RESOURCES & PRODUCTIVITY DETAILS
Sewerage Works
Productivity
Activity Description Resources 0-3m 3-6m
Excavate - Pipeline Labour - 2, Ganger - 0.50, Excavator - 1 120 m/day 60 m/day
Labour - 5,Ganger - 0.50,Pipe Fitter - 1,Boom Loader - 0.25,
Lay Pipeline 120 m/day 75 m/day
Truck - 0.2, Hiab - 0.25, Wheel Loader - 0.10
Labour - 4,Ganger - 0.25,Pipe Fitter - 1,Boom Loader - 0.25,
Initial Backfilling & Testing 75 m/day 40 m/day
Truck - 0.25, Water Tanker - 0.30, Wheel Loader - 0.10
Labour - 6,Ganger - 0.50,Water tanker - 0.50,Truck - 0.25,
Final Backfilling 75 m/day 40 m/day
Wheel Loader - 0.25,Skid Loader - 1,Hand Roller - 1,Plate Compactor - 2
Labour - 6,Ganger - 0.25,Mason - 2,Carpenter - 2,
Manhole/Chambers 1.00 nr/day 1.00 nr/day
Steel Fixer - 2,Hiab - 0.25,Excavator - 0.25
Excavate HC pipeline Labour - 2,Ganger - 0.50,JCB - 1, Plate Compactor - 0.25 100 m/day
Lay House connection pipeline Labour - 2,Ganger - 0.25,Pipe Fitter - 1 100 m/day
Labour - 2,Ganger - 0.50,Skid Loader - 0.25,
Backfill HC pipeline 75 m/day
Water Tanker - 0.125,Plate Compactor - 1
House Connection Chambers Labour - 2,Carpenter - 1,Mason - 1,Pipe Fitter - 0.5,JCB - 0.25, Hiab - 0.25 5 nr/day
Install Dewatering Labour - 2,Ganger - 0.5,Dewatering Pump - 2 120 m/day
S & PRODUCTIVITY DETAILS
Productivity
6-9m 9 - 12 m
25 m/day 8 m/day
40 m/day 8 m/day
35 m/day 8 m/day
35 m/day 8 m/day
1.00 nr/day 0.25 nr/day
RESOURCES & PRODUCTIVITY DETAILS
RESOURCES & PRODUCTIVITY DETAILS
Drainage Works
Productivity
Activity Description Resources
0-3m 3-6m
Excavate - Pipeline Labour - 2,Ganger - 0.50,Excavator - 1 120 m/day 60 m/day
Labour - 5,Ganger - 0.50,Pipe Fitter - 1,Boom Loader - 0.25,
Lay Pipeline 120 m/day 75 m/day
Truck - 0.2, Hiab - 0.25, Wheel Loader - 0.10
Labour - 4,Ganger - 0.25,Pipe Fitter - 1,Boom Loader - 0.25,
Initial Backfilling & Testing 75 m/day 40 m/day
Truck - 0.25, Water Tanker - 0.3, Wheel Loader - 0.10
Labour - 6,Ganger - 0.50,Water tanker - 0.50,Truck - 0.25,
Final Backfilling 75 m/day 40 m/day
Wheel Loader - 0.25,Skid Loader - 1,Hand Roller - 1,Plate Compactor - 2
Labour - 6,Ganger - 0.25,Mason - 2,Carpenter - 2,
Manhole/Chambers 1.00 nr/day 1.00 nr/day
Steel Fixer - 2,Hiab - 0.25,Excavator - 0.25
Excavate pipeline Labour - 2,Ganger - 0.50,JCB - 1, Plate Compactor - 0.25 100 m/day
Lay Gully pipeline Labour - 2,Ganger - 0.25,Pipe Fitter - 1 100 m/day
Labour - 2,Ganger - 0.50,Skid Loader - 0.25,
Backfill Gully pipeline 75 m/day
Water Tanker - 0.125,Plate Compactor - 1
Gullies Labour - 4,Carpenter - 2,Mason - 2,Pipe Fitter - 1, Hiab - 0.50, JCB - 0.50 5 nr/day
Install Dewatering Labour - 2,Ganger - 0.5,Dewatering Pump - 2 120 m/day
S & PRODUCTIVITY DETAILS
S & PRODUCTIVITY DETAILS
Productivity
6-9m 9 - 12 m
25 m/day 8 m/day
40 m/day 8 m/day
35 m/day 8 m/day
35 m/day 8 m/day
1.00 nr/day 0.25 nr/day
RESOURCES & PRODUCTIVITY DETAILS
RESOURCES & PRODUCTIVITY DETAILS
Irrigation Works
Productivity
Activity Description Resources
0-3
Excavate - Pipeline Labour - 3,Ganger - 0.75,Excavator - 1.50 200 m/day
Labour - 7,Ganger - 0.70,Pipe Fitter - 1.50,Boom Loader - 0.375,
Lay Pipeline 200 m/day
Truck - 0.30, Hiab - 0.375, Wheel Loader - 0.10
Labour - 6,Ganger - 0.375,Pipe Fitter - 1.50,Boom Loader - 0.375,
Initial Backfilling 200 m/day
Truck - 0.375, Water Tanker - 0.45, Wheel Loader - 0.10
Pressure Testing Labour - 2,Ganger - 0.25,Pipe Fitter - 1, Air Compressor - 0.1 200 m/day
Concrete thrust blocks Labour - 2,Ganger - 0.25,Carpenter - 2,Mason - 2 4 nr/day
Labour - 9,Ganger - 0.75,Water tanker - 0.75,Truck - 0.375,
Final Backfilling Wheel Loader - 0.375,Skid Loader - 1.50,Hand Roller - 1.50,Plate Compactor - 150 m/day
3
