Highway Project Study Guidelines
Highway Project Study Guidelines
MINISTRY OF TRANSPORTS
NATIONAL DEPARTMENT OF TRANSPORT INFRASTRUCTURE
DIRECTORATE OF PLANNING AND RESEARCH
GENERAL COORDINATION OF STUDIES AND RESEARCH
INSTITUTE OF HIGHWAY RESEARCH
BASICGUIDELINESFORELABORATION
ONSTUDIESANDHIGHWAYPROJECTS
BASICSCOPES/SERVICEINSTRUCTIONS
REVIEW
Engesur Technical Consulting Ltd.
TECHNICAL TEAM:
Engineer José Luis Mattos de Britto Pereira Technician Marcus Vinicius de Azevedo Lima
Coordinator (Information Technology Technician)
Eng. Zomar Antonio Trinta Technician Alexandre Martins Ramos
Supervisor Computer Technician
Engineer Amarílio Carvalho de Oliveira Technician Reginaldo Santos de Souza
Consultant Computer Technician
SUPERVISION COMMISSION:
Engineer Gabriel de Lucena Stuckert Engineer Elias Salomão Nigri
(DNIT / DPP / IPR) (DNIT / DPP / IPR)
Engineer Mirandir Dias da Silva Engineer José Carlos Martins Barbosa
(DNIT / DPP / IPR) (DNIT / DPP / IPR)
CDD 625.722
Printed in Brazil
2nd Edition
Rio de Janeiro
2005
MINISTRY OF TRANSPORTS
NATIONAL DEPARTMENT OF TRANSPORT INFRASTRUCTURE
DIRECTORATE OF PLANNING AND RESEARCH
ROAD RESEARCH INSTITUTE
PRESENTATION
In this context, it was about reviewing and updating the document entitled 'Basic Guidelines'
for the Preparation of Road Studies and Projects - Basic Scopes and Instructions
Serviço”, editado em 1999 pelo mesmo IPR a partir de uma revisão parcial do chamado
Consulting Services Manual for Road Studies and Projects, in turn,
dating back to 1978. The main motivation for this review and update was to
adjust the Guidelines to the conceptualization of Basic Project and Executive Project, defined by
Law No. 8,666, of June 21, 1993.
According to the mentioned law, which establishes regulations for bidding and contracts of
Public Administration, Basic Project is 'the set of necessary elements and
sufficient... to characterize a work or service” (Art. 6, Section IX), while
Executive Project is "the set of elements necessary and sufficient for execution
complete of the work” (Article 6, Item X).
Thus, the Guidelines, now revised and delivered to the road community, propose to
basically to address this conceptual change and understand Basic Scopes and
Service Instructions for carrying out various road studies and projects.
As the title itself indicates, they have a guiding character either for the preparation of
Terms of Reference, whether for the actual development of studies and projects
relevant. They signal a path already travelled and established, but do not dismiss a
adaptation to reality and the particularities of each case individually. And in this they differ
the conventional technical standards, which have legal force and require compliance.
The two constituent elements of the Guidelines can also be defined in lines.
general. A Basic Scope establishes the guidelines for the development of the various
types of studies and engineering projects, and a Service Instruction indicates the phases and
the technical procedures adopted in the preparation of those same studies and projects.
Both, therefore, complement each other. The Scope sets and describes; the Instruction details.
technically.
Both represent efficient instruments in the accomplishment of the so-called cost process.
service life of highways under the responsibility of the Federal Administration, a process that integrates
project, construction, maintenance, rehabilitation and restoration ultimately aims at
maximize user benefits while minimizing total costs of
public heritage and the user's own.
Basic Guidelines for the Preparation of Road Studies and Projects 4
We would appreciate receiving any type of comment, observation, suggestion, and criticism that
may contribute to the improvement of the Guidelines. As much as possible,
we will respond to readers and users who send us their contributions, the
those, as long as they are substantiated and relevant, will be used in a future edition.
the Guidelines.
Mailing address:
SUMMARY
PRESENTATION
1. INTRODUCTION
2. BASIC SCOPES
2.1. Definition
3. SERVICE INSTRUCTIONS
3.1. Definition
4. BIBLIOGRAPHY
Basic Guidelines for the Preparation of Road Studies and Projects 9
1 - INTRODUCTION
Basic Guidelines for the Preparation of Road Studies and Projects 10
Basic Guidelines for the Preparation of Road Studies and Projects 11
1 INTRODUCTION
This volume is the result of the revision and updating of the first version of the Guidelines
Basics for Preparation of Road Studies and Projects – Basic Scopes and
Service Instructions, edited in 1999 by the Road Research Institute (IPR).
The process of reviewing and updating the bibliographic collection, which was already an activity
essential and permanent within the IPR, gained momentum from the moment it was
I officially need to transform the DNER documentation into DNIT documentation.
view from the extinction of the first and the creation of the second, not to mention the inevitable
(although welcome) advances in the sector's technology. In the specific case of the Guidelines
Basically, there were two other central issues. First of all, the Guidelines constitute
a cornerstone in the bibliography of the governing body, whether unimodal (as it was the
DNER), should be multimodal (as DNIT is), and therefore are worthy of continuous review
and privileged. Secondly, there was a need to change the terminology until
then used by the Guidelines inserting the most current concepts of Basic Design and
Executive Project.
Despite this, in light of the breadth of the topics addressed and the constant evolution of
procedures and methods, as well as the possibility of using, more and more,
the practice and knowledge of all the technicians involved with the sector, cannot be
consider the exhaustion of the matter with this publication. In fact, the IPR, when recommending
the immediate use of the Guidelines by every professional in the field does not require that this
do not abandon your own accumulated experience nor discard the attentive observation of
specificities of the problem at hand, and hopes that the constant handling of the
material, generating questions and corrections, lead the Guidelines to reflect both
as much as possible the reality of the office and the field, raising them higher and higher to the level
of documentary excellence.
THE BACKGROUND
Until the mid-1950s, the design of a highway was prepared directly by the
National Department of Highways (DNER), which was also responsible for
inspection of works. The projects of that time emphasized definitions and controls.
geometric in the face of both the abundant availability of topographical resources and the
virtual non-existence of paving in the country. The preparatory studies of the projects
They are practically limited to topographic surveys and special artworks.
and only in exceptional cases, to the probing of the subsoil. The objectives that guided the
Basic Guidelines for the Development of Road Studies and Projects 12
the projects were the reduction of costs in terms of earthworks volume and its
framing to the required geometric characteristics.
Starting in 1956, the government formulated an extensive program for the road sector,
determining that the DNER should start transferring the projects to the private initiative.
Thus, geotechnical studies, geometric projects, and pavement designs have passed
for the hands of engineering service companies. At the same time, were created the
Special Works Committees, to which facilities were granted
operational, financial, and logistical support. With the support of engineering companies
in the areas of surveying, geotechnics, and paving, they were implemented and paved
extensive road stretches, of audacious design for the time, in record time and
with unquestionable executive success.
In this period, which is marked by great material achievements and extends until the
By the end of the 1960s, there is a growing application of determinations and verifications of
quality. Engineering projects did not yet exist, such as those we have in conception.
atual. Eles eram, antes, constituídos por peças isoladas que se agregavam de acordo
with the requirements of the execution schedules of the works.
In the period between 1966 and 1968, plans were developed with resources from the Bank
World (BIRD), the so-called Regional Master Plans. These, when counting on the
contribution of foreign consulting firms and the participation, in return, of technicians
national, allowed for the first time a significant transfer of technology from
transport area of developed countries.
THE CONSOLIDATION
The requirement for the existence and presentation of a complete Engineering Project and
approved as a condition for the contracting of works was legally established by the
first time by Decree-Law No. 185, of 02/23/1967 (Art. 1). With the subsequent
the promulgation of Decree-Law No. 200, of 02/25/1967, made it possible for the DNER to
hiring, at the end of the same year, of the first national consulting services for
geotechnical studies and pavement design. As for the hiring of companies for
Consulting for the preparation of Final Engineering Projects was only made possible from
from 1968, when the Standards for Hiring were published on March twenty-sixth
of Consulting Services, which meant a definitive opening for the market.
The crowning of this entire evolutionary process can be considered the Manual of
Consulting Services for Road Studies and Projects. Developed over the years
70 and approved in 1978, the Manual condensed the accumulated experience both by the Division
of Studies and Projects (DEP) of the DNER as well as by consulting companies that
they had been working for the DNER since 1968, constituting a compilation of several
technical documents, service instructions, and circulars in effect until its date of
publication. Comprised of nine volumes, the Manual highlighted the volumes
2.3 - Basic Scopes and 2.4.1 and 2.4.2 - Service Instructions.
The Guidelines, therefore, originate from a Manual and largely preserve the
qualities of a Manual. In other words, the Basic Scopes and the Instructions of
Services that make up the Guidelines essentially have the character of a guide, as indicated
the title itself, and not of norm, it is recommended that each study or project
road transport particularly observe the specificities of the road segment at play, such
as the object of each contract.
In other words, the project should be seen as an act of creation, during the
which author applies their knowledge, experiences, and skills
personal to the resolution of the issues inherent to the project. Like any creative process,
he should not be subject exclusively to rigid rules or routine solutions and
conventional. These have their value and application, but the schematization
excessive can only harm. No matter how small, the project of a stretch of highway
involves new and specific problems, whose particular solution cannot be
fully repeated. The role of the Basic Scopes and the Service Instructions is to
Basic Guidelines for the Preparation of Road Studies and Projects 14
The definitions of Basic Project and Executive Project that integrate the legal provisions
about bidding and contracts in Public Administration first appeared in
Decree-Law No. 2,300, of 11/21/1986, Articles 5 and 6, and subsequently in Law No. 8,666, of
06/21/93, Articles 6, 7, and 9, also known as the Bidding Law.
The present review of the Basic Guidelines was primarily motivated by the
establishment of a minimum standard for guidance regarding activities
inherent to the Basic Projects and Executive Projects. The result was this document
maintaining the previous structure of two chapters and covering 17 Basic Scopes (EB-
101 a EB-117) and 46 Service Instructions (IS-201 to IS-246)
It is never too much to repeat that the Basic Guidelines, even without having coercive power,
constitute essential documentation for road engineering, illustrating and
pointing safe paths for achieving satisfactory results, for which
also compete common sense, intelligence, reminiscences, and the ability to unite
practice and theory that should characterize the highway engineer.
I - basic project;
II - executive project;
§2 "Works and services may only be put out to tender when... there is a project"
basic approved by the competent authority...
NEW STRUCTURE
This review process resulted in the new document now presented, which encompasses
17 Basic Scopes (EB-101 to EB-117), and 46 Service Instructions (IS-201 to IS-246).
The previous structure was maintained, considering the two chapters below:
Section 2 covers the relationship and details of the most commonly used Basic Scopes.
at DNIT in its studies and road engineering projects, being destined for its
technical staff, for the definition and framing of services to be performed and in
monitoring of its preparation.
The breadth and differentiation of the subjects addressed, the various criteria adopted in their
development, the constant evolution of procedures, the possibility of using
increasingly the experience of all participating technicians in the road sector and
several other factors make the IPR not consider this document as
a final approach of the subject.
2 - BASIC SCOPES
Basic Guidelines for the Preparation of Road Studies and Projects 18
Basic Guidelines for the Preparation of Road Studies and Projects 19
2 BASIC SCOPES
2.1 DEFINITION
The Basic Scopes are schematic documents that establish the guidelines
basics for the development of the various types of engineering studies and projects,
indicating procedures regarding the successive technical stages to be fulfilled, and
understanding definition, phases, elaboration and presentation of results.
The Basic Scopes aim to guide the technician in formulating the Terms of
References that precede the preparation of studies and road engineering projects,
and therefore, they must always be adapted to the particular conditions of each segment of
road in question. In principle, each Basic Scope relates to a given number of
Service Instructions.
EB-102 Basic Engineering Project for the Implementation and Paving of Highways
EB-108 Studies for the Adaptation of Capacity and Safety of Existing Highways
This is the Review and Update of the text of the Basic Scopes contained in
Basic Guidelines for the Development of Highway Studies and Projects - Basic Scopes
The Service Instructions, edited in 1999 by the Directorate of Technological Development
do DNER/IPR.
a) They were reviewed, without changes to the methodology, but adjusted to the new ones
designations of the phases of the related Service Instructions, the following Scopes
Basics:
b) The other Scopes have been adapted to incorporate the division into Projects.
Basics and Executives, and to attend to the interdependence of related Scopes, in addition to
they will be reviewed in their content due to adjustments in the procedures
recommended methodologies.
c) In the current version, the old EB-106 - Engineering Project for has been eliminated
Highway Rehabilitation with Improvements, as it is satisfactorily covered by
new Scopes EB-106 and EB-107.
e) The current highest number of Basic Scopes, which increased from 14 to 17, resulted from
most frequent use of the division into Basic Project and Executive Project.
3 - SERVICE INSTRUCTIONS
Basic Guidelines for the Preparation of Road Studies and Projects 24
Basic Guidelines for the Preparation of Road Studies and Projects 25
3 SERVICE INSTRUCTIONS
3.1 DEFINITION
The Service Instructions are documents that provide general guidance for the
development of various Studies, Basic Projects, and Executive Projects,
members of certain types of road engineering projects, with indication of
procedures related to the successive technical stages to be fulfilled, including
objective, phases, preparation and presentation of results.
It is important to emphasize that the instructions contained in the Service Instructions must be
always, in each case, to be adjusted to the particular conditions of the segment of
highway under study, in such a way that the quantities of tests, surveys, materials,
equipment and other components, should align with the objectives of the Basic Scope to be
adopted.
IS-227 Aerial photogrammetric restitution and field support for engineering project
bus station
This is a review of the text and the introduction of changes to the Service Instructions.
Constants of the Basic Guidelines for the Preparation of Road Studies and Projects -
Basic Scopes and Service Instructions - 1999, with a view to their adjustment to
Basic Scopes - EB's, revised as outlined in Chapter 1 - Basic Scopes,
aiming at the consolidation of the concepts of Basic Engineering Project and Project
Engineering Executive.
ANNEX A -
BASIC SCOPES
Basic Guidelines for the Development of Road Studies and Projects 30
Basic Guidelines for Developments of Road Studies and Projects 31
ANNEX A1
EB-101 - BASIC SCOPE FOR THE DEVELOPMENT OF STUDIES
TECHNICAL AND ECONOMIC FEASIBILITY OF HIGHWAYS
1 DEFINITION
The technical and economic feasibility study of highways is referred to as the set of
studies developed to evaluate the social and economic benefits arising from
of investments in the implementation of new highways or improvements of highways already
existing. The assessment determines whether the estimated benefits outweigh the costs associated with the
projects and execution of the planned works.
a) Preliminary;
b) Definitive.
3 DEVELOPMENT OF STUDIES
The technical and economic feasibility studies must demonstrate whether the alternative
chosen, focusing on design and technical and operational characteristics, offers
greater benefit than others, in terms of costs.
It will be essential to conduct studies related to the impact of the highway on the environment.
environment and the establishment of a schedule for the execution of the works, in accordance with the
For the purposes of preparing the feasibility study for the implementation of a highway, or
improvements on existing highway, there will be a need to estimate traffic - current and
future, establish the technical and operational characteristics, set the possible guidelines
of the axis.
a) Environmental studies;
c) Complementary research;
EB-101 - Basic Scope for the Preparation of Technical and Economic Feasibility Studies for Highways
Basic Guidelines for the Preparation of Highway Studies and Projects 32
socio-economic survey;
The Environmental Studies must characterize the environmental situation of the area of influence of
enterprise in the physical, biotic, and anthropic aspects, aiming for knowledge
from the region before the implementation of the project, serving as a reference for
assessment of the environmental impacts arising from the construction and operation of the highway, and of the
environmental liabilities.
The Environmental Diagnosis will identify and analyze the possible impacts.
environmental, and identified the environmental liabilities, of the alternatives, at a preliminary level.
In selecting the alternatives, the privileged areas must be identified and weighed.
by law (Biological and Indigenous Reserves, Conservation Units, etc.)
During the preparation of the environmental studies, activities will also be developed.
following:
c) verification with the competent authorities of the existence of restrictive factors for use
only by highway (urban areas and Conservation Units);
The study area of influence, traffic zones, and guidelines should be determined.
technically possible, likely traffic of the various alternatives, class and standard of
highway. For this purpose, surveys, information, and other data may be used.
available regarding the considered region, such as: maps, geographical charts,
aerophotogrammetry, geological and geotechnical studies, volumetric count data
EB-101 - Basic Scope for the Preparation of Technical and Economic Feasibility Studies for Highways
Basic Guidelines for the Preparation of Road Studies and Projects 33
obtained from traffic studies already conducted in the area of interest of the studies
feasibility, and the unit construction costs.
To complement and update the available information, the following will also be necessary
following research:
EB-101 - Basic Scope for the Preparation of Technical and Economic Feasibility Studies for Highways
Basic Guidelines for the Preparation of Highway Studies and Projects 34
user's opinion.
- other information that may be of interest for the study of the highway.
c) Fast registration: after researching and analyzing the available data, go through the
alternatives aiming to identify the relief, classifying the alternatives according to
importance, recording the locations of the main accesses, checking the condition of
pavement conservation, observations related to traffic profile, geometry of
via and relevant data, such as the environmental management of the alternatives considered, by
example.
From the possession of the surveys and complementary research, the following must be determined
current traffic parameters, for each alternative, by type of vehicle. With these
information and with the traffic growth model, determined in the socio-
economic, project traffic for a period of 20 years. The installments should be obtained
estimates of normal, generated, and diverted traffic.
a) indication of the peak factor of the k-th hour, aimed at capacity studies of
via;
b) tabela de volume de tráfego potencial, atual e futuro, para cada alternativa até o
20-year horizon of the project. These elements should consider each year and type.
of vehicle;
c) profile of seasonal traffic variation, as well as the average changes over time
day.
To understand the importance of these calculations, it should be emphasized that the evaluation
identifica os estrangulamentos do tráfego nos segmentos estudados, analisando os
effects on the service levels of the highway and, consequently, the profitability of
introduction of the proposed improvements. For this purpose, the roadmap should be adopted and
the recommended methodology in the Highway Capacity Manual - HCM, updated version.
EB-101 - Basic Scope for Developing Technical and Economic Feasibility Studies for Highways
Basic Guidelines for the Preparation of Road Studies and Projects 35
3.3. FINALPHASE
Based on the potentialities of each alternative studied, and on the methodology adopted
in traffic projections, the benefits to users will be defined as indicated to
to follow
b) indirect benefits: stemming from the social and economic development of the region
in light of the road investments made. The indirect benefits are
expressed in terms of the net growth of local production, of real appreciation
the properties located in the influence area of the highway, of the highest revenue
fiscal, and above all the social evolution, of income and the adequate redistribution of
population residing in the studied region. When necessary for better
representing the costs should adopt the theory of shadow prices.
The direct benefits will be calculated based on a comparative analysis of the costs.
vehicle operations, road maintenance, accidents, and travel time, assessed
EB-101 - Basic Scope for the Preparation of Technical and Economic Feasibility Studies for Highways
Basic Guidelines for the Preparation of Road Studies and Projects 36
the existing alternatives and the same expected costs in light of the implementation of the
new highway or improvements implemented on the existing highway, calculated
for each studied alternative.
EB-101 - Basic Scope for the Preparation of Technical and Economic Feasibility Studies for Highways
Basic Guidelines for the Preparation of Highway Studies and Projects 37
Since they constitute equivalent magnitudes, the net value of the increase of the
local production should not be added to the value of the benefits arising from the
generated traffic.
The benefits resulting from the appreciation of properties located in the area of
direct influence of the highway to be implemented or improved, should only be
incorporated into the benefits with reduced operational costs of the vehicles and,
with the time spent on long-distance travels, from origin to destination
located outside the limits of the considered area.
EB-101 - Basic Scope for the Preparation of Technical and Economic Feasibility Studies for Highways
Basic Guidelines for the Development of Highway Studies and Projects 38
a) Custos de investimento
Implementation cost
Conservation cost
Maintenance cost
The investment required for each alternative studied must include costs of
construction, according to the following items, thus related:
a) Earthworks;
b) Drainage;
e) Paving;
Lighting;
h) Signaling;
i) Supplementary works;
p) Occasional costs;
Operating and maintenance costs for the useful life period (to be defined),
normally considered as 20 years for the case of highways.
EB-101 - Basic Scope for the Preparation of Technical and Economic Feasibility Studies for Highways
Basic Guidelines for the Preparation of Road Studies and Projects 39
When requested in the terms of reference for the services, the cost components in
foreign currency, resulting from credit operations and with import of
equipment, vehicles, building materials, fuels, and others, will be
determined and indicated in their own columns in the cost composition spreadsheets.
a) Implementation costs
b) Conservation costs
This is the cost of the interventions aimed at keeping the highway intact.
adequate techno-operational conditions throughout the analysis period (in general
fixed from 10 to 20 years). The interventions include:
EB-101 - Basic Scope for the Development of Technical and Economic Feasibility Studies for Highways
Basic Guidelines for the Development of Road Studies and Projects 40
c) Maintenance costs
They are the costs of investments that ensure standards of fluidity and safety.
of traffic and of effective service delivery to users. The average values
adopted will be consistent with those practiced by the agency.
The operating costs of the vehicles will be obtained through the methodology of
HDM-4 Highway Development & Management model, currently in use in the field
road transport. The unit costs adopted must be consistent with those
practiced by the agency.
The costs associated with these events must be obtained from the analysis
of traffic conditions for each alternative, checking for the existence of points
critical points and low traffic capacity. After the completion of these
costs corresponding will be calculated. The average values
practices should be consistent with those practiced by the agency.
A comparative analysis will be prepared between the benefits of each alternative and costs.
estimates for implementation. There will be a need for updates to the benefits and the
costs, by applying a capital opportunity rate. They should be calculated.
absolute B/C ratio (benefit/cost), the B-C ratio, and the internal rate of return IRR.
A sensitivity analysis will be presented that considers the effects on the results.
the variations of the main parameters such as traffic estimates, allocated value
the travel time of users, and construction costs.
EB-101 - Basic Scope for the Preparation of Technical and Economic Feasibility Studies for Highways
Basic Guidelines for the Development of Road Studies and Projects 41
For each alternative under study, the following feasibility indicators will be calculated:
− B-C - Updated net benefit (Net Present Value) at a real interest rate of 12% per
yes
− B/C - Relação benefício/custo, à taxa real de juros de 12% ao ano.
These indicators will be calculated (economic and financial), and an analysis will be made of
sensitivity, with successive variations in costs and benefits.
