNIT-04 UNIT-05
Packages/ Linked Project Scheduled Date
Sl. Date of Award
of Completion
ual Date of % % % % %
Milestones Completion
Completion Completion Completion Completion Completion

Bygging India Ltd for Unit 03.02.20 30.12.23 Shell Concreting-100% Shell Concreting-100% SC-100%
1 Chimney #1&2; Paharpur for Unit #3&4; 24.02.20 31.07.22 Flue can Erection Flue can Erection FCE-
ByggingIndia Ltdfor Unit #5 12.02.20 100% 100% 100%
Powermech (Conveyor package) 09.08.20 31.12.22 28.02.24 95.29%
2 Coal Handling Plant (Civil) Powermech (Wagon tripler) 10.12.20 30.06.23 28.02.24 99.79%
Powermech (Stacker Reclaimer ) 08.10.20 30.06.23 30.08.23 100%
3 Ash Handling Plant BHEL/ Powermech 08.06.21 31.12.22 30.05.24 76.63%
4 Fuel Oil System BHEL/Thermosystems 19.02.21 31.07.22 30.06.23 100%
BHEL/NBCC for Unit #1 (Now M/s Paharpur) 09.01.21 30.10.22 31.05.24
BHEL/Gammon for Unit#2 18.12.20 28.02.23 31.05.24
5 Cooling Towers BHEL/NBCC for Unit#3 06.02.21 31.03.23 30.06.24 91.60% 91.95% 87.70% 70.07% 53.26%
BHEL/Gammon for Unit#4 25.02.21 30.04.23 31.08.24
BHEL/NBCC for Unit#5 18.03.21 31.05.23 30.09.24

6 CW Pump house CW pump house & channel - BHEL/HES 31.07.24 99% 99% 75.83% 75.83% 75.83%

7 WPT Plant BHEL/SCC 03.02.21 31.01.22 31.03.24 97%


8 DM Plant BHEL/SCC 01.10.20 31.01.22 31.03.24 99.85%
9 Compressed Air System BHEL/HES 12.02.21 31.05.22 31.03.24 99.17%
10 Fire Protection System BHEL - 31.07.22 31.05.24 6.10%
11 Switch Yard BHEL/Bluechip 13.02.21 31.07.22 30.03.24 85%
BHEL/EIPL for Unit-1 14.12.19 30.10.22 28.02.24
12 Generator Transformers
BHEL/KEPL for Unit-2
17.10.20 31.12.22 28.02.24
13 Station Transformers BHEL/EIPL for Unit-3
26.10.19 31.01.23 28.02.24 98.5% 97% 98.5% 97% 90%
BHEL/KEPL for Unit-4
14 Unit Transformers BHEL/KEPL for Unit-5 22.10.19 31.03.23 28.02.24
18.12.19 31.05.23 31.03.24
15 Railway Siding Work in progress 06.12.23 30.04.24 68%
16 Power Evacuation Lines TS TRANSCO/MEIL 06.08.20 24.02.22 31.10.24 87%

CRITICAL ISSUES
1) Issue of fresh EC pending, hence all commissioning works on hold.
TSGENCO has filed Execution Application on 13-09-2023 before Hon’ble NGT, Chennai. The Hon’ble NGT, while disposing the aforementioned Execution application, has
directed the MoEF&CC, GoI to issue the additional ToR. In compliance to the above judgement dated. 30.10.2023, MoEF&CC, GoI has issued additional ToR on 08.11.2023
where in, it was also directed to conduct public hearing. In view of the recommendations given by the Expert Appraisal Committee in its meeting held on 02.11.2022, Hon’ble
NGT being approached by TSGENCO praying for exemption of public hearing and proceed with the public consultation to avoid further delay in commissioning of the project.

REASONS OF DELAY
1) Delay in agency finalization of Main plant civil works and Boiler erection works.
2) The works of YTPS were adversely affected due to Covid-19 (1.0) as lockdown was imposed by State Government. Further upon resumption of the site works also, the
works could not progress at the required pace, due to acute shortage of man power as most of the available workers at site have left.
3) The impact of monsoons and unprecedented rains during other seasons resulted in frequent dewatering caused interruption to the movement of men and machinery which
affected the work progress at YTPS site.
4) The outbreak of Covid-19 (2.0) again hit the country with higher magnitude from March 2021 onwards. Number of workers and engineers are effected with Covid-19 in
the project. Erection works are hampered due to non-availability of oxygen cylinders as the oxygen is diverted to Hospitals as per the directions of State Government.

43
Status as on 31-01-2024
BHUSAWAL SUPERCRITICAL TPP, Unit# 6 (1X660 MW) / MAHAGENCO (STATE SECTOR )
Village Pimpari Sekam, Tal Bhusawal, Distt.- Jalgaon, Maharashtra, Pincode-425307
E-Gen Portal Registration No. (U#6 - 1200002450)
Main Plant Vendor - M/s BHEL (EPC Contract-17.01.2018)
Project Developer / Implementing Agency - MAHAGENCO
Unit No. LoA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#6 Jan-2018 May-2022 Mar-2024
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal, Indigenous ORIGINAL ESTIMATED COST
4548.00
COAL COMBUSTION OF THE PROJECT
Super Critical
TECHNOLOGY
LATEST ESTIMATED COST 4550.97
APPROVAL DATE / NTP 25-09-2009
DATE OF FINANCIAL
NA
EPC/BTG/BoP Contractor M/s BHEL (EPC Contract, LoA:17.01.2018) CLOSURE
Details (Package Wise)
YEAR WISE EXPENDITURE
Long Term Power Purchase Agreement dated 24.12.2010 with
PPA Maharashtra state Electricity Distribution Co. ltd for 100% of installed
capacity
2018-19 51.21
Allocated Mine - WCL, Umred/Ghugus; Distance from mine –
403/430km; Allocation Date: 11-09-2020, Source:WCL mines ,Grade: 2019-20 564.66
COAL LINKAGE/FSA
G9/G10, Quantity : 318 million tonne.
2020-21 889.57
Maharashtra State Electricity Transmission Company Ltd (MSETCL)
vide letter no MSETCL/CO/STU/302 B/B_GC/No. 12757, dated
START UP POWER 2021-22 1261.79
06/12/2018 approved Grid connectivity, which is valid till 06.06.2021.
AGREEMENT
Letter regarding extension up to Dec-2022, is sent to STU, MSETCL
on 07.05.2021. 2022-23 616.04

EXPENDITURE OF JAN’2024 35.31


Tx Line Developer MSETCL TOTAL EXPENDITURE
4082.52
(upto 31.01.2024)
Tx Line Name LILOing of Bhusawal-II - Aurangabad
POWER EVACUATION
Tx Voltage Level I, 400 KV, D/C line at Thaptitanda
SYSTEM

Configuration of Tx Line
(S/C or D/C)

Total Land Required: 120.39 Hectare


LAND POSSESSION Total land acquired: 118.415 Hectare Total land in use: 118.415
Hectare

WATER ALLOCATION Source: - Tapi River, Quantity: - 18.85 MM3 Per Annum.

