SAMPUL

The document outlines the budget plan for the fire fighting installation project at the Institute of Technology Habibie (ITH) campus in Pare Pare, totaling approximately 1.117 billion IDR. It details costs associated with various floors of the building, including materials and labor for plumbing work related to fire safety. The budget is rounded to 1,117,705,000 IDR and is presented in a structured format for clarity.

Uploaded by

kampretoo99
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
12 views5 pages

SAMPUL

The document outlines the budget plan for the fire fighting installation project at the Institute of Technology Habibie (ITH) campus in Pare Pare, totaling approximately 1.117 billion IDR. It details costs associated with various floors of the building, including materials and labor for plumbing work related to fire safety. The budget is rounded to 1,117,705,000 IDR and is presented in a structured format for clarity.

Uploaded by

kampretoo99
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

RENCANA ANGGARAN BIAYA

PEKERJAAN INSTALASI FIRE FIGHTING KAMPUS


INSTITUTE TEKNOLOGI HABIBIE
( ITH ) PARE PARE

MAKASSAR
2024
PROYEK : PEMBANGUNAN KAMPUS INSTITUTE TEKNOLOGI HABIBIE (ITH) PARE PARE
PEKERJAAN : INTALASI FIRE FIGTING

NO REKAPITULASI JUMLAH HARGA

1 LANTAI SEMI BASEMENT


28,463,848.00
2 LANTAI BASEMENT
159,569,482.26
3 LANTAI SATU
178,281,038.00
4 LANTAI DUA
178,281,036.26
5 LANTAI TIGA
178,281,038.00
6 LANTAI EMPAT
178,281,038.00
7 LANTAI LIMA
178,281,038.00
8 LANTAI TOP
38,266,747.00
TOTAL 1,117,705,265.52
Pembulatan 1,117,705,000.00

Terbilang : Satu Milyar Seratus Tujuh Belas Juta Tujuh Ratus Lima Ribu Rupiah.
Proyek : Pembangunan Kampus Institute Tekhnologi Habibie ( ITH ) Pare - Pare

H. Satuan
No Uraian Pekerjaan Vol. Sat. Jml. Harga (Rp)
(Rp)

V PEKERJAAN PLUMBING
A. PEKERJAAN INSTALASI FIRE FIGHTING
1. LANTAI SEMI BASEMENT
- Pek. Pas. Pipa BSP SCH 40 Dia. 3" = 80 mm 17.00 M 350,378.00 5,956,426.00
- Pek. Pas. Pipa BSP SCH 40 Dia. 1.1/4" = 32 mm 42.00 M 203,696.00 8,555,232.00
- Pek. Pas. Pipa BSP SCH 50 Dia. 2" = 50 mm 5.00 M 266,800.00 1,334,000.00
- Pek. Pas. Pipa BSP SCH 50 Dia. 2 1/2" = 65 mm 10.00 M 340,141.00 3,401,410.00
- Pek. Pas. Pipa BSP SCH 40 Dia. 1" = 25 mm 20.00 M 133,139.00 2,662,780.00
- Pek. [Link] Valve 1.1/4" 2.00 Bh - -
- Pek. [Link] Valve 2" 2.00 Bh - -
- Pek. [Link] Valve 3" (hydrant) 1.00 Bh 6,554,000.00 6,554,000.00

Jumlah LT. Semi basement 28,463,848.00


-
2. LANTAI BASEMENT -
-
- Pek. Pas. Pipa BSP SCH 40 Dia. 3" = 80 mm 113.00 M 350,378.00 39,592,714.00
- Pek. Pas. Pipa BSP SCH 50 Dia. 2 1/2" = 65 mm 84.00 M 340,141.00 28,571,844.00
- Pek. Pas. Pipa BSP SCH 50 Dia. 2" = 50 mm 97.00 M 266,800.00 25,879,600.00
- Pek. Pas. Pipa BSP SCH 40 Dia. 1.1/4" = 32 mm 92.00 M 203,696.00 18,740,032.00
- Pek. Pas. Pipa BSP SCH 40 Dia. 1" = 25 mm 146.00 M 133,139.00 19,438,294.00
- Pek. Pas. Sprinkler 73.00 Bh - -
- Pek. [Link] Valve 2" 5.00 Bh - -
- Pek. Pas. Fire Extingusher (FE) 4.00 Bh 3,683,000.00 14,732,000.00
- Pek. Pemasangan Hydrant Box 3.00 Unit 4,204,999.42 12,614,998.26

