Guggenheim Abu Dhabi FF&E Package Report
Guggenheim Abu Dhabi FF&E Package Report
FF&E Package
PROGRAM NARRATION
INDEX
1. PROJECT SUMMARY
2. WBS
3. PROGRAM WEIGHTAGE
4. CALENDAR
5 PROJECT S-CURVE
6. MANPOWER HISTOGRAM
7. EARNED VALUE
8. CRITICAL PATH
9. KPI’S
P|2
FF&E PACKAGE
01. PROJECT SUMMARY
P|3
FF&E PACKAGE
02. WBS
P|4
FF&E PACKAGE
02. WBS_LEVEL 3
P|5
FF&E PACKAGE
04. PROGRESS MEASUREMENT-WEIGHTAGE DISTRIBUTION
WEIGHTAGE DISTRIBUTION
P|6
FF&E PACKAGE
04. COST DISTRIBUTION
COST DISTRIBUTION
P|7
FF&E PACKAGE
05. CALENDAR
PROJECT CALENDAR
HOLIDAYS : 2025
JUNE - 05th 06th & 26th
SEPTEMBER - 04th
NOVEMBER -30th
DECEMBER - 01st & 02nd
2026
JANUARY - 01st
MARCH - 18th 19th & 20th
MAY - 26th 27th 28th & 29th
P|7
PROGRESS %
weekly
Weekly
Actual%
DATA DATE : #######
Planned%
Actual %-
Planned %-
Cumulative
Cumulative-
Description
0.00%
1.00%
1.50%
2.00%
2.50%
3.00%
3.50%
4.50%
0.50%
4.00%
0.11% 0.11% 23-May-25
1.56% 0.57%
Actual %- weekly
20-Jun-25
Planned %- Weekly
Cumulative-Actual%
Cumulative Planned%
FF&E Package
DATA DATE : #######
16% 120%
Planned %- Monthly PROJECT S CURVE- MONTHLY
Actual %- Monthly
14% Cumulative Planned% 100%
Cumulative-Actual%
12%
80%
10%
8% 60%
6%
40%
4%
20%
2%
0% 0%
May-25
May-26
Aug-25
Dec-25
Nov-25
Mar-26
Sep-25
Oct-25
Feb-26
Jan-26
Apr-26
Jun-25
Jul-25
Description
10.93%
11.43%
14.18%
0.26%
2.07%
9.71%
8.30%
7.19%
8.06%
8.65%
7.72%
8.82%
2.69%
Planned %-
MONTHLY PROGRESS %
Monthly
Actual %-
Monthly
100.00%
12.03%
22.96%
31.26%
38.45%
46.51%
57.94%
66.59%
74.31%
88.49%
97.31%
0.26%
2.33%
Cumulative
Planned%
Cumulative-
Actual%
GUGGENHEIM ABU DHABI
FF&E Package
DATA DATE : 11-Jul-25
16% 120%
Planned %- Weekly
Actual %- weekly
ENGINEERING
14% Cumulative Planned%
Cumulative-Actual% 100%
12%
80%
10%
8% 60%
6%
40%
4%
20%
2%
0% 0%
15-Aug-25
22-Aug-25
29-Aug-25
12-Sep-25
27-Jun-25
1-Aug-25
8-Aug-25
11-Jul-25
18-Jul-25
25-Jul-25
5-Sep-25
4-Jul-25
Description
12.10%
12.77%
13.39%
1.55%
6.28%
7.84%
9.59%
9.02%
5.84%
6.97%
9.68%
4.99%
Planned %- Weekly
ENG-PROGRESS
Actual %- weekly
100.00%
15.67%
25.26%
34.27%
40.11%
47.08%
59.18%
71.95%
85.33%
95.01%
1.55%
7.83%
Cumulative
Planned%
Cumulative-Actual%
PRO-PROGRESS
weekly
Weekly
Actual%
Planned%
Actual %-
Planned %-
Cumulative
Description
0%
2%
3%
4%
5%
1%
6%
Cumulative-
0.09% 0.09% 30-May-25
Cumulative-Actual%
20%
100%
120%
MOCKUP & SAMPLE - PROGRESS
Actual
Weekly
Weekly
Planned
DATA DATE : 6-Feb-26
Cumulative
Cumulative-
Actual Value-
Description
0%
8%
2%
4%
6%
10%
12%
Planned Value-
0.15% 0.15% 11-Jul-25
FF&E Package
DATA DATE : 6-Feb-26
20% 120%
Planned Value- Weekly INSTALLATION
18% Actual Value- Weekly
Cumulative Planned
100%
16% Cumulative-Actual
14%
80%
12%
10% 60%
8%
40%
6%
4%
20%
2%
0% 0%
18.17% 13-Mar-26
16.28% 20-Mar-26
27-Mar-26
13-Feb-26
10.52% 20-Feb-26
12.61% 27-Feb-26
10-Apr-26
17-Apr-26
24-Apr-26
6-Mar-26
6-Feb-26
3-Apr-26
Description
INSTALLATION - PROGRESS
17.83%
2.80%
5.88%
7.30%
3.51%
2.58%
1.92%
0.62%
Planned Value-
Weekly
Actual Value-
Weekly
100.00%
19.19%
31.80%
49.63%
67.80%
84.08%
91.38%
94.89%
97.47%
99.38%
2.80%
8.67%
