IBC Laws® | www.ibclaw.
in
I. Case Reference
Case Citation : (2017) ibclaw.in 203 SC
Case Name : Eitzen Bulk A/S Vs. Ashapura Minechem Ltd. & Anr.
Civil Appeal Nos. 5131-5133 of 2016 with Civil Appeal Nos. 5136 of 2016
Appeal No. :
with Civil Appeal Nos. 5134-5135 of 2016
Judgment Date : 13-May-16
Court/Bench : Supreme Court of India
Coram : Mr. Justice Fakkir Mohamed Ibrahim Kalifulla and Mr. Justice S. A. Bobde
Original Judgment : Download
II. Full text of the judgment
JUDGMENT
S. A. BOBDE, J.
Leave granted in SLP (C) Nos.2210-2212/2011, SLP (C) Nos.3959/2012 and SLP (C)
No.7562-7563/2016.
2. The dispute in these appeals, arises out of the Contract of Affreightment dated 18.1.2008
(hereinafter referred as `the Contract’). Eitzen Bulk A/S of Denmark (hereinafter referred to as
`Eitzen’) entered into the contract with Ashapura Minechem Limited of Mumbai (hereinafter
referred to as `Ashapura’) as charterers for shipment of bauxite from India to China. The Charter
party contains an Arbitration Clause as follows:-
“Clause No. 28
Any dispute arising under this C.O.A. is to be settled and referred to Arbitration in London.
One Arbitrator to be employed by the Charterers and one by the Owners and in case they shall
not agree then shall appoint an Umpire whose decision shall be final and binding, the
Arbitrators and Umpire to be Commercial Shipping Men. English Law to apply.
Notwithstanding anything to the contrary agreed in the C.O.A., all disputes where the amount
involved is less then USD 50,000/- (fifty thousand) the Arbitration shall be conducted in
accordance with the Small Claims Procedure of the L.M.A.A.”
(emphasis supplied)
3. Disputes having arisen between the parties, the matter was referred to Arbitration by a sole
Arbitrator. The Arbitration was held in London according to English Law. Ashapura Minechem was
held liable and directed to pay a sum of 36,306,104 US$ together with compound interest at the rate
of 3.75 % per annum. In addition they were directed to pay 74,135 US$ together with compound
interest at the rate of 3.75% per annum and another sum of 90,233.66 Pounds together with
compound interest at the rate of 2.5% per annum vide Award of the Sole Arbitrator dated 26.5.2009.
Proceedings in Gujarat
Print Date: August 1, 2025 Page 1 of 9 Printed for:
IBC Laws® | www.ibclaw.in
4. Before Arbitration had commenced, Ashapura filed a suit alongwith an application for injunction
before the Civil Judge at Jam-khambalia, Gujarat praying inter-alia that the Contract and the
Arbitration Clause contained therein was illegal, null and void, ab-initio. Though initially an interim
injunction was granted, the learned Civil Judge dismissed the suit for want of jurisdiction vide order
dated 12.1.2009. The appeal filed by Ashapura before the Gujarat High Court was dismissed as
withdrawn on 2.7.2009.
5. In London, Mr. Tim Marshal, who was appointed as Arbitrator, held that Ashapura was in
repudiatory breach and awarded Eitzen Bulk an amount of 36,306,104.00 $ plus interest, as stated
above.
6. Having failed to stall the Arbitration and then having failed in the Arbitration proceedings,
Ashapura resorted to Section 34 of the Arbitration Act and filed objections in India in respect of the
Award passed in London. These proceedings were filed before the District Judge, Jamnagar for
setting aside the Foreign Award made in London. A Misc. Civil Application No. 101/2009 for
injunction restricting Eitzen Bulk from enforcing the Award in foreign jurisdictions outside India was
also moved. The District Judge, Jamnagar on 24.8.2009 dismissed the application for injunction
seeking restraint on enforcement of the Award.
7. From 14.7.2009 to 3.8.2009 Eitzen applied for enforcement of the Award in the countries of
Netherlands, USA, Belgium, UK. The Courts in various jurisdictions have held the Award to be
enforceable as a judgment of the Court.
8. On 14th July, 2009, the appellant filed proceedings in Netherlands Court seeking a declaration
that the award dated 26th May, 2009 is enforceable as a judgment of the Court. The respondent
appeared in the said proceedings and filed their objections. The Netherlands Court, however,
declared that the award is enforceable as a judgment of the Court on 17th March, 2010.