Jumlah LT. Basement 159,569,482.26


-
3. LANTAI SATU -
-
- Pek. Pas. Pipa BSP SCH 40 Dia. 3" = 80 mm 125.00 M 350,378.00 43,797,250.00
- Pek. Pas. Pipa BSP SCH 50 Dia. 2 1/2" = 65 mm 83.00 M 340,141.00 28,231,703.00
- Pek. Pas. Pipa BSP SCH 50 Dia. 2" = 50 mm 97.00 M 266,800.00 25,879,600.00
- Pek. Pas. Pipa BSP SCH 40 Dia. 1.1/4" = 32 mm 92.00 M 203,696.00 18,740,032.00
- Pek. Pas. Pipa BSP SCH 40 Dia. 1" = 25 mm 147.00 M 133,139.00 19,571,433.00
- Pek. Pas. Sprinkler 77.00 Bh 143,260.00 11,031,020.00
- Pek. [Link] Valve 2" 5.00 Bh - -
- Pek. Pas. Fire Extingusher (FE) 5.00 Bh 3,683,000.00 18,415,000.00
- Pek. Pemasangan Hydrant Box 3.00 Unit 4,205,000.00 12,615,000.00
-
Jumlah LT. Satu - 178,281,038.00
H. Satuan
No Uraian Pekerjaan Vol. Sat. Jml. Harga (Rp)
(Rp)
- -
4. LANTAI DUA - -
- -
- Pek. Pas. Pipa BSP SCH 40 Dia. 3" = 80 mm 125.00 M 350,378.00 43,797,250.00
- Pek. Pas. Pipa BSP SCH 50 Dia. 2 1/2" = 65 mm 83.00 M 340,141.00 28,231,703.00
- Pek. Pas. Pipa BSP SCH 50 Dia. 2" = 50 mm 97.00 M 266,800.00 25,879,600.00
- Pek. Pas. Pipa BSP SCH 40 Dia. 1.1/4" = 32 mm 92.00 M 203,696.00 18,740,032.00
- Pek. Pas. Pipa BSP SCH 40 Dia. 1" = 25 mm 147.00 M 133,139.00 19,571,433.00
- Pek. Pas. Sprinkler 77.00 Bh 143,260.00 11,031,020.00
- Pek. [Link] Valve 2" 5.00 Bh - -
- Pek. Pas. Fire Extingusher (FE) 5.00 Bh 3,683,000.00 18,415,000.00
- Pek. Pemasangan Hydrant Box 3.00 Unit 4,204,999.42 12,614,998.26
-
Jumlah LT. Dua - 178,281,036.26
-
5. LANTAI TIGA - -
- -
- Pek. Pas. Pipa BSP SCH 40 Dia. 3" = 80 mm 125.00 M 350,378.00 43,797,250.00
- Pek. Pas. Pipa BSP SCH 50 Dia. 2 1/2" = 65 mm 83.00 M 340,141.00 28,231,703.00
- Pek. Pas. Pipa BSP SCH 50 Dia. 2" = 50 mm 97.00 M 266,800.00 25,879,600.00
- Pek. Pas. Pipa BSP SCH 40 Dia. 1.1/4" = 32 mm 92.00 M 203,696.00 18,740,032.00
- Pek. Pas. Pipa BSP SCH 40 Dia. 1" = 25 mm 147.00 M 133,139.00 19,571,433.00
- Pek. Pas. Sprinkler 77.00 Bh 143,260.00 11,031,020.00
- Pek. [Link] Valve 2" 5.00 Bh - -
- Pek. Pas. Fire Extingusher (FE) 5.00 Bh 3,683,000.00 18,415,000.00
- Pek. Pemasangan Hydrant Box 3.00 Unit 4,205,000.00 12,615,000.00
-
Jumlah LT. Tiga - 178,281,038.00
-
6. LANTAI EMPAT - -
- -
