02 Crew Movement Calculation For Pipeine Works

The document outlines the crew allocation and project schedule for sewer pipeline and house connection piping works, detailing various segments with specific activity IDs, start and finish dates, material quantities, and required crew numbers. Each segment has a defined duration and is categorized under pipe bedding and laying activities. The timeline spans from September 2025 to May 2026.

Uploaded by

Dilip Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views1 page

02 Crew Movement Calculation For Pipeine Works

The document outlines the crew allocation and project schedule for sewer pipeline and house connection piping works, detailing various segments with specific activity IDs, start and finish dates, material quantities, and required crew numbers. Each segment has a defined duration and is categorized under pipe bedding and laying activities. The timeline spans from September 2025 to May 2026.

Uploaded by

Dilip Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

CREW ALLOCATION NEW N AREA

14/May/26

29/May/26
15/Nov/25

30/Nov/25

15/Dec/25

30/Dec/25
16/Sep/25

15/Mar/26

30/Mar/26
13/Feb/26

28/Feb/26
16/Oct/25

31/Oct/25

14/Apr/26

29/Apr/26
14/Jan/26

29/Jan/26
1/Sep/25

1/Oct/25
Original
Activity ID Activity Name BL Project Start BL Project Finish Material Qty CREW nos
Duration

Sewer Pipeline 200mm to 315mm


Segment - 01
MSN-SWR-1380 Pipe Bedding & Laying 41 28-Oct-25 17-Dec-25 3,263 T1, T2
Segment - 02
MSN-SWR-1380 Pipe Bedding & Laying 41 17-Dec-25 5-Feb-26 3,263 T1, T2
House Connections
Segment - 01 - 160mm
Piping Works
MSN-HCC-2610 Pipe Bedding & Laying 15 18-Oct-25 10-Nov-25 804 T3, T4, T5, T6, T7, T8
Segment - 02 - 160mm
Piping Works
MSN-HCC-2710 Pipe Bedding & Laying 15 11-Nov-25 7-Dec-25 804 T3, T4, T5, T6, T7, T8
Segment - 03 - 160mm
Piping Works
MSN-HCC-2800 Pipe Bedding & Laying 15 7-Dec-25 30-Dec-25 804 T3, T4, T5, T6, T7, T8
Segment - 04 - 160mm
Piping Works
MSN-HCC-2900 Pipe Bedding & Laying 15 30-Dec-25 25-Jan-25 804 T3, T4, T5, T6, T7, T8
Segment - 05 - 160mm
Piping Works
MSN-HCC-3000 Pipe Bedding & Laying 15 25-Jan-25 17-Feb-26 804 T3, T4, T5, T6, T7, T8
Segment - 06 - 160mm
Piping Works
MSN-HCC-3090 Pipe Bedding & Laying 15 17-Feb-25 12-Mar-25 804 T3, T4, T5, T6, T7, T8
Segment - 07 - 160mm
Piping Works
MSN-HCC-3190 Pipe Bedding & Laying 15 12-Mar-25 9-Apr-25 804 T3, T4, T5, T6, T7, T8
Segment - 08 - 160mm
Piping Works
MSN-HCC-3290 Pipe Bedding & Laying 25 9-Apr-25 9-May-25 804 T3, T4, T5, T6, T7, T8