Drainage System Improvement in Chümoukedima

The project aims to improve the drainage system at H Khel, Diphupar village in Chümoukedima District, Nagaland, with an estimated cost of Rs. 351.95 Lakhs. It focuses on constructing pucca drains and enhancing existing infrastructure to mitigate waterlogging and protect local assets during monsoon seasons. The project is expected to benefit approximately 1300 residents, primarily from the Schedule Tribe community, by safeguarding their properties and improving socio-economic conditions.

Uploaded by

secirclewrd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
57 views6 pages

Drainage System Improvement in Chümoukedima

The project aims to improve the drainage system at H Khel, Diphupar village in Chümoukedima District, Nagaland, with an estimated cost of Rs. 351.95 Lakhs. It focuses on constructing pucca drains and enhancing existing infrastructure to mitigate waterlogging and protect local assets during monsoon seasons. The project is expected to benefit approximately 1300 residents, primarily from the Schedule Tribe community, by safeguarding their properties and improving socio-economic conditions.

Uploaded by

secirclewrd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

GOVERNMENT OF NAGALAND

CONCEPT NOTE
ON

“Improvement of Drainage system at H Khel,


Diphupar village, Chümoukedima District,
Nagaland”

ESTIMATED COST: Rs. 351.95 Lakhs

SE CIRCLE-1, WATER RESOURCES DEPARTMENT


CHÜMOUKEDIMA, NAGALAND
CONCEPT NOTE

S Items Detailed information


No
A General Information about the
Project
i. Name of the Project Improvement of Drainage system at H-Khel,
Diphupar village ,Chümoukedima District,
Nagaland

ii. Objectives of the Project The objective is for improvement of existing


unlined drains with construction of pucca/lined
drains, widening and re-sectioning of the drains
for protection of inhabited areas and mitigate
inundation /water logging due to over flow from
the nallah.
iii. Estimated Cost of the Project Rs. 351.95 Lakhs

iv. Name of the river/stream H-Khel Nallah

v. Availability of land and land size.


Indicate clearly whether owned by Sufficient Land available and Community owned
Govt./leased/donated/community
owned etc.
vi. Location of project H-Khel, Diphupar, Chümoukedima Dist,
Nagaland.

Latitude 25°52’58.46’’N
Longitude 93°45’59.52’’E

vii. Name of district and Chümoukedima District, Chümoukedima block,


sub-division/block where proposed Nagaland
project will be located
viii. Proposing/Implementing Water Resources Department
Department
ix. Name of the executing Water Resources Department
Department/ Agency
x. Enclose non-duplication Certificate NA
xi. Indicate sustainability of project The project will be executed with design
including operation and structures recommended by CWC and the
maintenance of assets on operation and maintenance of assets created will
completion of project be looked after by the H-Khel community on
completion of the project

xii. Give details of the existing - One SE in the SE Circle-1 in the district
infrastructure and facilities - One EE in the SE Circle-1 in the district
available in the proposed project - One SDO in the SE Circle-1 in the district
location and also in the district and - One JE in the SE Circle-1 in the district
sub-division/ block

B Justification/ Rationale for the


Project
i. State the nature and magnitude of The proposed project is located under H-Khel of
the problem faced or the potential Diphupar village. It is seen that during monsoon
to be tapped. Elaborate the the storm runoff from the National highway and
problems to be addressed or adjoining Khels is diverted through these two
benefits that will accrue through drains which serves as the collector drain. Due to
the project. For social the larger quantity of runoff, this drain’s carrying
infrastructure project, also give the capacity is compromised and leads to overspilling
baseline of socio-economic which inundates landed assets and causes
parameters/indicators to justify the inconvenience to the locality. The existing drains
proposal. are narrow and not lined as such with the
amount of runoff it has led to soil erosion and the
adjoining structures/buildings are also affected.
The Cross drains have less carrying capacity and
thus adds to the stagnation and obstruction of
the free flow of water.
Community led restoration/desilting works by
self-funding with locally available resources have
been attempted but has not yielded any
significant results.
The project will be justified on the basis of the
benefit cost ratio and the drainage system will be
overhauled with sufficient carrying capacity of
the drains as well as the cross drains.
On completion of the project, this will greatly
contribute to the socio-economic development
and over-all well-being of the people of H Khel.
The project is proposed mainly to safeguard the
assets and drain the storm waters efficiently
without any hindrance to the community.

