Tutorial 1
Name :
ID :
1. Table 1 summarises the Layang-1 Electrical Submersible Pump (ESP) design.
Table 1. Data for Well Layang-1.
Depth 10000 ft
Reservoir pressure 1500 psi
Well productivity index 3 stb/day/psi
Tubing internal diameter 0.188 ft
Surface manifold pressure 50 psi
Design well production 1500 stb/d
Produced fluid properties Water
Fluid density 0.433 psi/ft
Viscosity 1.05 cp
Fluid specific gravity 1.02
Moody friction factor 0.03
(a) Calculate the pipe friction loss (ΔPf) (4 marks)
(b) Calculate the required pump discharge pressure (Pd) (3 marks)
(c) Calculate the pump intake pressure (Pin) (3 marks)
(d) Calculate the number of pump stages (N) required (4 marks)
(e) Minimum electric motor power (HHP) (3 marks)
Tutorial 1
2. Design a gas lift installation for the following conditions:
Tubing 3.958 in
Required Production Rate 3000 stb/d
Water Cut 0%
Gas Oil Ratio 200 scf/stb
Gas Specific Gravity 0.65
o
Average Flowing Temperature 150 F
Reservoir Productivity Index 4 bpd/psi
Reservoir Depth 12,000 ft
Reservoir Pressure 3800 psi
Lift Gas Injection Gradient 30 psi/1000 ft
Minimum flowing tubing head 150 psi
pressure to transfer fluids to separator
o
Dead Oil Density 35 API (psi/ft)
Brine Density 0.45 psi/ft
Lift Gas Injection Rate 3,800,000 scf/d
Assume that the well is closed in with dead oil in the tubing and brine in the casing/tubing
annulus.
(a) Does this well require artificial lift to produce? (5 marks)
(b) What depth should the gas lift valve be installed in a single valve lift installation in
order to achieve the required production? (8 marks)
(c) What is the minimum surface gas injection pressure to kick the well off in the
configuration described? (3 marks)
(d) How does this change if dead crude oil was present in the casing/tubing annulus
instead of brine? (3 marks)