Clearance obtained date from concerned authority: 27/11/2012 validity


MOEF CLEARANCE
: 26/11/2022
CIVIL AVIATION Clearance obtained date from concerned authority: 27/08/2008 validity
CLEARANCE : 23/02/2022
CPCB CLEARANCE Not Applicable
Clearance obtained date from concerned authority: 10/06/2020 validity
SPCB CLEARANCE : The consent to establish is granted for period up to commissioning of
the unit or up to 5 years whichever is earlier.
Clearance obtained date from concerned authority: 14/01/2020
FOREST CLEARANCE
validity: 26/11/2022.

44
Status as on 31-01-2024
Status as on 31-01-2024
BHUSAWAL SUPERCRITICAL TPP, Unit# 6 (1X660 MW) / MAHAGENCO (STATE SECTOR )
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL) STATUS OF MAIN PLANT PACKAGE (BTG) : M/S BHEL
UNIT-06 UNIT-06
Sl. Packages AREA
% Completion
Sl. MILESTONE
Anticipated / Actual Date of
Original Date of Completion
Completion
CIVIL
1 BOILER STRUCTURE WORKS 96%
1 COMPLETION OF BOILER FOUNDATION 25.11.2019 15.11.2019 PRESSURE PARTS
2 START OF BOILER ERECTION 30.11.2019 22.11.2019 CIVIL
3 BOILER DRUM LIFTING (if sub-critical unit) NA NA 2 TG STRUCTURE WORKS 99%
BOILER CEILING GIRDER LIFTING
4
COMPLETION
30.06.2020 20.01.2021 PRESSURE PARTS
5 CONDENSER ERECTION START 31.10.2020 30.03.2022 3 ESP PASS STATUS 98%
6 TG ERECTION START 30.11.2020 03.03.2022 CIVIL WORK
7 HP PIPING ERECTION START 11.05.2021 22.03.2021 4 FGD MATERIAL SUPPLY 66%
8 BOILER HYDRO TEST (DRAINABLE) 31.05.2021 04.11.2022 ERECTION WORK
COMPLETION
9 BOILER HYDRO TEST (NON-DRAINABLE)
COMPLETION
10.11.2021
Mar-2023 STATUS OF BOPs
10 TG BOX UP 30.11.2021 10.04.2023 UNIT-01
Scheduled Anticipated/Act
Packages/ Linked Project Date of
11 HP PIPING ERECTION COMPLETION 25.04.2022 Oct,2023 Sl. Vendor/Contracting Agency (EPC- BHEL) Date of ual Date of
Milestones Award
Completion Completion % Completion

12 START OF OILFLUSHING 04.12.2021 June-2023


1 Chimney M/s Powermech 30.05.2019 28.02.2022 Feb-2024 99%

M/s BJCL & Macawber Beekay Pvt Ltd.(Conveyor 27.05.2019 30.04.2022 Feb-2024 78%
13 BOILER LIGHT UP 30.11.2021 Mar-2023 package
2 Coal Handling Plant M/s BJCL& Promac (Wagon tippler) 28.05.2019 30.04.2022 Mar-2024 70%

M/s BJCL& Promac(Stacker Reclaimer) 24.08.2019, 90%


28.05.2019 30.04.2022 Feb-2024
14 CHEMICAL CLEANING COMPLETION 20.12.2021 Jun-2023
M/s BJCL & Macawber Beekay Pvt Ltd. 24.08.2019, 81%
3 Ash Handling Plant 31.03.2022 Feb-2024
23.12.2021
4 Fuel Oil System M/s. New Fire Engineers Pvt Ltd. 19.09.2019 21.11.2021 Feb-2024 97%
15 STEAM BLOWING START 24.01.2022 Sep-2023
M/s Hayagrev civil engineering Pvt Ltd 1.11.2019, 99%
5 Cooling Towers 31.03.2022 Feb-2024
05.03.2022
6 CW Pump house M/s Alpha power engineering services Pvt 29.01.2019 28.02.2022 Jan-2024 100%
16 STEAM BLOWING COMPLETION 19.02.2022 Oct-2023 Ltd,G&J Pvt Ltd.
7 WPT Plant M/s Clear Water company 17.02.2020 12.12.2021 Feb-2024 86%

8 DM Plant M/s Wipro Enterprises Pvt Ltd 14.01.2020 30.11.2021 Feb-2024 99%
17 ROLLING & SYNC. 31.03.2022 17-01-2024
9 Compressed Air System M/s Elgi equipment Ltd. 24.08.2020 04.11.2021 Feb-2024 99%

10 Fire Protection System M/s Alpha power engineering services Pvt Ltd 29.01.2021 20.05.2021 Mar-2024 98%
18 FULL LOAD 30.04.2022 Mar-2024
11 Switch Yard M/s BNC Power Projects Ltd 15.02.2021 28.02.2022 Jan-2023 100%

12 Station Transformers M/s BHEL 17.01.2018 08.07.2021 Jan-2023 100%


19 TRIAL RUN 31.05.2022 Mar-2024
13 Unit Transformers M/s BHEL 17.01.2018 20.01.2022 Mar-2024 90%

14 Railway Siding ISC Projects 02.01.2021 31.03.2022 Mar-2024 86%


Mar-2024
20 COD 31.05.2022
15 Power Evacuation Lines MSETCL/BNC Power Projects 15.02.2021 28.02.2022 Feb,2023 100%

CRITICAL ISSUES
i) Delay in laying of Ash Dyke pipe lines- pedestal works pending (9000 m/ 11646 m length completed). Likely to be completed by 15-03-2024.
ii) Delay in readiness of PA Fan duct.
iii) Coal Bunker(RHS) & CHP structural welding works pending which is critical for coal firing activity.
iv) Railway siding: civil works are pending which are critical for Trial Operation.

