Quotation for Al Ain Spa Renovation

Silver Dates General Maintenance LLC submitted a quotation for civil works at Skin Glow Wellness & Spa in Al Ain, Abu Dhabi, totaling 185,000 AED after discounts. The scope includes demolition, block work, finishing, joinery, AC installation, electrical, and plumbing work, with a payment structure based on project milestones. The estimated completion time for the project is three weeks, with additional charges for any changes or extra work.

Uploaded by

khalilabdin5
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
68 views3 pages

Quotation for Al Ain Spa Renovation

Silver Dates General Maintenance LLC submitted a quotation for civil works at Skin Glow Wellness & Spa in Al Ain, Abu Dhabi, totaling 185,000 AED after discounts. The scope includes demolition, block work, finishing, joinery, AC installation, electrical, and plumbing work, with a payment structure based on project milestones. The estimated completion time for the project is three weeks, with additional charges for any changes or extra work.

Uploaded by

khalilabdin5
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

SILVER DATES GENERAL MAINTENANCE LLC

Quotation
To, Date:12/04/2024
The Manager
Project: SKIN GLOW WELLNESS & SPA
AL AIN - AL MUTARID ABUDHABI UAE

Submit quotation for civil works with materials

Dear Sir,
We pleased to submit our lowest quotation price for the
mentioned work including materials & working charges details as
follow.

Scope of works,
NO. Description QTY Rate Total
1 DEMOLISH WORKS

01 EXISTING WALLS DEMOLISHING 82.8 100 8,280

2 BLOCKS WORK

02 20 cm Hollow Blocks with 86.4 60 5,184


plaster
02 10 cm Hollow Blocks with 11.34 60 680
plaster
6 FINISHING WORK

06 INTERNAL FINISHING

06 FLOORING

06 Floor Finishing Type - 1 ceramic ( Rooms + Halls ) ( Brand 220 75 16,500


india size 60x60)
06 Floor Finishing Type - 2 ceramic ( Bath + Kitchen ) ( Brand 50 75 3,750
india size 60x60)
06 Floor Finishing Type - 3 ceramic ( Balcony ) ( Brand 60.71 75 4,553
india size 60x60)
06 SKIRTING

06 Skirting Finishing Type - 1( Rooms + Halls ) 190 40 7,600

06 WALLS

06 Wall Finishing Type - INTERNAL PAINT 782 20 15,640


06 Wall Finishing Type – CERAMIC ( Brand 180 75 13,500
india size 30x60)
06 CEILING

06 Ceiling Finishing Type - 1 ( Rooms + Halls ) gypsum ceiling with 250 75 18,750
covalight

06 Ceiling Finishing Type - 2 ( Bath + Kitchen ) gypsum 50 85 4,250


ceiling with covalight
06 Ceiling Finishing Type - 3 ( Balcony ) gypsum 60.71 85 5,160
ceiling with covalight
7 JOINERY & IRONMONGERY WORK

07 External duble glass Doors - 1 3,500 3,500


Type
07 Internal sold MDF Doors with 8 2,200 17,600
white polish - Type1
07 Toilet Doors sold MDF with 6 2,200 13,200
white polish - Type2
07 kitchen Doors – Type 1 2,200 2,200

8 A C WORK (SPLIT UNITS )

08 Split Unit supply and installations ( brand super gernal ac ) 12 2,000 24,000
08 Supply installation kitchen and bath exhausts fan 7 100 700

08 Warranties ( AC compressor 5 years warranties

9 ELECTRICAL WORK
09 Remove old wire and install new wire ground & first floor brand is al
sawed
09 Remove all sockets single and double and new install
09 Switch (one gang 2 gang 3 gang) after new install switch
09 Supply install new light
09 Remove all tv cable and install new
09 Remove old data cable inside and install new LS LS 28,000
09 Remove all breaker and install new breaker
10 PLUMBING WORK
010 Supply install for (4 WC)
010 Guess toilet and master bedroom ( J F)
010 Supply and install master bedroom with jacuzzi will be converted in 2 LS LS 15,000
011 Supply instal CCTV camera 4 LS 3,000
Total 210,967
amount
25,967
Discount
Total 185,000
amount
Payment terms
1: Advance 50% payment
2:50% work complete after 25% payment
3:90% work complete after 20% payment
4:All work completes after 5% payment

NOTE:
[Link] complete works time period for 3 weeks
[Link] any delay payment will not include for time period of 3 weeks.
[Link] scope of work if any changes and extra additional work after we have additional
charges

Thank you

SILVER DATES GENERAL MAINTENANCE LLC


Mobile:0553321539