CEBU INSTITUTE OF TECHNOLOGY-UNIVERSITY
DEPARTMENT OF ARCHITECTURE
THE COSTA MARE PROJECT
HANOI HUNG YEN, VIETNAM
COMMERCIAL AND TECHNICAL
PROPOSAL
BY:
CABURAL, VIÑE APRIL ROSE A.
CHIU, KHYLLE ANDRE A.
LACANO, JOHN REY L.
ARCH492-R4
MAY 2025
TABLE OF CONTENTS
1.0 INTRODUCTION
1.1 PROJECT OVERVIEW
1.2 PROJECT DETAILS
2.0 PROJECT UNDERSTANDING AND SCOPE
2.1 PROBLEM STATEMENT
2.2 SCOPE OF SERVICES
3.0 METHODOLOGY
3.1 DESIGN METHODOLOGY AND APPROACH
3.2 PROJECT PHASES AND KEY DELIVERABLES
4.0 TIMELINE AND PROCESS GUIDE
5.0 TERMS AND CONDITIONS
5.1 ASSUMPTIONS/TERMS OF AGREEMENT
5.2 COMPLETION
5.3 CONTRACT CANCELLATION
5.4 CONSULTANT’S LIABILITY
5.5 COPYRIGHT AND USE OF DOCUMENTS
5.6 CLIENT’S RESPONSIBILITIES
5.7 POST-CONTRACT – CONSTRUCTION STAGE SERVICES
6.0 QUOTE AND SIGN-OFF EXCLUSIONS
6.1 QUOTE AND SIGN-OFF
6.2 EXCLUSIONS
1.0 INTRODUCTION
1.1 PROJECT OVERVIEW
The Costa Mare Project is a proposed residential development located within
the growing urban corridor of Hanoi-Hung Yen, Vietnam. Commissioned by a private
developer as part of a larger master plan, the project involves the design and
construction of two residential plots, each comprising two high-rise towers (2B+G+31
floors) with shared basement levels. The development is envisioned to provide a
modern, high-density living environment, integrated with commercial and public
amenities.
1.2 PROJECT DETAILS
Project Location: Hanoi Hung Yen, Vietnam
The project comprises 2 (two) plots, comprising 2 (two) towers, one for each
plot, with a shared basement.
TOWER 1-2B+G+31
Site Area 11,582.0 sq.m.
Maximum Footprint Area 3,326.0 sq.m.
Total GFA 99,780.0 sq.m.
Commercial GFA 3,326.0 sq.m.
Residential GFA 96,454.0 sq.m.
Total Basement Area 23,134.0 sq.m.
Max. No. of Basements 2
Maximum Storey Height 31
TOWER 2-2B+G+31
Site Area 11,331.0 sq.m.
Maximum Footprint Area 3,326.0 sq.m.
Total GFA 99,780.0 sq.m.
Commercial GFA 3,326.0 sq.m.
Residential GFA 96,454.0 sq.m.
Total Basement Area 22,662.0 sq.m.
Max. No. of Basements 2
Maximum Storey Height 31
BASEMENT UNDER PARK
Total Basement Area 33,296.0 sq.m.
2.0 PROJECT UNDERSTANDING AND SCOPE
2.1 PROBLEM STATEMENT
The Hanoi Hung Yen region is undergoing rapid urbanization, escalating the
demand for high-quality, sustainable housing. Given this, there are key challenges the
Costa Mare Project seeks to address, which include the following:
Insufficient modern, high-end residential developments
The rapid growth of the urban population has not been met with a
proportional rise in contemporary, high-quality residential spaces. Existing
housing often lacks the amenities, sustainability measures, and design
standards expected by an evolving market demanding luxurious and
functional living.
Traffic congestion and a lack of efficient underground parking solutions
As urban density increases, road networks and surface parking lots are
under immense pressure. Without comprehensive underground parking and
traffic management systems, developments risk contributing to congestion,
inefficiency, and resident dissatisfaction. Costa Mare will integrate expensive,
shared basement parking to alleviate such stresses.
