0% found this document useful (0 votes)
13 views1 page

Road Rehabilitation Bill for Saramandi

The document outlines the bill of quantities for the rehabilitation of the road to Saramandi Research Station in East Sepik Province, detailing various construction works and associated costs. The total estimated cost for the project is PGK 963,762.65, which includes general works, site clearance, earthworks, sub-base preparation, stone masonry, and pipe culverts. Each section specifies unit prices, quantities, and total amounts for the respective tasks involved in the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views1 page

Road Rehabilitation Bill for Saramandi

The document outlines the bill of quantities for the rehabilitation of the road to Saramandi Research Station in East Sepik Province, detailing various construction works and associated costs. The total estimated cost for the project is PGK 963,762.65, which includes general works, site clearance, earthworks, sub-base preparation, stone masonry, and pipe culverts. Each section specifies unit prices, quantities, and total amounts for the respective tasks involved in the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

East Sepik Province

Rehabiliation of Road to Saramandi Research Station

BILL OF QUANTITY

Chainage start: 0+000 Road Name: Gavian to Saramandi Research Station


Chainage end: 4+000 District: Angoram
Length : 4000 Province: East Sepik

Pay SPEC Unit Price


S.N. Description Unit Quantity Total Amount(PGK)
Item No. REF (PGK)
1.0 General Works
1 1.1 SS-1.1 Provide policies for insurance of loss of or damage to Works, Plant and
Materials; Loss of or damage to equipment; Third Party Insurance and
Loss of or damage to property and Personal injury or Death as LS 1.00 15,000.00 15,000.00
pescribed.

2 1.2 SS-1.2 Provide and maintain traffic safety, control measures and temporary
diversions during construction as instructed by the Engineer. LS 1.00 5,000.00 5,000.00

3 1.3 SS-1.3 Provide, maintain and run material testing laboratory at site as
instructed by the Engineer. At the end of Cotract, the furniture,
equipment and fixtures will become the property of the Contractor. LS 1.00 10,000.00 10,000.00

4 1.4 SS-1.4 Supply, Provide and maintain Occupational Safety & Health during
LS 1.00 3,000.00 3,000.00
construction
5 1.5 SS-1.5
Provide and establish the labour camps, adequate drinking water
facility and toilets for labors and Demolish camp site and re-instate the LS 1.00 21,000.00 21,000.00
ground as per specifications and as instructed by the Engineer
Total 1: 54,000.00
2.0 Site Clearance
6 2.1 SS-1.6 Clearing and grubbing including the cutting of trees (only if necessary)
having girth of less than 30 cm when measured at 1 m above the m2 40,000 3.19 127,600.00
ground.

Total 2: 127,600.00
3 Earthworks
7 3.1 SS-2.1 Roadway, and drain excavation in all type of material (soil and rock)
including disposal of excavated material up to a lead of 50 m at
approved environmentally safe tipping sites as per drawing or as m3 2,115.00 23.20 49,068.00
directed by Engineer.

8 3.2 SS-2.2 Earthwork in excavation for foundation of structures in all type of soil
and rock material including disposal of excavated material at approved
m3 19.20 56.12 1,077.50
environmentally safe tipping sites.

9 3.3 SS- 2.3 Construction of roadway embankments, shoulders and other


miscellaneous filling and backfilling with approved materials including
the cost of transportation of the material and benching as required. m3 540.00 81.20 43,848.00

10 3.4 SS-2.4 Backfill behind structure with suitable common material


m3 15.20 66.20 1,006.24
Total 3 : 94,999.74
4 Sub-base and Shoulders
12 4.1 SS-2.6 Preparation of subgrade (filling or cutting up to a depth of 200 mm) to
designed grade, line, level, super-elevation and camber including
watering and compaction. m2 24,000.00 6.50 156,000.00

13 4.2 SS-8.1.3 Preparation of bedding for hume pipe with granular material including
all complete m3 48.00 239.44 11,493.12

14 4.3 SS-3.0-3.1 Providing, laying, spreading, leveling and compaction of granular sub-
base as per specification. m3 4,400.00 60.00 264,000.00

Total 4: 431,493.12
5 Stone Masonry for Structures
15 5.1 SS-4.0 Stone masonry work including full compensation for all labour,
materials and other incidentals required to complete the work as per the
Specifications and drawings. It includes full compensation for using
specially dressed stones on the face of walls with batter and makes m3 9.00 322.00 2,898.00
provision for weep holes of dia 75 mm HDP 10 kg/ cm2pipes as
necessary in MM7.5 cement sand mortar

17 5.3 SS-10 Supply and place dry stone soling. m3 - -


Total 5: 2,898.00
7 Formwork and Surface Finish for Structures
19 7.1 SS 7 Providing , Preparing and Installing form work using timber & wood
& removing after completion for Slab & beam structure m2 14.60 45.00 657.00

Total: 6 657.00
8 Steel Reinforcement for Structures
20 8.1 SS-6 Providing Reinforcement for RCC works including bending, placing,
binding and fixing in position as shown on the drawings and as directed
kg -
by the Engineer.

Total: 8
9 Plain and Reinforced Cement Concrete for
Structures
21 9.1 SS-5 Providing and placing cement concrete of grade M 15/20 including
compaction, curing all complete as per specification m3 7.00 900.00 6,300.00

22 9.2 SS-5 Providing and placing cement concrete of grade M 20/20 including
compaction, curing all complete as per specification m3 22.00 1,100.00 24,200.00

Total : 8 30,500.00
11 I) Pipe Culvert: Supply and Place Flanged Nestable metal pipe

29 11.1 SS 8.2 a) 600 mm diameter pipe ( Armco Corrugate Pipe 600) rm 8.00 1,600.00 12,800.00
SS 8.3 b) 900 mm diameter pipe ( Armco Corrugate Pipe 900) rm 36.00 1,900.00 68,400.00
SS 8.4 c) 1200 mm diameter pipe ( Armco Corrugate Pipe 1200) rm 24.00 2,200.00 52,800.00
Total : 9 134,000.00

Sub Total 876,147.86


GST@10% 87,614.79
Grand Total 963,762.65

You might also like