REASONS OF DELAY
Due to Covid-19 pandemic.

45
Status as on 31-01-2024

SAGARDIGHI TPP, St-III, Unit# 5 (1X660 MW) / WBPDCL (STATE SECTOR )

PS-Sagardighi, PO-Manigram, Block-Sagardighi, Subdivision-Jangipur, Distt.-Murshidabad (W. B.), Pin-742 237


E-Gen Portal Registration No. (U#5 - 1200002116)
Project Developer / Implementing Agency - WBPDCL Main Plant Vendor - M/s BHEL (EPC Contract)
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#5 27th Dec-2018 Jan-2024 Jan-2025
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal, Indigenous ORIGINAL ESTIMATED COST
3862.65*
COAL COMBUSTION OF THE PROJECT
Super Critical
TECHNOLOGY
LATEST ESTIMATED COST 4567.32#
Notice to Proceed Date : 01.07.2020; The proposal was approved in
APPROVAL DATE / NTP
the State Cabinet held on 23.03.2018. DATE OF FINANCIAL
02.01.2017
EPC/BTG/BoP Contractor EPC contract awarded to BHEL (LOA : 27.12.2018) CLOSURE
Details (Package Wise)
YEAR WISE EXPENDITURE
PPA Power Purchase Agreement executed with WBSEDCL
2018-19 70.00

Allocated Mine - Pachhwara (North) Captive Coal Mine of WBPDCL. 2019-20 56.25
COAL LINKAGE/FSA Distance from mine - 150 km (non pithead);
Coal will be sourced mainly from captive coal mines of WBPDCL 2020-21 362.47

2021-22 330.97
START UP POWER Start up power shall be obtained from the other running units of the
AGREEMENT Sagardighi Thermal Power Project
2022-23 662.34

EXPENDITURE OF Jan’2024 42.20


Tx Line Developer TOTAL EXPENDITURE
STPP – New Sagardighi, 220 KV, D/c
1899.79
i) (upto 31.01.2024)
line,
Tx Line Name ii) STPP- Farakka, 400 KV D/c line,
POWER EVACUATION
Tx Voltage Level iii) STPP-Purulia 400 KV D/c line, * Approved in the State Cabinet held on
SYSTEM
iv) STPP- Baharampore 400 KV, D/C line, 23.03.2018
v) STPP- Gokarna 400 KV D/C line.
Configuration of Tx Line # Awaiting Approval
(S/C or D/C)

Adequate land is available for the project. (WBPDCL have 365 Ha of


LAND POSSESSION land under possession for Phases I, II & III of the plant and another
184 Ha for ash disposal.)

Source:River Bhagirathi/Hooghly Quantity:74.36 cusec of water in


WATER ALLOCATION total for the entire Project. Permission vide F. No. TE-
15015/1/2019/NMCG, Dated: 01.07.2019 accorded by National
Environmental clearance vide F. No. J-13012/01/2019-IA. I (T) dated
MOEF CLEARANCE
24.03.2020 accorded by MoEF & CC Govt. of India for new unit No 5
CIVIL AVIATION NOC for height Clearance vide NOC ID:
CLEARANCE MALD/EAST/B/100316/175516, Dated: 19.10.2016 obtained from
CPCB CLEARANCE Not Applicable

Online application for Grant of Consent to Establish / NoC has been be


SPCB CLEARANCE
made to WBPCB on 27.03.2021

FOREST CLEARANCE Not Applicable

46
Status as on 31-01-2024
SAGARDIGHI TPP, St-III, Unit# 5 (1X660 MW) / WBPDCL (STATE SECTOR )
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL) STATUS OF MAIN PLANT PACKAGE (BTG) : M/s BHEL
UNIT-05 UNIT-05
Sl. Packages AREA
% Completion
Sl. MILESTONE Anticipated / Actual Date of
Original Date of Completion CIVIL 100%
Completion
1 BOILER STRUCTURE 46.13%

COMPLETION OF BOILER PRESSURE PARTS 89.94%


1 19.04.2021 16.10.2021
FOUNDATION CIVIL 100%

2 START OF BOILER ERECTION 29.04.2021 27.03.2021 2 TG


STRUCTURE -
BOILER DRUM LIFTING (if sub-critical
3 NA NA CIVIL WORKS 100%
unit)
3 ESP
BOILER CEILING GIRDER LIFTING STRUCTURAL WORKS 91.99%
4 30.12.2021 22.06.2022
COMPLETION 4 FGD NOT STARTED YET

5 CONDENSER ERECTION START 03.03.2022 03.08.2022 STATUS OF BOPs


6 TG ERECTION START 02.05.2022 28.08.2022 UNIT-01
Scheduled Anticipated/A
15.04.23 Packages/ Linked Project Vendor/Contracting Agency (EPC- Date of
7 HP PIPING ERECTION START 25.11.2022 Sl. Date of ctual Date of
Milestones BHEL) Award
Completion Completion % Completion
Feb’24
BOILER HYDRO TEST (DRAINABLE)
8 30.12.2022
COMPLETION M/s. BHEL 17.08.2021
1 Chimney (ZERO 17.05.2023 55%

Mar’24 Conveyor package: Bengal Tools 27.12.2018 35.00%.


BOILER HYDRO TEST (NON- 15.12.2023
9 29.05.2023 Limited (ZERO
DRAINABLE) COMPLETION 2 Coal Handling Plant Twin Wagon Tippler : DATE AS 13.12.2023
ThyssenKrupp PER
10 TG BOX UP 01.06.2023 Feb’24 Existing Stacker Reclaimer of
Stage-II will be used
Apr’24 3 Ash Handling Plant M/s. MacawberBeekey Pvt. Ltd. 28.03.2024 40.00%
27.12.2018
11 HP PIPING ERECTION COMPLETION 26.08.2023 (ZERO
4 Fuel Oil System M/s. BHEL 27.08.2023 0%
DATE AS
June’24 M/s. Paharpur Cooling Towers PER
12 START OF OIL FLUSHING 28.03.2023 5 Cooling Towers Limited 31.12.2022 Jun’2024 99.00%
CONTRACT
13 BOILER LIGHT UP 13.06.2023 Jun’24 6 CW Pump house M/s. BHEL 01.07.2020) 09.12.2023 37.75%

8 WPT Plant
Jun,24 Existing from Stage – II Project
14 CHEMICAL CLEANING COMPLETION 28.06.2023 Will be used from Existing
will be used.
9 DM Plant

July’24 20.00%
15 STEAM BLOWING START 13.07.2023 11 Compressed Air System M/s. BHEL 25.08.2023
27.12.2018 02.00%
16 STEAM BLOWING COMPLETION 12.08.2023 Aug’24 12 Fire Protection System M/s. BHEL 24.03.2024
(ZERO
Sep’24 DATE AS 73.00%
15 Switch Yard M/s. BHEL 22.03.2024
PER
17 ROLLING & SYNC. 01.09.2023
16 Station Transformers M/s. BHEL CONTRACT 30.03.2023
01.07.2020) 40.35%
Dec.’24 18 Unit Transformers M/s. BHEL 27.08.2023
18 FULL LOAD 01.11.2023
19 Railway Siding Railway siding exists. M/s. Rites will do the modification job for connecting Twin Wagon Tippler for Stage 3.