Demand for energy-efficient and sustainable residential environments
With rising awareness of climate change and the environmental
footprint of developments, there is a strong demand for homes that use
resources efficiently, minimize emissions, and contribute to broader
sustainability goals. Costa Mare aims to lead by integrating green building
strategies and energy-saving systems.
Need for high-rise community spaces that encourage social interaction
High-rise living often leads to social isolation if community spaces are
not thoughtfully designed. The project addresses this by providing extensive
shared amenities such as landscaped gardens, communal lounges, fitness
centers, and social hubs to foster a strong sense of belonging and neighborly
interaction.
The Costa Mare Project aims to meet these demands by delivering a
community-oriented, luxurious, sustainable, and resilient development that fosters
economic and social growth.
2.2 SCOPE OF SERVICES
Our comprehensive scope covers full architectural, engineering, and design
consultancy, ensuring seamless project delivery from concept to completion. The
specific services include the following:
1. Architectural Design.
The scope includes the design of residential towers, podiums, and integrated
commercial areas, with emphasis on spatial efficiency, aesthetic quality, and
environmental sustainability. The architectural solution is expected to respond to
urban context, optimize daylight and ventilation, and create a distinctive identity
within the development.
2. Structural Engineering Coordination
Structural design will ensure the buildings meet performance requirements for
safety, stability, and efficiency. Coordination will focus on seismic resilience, wind
load considerations, and material optimization for high-rise construction, aligning
with both local and international building standards.
3. MEP Engineering Coordination
Mechanical, Electrical, and Plumbing systems will be integrated to ensure reliable
building operations, energy efficiency, and occupant comfort. Coordination will
include smart building technologies, centralized utilities, fire safety systems, and
sustainable water and energy management strategies.
4. Landscape Architecture
The landscape design will provide vibrant and functional outdoor spaces,
enhancing the development’s livability and environmental performance.
Elements include softscape and hardscape design, pedestrian circulation, green
buffers, recreational areas, and integration of stormwater management solutions.
5. Interior Design
Interior spaces for residential units, public lobbies, and shared amenities will be
designed to meet modern lifestyle expectations. Focus areas include space
planning, material selection, lighting, acoustics, and detailing, with a balance of
functionality, durability, and contemporary aesthetics.
6. Signage & Wayfinding
A unified signage and wayfinding system will be developed to improve spatial
orientation and user navigation across the development. The design will be
accessible, visually consistent, and strategically positioned to support safety,
legibility, and brand identity.
7. Interior & Exterior Lighting Design
Lighting design will address both functional and experiential aspects, with energy-
efficient systems applied to indoor spaces, façades, landscapes, and circulation
zones. Emphasis will be placed on lighting quality, control systems, visual comfort,
and enhancement of architectural features.
8. Tender Documentation and IFC
Comprehensive documentation will be prepared for the tendering and
construction phases, including technical drawings, schedules, and specifications.
These packages will ensure clear communication of design intent, facilitate
accurate pricing, and support compliance during construction.
9. Construction Supervision and Post-Completion Support
Construction phase services will include on-site design supervision, quality control,
and coordination with contractors. Post-completion support will extend through
the Defects Liability Period, ensuring adherence to design specifications and
addressing operational or maintenance concerns.
3.0 METHODOLOGY
To ensure the successful delivery of the Costa Mare Project, the developers will
implement a phased and collaborative project methodology. The approach will
emphasize the early-stage planning, clear communication, and coordination among all
consultants and stakeholders. Design development will proceed through defined phases—
beginning with strategic definition and concept design, progressing through detailed
design and tendering, and culminating in construction and post-completion support.
Quality, cost control, regulatory compliance, and timely delivery will be prioritized
throughout, with the integration of digital tools and value engineering to optimize
outcomes across all disciplines.
3.1 DESIGN METHODOLOGY AND APPROACH
The design methodology for The Costa Mare Project is structured around a
comprehensive, phase-based process that ensures clarity, quality, and consistency
across all stages of development. The approach is multidisciplinary, collaborative, and
tailored to meet the technical, aesthetic, and commercial objectives of the project.