ii. The development objectives The main objectives of the proposal are to
proposed to be achieved protect the area from inundation by channelizing
the water. To provide pucca drains, re-sectioning,
re-construction of cross drains for sufficient
carrying capacity.

iii. Indicate the sections and number Population benefitted= 1300


of population to be benefitted. The whole population belongs to Schedule Tribe.
iv For income generating activities/
skill development indicate the
number of beneficiaries targeted N/A
and the methodology for selection
of beneficiaries. Indicate nos. of
female and male beneficiaries
separately.
C Project Description & Main
Activities
i. Sector under which project is Water related works, Drainage
proposed
ii. Project description (Provide a brief The H Khel of Diphupar village is one of the major
write-up on the project) Khels in the village with low and undulating
terrain. These two nallahs are of vital importance
to the locality since all individual drains are
connected to this drainage system. One drain
originates from C khel area and the other from
the central jail area and then merges
downstream the Horticulture farm which in turn
joins the sugarmill nallah at Chekiye Village Block-
3.
The residents of this Khel primary depend upon
this two nallahs to dispose off their storm as well
as households wastes. The Office of the
Superintending Engineer, Circle-1, Executive
Engineer, Investigation Cell; Water Resources
Department, Churches, Paying guest
accommodations, Hostels etc and a host of
individual residences are established between
these two nallahs.
Over the years it was observed that during
monsoon, the nallahs over flow and causes
immense hardships to the residents. The nallah
on the northern side of the H- Khel is about 550
m whereas the southern nallah is about 720 m.
till their confluence. Then the nallah joins the
sugarmill nallah after traversing about 500 m at
Chekiye Block -3. Erosion of the banks have
damaged some of the boundary walls of the
Horticulture Farm and further damage to the
walls are very likely unless proper and pucca
drain is constructed along these stretches.
It is therefore proposed to construct pucca drain
for a total length of 1770 m along with three nos
of culverts till its confluence with Sugarmill
nallah.
Upon commissioning of this project, valuable
landed properties and public utility assets,
plantations etc along these stretches of the nallah
will be protected and pave the way for future
development activities. Hence, the proposed
“Improvement of Drainage system at H-Khel”,
have to be implemented to protect the landed
assets of the public and socio-economic activities
of the people.
iii Component-wise cost of GENERAL ABSTRACT OF COST
. project/main activities
(e.g. buildings and other Sl.
Particulars
civil works, machineries, No
tools & equipments, A Preliminary survey, Collection of Datas,
₹ 5,00,000.00
miscellaneous fixed assets, 1 Preparation of DPR
agricultural inputs, training 2 C-Works
components etc.) i) Construction of RCC Drain ₹ 2,83,50,000.00
ii) Construction of Cross Drains ₹ 6,50,000.00
i)Total of C works ₹ 2,90,00,000.00
ii) Add 9.19% for price escalation on Total
₹ 26,65,100.00
of C works
iii) Sub Total - 1 (i+ii) ₹ 3,16,65,100.00

iv) Add 5.31 % of Sub Total -1 ( Increase of ₹ 16,81,417.00


GST from 12% -18%)
v)Sub Total II (iii+iv) ₹ 3,33,46,517.00
vi) Add 3% Contingency of Sub Total II ₹ 10,00,396.00
vii)Total of C works (v+vi) ₹ 3,43,46,913.00
Total of A (1+2)_ ₹ 3,48,46,913.00
Audit and 3rd Party Performance
₹ 3,48,469.00
B Evaluation & Monitoring @ 1% of A
Grand Total (A+B) ₹ 3,51,95,382.00
Say ₹ 3,51,95,000.00
iv List out basic indicators for Protection of the locality from waterlogging, inundation and
measuring achievement/ damages to land and its landed properties
Success of the project
D Physical details
Year-wise phasing & Time Time frame for completion of the project is 12 months
frame for completion of 2025-26 2026-27
project 40% 60%
Financial details
Year-wise phasing 2025-26 2026-27
40% 60%
F Indicate if any statutory Shall be produced and appended at the time of preparation of Detail
clearances including Project Report
forest and Environmental
Clearances etc. are
required.

Superintending Engineer
SE Circle-1, Water Resources Department
Chümoukedima, Nagaland