Power Evacuation from the proposed unit shall be done through the existing electrical network
19 TRIAL RUN 01.01.2024 Jan-25 consisting of following feeders
i) STPP – New Sagardighi, 220 KV, D/c line,
20 Power Evacuation Lines ii) STPP- Farakka, 400 KV D/c line,
iii) STPP-Purulia 400 KV D/c line,
20 COD Jan-24 Jan-25 iv) STPP-Subhashgram 400KV D/c line,
v) STPP-Jeerat 400KV D/c line,
vi) STPP- Baharampore 400 KV, D/C line,
vii) STPP- Gokarna 400 KV D/C line.

CRITICAL ISSUES
- Delay in supply of critical piping, LT Switchgear
- Slow progress in CHP
- Supply of SCR package for NOx control

REASONS OF DELAY
1. Effect of COVID -19 during Project Tenure:, Scarcity of Industrial Oxygen affected fabrication work. Quarantine of workers & officials.
2. Restrictions affected mobilization.
3. Delay in sequential supply of Critical Items, mainly Boiler Pressure Parts from BHEL-Trichy works.
4. Delay in supply of Double Girder EOT Crane (more than 100 MT capacity) which resulting in delay in delay in Turbine Erection. TPI completed in Feb 2023.
5. Delay in ordering of Bought out items, like :
• Condensate Polishing Unit.
• Mill Rejection System.
• Control Valves.

47
Status as on 31-01-2024
MAHAN USCTPP, Ph-II, Unit# 3 & 4 (2X800 MW) / Mahan Energen Ltd. (PRIVATE SECTOR)
Village: Bandhaura, Post: Karsualal,Tehsil: Mada, District: Singrauli, Madhya Pradesh – 486886
E-Gen Portal Registration No. (U#3 - 1200003898 ; U#4 - 1200003899 )
Project Developer / Implementing Agency -
Main Plant Vendor : SG, TG - BHEL (Supply)
Mahan Energen Ltd
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#3 Nov-2026 Dec-2026
Aug-2023
Unit#4 May-2027 May-2027
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal Based ORIGINAL ESTIMATED COST
12439.00
COAL COMBUSTION OF THE PROJECT
Ultra-supercritical
TECHNOLOGY
LATEST ESTIMATED COST 12439.00
APPROVAL DATE / NTP 20.06.2023
DATE OF FINANCIAL
20.06.2023
CLOSURE
EPC/BTG/BoP Contractor
20-Aug-23: BTG Supply & Supervision Ordering to M/s BHEL YEAR WISE EXPENDITURE
Details (Package Wise)

2022-23 53

Long term Power Sale Agreement ("PSA") signed for supply of 1320 2023-24 196
PPA
MW (Gross) power to Madhya Pradesh Power Management Co. Ltd.
("MPPMCL") for period of 25 years w.e.f. COD of the project term. EXPENDITURE OF Jan’2024 127.98

Allocated coal linkage of 5 MTPA from WCL under para b(iv) of the TOTAL EXPENDITURE (upto
COAL LINKAGE/FSA SHAKTI Policy. Balance coal requirement will be fulfilled by nearby 660.84
31.01.2024)
commercial mine.

START UP POWER
Startup power will be arranged from transmission to be developed
AGREEMENT
by MPPMCL in line with the PSA.

Tx Line Developer MPPMCL

As per PSA, Power Evacuation from


Tx Line Name
POWER EVACUATION the bus bar of the power station is to
Tx Voltage Level
SYSTEM be developed by MPPMCL.

Configuration of Tx Line
(S/C or D/C)
Total land required for proposed expansion area is 288 Acres
LAND POSSESSION
which is already in possession. The total area of the Project
site is 920 Acres including exsiting facility.

WATER ALLOCATION Agreement signed on 18-Oct-22 for drawl of 36 MCM water from
River Rihand (Govind Vallabh Pant Sagar) with the validity of 30
years

MOEF CLEARANCE MoEFCC Clearance for the Project obtained on 27-Jul-23 (Validity of
10 years as per guideline)
CIVIL AVIATION
CLEARANCE NOT APPLICABLE

CPCB CLEARANCE NOT APPLICABLE

SPCB CLEARANCE CTE awaited.

FOREST CLEARANCE
NOT APPLICABLE

48
Status as on 31-01-2024
MAHAN USCTPP, Ph-II, Unit# 3 & 4 (2X800 MW) / Mahan Energen Ltd. (PRIVATE SECTOR)
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL) STATUS OF MAIN PLANT PACKAGE (BTG) : SG, TG – BHEL (Supply)
UNIT-03 UNIT-04 UNIT-03 UNIT-04
Sl. Packages AREA
% %
Actual / Actual / Completion Completion
Sl. MILESTONE 0%
Original Date Anticipated Original Date Anticipated CIVIL 0%
Date Date 0% 0%
1 BOILER STRUCTURE