Cumulative Planned
Cumulative-Actual
GUGGENHEIM ABU DHABI
FF&E Package
80
Planned - Manpower
MANPOWER HISTOGRAM -WEEKLY
70 Actual- Manpower
60
50
40
30
20
10
01-May-26
08-May-26
15-May-26
18-May-26
06-Mar-26
13-Mar-26
20-Mar-26
27-Mar-26
06-Feb-26
13-Feb-26
20-Feb-26
27-Feb-26
03-Apr-26
10-Apr-26
17-Apr-26
24-Apr-26
Weekly Manpower
Description
Planned - Manpower 11 23 40 48 68 70 65 33 20 18 20 13 10 10 10 10
Actual- Manpower
Earned Value-Weekly
weekly
Weekly
Actual%
DATA DATE : #######
Planned%
Actual %-
Planned %-
Cumulative
Cumulative-
Description
0
100,000
300,000
400,000
500,000
600,000
700,000
800,000
200,000
5,686 5,686 23-May-25
20-Jun-25
Actual %- weekly
248,013 106,335
Planned %- Weekly
Cumulative-Actual%
Cumulative Planned%
15,000,000
GUGGENHEIM ABU DHABI
FF&E Package
DATA DATE : 6-Feb-26 3,500,000 Planned Value- Monthly
25,000,000
EARNED VALUE-MONTHLY
Actual Value- Monthly
Cumulative-Actual
3,000,000 Cumulative Planned
20,000,000
2,500,000
15,000,000
2,000,000
1,500,000
10,000,000
1,000,000
5,000,000
500,000
0 0
May-25
May-26
Aug-25
Dec-25
Nov-25
Mar-26
Sep-25
Oct-25
Feb-26
Jan-26
Apr-26
Jun-25
Jul-25
Description
2,353,074
2,837,667
2,235,840
1,967,208
2,203,973
3,090,390
2,321,170
1,093,400
2,082,214
1,007,545
Planned Value-
387,940
365,356
19,836
Monthly
Earned Value
Actual Value-
Monthly
12,005,538
15,095,928
17,417,098
18,510,498
20,592,712
21,600,257
21,965,613
2,760,850
5,598,517
7,834,357
9,801,565
Cumulative
407,776
19,836
Planned
Cumulative-
Actual
FF&E PACKAGE
0. CRITICAL PATH
P|8
GUGGENHEIM, ABU DHABI - BASELINE -
R7
Activity ID Activity Name Original Start Finish Total FloatMay June July August S October November December January February March April May
Duration 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1
- 1 2 3 4 5 6 7 8 9 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 5 5 5 5
GUGGENHEIM, ABU DHABI - BASELINE - R7 365 19-May-25 18-May-26 0
Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
Page 1 of 4
Actual Level of Effort Milestone 19-May-25
Primary Baseline Summary
Actual Work
Remaining Work
GUGGENHEIM, ABU DHABI - BASELINE -
R7
Activity ID Activity Name Original Start Finish Total FloatMay June July August S October November December January February March April May
Duration 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1
- 1 2 3 4 5 6 7 8 9 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 5 5 5 5
MATERIAL SUBMISSION 12 21-Jun-25 05-Jul-25 0
GG-E-MS-R0-S-1160 MS Preparation / Submission for Circulation Bench (CF.02.01, CF.03.01) 12 21-Jun-25 05-Jul-25 0
MATERIAL REVIEW & COMMENTS 10 07-Jul-25 18-Jul-25 0
GG-E-MS-R0-A-1160 MS Review / Comments for Circulation Bench (CF.02.01, CF.03.01) 10 07-Jul-25 18-Jul-25 0
MATERIAL SUBMITTAL - REV 01 (REVIEW & APPROVAL) 10 04-Aug-25 15-Aug-25 0
MATERIAL REVIEW & APPROVAL 10 04-Aug-25 15-Aug-25 0
GG-E-MS-R1-A-1160 MS Review /Approval for Circulation Bench (CF.02.01, CF.03.01) 10 04-Aug-25 15-Aug-25 0
MATERIAL ORDER 24 31-Oct-25 23-Nov-25 0
LOOSE FURNITURE ITEMS 6 31-Oct-25 05-Nov-25 0
