REPORT DATE : 05.05.
2025
Name of Work: Construction of Super Speciality Hospital, Jagdalp
PROJECT
Employer: CPWD
Contractor: M/s. SBEC Projects Private Limited
Dur. in Days: Total
Sl. No. Activity Description
Main Building
1 Earthwork
2 Sand Filling
3 PCC(1:3:6)
4 Water Proofing work
a Horizontal Surface
b Vertical Surface
5 Reinforcement Work
6 Form work
7 M35 Grade(RMC)
8 M40 Grade(RMC)
9 M25 Grade Grade Slab
10 M25 Grade Lintel
11 M15 Grade Concrete
12 M20 Grade Concrete
13 230mm thick Brickwork
14 115mm thick Brickwork
15 Door Frames Fixing
16 Internal Plastering work
17 Solid Blocks
18 Gypsum Plastering
19 External Plasterings
20 Floorings and Claddings
a Granite Flooring
b Granite Cladding
c Vitrified Tiles Flooring
d Vitrified Tiles Cladding
e Ceramic Tiles - Cladding
f Kota Stone Flooring
g CC Flooring
h Chequred Tile Flooring
21 Single Coat Putty over Gyp Plaster
22 Dolpur Stone Cladding
23 Brick Bat Coba Water Proofing
24 Flush Shutter Fixing
25 Window Sill and Jambs
26 Tile Grouting
27 Fixing of GRC Jali
28 Phonolic Sheet Fixing to Ceilings
29 for E&M Works
Service Building
1 Earthwork
2 Sand Filling
3 PCC(1:3:6)
4 Reinforcement Work
5 M35 Grade(RMC)
6 Shuttering Works all
7 M25 Grade
8 230mm thick Brickwork
9 Gypsum Wall Plastering
WORK PROGRESS
10 External Plasterings
11 Hardcrete Floorings
12 Single Coat Putty over Gyp Plaster
13 Brick Bat Coba Water Proofing
UG Sump
1 Earthwork
2 PCC(1:3:6)
WOR
3 M35 Grade(RMC)
4 Shuttering Works all
5 Reinforcement Work
6 230mm thick Brickwork
7 Internal Plastering work
8 External Plasterings
9 Brick Bat Coba Water Proofing
10 Water Proofing work - Kotastone
a Horizontal Surface
b Vertical Surface
c Tank top Screed
c Vitrified Tiles Flooring
d Vitrified Tiles Cladding
STP and ETP
1 Earthwork
2 PCC(1:3:6)
3 M25 Grade
4 Shuttering Works all
5 Reinforcement Work
6 230mm thick Brickwork
7 Water Proofing - Rough Kotastone
8 Brick Bat Coba Water Proofing
9 Internal Plastering work
Compound wall
1 Earthwork
2 PCC(1:3:6)
3 Reinforcement Work
4 M25 Grade
5 Shuttering Works all
6 230mm thick Brickwork
7 Internal Plastering work
8 MS Grill Fixing
Road work
1 Gravel Filling
2 GSB Laying
3 M30 Grade - Roads
4 Kerb Stone Fixing
5 Paver Block Fixing
Drains
1 Earthwork
2 PCC(1:3:6)
3 M25 Grade - Drains&Culverts
4 Shuttering Works all
5 Reinforcement Work
6 Cement Plaster - Drains
E&M Works
Sl. No. Name of the Contractor
Sukant Pradhan
1
CompanyNMT
2 Raj Kumar
3 Basudev Guman Singh
4 Solar/SLR/Aavya/UPS/DG/Chllers
5 Gasi Ram/Bablu/Deepak/inesh
6 Basudev Guman Singh
7 STP&ETP
8 Raish Khan
9 Sanjith/Sunil
Sanjith/Sunil
10 Bhimsaria
11 Limra Interior
12 Kohinoor/Others
Pandit Constructions
13
Man Power
Mirror Fix Agency
Sharma Conctructions
Mangaturam
14
Local Tiler
Sai vani
15
M Rambabu
16 Jagannadh Das
17 Ramesh Sharma
18 Jakir Hussain
19 Raheman
20 Nav Air/Sanjit Sharma
21 Bablu/Manoj/RBL/BMS
22 Vynil Flooring team
23 Alukraftz/Ramesh
Kanha Aluminium
24 Yaswanth
25 Vaibhav Laxmi Enterprises
26 KK Comfort
27 QSE Pvt/Pradeep Sharma/PP Entp
28 Deepak Kumar
29 Jhonson Lift
30 Wetech/others/Adharv/Seimens
Sl. No. Name of the Contractor
1
Machinary
Machinary
Sl. No. Description
1 Cement
2 Sand
3 12mm Metal
4 20mm Metal
5 40mm Metal
6 Fly Ash Bricks
7 Solid Blocks
8 Vitrified Tiles - 800x800
9 Vitrified Tiles - 600x600 - Double Charged
10 Vitrified Tiles - 600x600 - Mat Finish
11 Ceramic Tiles - 300x600 - Walls
12 Granite Floor/Dado
13 Kota stone - 40 mm Thick
14 Gypsum Elite 90
15 Kota Stone
16 Clay Bricks
17 Crusher Dust
18 Gravel
19 Door Frames
MATERIAL
20 Flush Shutter Fixing
21 Weberset Firm
22 Weberset Classic(Grey)
23 Weberset Nova
24 Wall Premium Plaster
25 Fiber Mesh
26 Gyproc Bond-II
27 RCC Hume Pipes(NP3) - 600
28 RCC Hume Pipes(NP3) - 300
29 RCC Hume Pipes(NP3) - 150
30 GSB
31 MS Foot rest
32 Epoxy Grout
33 Birla white(Putty)
34 External Primer
35 Chequered Tiles
36 Paver Block
37 Kerb Stone
Other Materials
Prepared by: Raju
SIGN
SBEC PROJECTS PRIVATE LIMITED
5.05.2025
uper Speciality Hospital, Jagdalpur under PMSSY (Phase-IV) on EPC basis.