The methodology is guided by the following principles:
1. User-Centric Design. Prioritizing functionality, livability, and comfort for end-users
in both residential and commercial components.
2. Contextual Integration. Designing with sensitivity to the local urban, cultural, and
environmental context of Hanoi-Hung Yen.
3. Sustainability and Efficiency. Applying green building strategies, efficient systems,
and materials to reduce environmental impact.
4. Technical Coordination. Ensuring seamless integration of architectural, structural,
MEP, landscape, and interior elements.
5. Digital Collaboration.Utilizing Building Information Modeling (BIM) and other digital
tools for coordination, documentation, and clash detection.
3.2 PROJECT PHASES AND KEY DELIVERABLES
1. Strategic Definition Phase
Initial review of project objectives and constraints
Site and context analysis
Project strategy and scope definition
Stakeholder alignment
2. Preparation & Briefing Phase
Development of design brief and space program
Confirmation of project goals, KPIs, and success metrics
Identification of regulatory and planning requirements
3. Concept Design Phase (Pre-Concept and Final Concept)
Initial design options, massing studies, and spatial configurations
Finalization of overall design intent and concept narrative
3D visualizations, schematic diagrams, and area schedules
Review and approval by client and authorities
4. Developed / Schematic Design Phase
Detailed design layouts for all key components (towers, podiums, commercial
zones, basements)
Coordination with structure, MEP, and landscape systems
Preliminary materials and finishes selection
Compliance checks with local codes and zoning regulations
5. Technical / Detailed Design Phase
Full technical documentation including plans, sections, elevations, and details
Engineering drawings and system layouts (structural, MEP, lighting, signage,
etc.)
Detailed material specifications and product selections
Coordination sets for clash resolution using BIM
6. Tender Stage & Authority Approvals
Tender-ready drawing sets and technical specifications
Bill of Quantities and scope definitions for contractor bidding
Support during contractor queries and bid evaluations
Submission packages for authority review and permitting
7. IFC (Issued for Construction) Stage
Construction documentation with coordinated drawings across disciplines
Shop drawing reviews and contractor coordination support
Final updates based on authority and contractor inputs
8. Site Supervision During Construction
Regular site inspections and progress reviews
Design compliance checks and construction quality control
Review of submittals and Requests for Information (RFIs)
Coordination of on-site design adjustments
9. Retention Period (Post-Handover Support)
Ongoing design consultation during the Defects Liability Period
Support in resolving post-occupancy issues
Final design adjustments and record documentation (As-Built Drawings)
4.0 TIMELINE AND PROCESS GUIDE
PROJECT TIMELINE
PHASE DURATION DELIVERABLES
Project strategy, site analysis,
Strategic Definition Phase 1 month
stakeholder goals
Finalized design brief, spatial
program, authority
Preparation & Briefing Phase 1 month
requirement review
Pre-Concept Design Phase 2 months Massing, spatial layouts,
design intent, 3D visuals
Final Concept Design Phase 2 months
Refined plans, coordinated
Developed Design/Schematic layouts, initial materials and
3 months
Design Phase systems integration
Full technical documentation,
Technical Design/ Detailed specifications, BIM
5 months
Design Phase coordination
Tender documents, BOQ,
Tender Stage & Authority contractor packages,
3 months
Approval authority submissions
Aligned with the Final IFC documentation,
IFC (Issued for Construction) contractor contractor coordination
program
Ongoing supervision, site
reports, design clarifications
Aligned with the
Site Supervision During
construction
Construction
programme
Defect inspections, post-
Retention Period (Post- occupancy support, as-built
12 months
Handover Support) documentation
Estimated Design Delivery Start Q3 2025
Target Construction Start Late 2026
PROJECT PROCESS GUIDE
Phase 1–2: Project Initiation & Briefing
Conduct kickoff meetings with stakeholders
Review site conditions, regulatory context, and project goals
Develop and approve the project brief and success metrics
Phase 3: Concept Design
Explore multiple design options (massing, orientation, program distribution)
Conduct internal design reviews and value engineering exercises
Present final concept with 3D visuals and area statements for client approvaL