Irrigation Valve Chambers/ Labour - 5,Ganger - 0.30,Mason - 1,Carpenter - 1,
1.00 nr/day
Air valve chambers Steel Fixer - 1.3,Pipe Fitter - 0.30,Hiab - 0.30,Back Hoe Loader - 0.30
Installation of Fire Hydrants Labour - 2,Pipe Fitter - 0.50,JCB - 0.10,Hiab - 0.25 1 nr/day
S & PRODUCTIVITY DETAILS
S & PRODUCTIVITY DETAILS
Productivity
RESOURCES & PRODUCTIVITY DETAILS
RESOURCES & PRODUCTIVITY DETAILS
Firefighting Works
Productivity
Activity Description Resources
0-3
Excavate - Pipeline Labour - 3,Ganger - 0.75,Excavator - 1.50 200 m/day
Labour - 7,Ganger - 0.70,Pipe Fitter - 1.50,Boom Loader - 0.375,
Lay Pipeline 200 m/day
Truck - 0.30, Hiab - 0.375, Wheel Loader - 0.10
Labour - 6,Ganger - 0.375,Pipe Fitter - 1.50,Boom Loader - 0.375,
Initial Backfilling 200 m/day
Truck - 0.375, Water Tanker - 0.45, Wheel Loader - 0.10
Pressure Testing Labour - 2,Ganger - 0.25,Pipe Fitter - 1, Air Compressor - 0.1 200 m/day
Concrete thrust blocks Labour - 2,Ganger - 0.25,Carpenter - 2,Mason - 2 4 nr/day
Labour - 9,Ganger - 0.75,Water tanker - 0.75,Truck - 0.375,
Final Backfilling Wheel Loader - 0.375,Skid Loader - 1.50,Hand Roller - 1.50,Plate Compactor - 150 m/day
3
Irrigation Valve Chambers/ Labour - 5,Ganger - 0.30,Mason - 1,Carpenter - 1,
1.00 nr/day
Air valve chambers Steel Fixer - 1.3,Pipe Fitter - 0.30,Hiab - 0.30,Back Hoe Loader - 0.30
Installation of Fire Hydrants Labour - 2,Pipe Fitter - 0.50,JCB - 0.10,Hiab - 0.25 1 nr/day
S & PRODUCTIVITY DETAILS
S & PRODUCTIVITY DETAILS
Productivity
RESOURCES & PRODUCTIVITY DETAILS
RESOURCES & PRODUCTIVITY DETAILS
Water Works
Productivity
Activity Description Resources
0-3
Excavate - Pipeline Labour - 4,Ganger - 1,Excavator - 2 200 m/day
Labour - 10,Ganger - 1,Pipe Fitter - 2,Boom Loader - 0.50,
Lay Pipeline 200 m/day
Truck - 0.40, Hiab - 0.50, Wheel Loader - 0.10
Labour - 8,Ganger - 0.50,Pipe Fitter - 2,Boom Loader - 0.50,
Initial Backfilling 200 m/day
Truck - 0.50, Water Tanker - 0.60, Wheel Loader - 0.10
Pressure Testing Labour - 2,Ganger - 0.25,Pipe Fitter - 1, Air Compressor 200 m/day
Concrete thrust blocks Labour - 2,Ganger - 0.25,Carpenter - 2,Mason - 2 6 nr/day
Labour - 9,Ganger - 1,Water tanker - 1,Truck - 0.50,
Final Backfilling 150 m/day
Wheel Loader - 0.50,Skid Loader - 2,Hand Roller - 2,Plate Compactor - 4
Water Valve Chambers/ Labour - 6,Ganger - 0.38,Mason - 1.5,Carpenter - 1.5,
1.00 nr/day
Air valve chambers Steel Fixer - 1.5,Pipe Fitter - 0.38,Hiab - 0.19,Back Hoe Loader - 0.38
S & PRODUCTIVITY DETAILS
S & PRODUCTIVITY DETAILS
Productivity
RESOURCES & PRODUCTIVITY DETAILS
Telecommunication Works
Productivity
Activity Description Resources
0-3
Excavate - Telecommunication Ducts Labour - 2,Ganger - 0.50,Back Hoe Loader - 1 150 m/day
Lay Joint core cable ducts Labour - 4,Ganger - 0.25,Pipe Fitter - 1,Hiab - 0.25 150 m/day
Labour - 4,Ganger - 0.25,Skid Loader - 0.25,
Selected excavated surround/
Water Tanker - 0.25,Wheel loader - 0.25, 150 m/day
mass concrete surround
Hand roller - 0.50,Plate Compactor - 1
Labour - 6,Ganger - 0.375,Carpenter - 1,Mason - 2.80,
Manholes & Junction Boxes 1.00 nr/day
Steel Fixer - 2.80,Hiab - 0.375
S & PRODUCTIVITY DETAILS
Productivity
RESOURCES & PRODUCTIVITY DETAILS
RESOURCES & PRODUCTIVITY DETAILS
Road Works
Activity Description Resources Productivity
Labour - 3,Ganger - 1,Dozer - 1 ,Grader - 1.10, Wheel
Earthworks 1000 m3
Loader - 1,Vibratory Roller - 1.10, Truck - 2,Water tanker - 3
Labour - 2,Ganger - 0.50,Grader - 1,Vibratory Roller - 1,
Subbase 2000 m2 200 m3
Water Tanker - 0.50,Truck - 2
Labour - 4,Ganger - 0.25,Mason - 2,Carpenter - 2,
Kerbs 100 m ( 2 teams) Total = 200m
Hiab - 0.25,Truck - 0.1,Plate Compactor - 0.25.