s Private Limited
From:
Location Unit
Cum
Cum
Cum
Sqm
Sqm
MT
Sqm
Cum
Cum
Cum
Cum
Cum
Cum
Cum
Sqm
Each
Sqm
Cum
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm
Nos
Sqm
Sqm
Sqm
Sqm
Cum
Cum
Cum
MT
Cum
Cum
Cum
Cum
Sqm
Sqm
Sqm
Sqm
Sqm
Cum
Cum
Cum
Sqm
MT
Cum
Sqm
Sqm
Sqm
Sqm
Sqm
Cum
Sqm
Sqm
Cum
Cum
Cum
Sqm
MT
Cum
Sqm
Sqm
Sqm
Cum
Cum
MT
Cum
Sqm
Cum
Sqm
Rmt
Cum
Cum
Cum
Rmt
Sqm
Cum
Cum
Cum
Sqm
MT
Sqm
Type of the
Name of the work Unit
work
Misc Works NMR Nos
Misc Works NMR Nos
Masonry Works QTY Nos
Misc Works NMR Nos
Misc Works Qty Nos
Misc Works NMR Nos
Misc Works Qty Nos
STP&ETP Qty Nos
SS Railing Works QTY Nos
Shuttering /Rod Bending work Qty Nos
Misc Works NMR Nos
UPVC Door Fixing QTY Nos
Ceilings QTY Nos
Exp. Joint Works QTY Nos
Masonry Works NMR Nos
Misc Works Qty Nos
Granite Counters QTY Nos
Floor and Wall
QTY Nos
Finishes
Tile Fixing NMR Nos
Water Proofing Works QTY
Nos
Water Proofing Works Qty
Plumbing Works QTY Nos
Carpenter QTY Nos
Painting work QTY Nos
NMR Nos
Painting work
QTY Nos
Fire Doors/Duct Doors QTY Nos
Misc Works QTY Nos
Floorings QTY Nos
Alu Doors nad Windows QTY Nos
ACP,Glazing Works QTY Nos
MEP Works Qty Nos
Electrical works QTY Nos
HVAC QTY Nos
Fire Fighting QTY Nos
Fire Alarm Works QTY Nos
Lift work QTY Nos
BMS Works/CCTV QTY Nos
Working Diesel
Name of the Machine
From To Issue-ltr
Bar Bending
RECEIPTS
Unit
FOR DAY TILL DATE
MT 11050.35
Cum 21548.41
Cum 6797.15
Cum 11475.57
Cum 2402.74
No's 3247976.00
No's 22272.00
Sqm 6216.96
Sqm 5577.12
Sqm 1380.96
Sqm 5266.80
Sqm 23539.61
Sqm 1441.26
MT 1033.70
Sqm 849.44
No's 295280.00
Cum 74.43
Cum 6049.28
Nos 280.00
Nos 233.00
MT 75.98
MT 99.00
MT 53.00
MT 909.00
Sqm 7785.00
Kg 7480.00
No's 77.50
No's 170.00
No's 28.00
Cum 2392.14
Nos 180.00
KG 1115.00
MT 31.29
Ltrs 2820.00
Sqm 2444.76
Nos 32133.00
Nos 3035.00
Stores:Balram
CTS PRIVATE LIMITED
on EPC basis.