4 PRESENTATION
PRELIMINARY REPORT
EB-101 - Basic Scope for the Preparation of Technical and Economic Feasibility Studies for Highways
Basic Guidelines for the Preparation of Highway Studies and Projects 42
FINAL REPORT
FORMAT
VOLUME TITLE
Impression
Minute
Definitive
Study Report
1 Brief description of the conclusions and results of A-4 A-4
technical and economic studies conducted;
Environmental Assessment Report of the Alternatives -
2 A-4 A-4
RAAA
Justificative Memo
Volume 3.1
3 Economic and traffic studies A-4 A-4
Volume 3.2
Engineering studies
Budget
4 A-4 A-4
Cost of services
EB-101 - Basic Scope for the Preparation of Technical and Economic Feasibility Studies for Highways
Basic Guidelines for the Development of Road Studies and Projects 43
ANNEX A2
EB-102 - BASIC SCOPE FOR THE PREPARATION OF BASIC PROJECT
ENGINEERING FOR THE IMPLEMENTATION AND PAVING OF HIGHWAYS
1 DEFINITION
a) Preliminary Phase;
The Basic Engineering Project for the Implementation and Paving of Highways must
count the following elements:
a) development of the chosen solution in order to provide a global view of the work and
identify all of its constituent elements clearly;
b) global and localized technical solutions, sufficiently detailed, in such a way as to
minimize the need for revisions during the project development phases
executive, and of carrying out the works;
c) identification of the types of services to be executed, of materials to be incorporated into the work and of
equipment to be used, as well as their specifications, in order to ensure the
best results for the venture;
EB-102 - Escopo Básico para Elaboração de Projeto Básico de Engenharia para Implantação e Pavimentação de Rodovias
Basic Guidelines for the Preparation of Highway Studies and Projects 44
The Preliminary Phase is characterized by data collection and the conduct of studies.
specific with the purpose of establishing the Basic Project for implementation and
paving of the highway, therefore being a phase of diagnosis and recommendations
based on the conclusions of the developed studies, through the presentation of
various selected and studied alternatives and the assembly of the work plan for
the next phase, of Basic Project.
b) Traffic Studies;
c) Geological Studies;
d) Hydrological Studies;
If there are already Technical and Economic Feasibility Studies for the road segment to
to be designed, a detailed analysis of the raised elements will be carried out, and to a
substantial assessment of the conclusions of the existing study, always in compliance with
Related Service Instructions above.
EB-102 - Basic Scope for the Preparation of Basic Engineering Project for the Implementation and Paving of Highways
Basic Guidelines for the Preparation of Road Studies and Projects 45
a) Data related to the history of the VMD and fleet composition, obtained from DNIT;
c) Volumetric and classificatory counts, carried out for at least 3 days, in the
situations where traffic data is not available or is
outdated;
EB-102 - Basic Scope for the Development of Basic Engineering Project for the Implementation and Paving of Highways
Diretrizes Básicas para Elaboração de Estudos e Projetos Rodoviários 46
c) Field investigations
It basically consists of the collection of hydrological data (climate, rainfall, river flow and
geomorphology) of the region.
The Environmental Component of the Project, in this Preliminary Phase, consists of the preparation of
Preliminary Environmental Diagnosis of the direct influence area of the Enterprise, and
in the evaluations of the occurrences registered in the environmental assessments, and of the
environmental impacts that may result from the execution of the works, aiming at
proposal of environmental protection measures.
It should characterize the environmental situation of the area of influence of the enterprise in
physical, biotic, anthropic aspects, aiming for knowledge of the region before the
implementation of the enterprise, serving as a reference for assessing the impacts
environmental impacts arising from the construction and operation of the highway, and from environmental liabilities.
In this Preliminary Phase, the Environmental Component of the project must be developed accordingly.
with aIS-246 - Environmental Component of Road Engineering Projects - Phase
Preliminary, to be consolidated by the Preliminary Environmental Assessment Report -
RPAA, which will enable decision-making for the optimization of technical alternatives and
locational, as well as the initiative of DNIT, together with the Licensing Environmental Agency, to
request for the Preliminary License - LP of the Enterprise.
With the approval of the conclusions and recommendations of the Preliminary phase, the
basic project phase, with the purpose of selecting the alignment option to be
consolidated and detail the selected solution, providing plans, drawings and others
elements that enable an adequate identification of the work to be executed
(Quantities, Specifications, and Execution Plan).
a) Traffic Study
EB-102 - Basic Scope for the Preparation of Basic Engineering Project for the Implementation and Paving of Highways
Basic Guidelines for the Preparation of Road Studies and Projects 47
c) Geological Study
d) Hydrological Study
e) Routing Study
f) Topographic Study
g) Estudo Geotécnico
h) Geometric Project
i) Earthwork Project
j) Drainage Project
k) Pavement Project
n) Signage Project
p) Expropriation Project
Environmental Component of the Project
r) Project Budget
EB-102 - Basic Scope for the Elaboration of Basic Engineering Project for the Implementation and Paving of Highways
Basic Guidelines for the Development of Road Studies and Projects 48
In the development of the activities of this Basic Project Phase, the following must be observed
the following aspects:
The preparation of the schematic registration of the highway must indicate the following elements:
EB-102 - Basic Scope for the Development of Basic Engineering Project for the Implementation and Paving of Highways
Basic Guidelines for the Preparation of Road Studies and Projects 49
b) Characterization of the highway sections regarding the type of pavement and layers,
indicating the dimensions of the right-of-way, the platform, the pavement and the
berths;
These studies will aim to evaluate the traffic behavior of the highway, for
homogeneous subsection, during the useful life period, counted from the release of the section to
traffic, based on the existing geometric project and the topographic studies carried out.
For the purposes of this scope, a homogeneous subsegment is understood as one that has the
same geometric characteristics and the same volumes and traffic compositions.
c) Data processing;
d) Traffic projections;
e) Determination of the number N.
b) Geological mapping;
c) Geological description of the review;
d) Recommendations.
EB-102 - Basic Scope for the Preparation of Basic Engineering Project for the Implementation and Pavement of Highways
Basic Guidelines for the Preparation of Highway Studies and Projects 50
The topographic studies for the Basic Project are developed in a single phase, therefore
after the preliminary definition of the routes to be studied and may be carried out by:
Aerial Photogrammetric Coverage and Support for Basic Highway Project – Phase
IS-226
Basic Project (Single Phase)
Aerophotogrammetric Restoration and Field Support for Basic Project
IS-227
Highway - Basic Project Phase (Single Phase)
The topographic survey by conventional process will have the sequence indicated to
to follow
EB-102 - Basic Scope for Preparing Basic Engineering Project for Implementation and Paving of Highways
Basic Guidelines for the Development of Highway Studies and Projects 51
e) Additional surveys
f) Total space
g) Tracking
Geotechnical studies at this stage of the Basic Project must be carried out for the
selected alternatives, referenced to the geological studies (item 3.3.3), and
involving the following activities:
3.3.8. GEOMETRICPROJECT
EB-102 - Basic Scope for the Development of Basic Engineering Project for Implementation and Paving of Highways
Basic Guidelines for the Preparation of Road Studies and Projects 52
b) Study of alternatives for the crossing, regarding the location of implementation of the
work;
c) Study of feasible structural solutions, as a result of the examination of the location
implementation, with a definition, for each proposed solution, of the total length of
work, number of spans, main geometric characteristics, extent of embankments of
access and foundations;
EB-102 - Basic Scope for the Development of Basic Engineering Project for the Implementation and Paving of Highways
Basic Guidelines for the Preparation of Road Studies and Projects 53
With the data obtained in the preparation of the highway registration, where the
deficiencies of the road signs in the section, the signaling project will be developed.
In this Basic Project phase, the Expropriation Project will be limited to an assessment.
the areas to be expropriated, and an estimate of their costs.
These procedures should be based on the Geometric Project developed in this phase.
The Environmental Component of the Project, in this Basic Design Phase, must be
developed according to the following activities:
In this Basic Project Phase, the Environmental Component of the project must be developed.
according to the provisions of IS-246 - Environmental Component of Projects
Highway Engineering - Basic Design Phase.
The Environmental Component of the Project at this Stage will be consolidated by the Basic Report.
of Environmental Assessment - RBAA, which serves as the document to support the
analysis and evaluation of the environmental damages caused by the Enterprise, having as
one of its main functions is to provide the licensing authority with the decision-making tools in the sense
to grant the Installation License - IL, of the Project, whenever
the conduction of the bidding for the work is based on this Basic Engineering Project.
EB-102 - Basic Scope for the Preparation of Basic Engineering Project for the Implementation and Paving of Highways
Basic Guidelines for the Preparation of Road Studies and Projects 54
At the end of the studies developed in this phase, the costs of the work will be defined.
for pavement rehabilitation and the introduction of improvements to increase capacity and
security adopting the methodology recommended in IS-220 Budget of the Work -
Preliminary Phase and Basic Project and the recommendations of the Cost System
Road workers of DNIT - SICRO.
Presentation of the rational sequence of the set of activities that must be executed
of the project, indicating the problems of climatic, administrative, technical nature and
segurança; época do início dos trabalhos; período de execução; conseqüência da
location, type of work and other conditioning factors for construction, including
implications with traffic, in the case of existing highways.
The Execution Plan for the work, to be prepared for each construction lot, will include
consideration of the aspects related to climate and rainfall, particularly regarding
to the rainy season and number of rainy days per month, logistical support, deadline for the
execution of the works, minimum equipment, and service attack plan.
EB-102 - Basic Scope for the Preparation of Basic Engineering Project for Implementation and Paving of Highways
Basic Guidelines for the Preparation of Road Studies and Projects 55
At the end of the Preliminary Phase, the Preliminary Report of the Basic Project will be presented.
containing the conclusions of the studies developed and the proposed recommendations, the
which will be constituted by the volumes listed below.
PRELIMINARY REPORT
4.2.1. MINUTES
At the end of the Basic Design Phase, the Draft of the Final Report will be presented.
Basic Project, in 4 volumes, as per the list below.
FINAL REPORT
After the approval of the Draft, the Final Report's Definitive Print will be presented.
of the Basic Project, according to the volumes listed below.
EB-102 - Basic Scope for the Preparation of Basic Engineering Project for the Implementation and Paving of Highways
Basic Guidelines for the Development of Road Studies and Projects 56
ANNEX A3
EB-103 - BASIC SCOPE FOR THE DEVELOPMENT OF EXECUTIVE PROJECT
ENGINEERING FOR THE IMPLEMENTATION AND PAVING OF ROADS
1 DEFINITION
a) Preliminary Phase
This Basic Scope pertains to the Executive Engineering Project for Implementation and
Paving of Highways, to be developed consecutively to the respective
Preliminary studies and the respective basic project, allowing to characterize the work
completely from the execution point of view, and containing all the elements of the phases
previous ones, supplemented by the level of detail specific to the Executive Project, so that
to provide a comprehensive overview of the work and identify all its constructive elements
clearly.
The Preliminary Phase is characterized by data collection and the conduct of studies.
specific with the purpose of establishing the Basic Project for implementation and
pavement of the highway, therefore being a phase of diagnosis and recommendations
based on the conclusions of the studies developed, through the presentation of
various selected and studied alternatives and the assembly of the work plan for
the next phase, of Basic Design.
b) Traffic Studies;
EB-103 - Basic Scope for the Preparation of an Executive Engineering Project for the Implementation and Paving of Highways
Basic Guidelines for the Preparation of Road Studies and Projects 57
c) Geological Studies;
d) Hydrological Studies;
e) Estudos de Traçado; e
Environmental Component of the Project.
If a Basic Project has already been prepared for the road segment to be executed
designed, a detailed analysis of the raised elements will be carried out, and to a
substantial evaluation of the conclusions of the Preliminary Phase of the existing Basic project,
always in accordance with the above-mentioned Service Instructions.
EB-103 - Basic Scope for the Development of an Executive Engineering Project for the Implementation and Paving of Highways
Basic Guidelines for the Development of Highway Studies and Projects 58
a) Data related to the history of the VMD and fleet composition, obtained from DNIT;
c) Volumetric and classificatory counts, carried out for at least 3 days, in the
situations where traffic data is not available or is
outdated;
c) Field investigations
It basically consists of the collection of hydrological data (climate, precipitation, river flow and
geomorphology of the region.
The trace studies will primarily aim to identify the alternatives for
tracing to be considered in the conduct of studies and the preparation of the registry
topographical.
EB-103 - Basic Scope for the Development of Executive Engineering Project for the Implementation and Paving of Highways
Basic Guidelines for the Preparation of Highway Studies and Projects 59
The Environmental Component of the Project, in this Preliminary Phase, consists of the preparation of
Preliminary Environmental Diagnosis of the area of direct influence of the Enterprise, and in the
evaluations of the occurrences registered in environmental surveys, and of the impacts
environmental impacts that may arise from the execution of the works, aiming at the proposal of
environmental protection measures.
It must characterize the environmental situation of the area of influence of the enterprise in
physical, biotic, anthropogenic aspects, aiming for knowledge of the region before the
implementation of the project, serving as a reference for evaluating the impacts
environmental impacts arising from the works and operation of the highway, and from environmental liabilities.
In this Preliminary Phase, the Environmental Component of the project must be developed accordingly.
with aIS-246 - Environmental Component of Road Engineering Projects - Phase
Preliminary, to be consolidated by the Preliminary Environmental Assessment Report -
RPAA, which will allow decision-making for the optimization of technical alternatives and
locational, as well as the initiative of DNIT, together with the Licensing Environmental Agency, to
request for the Preliminary License - LP of the Enterprise.
With the approval of the conclusions and recommendations from the Preliminary phase, the
basic design phase, with the purpose of selecting the routing alternative to be
consolidated and detail the selected solution, providing plans, drawings and others
elements that enable an adequate identification of the work to be executed.
a) Traffic Study
c) Geological Study
d) Hydrological Study
e) Route Study
f) Topographic Study
g) Geotechnical Study
h) Geometric Project
Earthworks Project
j) Drainage Project
k) Pavement Project
EB-103 - Basic Scope for the Development of Executive Engineering Project for the Implementation and Paving of Highways
Basic Guidelines for the Preparation of Road Studies and Projects 60
n) Signage Project
p) Expropriation Project
Environmental Component of the Project
If there is already a Basic Project prepared for the road segment to be executed.
designed, a detailed reassessment of its Basic Design phase will be carried out, the
starting from:
EB-103 - Basic Scope for the Development of Engineering Executive Project for the Implementation and Paving of Highways
Basic Guidelines for the Preparation of Road Studies and Projects 61
a) Evaluation of the basic project developed, considering the necessary services for
execution of the work and corresponding costs;
c) Evaluation of any and all observations deemed relevant and that come
modify any conclusion or recommendation of the existing Basic Project;
d) Elaboration of a conclusive opinion regarding the solutions presented in the Basic Project
existing through the analysis of its Presentation Volumes (Volumes 1, 2, 3, and 4)
In case there is a need for a complement to the proposed solutions of the project
Existing basics, the corresponding Service Instructions must be followed.
In the development of the activities of this Basic Project Phase, the following must be observed
the following aspects:
The preparation of the schematic registration of the highway must indicate the following elements:
These studies will aim to evaluate the traffic behavior of the highway,
homogeneous subsegment, during the useful life period, counted from the release of the segment to
traffic, based on the existing geometric design and the topographic studies carried out.
For the purpose of this scope, a homogeneous subsection is understood to be one that has the
same geometric characteristics and the same volumes and traffic compositions.
EB-103 - Basic Scope for the Preparation of an Executive Engineering Project for the Implementation and Paving of Highways
Basic Guidelines for the Development of Road Studies and Projects 62
c) Data processing;
d) Traffic projections;
e) Determination of the number N.
b) Geological mapping;
c) Geological description of the review;
d) Recommendations.
The topographic studies for the Basic Project develop in a single phase, therefore
after the preliminary definition of the routes to be studied and can be carried out by:
EB-103 - Basic Scope for the Development of Executive Engineering Project for the Implementation and Paving of Highways
Basic Guidelines for the Preparation of Road Studies and Projects 63
Aerial Photogrammetry Coverage and Support for Basic Road Project - Phase
IS-226
Basic Project (Single phase)
Aerophotogrammetric Restitution and Field Support for Basic Project of
IS-227
Highway - Basic Project Phase (Single Phase)
The topographic survey through the conventional process will follow the indicated sequence.
follow
e) Complementary surveys
total spaces
g) Tracking
Geotechnical studies at this Basic Project phase should be carried out for the
selected alternatives, referenced to the geological studies (item 3.3.3), and
involving the following activities:
EB-103 - Basic Scope for the Elaboration of Engineering Executive Project for the Implementation and Paving of Highways
Basic Guidelines for the Preparation of Road Studies and Projects 64
The basic paving project includes the definition of the pavement design,
starting from the preliminary sizing and structural solutions of the pavement, which must
to be subject to technical-economic analysis, and the estimation of service quantities:
b) Study of alternatives for the crossing, regarding the implantation location of the
work;
EB-103 - Basic Scope for the Preparation of Executive Engineering Project for the Implementation and Pavement of Highways
Basic Guidelines for the Preparation of Road Studies and Projects 65
c) Study of feasible structural solutions, resulting from the examination of the location
implementation, with definition, for each proposed solution, of the total length of the
work, number of spans, main geometric characteristics, length of the embankments of
access and foundations;
With the data obtained in the preparation of the highway registration, where the were marked the
deficiencies of the road signaling of the section, the basic project will be prepared
signaling.
In this Basic Project phase, the Expropriation Project will be limited to an assessment.
the areas to be expropriated, and an estimate of their costs.
These procedures should be based on the Geometric Project developed in this phase.
The Environmental Component of the Project, in this Basic Design Phase, should be
developed according to the following activities:
EB-103 - Basic Scope for the Development of Executive Engineering Project for Implementation and Paving of Highways
Basic Guidelines for the Preparation of Road Studies and Projects 66
In this Basic Design Phase, the Environmental Component of the project must be developed.
according to the provisions of IS-246 - Environmental Component of Projects
Road Engineering - Basic Project Phase.
The Environmental Component of the Project at this Stage will be consolidated by the Basic Report.
of Environmental Assessment - RBAA, which acts as the document to support the
analysis and evaluation of the environmental damage caused by the Enterprise, having as
one of its main functions is to provide tools for the licensing authority's decision making in the sense of
to grant the Installation License - LI, of the Enterprise, whenever the
the bidding for the work is based on this Basic Engineering Project.
At the end of the studies developed in this phase, the costs of the work will be defined.
for pavement rehabilitation, and the introduction of improvements to increase capacity and
segurança adotando-se a metodologia preconizada naIS-220 Orçamento da Obra -
Preliminary and Basic Project Phases and the recommendations of the Cost System
Road workers of DNIT - SICRO.
With the approval of the conclusions and recommendations of the Basic Design Phase, it will be
the executive project phase has started, with the purpose of detailing the selected solution,
providing plans, drawings, and service notes that allow for the construction of the
road. The following elements must be provided:
The Environmental Component of the Project at this Executive Project Phase consists of
detailed planning and budgeting of environmental protection measures, both corrective and preventive
preventive measures, indicated in the Basic Project Phase, aimed at rehabilitation/recovery
of environmental liability and the execution of works in an environmentally correct manner.
EB-103 - Basic Scope for the Preparation of Engineering Executive Project for Implementation and Paving of Highways
Basic Guidelines for the Preparation of Road Studies and Projects 67
In this Executive Project Phase, the Environmental Component of the Project will be prepared from
in accordance with the provisions of IS-246 - Environmental Component of Projects
Road Engineering - Executive Project Phase.
In the case where the bidding for the work is based on this Executive Project of
Engineering, the Final Environmental Assessment Report - RFAA must provide
additional information that allows DNIT to request from the Environmental Body
Licensor, the Installation License - LI, of the Enterprise.
The activities to be developed in this phase must comply with the provisions in
Service Instructions:
EB-103 - Basic Scope for the Development of Executive Engineering Project for the Implementation and Paving of Highways
Basic Guidelines for the Development of Road Studies and Projects 68
The technical team responsible for the development of the Component must be presented.
Project Environment, indicating the name, the professional area, and the registration number in.
respective class council of each team member.
At the end of the Preliminary Phase, the Preliminary Project Report will be presented
Executive summary, containing the conclusions of the studies conducted and the recommendations
proposals, which will be constituted by the volumes listed below.
PRELIMINARY REPORT
EB-103 - Basic Scope for the Development of Executive Engineering Project for the Implementation and Paving of Highways
Basic Guidelines for the Preparation of Road Studies and Projects 69
At the end of the basic project phase, the Basic Project Report will be presented.
Executive, containing the proposed solutions, indicative charts of the characteristics
techniques and operations, quantitative services and preliminary projects, consisting of
following volumes:
BASIC REPORT
Finalizing the preparation of the Executive Project, the Final Report will be presented.
Executive Project, initially in the form of a draft. After examination and approval of the
DNIT will be presented in the form of a definitive print. The Final Report will be
consisting of the following volumes:
FINAL REPORT
FORMAT
VOLUME TITLE
Impression
Minute
Definitive
EB-103 - Basic Scope for the Preparation of Executive Engineering Project for the Implementation and Paving of Highways
Basic Guidelines for the Preparation of Road Studies and Projects 70
ANNEX A4
EB-104 - BASIC SCOPE FOR THE ELABORATION OF BASIC PROJECT
ENGINEERING FOR ROAD REHABILITATION
WITH LOW-COST IMPROVEMENTS
1 DEFINITIONS
It consists of the set of studies and projects developed with the primary objective of
reinforcing the existing pavement, by adding new structural layers or by
replacement of one or more layers, so that the resulting structure can
economically support the repetition of load per axis during the new
project period established, in conditions of comfort and safety for the
user, during the new project period established. The following must be observed:
provisions of the Basic Scope EB-114: Basic Engineering Project for
Pavement Rehabilitation of the Highway.
c) Sound devices;
d) Implementation of delineators;
EB-104 - Basic Scope for the Preparation of Basic Engineering Project for the Rehabilitation of Highway with Low-Cost Improvements
Basic Guidelines for the Development of Road Studies and Projects 71
a) Preliminary Phase;
The Basic Engineering Project for the Rehabilitation of Highways with Low Improvements
Cost should include the following elements:
a) development of the chosen solution in order to provide a global view of the work and
identify all its constituent elements clearly;
c) identification of the types of services to be executed, of materials to be incorporated into the work and of
equipment to be used, as well as their specifications, in order to ensure the
best results for the venture;
f) budget for the overall cost of the work, based on service quantities and
supplies of materials and properly assessed transportation.
