0% found this document useful (0 votes)
22 views36 pages

Sewerage and Drainage Productivity Metrics

Uploaded by

Khaled Youssef
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views36 pages

Sewerage and Drainage Productivity Metrics

Uploaded by

Khaled Youssef
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

RESOURCES & PRODUCTIVITY DETAILS

Sewerage Works

Productivity
Activity Description Resources 0-3m 3-6m
Excavate - Pipeline Labour - 2, Ganger - 0.50, Excavator - 1 120 m/day 60 m/day
Labour - 5,Ganger - 0.50,Pipe Fitter - 1,Boom Loader - 0.25,
Lay Pipeline 120 m/day 75 m/day
Truck - 0.2, Hiab - 0.25, Wheel Loader - 0.10
Labour - 4,Ganger - 0.25,Pipe Fitter - 1,Boom Loader - 0.25,
Initial Backfilling & Testing 75 m/day 40 m/day
Truck - 0.25, Water Tanker - 0.30, Wheel Loader - 0.10

Labour - 6,Ganger - 0.50,Water tanker - 0.50,Truck - 0.25,


Final Backfilling 75 m/day 40 m/day
Wheel Loader - 0.25,Skid Loader - 1,Hand Roller - 1,Plate Compactor - 2

Labour - 6,Ganger - 0.25,Mason - 2,Carpenter - 2,


Manhole/Chambers 1.00 nr/day 1.00 nr/day
Steel Fixer - 2,Hiab - 0.25,Excavator - 0.25

Excavate HC pipeline Labour - 2,Ganger - 0.50,JCB - 1, Plate Compactor - 0.25 100 m/day

Lay House connection pipeline Labour - 2,Ganger - 0.25,Pipe Fitter - 1 100 m/day
Labour - 2,Ganger - 0.50,Skid Loader - 0.25,
Backfill HC pipeline 75 m/day
Water Tanker - 0.125,Plate Compactor - 1
House Connection Chambers Labour - 2,Carpenter - 1,Mason - 1,Pipe Fitter - 0.5,JCB - 0.25, Hiab - 0.25 5 nr/day

Install Dewatering Labour - 2,Ganger - 0.5,Dewatering Pump - 2 120 m/day


S & PRODUCTIVITY DETAILS

Productivity
6-9m 9 - 12 m
25 m/day 8 m/day

40 m/day 8 m/day

35 m/day 8 m/day

35 m/day 8 m/day

1.00 nr/day 0.25 nr/day


RESOURCES & PRODUCTIVITY DETAILS
RESOURCES & PRODUCTIVITY DETAILS
Drainage Works

Productivity
Activity Description Resources
0-3m 3-6m

Excavate - Pipeline Labour - 2,Ganger - 0.50,Excavator - 1 120 m/day 60 m/day

Labour - 5,Ganger - 0.50,Pipe Fitter - 1,Boom Loader - 0.25,


Lay Pipeline 120 m/day 75 m/day
Truck - 0.2, Hiab - 0.25, Wheel Loader - 0.10
Labour - 4,Ganger - 0.25,Pipe Fitter - 1,Boom Loader - 0.25,
Initial Backfilling & Testing 75 m/day 40 m/day
Truck - 0.25, Water Tanker - 0.3, Wheel Loader - 0.10

Labour - 6,Ganger - 0.50,Water tanker - 0.50,Truck - 0.25,


Final Backfilling 75 m/day 40 m/day
Wheel Loader - 0.25,Skid Loader - 1,Hand Roller - 1,Plate Compactor - 2

Labour - 6,Ganger - 0.25,Mason - 2,Carpenter - 2,


Manhole/Chambers 1.00 nr/day 1.00 nr/day
Steel Fixer - 2,Hiab - 0.25,Excavator - 0.25

Excavate pipeline Labour - 2,Ganger - 0.50,JCB - 1, Plate Compactor - 0.25 100 m/day