1 COMPLETION OF BOILER PRESSURE PARTS 0% 0%


Oct-24 Oct-24 May-25 May-25
FOUNDATION
2 START OF BOILER ERECTION CIVIL 0% 0%
Jul-24 Jul-24 Jan-25 Jan-25
3 BOILER DRUM LIFTING (if sub-critical 2 TG STRUCTURE
NA NA
unit)
4 BOILER CEILING GIRDER LIFTING Jan-25 Jan-25 Jul-25 Jul-25 TG ERECTION 0% 0%
COMPLETION
5 CONDENSER ERECTION START 3 ESP UNDER PROGRESS 0% 0%
Jun-25 Jun-25 Dec-25 Dec-25
6 TG ERECTION START CIVIL WORK 0% 0%
Sep-25 Sep-25 Mar-26 Mar-26
7 HP PIPING ERECTION START MATERIAL SUPPLY 0% 0%
Aug-25 Aug-25 Feb-26 Feb-26
4 FGD
8 BOILER HYDRO TEST (DRAINABLE) 0% 0%
COMPLETION Feb-26 Feb-26 Aug-26 Aug-26
ERECTION WORK
9 BOILER HYDRO TEST (NON-
DRAINABLE) COMPLETION Apr-26 Apr-26 Oct-26 Oct-26
10 TG BOX UP Jul-26 Jul-26 Jan-27 Jan-27 STATUS OF BOPs
11 HP PIPING ERECTION COMPLETION Apr-26 Apr-26 Oct-26 Oct-26 Packages/ Anticipated UNIT-03 UNIT-04
Scheduled
Sl. Linked Project Vendor/Contracting Date of /Actual
12 START OF OIL FLUSHING Apr-26 Apr-26 Oct-26 Oct-26 Date of % %
Milestones Agency Award Date of
Completion
13 BOILER LIGHT UP Aug-26 Aug-26 Feb-27 Feb-27 Completion Completion Completion

14 CHEMICAL CLEANING COMPLETION 0% 0%


Jun-26 Jun-26 Dec-26 Dec-26
1 Chimney Jul-26
Mar-24 Jul-26
15 STEAM BLOWING START Aug-26 Feb-27
Aug-26 Feb-27
Mar-24 Jun-26 Jun-26 0% 0%
2 Coal HandlingPlant
Conveyor Package 0% 0%
NA NA NA
Oct-26 Mar-27 Wagon Tippler 0% 0%
16 Mar-24 Apr-26 Apr-26
STEAM BLOWING COMPLETION Sep-26 Mar-27 Crusher House Pkg
3 Ash Handling Mar-24 Jun-26 Jun-26 0% 0%

4 Fuel Oil System Jul-24 Jun-26 Jun-26 0% 0%

17 Dec-26 May-27 5 Cooling Towers Mar-24 May-26 May-26 0% 0%


ROLLING & SYNC. Nov-26 May-27
6 CW Pump House and 0% 0%
Tender Floated, Pre-Bid May-24 May-26 May-26
Piping
under progress 0% 0%
7 WPT Plant Mar-24 Jan-26 Jan-26
18 Dec-26 May-27 8 DM Plant Mar-24 Jan-26 Jan-26 0% 0%
FULL LOAD Nov-26 May-27
9 Compressed Air 0% 0%
May-24 Feb-26 Feb-26
System
10 Fire Protection Jun-24 May-26 May-26
0% 0%
System
19 Dec-26 May-27 0% 0%
TRIAL RUN Nov-26 May-27 11 Switch Yard Mar-24 May-26 May-26
12 Station Txer Mar-24 Jul-26 Jul-26 0% 0%

13 Generator Txer Mar-24 Jul-26 Jul-26 0% 0%


14 Unit Txer May-24 Mar-26 Mar-26 0% 0%
20
COD Dec-26 Jan-27 Jun-27 Jun-27 0% 0%
15 Railway Siding NA NA NA
16 Power evacuation NA

CRITICAL ISSUES

-------------

REASONS OF DELAY

-----------------

49
Status as on 31-01-2024
YELAHANKA COMBINED CYCLE PP (YCCPP), Unit# 1 (1x370 MW) / KPCL (STATE SECTOR )
Yelahanka Combined Cycle Power Plant (YCCPP), Doddballapura Road, Bengaluru (Karnataka)-560 064
E-Gen Portal Registration No. (U#1 -1200002031 )
Project Developer / Implementing Agency - KPCL Main Plant Vendor - BHEL (EPC Contract-03.11.2015)
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#1 Nov-2015 Feb-2018 Feb-2024
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE RLNG (Regasified Liquified Natural Gas) ORIGINAL ESTIMATED COST
1571.18
COAL COMBUSTION OF THE PROJECT
NOT APPLICABLE
TECHNOLOGY
LATEST ESTIMATED COST 2055.23
Approval Date: Government Of Karnataka Order No. EN78PPC2010
APPROVAL DATE / NTP
Bengaluru dated:05.07.2011 DATE OF FINANCIAL
31.03.2021
EPC/BTG/BoP Contractor EPC Contractor: M/s BHEL CLOSURE
Details (Package Wise) LOA Date:03.11.2015
YEAR WISE EXPENDITURE
PPA Under Process
2015-16 4.87

2016-17 152.89
COAL LINKAGE/FSA NOT APPLICABLE
2017-18 1050.00

2018-19 140.93
START UP POWER 20000 KVA on HT basis vide BESCOM Letter No. CEE/BMAZ-
AGREEMENT N/SEE(O)/AEE-2/18-19/2473-78 dated:17.11.2018
2019-20 171.41
Tx Line Developer KPTCL
2020-21 219.28
Tx Line Name
POWER EVACUATION 2021-22 263.80
Tx Voltage Level 3 nos. of 220 kV lines are ready (Dec-
SYSTEM
2018) for the power evacuation
2022-23 167.74

EXPENDITURE OF DEC’2023 3.87


Configuration of Tx Line
(S/C or D/C) TOTAL EXPENDITURE (upto
2334.74
The land was acquired during 1994 to establish Diesel generation plant 31.12.2023)
and DG plant has been operated from 1994 to Aug 2013. The DC plant
LAND POSSESSION was stopped from Aug 2013 due to High operating cost &
environmental issues. The YCCPP is established in the same plant by
dismantling required space as per the order of GoK.