9. On 24th July, 2009, the United States District Court for Southern State of New York declared the
award dated 26th May, 2009 enforceable as a judgment of that court. The proceedings filed by the
appellant were contested by the respondent.
10. On 27th July, 2009, the appellant filed present proceedings under Sections 47 to 49 of Part II of
the Arbitration Act for enforcing the award dated 26th May, 2009 on the ground that the respondent
was carrying on business within the jurisdiction of this Court and has its registered office and
corporate office and assets within the territorial jurisdiction of this Court.
11. On 29th July, 2009, the Antwerp Court declared the award dated 26th May, 2009 enforceable as
a judgment of the Court. The said proceedings were contested by the respondent. On 3rd August,
2009, the English High Court declared the award dated 26th May, 2009 enforceable as a judgment
of the Court.
12. Against the rejection of the application for injunction Ashapura filed a petition under Articles
226 and 227 of the Constitution of India before the High Court of Gujarat at Ahmadabad for a Writ of
Certiorari to quash and set aside the Order dated 24.8.2009 rendered by the District Judge, Jam-
Khambalia and for a direction not to enforce the execution of the judgment dated 24.7.2009.
Ashapura inter-alia contended that the Award cannot be enforced or executed since their objections
under Section 34 were pending. A learned Single Judge who heard the petition however, observed
Print Date: August 1, 2025 Page 2 of 9 Printed for:
IBC Laws® | www.ibclaw.in
that the issues before him were inextricably connected with the issues of jurisdiction of the Court in
the Section 34 application and the contentions of Eitzen opposing the said Section 34 application.
The Single Judge, therefore, set aside the Order dated 24.8.2009 and remanded the matter for fresh
decision in accordance with law by Order dated 3.9.2009. In Letters Patent Appeal filed by Eitzen
the Division Bench of the High Court of Gujarat directed the District Judge to consider all
contentions by its Order dated 29.10.2009.
13. Eitzen however questioned the very jurisdiction of a Court in India to decide objections under
Section 34 of the Arbitration Act in respect of a Foreign Award by way of a Writ Petition. They
prayed for issue of a Writ of Prohibition and an Order restraining the learned District Judge at Jam-
Khambhalia from adjudicating Ashapura’s application under Section 34 of the Arbitration and
Conciliation Act, 1996 against the Foreign Award dated 26.5.2009.
14. A learned Single Judge issued notice and stayed further proceedings before the Jamnagar Court
on 20.11.2009. Ashapura however filed LPA No. 2469 of 2009 challenging the Order of the learned
Single Judge dated 20.11.2009. The Division Bench which heard the appeal has held by Judgment
and Order dated 22.9.2010, that Ashapura is entitled to challenge the Foreign Award under Section
34 of Part I of the Arbitration Act. It has further held that the territorial jurisdiction is a mixed
question of fact and law and is required to be decided by the Trial Court on the basis of the Plaint
and Written Statement and Evidence before it. This judgment was questioned by way of SLP (C) Nos.
2210-2212 of 2011 filed by Eitzen.
Proceedings in Maharashtra
15. On 27.7.2009, Eitzen filed Arbitration Petition No. 561/2009 under Sections 47 to 49 of the
Arbitration Act for enforcing the Foreign Award in the Bombay High Court, within whose jurisdiction
Ashapura carries on business and has a registered office. The Award was also received by Ashapura
within the jurisdiction of the Bombay High Court. This petition for enforcement was filed on the
basis that Part I of the Arbitration Act has no application to a Foreign Award made in London under
English Law. The petition for enforcement of a Foreign Award was accompanied by Notice of Motion
No. 3143 of 2009 under Section 49 (3) of the Arbitration Act for securing their claim under the ex-
parte Award dated 26.5.2009.
16. The learned Single Judge held that since the parties had agreed that the juridical seat of the
Arbitration in this case would be at London and English Law would apply there was an express and
in any case an implied, exclusion of Part I of the Arbitration Act.
17. Ashapura filed Notice of Motion No. 3975 of 2009 claiming that since proceedings had already
been initiated under Part I before the Gujarat High Court, the Bombay High Court had no
jurisdiction in the matter by virtue of Section 42 of the Arbitration Act. A learned Single Judge of the
Bombay High Court vide order dated 05.10.2011 dismissed the Notice of Motion and held that Part I
of the Arbitration Act was excluded by the parties and therefore Section 42, which occurs in Part I,
had no application to the present case. The learned Single Judge also directed that the petition be
heard on merits. This decision is questioned by Ashapura in SLP (C) No. 3959 of 2012.