GUG-PRO-ORD-1370 Material Order for Make Up Counter Chair (CH.13.01) 6 31-Oct-25 05-Nov-25 0
CUSTOM MADE ITEMS 18 06-Nov-25 23-Nov-25 0
GUG-PRO-ORD-1160 Material Order for Circulation Bench (CF.02.01, CF.03.01) 6 06-Nov-25 11-Nov-25 0
GUG-PRO-ORD-1000 Material Order for Desk Chair (DC.02.01, IF-03) 6 12-Nov-25 17-Nov-25 0
GUG-PRO-ORD-1010 Material Order for Desk Chair (DC.01.01, LIB-04) 6 12-Nov-25 17-Nov-25 0
GUG-PRO-ORD-1050 Material Order for Guest Chair (CH.06.02, IF-02) 6 18-Nov-25 23-Nov-25 0
MATERIAL PRODUCTION AND DELIVERY 89 06-Nov-25 02-Feb-26 0
LOOSE FURNITURE ITEMS 89 06-Nov-25 02-Feb-26 0
GUG-PRO-PRD-1370 Material Production and Delivery for Make Up Counter Chair (CH.13.01) 89 06-Nov-25 02-Feb-26 0
CUSTOM MADE ITEMS 83 12-Nov-25 02-Feb-26 0
GUG-PRO-PRD-1000 Material Production and Delivery for Desk Chair (DC.02.01, IF-03) 75 18-Nov-25 31-Jan-26 0
GUG-PRO-PRD-1010 Material Production and Delivery for Desk Chair (DC.01.01, LIB-04) 75 18-Nov-25 31-Jan-26 0
GUG-PRO-PRD-1160 Material Production and Delivery for Circulation Bench (CF.02.01, CF.03.01) 82 12-Nov-25 01-Feb-26 0
GUG-PRO-PRD-1050 Material Production and Delivery for Guest Chair (CH.06.02, IF-02) 71 24-Nov-25 02-Feb-26 0
Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
Page 2 of 4
Actual Level of Effort Milestone 19-May-25
Primary Baseline Summary
Actual Work
Remaining Work
GUGGENHEIM, ABU DHABI - BASELINE -
R7
Activity ID Activity Name Original Start Finish Total FloatMay June July August S October November December January February March April May
Duration 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1
- 1 2 3 4 5 6 7 8 9 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 5 5 5 5
COMMON AREA 15 16-Feb-26 04-Mar-26 0
GUG-INS-B1Z1-L1-1020 Installation of Adjustable Wall Mounted Shelving (3 Shelves) (SH.01.01) 15 16-Feb-26 04-Mar-26 0
GALLERY - 106 12 24-Mar-26 06-Apr-26 0
GUG-INS-B1Z1-L1-1170 Installation of Gallery Bench (CF.01.01) 12 24-Mar-26 06-Apr-26 0
GALLERY - 107 - FLEXIBLE THEATRE 15 01-Apr-26 17-Apr-26 0
GUG-INS-B1Z1-L1-1000 Installation of Flexible Theater Chair (CH.15.01) 15 01-Apr-26 17-Apr-26 0
GUG-INS-B1Z1-L1-1010 Installation of Flexible Theater Table (TB.13.01) 15 01-Apr-26 17-Apr-26 0
GUG-INS-B1Z1-L1-1030 Installation of Make Up Counter Chair (CH.13.01) 15 01-Apr-26 17-Apr-26 0
GUG-INS-B1Z1-L1-1090 Installation of Red Sofa (LC.07.01, SF.03.01) 15 01-Apr-26 17-Apr-26 0
GUG-INS-B1Z1-L1-1100 Installation of Side Table (CT.08.01) 15 01-Apr-26 17-Apr-26 0
GUG-INS-B1Z1-L1-1110 Installation of Coffee Table (CT.03.01) 15 01-Apr-26 17-Apr-26 0
LEVEL 01 MEZZANINE 15 24-Feb-26 12-Mar-26 0
COMMON AREA 15 24-Feb-26 12-Mar-26 0
GUG-IN-B1Z1-L1M-1000 Installation of Desk Chair (DC.01.01, LIB-04) 15 24-Feb-26 12-Mar-26 0
LEVEL 02 25 13-Mar-26 10-Apr-26 0
COMMON AREA 25 13-Mar-26 10-Apr-26 0
GUG-IN-B1Z1-L2-1000 Installation of Desk Chair (DC.01.01, LIB-04) 15 13-Mar-26 30-Mar-26 0
GUG-IN-B1Z1-L2-1010 Installation of Adjustable Wall Mounted Shelving (3 Shelves) (SH.01.01) 15 13-Mar-26 30-Mar-26 0
GUG-IN-B1Z1-L2-1050 Installation of Back Of House Standard Shelving 15 13-Mar-26 30-Mar-26 0
