CREW ALLOCATION NEW N AREA
14/May/26
29/May/26
15/Nov/25
30/Nov/25
15/Dec/25
30/Dec/25
16/Sep/25
15/Mar/26
30/Mar/26
13/Feb/26
28/Feb/26
16/Oct/25
31/Oct/25
14/Apr/26
29/Apr/26
14/Jan/26
29/Jan/26
1/Sep/25
1/Oct/25
Original
Activity ID Activity Name BL Project Start BL Project Finish Material Qty CREW nos
Duration
Sewer Pipeline 200mm to 315mm
Segment - 01
MSN-SWR-1380 Pipe Bedding & Laying 41 28-Oct-25 17-Dec-25 3,263 T1, T2
Segment - 02
MSN-SWR-1380 Pipe Bedding & Laying 41 17-Dec-25 5-Feb-26 3,263 T1, T2
House Connections
Segment - 01 - 160mm
Piping Works
MSN-HCC-2610 Pipe Bedding & Laying 15 18-Oct-25 10-Nov-25 804 T3, T4, T5, T6, T7, T8
Segment - 02 - 160mm
Piping Works
MSN-HCC-2710 Pipe Bedding & Laying 15 11-Nov-25 7-Dec-25 804 T3, T4, T5, T6, T7, T8
Segment - 03 - 160mm
Piping Works
MSN-HCC-2800 Pipe Bedding & Laying 15 7-Dec-25 30-Dec-25 804 T3, T4, T5, T6, T7, T8
Segment - 04 - 160mm
Piping Works
MSN-HCC-2900 Pipe Bedding & Laying 15 30-Dec-25 25-Jan-25 804 T3, T4, T5, T6, T7, T8
Segment - 05 - 160mm
Piping Works
MSN-HCC-3000 Pipe Bedding & Laying 15 25-Jan-25 17-Feb-26 804 T3, T4, T5, T6, T7, T8
Segment - 06 - 160mm
Piping Works
MSN-HCC-3090 Pipe Bedding & Laying 15 17-Feb-25 12-Mar-25 804 T3, T4, T5, T6, T7, T8
Segment - 07 - 160mm
Piping Works
MSN-HCC-3190 Pipe Bedding & Laying 15 12-Mar-25 9-Apr-25 804 T3, T4, T5, T6, T7, T8
Segment - 08 - 160mm
Piping Works
MSN-HCC-3290 Pipe Bedding & Laying 25 9-Apr-25 9-May-25 804 T3, T4, T5, T6, T7, T8