Lay Gully pipeline Labour - 2,Ganger - 0.25,Pipe Fitter - 1 100 m/day

Labour - 2,Ganger - 0.50,Skid Loader - 0.25,


Backfill Gully pipeline 75 m/day
Water Tanker - 0.125,Plate Compactor - 1

Gullies Labour - 4,Carpenter - 2,Mason - 2,Pipe Fitter - 1, Hiab - 0.50, JCB - 0.50 5 nr/day

Install Dewatering Labour - 2,Ganger - 0.5,Dewatering Pump - 2 120 m/day


S & PRODUCTIVITY DETAILS
S & PRODUCTIVITY DETAILS

Productivity
6-9m 9 - 12 m

25 m/day 8 m/day

40 m/day 8 m/day

35 m/day 8 m/day

35 m/day 8 m/day

1.00 nr/day 0.25 nr/day


RESOURCES & PRODUCTIVITY DETAILS
RESOURCES & PRODUCTIVITY DETAILS

Irrigation Works

Productivity
Activity Description Resources
0-3
Excavate - Pipeline Labour - 3,Ganger - 0.75,Excavator - 1.50 200 m/day
Labour - 7,Ganger - 0.70,Pipe Fitter - 1.50,Boom Loader - 0.375,
Lay Pipeline 200 m/day
Truck - 0.30, Hiab - 0.375, Wheel Loader - 0.10
Labour - 6,Ganger - 0.375,Pipe Fitter - 1.50,Boom Loader - 0.375,
Initial Backfilling 200 m/day
Truck - 0.375, Water Tanker - 0.45, Wheel Loader - 0.10
Pressure Testing Labour - 2,Ganger - 0.25,Pipe Fitter - 1, Air Compressor - 0.1 200 m/day

Concrete thrust blocks Labour - 2,Ganger - 0.25,Carpenter - 2,Mason - 2 4 nr/day


Labour - 9,Ganger - 0.75,Water tanker - 0.75,Truck - 0.375,
Final Backfilling Wheel Loader - 0.375,Skid Loader - 1.50,Hand Roller - 1.50,Plate Compactor - 150 m/day
3
Irrigation Valve Chambers/ Labour - 5,Ganger - 0.30,Mason - 1,Carpenter - 1,
1.00 nr/day
Air valve chambers Steel Fixer - 1.3,Pipe Fitter - 0.30,Hiab - 0.30,Back Hoe Loader - 0.30
Installation of Fire Hydrants Labour - 2,Pipe Fitter - 0.50,JCB - 0.10,Hiab - 0.25 1 nr/day
S & PRODUCTIVITY DETAILS
S & PRODUCTIVITY DETAILS

Productivity
RESOURCES & PRODUCTIVITY DETAILS
RESOURCES & PRODUCTIVITY DETAILS

Firefighting Works

Productivity
Activity Description Resources
0-3
Excavate - Pipeline Labour - 3,Ganger - 0.75,Excavator - 1.50 200 m/day
Labour - 7,Ganger - 0.70,Pipe Fitter - 1.50,Boom Loader - 0.375,
Lay Pipeline 200 m/day
Truck - 0.30, Hiab - 0.375, Wheel Loader - 0.10
Labour - 6,Ganger - 0.375,Pipe Fitter - 1.50,Boom Loader - 0.375,
Initial Backfilling 200 m/day
Truck - 0.375, Water Tanker - 0.45, Wheel Loader - 0.10
Pressure Testing Labour - 2,Ganger - 0.25,Pipe Fitter - 1, Air Compressor - 0.1 200 m/day