- Pek. Pas. Pipa BSP SCH 40 Dia. 3" = 80 mm 125.00 M 350,378.00 43,797,250.00
- Pek. Pas. Pipa BSP SCH 50 Dia. 2 1/2" = 65 mm 83.00 M 340,141.00 28,231,703.00
- Pek. Pas. Pipa BSP SCH 50 Dia. 2" = 50 mm 97.00 M 266,800.00 25,879,600.00
- Pek. Pas. Pipa BSP SCH 40 Dia. 1.1/4" = 32 mm 92.00 M 203,696.00 18,740,032.00
- Pek. Pas. Pipa BSP SCH 40 Dia. 1" = 25 mm 147.00 M 133,139.00 19,571,433.00
- Pek. Pas. Sprinkler 77.00 Bh 143,260.00 11,031,020.00
- Pek. [Link] Valve 2" 5.00 Bh - -
- Pek. Pas. Fire Extingusher (FE) 5.00 Bh 3,683,000.00 18,415,000.00
- Pek. Pemasangan Hydrant Box 3.00 Unit 4,205,000.00 12,615,000.00
-
Jumlah LT. Empat - 178,281,038.00
H. Satuan
No Uraian Pekerjaan Vol. Sat. Jml. Harga (Rp)
(Rp)
-
7. LANTAI LIMA - -
- -
- Pek. Pas. Pipa BSP SCH 40 Dia. 3" = 80 mm 125.00 M 350,378.00 43,797,250.00
- Pek. Pas. Pipa BSP SCH 50 Dia. 2 1/2" = 65 mm 83.00 M 340,141.00 28,231,703.00
- Pek. Pas. Pipa BSP SCH 50 Dia. 2" = 50 mm 97.00 M 266,800.00 25,879,600.00
- Pek. Pas. Pipa BSP SCH 40 Dia. 1.1/4" = 32 mm 92.00 M 203,696.00 18,740,032.00
- Pek. Pas. Pipa BSP SCH 40 Dia. 1" = 25 mm 147.00 M 133,139.00 19,571,433.00
- Pek. Pas. Sprinkler 77.00 Bh 143,260.00 11,031,020.00
- Pek. [Link] Valve 2" 5.00 Bh - -
- Pek. Pas. Fire Extingusher (FE) 5.00 Bh 3,683,000.00 18,415,000.00
- Pek. Pemasangan Hydrant Box 3.00 Unit 4,205,000.00 12,615,000.00
-
Jumlah LT. Lima - 178,281,038.00
-
8. LANTAI TOP - -
- -
- Pek. Pas. Pipa BSP SCH 40 Dia. 3" = 80 mm 17.00 M 350,378.00 5,956,426.00
- Pek. Pas. Pipa BSP SCH 50 Dia. 2 1/2" = 65 mm 42.00 M 340,141.00 14,285,922.00
- Pek. Pas. Pipa BSP SCH 50 Dia. 2" = 50 mm 5.00 M 266,800.00 1,334,000.00
- Pek. Pas. Pipa BSP SCH 40 Dia. 1.1/4" = 32 mm 10.00 M 203,696.00 2,036,960.00
- Pek. Pas. Pipa BSP SCH 40 Dia. 1" = 25 mm 21.00 M 133,139.00 2,795,919.00
- Pek. Pas. Sprinkler 2.00 Bh 143,260.00 286,520.00
- Pek. [Link] Valve 2" 11.00 Bh - -
- Pek. Pas. Fire Extingusher (FE) 2.00 Bh 3,683,000.00 7,366,000.00
- Pek. Pemasangan Hydrant Box 1.00 Unit 4,205,000.00 4,205,000.00

Jumlah LT. Top 38,266,747.00


TOTAL 1,117,705,265.52
Pembulatan 1,117,705,000.00
Terbilang : Satu Milyar Seratus Tujuh Belas Juta Tujuh Ratus Lima Ribu Rupiah.