S.No.
Description of Item Unit No of Poles
Providing and laying in position cement concrete of specified
1 grade M15 (1:2:4) in precast frustum-shaped pole including m³ 1000
centering, shuttering, mixing, placing and finishing etc. all
complete as per CPWD specs.
Reinforcement for RCC work including straightening, cutting,
2 bending, placing in position and binding all complete – using kg 1000
mild steel bars (6 mm dia)
3 Binding wire Cost kg 1000
Fabricating and fixing steel moulds suitable for casting poles
3 with taper shape (base dia 200 mm, top dia 150 mm, height 900 each 40
mm) including all welding, fixing handles, etc., complete –
reusable mould cost per pole.
4 Manpower Cost Total
Total
So for Each Pole Cost with fixing, after add Contractor Profit 353.96
GST(18%) 63.71
Total cost 417.68
Qty Rate (₹) Amount (₹) Remarks
0.0218 5967 130080.6
1.654 66 109164
0.01654 88 1455.52
1 250 10000
103264.25
353964.37
353.96
63.71
417.68
Activity Skilled (Mandays) Unskilled (Mandays) Skilled Cost (₹)
Cutting & Bending of Reinforcement 10 0 6470
Shuttering and Formwork 25 10 16175
Mixing, Placing & Compaction of Concrete 25 30 16175
Curing and Demoulding 10 10 6470
Pole Erection & Finishing 15 25 9705
Cost after add contractor profit o
Unskilled Cost (₹) Total Cost (₹) Remarks
0 6470
4640 20815
1) Skilled manpower- 647,
13920 30095 2) Unskilled manpower Rate - 464 (As
4640 11110 per current rate of Govt. of
Jharkhand)
11600 21305
Total 89795
fter add contractor profit of 15% 103264.25