1. What is WBS?
A Hierarchal decomposition of project work which gives deliverables at the end.
It define the scope.
Scope statement is output of WBS....
2. WBS DICTIONARY
More detailing attributes of activity in WBS is covered up in the WBS dictionary.
3. Why WBS?
All elements of the WBS can be communicated to the key players in the project.
Project progress can be monitored.
Accurate cost estimates can be developed.
Project activities can be scheduled with definite start and completion time.
4. Objective of WBS?
To easily plan, budget, schedule, monitor and control.
5. WBS Sequence
ProjectPhaseDeliverablesWork packageActivities/ task
6. What is Deliverables?
Any unique and verifiable result that must be produced to complete a project. Usually the
lowest level of the WBS.
7. Scheduled Activity/ task
A component of work performed to create a deliverable. It consume resource and time.
It has definite start time and end time.
8. Project Schedule or Scheduling
Scheduling is the process of determining the sequential order of activities, assigning planned
duration and determining the start and finish dates of each activity.
9. What is Planning
Planning is the process of identifying all activities necessary to complete the project.
10. Difference between planning and scheduling
Planning is the process of identifying all activities necessary to complete the project. While
scheduling is the process of determining the sequential order of activities, assigning planned
duration and determining the start and finish dates of each activity. Planning is a prerequisite to
scheduling.
11. What is Duration?
Total number of work periods required to complete a scheduled activity.
12. What is Milestone?
A significant event shows the completion of a major deliverable.
A “measuring point”.
Milestones have “0” (zero) duration and no resource assignments.
13. Task interdependency
Mandatory” or “Hard Logic”----- this are necessary to fallow and link internally in Network. This
cannot be change.
Discretionary” or “Soft Logic”------this can be change by project team
External Event---it id depend on outer events.
14. Difference between Event and task/Activity?
Event represent the movement at which the task started and finish.
Event is start or finish of more than one activity.
Taskrepresent time to do the task.Can be real or not real (Dummy) in AOA
15. Type of task relationship
Finish to start
Start to finish
Finish to finish
Start to start
16. Lead and lag (According to Finish to start).
Lead---starting the Successor activity before finishing the Predecessor activity (-ve).
Lag----- Starting the Successor Activity by adding a delay after completing Predecessor activity
(+ve).
The above two points are related to finish to start relationship, but Lag and lead will change
according to other three relationships.
17. Adjusting lead and lag.
Aligning the activity which is behind the schedule with plan.
18. Applying Lead and Lag
Adjusting amount of time between Predecessor and Successor.
19. Activity on Arrow (AOA)
Tasks represented by arrows (length not related to duration)
Dependency shown as node
Only F-S relationship used
Activity (arrow)
Work element or task
Can be real or not real (Dummy)
Name or identification of the tasks (label) must be added
Event (node)
The start and/or finish of one or more activities
Tail (preceding) and head (succeeding) no
TASK
EVENT
20. Precedence Diagram Method (PDM) or AON
Tasks represented by nodes
Dependency shown as arrows or links between nodes
All task relationships can be used (FS, FF, SS, SF)
Activity (Node)
Work element or task
Name or identification of the tasks must be added
No need for dummy (unreal) activities
Dependency or sequence arrow
Shows the interrelationship between activities
TASK A TASK B
Arrow show interdependency
21. Critical Path Method (CPM)
Deterministic with only one estimation
The purpose of Critical Path Method is to finish a project in the shortest amount of time.
It has longest path and shortest duration.
22. Critical Activity
The activity on critical path
It has zero float or slack.
23.
Dummy Activity
A Dummy activity is an imaginary activity/simulated activity.
It does not exist in the Project activities.
Activities that do not require resources and duration.
It is used in the network diagram to show dependency relationship between two or more
activities.
Add minimum no of dummy in the network diagram.
24. When dummy activity is needed?
When the project contains groups of two or more jobs which have common predecessor.
It is represented by a dotted line.
25. Program Evaluation and Review Technique (PERT)
PERT is an extension of CPM.
Uses probabilistic time estimates.
Three time estimates for each activity (to, tm and tp)
26. When to use PERT
Used for non-repetitive jobs (research and development work)
Where the time and cost estimates tend to be quite uncertain.