Phase 4: Developed Design / Schematic Design
Refine floor plans, façade concepts, and building systems
Coordinate with structural, MEP, and landscape consultants
Prepare material palettes, outline specs, and code compliance checks
Phase 5: Technical / Detailed Design
Translate approved design into construction-level drawings and documents
Finalize coordinated BIM models for all disciplines
Prepare technical specifications, detailing, and system layouts
Phase 6: Tendering & Approvals
Issue tender packages to shortlisted contractors
Respond to RFIs and provide clarifications
Submit documents for authority approvals and revise based on feedback
Phase 7: IFC Documentation
Finalize all drawings and specifications for construction
Incorporate authority and contractor comments
Deliver construction-ready sets with sign-offs
Phase 8: Construction Supervision
Conduct regular site visits and coordination meetings
Review contractor submittals and shop drawings
Provide timely responses to RFIs and ensure design intent is maintained
Phase 9: Retention Period / Post-Handover
Monitor building performance during the defects liability period
Address post-occupancy adjustments and warranty issues
Compile and deliver final as-built drawings and O&M manuals
5.0 TERMS AND CONDITIONS
This section establishes the contractual framework governing the provision of architectural
and related consultancy services for The Costa Mare Project in Hanoi–Hung Yen, Vietnam.
It sets out the responsibilities, rights, and obligations of both the Client and the Consultant
throughout the duration of the engagement.
5.1 ASSUMPTIONS/TERMS OF AGREEMENT
The Consultant’s scope of services, fees, and timeline have been defined based
on assumptions derived from the Client’s initial brief, project data, and regulatory context.
It is assumed that the Client will provide accurate and timely information and that no
substantial changes will occur to the project parameters unless formally revised by both
parties. Any deviation from the original scope or unforeseen complexities may require a
formal variation and adjustment of fees or delivery schedule.
Key Deliverables:
Executed consultancy agreement
Defined scope of works per project phase
Agreed fee proposal and payment schedule
Documented project assumptions and constraints
5.2 COMPLETION
A phase of work shall be deemed completed when all specified deliverables have
been submitted by the Consultant and formally accepted in writing by the Client.
Completion is subject to the timely provision of inputs and approvals from the Client.
Delays or non-approvals that fall outside the Consultant’s control may affect the project
timeline.
Key Deliverables (per phase):
Design submissions (Concept, Developed, Technical, IFC)
Authority submission documentation
Client approval forms or sign-off records
Phase completion reports (as applicable)
5.3 CONTRACT CANCELLATION
Either party reserves the right to terminate the agreement with justified cause and
written notice. In the event of termination, the Consultant shall be compensated for all
work completed up to the date of termination, including reimbursable expenses. All
completed deliverables shall be handed over to the Client upon receipt of outstanding
payments. Grounds for termination include non-performance, breach of contract, or
force majeure.
Key Deliverables upon Termination:
Inventory of completed work and percentage progress
Final invoice for completed services
Transfer of prepared documentation and source files
Official notice of termination and contractual closure
5.4 CONSULTANT’S LIABILITY
The Consultant shall be liable for damages arising from professional negligence,
errors, or omissions in the performance of their services, within the limits prescribed in the
agreement. The Consultant’s liability is typically limited to the value of fees received and
shall exclude consequential or indirect damages. Liability does not extend to contractor
execution, third-party performance, or unauthorized design modifications.
Supporting Documentation:
QA/QC records and internal design reviews
Professional indemnity insurance certificate
Error rectification logs (if applicable)
5.5 COPYRIGHT AND USE OF DOCUMENTS
All original design works, drawings, models, and documentation prepared by the
Consultant shall remain their intellectual property. The Client is granted a non-transferable
license to use the documents exclusively for the design, construction, and operation of
The Costa Mare Project. Reproduction, modification, or reuse of documents for other
purposes without written consent is prohibited.
