Berlin Wall Construction and Applications
Berlin Wall Construction and Applications
The Berlin walls or micro Berlin walls allow the realization of retention.
temporary or permanent for the creation of excavations at the site of existing buildings, for
stabilize landslides or at the edge of banks.
I. Principle:
The vertical profiles are vibro-driven into the ground or placed in a borehole executed at
preliminary. This technique is applied in the presence of very hard soil or
underground obstacles.
2. Concrete filling:
After the implementation of the profile to fill the borehole with a product of
sealing, generally a highly dosed cement slurry that serves to ensure
the waterproofing of the ground and preventing the rise of the water table in the excavation.
Above the excavation level, we evacuate sand, cement, or gravel to
reinforce the foundation (figure 3).
3. Shielding:
The shielding elements are placed between the profiles as it progresses
the local excavation. They are placed perpendicular to these and directly after
each excavation phase.
This operation takes place in successive horizontal layers (0.2 to 1m) until the
level of installation of any horizontal supports.
4. Excavation of the dig
The excavation is dug around its entire perimeter to the level of installation of any possible vents.
horizontal supports.
The installation of the shoring continues as the excavation progresses until the
final level of the excavation.
5. Establishment of anchoring:
The Berlin walls only serve the purpose of supporting the earth, and not for waterproofing.
water. They can be applied in the following situations:
Economic
Quick to implement,
Provides a dry, clean, and flat work platform.
2. Disadvantages:
Molded wall:
The diaphragm wall is a reinforced concrete screen cast in the ground constructed in trenches.
open supported by mud.
They generally act as a waterproof barrier or as retaining walls.
for rather deep excavations.
The walls are generally 600 to 1500 mm thick, with a width between 2000 and 3500 mm
and can be excavated to depths of 60m or more [2].
I. Principle:
Murettes guides :
They serve the purpose of:
materialize the installation of the wall,
Guide the bucket at the start of the drilling.
• form a mud reserve and prevent landslides due to the effects of tidal variations,
• provide stable support for delicate operations such as setting up cages
of reinforcements, etc.
Forage
The hard grounds and obstacles are broken up using a heavy drill suspended from one of the
two drilling cables.
A mixture of bentonite and water called drilling mud is fed in as needed.
forage to ensure the maintenance of the trench and to exert a constant pressure to avoid
total collapse.
The excavated materials are loaded into trucks and then transported to a settling pit.
by cutting and/or grinding the ground using toothed wheels:
3. Panel equipment:
Once the diaphragm wall is fully excavated and the extracted soil is replaced with the
Bentonite, we place a sealing profile called waterstop on either side of the
Panel to ensure the sealing of the connection, then we set up the rebar cages.
sized after the installation of the concrete wedges.
4. The concreting:
The concreting is done using immersion tubes lowered to the bottom of the borehole.
As the concrete rises, the bentonite mud is pushed upwards. This one
is pumped to the plant to be recycled.
We stop the concreting as soon as the concrete has risen to the level of the guide walls.
The construction of the diaphragm wall is carried out by alternating and contiguous panels in order to
to obtain a continuous wall in the ground that represents a permanent support structure.
Figure 3: steps for executing an individual panel
The diaphragm walls have several uses in the field of construction such as:
Sealing screens
- A support
Assistance in the construction of underground parking using the 'top down' method
also 'covered trench'.
Advantages:
The diaphragm walls allow for the creation of a relatively watertight enclosure.
curved sails are possible. They are widely used for basins because this
particular form is self-stable
The wall is very rigid, which greatly limits head movements. This point is very
important when there are buildings nearby.
no vibration is generated
If necessary, we can reinforce the wall with buttresses, tie rods, or braces.
The work is definitive and its duration is important if the coating is respected.
2. Disadvantages:
The diaphragm wall technique is very expensive.
the mechanical and durability characteristics of concrete are lower because concrete is
sunk upon contact with the ground.
Navigateion
References:
[1] The provided text is a URL and does not contain translatable content.
Berlin type 1 - [Link]/
[2]Invalid URL format. No text to [Link] 2016/ Technology-diaphragm-walls-soilmec
[Link]/
[Link]
civil/geotechnique/fauqueux/diaphragm_walls/co/DiaphragmWalls_17.html