The preliminary phase is characterized by surveys and studies of the current conditions of the
highway with the purpose of establishing the basic project for its rehabilitation,
being, therefore, a phase of diagnosis and recommendations based on the conclusions
of the studies developed (including physical and operational improvements), through the
EB-104 - Basic Scope for the Preparation of Basic Engineering Project for the Rehabilitation of Roads with Low-Cost Improvements
Basic Guidelines for the Development of Road Studies and Projects 72
presentation of the various alternatives studied and work plan for the phase of
basic project.
b) Traffic studies;
d) Geological studies;
e) Hydrological studies;
f) Preliminary Evaluation of the Existing Pavement, and
In the development of the activities of this Preliminary Phase, the following must be addressed
following aspects:
c) Information about the existing pavement, covering the characteristics of the subgrade,
thickness and composition of the pavement layers, nature and execution period
of any rehabilitation and maintenance work; and
a) Data related to the history of the VMD and fleet composition, obtained from DNIT;
EB-104 - Basic Scope for the Preparation of Basic Engineering Project for Highway Rehabilitation with Low-Cost Improvements
Basic Guidelines for the Preparation of Road Studies and Projects 73
a) Stretch Registration;
After the collection and analysis of data on accidents, the section should be inspected.
aiming to detect failures in the adopted traffic engineering system, in what it says
regarding visibility deficiencies, geometry issues, superelevation
inadequate, poor or non-existent signage, insufficient road capacity, locations
unsuitable for pedestrian crossings, among others.
c) Field investigation
EB-104 - Basic Scope for the Preparation of Basic Engineering Project for Highway Rehabilitation with Low-Cost Improvements
Basic Guidelines for the Preparation of Road Studies and Projects 74
It basically consists of the collection of hydrological data (climate, rainfall, river flow, and
geomorphology) of the region.
The preliminary studies of the existing pavement, for the purpose of identifying solutions
alternatives should encompass the analysis of existing field surveys with the
objective of determining the functional and structural conditions for identification of the
solutions.
The Environmental Component of the Project, in this Preliminary Phase, consists of the preparation of
Diagnóstico Preliminar Ambientalda área de influência direta do Empreendimento, e
In the evaluations of the occurrences registered in the environmental surveys, and of the
environmental impacts that may arise from the execution of the works, aiming at
proposal of environmental protection measures.
It should characterize the environmental situation of the area influenced by the enterprise in
physical, biotic, anthropogenic aspects, aiming for an understanding of the region before the
implementation of the enterprise, serving as a reference for assessing the impacts
environmental impacts arising from the construction and operation of the highway, and from environmental liabilities.
In this Preliminary Phase of the Environmental Component of the project, it must be prepared for
agreement with aIS-246 - Environmental Component of Road Engineering Projects
Preliminary Phase, to be consolidated by the Preliminary Environmental Assessment Report
RPAA, which will enable decision-making for the optimization of technical alternatives and
locational, as well as the initiative of DNIT, with the Licensing Environmental Agency, to
request for the Preliminary License - LP of the Project.
The basic project phase is characterized by the study of the current conditions of the highway with
the purpose of establishing a project for recovery, diagnosis, and recommendations. This
conjugate recovery measures for existing roads, low cost covering the
environmental passive, with no need to develop a routing study.
A study will be conducted on the degree of degradation reached by the pavement, determining its
causes and preliminarily assessing the cost of recovery.
Being common highways with paved lanes, with dirt shoulders and
deprived of surface drainage work, it is understood that together with the
the recovery of the pavement of the runways should study the system of
surface drainage and check the need to pave the shoulders.
EB-104 - Basic Scope for the Preparation of Basic Engineering Project for Highway Rehabilitation with Low-Cost Improvements
Basic Guidelines for the Preparation of Road Studies and Projects 75
b) Traffic Study
c) Geological Study
d) Hydrological Study
e) Topographic Study
Geotechnical Study
g) Geometric Project
h) Drainage Project
j) Signage Project
m) Project Budget
EB-104 - Basic Scope for the Development of Basic Engineering Project for the Rehabilitation of Highway with Low-Cost Improvements
Basic Guidelines for the Preparation of Road Studies and Projects 76
In the development of the activities of this Basic Project Phase, the following must be observed
the following aspects:
The preparation of the schematic registration of the highway should indicate the following elements:
EB-104 - Basic Scope for the Development of Basic Engineering Project for Rehabilitation of Highway with Low-Cost Improvements
Basic Guidelines for the Preparation of Road Studies and Projects 77
These studies will aim to evaluate the traffic behavior of the highway, by
homogeneous segment, during the useful life period, counted from the release of the segment to
traffic, based on the existing geometric design and the topographic studies conducted.
For the purposes of this scope, a homogeneous subsection is understood to be one that has the
the same geometric characteristics and the same volumes and traffic compositions.
c) Data processing;
d) Traffic projections;
e) Determination of the number N.
b) Geological mapping;
c) Geological description of the region;
d) Recommendations.
a) Collection of local information and with conservation teams regarding the operation
two devices for surface and deep drainage;
EB-104 - Basic Scope for the Development of Basic Engineering Project for the Rehabilitation of Highway with Low-Cost Improvements
Basic Guidelines for the Preparation of Road Studies and Projects 78
The topographic studies, for this phase of the Basic Project, are limited to the survey.
cadastral of the existing highway right of way.
e) Registration and selection of quarries, sandbanks, and other materials existing along
from the highway, which may be used in the pavement rehabilitation project;
Methodology Title
The existing pavement being Rigid Pavement, the following must be observed
methodologies:
EB-104 - Basic Scope for the Preparation of Basic Engineering Project for the Rehabilitation of Highway with Low-Cost Improvements
Basic Guidelines for the Preparation of Road Studies and Projects 79
Methodology Title
Based on the Geotechnical Studies and the Evaluation of the Existing Pavement, a report will be prepared.
The Basic Rehabilitation Project of the Pavement, based on the Service Instructions and
Next rules:
Norma Activity
In the development of the Pavement Rehabilitation Project, at this stage, the following should be adopted
the following criteria:
a) size the pavement using, at least, three methods indicated in the table
previous
b) adopt layer thicknesses of reinforcement provided by the method that best fits
adapted to the functional and structural conditions of each homogeneous segment;
c) compare the costs of the alternatives in order to choose the most appropriate solution and
present the justification for the chosen solution in volume 3.
EB-104 - Basic Scope for Developing Basic Engineering Project for Highway Rehabilitation with Low-Cost Improvements
Basic Guidelines for the Development of Road Studies and Projects 80
The Pavement Rehabilitation Project must contain, at a minimum, the following elements:
− Physical schedule;
The existing pavement being a rigid pavement, the methodologies must be observed.
exposed in the Rigid Pavement Manual of DNIT, currently under revision in
IPR.
With the data obtained in the preparation of the highway registration, where were marked the
deficiencies of the road signaling in the stretch, a signaling project will be developed.
It will be developed including the replacement or repairs of defenses, barriers, and fences.
delimitation and possible containment works.
The Environmental Component of the Project, in this Basic Project Phase, must be
developed according to the following activities:
EB-104 - Basic Scope for the Preparation of Basic Engineering Project for Road Rehabilitation with Low-Cost Improvements
Basic Guidelines for the Preparation of Road Studies and Projects 81
In this Basic Design Phase, the Environmental Component of the project must be developed.
according to the provisions of IS-246 - Environmental Component of Projects
Road Engineering - Basic Design Phase.
The Environmental Component of the Project at this Stage will be consolidated by the Basic Report.
of Environmental Assessment - RBAA, which is configured as the document to support the
analysis and assessment of the environmental damages caused by the Enterprise, having as
one of its main functions is to provide the licensing authority with the necessary tools to make a decision
to grant the Installation License - LI, of the Enterprise, whenever the
the conduct of the bidding for the work is based on this Basic Engineering Project.
At the end of the work developed in this phase, the costs of the services will be estimated.
para reabilitação do pavimento e introdução de recursos de baixo custo, adotando-se a
methodology recommended in IS-220 Budget of the work - Basic Project phase and in
recommendations of the Road Cost System of DNIT - SICRO.
Presentation of the rational sequence of the set of activities that should be executed
of the project, indicating the problems of a climatic, administrative, technical and
security; time of the start of the work; execution period; consequence of
location, type of work and other conditioning factors for construction, including
implications with traffic, in the case of existing highways.
The Execution Plan for the work, to be prepared for each construction lot, will take into account
considering the aspects related to climate and rainfall, especially regarding
to the rainy season and number of rainy days per month, logistical support, deadline for the
execution of the works, minimum equipment and service attack plan.
At the end of the Preliminary Phase, the Preliminary Report of the Basic Project will be presented,
containing the conclusions of the developed studies and the proposed recommendations, the
which will be constituted by the volumes listed below.
PRELIMINARY REPORT
EB-104 - Basic Scope for the Preparation of Basic Engineering Project for Rehabilitation of Highway with Low-Cost Improvements
Basic Guidelines for the Development of Road Studies and Projects 82
4.2.1. MINUTE
At the end of the Basic Project, the Draft of the Final Project Report will be presented.
Basic, in 4 volumes, as per the list below.
After the approval of the Draft, the Final Report's Definitive Print will be presented.
of the Basic Project, according to the volumes below.
EB-104 - Basic Scope for the Preparation of Basic Engineering Project for Highway Rehabilitation with Low-Cost Improvements
Basic Guidelines for the Preparation of Highway Studies and Projects 83
ANNEX A5
EB-105 - EXECUTIVE ENGINEERING PROJECT FOR REHABILITATION
OF THE HIGHWAY WITH LOW-COST IMPROVEMENTS
1 DEFINITIONS
It consists of the set of studies and projects developed with the aim of reinforcing the
existing pavement, either by adding new structural layers, or by replacement of
one or more layers of the pavement, in such a way that the resulting structure can
economically support the repetition of the loads per axle incident, under conditions of
safety and comfort for the user, during the new project period.
c) Sound devices;
d) Implementation of delineators;
e) Construction of platforms on the shoulders for localized conversions;
EB-105 - Executive Engineering Project for Highway Rehabilitation with Low-Cost Improvements
Basic Guidelines for the Development of Road Studies and Projects 84
a) Preliminary Phase;
This Basic Scope refers to the Executive Engineering Project for Rehabilitation of
Highway with Low-Cost Improvements, to be developed consecutively to
respective Preliminary Studies and the respective Basic Project, allowing to characterize the
work completely from the execution point of view, and containing all the elements of the
previous phases, added with the level of detail specific to the Executive Project, such that
It provides a global view of the work and identifies all its elements.
constructive with clarity.
The preliminary phase is characterized by surveys and studies of the current conditions of the
highway with the purpose of establishing the basic project for its rehabilitation,
being, therefore, a phase of diagnosis and recommendations based on the conclusions
from the studies developed (including physical and operational improvements), through the
presentation of the various alternatives studied and work plan for the phase of
basic project.
b) Traffic studies;
d) Geological studies;
e) Hydrological studies;
f) Preliminary Assessment of the Existing Pavement, and
EB-105 - Executive Engineering Project for Road Rehabilitation with Low-Cost Improvements
Basic Guidelines for the Preparation of Road Studies and Projects 85
If there is already a Basic Project prepared for the road segment to be executed
designed, a detailed analysis of the raised elements will be carried out, and to a
substantial assessment of the conclusions of the Preliminary Phase of the existing Basic Project,
always in accordance with the above-related Service Instructions.
In the development of the activities of this Preliminary Phase, the following must be observed:
following aspects:
c) Information about the existing pavement, covering the characteristics of the subgrade,
thickness and composition of the pavement layers, nature and execution period
on potential rehabilitation and maintenance work; and
EB-105 - Executive Engineering Project for Rehabilitation of Highway with Low-Cost Improvements
Basic Guidelines for the Preparation of Road Studies and Projects 86
a) Data related to the history of VMD and fleet composition, obtained from DNIT;
c) Volume and classification counts, carried out for at least 3 days, in the
situations where traffic data is not available or is
outdated;
After the collection and analysis of data on accidents, the section must be inspected.
aiming to detect failures in the adopted traffic engineering system, concerning
regarding visibility deficiencies, geometry issues, superelevation
inadequate, poor or non-existent signage, insufficient road capacity, locations
unsuitable for pedestrian crossings, among others.
EB-105 - Executive Engineering Project for Road Rehabilitation with Low-Cost Improvements
Basic Guidelines for the Preparation of Highway Studies and Projects 87
c) Field investigations
Basically consists of the collection of hydrological data (climate, rainfall, river flow and
geomorphology) of the region.
The preliminary studies of the existing pavement, for the purpose of identifying the solutions
alternatives should encompass the analysis of existing field surveys with the
objective of determining the functional and structural conditions for identification of the
solutions.
The Environmental Component of the Project, in this Preliminary Phase, consists of the preparation of
Preliminary Environmental Diagnosis of the direct influence area of the Enterprise, and
in the assessments of the occurrences registered in the environmental surveys, and of the
environmental impacts that may arise from the execution of the works, aiming at
proposed measures for environmental protection.
It must characterize the environmental situation of the influence area of the enterprise in
physical, biotic, anthropic aspects, aiming for an understanding of the region before the
implantação do empreendimento, servindo de referência para avaliação dos impactos
environmental impacts arising from the works and operation of the highway, and from environmental liabilities.
In this Preliminary Phase of the Environmental Component of the project, it must be developed
agreement with aIS-246 - Environmental Component of Road Engineering Projects
Preliminary Phase, to be consolidated by the Preliminary Environmental Assessment Report
RPAA, which will enable decision-making for the optimization of technical alternatives and
locational, as well as the initiative of DNIT, together with the Licensing Environmental Agency, to
request for the Preliminary License - LP of the Undertaking.
The basic design phase is characterized by the study of the current conditions of the highway with
the purpose of establishing a project for recovery, diagnosis, and recommendations. This
conjugate recovery measures for existing highways, at low cost, covering the
environmental liability, with no need to develop a route study.
A study will be conducted on the degree of degradation reached by the pavement, determining its
causes and preliminarily assessing the recovery cost.
EB-105 - Executive Engineering Project for Highway Rehabilitation with Low-Cost Improvements
Basic Guidelines for the Preparation of Road Studies and Projects 88
Being common roadways with paved lanes, with dirt shoulders and
lacking surface drainage works, it is understood that together with the
the recovery of the pavement of the runways must study the system of
surface drainage and check the need to pave the shoulders.
b) Traffic Study
c) Geological Study
d) Hydrological Study
e) Topographic Study
Geotechnical Study
g) Drainage Project
i) Signaling Project
Project Budget
EB-105 - Executive Engineering Project for Road Rehabilitation with Low-Cost Improvements
Basic Guidelines for the Preparation of Road Studies and Projects 89
If there is already a Basic Project prepared for the road segment to be executed
designed, a detailed re-evaluation of its Basic Project phase will be carried out,
to leave from:
a) Evaluation of the basic project developed, considering the necessary services for the
execution of the work and corresponding costs;
c) Evaluation of all and any observations deemed relevant and that may come
to modify any conclusion or recommendation of the existing Basic Project;
d) Preparation of a conclusive opinion regarding the solutions presented in the Basic Project
existing through the analysis of its Presentation Volumes (Volumes 1, 2, 3, and 4)
In the development of the activities of this Basic Project Phase, the following must be observed:
the following aspects:
The preparation of the schematic registration of the highway must indicate the following elements:
EB-105 - Executive Engineering Project for Highway Rehabilitation with Low-Cost Improvements
Basic Guidelines for the Preparation of Road Studies and Projects 90
These studies will aim to evaluate the traffic behavior of the highway, by
homogeneous subsection, during the useful life period, counted from the release of the section to
traffic, based on the existing geometric design and the topographical studies carried out.
For the purpose of this scope, a homogeneous subsegment is understood to be one that has the
same geometric characteristics and the same volumes and traffic compositions.
c) Data processing;
d) Traffic projections;
e) Determination of the number N.
b) Geological mapping;
c) Geological description of the region;
d) Recommendations.
EB-105 - Executive Engineering Project for Road Rehabilitation with Low-Cost Improvements
Basic Guidelines for the Preparation of Road Studies and Projects 91
a) Collection of local information and with conservation teams regarding the operation
two devices for surface and deep drainage;
The topographic studies for this phase of the Basic Project are limited to the survey.
cadastre of the domain strip of the existing highway.
e) Registration and selection of quarries, sandbanks, and other materials existing along
from the highway, which may be used in the pavement rehabilitation project;
EB-105 - Executive Engineering Project for Road Rehabilitation with Low-Cost Improvements
Basic Guidelines for the Development of Road Studies and Projects 92
Flexible and Semi-Rigid Pavements - Basic Project Phase and the methodologies
follow indicated:
Methodology Title
The existing pavement being Rigid Pavement, the following should be observed
methodologies:
Methodology Title
Based on the Geotechnical Studies and the Evaluation of the Existing Pavement, a report will be prepared.
the Basic Rehabilitation Project of the Pavement, based on the Service Instructions and
Following rules:
EB-105 - Executive Engineering Project for Highway Rehabilitation with Low-Cost Improvements
Basic Guidelines for the Preparation of Road Studies and Projects 93
Norma Activity
In the preparation of the Pavement Rehabilitation Project, at this stage, the following should be adopted
the following criteria:
a) dimension the pavement using at least three methods indicated in the table
anterior
b) adopt the thicknesses of the reinforcement layer provided by the method that best fits
adapt to the functional and structural conditions of each homogeneous segment;
c) compare the costs of the alternatives in order to choose the most suitable solution and
present the justification for the chosen solution in volume 3.
The basic rehabilitation project for the pavement must contain, at a minimum, the following
elements:
− Physical schedule;
The existing pavement being a rigid pavement, the methodologies must be observed.
exposed in the Rigid Pavement Manual of DNER, currently under revision in
IPR.
EB-105 - Executive Engineering Project for the Rehabilitation of a Highway with Low-Cost Improvements
Basic Guidelines for the Preparation of Road Studies and Projects 94
With the data obtained in the preparation of the highway registration, where the were marked the
deficiencies in the road signage of the section, the signage project will be developed.
The Environmental Component of the Project, in this Basic Project Phase, must be
developed according to the following activities:
In this Basic Project Phase, the Environmental Component of the project must be developed.
according to the provisions of IS-246 - Environmental Component of Projects
Road Engineering - Basic Project Phase.
The Environmental Component of the Project in this Phase will be consolidated by the Basic Report.
of Environmental Assessment - RBAA, which serves as the document to support the
analysis and assessment of the environmental damage caused by the Enterprise, aimed at
one of its main functions is to instrumentalize the decision of the licensing authority in the sense
to grant the Installation License - LI, of the Enterprise, whenever the
the bidding for the work is based on this Basic Engineering Project.
At the end of the work carried out in this phase, the costs of the services will be estimated.
for the rehabilitation of the pavement, and introduction of low-cost improvements adopting
methodology recommended in IS-220 Budget of the work - Basic Project Phase and in the
recommendations from the Road Cost System of DNIT - SICRO.
With the approval of the conclusions and recommendations of the Basic Design Phase will be
the Executive Project phase has begun with the purpose of detailing the selected solution,
EB-105 - Executive Engineering Project for Road Rehabilitation with Low-Cost Improvements
Basic Guidelines for the Preparation of Road Studies and Projects 95
providing plants, drawings and service notes that allow for the construction of
highway. The following elements must be provided:
The Environmental Component of the Project in this Executive Project Phase consists of
detailing and budgeting of environmental protection measures, both corrective and
preventive measures, indicated in the Basic Design Phase, aiming at rehabilitation/recovery
the environmental liability and the execution of the works in an environmentally correct manner.
In this Executive Project Phase, the Environmental Component of the Project will be developed from
in accordance with the provisions of IS-246 - Environmental Component of Projects
Road Engineering - Executive Design Phase.
The Environmental Component of the Project, at this Stage, will be consolidated by the Final Report.
Environmental Assessment - RFAA that should contain the elements that characterize the
detailing of the environmental protection measures established in the Design Phase
Basic.
In the case where the bidding for the work is based on this Executive Project of
Engineering, the Final Environmental Assessment Report - RFAA must provide
additional information that allows DNIT to request from the Environmental Agency
Licensor, the Installation License - LI, of the Enterprise.
The activities to be developed in this phase must comply with the provisions in
Service Instructions:
EB-105 - Executive Engineering Project for Highway Rehabilitation with Low-Cost Improvements
Basic Guidelines for the Preparation of Highway Studies and Projects 96
At the end of the Preliminary Phase, the Preliminary Project Report will be presented.
Executive summary, containing the conclusions of the studies conducted and the recommendations
proposals, which will consist of the volumes listed below.
PRELIMINARY REPORT
At the end of the Basic Design phase, the Basic Project Report will be presented.
Executive, containing the proposed solutions, indicative tables of the characteristics
techniques and operational and quantitative services, composed of the following volumes:
BASIC REPORT
EB-105 - Executive Engineering Project for Highway Rehabilitation with Low-Cost Improvements
Basic Guidelines for the Preparation of Highway Studies and Projects 97
Finalizing the preparation of the Executive Project, the Final Report will be presented.
Executive Project, initially in the form of a Draft. After examination and approval by DNIT,
will be presented in the form of a Final Print. The Final Report will consist of
by the following volumes:
FINAL REPORT
FORMAT
VOLUME TITLE
Printing
Minute
Definitive
EB-105 - Executive Engineering Project for Highway Rehabilitation with Low-Cost Improvements
Basic Guidelines for the Preparation of Road Studies and Projects 98
ANNEX A6
EB-106 - BASIC ENGINEERING PROJECT FOR HIGHWAY REHABILITATION
WITH IMPROVEMENTS FOR ADJUSTING CAPACITY AND SAFETY
1 DEFINITIONS
It also consists of the introduction of improvements for capacity and safety adjustment,
related to problems not directly linked to the existing pavement, such as:
line improvements for the elimination of critical points, duplication of the track,
construction of side streets, implementation of third lanes, construction and/or
rearrangement of intersections and accesses, urban crossings, reinforcement and widening of
special works of art and construction of walkways for pedestrian crossing.
a) Preliminary Phase;
The Basic Engineering Project for the Rehabilitation of Highways with Improvements for
The adequacy of Capacity and Safety must contain the following elements:
EB-106 - Basic Engineering Project for the Rehabilitation of a Highway with Improvements for Capacity and Safety Adequacy
Basic Guidelines for the Elaboration of Highway Studies and Projects 99
a) development of the chosen solution in order to provide a global view of the work and
identify all its constituent elements clearly;
c) identification of the types of services to be performed, of materials to be incorporated into the work and of
equipment to be used, as well as their specifications, in order to ensure the
best results for the venture;
The Preliminary Phase is characterized by the surveys and studies of the current conditions of
road with the purpose of establishing the basic project for its restoration,
being, therefore, a phase of diagnosis and recommendations based on the conclusions
of the studies developed (including physical and operational improvements), through the
presentation of the various alternatives studied and of the work plan for the phase of
Basic Project.