27. What does actually the PERT calculate
Calculate the expected time for each activity (te)
Calculate the variance of the duration of each activity
Calculate the variance of the project duration by summing up the variances of the activities on
the critical path
Triple point estimate (te)
Te = to+4tm+tp
6
(Variance of the duration of the activity) S² = (Tp – To) ²
36
28. Calculating Forward Pass
Calculate Early Start & Early Finish dates.it work from project start date.
29. BACKWARD PASS
Calculate Late Start & Late Finish dates.it work from project end date.
30. Total float
The total amount of time that a scheduled activity can be delayed or extended without delaying
the project end date or violating a schedule constraint.
31. Free Float
The amount of time that a scheduled activity can be delayed without delaying the start of the
next activity in the network.
32. Negative Float
The amount of time that by which a critical activity misses a required date.
33. Significance of Gantt chart.
The main purpose of a Gantt chart is to display the schedule of activities.
34. Triple constraints of a project
Time, scope and cost (TCS)
Time
Cost Scope
35. Critical Path vs Critical Chain
CP is the series of activities that determines the duration of the project as per precedence logic
o Activity durations are fixed
o Resources are unlimited
CC is a critical sequence – longest chain of tasks considering both, task dependencies and
resource dependencies
o Realistic project duration
o Leveled resources
36. Whatisleveling?
Distributing resources equitably across the project
37. Whylevel?
Eliminateextraordinarydemandforresources
ImproveResourceProductivityandEfficiency
Predict material and equipment requirements better
Reduce cash shortages
38. Resources identification
Set of resources required
39. Resources allocation
Assigning the resources for each activity
40. Resources aggregation
Daily resource requirement.
41. Resources smoothing
Time constrained scheduling. In this resource can be increases.
Shifting/ stretching/ splitting activities
o Within available floats
42. Resources leveling
Resource constrained scheduling.In this Duration of project may be increases...
Shifting/ stretching/ splitting activities/crashing
o Firstly, within available floats
o If required, beyond float.
43. Workload
Theamountofworkimposedonaresource
44. Resource loading
Theamountofparticularresourceneededtoconductalltheactivities.
45. How Resources leveling is done?or types of resource leveling?
Shifting the start times of activities
Stretching activities
Splitting activities
Crashing
46. Purposes of Resources Scheduling
To minimize idle time (and cost) of resources
To decide the optimal size of resources to be procured
To avoid over-allocations for resources
47. What is Time- cost trade-off?
Determining the minimum total cost for a possible project duration
48. Fast tracking
Overlapping the critical activities
No change in direct cost
Resource & space conflict
Increase risk
49. Re-allocation of resources
Withdrawing resources from non-critical activities & allocating to critical activities
No change in direct cost
Reduces floats
50. Compression/ Crashing
Reducing duration(s) of critical activity (activities)
Increasing the resources for critical activities
Additional resources at premium cost
Increase direct cost
Decrease in indirect cost up to certain time period.
51. Why Monitoring and Control?
Goal is to detect and correct deviation from desired
o Budget
o Schedule
o Quality
52. What is Earn Value Management (EVM)?
Earn Value Management (EVM) technique used to track the Progress and Status of a Project
&Forecast the likely future performance of the Project.
53. Earn Value (EV) OR BCWP
How much the project have earn against the Plan Value (PV) or BCWS as of reporting date.
EV = % complete x budget at completion.
54. Plan Value (PV) OR BCWS
The total cost of the work scheduled/planned as of a reporting date.
PV or BCWS = Hr. Rate x Total hour of work schedule/planned
55. Actual Cost (AC) OR ACWP
It shows how much actual cost has incurred to complete the activity as of reporting date.
AC or ACWP = Hr. Rate x total hour spent
56. Budget At Completion (BAC)
It is the total budget allocated to the project.
57. Estimate At completion (EAC)
It is the estimated cost of the project at the end of the project.
EAC = AC + ETC (Estimate to complete)
58. % complete planned
The percentage of work which was planned to be completed by the Reporting Date.