15 MLD Tertiary treated plant at JAKKUR is supplying water to


WATER ALLOCATION
YCCP Plant

Approval No : State Level environment impact assessment


MOEF CLEARANCE
authority(SEIAA) no SEIAA20IND 2014 DATED 1/9/2015
CIVIL AVIATION
Approval no : AAI /KIA/ATM/NOC/488-92 DATED 5/5/2015
CLEARANCE
CPCB CLEARANCE NOT APPLICABLE

Approval No : KSPCB/CFE/CEO/KPCL/2015-16/H1033 DATED


SPCB CLEARANCE
02/11/2015

FOREST CLEARANCE Letter No: SEIAA 20 IND 2014 dated 01.09.2015

50
Status as on 31-01-2024
YELAHANKA COMBINED CYCLE PP (YCCPP), Unit# 1 (1x370 MW) / KPCL (STATE SECTOR)
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL) STATUS OF MAIN PLANT PACKAGE (BTG) : (BHEL-BTG VENDOR)
UNIT-01 UNIT-01
(GT+ST) Sl. Packages AREA (GT+ST)
Sl. MILESTONE % Completion
Anticipated / Actual Date of
Original Date of Completion
Completion
CIVIL 100%
1 BOILER STRUCTURE 99%
1 COMPLETION OF BOILER FOUNDATION 30.06.2016 14.11.2016 PRESSURE PARTS 99%
2 START OF BOILER ERECTION 01.07.2016 09.11.2016 CIVIL 100%
2 Gas T/ TG STRUCTURE 99%
3 BOILER DRUM LIFTING (if sub-critical unit) 10.03.2017 07.04.2017
TG ERECTION 99%
BOILER CEILING GIRDER LIFTING 3 ESP Not Applicable Not Applicable
4 30.11.2016 21.12.2016
COMPLETION
CIVIL WORK
MATERIAL SUPPLY
5 CONDENSER ERECTION START 14.08.2017 Nov-17 4 FGD Not Applicable
ERECTION WORK
6 TG ERECTION START - -
STATUS OF BOPs
Packages/ Scheduled Anticipated/A
UNIT-01
Vendor/Contracting Agency Date of
7 HP PIPING ERECTION START - Sep-17 Sl. Linked Project Award
Date of ctual Date of %
(EPC- BHEL) Completion Completion
Milestones Completion

M/s BHEL (Mech.) Nov, 2015 14.10.2017 06.04.2017 100%


1 Chimney
BOILER HYDRO TEST (DRAINABLE) M/s BJCL (Civil) 18.08.2016 - 10.11.2016 100%
8 30.06.2017 27.11.2017
COMPLETION

2 Coal Handling Plant NA NA NA NA NA


BOILER HYDRO TEST (NON-DRAINABLE)
9 30.06.2017 27.11.2017
COMPLETION
3 Ash Handling Plant NA NA NA NA NA

ST 30.09.2017 Feb, 2021 4 Fuel Oil System NA NA NA NA NA


10 TG BOX UP
GT 30.09.2017 Sept, 2021
M/s BHEL/ Paharpur (Mech.) 09.11.2015 09.02.2018 31.12.2021 100%
5 Cooling Towers
M/s BHEL/ BJCL (Civil) 05.01.2017 - 31.03.2021 100%
11 HP PIPING ERECTION COMPLETION - Nov-21
M/s BHEL (Mech.) 09.11.2015 09.05.2018 11.07.2020 100%
6 CW Pump house
START OF ST 30.09.2017 Dec, 2020 M/s BHEL/BJCL (Civil) 02.11.2016 - 30.11.2020 100%
12 OILFLUSHIN
G GT 09.10.2017 29.08.2018 7 WPT Plant NA NA NA NA NA

M/s BHEL/GE (Mech.) 09.11.2015 09.05.2018 06.02.2021 100%


13 BOILER LIGHT UP NA NA 8 DM Plant
M/s BHEL/BJCL (Civil) 06.02.2017 - 31.03.2017 100%

M/s BHEL/ELGI (Mech.) Nov,2015 17.08.2017 16.05.2019 100%


14 CHEMICAL CLEANING COMPLETION 02.11.2017 Mar-24 9 Compressed Air System
M/s BHEL/BJCL (Civil) 10.03.2018 - 31.10.2019 100%

M/s BHEL (Mech.) 09.11.2015 09.05.2018 15.07.2021 100%


15 STEAM BLOWING START 01.12.2017 Apr-24 10 Fire Protection System
M/s BHEL/BJCL (Civil) 20.11.2020 - 30.04.2021 100%

M/s BHEL-TBG (Elect.) 03.01.2015 04.04.2018 19.01.2019 100%


16 STEAM BLOWING COMPLETION 15.12.2017 May-24 11 Switch Yard
M/s BHEL (TBG) (Civil) 17.04.2017 - 05.11.2018 100%

12 Station Transformers M/s BHEL/BJCL (Civil) 10.04.2017 - 31.03.2020 100%


17 ROLLING & SYNC. 16.12.2017 Jun-24
21.01.19-GT
13 Generator Transformers M/s BHEL PSSR 03.11.2015 04.04.2018 100%
23.12.19-ST
18 FULL LOAD 17.12.2017 Jun-24
M/s BHEL PSSR (Elect.) 03.01.2015 04.04.2018 21.01.2019- ST
14 Unit Transformers 100%
M/s BHEL/BJCL (Civil) 10.04.2017 - 31.03.2020
19 TRIAL RUN 07.02.2018 Jun-24
15 Railway Siding NA NA NA NA NA

20 COD 01.03.2018 JuN-24 16 Power Evacuation Lines KPTCL 21.12.2017 System ready 28.12.2018 95%

CRITICAL ISSUES
Project is ready. Commissioning is pending due to non-availability of Gas from M/s GAIL.

REASONS OF DELAY
Non-mobilization of required man power & prioritization of works by M/s BHEL (EPC contractor).

51
(The project is on hold since March 2021 due to NGT order) Status as on 31-01-2024
UPPUR STPP, Unit# 1 & 2 (2x800 MW) / TANGEDCO (STATE SECTOR )
Uppur STPP, Ramnad District - 623503, Tamil Nadu
E-Gen Portal Registration No. (U#1 - NA; U#2 - NA)
Project Developer / Implementing Agency - TANGEDCO Main Plant Vendor - M/S BHEL
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#1 On Hold
Feb-2016
Unit#2 On Hold
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal, Indigenous & Imported (MMTC) ORIGINAL ESTIMATED COST
12778.00
COAL COMBUSTION OF THE PROJECT
Supercritical
TECHNOLOGY Not
LATEST ESTIMATED COST
BGT-SE/E/T & H(P)/OT No. 01/ 2015-16. BOP- Applicable
APPROVAL DATE / NTP SE/E/T&H(P)/[Link].1/2020-21. SWIOP-SE/C/TP/[Link].2/2016- DATE OF FINANCIAL Financial tie up with
17. CLOSURE M/s. PFC

EPC/BTG/BoP Contractor
Order placed on M/s. BHEL on 27/02/2016. YEAR WISE EXPENDITURE
Details (Package Wise)