18. The learned Single Judge of the Bombay High Court has allowed Arbitration Petition No. 561 of
2009 of Eitzen for enforcing the Foreign Award dated 26.5.2009.
Print Date: August 1, 2025 Page 3 of 9 Printed for:
IBC Laws® | www.ibclaw.in
19. As a preliminary objection, it was contented before the Bombay High Court that this Court had
passed an Order on 27.2.2012 ordering status quo on further proceedings and, therefore, the
Hon’ble Court ought not to proceed in the matter. That this Order was to operate upto 16.4.2012
and was thereafter extended till 22.8.2012. The High Court rejected this contention on the ground
that the Order of status quo had not been extended. We have examined the matter and find that
there was no Order of this Court restraining the High Court from hearing the matter in October,
2015.
20. The High Court has also rejected the contention of Ashapura under Section 421 of the Arbitration
Act, rightly; that since an application under Section 34 of the Arbitration Act, which is an application
contemplated by Part I of the Arbitration Act, has been made before the Court in Gujarat and that
Court alone has jurisdiction over the Arbitration proceedings and all subsequent applications must
be made to that Court alone. This contention was rejected by the High Court on the ground that
Section 42 occurs in Part I of the Arbitration Act and in its view since Part I itself had no application
to the Foreign Award, Section 42 would have no application either. The moot question thus arises is
whether Part I of the Arbitration Act has any application to the Foreign Award in this case where the
proceedings were held in London and the Arbitration was governed by English Law.
Before this Court
21. We thus have, on the one hand, the decision of the Gujarat High Court holding that a Court in
India has jurisdiction under Section 34 to decide objections raised in respect of a Foreign Award
because Part I of the Arbitration Act is not excluded from operation in respect of a Foreign Award
and on the other, a decision of the Bombay High Court holding that Part I is excluded from operation
in case of a Foreign Award and thereupon directing enforcement of the Award. The decisions of the
Gujarat High Court are questioned by Eitzen by way of SLP (C) Nos.2210-2212/2011. The decisions
of the Bombay High Court are questioned by Ashapura by way of SLP (C) Nos.7562-7563/2016.
Interim order dated 05.10.2011 passed by the High Court of Judicature at Bombay in Notice of
Motion No. 3975 of 2009 in Arbitration Petition No. 561 of 2009 is under challenge in appeal arising
out of SLP (C) No. 3959 of 2012.
22. Apparently Ashapura had a similar dispute with Armada (Singapore) Pvt. Ltd. Armada had,
similarly filed an application for enforcement of the foreign award in its favour under Section 42 of
the Arbitration Act being Arbitration Petition Nos.1359 and 1360 of 2010 before the Bombay High
Court. Ashapura has raised similar objection to the enforcement of the Foreign Award by way of
Notice of Motion. By Notices of Motion Nos. 2390 and 2444 of 2012 Ashapura had contended that
the Bombay High Court cannot entertain the application in view of the Section 42 of the Arbitration
Act. Both these Notices of Motion were dismissed by the learned Single Judge of the Bombay High
Court. Ashapura has challenged the said dismissal by way of filing SLP Nos.….of 2016 [CC Nos.3266
and 3382 of 2013] before this Court.
23. It may be noted at the outset that since proceedings under the Sick Industrial Companies
(Special Provisions) Act, 1985 (for short, the SICA Act) are pending before the Board for Industrial
and Financial Reconstruction (BIFR), though the Bombay High Court has ordered execution of the
Award, it has held that Eitzen would not be entitled to take any step in execution of the Award or
seek any relief in violation of Section 22 of the SICA Act without permission from the BIFR.
The main question
Print Date: August 1, 2025 Page 4 of 9 Printed for:
IBC Laws® | www.ibclaw.in
24. Thus, the main question on which contentions were advanced by the learned counsel for the
parties is whether Part I of the Arbitration Act is excluded from its operation in case of a Foreign
Award where the Arbitration is not held in India and is governed by foreign law.
25. Shri Prashant S. Pratap, learned senior counsel appearing for Eitzen submitted that the main
issue is covered by a decision of this Court in Bhatia International v. Bulk Trading S.A. and
another2 and two recent decisions of this Court in Union of India v. Reliance Industries Limited
and others3 and Harmony Innovation Shipping Limited v. Gupta Coal India Limited and
another4. We have not considered the decision in the Balco v. Kaiser Aluminium Technical
Services Inc.5 since the decision in that case does not govern Arbitration agreements entered prior
to 6.9.2012 and the contract in the instant case is dated 18.1.2008.
