DESCRIPTION NO.
LENGTH(m) BREADTH(m)
earthwork in excavation
(a)long wall 2 7.1 0.7
(b)short wall 3 3.5 0.7
Lime concrete in foundtion
(a)long wall 2 7.1 0.7
(b)short wall 3 3.5 0.7
1st class brickwork in foundation & plinth
(a)long wall (I)1s footing 50 cm 2 6.9 0.5
(II)2nd footing 40 cm 2 6.8 0.4
(III)Plinth wall 30 cm 2 6.7 0.3
(b)short wall (I)1s footing 50 cm 3 3.7 0.5
(II)2nd footing 40 cm 3 3.8 0.4
(III)Plinth wall 30 cm 3 3.9 0.3
2.5cm thk DPC
(a)long wall 2 6.6 0.2
(b)short wall 3 4 0.2
(D)Deduction for Door Opening 2 1.2 0.2
1st class brickwork in cement mortar
(a)long wall 2 6.6 0.2
(b)short wall 3 4 0.2
(c)Deduction for window opening 2 1 0.2
(d)Deduction for Door Opening 2 1.2 0.2
(e)Deduction for part lintel
(I) window 2 1 0.2
(II)Door 2 1.2 0.2
HEIGHT(m) QUANTITY(cu.m) TOTAL EXPLANATION NOTE
0.9 8.946 6.6+2*0.5/2=7.1
0.9 6.615 15.561 4.0-2*0.5/2=3.5
0.2 1.988
0.2 1.47 3.458
0.2 1.38 6.6+2*0.3/2=6.9
0.2 1.088 6.6+2*0.2/2=6.8
0.5 2.01 6.6+2*0.1/2=6.7
0.2 1.11 4.0-(2*0.3/2)=3.7
0.2 0.912 4.0-(2*0.2/2)=3.8
0.5 1.755 8.255 4.0-(2*0.1/2)=3.9
2.64
2.4
0.2 0.48 4.56
3.125 8.25
3.125 7.5
1.2 0.48
2.1 1.008
0.15 0.06
0.15 0.072 14.13