121 Le Mariche Subd. E. Rodriguez Sr. Ave.
Quezon City- Main office (+63-397-4992)
# 18 M1 Central Bldg. Matimyas St. Cr. E. Rodriguez Sr. Avenue, Brgy. Don Manuel, Quezon City-Branch Office (+63-753-5379)
Project : Bataan Truck Stop Facilities
Location : Abucay Bataan
Owner :
Subject : BILL OF QUANTITIES
Date : August 15, 2022
ITEM NO. DESCRIPTION QTY UNIT MATERIAL COST LABOR COST/ equipment AMOUNT
A General Requirements
Mobization & Demobilization 1 lot 160,000.00 160,000.00 160,000.00
Temporary facilities ( baracks [Link] ) 1 lot 50,000.00 50,000.00 23,000.00 23,000.00 73,000.00
Site Supervision 1 lot 120,000.00 120,000.00 120,000.00
50,000.00 303,000.00 353,000.00
1.0 EARTH WORKS
Survey works 1 lot 120,000.00 120,000.00
Clearing and Grabbing 14,000.00 m2 - 75.00 1,050,000.00 1,050,000.00
Lot Grading 8,000.00 m2 - 35.00 280,000.00 280,000.00
Embankment from roadway excavation common 2,110.00 m3 - 90.00 189,900.00 189,900.00
Subgrade preparation common materials 2,110.00 m3 - 80.00 168,800.00 168,800.00
Sub total 1,808,700.00 1,808,700.00
Subbase & Base course
Aggregates Subbase course with spreading 1,340.00 m3 - 160.00 214,400.00 214,400.00
Sub total 214,400.00 214,400.00
Surface Course
Gravel Surface course w/ spreading & compaction 335.00 m3 1,200.00 402,000.00 360.00 120,600.00 522,600.00
Portland cement concrete pavement ( unreinforce )
1,680.50 m3 5,300.00 8,906,650.00 650.00 1,092,325.00 9,998,975.00
250mm thk @ 14 days
Side walk ( t 100mm ) 240.00 lm 690.00 165,600.00 180.00 43,200.00 208,800.00
Curve & Gutter 460.00 lm 780.00 358,800.00 180.00 82,800.00 441,600.00
Side Metal Forms 240.00 lm 580.00 139,200.00 250.00 60,000.00 199,200.00
Page 1 of 2
ITEM NO. DESCRIPTION QTY UNIT MATERIAL COST LABOR COST/ equipment AMOUNT
9,972,250.00 1,398,925.00 11,371,175.00
2.0 DRAINAGE WORKS - -
Pipe Culvert & Dainage Excavation 350.00 lm - 85.00 29,750.00 29,750.00
Pipe Culvert 610 mm dia. Class 11 RCPC depth 1.6 320.00 lm 1,800.00 576,000.00 600.00 192,000.00 768,000.00
Pipe Culvert 910 mm dia. Class 11 RCPC depth 1.6 120.00 lm 2,200.00 264,000.00 800.00 96,000.00 360,000.00
Curve Inlet manhole 610 dia. RCPC 12.00 pcs 3,500.00 42,000.00 1,600.00 19,200.00 61,200.00
Curve Inlet manhole 910 dia. RCPC 12.00 pcs 4,600.00 55,200.00 1,950.00 23,400.00 78,600.00
Structural Backfill RCPC lm - - -
Sub-total 937,200.00 360,350.00 1,297,550.00
3.0 SEWER WORKS
Excavation 100mm diameter pipe pvc 746 lm 180.00 134,280.00 134,280.00
Excavation 200mm diameter pvc 520 lm 180.00 93,600.00 93,600.00
Manhole for sewer line 6 pcs 15,000.00 90,000.00 1,250.00 7,500.00 97,500.00
Backfill & compaction 650 lm 240.00 156,000.00 156,000.00
Sub - total 90,000.00 163,500.00 481,380.00
4.0 WATER WORKS
Excavation 100mm pipe
Excavation 50mm pipe
Installation 100 mm pipe
Installation 50 mm pipe
Installation of house hold pipe
Installation of fire hydrant
Installation of gate valve
Sub total 120,000.00
TOTAL COST 15,646,205.00
PREPARED BY ;
AR. ROMANO A. REYES
OPERATIONS MANAGER
0917-6270731
Page 2 of 2