Documentation Includes:
Copyright statement in deliverables
Document version control and usage disclaimer
License-to-use letter (if requested by the Client)
5.6 CLIENT’S RESPONSIBILITIES
The Client shall provide the Consultant with timely and accurate project
information, including legal site data, geotechnical reports, utility surveys, and design
input decisions. The Client is also responsible for engaging other required consultants,
securing permits, and issuing feedback or approvals in accordance with the project
schedule.
Expected Deliverables from Client:
Site ownership documents and topographical survey
Planning and regulatory data
Design brief and functional requirements
Signed approvals of design submissions
5.7 POST-CONTRACT – CONSTRUCTION STAGE SERVICES
Following the issuance of construction documentation, the Consultant shall
provide post-contract services, including construction supervision support, review of
contractor submittals, site inspections, and responses to RFIs. During the Defects Liability
Period (typically 12 months post-handover), the Consultant shall support the Client with
defect reviews and close-out documentation.
Key Deliverables:
Site visit and inspection reports
Responses to RFIs and shop drawing reviews
Snagging and defect tracking reports
As-built drawing reviews
Project close-out and final certification (if required)
6.0 QUOTE AND SIGN-OFF
PROJECT QUOTATION SUMMARY
Description of Services Fee (USD) Remarks
Architectural Design $180,000 Includes towers, podium,
and commercial zones
Structural Engineering $60,000 Design integration and
Coordination seismic/wind load
considerations
MEP Engineering $70,000 Energy-efficient systems,
Coordination fire safety, and utilities
Landscape Architecture $25,000 Softscape, hardscape,
circulation, and water
management
Interior Design $45,000 Residential units, lobbies,
amenities
Signage & Wayfinding $8,000 Integrated, accessible
Design navigation system
Lighting Design (Interior & $12,000 Energy-efficient and
Exterior) feature-enhancing
systems
Tender Documentation & $30,000 Full technical drawings
IFC and specifications
Construction Supervision & $40,000 On-site reviews, defect
Post-Completion Support inspections, and as-built
submissions
Contingency (5%) $23,500 For potential design
changes or escalations
Total Professional Fee (USD): $493,500
Payment Terms:
-20% upon Contract Signing
-60% distributed across milestones
-20% upon Final Completion
Note: All fees are exclusive of VAT and reimbursable expenses (travel, printing, third-party
testing, etc.), which will be billed separately with prior client approval. This quotation remains
valid for 60 days from the date of issue.
ACCEPTANCE AND SIGN-OFF
We, the undersigned, hereby agree to the scope of work, fees, and terms outlined in this
Commercial and Technical Proposal for The Costa Mare Project in Hanoi–Hung Yen,
Vietnam. We affirm our mutual commitment to the successful and timely delivery of this
development in line with the shared goals of design excellence, functionality, and
sustainability.
For the Client
Authorized Representative:
Name: ____________________________
Position: _________________________
Signature: _________________________
Date: ____________________________
For the Consultant
Authorized Representatives:
Name: CABURAL, VIÑE APRIL ROSE A.
Signature: _________________________
Date: ____________________________
Name: CHIU, KHYLLE ANDRE A.
Signature: _________________________
Date: ____________________________
Name: LACANO, JOHN REY L.
Signature: _________________________
Date: ____________________________
6.1 EXCLUSIONS
The following items are explicitly excluded from the Consultant's scope unless separately
commissioned by the Client:
- Environmental Impact Assessment (EIA) and Traffic Impact Assessment (TIA)
- Detailed cost estimation and quantity surveying beyond scope coordination
- LEED or other green building certification application fees and processes
- Government permitting and legal document preparation
- Marketing materials and real estate branding
- Furniture, Fixtures, and Equipment (FF&E) procurement and installation
- Direct coordination with contractors outside of formal construction supervision scope
- Security, AV, and ICT specialist design beyond general MEP coordination
- Physical scale models or virtual reality walkthroughs
- Third-party testing and commissioning services
**END OF DOCUMENT**