Excavation Checklist

The document is an excavation checklist outlining essential activities and acceptance criteria for a construction project. It includes items such as ensuring approved shop drawings are used, obtaining excavation permits, and verifying compaction of dune sand. The checklist is designed for use by various parties involved in the project, including engineers and contractors.

Uploaded by

Madhavan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
51 views1 page

Excavation Checklist

The document is an excavation checklist outlining essential activities and acceptance criteria for a construction project. It includes items such as ensuring approved shop drawings are used, obtaining excavation permits, and verifying compaction of dune sand. The checklist is designed for use by various parties involved in the project, including engineers and contractors.

Uploaded by

Madhavan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

EXCAVATION CHECK LIST

Project Name:

Consultant

Client:

Main Contractor

Sub Contractor:
Location:
Inspection Party
Item
Main Activity Acceptance Criteria Remarks
No. FM/ PE QA/QC Jouzy Empower

1.0 Ensure Approved Shop drawing is used. Approved drawing

Is Method Statement / ITP / Risk


Approved Submittals
2.0 Assessment approved and being followed
Briefing Card
and briefed.

Ensure excavation permit is obtained if Approved Submittals


3.0
required. Briefing Card

The boundary of the area to be excavated


will be
4.0 Approved drawing
marked as per the construction drawing
.

Ensure the ground levels are as per


Approved drawing
5.0 Approved drawing
Survey Reports

Excavations conform to lines and


6.0 Approved drawing
elevations shown on Drawings.
Ensure Engineers Inspection completed
when the specified levels / limits
of excavation are reached. (Submit Survey Approved drawing
7.0
Inspection Survey Reports
Request to Consultant).
Ensure the bottom of excavation is properly
Approved drawing
8.0 compacted as required to allow for other
Survey Reports
construction work
Density test conducted on trench bottom
(Formation level)to verify satisfactory Conmpaction test
9.0
compaction before release for Dune Sand Results-95%
Laying

Approved Material
Verify Dune sand materials to be used are
10.0 Lab test Report
approved

Approved Material
Verify Dune sand Filled 150mm above the
11.0 Survey Report
Formation Level

Verify laid Dune sand is watered and


12.0 Survey Report
compacted

Overseas AST Engineer/Foreman Overseas AST QA/QC Engineer Jouzy|Axianta Empower

Name & Signature Name & Signature Name & Signature Name & Signature

MSP051-PRC-002-CKL-01 1st Issue Dated 16/05/2013