The activities of the Preliminary Phase should be initiated by the Capacity Studies.
road segment to be designed, aiming at identifying physical improvements and
operational measures to be introduced on the highway, following the increase in its capacity
road
These studies should be conducted according to the provisions of the Basic Scope.
EB-108: Studies for the Adjustment of Capacity and Safety of Highways
Existing.
Traffic Studies;
c) Geological Studies;
d) Hydrological Studies;
e) Alignment Studies;
EB-106 - Basic Engineering Project for the Rehabilitation of a Highway with Improvements for Capacity and Safety Adjustment
Basic Guidelines for the Preparation of Road Studies and Projects 100
In the development of the activities of this Preliminary Phase, the following must be observed
following aspects:
a) Data related to the history of the VMD and fleet composition, obtained from DNIT;
EB-106 - Basic Engineering Project for the Rehabilitation of Highway with Improvements for Capacity and Safety Adjustment
Basic Guidelines for the Preparation of Road Studies and Projects 101
c) Volumetric and classification counts, carried out at least over 3 days, in the
situations where traffic data is not available or is
outdated;
c) Field investigations
It basically consists of the collection of hydrological data (climate, rainfall, river flow and
geomorphology) of the region.
The tracing studies will primarily aim to identify alternative options for
layout of the improvements to be introduced on the highway, and preparation of the registration
topographic.
Additional information will be gathered beyond what is available at DNIT, for the
identification of works with problems and the possible causes.
The studies of the existing pavement, for the purpose of identifying alternative solutions,
should cover the analysis of existing field surveys with the aim of
determine the functional and structural conditions for identifying solutions.
EB-106 - Basic Engineering Project for Highway Rehabilitation with Improvements for Capacity and Safety Adjustment
Basic Guidelines for the Preparation of Road Studies and Projects 102
The Environmental Component of the Project, in this Preliminary Phase, consists of the preparation of
Preliminary Environmental Diagnosis of the direct influence area of the Enterprise, and
in the evaluations of the occurrences registered in the environmental assessments, and of the
environmental impacts that may result from the execution of the works, aiming at
proposal of environmental protection measures.
It must characterize the environmental situation of the area of influence of the enterprise in
physical, biotic, anthropic aspects, aiming for knowledge of the region before the
implementation of the enterprise, serving as a reference for assessing the impacts
environmental aspects arising from the works and operation of the highway, and from the environmental liabilities.
In this Preliminary Phase of the Environmental Component of the project, it must be prepared for
agreement with aIS-246 - Environmental Component of Road Engineering Projects
Preliminary Phase, to be consolidated by the Preliminary Environmental Assessment Report
RAAP, which will enable decision-making for optimizing technical alternatives and
locational, as well as the initiative of DNIT, together with the Licensing Environmental Agency, to
request for the Preliminary License - LP of the Enterprise.
With the approval of the conclusions and recommendations of the Preliminary phase, the
basic project phase, with the purpose of selecting the alignment alternative to be
consolidated and detail the selected solution, providing plans, drawings, and others
elements that enable an adequate identification of the work to be executed
(Quantities, Specifications and Execution Plan).
b) Traffic Study
d) Geological Study
e) Hydrological Study
f) Alignment Study
g) Topographic Study
h) Geotechnical Study
Geometric Project
j) Earthworks Project
k) Drainage Project
EB-106 - Basic Engineering Project for the Rehabilitation of a Highway with Improvements for Capacity and Safety Adequacy
Basic Guidelines for the Preparation of Road Studies and Projects 103
Signage Project
q) Expropriation Project
Environmental Component
EB-106 - Basic Engineering Project for the Rehabilitation of a Highway with Improvements for Capacity and Safety Adjustment
Basic Guidelines for the Preparation of Road Studies and Projects 104
In the development of the activities of this Basic Project Phase, the following must be observed
the following aspects:
The preparation of the schematic road register must indicate the following elements:
EB-106 - Basic Engineering Project for the Rehabilitation of a Highway with Improvements for Capacity and Safety Adjustment
Basic Guidelines for the Development of Road Studies and Projects 105
These studies will aim to assess the traffic behavior of the highway, for
homogeneous subsection, in the period of the useful life, counted from the release of the section to
traffic, based on the existing geometric project and the topographic studies carried out.
For the purpose of this scope, a homogeneous segment is understood as one that has
mesmas características geométricas e os mesmos volumes e composições de tráfego.
c) Data processing;
d) Traffic projections;
e) Determination of the number N.
Section Registration;
EB-106 - Basic Engineering Project for Rehabilitation of Highway with Improvements for Capacity and Safety Adequacy
Basic Guidelines for the Preparation of Road Studies and Projects 106
After the collection and analysis of data on accidents, the section should be inspected.
aiming to detect failures in the adopted traffic engineering system, regarding
regarding visibility deficiencies, geometry issues, superelevation
inadequate, poor or nonexistent signage, insufficient road capacity, locations
unsuitable for pedestrian crossings, among others.
b) Geological mapping;
c) Geological description of the review;
d) Recommendations.
The routing alternatives for the improvements to be introduced on the highway should be
submitted to a comparative assessment for the purpose of defining the routes to be
designed.
EB-106 - Basic Engineering Project for Road Rehabilitation with Improvements for Capacity and Safety Adequacy
Basic Guidelines for the Preparation of Road Studies and Projects 107
The topographic studies for the Basic Project are developed in a single phase, therefore
after the preliminary definition of the routes to be studied and they can be carried out by:
The topographic survey through aerial photogrammetric processes will observe the following
sequence:
IS-226 Aerial Photography Coverage and Support for Basic Highway Project – Phase
Basic Project (Single Phase)
Aerophotogrammetric Reimbursement and Field Support for Basic Project of
IS-227
Highway - Basic Project Phase (Single Phase)
The topographical survey by conventional process will have the indicated sequence
to follow
e) Complementary surveys
f) Total spaces
g) Tracking
EB-106 - Basic Engineering Project for Rehabilitation of Highway with Improvements for Capacity and Safety Adequacy
Basic Guidelines for the Preparation of Road Studies and Projects 108
e) Registration and selection of quarries, sand pits, and other materials existing along
from the highway, which may be used in the pavement rehabilitation project;
Methodology Title
The existing pavement being Rigid Pavement, the following must be observed
methodologies:
Methodology Title
EB-106 - Basic Engineering Project for the Rehabilitation of a Highway with Improvements for Capacity and Safety Adjustment
Basic Guidelines for the Preparation of Road Studies and Projects 109
Based on the geotechnical studies and the assessment of the existing pavement, the will be done
pavement rehabilitation project, based on the Service Instructions and Standards
following:
EB-106 - Basic Engineering Project for the Rehabilitation of a Highway with Improvements for Capacity and Safety Adjustment
Basic Guidelines for the Preparation of Road Studies and Projects 110
Norma Activity
In the preparation of the Pavement Rehabilitation Project, at this stage of Basic Project
the following criteria should be adopted:
a) size the pavement using at least three methods indicated in the table
previous
b) adopt thicknesses of the reinforcement layer provided by the method that best
adapt to the functional and structural conditions of each homogeneous segment;
c) compare the costs of the alternatives for the purpose of choosing the most suitable solution and
present the justification for the chosen solution in volume 3.
The basic rehabilitation project of the pavement must contain, at a minimum, the following
elements:
− Physical schedule;
The existing pavement being Rigid Pavement, the methodologies must be observed.
exposed in the Rigid Pavements Manual of DNER, now under revision in
IPR.
EB-106 - Basic Engineering Project for the Rehabilitation of a Highway with Improvements for Capacity and Safety Adjustment
Basic Guidelines for the Preparation of Road Studies and Projects 111
b) Study of alternatives for the crossing, regarding the location of implementation of the
work;
e) Choice of the solution, opting for the one that best meets the technical criteria,
economic and administrative requirements and operational requirements for the highway. Consider the
architectural and landscaping aspects of the work;
f) Structural calculation memory of the adopted solution defining the main sections and
elements of relevance in the structure, including the resistance checks and
approximate amount of armor;
This project, at this stage of Basic Design, comprises the graphic representation of
intersections, returns, and planned accesses. It should include:
With the data obtained in the preparation of the highway registration, where the were marked the
Deficiencies in the road signage of the section, a signage project will be developed.
EB-106 - Basic Engineering Project for the Rehabilitation of a Highway with Improvements for Capacity and Safety Adjustment
Basic Guidelines for the Preparation of Road Studies and Projects 112
In this Basic Project phase, the Expropriation Project will be limited to an assessment.
the areas to be expropriated, and an estimate of their costs.
These procedures should be based on the Geometric Design developed in this phase.
The Environmental Component of the Project, in this Basic Design Phase, must be
developed according to the following activities:
In this Basic Project Phase, the Environmental Component of the project must be developed.
segundo as disposições daIS-246 - Componente Ambiental de Projetos de
Road Engineering - Basic Project Phase.
The Environmental Component of the Project in this Phase will be consolidated by the Basic Report.
of Environmental Assessment - RBAA, which serves as the document to support the
analysis and evaluation of the environmental damage caused by the enterprise, having as
one of its main functions is to provide the licensing body with the means to make a decision in the sense
to grant the Installation License - LI, of the Undertaking, whenever the
the bidding for the work is based on this Basic Engineering Project.
At the end of the studies conducted in this phase, the costs of the work will be defined.
for pavement rehabilitation and introduction of improvements to increase capacity and
safety adopting the methodology recommended in IS-220 Project Budget -
Preliminary and Basic Project Phase and the recommendations of the Cost System
Road workers of DNIT - SICRO.
EB-106 - Basic Engineering Project for Highway Rehabilitation with Improvements for Capacity and Safety Adequacy
Basic Guidelines for the Preparation of Road Studies and Projects 113
Presentation of the rational sequence of the set of activities that should be executed.
of the project, indicating the problems of a climatic, administrative, technical and
segurança; época do início dos trabalhos; período de execução; conseqüência da
location, type of construction and other conditioning factors for building, including
implications with traffic, in the case of existing highways.
The Execution Plan for the work, to be prepared for each construction lot, will take into account
consideration of the aspects related to climate and rainfall, particularly concerning
to the rainy season and number of rainy days per month, logistical support, deadline for the
Execution of the works, minimum equipment, and service attack plan.
At the end of the Preliminary Phase, the Preliminary Report of the Basic Project will be presented.
containing the conclusions of the studies developed and the proposed recommendations, the
which will be constituted by the volumes listed below.
PRELIMINARY REPORT
4.2.1. MINUTES
At the end of the Basic Project, the Draft of the Final Project Report will be presented
Basic, in 4 volumes, as per the list below.
EB-106 - Basic Engineering Project for the Rehabilitation of a Highway with Improvements for Capacity and Safety Adaptation
Basic Guidelines for the Development of Road Studies and Projects 114
After the draft is approved, the final report will be presented in its definitive form.
of the Basic Project, according to the volumes listed below.
EB-106 - Basic Engineering Project for Road Rehabilitation with Improvements for Capacity and Safety Adequacy
Basic Guidelines for the Preparation of Road Studies and Projects 115
APPENDIX A7
EB-107 - EXECUTIVE ENGINEERING PROJECT FOR REHABILITATION OF
HIGHWAY WITH IMPROVEMENTS FOR CAPACITY AND SAFETY ADJUSTMENT
1 DEFINITIONS
It consists of the set of studies and projects developed with the aim of reinforcing the
existing pavement, by adding new structural layers, or by replacement of
one or more layers of the pavement, or to proceed with the total recomposition of the
pavement, in such a way that the resulting structure can economically support the
repetition of loads per axle incident, in conditions of safety and comfort for the
user, during the new project period. The provisions of must be observed.
Basic Scope EB-115: Executive Engineering Project for Rehabilitation of
Road Pavements.
It also consists of the introduction of improvements for adjustment of capacity and safety,
related to problems not directly linked to the existing pavement, such as:
route improvements for the elimination of critical points, lane duplication,
construction of side streets, implementation of third lanes, construction and/or
remodeling of intersections and accesses, urban crossings, reinforcement and widening of
special artworks and construction of walkways for pedestrian crossings.
a) Preliminary Phase;
This Basic Scope refers to the Executive Engineering Project for Rehabilitation of
Highway with Improvements for Capacity and Safety Adjustment, to be developed
subsequent to the respective Preliminary Studies and the respective Basic Project,
allowing to fully characterize the work from the point of view of execution, and containing
EB-107 - Executive Engineering Project for Rehabilitation of Highway with Improvements for Capacity and Safety Adjustment
Basic Guidelines for the Preparation of Road Studies and Projects 116
all the elements from the previous phases, added to the level of detail specific to
Executive Project, in such a way as to provide a global view of the work and identify all the
its constructive elements clearly.
The preliminary phase is characterized by the surveys and studies of the current conditions of
highway with the purpose of establishing the basic project for its rehabilitation,
being, therefore, a phase of diagnosis and recommendations based on the conclusions
of the developed studies (including physical and operational improvements), through the
presentation of the various alternatives studied and work plan for the phase of
basic project.
The activities of the Preliminary Phase must be initiated by the Capacity Studies.
road segment to be designed, aiming at identifying physical improvements and
operational measures to be introduced on the highway, based on the increase of its capacity
road.
These studies must be conducted according to the provisions of the Basic Scope.
EB-108: Studies for the Adjustment of Capacity and Safety of Highways
Existing.
The following will develop the works aiming at the conceptualization of the restoration of
existing pavement, involving the following activities:
b) Traffic Studies;
c) Geological Studies;
d) Hydrological Studies;
e) Alignment Studies;
EB-107 - Executive Engineering Project for Rehabilitation of Highway with Improvements for Capacity and Safety Adjustment
Basic Guidelines for the Preparation of Road Studies and Projects 117
If a Basic Project has already been prepared for the road segment to be executed
designed, a detailed analysis of the raised elements will be carried out, and to a
substantial evaluation of the conclusions of the Preliminary Phase of the existing Basic Project,
always in accordance with the above Service Instructions.
In the development of the activities of this Preliminary Phase, the following must be observed
following aspects:
c) Information about the existing pavement, covering the characteristics of the subgrade,
thickness and composition of pavement layers, nature and execution period
of any rehabilitation and maintenance work; and
EB-107 - Executive Engineering Project for Road Rehabilitation with Improvements for Capacity and Safety Adjustment
Basic Guidelines for the Development of Road Studies and Projects 118
a) Data related to the history of the VMD and fleet composition, obtained from DNIT;
c) Field investigations
Basically consists of the collection of hydrological data (climate, rainfall, river flow and
geomorphology) of the region.
Additional information will be gathered beyond what is available from DNIT, for the
identification of the works with problems and the possible causes.
EB-107 - Executive Engineering Project for Rehabilitation of Highway with Improvements for Capacity and Safety Adequacy
Basic Guidelines for the Development of Road Studies and Projects 119
The preliminary studies of the existing pavement, for the purpose of identifying the solutions
alternatives must encompass the analysis of existing field surveys with the
Objective of determining the functional and structural conditions for identification of
solutions.
The Environmental Component of the Project, in this Preliminary Phase, consists of the preparation of
Preliminary Environmental Diagnosis of the direct influence area of the Enterprise, and
in the assessments of the occurrences registered in the environmental surveys, and of the
environmental impacts that may arise from the execution of the works, aiming at
proposal for environmental protection measures.
It must characterize the environmental situation of the area of influence of the project in
physical, biotic, anthropic aspects, aiming for knowledge of the region before the
implementation of the venture, serving as a reference for assessing the impacts
environmental impacts resulting from the construction and operation of the highway, and from environmental liabilities.
In this Preliminary Phase of the Environmental Component of the project, it must be developed
agreement with aIS-246 - Environmental Component of Road Engineering Projects
Preliminary Phase, to be consolidated by the Preliminary Environmental Assessment Report
RPAA, which will allow for decision-making to optimize technical alternatives.
locational, as well as the initiative of DNIT, together with the Licensing Environmental Agency, to
Request for the Preliminary License-LP of the Enterprise.
With the approval of the conclusions and recommendations of the Preliminary phase, the
Basic Project Phase, with the aim of selecting the layout alternative to be
consolidated and detail the selected solution, providing plans, drawings and others
elements that enable an adequate identification of the work to be executed.
b) Traffic Study
d) Geological Study
Hydrological Study
f) Route Study
g) Topographic Study
EB-107 - Executive Engineering Project for Highway Rehabilitation with Improvements for Capacity and Safety Adjustment
Basic Guidelines for the Preparation of Road Studies and Projects 120
h) Geotechnical Study
i) Geometric Project
Earthworks project
k) Drainage Project
o) Signaling Project
Expropriation Project
Environmental Component
s) Project Budget
EB-107 - Executive Engineering Project for Highway Rehabilitation with Improvements for Capacity and Safety Adjustment
Basic Guidelines for the Preparation of Highway Studies and Projects 121
If a Basic Project has already been prepared for the road segment to be executed
designed, a detailed re-evaluation of its Basic Project phase will be carried out,
starting from:
a) Evaluation of the basic project developed, considering the necessary services for
execution of the work and corresponding costs;
EB-107 - Executive Engineering Project for the Rehabilitation of Highway with Improvements for Capacity and Safety Adjustment
Diretrizes Básicas para Elaboração de Estudos e Projetos Rodoviários 122
c) Evaluation of all and any observation deemed relevant and that comes
modify any conclusion or recommendation of the existing Basic Project;
d) Preparation of a conclusive opinion regarding the solutions presented in the Basic Project
existing through the analysis of its Presentation Volumes (Volumes 1, 2, 3, and 4)
In the development of the activities of this Basic Project Phase, the following must be observed
the following aspects:
The preparation of the schematic registration of the highway should indicate the following elements:
These studies will aim to assess the traffic capacity of the highway, by subsection.
homogeneous, over the useful life period, counted from the release of the section to traffic,
based on the existing geometric project and the topographic studies carried out. For
For the purpose of this scope, a homogeneous subsection is understood to be one that has the
same geometric characteristics and the same volumes and traffic compositions.
c) Data processing;
EB-107 - Executive Engineering Project for the Rehabilitation of a Highway with Improvements for Capacity and Safety Adequacy
Basic Guidelines for the Preparation of Highway Studies and Projects 123
Traffic projections;
e) Determination of the number N.
a) Stretch Registration;
After the collection and analysis of data on accidents, the section should be inspected.
aiming to detect failures in the adopted traffic engineering system, in what it says
regarding visibility deficiencies, geometry issues, superelevation
inadequate, poor or non-existent signage, insufficient road capacity, locations
unsuitable for pedestrian crossings, among others.
b) Geological mapping;
c) Geological description of the review;
d) Recommendations.
EB-107 - Executive Engineering Project for the Rehabilitation of a Highway with Improvements for Capacity and Safety Adequacy
Basic Guidelines for the Preparation of Road Studies and Projects 124
a) Collection of local information and with conservation teams regarding the functioning
two devices for surface and deep drainage;
The route alternatives for the improvements to be introduced on the highway must be
submitted to a comparative assessment for the purposes of defining the routes to be
designed.
The topographic studies for the Basic Project are developed in a single phase, and
may be carried out by:
Aerial Photogrammetric Coverage and Support for Basic Highway Project - Phase
IS-226
of Basic Project (Single Phase)
Aerophotogrammetric Restitution and Field Support for Basic Project
IS-227
Highway - Basic Project Phase (Single Phase)
EB-107 - Executive Engineering Project for the Rehabilitation of a Highway with Improvements for Capacity and Safety Adaptation
Basic Guidelines for the Preparation of Road Studies and Projects 125
The topographic survey by conventional process will follow the sequence indicated to
to follow
e) Additional surveys
f) Total space
g) Tracking
e) Registration and selection of quarries, sand pits, and other materials existing along
from the highway, which may be used in the pavement rehabilitation project;
EB-107 - Executive Engineering Project for Road Rehabilitation with Improvements for Capacity and Safety Adjustment
Basic Guidelines for the Development of Road Studies and Projects 126
Methodology Title
The existing pavement being Rigid Pavement, the following must be observed
methodologies:
Methodology Title
c) Typical cross sections of the platforms, based on the conclusions of the Studies of
Traffic carried out in this phase.
Research will still be carried out to determine possible locations for boxes of
loans.
EB-107 - Executive Engineering Project for the Rehabilitation of a Highway with Improvements for Capacity and Safety Adequacy
Basic Guidelines for the Preparation of Road Studies and Projects 127
Based on the geotechnical studies and the assessment of the existing pavement, a draft will be prepared.
pavement rehabilitation project, based on the Service Instructions and Standards
the following:
Norma Activity
In the preparation of the Pavement Rehabilitation Project, the criteria must be adopted
following:
a) size the pavement using at least three methods indicated in the table
anterior
b) adopt thicknesses of the reinforcement layer provided by the method that best
adapt to the functional and structural conditions of each homogeneous segment;
c) compare the costs of alternatives for the purpose of choosing the most suitable solution and
present the justification for the chosen solution in volume 3.
In this Basic Project phase, the pavement rehabilitation project must contain, in
minimum, the following elements:
EB-107 - Executive Engineering Project for Highway Rehabilitation with Improvements for Capacity and Safety Adjustment
Basic Guidelines for the Preparation of Road Studies and Projects 128
− Physical schedule;
The pavement being rigid pavement, the methodologies presented must be observed.
In the Manual of Rigid Pavements of DNIT, currently undergoing revision at IPR.
b) Study of alternatives for the crossing, regarding the location of implementation of the
work;
c) Study of the feasible structural solutions, resulting from the examination of the site
implementation, with definition, for each proposed solution, of the total length of the
work, number of spans, main geometric characteristics, extent of the fills of
access and foundations;
e) Choice of the solution, opting for the one that best meets the technical criteria,
economic and administrative requirements and operational requirements for the highway. Consider the
architectural and landscaping aspects of the work;
f) Structural calculation memory of the adopted solution defining the main sections and
relevant elements in the structure, including resistance checks and
approximate amount of armor;
This project comprises the graphical representation of intersections, returns, and access points.
expected. It should include:
EB-107 - Executive Engineering Project for Highway Rehabilitation with Improvements for Capacity and Safety Adaptation
Basic Guidelines for the Preparation of Road Studies and Projects 129
With the data obtained during the road registration process, where the
deficiencies of the road signaling of the section, the signaling project will be developed.
In this Basic Project phase, the Expropriation Project will be limited to an evaluation.
the areas to be expropriated, and an estimate of their costs.
These procedures should be based on the Geometric Project developed in this phase.
The Environmental Component of the Project, in this Basic Design Phase, should be
developed according to the following activities:
In this Basic Design Phase, the Environmental Component of the project must be developed.
according to the provisions of IS-246 - Environmental Component of Projects
Road Engineering - Basic Project Phase.
