0% found this document useful (0 votes)
58 views4 pages

Rate Analysis of Demarcation Pole

The document outlines the costs and specifications for providing and laying cement concrete poles, including materials, labor, and contractor profit. It details the quantities, rates, and total costs associated with each phase of the project, including skilled and unskilled labor requirements. The final total cost for each pole, including GST, is calculated to be ₹417.68.

Uploaded by

deep.deysss90
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
58 views4 pages

Rate Analysis of Demarcation Pole

The document outlines the costs and specifications for providing and laying cement concrete poles, including materials, labor, and contractor profit. It details the quantities, rates, and total costs associated with each phase of the project, including skilled and unskilled labor requirements. The final total cost for each pole, including GST, is calculated to be ₹417.68.

Uploaded by

deep.deysss90
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

S.No.

Description of Item Unit No of Poles

Providing and laying in position cement concrete of specified


1 grade M15 (1:2:4) in precast frustum-shaped pole including m³ 1000
centering, shuttering, mixing, placing and finishing etc. all
complete as per CPWD specs.

Reinforcement for RCC work including straightening, cutting,


2 bending, placing in position and binding all complete – using kg 1000
mild steel bars (6 mm dia)
3 Binding wire Cost kg 1000

Fabricating and fixing steel moulds suitable for casting poles


3 with taper shape (base dia 200 mm, top dia 150 mm, height 900 each 40
mm) including all welding, fixing handles, etc., complete –
reusable mould cost per pole.
4 Manpower Cost Total
Total

So for Each Pole Cost with fixing, after add Contractor Profit 353.96
GST(18%) 63.71
Total cost 417.68
Qty Rate (₹) Amount (₹) Remarks

0.0218 5967 130080.6

1.654 66 109164

0.01654 88 1455.52

1 250 10000

103264.25
353964.37

353.96
63.71
417.68
Activity Skilled (Mandays) Unskilled (Mandays) Skilled Cost (₹)
Cutting & Bending of Reinforcement 10 0 6470
Shuttering and Formwork 25 10 16175
Mixing, Placing & Compaction of Concrete 25 30 16175
Curing and Demoulding 10 10 6470
Pole Erection & Finishing 15 25 9705

Cost after add contractor profit o


Unskilled Cost (₹) Total Cost (₹) Remarks
0 6470
4640 20815
1) Skilled manpower- 647,
13920 30095 2) Unskilled manpower Rate - 464 (As
4640 11110 per current rate of Govt. of
Jharkhand)
11600 21305
Total 89795
fter add contractor profit of 15% 103264.25

You might also like