Project Start Date
Project Handover Date(Fin
Elapsed Balance
om: To: Site Conditions:
FOR THE DAY
TOTAL QTY. PL. NEXT DAY
PLANNED ACHIEVED
18937.00
663.00
474.00
1025.00
296.00
2077.00
67958.00
10602.59
3333.00
225.39
627.00
95.00
5.50
5342.30
10148.00
293.00
25250.00
25.00
66909.00
21262.00
11689.00
8669.00
6677.00
4923.00
4933.00
1197.00
1251.00
2178.10
30020.00
1717.00
3034.00
293.00
673.00
16533.00
1125.00
1925.00
1250.00
85.00
110.00
80.00
533.00
3057.00
197.00
199.20
2424.00
958.00
734.00
2424.00
839.00
2610.00
78.00
641.00
1763.00
54.00
48.00
1100.00
260.00
308.00
517.00
534.00
50.00
120.35
529.00
1688.00
35.00
416.00
1728.00
33.39
22.00
600.00
37.00
854.00
1747.00
98.43
29.74
376.00
3295.00
357.00
5600.00 10.68
1015.00
11363.00
1793.00
2751.00
1125.00
1855.00
926.00
142.00
574.00
3462.00
31.80
1453.00
Skilled M/C F/C Location of the work Description of the
1.0 9.0 Main Building Curing, House Keeping Wor
Stores Material Shifting
Helpers to Mason and Carpenters
1.0 DuCts Slab Centering/Packing Wo
1.0 1.0 Boundary Wall Plasterings
1.0 Ducts Centering for Cover Slab
1.0 Main Building CP Fitting Check
2.0 Main Building DB Works
1.0 3.0 Main Building Lifts Commissioning
Location of the work Description of the work
CONSUMED
ITEM Unit
FOR DAY TILL DATE FOR DAY
0.04 11035.48 STEEL
0.14 19035.03 8mm Dia MT
0.00 6256.03 10mm Dia MT
0.00 11065.43 12mm Dia MT
0.00 1859.60 16mm Dia MT
0.00 3184478.55 20mm Dia MT
21894.00 25mm Dia MT
32mm Dia MT
0.00 12933.88
MS Pipes(91.5 Rmt
0.00 5260.28 MS Pipes(60mm Rmt
0.00 23407.50 MS L-Angle(75 Rmt
0.00 1335.38 MS Plates(12mm Sqm
1024.20
849.44
0.00 279242.26
74.43
6049.28
280.00
223.00
75.98
99.00 RMC
53.00 M10 Cum
903.84 M15 Cum
7200.00 M25 Cum
7480.00 M35 Cum
77.50 M40 Cum
169.80 M30 Cum
28.00 M30 by Azax Cum
2392.14
180.00
1115.00
30.51
1900.00
2351.45
30045.00
2582.00
Project Manager
m
In-cha
Start Date 10.08.2018
Handover Date(Final) 19.01.2024
CUMM. TILL DATE % COMP
18936.00 100.0%
682.41 102.9%
484.69 102.3%
1025.00 100.0%
296.00 100.0%
2065.96 99.5%
67957.32 100.0%
10602.86 100.0%
3330.87 99.9%
244.10 108.3%
645.73 103.0%
91.13 95.9%
5.68 103.3%
5575.38 104.4%
8738.80 86.1%
277.00 94.5%
29260.07 115.9%
25.00 100.0%
58972.46 88.1%
9478.83 44.6%
12817.31 109.7%
9051.50 104.4%
6760.56 101.3%
5189.41 105.4%
4921.26 99.8%
1314.85 109.8%
1629.83 130.3%
2401.70 110.3%
39830.56 132.7%
1982.75 115.5%
3252.81 107.2%
223.00 76.1%
423.25 62.9%
9280.61 56.1%
881.73 78.4%
1300.56 67.6%
1247.70 99.8%
70.15 82.5%
117.52 106.8%
80.45 100.6%
571.98 107.3%
3056.52 100.0%
221.37 112.4%
229.63 115.3%
2273.64 93.8%
973.88 101.7%
639.61 87.1%
1032.36 42.6%
838.87 100.0%
2609.52 100.0%
78.89 101.1%
643.71 100.4%
1762.55 100.0%
53.93 99.9%
48.62 101.3%
1877.06 170.6%
259.84 99.9%
321.29 104.3%
516.75 100.0%
531.13 99.5%
2.05 4.1%
76.60 63.6%
611.29 115.6%
1527.20 90.5%
40.05 114.4%
422.46 101.6%
1727.97 100.0%
33.39 100.0%
16.83 76.5%
334.85 55.8%
36.50 98.6%
1064.55 124.7%
1388.28 79.5%
63.10 64.1%
17.16 57.7%
373.44 99.3%
1755.77 53.3%
430.13 120.5%
4674.26 83.5%
285.00 28.1%
5751.76 50.6%
1275.23 71.1%
3039.00 110.5%
806.00 71.6%
1198.05 64.6%
646.76 69.8%
201.28 141.7%
421.39 73.4%
2966.15 85.7%
25.24 79.4%
724.44 49.9%
Description of the work Qty
House Keeping Work
l Shifting
n and Carpenters
ntering/Packing Works
ngs Sqm 10.68
ng for Cover Slab
ng Check
ks
mmissioning
of the work Qty
RECEIPTS
FOR DAY TILL DATE
334.63
451.185
244.13
407.71
171.54
350.73
406.81
526.00
1153.00
118.00
23.90
55.70
128.45
1180.29
12348.00
3408.12
910.93
2118.96
In-charge:E.RAMBABU
Sl No Supplier Item
Unit Qty