Labour - 2,Ganger - 0.5,Grader - 1,Vibratory Roller - 1,
Road base 2000 m2 201 m3
Water Tanker - 0.5,Truck - 2,Wheel Loader - 0.5,
Asphalt Labour - 8,Ganger - 1,Paver - 2,Tandem Roller - 1,
Asphalt - Base Course Water Tanker - 1,Skid Loader - 0.5,PTR - 3, 2000 m2 600 ton
Asphalt Truck - 3,Hand roller - 0.5
Asphalt Labour - 8,Ganger - 1,Paver - 2,Tandem Roller - 1,
Asphalt - Wearing Course Water Tanker - 1,Skid Loader - 0.5,PTR - 3, 2000 m2 600 ton
Asphalt Truck - 3,Hand roller - 0.5
Labour - 12,Mason - 6,Ganger - 1.0,Hiab - 0.3
Interlock Tiles 300 m2
Truck - 0.30,Skid Loader - 0.75,Plate Compactor - 1.5
S & PRODUCTIVITY DETAILS
S & PRODUCTIVITY DETAILS
Productivity
( 2 teams) Total = 200m
RESOURCES & PRODUCTIVITY DETAILS
RESOURCES & PRODUCTIVITY DETAILS
Electrical Works
Productivity
Activity Description Resources
0-3
Excavation Labour - 3,Ganger - 0.30,JCB - 1 300 m/day
Cable Laying Labour - 3,Ganger - 0.30,JCB - 0.10,Electrician - 1 300 m/day
Backfilling Labour - 2,Ganger - 0.20,JCB - 0.50,Water tanker - 0.25, Plate Compactor - 1 150 m/day
S & PRODUCTIVITY DETAILS
S & PRODUCTIVITY DETAILS
Productivity
RESOURCES & PRODUCTIVITY DETAILS
Street Lighting Works
Productivity
Activity Description Resources
0-3
Excavation Labour - 3,Ganger - 0.30,JCB - 1 200 m/day
Cable Laying Labour - 3,Ganger - 0.30,Electrician - 1 200 m/day
Labour - 2,Ganger - 0.20,JCB - 0.50,Water tanker - 0.25, Plate Compactor - 1,
Backfilling 200 m/day
Back Hoe Loader - 0.50
Labour - 3,Ganger - 0.50,Carpenter - 1,Mason - 1,
Street Lighting Foundation 15 nr/day
Steel Fixer - 1,JCB - 0.5,Water Tanker - 0.25,Hiab - 0.25
Street Lighting Columns Labour - 1.50,Ganger - 0.50,Hiab - 0.25,Truck - 0.50, Crane - 0.50 15 nr/day
Install new lighting luminaries Labour - 3,Electrician - 1.50,Crane - 0.275 15 nr/day
Labour - 1,Ganger - 0.25,Carpenter - 0.25,Mason - 0.50,
Street Lighting Feeder Pillar 1 nr/day
JCB - 0.10,Hiab - 0.25.
S & PRODUCTIVITY DETAILS
Productivity
RESOURCES & PRODUCTIVITY DETAILS
RESOURCES & PRODUCTIVITY DETAILS
Duct Crossing Works
Productivity
Activity Description Resources
0-3
Labour - 6,Ganger - 1,Pipe Fitter - 2,JCB - 1,
Excavate,Lay & Backfill Road crossings ducts Wheel Loader - 0.5,Water Tanker - 0.5,Skid Loader - 0.5, 50 m/day
Plate Compactor - 1. Back hoe Loader - 1.00
S & PRODUCTIVITY DETAILS
S & PRODUCTIVITY DETAILS
Productivity
RESOURCES & PRODUCTIVITY DETAILS
Final Works
Productivity
Activity Description Resources
0-3
Chlorination & Bacterial test Labour - 2,Ganger - 0.25 100 m/day
Inspection & Handover Labour - 2,Ganger - 0.20,Pipe Fitter - 0.50
S & PRODUCTIVITY DETAILS
Productivity