Sports Floor Construction Terms of Reference
Sports Floor Construction Terms of Reference
2. PUBLIC PURPOSE
The present process seeks to improve the level of integration of the educational institution, as well as to maintain the
functionality of the different circulation and recreation areas for students and staff of the
educational institution, also aiming to raise levels of efficiency and user satisfaction
internal and external.
3. BACKGROUND
The Municipality is carrying out the improvement of educational services at all levels.
Calca province, in order to improve educational quality at all levels and achieve results
satisfactory with the student body when they migrate to other competitive options. In that sense, with the
In order to achieve this objective, it is necessary to hire the service of qualified labor.
PAVING, CONCRETE FILLING FORMWORK AND ASPHALT JOINTS IN THE SPORTS SLAB; by
to be a complement to achieve the scheduled goals until a satisfactory conclusion of the
infrastructure.
The following project was approved by mayoral resolution N°0278-2014/A-MPC on October 23, 2014.
It also has Budget Credit Certification No. 0020; which was approved on January 28.
of the current year.
Specific Objectives:
Having an adequate recreation area for students.
Ensure the lifespan of the flooring in the sports slab
Promote sports activities.
Activities
Understand the preparation, cleaning, layout and leveling work, paving, formwork, filling of
concrete, frottage finish and sealing of joints with asphalt of the honor courtyard floors and slab
sports.
For the present provision of the service, the following activities will be carried out:
General cleaning of the area to be intervened.
Tracing and replanting of the slab and honor courtyard.
Paved with medium stone of 6"
Control of levels and slopes.
Concrete filling F’c=175 kg/cm2
Surface finish (frotachado)
Curing of concrete.
Joint sealing with asphalt RC-250
description CANTIDAD
PAVING, FORMING, CONCRETE FILLING AND JOINTS
ASPHALTIC ON THE SPORTS FLOOR. M2 1260
PAVING, FORMWORK, CONCRETE FILLING AND JOINTS
ASPHALTIC IN THE COURTYARD OF HONOR. M2 162
TOTAL 1422
5.2. Procedure
The surfaces of the slab will have a troweled finish (non-slip). All unevenness will be
removed, leaving the surface as smooth as possible.
It is the concrete layer that is poured over a cobblestone laid in a 3" layer. The concrete dosage will be
prepared using fine and coarse aggregate, with a concrete strength dosage of f'c=175
kg/cm2.
Cobblestone
The base where work will be done must be previously compacted and leveled. The level of compaction must
to have 15 cm and it will be loan material.
Cleaning of the area where the slab and honor patio are located, having to remove all waste or
organic material (plants, roots, etc.) that remains after compaction with material from
loan; remove and relocate to a position distant from the area where this work is done.
Carry out the drawing and layout of the project in the field, indicating in the field the details and alignments that
they will guide the contractor on the work plan.
The placement of the 6" stone will be done by always checking the corresponding levels and slopes.
The paving must be perfect without any unevenness and any that protrudes above the finished level.
They will be replaced before the concrete is poured.
FORMWORK
It corresponds to the formwork and stripping of the faces of the slabs; and they must be executed in compliance with
the corresponding technical specifications and the geometric characteristics indicated in the plans
relevant.
It also includes the manufacturing, placement, caulking, and removal of the normal formwork for slabs afterward.
that the time for formwork stripping is met. The wood used for the formwork will be checked and
authorized by the Supervision.
This batch refers to the formwork work for the slabs. The slabs should be poured block by block.
of 3.00 m. The areas to be formworked are the friezes, which must be perfectly secured and braced in the
extremes.
FILLING OF CONCRETE
Prior to the placement of concrete, the compacted, paved, and formwork soil must also be
wet and cleaned of foreign elements.
Consider the recommendations given regarding the curing of the slabs, which must be done the following day.
from the emptying, heal with plenty of water, making pools with sand that allow us to maintain a content
of acceptable humidity.
The concrete dosing must be that which meets the strength of f'c=175kg/cm2 and that will be
strictly controlled by residence and supervision.
Asphalt Joints
Once the curing period of the concrete sidewalks is finished, the joints will be cleaned vigorously.
carefully the bottom and the edges of the groove using metal brushes and brooms; for
then proceed with the placement of the sealing material with hot asphalt cement RC-250,
clean, dry, and fine sand, maintaining plasticity, subject to the approval of the inspecting engineer. Care will be taken.
especially the cleaning of the operation and any possible excess material will be removed. The sealing should not
to be carried out on rainy days, nor windy days, nor in low temperatures.
The width of the joint must comply with what is specified in the respective plan (1") and must be free from
powders, loose material, setting, completely dry. It is advisable to remove the surface grout by
an energetic brushing.
In case the joint depth exceeds the design, the excess space must be filled with
a polyurethane sponge or similar (teknoporn).
The asphalt printer should be left for 8 to 16 hours, depending on the ambient temperature or as specified by
the manufacturer.
Immediately after the placement is completed, a thin layer of sand will be applied,
on top of the material, to prevent the attack of ultraviolet rays. The excess sand will be removed that
it does not adhere.
The supplier must present samples of the finished floor of the slab using the materials that are
indicate in the technical specifications of the batch, for prior approval by the Supervision of the
Entity (MPC).
After polishing the terrazzo, the vitrification process will proceed.
Necessary resources.
Materials:
Portland cement type IP of 42.5 kg
3/4 inch crushed stone
Coarse aggregate
River concrete
Medium stone of 6"
Common wood for formwork
Asphalt RC-250
Water
Teams:
Concrete mixer.
Concrete vibrator
Wood cutter
Tools:
Ruleswith a square section of 3.00 and 6.00 m in length.
1Levelof bubble.
1 measuring tape
1 Rope for the layout.
1 Compaction element for onsite flooring.
1 Rubber mallet for tile seating.
1 Spade to spread the sand and mortar.
Rubber cubes.
Triangular palette.
Frotacho
Etc.
Action line to achieve goals and objectives (activities).
Not applicable
Activity schedule.
It will be coordinated with the residence and supervision for the development of the activities.
Advised risks.
Not applicable
The pavement will be constructed to withstand static and dynamic loads, with a passability
suitable. It is built entirely supported on the ground (natural in cut or embankment
compacted in filling), prepared to receive it, which is called sub-base.
And that the national building regulation CE-010 must comply with
Environmental impact
It does not correspond.
Insurance
It does not correspond.
Supplier Requirements
The supplier must have all the documentation of their represented party, and must also be
registered and authorized by the Sunat.
Valid registration in the single registry of taxpayers of the SUNAT, and single registry of suppliers
services issued by the OSCE that authorize it to carry out activities as a provider of
state services
. Copy of the RUC record
Supplier Profile
The provider must have and support an experience of no less than 02 contracts in activities.
similar.
Staff Profile
They must have at least 1 year of experience in similar duties or
civil construction.
PLACE
The location of the service will be in the Community of Huaran - Calca, 10 minutes from
district in vehicle, main track
DEADLINE
The execution period is 20 calendar days according to the project execution schedule.
after the signing of the contract.
5.15 Advances
If necessary, the Entity will grant advances upon request from the contractor up to thirty percent.
thirty percent (30%) of the original contract amount.
The advance can be established in services of single, continuous, or periodic execution, as long as the
The purpose of the advance is to provide liquidity to the contractor to facilitate the execution of the services.
under the conditions and opportunity agreed upon in the contract.
Subcontracting
Not applicable.
5.17. Confidentiality
Not applicable.
compliance report from the user area and the Infrastructure management.
0.10 * Amount
F*Deadline in days
When the maximum penalty amount is reached, the entity may resolve the
contract for breach