26. According to the learned counsel, Clause 28, which is the Arbitration Clause in the Contract,
clearly stipulates that any dispute under the Contract “is to be settled and referred to Arbitration in
London”. It further stipulates that English Law to apply. The parties have thus clearly intended that
the Arbitration will be conducted in accordance with English Law and the seat of the Arbitration will
be at London.
27. The question is whether the above stipulations show the intention of the parties to expressly or
impliedly exclude the provisions of Part I to the Arbitration, which was to be held outside India, i.e.,
in London. We think that the clause evinces such an intention by providing that the English Law will
apply to the Arbitration. The clause expressly provides that Indian Law or any other law will not
apply by positing that English Law will apply. The intention is that English Law will apply to the
resolution of any dispute arising under the law. This means that English Law will apply to the
conduct of the Arbitration. It must also follow that any objection to the conduct of the Arbitration or
the Award will also be governed by English Law. Clearly, this implies that the challenge to the
Award must be in accordance with English Law. There is thus an express exclusion of the
applicability of Part I to the instant Arbitration by Clause 28. In fact, Clause 28 deals with not only
the seat of Arbitration but also provides that there shall be two Arbitrators, one appointed by the
charterers and one by the owners and they shall appoint an Umpire, in case there is no agreement.
In this context, it may be noted that the Indian Arbitration and Conciliation Act, 1996 makes no
provision for Umpires and the intention is clearly to refer to an Umpire contemplated by Section 21
of the English Arbitration Act, 1996. It is thus clear that the intention is that the Arbitration should
be conducted under the English law, i.e. the English Arbitration Act, 1996. It may also be noted that
Sections 67, 68 and 69 of the English Arbitration Act provide for challenge to an Award on grounds
stated therein. The intention is thus clearly to exclude the applicability of Part I to the instant
Arbitration proceedings.
28. This is a case where two factors exclude the operation of Part I of the Arbitration Act. Firstly, the
seat of Arbitration which is in London and secondly the clause that English Law will apply. In fact,
such a situation has been held to exclude the applicability of Part I in a case where a similar clause
governed the Arbitration. In Reliance Industries Limited and another v. Union of India6, this
Court referred to judgments of some other jurisdictions and observed in paragraphs 55 to 57 as
follows:-
“55. The effect of choice of seat of arbitration was considered by the Court of Appeal in C v. D.
This judgment has been specifically approved by this Court in Balco and reiterated in Enercon.
Print Date: August 1, 2025 Page 5 of 9 Printed for:
IBC Laws® | www.ibclaw.in
In C v. D, the Court of Appeal has observed: (Bus LR p. 851, para 16)
“Primary conclusion
16. I shall deal with Mr Hirst’s arguments in due course but, in my judgment, they fail to
grapple with the central point at issue which is whether or not, by choosing London as
the seat of the arbitration, the parties must be taken to have agreed that proceedings on
the award should be only those permitted by English law. In my view they must be taken
to have so agreed for the reasons given by the Judge. The whole purpose of the balance
achieved by the Bermuda form (English arbitration but applying New York law to issues
arising under the policy) is that judicial remedies in respect of the award should be those
permitted by English law and only those so permitted. Mr Hirst could not say (and did
not say) that English judicial remedies for lack of jurisdiction on procedural
irregularities under Sections 67 and 68 of the 1996 Act were not permitted; he was
reduced to saying that New York judicial remedies were also permitted. That, however,
would be a recipe for litigation and (what is worse) confusion which cannot have been
intended by the parties. No doubt New York law has its own judicial remedies for want
of jurisdiction and serious irregularity but it could scarcely be supposed that a party
aggrieved by one part of an award could proceed in one jurisdiction and a party
aggrieved by another part of an award could proceed in another jurisdiction. Similarly,
in the case of a single complaint about an award, it could not be supposed that the
aggrieved party could complain in one jurisdiction and the satisfied party be entitled to
ask the other jurisdiction to declare its satisfaction with the award. There would be a
serious risk of parties rushing to get the first judgment or of conflicting decisions which
the parties cannot have contemplated.”