PPA NOT APPLICABLE. State sector project. 2016-17 16.74

Allocated Mine - SCCL (A.P.) to provide coal 3.942 MTPA; Distance 2017-18 226.62
from mine - 700 km (non pithead);
COAL LINKAGE/FSA
Also, MoU entered with M/s. MMTC for supply of imported coal of 2018-19 1594.15
5.02 MTPA on dated 25-05-2015.
2019-20 924.32
START UP POWER
230KV/11 Karaigudi Feeder
AGREEMENT 2020-21 366.61
Tx Line Developer TANTransco
2021-22
Tx Line Name
POWER EVACUATION 2022-23
Tx Voltage Level Uppur SCTPP – Virudhunagar, 765 KV,
SYSTEM
D/C line
EXPENDITURE OF JAN’2024 503.12
TOTAL EXPENDITURE (upto
3282.12
Configuration of Tx Line 31.01.2024)
(S/C or D/C)
Land required for the project is under TANGEDCO Possession. EPC
Contracts awarded to M/s. BHEL & M/S L&T has been suspended as
LAND POSSESSION per the NGT(SZ), Chennai Judgment dated 17.03.2021, delivered on
Appeal No. 144 of 2016(SZ) filed in the designated court for a period
of six months or until further orders.

Tamil Nadu Maritime Board has issued NOC for construction of Jetty
WATER ALLOCATION
for drawal and discharge of cooling water, vide 27.4.2015.

Ministry of Environment and Forest has accorded clearance for the


MOEF CLEARANCE
above Project on 18.05.2016.
CIVIL AVIATION Clearance expired on 21.11.2019. Clearance further extended upto
CLEARANCE 21.11.2024.
CPCB CLEARANCE NOT APPLICABLE. State sector project.
CRZ committee of MOEF recommended the Project on 28.1.16 and
SPCB CLEARANCE
MOM published in web site on 8.2.16.
FOREST CLEARANCE NOT APPLICABLE
* NOTE : The EPC contracts awarded to M/s. BHEL & M/S L&T have been suspended as per the NGT(SZ), Chennai Judgment dated 17.03.2021, deliveredon Appeal No. 144
of 2016 (SZ) filed in the designated court for a period of six months or until further orders. Considering the issues like NGT order, land litigation, local fishermen litigation and
BOP package retendering works, TANGEDCO Board vide on 29.04.2021 has accorded approval to shift the existing2x800 MW Uppur STPP to Udangudi site as 2x800MW
Udangudi Stage-III and consider Uppur as a fresh project once all the legal issues in NGT and other places are settled and to approach GOTN for administrative approval.
Energy Secretary/GoTN has been addressed vide Letter dtd 10.05.2021 for approval of the above. Further, as informed by TANGEDCO, CMD has accorded approval on
27.08.2021 to form a high committee comprising of three directors and four Chief Engineers to re-study the shifting of UPPUR Project. High Level Committee have furnished
report on 22.10.2021 and recommended that the 2X800 MW Uppur Project shall be executed at Uppur itself. TANGEDCO Board in its 102nd meeting held on 29.10.2021 has
directed to obtain opinion from the Consultant M/s. Ernst & Young regarding the viability and feasibility of this project and the same is in progress. 52
UPPUR STPP, Unit# 1 & 2 (2x800 MW) / TANGEDCO (STATE SECTOR)
UNIT WISE MILESTONES ( ANTICIPATED / ACTUAL) STATUS OF MAIN PLANT PACKAGE (BTG)
UNIT-01 UNIT-02 UNIT-01 UNIT-02
Sl. Packages AREA
Actual / Actual /
% Completion % Completion
Sl. MILESTONE
Original Date Anticipated Original Date Anticipated CIVIL 23% 30%
Date Date
1 BOILER STRUCTURE 55% 31%
COMPLETION OF BOILER PRESSURE PARTS 1% 0%
1
FOUNDATION CIVIL
2 START OF BOILER ERECTION 03.06.18 03.06.18 2 TG STRUCTURE Works yet to commence
BOILER DRUM LIFTING (if sub-critical TG ERECTION
3 NA NA
unit) 3 ESP UNDER PROGRESS 14% 6%
BOILER CEILING GIRDER LIFTING CIVIL WORK
4
COMPLETION MATERIAL SUPPLY
4 FGD Contract is yet to be awarded
5 CONDENSER ERECTION START 23.01.20 23.01.20
ERECTION WORK
6 TG ERECTION START 19.03.20 19.03.20

7 HP PIPING ERECTION START 19.12.19 19.12.19 STATUS OF BOPs


BOILER HYDRO TEST (DRAINABLE) Packages/ Anticipated UNIT-01 UNIT-02
8 22.07.19 22.07.19 Scheduled
COMPLETION Vendor/Contracting Date of /Actual
Sl. Linked Project Award
Date of
Date of % %
Agency Completion
BOILER HYDRO TEST (NON-
Milestones Completion Completion Completion
9 20.01.20 Project is on 20.01.20 .
DRAINABLE) COMPLETION hold. Project is on 1 Chimney
hold.
10 TG BOX UP 13.02.20 13.02.20

11 HP PIPING ERECTION COMPLETION 19.12.19 19.12.19 2 Coal Handling Plant

12 START OF OILFLUSHING 19.03.20 19.03.20

13 BOILER LIGHT UP 12.02.20 12.02.20 3 Ash Handling Plant

14 CHEMICAL CLEANING COMPLETION 19.03.20 19.03.20 4 Fuel Oil System

15 STEAM BLOWING START 16.04.20 16.04.20 5 Cooling Towers


The contract The contract
6 CW Pump house was short was short
16 STEAM BLOWING COMPLETION 16.04.20 16.04.20 The contract was short closed due closed due to closed due to
7 WPT Plant to huge price escalation sought by huge price huge price
M/s RIL. escalation escalation
8 DM Plant sought by M/s sought by M/s
17 ROLLING & SYNC. 06.05.20 06.05.20 RIL. RIL.
9 Compressed Air System