Concrete thrust blocks Labour - 2,Ganger - 0.25,Carpenter - 2,Mason - 2 4 nr/day


Labour - 9,Ganger - 0.75,Water tanker - 0.75,Truck - 0.375,
Final Backfilling Wheel Loader - 0.375,Skid Loader - 1.50,Hand Roller - 1.50,Plate Compactor - 150 m/day
3
Irrigation Valve Chambers/ Labour - 5,Ganger - 0.30,Mason - 1,Carpenter - 1,
1.00 nr/day
Air valve chambers Steel Fixer - 1.3,Pipe Fitter - 0.30,Hiab - 0.30,Back Hoe Loader - 0.30
Installation of Fire Hydrants Labour - 2,Pipe Fitter - 0.50,JCB - 0.10,Hiab - 0.25 1 nr/day
S & PRODUCTIVITY DETAILS
S & PRODUCTIVITY DETAILS

Productivity
RESOURCES & PRODUCTIVITY DETAILS
RESOURCES & PRODUCTIVITY DETAILS
Water Works

Productivity
Activity Description Resources
0-3
Excavate - Pipeline Labour - 4,Ganger - 1,Excavator - 2 200 m/day
Labour - 10,Ganger - 1,Pipe Fitter - 2,Boom Loader - 0.50,
Lay Pipeline 200 m/day
Truck - 0.40, Hiab - 0.50, Wheel Loader - 0.10

Labour - 8,Ganger - 0.50,Pipe Fitter - 2,Boom Loader - 0.50,


Initial Backfilling 200 m/day
Truck - 0.50, Water Tanker - 0.60, Wheel Loader - 0.10

Pressure Testing Labour - 2,Ganger - 0.25,Pipe Fitter - 1, Air Compressor 200 m/day

Concrete thrust blocks Labour - 2,Ganger - 0.25,Carpenter - 2,Mason - 2 6 nr/day

Labour - 9,Ganger - 1,Water tanker - 1,Truck - 0.50,


Final Backfilling 150 m/day
Wheel Loader - 0.50,Skid Loader - 2,Hand Roller - 2,Plate Compactor - 4

Water Valve Chambers/ Labour - 6,Ganger - 0.38,Mason - 1.5,Carpenter - 1.5,


1.00 nr/day
Air valve chambers Steel Fixer - 1.5,Pipe Fitter - 0.38,Hiab - 0.19,Back Hoe Loader - 0.38
S & PRODUCTIVITY DETAILS
S & PRODUCTIVITY DETAILS

Productivity
RESOURCES & PRODUCTIVITY DETAILS

Telecommunication Works

Productivity
Activity Description Resources
0-3
Excavate - Telecommunication Ducts Labour - 2,Ganger - 0.50,Back Hoe Loader - 1 150 m/day
Lay Joint core cable ducts Labour - 4,Ganger - 0.25,Pipe Fitter - 1,Hiab - 0.25 150 m/day
Labour - 4,Ganger - 0.25,Skid Loader - 0.25,
Selected excavated surround/
Water Tanker - 0.25,Wheel loader - 0.25, 150 m/day
mass concrete surround
Hand roller - 0.50,Plate Compactor - 1
Labour - 6,Ganger - 0.375,Carpenter - 1,Mason - 2.80,
Manholes & Junction Boxes 1.00 nr/day
Steel Fixer - 2.80,Hiab - 0.375
S & PRODUCTIVITY DETAILS

Productivity
RESOURCES & PRODUCTIVITY DETAILS
RESOURCES & PRODUCTIVITY DETAILS

Road Works

Activity Description Resources Productivity

Labour - 3,Ganger - 1,Dozer - 1 ,Grader - 1.10, Wheel


Earthworks 1000 m3
Loader - 1,Vibratory Roller - 1.10, Truck - 2,Water tanker - 3