The Environmental Component of the Project at this Stage will be consolidated by the Basic Report.
of Environmental Assessment - RBAA, which serves as the document to support the
EB-107 - Executive Engineering Project for Rehabilitation of Highway with Improvements for Capacity and Safety Adjustment
Basic Guidelines for the Preparation of Road Studies and Projects 130
analysis and evaluation of the environmental damages caused by the Enterprise, aiming at
one of its main functions is to instrumentalize the decision of the licensing body in the sense
to grant the Installation License - LI, of the Enterprise, whenever the
the execution of the bidding for the work is based on this Basic Engineering Project.
At the end of the studies conducted in this phase, the costs of the work will be estimated.
for pavement rehabilitation, and introduction of improvements to increase capacity and
safety adopting the methodology recommended in IS-220 Work Budget -
Preliminary Phase and Basic Project and in the recommendations of the Cost System
Road workers of DNIT - SICRO.
With the approval of the conclusions and recommendations of the Basic Design Phase, it will be
the executive project phase has begun, with the purpose of detailing the selected solution,
providing plants, drawings, and service notes that allow for the construction of
highway. The following elements must be provided:
b) subsidies for the preparation of the bidding plan and management of the work;
The Environmental Component of the Project in this Executive Project Phase consists of
detailed planning and budgeting for environmental protection measures, both corrective and
preventive measures indicated in the Basic Design Phase, aiming at rehabilitation/recovery
of environmental liability and the execution of works in an environmentally correct manner.
In this Executive Project Phase, the Environmental Component of the Project will be developed.
in accordance with the provisions of IS-246 - Environmental Component of Projects
Highway Engineering - Executive Project Phase.
The Environmental Component of the Project, in this Phase, will be consolidated by the Final Report.
of Environmental Assessment - RFAA that must contain the elements that characterize the
EB-107 - Executive Engineering Project for Road Rehabilitation with Improvements for Capacity and Safety Adjustment
Basic Guidelines for the Preparation of Road Studies and Projects 131
In the case where the bidding for the work is based on this Executive Project of
Engineering, the Final Environmental Assessment Report - RAAF should provide
additional information that allows DNIT to request from the Environmental Agency
Licensor, the Installation License - LI, of the Enterprise.
EB-107 - Executive Engineering Project for the Rehabilitation of Highway with Improvements for Capacity and Safety Adequacy
Basic Guidelines for the Preparation of Road Studies and Projects 132
At the end of the Preliminary Phase, the Preliminary Project Report will be presented.
Executive, containing the observations and preliminary recommendations considered.
relevant being constituted by the following volumes.
PRELIMINARY REPORT
At the end of the basic design phase, the Basic Project Report will be presented.
Executive, containing the proposed solutions, indicative tables of the characteristics
operational and quantitative techniques of the services, consisting of the volumes
following:
BASIC REPORT
Finalizing the preparation of the Executive Project, the Final Report will be presented.
Executive Project, initially in the form of a draft. After examination and approval by DNIT,
will be presented in the form of a final print. The Final Report will consist of
by the following volumes:
EB-107 - Executive Engineering Project for Highway Rehabilitation with Improvements for Capacity and Safety Upgrade
Basic Guidelines for the Preparation of Road Studies and Projects 133
FINAL REPORT
FORMAT
VOLUME TITLE
Printing
Minute
Definitive
EB-107 - Executive Engineering Project for the Rehabilitation of a Highway with Improvements for Capacity and Safety Adequacy
Basic Guidelines for the Preparation of Road Studies and Projects 134
ANNEX A8
EB-108 - BASIC SCOPE FOR THE DEVELOPMENT OF STUDIES FOR ADJUSTMENT
ON THE CAPACITY AND SAFETY OF EXISTING HIGHWAYS
1 DEFINITION
This scope includes the estimate of the costs for implementing the proposed improvements, the
formulation of a schedule and the development of a detailed scope for the phase
subsequent to the final engineering project.
2 STUDY PHASE
The studies will be conducted in a single phase, the Preliminary Phase, and will comprise the
following activities:
Data collection;
a) Collection of supplementary data;
b) Diagnosis of the current situation;
c) Traffic projections;
3 DEVELOPMENT OF STUDIES
EB-108 - Basic Scope for the Preparation of Studies for the Adaptation of Capacity and Safety of Existing Highways
Basic Guidelines for the Development of Road Studies and Projects 119
The preliminary studies of the existing pavement, for the purpose of identifying the solutions
alternatives must encompass the analysis of existing field surveys with the
Objective of determining the functional and structural conditions for identification of
solutions.
The Environmental Component of the Project, in this Preliminary Phase, consists of the preparation of
Preliminary Environmental Diagnosis of the direct influence area of the Enterprise, and
in the assessments of the occurrences registered in the environmental surveys, and of the
environmental impacts that may arise from the execution of the works, aiming at
proposal for environmental protection measures.
It must characterize the environmental situation of the area of influence of the project in
physical, biotic, anthropic aspects, aiming for knowledge of the region before the
implementation of the venture, serving as a reference for assessing the impacts
environmental impacts resulting from the construction and operation of the highway, and from environmental liabilities.
In this Preliminary Phase of the Environmental Component of the project, it must be developed
agreement with aIS-246 - Environmental Component of Road Engineering Projects
Preliminary Phase, to be consolidated by the Preliminary Environmental Assessment Report
RPAA, which will allow for decision-making to optimize technical alternatives.
locational, as well as the initiative of DNIT, together with the Licensing Environmental Agency, to
Request for the Preliminary License-LP of the Enterprise.
With the approval of the conclusions and recommendations of the Preliminary phase, the
Basic Project Phase, with the aim of selecting the layout alternative to be
consolidated and detail the selected solution, providing plans, drawings and others
elements that enable an adequate identification of the work to be executed.
b) Traffic Study
d) Geological Study
Hydrological Study
f) Route Study
g) Topographic Study
EB-107 - Executive Engineering Project for Highway Rehabilitation with Improvements for Capacity and Safety Adjustment
Basic Guidelines for the Development of Road Studies and Projects 136
This stage aims to identify the main problems observed, as well as the causes,
in order to conceive corrective measures for the solutions. Thus, the following
analyses should be carried out:
a) Determine the exact location of the critical sections, the danger pattern and the
comparison with the rates and indices of the other critical sections.
b) Obtain more information and refer to the absolute quantities for each section. For each
critical section to create the collision diagram, recording the types and
consequences of the most common accidents.
c) The next stage of the accident analysis will be to formulate a diagnosis of the main
causes of occurrences, confirmed by field inspections; and
d) Consider the data from the expedited survey conducted in the main
pedestrian crossing locations, intersections and junctions, generating hubs
traffic and relevant establishments in the study of accidents, such as schools,
hospitals, important businesses.
Since the studies aim for a short-term improvement program, many of the
analyses and conclusions will be based on the existing traffic. To reconcile any
EB-108 - Basic Scope for Preparing Studies for the Adjustment of Capacity and Safety of Existing Highways
Basic Guidelines for the Development of Road Studies and Projects 137
recommendations with the other traffic projections already made, referring them to
same or another year-horizon.
The preliminary study phase includes the definition of a set of measures that
eliminate, or even minimize the causes of the problems identified. This list of
probable solutions should consider not only the physical and operational interventions to
to implant, but also, the aspects not directly related to the road itself, such as the
use of the local road system, modifications in the patterns of riverside occupation, impact
Environmental and access control. It should be clarified that some of these measures
They will involve the local governmental institution.
Most of the time, it is not possible to reconcile relevant issues, such as mobility and
accessibility. The first refers to the road circulation itself,
especially the fluidity, safety, and comfort of the users. The second refers to the
ease of entry and exit in the transportation system under study.
The choice of the privileged function will be the result of the analyses conducted. Example: the
small-scale urban crossings, long-distance road traffic should be
prioritized, placing greater emphasis on the mobility aspect, to the detriment of accessibility.
Unlike highly densely populated urban areas, with vehicle flows towards the
non-predominant areas, the accessibility function will be treated specially, in
detriment to mobility.
d) lane duplication;
EB-108 - Basic Scope for the Development of Studies for the Adaptation of Capacity and Safety of Existing Highways
Basic Guidelines for the Preparation of Road Studies and Projects 138
This stage consists of choosing, among all the recommended measures in the stage
previous, that one or those that are more viable for implementation. The solution of
The problem can arise from a single measure or from a set.
For the choice of the most viable interventions, some questions should be raised.
considered, such as those listed below:
4 PRESENTATION
The presentation of the studies must follow the presentation systems in the Projects.
Basics and Executive Engineering for Road Rehabilitation with Improvements
for Capacity and Safety Adequacy, EB-106 and EB-107.
EB-108 - Basic Scope for Developing Studies for the Adaptation of the Capacity and Safety of Existing Highways
Basic Guidelines for the Development of Road Studies and Projects 139
ANNEX A9
EB-109 - BASIC SCOPE FOR THE ELABORATION OF BASIC PROJECT
ENGINEERING FOR HIGHWAY DUPLICATION
1 DEFINITION
a) Preliminary Phase;
The Basic Engineering Project for Road Duplication must contain the
following elements:
a) development of the chosen solution in order to provide a global view of the work and
identify all of its constituent elements clearly;
c) identification of the types of services to be executed, of materials to be incorporated into the work and of
equipment to be used, as well as their specifications, in order to ensure the
best results for the venture;
EB-109 - Basic Scope for the Preparation of Basic Engineering Project for the Duplication of Highway
Basic Guidelines for the Preparation of Road Studies and Projects 140
e) subsidies for the preparation of the bidding plan and project management, encompassing the
your programming, the supply strategy, the monitoring standards and others
necessary data in each case;
The Preliminary Phase is characterized by the development of the Functional Plan and Study of
Tracing Alternatives.
b) Traffic Studies;
c) Geological Studies;
d) Hydrological Studies;
e) Route Studies;
f) Assembly of the Functional Plan;
EB-109 - Basic Scope for the Preparation of Basic Engineering Project for Highway Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 141
If there are already Technical and Economic Feasibility Studies for the road segment
to be designed, a detailed analysis of the raised elements will be carried out, and to a
substantial assessment of the conclusions of existing studies, always in compliance
with the above related Service Instructions.
In the development of the activities of this Preliminary Phase, the following must be observed:
following aspects:
a) Data related to the history of the VMD and fleet composition, obtained from DNIT;
EB-109 - Basic Scope for the Development of Basic Engineering Project for Road Duplication
Basic Guidelines for the Development of Road Studies and Projects 142
c) Field investigations
Basically consists of the collection of hydrological data (climate, rainfall, streamflow and
geomorphology) of the region.
The tracing studies will primarily aim to identify the alternatives for
traces to be considered in the conduct of studies, in the case of a 2nd track
independent (remote) from the existing track.
The preliminary studies of the existing pavement, for the purpose of identifying the solutions
alternatives should encompass the analysis of existing field surveys with the
objective of determining the functional and structural conditions for identification of the
solutions.
EB-109 - Basic Scope for the Development of Basic Engineering Project for Highway Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 143
The Environmental Component of the Project, in this Preliminary Phase, consists of the elaboration of
Preliminary Environmental Diagnosis of the direct influence area of the Enterprise, and
in the assessments of the occurrences registered in the environmental surveys, and of the
environmental impacts that may arise from the execution of the works, aiming at the
proposal for environmental protection measures.
It must characterize the environmental situation of the area of influence of the enterprise in
physical, biotic, anthropic aspects, aiming for an understanding of the region before the
implementation of the enterprise, serving as a reference for assessing the impacts
environmental impacts arising from the works and operation of the highway, and from environmental liabilities.
In this Preliminary Phase, the Environmental Component of the project must be developed accordingly.
with aIS-246 - Environmental Component of Road Engineering Projects - Phase
Preliminary, to be consolidated by the Preliminary Environmental Assessment Report -
RPAA, which will enable decision-making for the optimization of technical alternatives
locational, as well as the initiative of DNIT, alongside the Licensing Environmental Agency, to
request for the Preliminary License (LP) of the Enterprise.
With the approval of the conclusions and recommendations of the Preliminary Phase, the
Basic Project phase, aimed at selecting the route alternative to be
consolidated and detailed the selected solution, through the estimation of quantities of
service and the preparation of plants, drawings, and other elements that enable the
perfect identification of the work to be executed.
In the highway segments where the possibility of constructing the new lane occurs
traffic, parallel and adjacent to the existing one, a study will be conducted to determine the side in
that will be launched, taking into account construction difficulties, problems of
expropriations and compensation for earthworks volumes. In the segments of
highway where there is a need to lay down the new lane with an independent guideline
from existing, one should, whenever possible, project returns at intervals of about 5
km.
b) Traffic Study
d) Geological Study
Hydrological Study
f) Trace Study
g) Topographic Study
EB-109 - Basic Scope for the Development of Basic Engineering Project for Road Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 144
h) Geotechnical Study
Geometric Project
j) Earthworks Project
k) Drainage Project
l) Paving Project
Signage Project
Expropriation Project
Environmental Component of the Project
u) Project Budget
EB-109 - Basic Scope for the Preparation of Basic Engineering Project for Road Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 145
In the development of the activities of this Basic Project Phase, the following must be observed
the following aspects:
EB-109 - Basic Scope for the Development of Basic Engineering Project for Road Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 146
The preparation of the schematic registration of the highway should indicate the following elements:
These studies will aim to evaluate the behavior of traffic on the highway, for
homogeneous subsection, during the useful life period, counted from the release of the section,
based on the existing geometric project and the topographic studies carried out
They also aim to determine the Number N for the purpose of sizing the
highway pavement.
c) Data processing;
d) Traffic projections;
e) Determination of the number N.
EB-109 - Basic Scope for Preparing Basic Engineering Project for Road Duplication
Basic Guidelines for the Development of Road Studies and Projects 147
a) Stretch Registration;
After the collection and analysis of data on accidents, the section should be inspected.
aiming to detect failures in the adopted traffic engineering system, in what it says
regarding visibility deficiencies, geometry problems, superelevation
inadequate, poor or nonexistent signaling, insufficient road capacity, locations
unsuitable for pedestrian crossings, among others.
b) Geological mapping;
c) Geological description of the review;
d) Recommendations.
a) Collection of local information and with conservation teams regarding the operation
two superficial and deep drainage devices;
EB-109 - Basic Scope for the Development of Basic Engineering Project for Highway Duplication
Basic Guidelines for Preparing Road Studies and Projects 148
At this stage, the identified routing alternatives for the independent runways
(removed) from the existing track, must undergo an evaluation process
comparison for the purpose of defining the paths to be designed.
The topographic studies for the Basic Project develop in a single phase, and
may be carried out by:
Aerial Photogrammetric Coverage and Support for Basic Highway Project - Phase
IS-226
Basic Project (Single Phase)
Aerophotogrammetric Restitution and Field Support for Basic Project
IS-227
Highway - Basic Project Phase (Single Phase)
The topographic survey by conventional process will have the indicated sequence to
to follow
d) Cross-section survey
e) Complementary surveys
f) Total space
g) Tracking
EB-109 - Basic Scope for the Development of Basic Engineering Project for Highway Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 149
[Link]. PISTAEXISTENTE
Geotechnical studies for the existing runway, in the case of Flexible and Semi-Pavements
Rigid materials will provide subsidies for the preparation of the diagnosis of the existing pavement.
consisting of the following activities:
a) Subjective survey of the pavement (visual inspection) aiming for the subdivision of
segment in homogeneous segments;
e) Registration and selection of quarries, sandbanks, and other materials existing along
from the highway, which may be used in the pavement rehabilitation project;
For the execution of the previously mentioned surveys, aIS 212 will be used.
Service Instruction for Structural Assessment and Rehabilitation Project
Flexible and Semi-Rigid Pavements - Basic Project Phase and the methodologies
follow indicated:
Methodology Title
The existing pavement being Rigid Pavement, the following should be observed
methodologies:
EB-109 - Basic Scope for the Preparation of Basic Engineering Project for Highway Duplication
Basic Guidelines for the Development of Road Studies and Projects 150
Methodology Title
2nd TRACK
For the runway to be implemented, the 2nd runway, the geotechnical studies should involve:
EB-109 - Basic Scope for the Preparation of Basic Engineering Project for Road Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 151
The runway paving project to be implemented, the 2nd runway, in this Project Phase
Basic encompasses the definition of the pavement design, based on the sizing.
preliminary and structural solutions of the pavement, which should be the subject of technical analysis-
economic, and the estimation of quantities of services:
Based on the geotechnical studies and the assessment of the existing pavement, the
rehabilitation project of the existing pavement, based on the Service Instructions and
Following standards, in the case of Flexible and Semi-Rigid Pavements:
Norma Activity
In the preparation of the Pavement Rehabilitation Project, at this stage, certain measures must be adopted.
the following criteria:
a) design the pavement using at least three methods indicated in the table
anterior;
b) adopt the thicknesses of the reinforcement layer provided by the method that best
suitable for the functional and structural conditions of each homogeneous segment;
c) compare the costs of the alternatives for the purpose of choosing the most appropriate solution and
present the justification for the chosen solution in volume 3.
EB-109 - Basic Scope for the Preparation of Basic Engineering Project for Road Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 152
The pavement rehabilitation project must include, at a minimum, the following elements:
− Physical schedule;
For the special artworks to be constructed as part of the 2nd lane, they must
the following activities must be carried out:
b) Study of alternatives for crossing, regarding the location for implementation of the
work;
For the existing works of art, the data collected in the Phase must be processed.
Preliminary, and based on this procedure, establish the need for reinforcement works,
of extensions, or substitutions, defining the types of services to be
carried out, and quantifying them at the basic project level.
EB-109 - Basic Scope for the Development of Basic Engineering Project for Highway Duplicating
Basic Guidelines for the Preparation of Road Studies and Projects 153
This project comprises the graphic representation of intersections, returns, and accesses.
foreseen. It should include:
With the data obtained in the preparation of the highway registration, where the were marked the
deficiencies of the road signaling in the section, a signaling project will be developed.
At this stage of the Basic Project, the Expropriation Project will be limited to an assessment
of the areas to be expropriated, and an estimate of their costs.
These procedures should be based on the Geometric Project developed in this phase.
The Environmental Component of the Project, in this Basic Project Phase, must be
developed according to the following activities:
EB-109 - Basic Scope for the Development of Basic Engineering Project for Highway Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 154
In this Basic Project Phase, the Environmental Component of the project must be developed.
segundo as disposições daIS-246 - Componente Ambiental de Projetos de
Road Engineering - Basic Project Phase.
The Environmental Component of the Project at this Stage will be consolidated by the Basic Report.
of Environmental Assessment - RBAA, which serves as the document to support the
analysis and assessment of the environmental damage caused by the Undertaking, taking as
one of its main functions is to equip the licensing body to make a decision in the sense
to grant the Installation License - LI, of the Enterprise, whenever the
the bidding for the work is based on this Basic Engineering Project.
At the end of the studies developed in this phase, the costs of the work will be estimated.
for pavement rehabilitation, and introduction of improvements to increase capacity and
security adopting the methodology recommended in IS-220 Budget of the Work -
Preliminary and Basic Project Phases and the recommendations of the Cost System
Road workers from DNIT - SICRO.
Presentation of the rational sequence of the set of activities that must be executed
of the project, indicating the problems of a climatic, administrative, technical nature and
segurança; época do início dos trabalhos; período de execução; conseqüência da
location, type of work and other conditioning factors for construction, including
implications with traffic, in the case of existing highways.
The Execution Plan of the work, to be prepared for each construction plot, will take into
consideration of the aspects related to climate and precipitation, particularly concerning
to the rainy period and number of rainy days per month, logistical support, deadline for the
execution of the works, minimum equipment and service attack plan.
At the end of the Preliminary Phase, the Preliminary Report of the Basic Project will be presented.
containing the conclusions of the studies developed and the proposed recommendations, the
which will be constituted by the volumes listed below.
EB-109 - Basic Scope for the Preparation of Basic Engineering Project for Highway Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 155
PRELIMINARY REPORT
4.2.1. MINUTES
At the end of the Basic Design Phase, the Draft of the Final Report will be presented.
Basic Project, in 4 volumes, according to the list below.
After the approval of the Draft, the Final Report's Definitive Print will be presented.
of the Basic Project, according to the volumes detailed below.
EB-109 - Basic Scope for the Preparation of Basic Engineering Project for Road Duplication
Basic Guidelines for the Development of Road Studies and Projects 156
ANNEX A10
EB-110 - BASIC SCOPE FOR THE DEVELOPMENT OF EXECUTIVE PROJECT
ENGINEERING FOR HIGHWAY DUPLICATION
1 DEFINITIONS
It is about the set of studies and projects that need to be developed, aiming at
prioritariamente a duplicação da pista e conseqüentemente das obras-de-arte especiais
existing and the adjustment of traffic schemes to the new situation of the track.
2 PROJECT PHASES
a) Preliminary Phase;
This Basic Scope refers to the Executive Engineering Project for Duplication of
Highway, to be developed consecutively to the respective Preliminary Studies and to
respective Basic Project, allowing to fully characterize the work from a point of view
of the execution, and containing all the elements of the previous phases, added to the level of
specific detailing of the Executive Project, in such a way as to provide a global view of the
work, and clearly identify all its constructive elements.
The Preliminary Phase is characterized by the preparation of the Functional Plan and Study of
Tracing Alternatives.
EB-110 - Basic Scope for the Development of Executive Engineering Project for Highway Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 157
b) Traffic Studies;
c) Geological Studies;
d) Hydrological Studies;
e) Survey Studies;
f) Assembly of the Functional Plan;
If there is already a Basic Project prepared for the road segment to be executed
designed, a detailed analysis of the raised elements will be carried out, and to a
substantial evaluation of the conclusions of the Preliminary Phase of the existing Basic Project,
always in accordance with the above-mentioned Service Instructions.
EB-110 - Basic Scope for the Preparation of Executive Engineering Project for the Duplication of a Highway
Basic Guidelines for the Preparation of Road Studies and Projects 158
In the development of the activities of this Preliminary Phase, the following must be observed
the following aspects:
a) Data related to the history of the VMD and fleet composition, obtained from DNIT;
It basically consists of the collection of hydrological data (climate, rainfall, river flow and
geomorphology) of the region.
EB-110 - Basic Scope for the Development of Executive Engineering Project for Road Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 159
The route studies will primarily aim to identify the alternatives for
traces to be considered in conducting studies, in the case of an independent track
(removed) from the existing track.
The preliminary studies of the existing pavement, for the purpose of identifying the solutions
alternatives should cover the analysis of existing field surveys with the
objective of determining the functional and structural conditions for identification of
solutions.
The Environmental Component of the Project, in this Preliminary Phase, consists of the preparation of
Preliminary Environmental Diagnosis of the direct influence area of the Enterprise, and
in the evaluations of the occurrences registered in the environmental surveys, and of the
environmental impacts that may arise from the execution of the works, aiming at
proposals for environmental protection measures.