10 Fire Protection System


18 FULL LOAD 03.06.20 03.06.20
11 Switch Yard

12 Station Transformers
19 TRIAL RUN Nov-20 Nov-20
13 Unit Transformers

14 Railway Siding
20 COD 01.02.21 01.02.21
15 Power Evacuation Lines

CRITICAL ISSUES
The EPC contracts awarded to M/s. BHEL & M/S L&T have been suspended as per the NGT(SZ), Chennai Judgment dated 17.03.2021, delivered on Appeal No. 144 of 2016(SZ) filed in the designated
court for a period of six months or until further orders. Considering the issues like NGT order, land litigation, local fishermen litigation and BOP package retendering works, TANGEDCO Board on
29.04.2021 has accorded approval to shift the existing 2x800 MW Uppur STPP to Udangudi site as 2x800MW Udangudi Stage-III and consider Uppur as a fresh project once all the legal issues in NGT and
other places are settled and to approach GOTN for administrative approval. Energy Secretary/GoTN has been addressed vide Letter dtd 10.05.2021 for approval of the above.
Against NGT order, SLP was filed by TANGEDCO in Supreme court on 16.04.2021. Honourable Supreme court of India granted stay on the impugned judgment passed by NGT on 01.07.2021. In the
review meeting of energy department chaired by Hon'ble Chief Minister on 22.07.2021, it was requested to restudy the shifting of Uppur project considering the energy demand. CMD has accorded approval
on 27.08.2021 to form a high level committee comprising of three Directors and four Chief Engineers to restudy the shifthing of Uppur Project. TANGEDCO Board in its 102nd meeting held on 29.10.2021
has directed to obtain opinion from the Consultant M/s Ernst & Young regarding the viability and feasibility of this project and the same is in prgress. Consultant has furnished the report on 07.01.22 and
recommended "To develop the Project at Uppur site itself" and the same was placed before the TANGEDCO Board in its 105th meeting held on 19.01.2022. The Board Directed to place the subject in the
next Board meeting for deliberations. In the next Board meeting held on 19.3.2022, the Board directed to restudy the viability & feasibility of consultant’s report submitted.

Strategic Consultant M/s.E&Y report and recommendations were placed before the TANGEDCO The Board after deliberations directed that the subject shall be referred to the Aravind Subramanian
Committee(EAC to Hon’ble CM of TN) seeking their expert views. As instructed by Board, all the relevant data’s are furnished to the committee. Committee report is awaited.

REASONS OF DELAY
NGT Ordered to stop the work.

53
Status as on 31-01-2024
ENNORE EXPANSION TPP, Unit# 1 (1x660 MW) / TANGEDCO (STATE SECTOR )
Ernavur Village, Tiruvottiyur Taluk, Thiruvallur District, Tamil Nadu
E-Gen Portal Registration No. (U#1 - 1200003521)
Project Developer / Implementing Agency - TANGEDCO Main Plant Vendor - M/s BGRESL (EPC)
Unit No. LOA Original Trial Run Date Anticipated / Actual Trial Run Date
Unit#1 14.07.2014
CLEARANCES AND STATIC DATA FINANCIAL DATA (Fig. in Rs. Crore)
FUEL TYPE Coal, Indigenous & Imported ORIGINAL ESTIMATED COST
4956
COAL COMBUSTION OF THE PROJECT
Super Critical
TECHNOLOGY 7093
LATEST ESTIMATED COST
APPROVAL DATE / NTP 14.07.2014 DATE OF FINANCIAL
CLOSURE
EPC/BTG/BoP Contractor
M/s BGRESL (EPC) wef June-2022 ( earlier this project was awarded YEAR WISE EXPENDITURE
Details (Package Wise) to M/s Lanco Infra)

PPA Entire power is to be utilized by TANGEDCO 2014-15 239.70

2015-16 288.91
Long term coal linkage submitted to Ministry of coal on 08.11.2006
COAL LINKAGE/FSA and pending with Ministry of coal. MoU with MMTC on 23.07.2012
for supplying of 2.00 MTPA Imported coal. 2016-17

2017-18
START UP POWER
AGREEMENT 2018-19
Tx Line Developer TANTRANSCO
2019-20

POWER EVACUATION 2020-21


SYSTEM Tx Line Name
Tx Voltage Level EXPENDITURE OF DEC’2023
TOTAL EXPENDITURE (upto
Configuration of Tx Line 31.12.2023)
(S/C or D/C)

Own land within the premises of existing ETPS


LAND POSSESSION

WATER ALLOCATION

MOEF CLEARANCE MoEF clearance Lr J-13011/62/[Link](T) dated 18.09.2014

CIVIL AVIATION Airport Authority’s Letter No AAI/20012/1468/2007-ARI(NOC),Dated


CLEARANCE 16th May 2008.
CPCB CLEARANCE

SPCB CLEARANCE Tamil Nadu Government GO (4D) No 01 Dated 15.11.2012.

FOREST CLEARANCE

54
ABBREVIATIONS

Abbreviation Description
AHP Ash Handling Plant NDCT Natural Draft Cooling Tower
ATT Air Tightness Test NLTH Non Linear Time History
BFP Boiler Feed Pump PAF Project Affected Families
BLU Boiler Light Up PA Fan Primary Air Fan
BOP Balance of Plant PPA Power Purchase Agreement
BTG Boiler Turbine Generator ROW Right Of Way
C&I Control & Instrumentation SBO Steam Blowing Operation
CHP Coal Handling Plant SCAPH Steam Coil Air Pre Heater
COD Commercial Operation Date SCR Selective Catalytic Reduction
CRH Cold Re Heat SG Steam Generator
CST Condensate Storage Tank ST Station Transformer
CW System Circulating Water System Synch. Synchronization
DM Water Plant De Mineralization Water Plant TDBFP Turbine Driven Boiler Feed Pump
EOT Electric Overhead Travelling TG Turbine Generator
EPC Erection Procurement & Commissioning WT Wagon Tippler
ESP Electro Static Precipitator UT Unit Transformer
FD Fan Forced Draft Fan GHP Gypsum Handling Plant
FGD Flue Gas Desulfurization LHP Limestone Handling Plant
FL Full Load ARV Air Release Valve
FO System Fuel Oil System WPT Water Pre Treatment
FSA Fuel Supply Agreement ETP Effluent Treatment Plant
GT Generator Transformer CPU/COLTCS Condensate Polishing Unit/Condenser On Load Tube
Cleaning System
HCSD High Concentrated Slurry Disposal
HPT High Pressure Turbine
HRH Hot Re Heat
HT Hydraulic Test
ICB Imported Coal Based
ID Fan Induced Draft Fan
IDCT Induced Draft Cooling Tower
LOA Letter of Award
MDBFP Motor Driven Boiler Feed Pump
MGR Merry Go Round
MOEF&CC Ministry of Environment, Forests & Climate
Change

55