Labour - 2,Ganger - 0.50,Grader - 1,Vibratory Roller - 1,


Subbase 2000 m2 200 m3
Water Tanker - 0.50,Truck - 2
Labour - 4,Ganger - 0.25,Mason - 2,Carpenter - 2,
Kerbs 100 m ( 2 teams) Total = 200m
Hiab - 0.25,Truck - 0.1,Plate Compactor - 0.25.
Labour - 2,Ganger - 0.5,Grader - 1,Vibratory Roller - 1,
Road base 2000 m2 201 m3
Water Tanker - 0.5,Truck - 2,Wheel Loader - 0.5,
Asphalt Labour - 8,Ganger - 1,Paver - 2,Tandem Roller - 1,
Asphalt - Base Course Water Tanker - 1,Skid Loader - 0.5,PTR - 3, 2000 m2 600 ton
Asphalt Truck - 3,Hand roller - 0.5
Asphalt Labour - 8,Ganger - 1,Paver - 2,Tandem Roller - 1,
Asphalt - Wearing Course Water Tanker - 1,Skid Loader - 0.5,PTR - 3, 2000 m2 600 ton
Asphalt Truck - 3,Hand roller - 0.5
Labour - 12,Mason - 6,Ganger - 1.0,Hiab - 0.3
Interlock Tiles 300 m2
Truck - 0.30,Skid Loader - 0.75,Plate Compactor - 1.5
S & PRODUCTIVITY DETAILS
S & PRODUCTIVITY DETAILS

Productivity

( 2 teams) Total = 200m


RESOURCES & PRODUCTIVITY DETAILS
RESOURCES & PRODUCTIVITY DETAILS
Electrical Works

Productivity
Activity Description Resources
0-3
Excavation Labour - 3,Ganger - 0.30,JCB - 1 300 m/day
Cable Laying Labour - 3,Ganger - 0.30,JCB - 0.10,Electrician - 1 300 m/day
Backfilling Labour - 2,Ganger - 0.20,JCB - 0.50,Water tanker - 0.25, Plate Compactor - 1 150 m/day
S & PRODUCTIVITY DETAILS
S & PRODUCTIVITY DETAILS

Productivity
RESOURCES & PRODUCTIVITY DETAILS

Street Lighting Works

Productivity
Activity Description Resources
0-3
Excavation Labour - 3,Ganger - 0.30,JCB - 1 200 m/day
Cable Laying Labour - 3,Ganger - 0.30,Electrician - 1 200 m/day
Labour - 2,Ganger - 0.20,JCB - 0.50,Water tanker - 0.25, Plate Compactor - 1,
Backfilling 200 m/day
Back Hoe Loader - 0.50
Labour - 3,Ganger - 0.50,Carpenter - 1,Mason - 1,
Street Lighting Foundation 15 nr/day
Steel Fixer - 1,JCB - 0.5,Water Tanker - 0.25,Hiab - 0.25
Street Lighting Columns Labour - 1.50,Ganger - 0.50,Hiab - 0.25,Truck - 0.50, Crane - 0.50 15 nr/day
Install new lighting luminaries Labour - 3,Electrician - 1.50,Crane - 0.275 15 nr/day
Labour - 1,Ganger - 0.25,Carpenter - 0.25,Mason - 0.50,
Street Lighting Feeder Pillar 1 nr/day
JCB - 0.10,Hiab - 0.25.
S & PRODUCTIVITY DETAILS

Productivity
RESOURCES & PRODUCTIVITY DETAILS
RESOURCES & PRODUCTIVITY DETAILS
Duct Crossing Works

Productivity
Activity Description Resources
0-3
Labour - 6,Ganger - 1,Pipe Fitter - 2,JCB - 1,
Excavate,Lay & Backfill Road crossings ducts Wheel Loader - 0.5,Water Tanker - 0.5,Skid Loader - 0.5, 50 m/day
Plate Compactor - 1. Back hoe Loader - 1.00
S & PRODUCTIVITY DETAILS
S & PRODUCTIVITY DETAILS

Productivity
RESOURCES & PRODUCTIVITY DETAILS

Final Works

Productivity
Activity Description Resources
0-3
Chlorination & Bacterial test Labour - 2,Ganger - 0.25 100 m/day
Inspection & Handover Labour - 2,Ganger - 0.20,Pipe Fitter - 0.50