GUG-IN-B1Z1-L2-1060 Installation of Guest Chair (CH.06.01) 15 13-Mar-26 30-Mar-26 0
GUG-IN-B1Z1-L2-1080 Installation of Quran Stand (QS.01.01) 15 13-Mar-26 30-Mar-26 0
GUG-IN-B1Z1-L2-1100 Installation of Circulation Bench (CF.02.01, CF.03.01) 15 13-Mar-26 30-Mar-26 0
GUG-IN-B1Z1-L2-1020 Installation of Lateral File Cabs (ADM-04,ADM-40, LF.01.01) 25 13-Mar-26 10-Apr-26 0
GUG-IN-B1Z1-L2-1030 Installation of Type C Desk - Large Straight Worksurface (DK.03.01) 25 13-Mar-26 10-Apr-26 0
GUG-IN-B1Z1-L2-1040 Installation of Worksurface & Storage (CB.01.01, CB.09.01) 25 13-Mar-26 10-Apr-26 0
GUG-IN-B1Z1-L2-1070 Installation of Pedestal File Cabinet (DS.01.01,ADM-13, ADM-23,ASO-21, EFW-108, PHO-24)25 13-Mar-26 10-Apr-26 0
GALLERY - 207 12 13-Mar-26 26-Mar-26 0
GUG-IN-B1Z1-L2-1150 Installation of Gallery Screen (CF.26.01) 12 13-Mar-26 26-Mar-26 0
GALLERY - 208 12 16-Mar-26 28-Mar-26 0
GUG-IN-B1Z1-L2-1090 Installation of Gallery Bench (CF.01.01) 12 16-Mar-26 28-Mar-26 0
LEVEL 03 17 24-Mar-26 11-Apr-26 0
GALLERY - 305 12 24-Mar-26 06-Apr-26 0
GUG-IN-B1Z1-L3-1000 Installation of Gallery Bench (CF.01.01) 12 24-Mar-26 06-Apr-26 0
GALLERY - 306 12 30-Mar-26 11-Apr-26 0
GUG-IN-B1Z1-L3-1030 Installation of Gallery Bench (CF.01.01) 12 30-Mar-26 11-Apr-26 0
LEVEL 04 12 04-Apr-26 17-Apr-26 0
GALLERY - 405 12 04-Apr-26 17-Apr-26 0
GUG-IN-B1Z1-L4-1020 Installation of Gallery Bench (CF.01.01) 12 04-Apr-26 17-Apr-26 0
BUILDING 02 - ZONE 2 15 03-Feb-26 19-Feb-26 0
CLEARANCES 0 03-Feb-26 03-Feb-26 0
GUG-IN-B2Z2-CL-1000 Site Readiness for Installation Works - Level 01 - B2Z2 0 03-Feb-26* 0
LEVEL 01 15 03-Feb-26 19-Feb-26 0
COMMON AREA 15 03-Feb-26 19-Feb-26 0
GUG-IN-B2Z2-L1-1000 Installation of Guest Chair (CH.06.02, IF-02) 15 03-Feb-26 19-Feb-26 0
BUILDING 03 - ZONE 3 23 03-Feb-26 28-Feb-26 0
CLEARANCES 0 03-Feb-26 03-Feb-26 0
GUG-IN-B3Z3-CL-1000 Site Readiness for Installation Works - Level 01 - B3Z3 0 03-Feb-26* 0
LEVEL 01 15 12-Feb-26 28-Feb-26 0
COMMON AREA 15 12-Feb-26 28-Feb-26 0
Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
Page 3 of 4
Actual Level of Effort Milestone 19-May-25
Primary Baseline Summary
Actual Work
Remaining Work
GUGGENHEIM, ABU DHABI - BASELINE -
R7
Activity ID Activity Name Original Start Finish Total FloatMay June July August S October November December January February March April May
Duration 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1
- 1 2 3 4 5 6 7 8 9 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 5 5 5 5
GUG-IN-B3Z3-L1-1000 Installation of Desk Chair (DC.02.01, IF-03) 15 12-Feb-26 28-Feb-26 0
ADMINISTRATION 0 03-Feb-26 03-Feb-26 0
CLEARANCES 0 03-Feb-26 03-Feb-26 0
GUG-INS-ADM-1190 Site Readiness for Installation Works -Administration Building - Level-1 Mezzanine 0 03-Feb-26* 0
Remaining Level of Effort Critical Remaining Work Date Revision Checked Approved
Page 4 of 4
Actual Level of Effort Milestone 19-May-25
Primary Baseline Summary
Actual Work
Remaining Work
FF&E PACKAGE
09. KPI’s
Legend:
SHOP DRAWINGS
METHOD STATEMENT
MATERIAL SUBMITTAL
MOCKUP SUBMISSION
P|9