56. The aforesaid observations in C v. D were subsequently followed by the High Court of
Justice, Queen’s Bench Division, Commercial Court (England) in Sulamerica Cia Nacional de
Seguros SA v. Enesa Engelharia SA — Enesa.In laying down the same proposition, the High
Court noticed that the issue in that case depended upon the weight to be given to the provision
in Condition 12 of the insurance policy that “the seat of the arbitration shall be London,
England”. It was observed that this necessarily carried with it the English Court’s supervisory
jurisdiction over the arbitration process. It was observed that:
“this follows from the express terms of the Arbitration Act, 1996 and, in particular, the
provisions of Section 2 which provide that Part I of the Arbitration Act, 1996 applies
where the seat of the arbitration is in England and Wales or Northern Ireland. This
immediately establishes a strong connection between the arbitration agreement itself
and the law of England. It is for this reason that recent authorities have laid stress upon
the locations of the seat of the arbitration as an important factor in determining the
proper law of the arbitration agreement.”
57. In our opinion, these observations in Sulamerica case are fully applicable to the facts and
circumstances of this case. The conclusion reached by the High Court would lead to the
chaotic situation where the parties would be left rushing between India and England for
redressal of their grievances. The provisions of Part I of the Arbitration Act, 1996 (Indian) are
necessarily excluded; being wholly inconsistent with the arbitration agreement which provides
Print Date: August 1, 2025 Page 6 of 9 Printed for:
IBC Laws® | www.ibclaw.in
“that arbitration agreement shall be governed by English law”. Thus the remedy for the
respondent to challenge any award rendered in the arbitration proceedings would lie under
the relevant provisions contained in the Arbitration Act, 1996 of England and Wales. Whether
or not such an application would now be entertained by the courts in England is not for us to
examine, it would have to be examined by the court of competent jurisdiction in England.”
29. We are in agreement with the above observation and in this clause 28 in the present case must
be intended to have a similar effect that is to exclude the applicability of Part I of the Indian
Arbitration and Conciliation Act since the parties have chosen London as the seat of Arbitration and
further provided that the Arbitration shall be governed by English Law. In this case the losing side
has relentlessly resorted to apparent remedies for stalling the execution of the Award and in fact
even attempted to prevent Arbitration. This case has become typical of cases where even the fruits
of Arbitration are interminably delayed. Even though it has been settled law for quite some time that
Part I is excluded where parties choose that the seat of Arbitration is outside India and the
Arbitration should be governed by the law of a foreign country.
30. Mr. Divan attempted to persuade us to accept the possibility that Part I is not excluded and in
any case not wholly excluded in such a case, but the law is too well settled and with good reasons,
for us to take any other view. We do not wish to endorse “a recipe for litigation and (what is worse)
confusion”7).
31. When the judgment in Reliance was sought to be indirectly reviewed in another case under the
same agreement and between the same parties, this Court reiterated its earlier view and observed in
Union of India v. Reliance Industries Limited and others in para 18 as follows:-
“18. It is important to note that in para 32 of Bhatia International itself this Court has held that
Part I of the Arbitration Act, 1996 will not apply if it has been excluded either expressly or by
necessary implication. Several judgments of this Court have held that Part I is excluded by
necessary implication if it is found that on the facts of a case either the juridical seat of the
arbitration is outside India or the law governing the arbitration agreement is a law other than
Indian law. This is now well settled by a series of decisions of this Court [see Videocon
Industries Ltd. v. Union of India, Dozco India (P) Ltd. v. Doosan Infracore Co. Ltd., Yograj
Infrastructure Ltd. v. Ssang Yong Engg. and Construction Co. Ltd., the very judgment in this
case reported in Reliance Industries Ltd. v. Union of India and a recent judgment in Harmony
Innovation Shipping Ltd. v. Gupta Coal India Ltd.].”
We see no reason to take a different view. In Bhatia International’s case, this Court concluded as
follows:
“To conclude, we hold that the provisions of Part I would apply to all arbitrations and to all
proceedings relating thereto. Where such arbitration is held in India the provisions of Part I
would compulsorily apply and parties are free to deviate only to the extent permitted by the
derogable provisions of Part I. In cases of international commercial arbitrations held out of
India provisions of Part I would apply unless the parties by agreement, express or implied,
exclude all or any of its provisions. In that case the laws or rules chosen by the parties would
prevail. Any provision, in Part I, which is contrary to or excluded by that law or rules will not
apply.”
Print Date: August 1, 2025 Page 7 of 9 Printed for:
IBC Laws® | www.ibclaw.in
32. We are thus of the view that by Clause 28, the parties chose to exclude the application of Part I
to the Arbitration proceedings between them by choosing London as the venue for Arbitration and
by making English law applicable to Arbitration, as observed earlier. It is too well settled by now
that where the parties choose a juridical seat of Arbitration outside India and provide that the law
which governs Arbitration will be a law other than Indian law, part I of the Act would not have any
application and, therefore, the award debtor would not be entitled to challenge the award by raising
objections under Section 34 before a Court in India. A Court in India could not have jurisdiction to
entertain such objections under Section 34 in such a case.
