RK Hydro Engineering & Associates Pvt.
Ltd
ILEP (TATOPANI) KHOLA HYDROPOWER PROJECT(25MW)
24 hours Tunnel Work Time Cycle
S.N Work Description Time Hours
AM PM
1 Shift Change 7am 7:30am 30mins
2 Arrangements For Drilling 7:30am 8am 30mins
3 Face Drilling Work 8am 10:30am 2hrs30mins
4 Loading & Blasting 10.30am 11:15am 45 mins
5 Mucking 11:15am 1:15pm 2hrs
6 Survey /Face maping 1:15pm 1:45pm 30mins
7 Arrangements For Drilling 1:45pm 2:15pm 30mins
8 Face Drilling Work 2:15pm 4:45pm 2hrs30mins
9 Loading & Blasting 4:45pm 5:30pm 45mins
10 Mucking 5:30pm 7:30pm 2hrs
11 Survey /Face maping 7:30pm 8pm 30mins
12 Arrangements For Drilling 8pm 8:30pm 30mins
13 Face Drilling Work 8:30pm 11pm 2.30hrs
14 Loading & Blasting 11pm 11:45pm 45mins
15 Mucking 11:45pm 1:45am 2hrs
16 Survey /Face maping 1:45am 2:15am 30mins
17 Arrangements For Drilling 2:15am 2:45am 30mins
18 Face Drilling Work 2:45am 5:15am 2hrs30mins
19 Loading & Blasting 5:15am 6am 45mins
20 Mucking 6am 7am 1hrs
t. Ltd
T(25MW)
Remarks
Mucking work is going on…......
RK Hydro Engineering & Associates Pvt. Ltd
ILEP (TATOPANI) KHOLA HYDROPOWER PROJECT(25MW)
Manpower Planning for Adit-1
MANPOWER DETAILS
Civil Department Mechanical Departm
S.N Designation nos Remarks Designation
1 Site Incharge/Engineer 1 Mechanical Engineer
2 Surveyor 1 [Link]
3 Geologist 1 Wheel Loader Opt.
4 Excutive HR 1 Tractor Driver
5 Supervisor 2 Camper Driver
6 Foreman 2 Tyre Fitter
7 Electrican 2 Mechanic Helper
9 Store Keeper 2 Muckloader Operator
10 All Rounder 2 Muckloader Helper
11 Driller 4
12 Welder 1
13 Helper 5
14 Survey Helper 1
15 Store Helper 2
16 Blaster 1
17 Cook 2
18 Cook Helper 2
19
Total 32
NECESSARY EQUIPMENT
S.N. Name Nos Remarks
1 DG-125kva 1
2 Electric Compressor 1
3 Diesel Compressor 1
4 Wheel Loader 1
5 camper 1
6 Tractor 3
7 Concrete Placer 1
8 Ventilation Fan 1
9 Shotcrete Machine 1
10 Concrete Mixer 1
11 Muckloader 1
12 TM 1
Total 14
vt. Ltd
WER PROJECT(25MW)
Mechanical Department
nos Remarks
1
1
1 call duty
3 call duty
2 call duty
1
2
1 call duty
1 call duty
13
[Link] ENGINEERING ASSOCIATES PVT.L
ILEP (TATOPANI) KHOLA HYDROPOWER PROJECT(25
MONTHLY WORK SCHEDULE
Chainage Monthly Qu
S.N Name of the Documents Unit
From To
1 HRT-Headrace Tunnel
A. Adit-1(299m)
A.1. Portal Area 15-Jan
1 Site Clearance Sqm 0+000.00 Completed
2 Open Excavation Cum Completed
3 ISMB (Rib) Set 5set
4 Spotbolt Nos -
5 Rock Bolt Nos -
6 Spilling Rod Nos 20.00
7 Wiremesh Sqm -
8 Shotcrete Sqm -
9 MS Formwork Sqm 54.66sqm
10 Concrete Backfill cum -
A.2. Inside Tunnel
1 Underground Excavation m 0+000.00 0+299.00
2 Shotcrete Sqm
3 Spotbolt Nos
4 Rock Bolt Nos. 0+000.00 0+299.00
5 Spilling Rod Nos.
6 ISMB (Rib) Set
7 Tie Rod Kg
8 Anchor Bolt Kg
9 MS Formwork Sqm
10 Wiremesh Sqm
11 Cement Grouting (Cement Bags) Kg
12 Resin Capsule Nos.
13 De-watering KW
14 Concrete Backfill Cum
15 Weep Holes Nos
A.1. Face-1 January
1 Underground Excavation m
2 Shotcrete Sqm
3 Spotbolt Nos
4 Rock Bolt Nos.
5 Spilling Rod Nos.
6 ISMB (Rib) Set
7 Tie Rod Kg
8 Anchor Bolt Kg
9 MS Formwork Sqm
10 Wiremesh Sqm
11 Cement Grouting (Cement Bags) Kg
12 Resin Capsule Nos.
13 De-watering KW
14 Concrete Backfill Cum
15 Weep Holes Nos -
A.2. Face-2
1 Underground Excavation m
2 Shotcrete Sqm
3 Spotbolt Nos
4 Rock Bolt Nos.
5 Spilling Rod Nos.
6 ISMB (Rib) Set
7 Tie Rod Kg
8 Anchor Bolt Kg
9 MS Formwork Sqm
10 Wiremesh Sqm
11 Cement Grouting (Cement Bags) Kg
12 Resin Capsule Nos.
13 De-watering KW
14 Concrete Backfill Cum
15 Weep Holes Nos
ASSOCIATES [Link]
OPOWER PROJECT(25MW)
K SCHEDULE
Year-2026
Monthly Quantity
Remarks
February March April May
80.00 80.00 90.00 49.00
-
1100.00
-
-
-
-
-
-
-
- 996.00
-
-
-
February March
-
-
-
-
-
-
-
-
-
-