ASSIGNMENT 1 SOLUTION
TIS COURSE
PREMASTER’S YEAR
PREPARED BY : [Link] YASSER IBRAHIM
Table of Contents
1-Intersections LOS Criteria ..................................................................................... 3
1-1-TWSC LOS Criteria: .............................................................................................. 3
1-2-Signalized Intersections LOS Criteria: ................................................................... 3
2-Sheet Questions ................................................................................................... 4
3-Existing Condition ................................................................................................. 5
3-1-Intersection 1: ..................................................................................................... 5
3-2- Intersection 2: .................................................................................................... 7
3-3-1- Intersection 3 (Before Optimization): ................................................................. 9
3-3-2-Intersection 3 (After Optimization): .................................................................... 9
3-4-1- Intersection 4 (Before Optimization): ............................................................... 10
3-4-2- Intersection 4 (After Optimization): .................................................................. 10
4-Horizon Year Before Project ................................................................................. 11
4-1-Intersection 1: ................................................................................................... 11
4-2- Intersection 2: .................................................................................................. 13
4-3- Intersection 3: .................................................................................................. 15
4-4- Intersection 4: .................................................................................................. 15
5-Trip Generation ................................................................................................... 16
6-Trip Distribution .................................................................................................. 17
7-Horizon Year After Project ................................................................................... 18
7-1- Intersection 1: .................................................................................................. 18
7-2- Intersection 2: .................................................................................................. 20
7-3- Intersection 3: .................................................................................................. 22
7-4- Intersection 4: .................................................................................................. 22
8-Project Entrance & Exit Analysis........................................................................... 23
9-Check of Warrants for Unsignalized Intersections ................................................ 25
9-1-Check of Intersection 1: ................................................................................ 27
9-1-1- Warrant 3: .................................................................................................. 27
9-1-2- Warrant 4: .................................................................................................. 28
9-1-3- Warrant 6: .................................................................................................. 28
9-2- Check of Intersection 2: ................................................................................ 29
9-2-1- Warrant 3: .................................................................................................. 29
9-2-2- Warrant 4: .................................................................................................. 29
9-2-3- Warrant 6: .................................................................................................. 30
10-Proposed Signal Plans of the Network ................................................................ 31
10-1- Network Layout: .............................................................................................. 31
10-2- Intersection 1 Summary:.................................................................................. 32
10-3- Intersection 2 Summary:.................................................................................. 33
10-4- Intersection 3 Summary:.................................................................................. 34
10-5- Intersection 4 Summary:.................................................................................. 35
11-Recommendations & Suggestions ...................................................................... 36
1-Intersections LOS Criteria
1-1-TWSC LOS Criteria:
1-2-Signalized Intersections LOS Criteria:
2-Sheet Questions
3-Existing Condition
3-1-Intersection 1:
Intersection LOS: A
3-2- Intersection 2:
Intersection LOS: B
3-3-1- Intersection 3 (Before Optimization):
3-3-2-Intersection 3 (After Optimization):
3-4-1- Intersection 4 (Before Optimization):
3-4-2- Intersection 4 (After Optimization):
4-Horizon Year Before Project
4-1-Intersection 1:
Intersection LOS: C
4-2- Intersection 2:
Intersection LOS: D
4-3- Intersection 3:
4-4- Intersection 4:
5-Trip Generation
Adjusted Volume = Unadjusted Volume * Public Transit Reduction Factor
Total Trips = 255 * 0.65 = 166 Trips
Production Trips = 135 * 0.65 = 88 Trips
Attraction Trips = 120 * 0.65 = 78 Trips
6-Trip Distribution
7-Horizon Year After Project
7-1- Intersection 1:
Intersection LOS: C
7-2- Intersection 2:
Intersection LOS: D
7-3- Intersection 3:
7-4- Intersection 4:
8-Project Entrance & Exit Analysis
Intersection LOS: A
9-Check of Warrants for Unsignalized Intersections
9-1-Check of Intersection 1:
9-1-1- Warrant 3:
Condition A (1): Total Stopped Time Delay of Minor WB = 753.1*25 + 255.2*19 + 11*43 =
24149.3 sec = 6.7 Hour < 5 hr
Condition A (2): Volume on the Same Minor St Approach = 87 vph > 150 vph
So, Condition A Is Not Met
Condition B:
Total Major = 2067 vph
High Minor = 87 vph > 150 vph So, Condition B Is Not Met
Warrant 3 Is Not Met
9-1-2- Warrant 4:
Total Major = 2067 vph
Total Pedestrians Crossing Major = 68 ped/hr > 133 ped/hr
Warrant 4 Is Not Met
9-1-3- Warrant 6:
Installing A Traffic Signal Will Provide Progressive Operation Between Intersection 1
and Intersection 4
D1-4 = 492 m < 300 m (1000 ft)
Warrant 6 Is Met
9-2- Check of Intersection 2:
9-2-1- Warrant 3:
Condition A (1): Total Stopped Time Delay of Minor EB = 807.5*19 + 748.7*11 + 105.9*68 =
30779.4 = 8.5 Hour < 5 hr
Condition A (2): Volume on the Same Minor St Approach = 98 vph > 150 vph
So, Condition A Is Not Met
Condition B:
Total Major = 2235 vph
High Minor = 98 vph > 150 vph So, Condition B Is Not Met
Warrant 3 Is Not Met
9-2-2- Warrant 4:
Total Major = 2235 vph
Total Pedestrians Crossing Major = 103 ped/hr > 133 ped/hr
Warrant 4 Is Not Met
9-2-3- Warrant 6:
Installing A Traffic Signal Will Provide Progressive Operation Between
Intersection 2 and Intersection 3
D2-3 = 328 m < 300 m (1000 ft)
Warrant 6 Is Met
10-Proposed Signal Plans of the Network
10-1- Network Layout:
Intersection 4
Intersection 1
Intersection 2
Intersection 3
10-2- Intersection 1 Summary:
10-3- Intersection 2 Summary:
10-4- Intersection 3 Summary:
10-5- Intersection 4 Summary:
11-Recommendations & Suggestions
• Implementation of Optimized Signal Timing plan of 4
Intersections to reduce Delay and improve Mobility for Entire
Network
• Provide one More Entrance & Exit For the project Between
Intersections 2&3 or Between Intersections 1&4 to reduce
Traffic volumes on Intersections 1&2, and to Improve the
Accessibility of the Project
• Provide Sufficient Acceleration and Deceleration Lanes for The
Entrance & Exit of the Project
• Provide traffic Signs and pavement Markings for all
intersections and Roads to ensure Traffic Safety for entire
Network
• Provide adequate Number of Parking Spaces for the Project to
cover the Parking Demand