33. As a matter of fact the mere choosing of the juridical seat of Arbitration attracts the law
applicable to such location. In other words it would not be necessary to specify which law would
apply to the Arbitration proceedings, since the law of the particular country would apply ipso jure.
The following passage from Redfern and Hunter on International Arbitration contains the following
explication of the issue:-
“It is also sometimes said that parties have selected the procedural law that will govern their
arbitration, by providing for arbitration in a particular country. This is too elliptical and, as an
English court itself held more recently in Breas of Doune Wind Farm it does not always hold
true. What the parties have done is to choose a place of arbitration in a particular country.
That choice brings with it submission to the laws of that country, including any mandatory
provisions of its law on arbitration. To say that the parties have ‘chosen’ that particular law to
govern the arbitration is rather like saying that an English woman who takes her car to France
has ‘chosen’ French traffic law, which will oblige her to drive on the right-hand side of the
road, to give priority to vehicles approaching from the right, and generally to obey traffic laws
to which she may not be accustomed. But it would be an odd use of language to say this
notional motorist had opted for ‘French traffic law’. What she has done is to choose to go to
France. The applicability of French law then follows automatically. It is not a matter of choice.
Parties may well choose a particular place of arbitration precisely because its lex arbitri is one
which they find attractive. Nevertheless, once a place of arbitration has been chosen, it brings
with it its own law. If that law contains provisions that are mandatory so far as arbitration are
concerned, those provisions must be obeyed. It is not a matter of choice any more than the
notional motorist is free to choose which local traffic laws to obey and which to disregard.”
34. In this view of the matter, the judgment of the Gujarat High Court holding that Ashapura’s
objections under Section 34 of the Arbitration Act are tenable before a Court in India that is the
Court at Jam-Khambalia, Gujarat is contrary to law. The proceedings under Section 34, which occurs
in Part I, are liable to be dismissed as untenable. The Civil Appeals of Eitzen are liable to succeed
and are, therefore, allowed. The judgment of the Bombay High Court dated 03.12.2015 enforcing the
Foreign Award under Part II of the Arbitration Act is correct and liable to be upheld.
35. In view of the above findings, appeals filed by Eitzen Bulk A/S, arising out of SLP (C) Nos.
2210-2212 of 2011 are allowed; appeals filed by Ashapura Minechem Ltd., arising out of SLP (C)
Nos. 7562-7563 of 2016 are dismissed; appeal arising out of SLP (C) No. 3959 of 2012 (filed by
Ashapura Minechem Ltd.) is dismissed.
36. Permission to file SLP (C) No.…of 2016 [CC No. 3266 of 2013 – filed by Ashapura Minechem
Ltd.] and SLP (C) No….of 2016 [CC No. 3382 of 2013 – filed by Ashapura Minechem Ltd.] is rejected.
Print Date: August 1, 2025 Page 8 of 9 Printed for:
IBC Laws® | www.ibclaw.in
No costs.
………………………………….……………….………….…..J.
[FAKKIR MOHAMED IBRAHIM KALIFULLA]
………………………………………………………..………J.
[S.A. BOBDE]
NEW DELHI,
MAY 13, 2016
----
–––
Disclaimer: While every effort is made to avoid any mistake or omission, this document including case-
summary/brief about the decision/ add. info/headnote/ judgment/order/ act/ rule/ regulation/ circular/
notification is being circulated on the condition and understanding that the publisher would not be liable
in any manner by reason of any mistake or omission or for any action taken or omitted to be taken or
advice rendered or accepted on the basis of this document. The authenticity of this text must be verified
from the original source. Read more here.
References:
1. Notwithstanding anything contained elsewhere in this Part or in any other law for the time
being in force, where with respect to an arbitration agreement any application under this Part
has been made in a Court, that Court alone shall have jurisdiction over the arbitral
proceedings and all subsequent applications arising out of that agreement and the arbitral
proceedings shall be made in that Court and in no other Court.[↩]
2. (2002) 4 SCC 105[↩]
3. (2015) 10 SCC 213[↩]
4. (2015) 9 SCC 172[↩]
5. (2012) 9 SCC 552[↩]
6. 2014 (7) SCC 603[↩]
7. C vs. D (2008 Bus LR 843[↩]
Print Date: August 1, 2025 Page 9 of 9 Printed for: