Practical Assessment for Building Technician

The document outlines a practical assessment for Building Technician Level 4, requiring candidates to construct a single Flemish brick wall according to provided drawings within a 3-hour timeframe. It includes instructions, resources available for the task, and an observation checklist for evaluating candidates' performance on various criteria. Candidates must achieve a minimum score of 50% to be deemed competent.

Uploaded by

andrew ratemo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
91 views5 pages

Practical Assessment for Building Technician

The document outlines a practical assessment for Building Technician Level 4, requiring candidates to construct a single Flemish brick wall according to provided drawings within a 3-hour timeframe. It includes instructions, resources available for the task, and an observation checklist for evaluating candidates' performance on various criteria. Candidates must achieve a minimum score of 50% to be deemed competent.

Uploaded by

andrew ratemo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

©2024 TVET CDACC

073206T4BLD
BUILDING TECHNICIAN LEVEL 4

CON/OS/BUT/CR/06/4/A
Execute Superstructure Works

PRACTICAL ASSESSMENT

Time: 3 HOURS

INSTRUCTIONS TO CANDIDATE:
1. You are required to perform the following task:
i. Construct a single Flemish brick wall as per working drawing.

Page 1 of 6
©2024 TVET CDACC

2. You are allowed to engage one helper who is NOT a candidate per two (2) candidates
during the practical assessment.
3. You have been provided with the following resources for the practical tasks:
 Trowel
 Straight edge
 Spirit level
 Plumb bob
 Spade
 Builders line
 Tape measure
 Bricks (225 mm x 110 mm x 75 mm)
 Lime
 Water

073205T4BLD
Page 1 of 6
©2024 TVET CDACC

BUILDING TECHNICIAN LEVEL 4

CON/OS/BUT/CR/03/4/A
Perform superstructure works March
2025

OBSERVATION CHECKLIST
Candidate’s name & Registration Code
Assessor’s name & Registration Code
Venue of Assessment
Date of assessment
Items to be evaluated: Please award marks as Marks Marks
Comments
appropriate. Give a brief comment on your observation. available obtained

1. Donned Personal protective gears according to Standard 2


Operating Procedures (dustcoat, safety boots)
(Award 2 marks)
2. Correctly interpreted the drawings. 3
(Award 3 marks for correct interpretation

3. Laid and constructed 5 courses correctly 10


(Award 2 marks for each correctly laid course.)

Page 2 of 6
©2024 TVET CDACC

4. Plastered the inner face 3


(Award 3 marks for correct execution of task)
5. Keyed horizontal joints. 3
(Award 3 marks for correct execution of task)
6. Flush vertical joints 3
(Award 3 marks for correct execution of task)
Sub Total 24

PRODUCT CHECKLIST

7. Dimensions 10
 1955
 1655
 225
 875
 230
 450
 115
 25
 1630
 1400

8. Horizontal level 3
(Award any 3 points x 1 mark each)
9. Vertical level 3
(Award any 3 points x 1 mark each)

10. Straightness 2
(Award any 2 sides x 1 mark each)
11. Squareness 3
(Award any 3 corners x 1 mark each)

Page 3 of 6
©2024 TVET CDACC

12. Appearance 2
(Award 2 marks for a good general appearance)
13. Completion 3
(Award 1 mark for 50% complete,
2 marks for 50-75% complete,
3 marks for above 75% complete)
Sub Total 26

TOTAL 50

The candidate was found to be:


Competent Not yet competent
(Please tick as appropriate)
(The candidate is competent if the candidate obtains at least 50%)
Feedback from candidate:

Feedback to candidate:

Candidate’s Signature Date

------------------------------ -----------------------------

Assessor’s Signature Date

------------------------------ -----------------------------

Page 4 of 6