% complete = PV/ Budget at completion (BAC)
59. % Completed Actual
The percentage of work which was actually completed by the Reporting Date.
% complete = AC/ Budget at completion
60. Variance At Completion (VAC)
It is difference between the budget cost (BAC) it is supposed to complete Vs now at what cost it
is expected to complete (EAC)
VAC = BAC – EAC
VAC = + ve --- under budget.
VAC = - ve---- Over Budget
61. SCHEDULE VARIANCE
Schedule Variance indicates how much ahead or behind schedule the project is.
Schedule variance---
SV= 0 ----- on schedule
SV= -ve--- behind schedule
SV= +ve--- Ahead schedule
SV = EV – PV
62. Cost variance
Cost Variance (CV) indicates how much over or under budget the project is.
CV= 0 ----- on cost
CV= -ve--- over budget
CV= +ve--- under budget
CV = EV - AC
63. To Complete Schedule Performance Indicator (TSPI).
Whatever the SPI is now, from onwards if we have to complete the project on time, at
what rate/efficiency remaining time on the project should be utilized.( it is like Cricket
Run rate)
TSPI-----Less than 1--- good resource utilization
TSPI-----More than 1--- poor resource utilization
64. Schedule Performance Index (SPI)
It gives the rate at which the work is completing.-----it should be equal to 1.
Less than 1----Behind the schedule
More than 1--- Ahead of schedule
SPI = EV/PV
65. Cost performance index (CPI)
It gives the rate at which we are gating return on our investment------ it should be equal
to 1.
Less than 1--- over budget
More than 1--- under budget
CPI = EV/AC
BAC
66. To Complete Cost Performance Indicator (TCPI)
At what rate/ efficiency the resources on the project should be utilized for remaining of the
project.
67. What is Scope?
The process of defining detail description of Product and services.
Define what is and what is not include in scope.
68. What is Scope Statement?
Define Deliverables and work required to create that deliverables.
Help in common understanding among stockholder.
Content of Project scope statement.
• Project Objective
• Product scope description
• Project scope requirement
• Project Boundaries
• Project deliverables
• Product acceptance criteria
• Project constraints
• Initial identified risk
• Schedule milestone
• Initial project organization
• Fund limitation
• Approved requirement
69. Product Scope and Project Scope.
Product Scope --- feature and function that characterized product.
Project Scope ---- The work that needed to accomplished to deliver the product.
DIFFERENCE BETWEEN PROJECT CHARTER AND PROJECT SCOPE STATEMENT
PROJECT CHARTER PROJECT SCOPE STATEMENT
• IT CONTAIN NAME AND AUTHORITY OF • IT DOSEN’T CONTAIN ANY NAME AND
SPONSER AUTHORITY OF SPONSER.
• WHO IS THE ASSIGN PROJECT MANAGER • IT IS PROGRESSIVELY ELEBORATIVE
• PROJECT APPROVAL REQUIREMENT DOCUMENT
• SUMMARY OF MILESTONE SCHEDULE • PROJECT DELEVERABLE
• SUMMERY OF BUDGET • ACCPTANCE CRITERIA
• PROJECT EXCLUSIONS
• HIGH LEVEL REQUIRMRNT • PROJECT CONSTRAINTS
• HIGH LEVEL RISK • PROJECT ASSUMPTION
• HIGH LEVEL PROJECT DISCRIPTION • PROJECT BOUNDRIES
• PURPOSE OF EXECUTING THE PROJECT.
70. Scope base line must have the following Documents :- ( IMP)
Project scope statement
WBS
WBS dictionary.
71. Analogous estimate
It is technique for estimating the duration and cost of an activity or project from historical data
from similar data or project.
72. Bottom- up estimate
It is techniquefor estimating the project duration or cost by aggregating the estimate of the
lower level of components of work breakdown structure.
73. What are the technique to find out cost estimate and time estimate?
Analogous estimate
Bottom- up estimate
Parametric estimate
74. Three point estimate
It is technique for estimating the project duration or cost by applying an average of Optimistic,
Pessimistic and most likely estimate when there is uncertainty with individual activity estimate.
o Triangular distribution. TE= to+tm+tp/3
o Beta distribution. TE= to+4tm+tp/6