Corrigendum5 RevTCS123

The document outlines the conceptual scheme for hillside slope protection measures at NH 66 near Cortalim, Goa, focusing on landslide mitigation. It includes details on ground improvement measures, reinforced soil structures, drainage systems, and geosynthetics for erosion control. The drawings are not for construction and are intended for planning purposes only.

Uploaded by

himanshjain40
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
21 views4 pages

Corrigendum5 RevTCS123

The document outlines the conceptual scheme for hillside slope protection measures at NH 66 near Cortalim, Goa, focusing on landslide mitigation. It includes details on ground improvement measures, reinforced soil structures, drainage systems, and geosynthetics for erosion control. The drawings are not for construction and are intended for planning purposes only.

Uploaded by

himanshjain40
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Note:-Ground improvement measures shall be carried out as per recommendations

Geosynthetics Erosion Control


of the Geotechnical Investigation Report, wherever necessary. Mat with Hydroseeding
Toe Drain

U-Pin

2
Subsurface drain PVC
pipe wrapped with non 1
wowen geotextile
Backfill
Reinforced soil wall
(Gabion fascia mesh size
10x12, 2.7/3.7 mm wire ø, Toe Drain
ZINC+PVC coated) Non-woven Geotextile

0.08(Typ.)

Detail- A
Structural Fill

H BIS Certified High
Strength Geogrid Drainage
Composite

Toe Drain Detail- B

Min. 1.0m
Embedment 100mm Thick PCC In-Situ Strata

TYPICAL CROSS SECTION OF REINFORCED SOIL STRUCTURE

Drawing Title:
LAND SLIDE MITIGATION AT CORTALIM GOA Client: PWD GOA Drawing No: SHEET 1 OF 3

Project:-
CONCEPTUAL SCHEME ONLY HILL SIDE SLOPE PROTECTION MEASURES AT NH 66 NEAR CORTALIM (SANTRANT
Date: 30-05-2025 N.T.S
NOT FOR CONSTRUCTION SLOPE AND FERRY POINT) IN THE STATE OF GOA
Note:-Ground improvement measures shall be carried out as per recommendations
Geosynthetics Erosion Control
of the Geotechnical Investigation Report, wherever necessary. Mat with Hydroseeding
Toe Drain

U-Pin

2
Subsurface drain PVC
pipe wrapped with non 1
wowen geotextile
Backfill
Reinforced soil wall
(Gabion fascia mesh size
10x12, 2.7/3.7 mm wire ø, Toe Drain
ZINC+PVC coated)
Non-woven Geotextile
0.08(Typ.)
H1

Berm
Structural Fill


Detail- A Drainage
Composite
BIS Certified High
Strength Geogrid
H

Toe Drain
Detail- B

In-Situ Strata
Min. 1.0m
Embedment 100mm Thick PCC

TYPICAL CROSS SECTION OF REINFORCED SOIL STRUCTURE

Drawing Title:
LAND SLIDE MITIGATION AT CORTALIM GOA Client: PWD GOA Drawing No: SHEET 2 OF 3

Project:-
CONCEPTUAL SCHEME ONLY HILL SIDE SLOPE PROTECTION MEASURES AT NH 66 NEAR CORTALIM (SANTRANT
Date: 30-05-2025 N.T.S
NOT FOR CONSTRUCTION SLOPE AND FERRY POINT) IN THE STATE OF GOA
Gabion
1.0
Non woven geotextile

0.08
(Typ.) Geogrid
Primary Reinforcement
( Length As Per Design )

12mm dia connector rod

DETAIL-A

Draining core
0.75 Non Woven Geotextile on
both sides
0.54
0.10
0.40 Transverse Half Perforated PVC Pipe
160mm Ø Wrapped With Geotextile 2%
0.34 Slope @ 10m C/c
Longitudinal Half Perforated PVC Pipe
0.50
160mm Ø Wrapped With Non Woven
DETAIL OF TOE DRAIN Geotextile
DETAIL-B

Drawing Title:
TYPICAL DETAIL Client: PWD GOA Drawing No: SHEET 3 OF 3

Project:-
CONCEPTUAL SCHEME ONLY HILL SIDE SLOPE PROTECTION MEASURES AT NH 66 NEAR CORTALIM (SANTRANT
Date: 30-05-2025 N.T.S
NOT FOR CONSTRUCTION SLOPE AND FERRY POINT) IN THE STATE OF GOA