It should characterize the environmental situation of the area of influence of the enterprise in
physical, biotic, anthropic aspects, aiming for an understanding of the region before the
EB-110 - Basic Scope for the Preparation of Executive Engineering Project for Highway Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 160
In this Preliminary Phase of the Environmental Component of the project, it must be prepared.
agreement with aIS-246 - Environmental Component of Road Engineering Projects
Preliminary Phase, to be consolidated by the Preliminary Environmental Assessment Report
RPAA, which will allow decision-making for the optimization of technical alternatives and
locational, as well as the initiative of DNIT, together with the Licensing Environmental Agency, to
request for the Preliminary License (LP) of the Enterprise.
With the approval of the conclusions and recommendations of the Preliminary Phase, the
Basic Design Phase, with the aim of selecting the routing alternative to be
consolidated and detailed the selected solution, through the estimation of quantities of
service and the preparation of plants, drawings, and other elements that enable the
perfect identification of the work to be executed.
In the highway segments where the possibility of constructing the new lane occurs
traffic, parallel and contiguous to the existing one, a study will be made to determine the side in
that will be released, taking into account construction difficulties, problems of
expropriations and compensation for earthmoving volumes. In the segments of
highway where it is necessary to launch the new lane with the independent guideline
from the existing, one should, whenever possible, project returns at intervals of about 5
km.
b) Traffic Study
d) Geological Study
e) Hydrological Study
f) Alignment Study
g) Topographic Study
h) Geotechnical Study
i) Geometric Project
j) Earthworks Project
k) Drainage Project
l) Paving Project
EB-110 - Basic Scope for the Development of Executive Engineering Project for Road Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 161
q) Projeto de Sinalização
s) Expropriation Project
Environmental Component of the Project
u) Work Budget
EB-110 - Basic Scope for the Preparation of Executive Engineering Project for Road Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 162
If a Basic Project has already been developed for the road segment, a will be carried out.
detailed reassessment of your Basic Project phase, based on:
a) Evaluation of the basic project developed, considering the necessary services for
execution of the work and corresponding costs;
EB-110 - Basic Scope for Development of Executive Engineering Project for Highway Duplication
Basic Guidelines for the Preparation of Highway Studies and Projects 163
c) Evaluation of any and all observations deemed relevant and that come
modify any conclusion or recommendation of the existing Basic Project;
d) Preparation of a conclusive opinion regarding the solutions presented in the Basic Project
existing through the analysis of its Presentation Volumes (Volumes 1, 2, 3, and 4)
In the development of the activities of this Basic Project Phase, the following must be observed
the following aspects:
The preparation of the schematic registration of the highway must indicate the following elements:
These studies will aim to evaluate the behavior of traffic on the highway, for
homogeneous subsection, during the useful life period, counted from the release of the subsection,
based on the existing geometric project and the topographical studies conducted
They also aim to determine the Number N, for the purpose of sizing the
roadway pavement.
c) Data processing;
d) Traffic projections;
EB-110 - Basic Scope for the Preparation of Executive Engineering Project for Highway Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 164
a) Section Registration;
After the collection and analysis of data on accidents, the section must be inspected.
aiming to detect failures in the adopted traffic engineering system, regarding
regarding visibility deficiencies, geometry problems, superelevation
inadequate, poor or nonexistent signage, insufficient road capacity, locations
unsuitable for pedestrian crossings, among others.
The following will define the engineering measures aimed at the elimination of these.
accidents, as well as the prioritization of critical sections for investment purposes in
function of accident indices and costs, before and after interventions of
engineering.
b) Geological mapping;
c) Geological description of the review;
d) Recommendations.
Hydrological studies will be carried out with a view to verifying the functioning
hydraulic of problematic surface and deep drainage devices
mainly those that have insufficient structural and flow conditions.
The following activities will be developed:
EB-110 - Basic Scope for the Preparation of Executive Engineering Project for Road Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 165
a) Collection of local information and with conservation teams regarding the operation
two surface and deep drainage devices;
At this stage, the identified routing alternatives for the independent tracks.
(removed) from the existing track, must undergo an evaluation process.
comparison for the purpose of defining the paths to be designed.
The topographic studies for the Basic Project are developed in a single phase, and
poderão ser realizados por:
The topographic survey by aerial photogrammetric process will observe the following
sequence:
Aerial Photogrammetry Coverage and Support for Basic Highway Project - Phase
IS-226
Basic Project (Single Phase)
Aerophotogrammetric Reimbursement and Field Support for Basic Project
IS-227
Highway - Basic Design Phase (Single Phase)
The topographic survey using conventional process will follow the sequence indicated to
to follow
EB-110 - Basic Scope for the Development of Engineering Executive Project for the Duplication of Highway
Basic Guidelines for the Preparation of Road Studies and Projects 166
e) Supplementary surveys
f) Total space
g) Tracking
[Link]. PISTAEXISTENTE
The geotechnical studies for the existing runway, in the case of Rigid and Semi-Pavements
Rigid ones will provide subsidies for the preparation of the diagnosis of the existing pavement,
consisting of the following activities:
e) Registration and selection of quarries, sandbanks, and other existing materials along
from the highway, which may be used in the pavement rehabilitation project;
Para a execução dos levantamentos anteriormente mencionados serão utilizadas aIS 212
Service Instruction for Structural Assessment and Rehabilitation Project of
Flexible and Semi-Rigid Pavements - Basic Design Phase and the methodologies
follow indicated:
EB-110 - Basic Scope for the Preparation of Engineering Executive Project for the Duplication of Highway
Basic Guidelines for the Development of Road Studies and Projects 167
Methodology Title
The existing pavement being Rigid Pavement, the following must be observed
methodologies
Methodology Title
2nd TRACK
For the runway to be implemented, the 2nd runway, the geotechnical studies should involve:
EB-110 - Basic Scope for the Development of Executive Engineering Project for Highway Duplication
Basic Guidelines for the Development of Road Studies and Projects 168
c) Typical cross sections of the platforms, based on the conclusions of the Studies of
Traffic carried out in this phase.
The project for the paving of the runway to be implemented, the 2nd runway, in this Project Phase
Basic includes the definition of the pavement design, based on sizing.
preliminary and structural solutions of the pavement, which should be subject to technical analysis
economic, and the estimate of service quantities:
Based on the geotechnical studies and the assessment of the existing pavement, a
basic project for the rehabilitation of the existing pavement, based on the Instructions of
Service and Standards following, in the case of flexible and semi-rigid pavements:
EB-110 - Basic Scope for the Preparation of Executive Engineering Project for Road Duplication
Basic Guidelines for the Preparation of Highway Studies and Projects 169
Norma Activity
In the preparation of the Pavement Rehabilitation Project, this phase must adopt
the following criteria:
a) dimension the pavement using at least three methods indicated in the table
anterior
b) adopt the thicknesses of the reinforcement layer provided by the method that best
adapt to the functional and structural conditions of each homogeneous segment;
c) compare the costs of the alternatives for the purpose of choosing the most suitable solution and
present the justification for the chosen solution in volume 3.
The pavement rehabilitation project must contain, at a minimum, the following elements:
− Physical schedule;
For the special artworks to be constructed as part of the 2nd track, they must
the following activities should be carried out:
EB-110 - Basic Scope for the Preparation of Executive Engineering Project for Road Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 170
b) Study of alternatives for the crossing, concerning the location of implantation of the
work;
c) Study of executable structural solutions, resulting from the examination of the site
implementation, with definition, for each proposed solution, of the total length of the
work, number of spans, main geometric characteristics, extent of the embankments of
access and foundations;
This basic project includes the graphical representation of intersections, returns and
expected accesses. It should include:
With the data obtained in the preparation of the highway registration, where they were marked
deficiencies of the road signage in the section, a signage project will be developed.
It will be prepared including the replacement or repairs of defenses, barriers, and fences.
delimitation and any possible containment works.
EB-110 - Basic Scope for the Development of Executive Engineering Project for Highway Duplicatio
Basic Guidelines for the Preparation of Road Studies and Projects 171
In this Basic Project phase, the Expropriation Project will be limited to an assessment.
the areas to be expropriated, and an estimate of their costs.
These procedures should be based on the Geometric Project developed in this phase.
The Environmental Component of the Project, in this Basic Project Phase, must be
developed according to the following activities:
In this Basic Project Phase, the Environmental Component of the project must be developed.
according to the provisions of IS-246 - Environmental Component of Projects
Road Engineering - Basic Design Phase.
The Environmental Component of the Project at this Stage will be consolidated by the Basic Report.
of Environmental Assessment - RBAA, which is configured as the document to subsidize the
analysis and evaluation of the environmental damage caused by the Enterprise, having as
one of its main functions is to equip the licensing authority's decision in the sense
to grant the Installation License - LI, of the Enterprise, whenever the
the bidding for the work is based on this Basic Engineering Project.
At the end of the studies developed in this phase, the costs of the work will be estimated.
for pavement rehabilitation, and introduction of improvements to increase capacity and
security adopting the methodology recommended in IS-220 Project Budget -
Preliminary Phase and Basic Project in the recommendations of the Cost System
Road workers of DNIT - SICRO.
The executive engineering project for the duplication of a highway is the set of elements
necessary and sufficient, with an appropriate level of precision, to characterize the work or
service, developed based on the indications of the preliminary technical studies, that
ensure the technical viability and proper treatment of the environmental impact of
enterprise, including the preparation of the necessary detailing for execution
EB-110 - Basic Scope for the Preparation of Executive Engineering Project for Highway Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 172
the works, the evaluation of its cost and the definition of the methods and the execution time,
having to include the following elements:
a) information that allows for the study and deduction of construction methods,
temporary installations and organizational conditions for the work;
b) subsidies for the preparation of the bidding plan and project management;
The Environmental Component of the Project at this Executive Project Phase consists of
detailing and preparation of the budget for environmental protection measures, wants
corrective, whether preventive, indicated in the Basic Project Phase, aiming at
rehabilitation/recovery of the environmental liabilities and the execution of the works in a way
environmentally friendly.
In this Executive Project Phase, the Environmental Component of the Project will be developed.
according to the provisions of IS-246 - Environmental Component of Projects
Road Engineering - Executive Design Phase.
The Environmental Component of the Project, at this Phase, will be consolidated by the Final Report.
of Environmental Assessment - RFAA that should contain the elements that characterize the
detailing of the environmental protection measures established in the Project Phase
Basic.
In the case where the bidding for the work is based on this Executive Project of
Engineering, the Final Environmental Assessment Report - RAAF must provide
additional information that allows DNIT to request from the Environmental Agency
Licensor, the Installation License - LI, of the Enterprise.
The activities to be developed in this phase must comply with the provisions in
following Service Instructions:
EB-110 - Basic Scope for the Development of Executive Engineering Project for Highway Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 173
At the end of the Preliminary Phase, the Preliminary Project Report will be presented.
Executive, containing the observations and recommendations deemed pertinent, being
consisting of the following volumes:
EB-110 - Basic Scope for the Preparation of Executive Engineering Project for Highway Duplication
Basic Guidelines for the Development of Road Studies and Projects 174
RELATORIO PRELIMINAR
At the end of the Basic Design Phase, the Basic Project Report will be presented.
Executive, containing the proposed solutions, indicative tables of the characteristics
techniques and operational and quantitative services, consisting of the following volumes:
BASIC PROJECT
With the completion of the Executive Project, the Final Report will be presented.
Executive Project, initially in the form of a draft. After review and approval by DNIT,
will be presented in the form of final printing. The Final Report will consist of
through the following volumes:
FINAL REPORT
VOLUME FORMAT
TITLE
Printing
Minute
Definitive
EB-110 - Basic Scope for the Preparation of Executive Engineering Project for Highway Duplication
Basic Guidelines for the Preparation of Road Studies and Projects 175
ANNEX A11
EB-111 - BASIC SCOPE FOR THE PREPARATION OF EXECUTIVE PROJECT
ENGINEERING FOR THE CONSTRUCTION OF LOCAL ROADS
1 DEFINITIONS
The Executive Engineering Project for the Construction of Rural Highways is called
a set of elements necessary and sufficient for the complete execution of the work, of
in accordance with the Technical Standards of DNER and DNIT.
Given the nature of the services and works to be carried out in the construction of highways
neighbors, the bidding for the work must be carried out solely and exclusively from its
Executive Project, with the Basic Project being an intermediate phase of the services.
This Basic Scope pertains to the Executive Engineering Project for Construction of
Local Roads, to be developed consecutively to the respective Studies
Preliminary studies and Basic Project, allowing to fully characterize the work from the point of view
view from the execution, and including all the elements from the previous phases, added with the
level of detail specific to the Executive Project, in such a way as to provide a view
global of the work, and identify all its constructive elements clearly.
The Preliminary Phase and Basic Project is characterized by data collection and
specific studies are being carried out with the purpose of defining the layout to be
designed.
EB-111 - Basic Scope for Preparing Executive Engineering Project for the Construction of Rural Roads
Basic Guidelines for the Preparation of Road Studies and Projects 176
a) Traffic studies;
b) Estudos de traçado;
c) Hydrological studies;
Traffic Studies of the Executive Project for the construction of rural roads
IS-236
Preliminary Phase and Basic Project (Single Phase)
Design studies of the executive project for the construction of local roads
IS-237
Preliminary Phase and Basic Design (Single Phase)
Hydrological Studies of the Executive Project for road construction
IS-239 neighbors - Preliminary Phase and Basic Project Phase (Single Phase)
d) Volumetric and classificatory counts, carried out for at least 3 days, in the
situations in which traffic data is not available or is
outdated;
EB-111 - Basic Scope for the Preparation of Executive Engineering Project for the Construction of Local Roads
Basic Guidelines for the Development of Road Studies and Projects 177
The Basic Project for Special Artworks will basically consist of the definition of
project conception.
Based on the conclusions and recommendations from the Preliminary Phase and Basic Project, it will be
Executive Project Phase initiated, with the purpose of detailing the selected solution.
providing plants, drawings, and service notes that allow for the bidding of the work.
The following elements must be provided:
− Topographic studies;
− Geotechnical studies;
− Geometric project;
− Earthmoving project;
− Drainage project;
− Fence project;
− Expropriation project;
− Environmental Component;
EB-111 - Basic Scope for the Preparation of Executive Engineering Project for the Construction of Local Roads
Basic Guidelines for the Preparation of Road Studies and Projects 178
EB-111 - Basic Scope for the Development of Executive Engineering Design for the Construction of Local Roads
Basic Guidelines for the Development of Highway Studies and Projects 179
EB-111 - Basic Scope for Preparing Engineering Executive Project for Construction of Country Roads
Basic Guidelines for the Preparation of Road Studies and Projects 180
Based on the Traffic Studies (Preliminary Phase and Basic Design) and on
Topographic studies must be developed:
The Drainage Project must dimension the selected devices for the
surface drainage systems, drainage of culverts, and deep drainage.
From the Project of Special Works of Art, this Executive Project Phase must include
basically:
b) Preparation of the graphic documentation of the project (floor plans, elevations and
longitudinal and transverse sections, as well as structural and architectural details.
At this stage, all the essential elements for the Instruction must be raised.
of the expropriation processes for the construction of the local highway.
EB-111 - Basic Scope for the Development of Executive Engineering Project for the Construction of Local Highways
Basic Guidelines for the Preparation of Highway Studies and Projects 181
The Environmental Component of the Project, in this Executive Project Phase, will be developed.
according to the following activities, and must comply with the provisions in the Service Instruction
The Environmental Component of the Project will be consolidated by the Assessment Report.
Environmental - RAA, which is established as the document to support the analysis and evaluation
two environmental damages caused by the Enterprise, having as one of its
main functions to empower the licensing authority's decision to grant
Installation License - LI, of the Enterprise.
At the end of the work carried out in this phase, the costs of the services will be defined and
works for the construction of the local highway, according to the recommendations of the System of
Road Costs of DNIT - SICRO, and in accordance with the methodology recommended in
Service Instruction:
Presentation of the rational sequence of the set of activities that must be executed.
of the project, indicating the problems of climatic, administrative, technical and
{"segurança":"security","época do início dos trabalhos":"time of the start of the work","período de execução":"execution period","conseqüência da":"consequence of"}
location, type of work and other conditioning factors for construction, including
implications with traffic, in the case of existing highways.
The Execution Plan for the work, to be prepared for each construction lot, will take into account
consideration of the aspects related to climate and rainfall, particularly regarding
to the rainy season and number of rainy days per month, logistical support, deadline for the
execution of the works, minimum equipment and action plan for the services.
EB-111 - Basic Scope for the Preparation of an Executive Engineering Project for the Construction of Local Roads
Basic Guidelines for the Development of Road Studies and Projects 182
4 PROJECT PRESENTATION
At the end of the Preliminary Phase and Basic Project, the Basic Report will be presented.
of the Project, containing the conclusions of the developed studies and the recommendations
proposals, which will be constituted by the volume detailed below.
BASIC REPORT
Finalizing the development of the Executive Project, the Final Report will be presented.
Project, initially in the form of a draft. After examination and approval by DNIT, it will be
presented in the form of a final print. The Final Report will consist of the
following volumes:
FINAL REPORT
FORMAT
VOLUME TITLE
Printing
Minute
Definitive
EB-111 - Basic Scope for the Preparation of Executive Engineering Project for the Construction of Local Highways
Basic Guidelines for the Preparation of Road Studies and Projects 183
APPENDIX A12
EB-112 - BASIC SCOPE FOR THE ELABORATION OF EXECUTIVE PROJECT
ENGINEERING FOR THE STABILIZATION OF ROAD EMBANKMENTS
1 DEFINITION
Given the nature of the services and works to be carried out for the stabilization of slopes
of highways, the bidding for the work must be carried out solely and exclusively from
your Executive Project, with the Basic Project being an intermediate stage of the services.
This Basic Scope pertains to the Executive Engineering Project for Stabilization
from Road Embankments, to be developed consecutively to the respective Studies
Preliminary studies and Basic Project, allowing to fully characterize the work from the point of view of
view of execution, and containing all the elements from the previous phases, added to the
detail level specific to the Executive Project, in such a way as to provide a view
global of the work, and identify all its constructive elements clearly.
This phase is characterized by the collection and analysis of existing information and by
development of studies, assessments, and services at Preliminary and Basic levels, that
allow the identification of the various solutions to be proposed.
EB-112 - Basic Scope for the Development of Executive Engineering Project for Stabilization of Road Slopes
Basic Guidelines for the Development of Road Studies and Projects 184
EB-112 - Basic Scope for the Development of Executive Engineering Project for Highway Slope Stabilization
Basic Guidelines for the Preparation of Road Studies and Projects 185
f) probing profiles.
EB-112 - Basic Scope for the Preparation of Executive Engineering Project for Slope Stabilization of Highways
Basic Guidelines for the Preparation of Road Studies and Projects 186
The survey profiles must have a homogeneous scale and contain the following elements
minimums
− Level reference;
− Position of NA;
− Tipo de sondagem;
− Type of sampler;
A plan showing the location of all the boreholes and tests must be provided.
executed, properly tied to easily identifiable known points.
b) cross sections drawn to scales 1:100, 1:200, and 1:500, depending on the
location of the slope;
c) rental of slabs and rock plates and boulders, perfectly tied together,
allowing for easy identification in the field, during the execution phase of the works;
i) cross sections, between offsets, at least three on each slope, covering the
affected region, the surveys and the necessary bindings; and
EB-112 - Basic Scope for the Preparation of Executive Engineering Project for Stabilization of Road Slopes
Basic Guidelines for the Preparation of Road Studies and Projects 187
Based on the data obtained from previous studies, the analysis should be conducted on
stability.
In this phase, the most suitable technical solution must be selected from solutions
identified alternatives, and proceeded to detail them at an executive level.
The following are the technical solutions that are usually recommended for
stabilization of roadway slopes:
a) Tensioned curtains;
Gabion wall;
e) Rip-rap wall;
f) Stacking;
g) Sub-horizontal drains.
The technical characteristics of these works, and the procedures to build them, are
expressed in the Basic Implementation Manual - DNER/1996.
In the case of the retaining structure project, internal drainage must be designed.
this, aiming to relieve the hydrostatic and hydrodynamic pressures of the water table,
existing in the vicinity of the work, reducing the total thrust on the aforementioned
structure.
When the cause of instability is due to the rise of the water table or the level
for confined aquifers, the use of sub-horizontal drains is recommended.
In cases of large-scale landslides, this is sometimes the only
economic solution that can be sought, as indicated in the Drainage Manual,
do DNER.
a) Preventing rainwater from the contributing basins from reaching, whether they are
subterranean or surface, both the protected areas of the slopes' surfaces
like the unsteady ones, leading them to safe places;
EB-112 - Basic Scope for the Preparation of Engineering Executive Project for the Stabilization of Road Slopes
Basic Guidelines for the Development of Road Studies and Projects 188
With the data obtained from the hydrological studies, the devices will be sized.
drainage intended to conduct water in order to meet the mentioned objectives.
The Environmental Component of the Project, in this Executive Project Phase, will be developed.
according to the following activities, and must comply with the provisions of the Service Instruction
The Environmental Component of the Project will be consolidated by the Evaluation Report.
Environmental - RAA, which is configured as the document to support the analysis and evaluation
two environmental damages caused by the Enterprise, having one of its
main functions to empower the licensing authority's decision to grant
Installation License - LI, of the Enterprise.
In the selection of plant species for the consortium of grasses and legumes,
consider the following:
EB-112 - Basic Scope for the Preparation of Executive Engineering Project for the Stabilization of Highway Slopes
Basic Guidelines for the Preparation of Road Studies and Projects 189
Understand the detailing of the selected technical solution, following the scale of
priorities defined in the study phase, including calculations, details, plans,
sections, etc., necessary for the complete clarification of the project and budget for the
stabilization of each slope.
Whenever necessary, monitoring of the slope should be proposed, aiming to observe the
behavior of the mass and confirm the correctness of the adopted technical solution.
4 PRESENTATION
The presentation of the Slope Stabilization Project in its Preliminary Phase and of
Basic Project will be carried out through the Basic Project Report, which must be
composed of the volume:
BASIC REPORT
FINAL REPORT
Format
Volume Discrimination
Minute
Definitive
Printing
EB-112 - Basic Scope for the Development of Executive Engineering Project for the Stabilization of Highway Slopes
Basic Guidelines for the Preparation of Road Studies and Projects 190
ANNEX A13
EB-113 - BASIC SCOPE FOR PROGRAM DEVELOPMENT
ROAD EXPLORATION - PER
1 DEFINITION
2.1. FIRSTPHASE
It should include the indication of the necessary Initial Works for a recovery.
the emergency operation of the highway, providing it with minimum safety conditions and
comfort, and relating the facilities to be implemented to allow operation
full of the highway, with all the necessary equipment and operational systems,
executed and completed within the deadline set by the PER, before the start of the charge
toll.
For each work, service or activity covered in the PER, the following will be defined:
EB-113 - Basic Scope for the Development of a Road Exploration Program (PER)
Basic Guidelines for the Elaboration of Highway Studies and Projects 191
b) unit and total quantities for the road recovery works, including
Initial Works and Capacity Expansion, in order to allow that the
competitors can quote the costs of the charges throughout the concession;
c) schedules, so that the competitors have full knowledge of the starts and
end of activities;
d) criteria for inspection and monitoring, with the respective graduation plans
sanctions to be applied to the Concessionaire for delay or total or partial non-performance
of the duties of the concession.
OPER will define the interventions of a structural, operational, organizational nature and
management of the highway, in order to meet acceptable highway standards,
establishing
– No management.
b) aspects of engineering and operation of the highway to be executed in the 1st
Phase:
Pavement;
• Lighting
• Containment
• Cleaning
EB-113 - Basic Scope for the Preparation of Road Exploration Program (PER)
Basic Guidelines for the Development of Road Studies and Projects 192
Access;
• Information services
• Quality control.
Highway improvements.
OPER should establish guidelines for the quantification and location of the squares
toll, based on the expected traffic volumes over the concession period.
Economic growth rates for the region should be raised, which will result in
growth rates of traffic in the various sections of the highway, along with the assessment of
levels of service respective throughout the concession period. With the aim of defining
the time when each improvement should be executed, it must be considered that the
operational level, at peak time, will be at least level D of the HCM - Highway
Capacity Manual, latest edition, regarding continuous sections. For the
intersections must comply with the recommendations of the Intersection Design Manual
of DNER, regarding the determination of level D, which is also based on the Standards
Germans.
EB-113 - Basic Scope for the Development of a Highway Exploration Program (PER)
Basic Guidelines for the Preparation of Road Studies and Projects 193
3.2. BASIC ENGINEERING PROJECT FOR THE RECOVERY AND OPERATION OF THE HIGHWAY
The Basic Engineering Project for the Recovery and Operation of the Highway will be
prepared to allow ANTT - National Agency for Land Transportation to bid,
select and hire the Concessionaire. With this objective, the basic project must
provide the definition of the highway needs, the schedule for the implementation of each
planned work or service, relating and quantifying the services to be executed
and preparing the respective budgets for the project.
The elements contained in the basic project will be used as support for the
preparation of the Bidding Notice, for the development of Technical and Price Proposals
dos concorrentes e para a análise e julgamento das referidas propostas.
The Basic Engineering Project for the Recovery of the Highway will be the set of
studies and projects to be developed with the aim of recovering the highway and equipping it with
operational characteristics suitable for your operation throughout the entire period of
concession.
The result obtained from the completion of this set of tasks will consist of
following elements:
Pavement restoration;
[Link]. STUDIES
– tying to the mileage of the existing signage, with precision of the ten
meters, two notable points of the highway, comprising at least, and not being
restricting them:
• start and end of special artworks;
Traffic and capacity studies will aim to support the preparation of the
basic projects for operational capacity and pavement adaptation, covering
EB-113 - Basic Scope for the Development of Highway Exploration Program (PER)
Basic Guidelines for the Preparation of Road Studies and Projects 195
the entire duration of the concession and also provide the necessary elements for the
calculation of the tariff and for the analyses of economic and financial feasibility of
enterprise.
Definition of growth rates and traffic volumes for the entire period of
granting;
Evaluate the stability conditions of the masses and slopes and, if necessary,
identifying potential risk areas;
EB-113 - Basic Scope for the Development of Road Exploration Program (PER)
Basic Guidelines for the Development of Road Studies and Projects 196
Surface drainage 10
Transposition of watercourses (culverts) 10 to 50
Special works of art 100
expedited topographic studies - these studies will be carried out only in the locations
where there is a need for the implementation of improvements and they are not found
reliable elements for the quantification of the services to be indicated. The elements
Raised will be properly tied to the mileage of the existing signage.
– Characterize the available materials for construction: natural soils, sands and
rock occurrences;
– Identify and tie to the mileage of the existing signage the locations with
stability problems of slopes and masses and indicate and quantify them
possible containment and stabilization solutions;
Characterize the foundation soils of embankments and current engineering works;
Identify and tie the existing signage mileage to the locations where
widenings, reinforcement or construction of new works will need to be carried out
special arts, with characterization of foundation soils.
The Environmental Studies must result in information that allows requests to be made,
together with the Environmental Licensing Body, the Preliminary License - LPeLicense of
Installation - LI, of the Enterprise.
i) estudos para avaliação do pavimento existente - estes trabalhos terão por objetivo:
Evaluate the existing condition of comfort and maintenance of the existing pavement;
EB-113 - Basic Scope for the Preparation of Road Exploration Program (PER)
Basic Guidelines for the Preparation of Road Studies and Projects 197
Support the preparation of the basic recovery projects for the pavement in
emergency level (1st Phase) and structural recovery (2nd Phase).
For the execution of this assessment, the available data can be used from
DNER related to the Pavement Management, as well as existing projects, since
that the referred elements may be considered valid for the project to be
proposed.
[Link]. PROJECTS
The projects will always be developed with the aim of indicating solutions.
of emergency and long-term recovery, since the collection of tolls, for
from the Concessionaire, it can only be initiated from the moment when the
The road must provide a minimum condition of safety and comfort for the user.
Initial Works - 1st phase
Initial Works is the term used for the set of all services that, when being
executed, enable immediate recovery to minimum levels of conditions
of safety and comfort offered by the highway to the user, as well as its operation,
to be implemented in the first months of the concession. Within this concept, the
basic project of initial works, to be developed based on the data collected in
fase de estudos, deverá prever as seguintes ações:
EB-113 - Basic Scope for the Preparation of Road Exploration Program (PER)
Basic Guidelines for the Preparation of Highway Studies and Projects 198
All work to be carried out in this phase will be related, detailed and
quantified, with the minimum quality criteria for being specified.
acceptance of these services by the Inspection.
General recovery of the road system, including the stabilization of slopes and
slopes, elimination of erosion, correction of platform subsidence, cleaning,
recovery and adaptation of the drainage system and implementation of devices
surface protection and landscaping;
EB-113 - Basic Scope for the Preparation of a Highway Exploration Program (PER)
Basic Guidelines for the Preparation of Road Studies and Projects 199
Also, this Project should be developed aiming at the implementation of two phases.
namely:
Basically, during this phase, which will precede the start of toll collection,
the recovery and/or implementation of the buildings and installation of
systems for full operation, the detailed organization of the operation, the
establishment of schedules for the implementation of the 'facilities' that
we will surpass the period of this phase, and the development of service of
relationship with the user.
EB-113 - Basic Scope for the Development of Road Exploration Program (PER)
Basic Guidelines for the Development of Road Studies and Projects 200
• Operational Control Center (CCO) - the most suitable location must be indicated
suitable and the deadline to complete the installation;
EB-113 - Basic Scope for the Development of Road Exploration Program (PER)
Basic Guidelines for the Preparation of Road Studies and Projects 201
For this phase, oPER should establish the minimum performance standards that
must be served by the highway operation systems and foresee the
completion of the installations which are expected to be concluded in this phase,
highlighting:
The maximum distance between the emergency call boxes will be 5 km.
should, however, be reduced in sections of heavier traffic or subject to
largest number of accidents.
It will restore the points of definitive deployment of the operation systems and
traffic control, highlighting, among others:
EB-113 - Basic Scope for the Development of a Road Exploration Program (PER)
Basic Guidelines for the Development of Road Studies and Projects 202
These services should have their quantities estimated, year by year, throughout the
concession period, including the construction period.
It will be composed of the necessary elements to define the task that, being
technically correct and socially acceptable, allows the execution of the PER and obtaining
an internal rate of return (IRR) compatible with the one adopted in the market for
ventures of the same nature, considering the traffic volume based on
properly grounded projections.
e) costs of services;
EB-113 - Basic Scope for the Development of a Road Exploration Program (PER)
Basic Guidelines for the Preparation of Highway Studies and Projects 203
All these parameters will be considered in accordance with the reality in force at the time of
drafting of the PERe, also consider the expectation of international inflation for the
concession period.
The methodologies and criteria to be used for conducting these studies and analyses
will be explained and justified for approval by the DNER during the phase of
elaboration of the PER. The SACRO system, available at DNER, may be used for
feasibility analysis implementation.
The Analysis of the Economic and Financial Viability of the Enterprise must be
presented with the following structure:
a) Presentation;
b) Methodological Summary;
c) Traffic Parameters;
d) General Budget;
Physical-Financial Programs;
For the standardization of the tariff proposals from the competitors for the Concession bidding,
the values of the construction costs, of the operation works will be defined in the PER,
conservation and maintenance of the equipment to be installed, the schedules
physical and financial, the estimates of the costs of insurance and guarantees, as well as the
possible sources of funding, the revenue statements, and the presentation of
demonstration of accounting and financial results.
EB-113 - Basic Scope for the Preparation of a Highway Exploration Program (PER)
Basic Guidelines for the Preparation of Road Studies and Projects 204
The terms of reference that will be part of the future notice must be presented in the PER.
of the bidding for the selection of the Concessionaire. These terms of reference will contain the
elements of the Basic Engineering Project for the Recovery of the Highway, the list of
works to be carried out, the schedules for the execution of the various works and
implementation of various systems and their respective quantities, encompassing
quantitative data of civil and road works, of maintenance and conservation activities, and
of equipment and systems for the operation and monitoring of the highway.
The terms of reference should clearly and objectively propose the way to
presentation of technical and pricing proposals, separating them into three distinct parts:
Technical Proposal, Economic and Financial Plan, and Toll Rate. They must indicate
instructions on filling out tables, presenting statements, and the format
of the judgment of the proposals from the competitors for the bidding of the Concession, covering
at least the following criteria: degree of understanding of the relevant issues,
consistency of the propositions, quality of the information presented, compatibility
from the Proposal with oPERe with the object of the bidding, coherence between the knowledge of
the problem is the work plan.
The proposals to be presented by the competitors in the bidding for selection of the
Concessionaire, they must be prepared in accordance with the notices of
Competition:
a) Technical Proposal;
b) Rate Proposal
EB-113 - Basic Scope for the Development of Road Exploration Program (PER)
Basic Guidelines for the Preparation of Road Studies and Projects 205
Toll Rate
4 PROGRAM PRESENTATION
The Final Report of the Highway Execution Program - PER will be presented
initially in the form of a draft, for examination by DNER. The final impression of
The Final Report should be edited according to the approved draft of the Final Report.
observed the corrections, additions, and clarifications resulting from the analysis
conducted by the inspection. The Final Report will contain all the studies and projects that
I support the adopted solutions, with the information, drawings, graphs, and attachments.
necessary for your analysis and understanding, including the list of works to be
executed, the schedules for the execution of all works and services and the implementation
of two different systems, and the respective quantities encompassing the civil works
bus stations and buildings, the electromechanical installations, the maintenance activities and
conservation, equipment and systems for the operation and monitoring of the highway. The
The Final Report must consist of the following volumes:
FINAL REPORT
EB-113 - Basic Scope for the Development of a Highway Exploration Program (PER)
Basic Guidelines for the Development of Highway Studies and Projects 206
ATTACHMENT A13
EB-114 - BASIC SCOPE FOR THE PREPARATION OF BASIC PROJECT FOR
HIGHWAY PAVEMENT REHABILITATION
1 DEFINITIONS
It consists of the set of studies and projects developed with the primary objective of
reinforce the existing pavement, either by adding new structural layers, or by
replacement of one or more layers of the pavement, or proceeding with the recomposition
total of the flooring, in such a way that the resulting structure can economically
support the repetition of the loads per axis incident, under safe conditions and
comfort for the user during the new project period.
The provisions of the Basic Scope EB-106: Basic Project must be observed.
Engineering for Pavement Rehabilitation with Improvements for Adaptation of
Capacity and Safety.
a) Preliminary Phase;
The Basic Engineering Project for the Rehabilitation of Road Pavements should
count the following elements:
a) development of the chosen solution in order to provide a global view of the work and
identify all of its constituent elements clearly;
EB-114 - Basic Scope for the Preparation of Basic Engineering Project for Highway Pavement Rehabilitation
Basic Guidelines for the Development of Road Studies and Projects 207
e) subsidies for the preparation of the bidding plan and project management, including
your programming, the supply strategy, the inspection standards, and others
necessary data in each case;
f) budget of the total cost of the work, based on service quantities and
supplies of materials and transports properly evaluated.
b) Traffic studies;
d) Geological studies;
e) Hydrological studies;
Preliminary Evaluation of the Existing Pavement, and
g) Environmental Component of the Project.
EB-114 - Basic Scope for the Preparation of Basic Engineering Project for the Rehabilitation of Highway Pavement
Basic Guidelines for the Development of Highway Studies and Projects 208
In the development of the activities of this Preliminary Phase, the following must be observed
following aspects:
a) Data related to the history of the VMD and fleet composition, obtained from DNIT;
c) Volumetric and classificatory counts, carried out for at least 3 days, in the
situations where traffic data is not available or is
outdated;
a) Section Registration;
EB-114 - Basic Scope for the Preparation of Basic Engineering Project for Road Pavement Rehabilitation
Basic Guidelines for the Development of Road Studies and Projects 209
After collecting and analyzing data on accidents, the section should be inspected.
aiming to detect failures in the adopted traffic engineering system, regarding
regarding visibility deficiencies, geometry problems, superelevation
inadequate, poor or nonexistent signage, insufficient road capacity, locations
unsuitable for pedestrian crossing, among others.
The following will define the engineering measures aimed at eliminating these.
accidents, as well as the prioritization of critical sections for investment purposes in
function of indices and accident costs, before and after the interventions of
engineering.
c) Field investigations
It basically consists of the collection of hydrological data (climate, rainfall, river flow and
geomorphology) of the region.
The preliminary studies of the existing pavement, for the purpose of identifying the solutions
alternatives should encompass the analysis of existing field surveys with the
objective of determining the functional and structural conditions for identification of the
solutions.
The Environmental Component of the Project, in this Preliminary Phase, consists of the preparation of
Preliminary Environmental Diagnosis of the direct influence area of the Enterprise, and
in the evaluations of the occurrences registered in the environmental surveys, and of the
environmental impacts that may result from the execution of the works, aiming at
proposition of environmental protection measures.
It must characterize the environmental situation of the area of influence of the enterprise in
physical, biotic, anthropic aspects, aiming for knowledge of the region before the
implementation of the project, serving as a reference for assessing the impacts
environmental impacts arising from the works and operation of the highway, and from the environmental liabilities.
EB-114 - Basic Scope for the Preparation of Basic Engineering Project for the Rehabilitation of Road Pavement
Basic Guidelines for the Preparation of Road Studies and Projects 210
In this Preliminary Phase of the Environmental Component of the project, it must be developed by
agreement with aIS-246 - Environmental Component of Highway Engineering Projects
Preliminary Phase, to be consolidated by the Preliminary Environmental Assessment Report
RPAA, which will allow for decision-making for the optimization of technical alternatives and
locational, as well as the initiative of DNIT, together with the Licensing Environmental Agency, to
end of request for the Preliminary License - LP of the Enterprise.
The basic project phase is characterized by the study of the current conditions of the highway with
the purpose of establishing a project for recovery, diagnosis, and recommendations. This
conjugate recovery measures for existing roads, covering environmental liabilities,
there is no need to develop route study.
A study will be conducted on the level of degradation reached by the pavement, determining
its causes and preliminarily assessing the cost of recovery.
Being common highways with paved lanes, with earthen shoulders and
devoid of surface drainage work, it is understood that together with the
the recovery of the pavement on the runways should study the system of
surface drainage and check the need to pave the shoulders.
b) Traffic Study
c) Geological Study
Hydrological Study
e) Topographic Study
f) Geotechnical Study
g) Drainage Project
i) Signage Project
EB-114 - Basic Scope for the Preparation of Basic Engineering Project for the Rehabilitation of Highway Pavement
Basic Guidelines for the Development of Highway Studies and Projects 211
l) Project Budget
In the development of the activities of this Basic Project Phase, the following must be observed
the following aspects:
The preparation of the schematic registration of the highway must indicate the following elements:
These studies will aim to evaluate the traffic behavior of the highway, for
homogeneous subsegment, during the useful life period, counted from the release of the segment to
traffic, based on the existing geometric design and the topographic studies carried out.
For the purposes of this scope, a homogeneous subsection is understood as one that has the
the same geometric characteristics and the same volumes and traffic compositions.
c) Data processing;
d) Traffic projections;
e) Determination of the number N.
b) Geological mapping;
c) Geological description of the review;
d) Recommendations.
3.3.4. ESTUDOSHIDROLÓGICOS
a) Collection of local information and with conservation teams regarding the operation
two devices for surface and deep drainage;
EB-114 - Basic Scope for the Development of Basic Engineering Project for the Rehabilitation of Highway Pavement
Basic Guidelines for the Development of Road Studies and Projects 213
The topographic studies for this Basic Project Phase are limited to the survey.
cadastral of the highway's right-of-way:
e) Registration and selection of quarries, sand pits, and other materials existing along
from the highway, which may be used in the pavement rehabilitation project;
For the execution of the aforementioned surveys, aIS 212 will be used.
Service Instruction for Structural Assessment and Rehabilitation Project
Flexible and Semi-Rigid Pavements - Basic Design Phase and the methodologies
follow indicated:
Methodology Title
The existing pavement being Rigid Pavement, the following must be observed
methodologies:
EB-114 - Basic Scope for the Development of Basic Engineering Project for the Rehabilitation of Road Pavement
Basic Guidelines for the Preparation of Road Studies and Projects 214
Methodology Title
Based on the geotechnical studies and the evaluation of the existing pavement, a will be prepared
pavement rehabilitation project, based on the Service Instructions and Standards
following:
Norma Activity
In the preparation of the Pavement Rehabilitation Project, this phase should adopt
the following criteria:
a) dimension the pavement using at least three methods indicated in the table
anterior
b) adopt thicknesses of the reinforcement layer provided by the method that best
adapt to the functional and structural conditions of each homogeneous segment;
c) compare the costs of the alternatives for the purpose of choosing the most suitable solution and
present the justification for the chosen solution in volume 3.
EB-114 - Basic Scope for the Development of Basic Engineering Project for Road Pavement Rehabilitation
Diretrizes Básicas para Elaboração de Estudos e Projetos Rodoviários 215
The pavement rehabilitation project must contain, at a minimum, the following elements:
− Physical schedule;
Since the existing pavement is rigid, the methodologies outlined in must be observed.
Rigid Pavements Manual, from DNIT, now under revision at IPR.
With the data obtained in the preparation of the highway registration, where were marked the
deficiencies of the road signage of the section, the signage project will be developed.
It will be developed including the replacement or repair of defenses, barriers, and fences.
delimitation and possible containment works.
The Environmental Component of the Project, in this Basic Project Phase, must be
developed according to the following activities:
In this Basic Project Phase, the Environmental Component of the project must be developed.
according to the provisions of IS-246 - Environmental Component of Projects
Road Engineering - Basic Design Phase.
EB-114 - Basic Scope for the Preparation of Basic Engineering Project for Road Pavement Rehabilitation
Basic Guidelines for the Development of Highway Studies and Projects 216
The Environmental Component of the Project in this Phase will be consolidated by the Basic Report.
of Environmental Assessment - RBAA, which serves as the document to support the
analysis and evaluation of the environmental damage caused by the Enterprise, having as
one of its main functions is to provide support for the decision of the licensing authority in order to
to grant the Installation License - LI, of the Enterprise, whenever the
the bidding for the work is based on this Basic Engineering Project.
At the end of the work developed in this phase, the costs of the services will be estimated.
for pavement rehabilitation, adopting the methodology recommended in IS-220
Budget of the work - Basic Project Phase and in the recommendations of the System
Road Costs of DNIT - SICRO.
Presentation of the rational sequence of the set of activities that must be executed
of the project, indicating the problems of a climatic, administrative, technical nature and
segurança; época do início dos trabalhos; período de execução; conseqüência da
location, type of work and other conditioning factors for construction, including
implications with traffic, in the case of existing highways.
The Execution Plan for the work, to be prepared for each construction lot, will take into account
considering the aspects related to climate and rainfall, particularly regarding
to the rainy season and the number of rainy days per month, logistical support, deadline for the
execution of the works, minimum equipment and attack plan for the services.
At the end of the Preliminary Phase, the Preliminary Report of the Basic Project will be presented.
containing the conclusions of the studies developed and the proposed recommendations, the
which will be constituted by the volumes detailed below.
PRELIMINARY REPORT
EB-114 - Basic Scope for the Preparation of Basic Engineering Project for the Rehabilitation of Highway Pavement
Basic Guidelines for the Preparation of Road Studies and Projects 217
4.2.1. MINUTES
At the end of the Basic Project Phase, the Draft of the Final Report will be presented.
Basic Project, in 4 volumes, as per the list below.
After the approval of the Draft, the Final Report's Definitive Print will be presented.
of the Project, according to the volumes detailed below.
EB-114 - Basic Scope for the Preparation of Basic Engineering Project for the Rehabilitation of Roadway Pavement
Basic Guidelines for the Development of Road Studies and Projects 218
ANNEX A15
EB-115 - BASIC SCOPE FOR THE DEVELOPMENT OF EXECUTIVE PROJECT
ENGINEERING FOR ROAD PAVEMENT REHABILITATION
1 DEFINITIONS
It consists of a set of studies and projects developed with the aim of strengthening the
existing pavement, by adding new structural layers, or by replacement of
one or more layers of the pavement, or to proceed with the complete recomposition of
pavement, in such a way that the resulting structure can economically support the
repetition of the loads per axle incident, under conditions of safety and comfort for the
user, during the new project period.
2 PROJECT PHASES
a) Preliminary Phase;
This Basic Scope refers to the Executive Engineering Project for Rehabilitation of
Highway pavement, to be developed consecutively to the respective studies.
Preliminary and the respective Basic Project, allowing to characterize the work
completely from the execution perspective, and containing all the elements of the phases
previous ones, added with the level of detail specific to the Executive Project, in such a way
to provide an overview of the work, and to identify all its constructive elements
clearly.
EB-115 - Basic Scope for the Development of Executive Engineering Project for Road Pavement Rehabilitation
Basic Guidelines for the Development of Road Studies and Projects 219
The preliminary phase is characterized by the surveys and studies of the current conditions of
highway for the purpose of establishing the basic project for its rehabilitation,
being, therefore, a phase of diagnosis and recommendations based on the conclusions
from the studies developed (including physical and operational improvements), through the
presentation of the various alternatives studied and the work plan for the phase of
basic project.
b) Traffic studies;
d) Geological studies;
e) Hydrological studies;
f) Preliminary Assessment of the Existing Pavement, and
If a Basic Project has already been prepared for the road segment to be executed
designed, a detailed analysis of the identified elements will be carried out, and a
substantial evaluation of the conclusions of the Preliminary Phase of the existing Basic Project,
always in accordance with the above related Service Instructions.
EB-115 - Basic Scope for the Preparation of Executive Engineering Project for Road Pavement Rehabilitation
Basic Guidelines for the Development of Road Studies and Projects 220
In the development of the activities of this Preliminary Phase, the following must be observed
following aspects:
a) Data related to the history of the VMD and fleet composition, obtained from DNIT;
a) Section Registration;
EB-115 - Basic Scope for the Preparation of Engineering Executive Project for Highway Pavement Rehabilitation
Basic Guidelines for the Preparation of Road Studies and Projects 221
After the collection and analysis of data on accidents, the section must be inspected.
aiming to detect failures in the adopted traffic engineering system, regarding
regarding visibility deficiencies, geometry problems, superelevation
inadequate, poor or non-existent signage, insufficient road capacity, locations
unsuitable for pedestrian crossing, among others.
The following will define the engineering measures aimed at the elimination of these.
accidents, as well as the prioritization of critical sections for investment purposes in
function of accident indices and costs, before and after the interventions of
engineering.
c) Field investigations
It basically consists of the collection of hydrological data (climate, rainfall, river flow and
geomorphology) of the region.
The preliminary studies of the existing pavement, for the purpose of identifying solutions
alternatives should cover the analysis of existing field surveys with the
objective of determining the functional and structural conditions for identification of the
solutions.
The Environmental Component of the Project, in this Preliminary Phase, consists of the preparation of
Preliminary Environmental Diagnosis of the direct influence area of the Enterprise, and
in the evaluations of the occurrences registered in the environmental surveys, and of the
environmental impacts that may arise from the execution of the works, aiming at
proposition of environmental protection measures.
It must characterize the environmental situation of the area of influence of the enterprise in
physical, biotic, anthropic aspects, aiming for knowledge of the region before the
EB-115 - Basic Scope for the Development of an Executive Engineering Project for the Rehabilitation of Highway Pavement
Basic Guidelines for the Preparation of Road Studies and Projects 222
In this Preliminary Phase of the Environmental Component of the project, it must be developed from
agreement with aIS-246 - Environmental Component of Road Engineering Projects
Preliminary Phase, to be consolidated by the Preliminary Environmental Evaluation Report
RPAA, which will allow for decision-making to optimize technical alternatives and
locational, as well as the initiative of DNIT, together with the Environmental Licensing Agency, to
request for the Preliminary License - LP of the Enterprise.
The basic design phase is characterized by the study of the current conditions of the highway with
the purpose of establishing a project for recovery, diagnosis, and recommendations. This
conjugate recovery measures for the existing highway, covering the environmental liabilities,
there is no need to develop a layout study.
A study will be conducted on the degree of degradation reached by the existing pavement.
determining its causes and preliminarily evaluating the cost of recovery.
Being common highways with paved lanes, with dirt shoulders and
lacking surface drainage works, it is understood that together with the
the recovery of the runway pavement must study the system of
surface drainage and check the need to pave the shoulders.
b) Traffic Study
c) Geological Study
d) Hydrological Study
e) Topographic Study
f) Geotechnical Study
g) Drainage Project
EB-115 - Basic Scope for the Preparation of Executive Engineering Project for the Rehabilitation of Highway Pavement
Basic Guidelines for the Development of Highway Studies and Projects 223
i) Signage Project
l) Project Budget
If a Basic Project has already been prepared for the road segment to be executed
designed, a detailed reassessment of its Basic Project phase will be carried out,
starting from:
a) Evaluation of the developed basic project, considering the necessary services for the
execution of the work and corresponding costs;
c) Evaluation of any and all observations deemed relevant and that come
modify any conclusion or recommendation of the existing Basic Project;
In the development of the activities of this Basic Project Phase, the following must be observed
the following aspects:
EB-115 - Basic Scope for the Development of Executive Engineering Project for the Rehabilitation of Road Pavement
Basic Guidelines for the Preparation of Road Studies and Projects 224
The preparation of the schematic register of the highway should indicate the following elements:
a) Domain range with bindings of the geographical features and other points
notable
b) Characterization of the highway sections regarding the type of pavement and layers,
indicating the dimensions of the domain strip, the platform, the pavement and the
berths;
These studies will aim to evaluate the behavior of traffic on the highway, for
homogeneous subsegment, during the useful life period, counted from the release of the segment to
traffic, based on the existing geometric design and the topographic studies conducted.
For the purpose of this scope, a homogeneous sub-section is understood as one that has the
the same geometric characteristics and the same volumes and traffic compositions.
c) Data processing;
d) Traffic projections;
e) Determination of the number N.
b) Geological mapping;
c) Geological description of the review;
d) Recommendations.
EB-115 - Basic Scope for the Development of Executive Engineering Project for Highway Pavement Rehabilitation
Basic Guidelines for the Development of Highway Studies and Projects 225
a) Collection of local information and with conservation teams regarding the operation
two drainage devices, surface and deep;
The topographic studies for this Basic Project Phase are limited to the survey.
cadastral of the right-of-way of the highway:
The geotechnical studies, whether the existing pavement is flexible or semi-rigid, will provide
subsidies for the elaboration of the pavement diagnosis, consisting of activities
following:
e) Registration and selection of quarries, sandbanks, and other materials existing along
from the highway, which may be used in the pavement rehabilitation project;
g) Pavement core samples to verify the types and thicknesses of layers and
characterization of the constituent materials.
For the execution of the aforementioned surveys, aIS 212 will be used.
Service Instruction for Structural Assessment and Rehabilitation Project
EB-115 - Basic Scope for the Preparation of Engineering Executive Project for Road Pavement Rehabilitation
Basic Guidelines for the Preparation of Road Studies and Projects 226
Flexible and Semi-Rigid Pavements - Basic Design Phase and the methodologies
follow indicated:
Methodology Title
The existing pavement being Rigid Pavement, the following must be observed
methodologies:
Methodology Title
Based on the geotechnical studies and the assessment of the existing pavement, the ...
rehabilitation project of the pavement, based on the following Service Instructions:
EB-115 - Basic Scope for the Development of Engineering Executive Project for Road Pavement Rehabilitation
Basic Guidelines for the Development of Road Studies and Projects 227
Norma Activity
In the preparation of the Pavement Rehabilitation Project, in this phase, the following should be adopted
the following criteria:
a) dimensioning the pavement using at least three methods indicated in the table
anterior;
b) adopt thicknesses of the reinforcement layer provided by the method that best fits
adapted to the functional and structural conditions of each homogeneous segment;
c) compare the costs of the alternatives for the purpose of choosing the most suitable solution and
present the justification for the chosen solution in volume 3.
The basic rehabilitation project of the pavement must contain, at a minimum, the following
elements:
− Physical schedule;
Since the existing pavement is rigid, the methodologies presented must be followed
Rigid Pavement Manual, by DNER.
With the data obtained in the preparation of the highway registration, where it was marked the
deficiencies in the road signage of the section, a signage project will be developed.
EB-115 - Basic Scope for the Preparation of Executive Engineering Project for the Rehabilitation of Highway Pavement
Basic Guidelines for the Preparation of Road Studies and Projects 228
The Environmental Component of the Project, in this Basic Project Phase, must be
desenvolvido segundo as seguintes atividades:
In this Basic Design Phase, the Environmental Component of the project must be developed.
according to the provisions of IS-246 - Environmental Component of Projects
Road Engineering - Basic Project Phase.
The Environmental Component of the Project at this Stage will be consolidated by the Basic Report.
de Avaliação Ambiental - RBAA, que se configura como o documento a subsidiar a
analysis and assessment of the environmental damage caused by the Project, having as
one of its main functions is to provide the licensing authority with the means to make decisions in terms of
to grant the Installation License - LI, of the Enterprise, whenever the
the bidding of the work is based on this Basic Engineering Project.
At the end of the work developed in this phase, the costs of the services will be estimated.
for pavement rehabilitation, adopting the methodology recommended in IS-220
Budget for the work - Basic Project phase and in the recommendations of the System
Road Costs of DNIT - SICRO.
With the approval of the conclusions and recommendations of the Basic Design Phase, it will be
the Executive Project phase has begun with the purpose of detailing the selected solution,
providing plants, drawings and service notes that allow for the construction of
highway.
EB-115 - Basic Scope for the Development of Executive Engineering Project for Highway Pavement Rehabilitation
Basic Guidelines for the Preparation of Road Studies and Projects 229
The Environmental Component of the Project in this Executive Project Phase consists of
detailing and budgeting of environmental protection measures, both corrective and
preventive measures, indicated in the Basic Project Phase, aiming for rehabilitation/recovery
of environmental liability and the execution of works in an environmentally correct manner.
The detailing activities must pay attention to the information or requirements of the
environmental agencies and other environmental studies prepared for the project.
It is noteworthy that for the interventions with the water sources intended for consumption
humans, protective devices must be designed in order to prevent or mitigate the
impacts resulting from possible incidents with the road transport of products
dangerous.
In this Executive Project Phase, the Environmental Component of the Project will be developed from
agreement with the provisions of IS-246 - Environmental Component of Projects
Road Engineering - Executive Design Phase.
The Environmental Component of the Project, at this Stage, will be consolidated by the Final Report.
of Environmental Assessment - RFAA that should contain the elements that characterize the
detailed description of the environmental protection measures established in the Project Phase
Basic.
In the case where the bidding for the work is based on this Executive Project of
Engineering, the Final Environmental Assessment Report - RAAF must provide
additional information that allows DNIT to request from the Environmental Agency
Licensor, the Installation License - LI, of the Enterprise.
The activities to be carried out in this phase should meet the provisions in
Service Instructions:
EB-115 - Basic Scope for the Preparation of Executive Engineering Project for Road Pavement Rehabilitation
Basic Guidelines for the Preparation of Road Studies and Projects 230
At the end of the Preliminary Phase, the Preliminary Project Report will be presented.
Executive summary, containing the conclusions of the studies developed and the recommendations
proposals, which will be composed of the volumes detailed below.
PRELIMINARY REPORT
At the end of the basic design phase, the Basic Project Report will be presented.
Executive, containing the proposed solutions, indicative tables of the characteristics
techniques and operational and quantitative services, composed of the following volumes:
EB-115 - Basic Scope for the Development of Engineering Executive Project for the Rehabilitation of Highway Pavement
Basic Guidelines for the Preparation of Road Studies and Projects 231
BASIC REPORT
Finalizing the preparation of the Executive Project, the Final Report will be presented.
Executive Project, initially in the form of a draft. After examination and approval by DNIT,
will be presented in the form of a final print. The Final Report will consist of
through the following volumes:
FINAL REPORT
FORMAT
VOLUME TITLE
Printing
Minute
Definitive
EB-115 - Basic Scope for the Development of Executive Engineering Project for the Rehabilitation of Road Pavement
Basic Guidelines for the Development of Road Studies and Projects 232
ANNEX A16
EB-116 - BASIC SCOPE FOR ELABORATION OF
ROAD REGISTRATION
1 DEFINITION
2 STAGES OF REGISTRATION
a) Preliminary Phase;
Final Phase.
The Preliminary Phase of road registration encompasses field services, which are
the following:
This survey will be carried out through the completion of registration forms.
with the indication of the following elements:
a) Road registration form indicating the characterization of the stretch of the highway,
["kilometer by kilometer","right-of-way","land use","resistance"]
lateral, cross sections, running surfaces, layout in profile and plan,
drainage conditions and degraded areas;
e) Registration form for environmental problems, inside and outside the domain range;
State currencies;
Degraded areas;
Regarding Flexible and Semi-Rigid Pavements, the data will be obtained from the
Database of the DNIT Pavement Management System and the built projects
existing, updated through consultations with the Federal Road Districts. They will be
the following complementary data has been raised:
d) Deflection;
The existing pavement being rigid pavement, the data will be obtained considering the
following methodologies
RIGID PAVEMENTS
Methodology Title
Evaluate the condition of the pavement surface allowing to conclude whether the segment presents the
running surface in satisfactory conditions, for any traffic situations,
according to the following methodologies:
Standards Title
RIGID PAVEMENTS
Methodology Title
Carry out continuous survey along the stretch, using measuring equipment
irregularity response type. The procedures for raising irregularities
they will follow the guidelines set out in the following methodologies:
Methodology Título
Methodology Title
DNER-ME 024 Pavement - Determination of deflections in the pavement by the Benkelman beam
Determination of deflections using a falling weight deflectometer
DNER-ME 273
weight deflectometer – FWD
The statistical analyses for data treatment should comply with the guidelines set forth in
procedures DNIT-ME-024 (Pavement - Determination of deflections in the pavement
by the Benkelman beam) and DNITPRO 011 (Structural evaluation of flexible pavements -
Procedure B).
Office work will include, in addition to the conferences and corrections of the files
of field, calculations and filing, the following activities:
4 PRESENTATION
ANNEX A17
EB-117 - BASIC SCOPE FOR ELABORATION
AS BUILT PROJECT
1 DEFINITION
It is the technical documentation developed with the aim of recording textually and
graphically represent what was effectively executed in the Enterprise. The
"Built" results from the physical and financial changes made to the original project.
a) Execution
Final
The 'As Built' must be developed based on the Project prepared for the
Enterprise and in the Partial Reports of Supervision/Inspection/Management,
containing the identification of the physical and financial changes made during the phase of
execution of works and services.
At this stage, they should be recorded in a specific chapter in the monthly/partial reports.
of supervision, the changes made to the original Project of the Enterprise.
Once the execution phase of the works and services is completed, the review of it must be finalized.
documentation related to the project, including in digital form, and extracting the data from the
monthly/partial supervision reports.
4 PROJECT PRESENTATION
The services executed related to the "As Built" must be reported in a chapter.
specific to the monthly/partial supervision report.
4.2. FINALPHASE
Upon completion of the final phase, the corresponding volumes must be presented to the
physical and financial changes made to the original project during the execution of the work
the service, which will constitute the 'As Built' Report.
The 'As Built' Report must be integrated into the Final Supervision Report.
ANNEX B -
SERVICE INSTRUCTIONS
Basic Guidelines for the Development of Road Studies and Projects 241
Basic Guidelines for the Development of Road Studies and Projects 242
ANNEX B1
IS-201 - SERVICE INSTRUCTION FOR STUDIES OF
TRAFFIC ON HIGHWAYS (RURAL AREA)
1 OBJECTIVE
2 STAGES OF STUDIES
a) Preliminary;
b) Definitive.
a) current: obtained from the National Traffic Counting Plan (PNCT) and Plans
Directors and other available sources.
Preliminary traffic allocation through the estimation of normal highway traffic (if
of existing roadways), plus the diverted and generated traffic, estimated
preliminarily.
3.2. FINALPHASE
The Traffic Study in the Definitive Phase will be developed based on the conclusions of the Phase
Preliminary, upon prior approval, will include the following activities
discriminated.
m) evaluation of results;
The direct influence area of the highway, encompassing the municipalities it cuts through and
those who depend on it for their access, divided into internal traffic zones. For
utilization of existing socioeconomic data, these areas will correspond
normally to the municipal boundaries, although it becomes necessary to subdivide the municipalities
for more than one traffic generation center.
The major economic centers, far from the region of direct influence, should be
represented by external traffic zones.
a) collection of existing data on the area of interest for the project, including maps,
plans, studies and traffic data, as well as any indicators of variations
seasonal traffic.
This phase encompasses the collection of socio-economic data, traffic generating poles,
distinct modal systems, among others. It involves the execution of the following services:
a) collection and compilation of any other data deemed valuable for execution
appropriate studies (climate, soil, population, production and
agricultural and industrial productivity and socio-economic parameters
necessary for traffic projections;
b) verification of the existence of traffic generation poles in the region that can
influence the traffic patterns of the highway;
This stage will determine the ability to generate trips for each traffic zone, in
function of the investment planned in the road system. To this end, some aspects must be
to be considered, such as the physical and operational characteristics of the network, data
socio-economic factors of the population in the region, daily variations, and seasonal factors.
The result of this stage will cover the number of trips attracted and generated from
of each area.
At least one of the various existing softwares will be used in order to obtain
precision and reliability in the results.
This stage involves the determination of the trip distribution matrix in the network.
traffic-related, that is, in the relationship between the various pairs of areas in terms of quantity
of travel. There are several methods, and the choice of the most appropriate one will depend on the
objectives and the precision of the study. Some more complex ones take into account the
impedance (costs) of the network during the trip distribution process. The most
known and used is the gravitational model, which needs to be well calibrated, so that
the best way to characterize travel patterns for the base year.
At least one of the various existing software must be used in order to obtain
precision and reliability in the results.
The work in this phase will consist of the development and study of technical alternatives.
for the planned road investments, alternatives that encompass both variations
In the layout, as the physical and operational characteristics of the highway and should
consider the traffic plans and studies, already prepared or in preparation, existing in
analysis horizon.
For that, some aspects that influence modal choice should be considered,
such as travel characteristics (purpose, costs, time/day, seasonal variations in
travel production, among others), characteristics of the various transportation systems,
such as regularity, comfort, safety, travel costs, duration of
trips, among others, and also characteristics of users or goods
transported, such as resident/vehicle ratio, type of trips produced, among
others.
At least one of the various existing software should be used in order to obtain
precision and reliability in the results.
This stage will consist of traffic allocation on the road network, considering the routes.
existing alternatives on the network.
The balance point between demand and supply should be sought, that is, the number of
travels in the various links must be suited to their respective drainage capacity.
considering aspects of fluency (travel time, travel costs, among
others) and safety (the worse the operating conditions, the greater the likelihood of
occurrence of accidents). Costs for users should also be considered,
such as travel times, fuel consumption, toll booths, among others.
This stage should show the deficiencies of the transportation system and/or its
needs based on demand.
At least one of the various existing software should be used in order to obtain
precision and reliability in the results.
Once the quantities of trips on the various links are known, one must then obtain
the corresponding vehicle flows, as well as the composition of the fleet in each one
of them. For this, it is important to know the average occupancy rates, or average tonnage
transported, for the various types of vehicles that make up the fleet on the roads under study.
It may be necessary to determine, for each of the various traffic zones, rates
differentiated by type of vehicle, leading to differentiated growth among the links that
compose the network under study.
Poderá também, ser necessário analisar cenários distintos, com o intuito de prever o
behavior of growth rates during the study period.
In the absence of weighing data from DNIT scales, for the definition of
factors of vehicles in the commercial fleet will be carried out through field surveys with
trucks, researching the loads per axle, over 2 consecutive days. Based on the
research or weighing, the weights by axle/set of axles will be determined
various types of vehicles that make up the fleet of users of the stretch. The surveys
of the field, necessary for the determination of the vehicle factors applicable to the highway
In study, they may be waived if they are available at DNIT.
At this stage, with the help of the available software on the market, must be
dimensioned as the system facilities, such as number of lanes and tracks, characteristics
physical and operational, that is, to size the interventions, with a view to the implementation of
improvements or the construction of the highway.
Using simulation techniques compatible with the complexity of the networks under analysis,
and considering the flow capacity of the roadway systems under study, collect
data for the base year and the projections of interzonal movements for the horizon of
project, allocating (manually or electronically) to the networks that incorporate the alternatives
under analysis.
There will be, therefore, an approximate vision of the future development of networks, of
need for modifications and the role of the proposed investments, in the long term.
The results of the loadings from the different networks will be analyzed and compared.
based on the volume/capacity relationships (considering the traffic composition and the
hourly, daily, and annual variations, in traffic flowcharts, in average speeds
of route, in the service levels for road networks and in transport costs,
however with a level of detail suitable for this stage.
a) the type and the standard of the road work (Class I, II, III, IV);
b) the number of lanes required for the road (including weaving lane, ramps and
need for ascending third lanes);
c) the determination of the number of standard axis operations, number N;
4 PRESENTATION
The presentation of the Traffic Study in its Preliminary Phase will be made through
of the Preliminary Report of the Engineering Project to which it corresponds.
This Report should include the Descriptive Memory of the activities carried out in this phase,
as follows:
PRELIMINARY REPORT
4.2. FINALSTAGE
In the Definitive Phase, the presentation of the Traffic Study will be made through the Report.
Basic of the Engineering Project to which it corresponds. Must be included.
ANNEX B2
IS-202 - SERVICE INSTRUCTION FOR GEOLOGICAL STUDIES
1 OBJECTIVE
The purpose of this service instruction is to define and specify the services
constants of Geological Studies in Road Engineering Projects, Project
Basic and Executive Project.
b) Final phase.
3 EXECUTION OF STUDIES
c) Field investigation.
Interpretative analysis of aerial photographs of the region, aiming to separate the units.
geotechnical interest mapable features, as well as detect the features (faults, joints,
contacts, schistosity, stratifications) that may interfere with the establishment of
geometric and geotechnical conditions of the guidelines; delimitation of locations with
probability of occurrence of construction materials, talus zones, scars of
ancient landslide movements; areas of compressible soils; mountain areas;
escarpas, cuestas, cristas, e quaisquer outras de interesse para o estudo.
These are supplementary field investigations aimed at consolidating the interpretation of the
aerial photographs and allow the execution of the drilling plan.
This phase will determine the spatial configuration of the occurring formations, their aspects
structural, textural and mineralogical, the modifications introduced by phenomena
secondary (tectonics, weathering, erosion, metamorphism, etc.) aimed at evaluation
of its geotechnical behavior and its workability as a construction material.
Special interest should be given to the results of the geology-climate interaction, that is,
geomorphology, vegetation, soils, hydrology, hydromorphism. At the same time, all the
areas marked as capable of providing usable materials, zones of
occurrences of compressible soils, and potentially unstable areas should be
visited and examined in order to estimate the characteristics and inherent problems.
The area to be researched should cover the entire region where the alternatives were inserted,
giving greater or lesser lateral extension to materials suitable for construction.
The Geological Study in the Definitive Phase will develop from the conclusions and
recommendations of the study in the previous phase, subject to prior approval by the body,
as detailed below.
The reconnaissance drilling plan will cover an area that allows for between the
alternatives, the choice of the best line considering the geological aspect. The drilling
they will be mechanical and/or geophysical, according to the desired purpose. The
The establishment of this plan will be based on preliminary maps and other information.
available geological data, and will seek solutions to major geological problems
geotechnical, such as:
a) talus zones;
how to collect samples that allow evaluating the physical and mechanical characteristics of
occurring soils and the consistent material overlapping beyond the position of the groundwater table.
The preliminary geological maps of the chosen alternatives will undergo a process in this phase.
systematic detailing through new careful observations (measures of
attitudes, schistosity, jointing, more precise location of contacts) and of the
results of the surveys planned in the survey plan. They should be mapped.
with convenient symbolism, the geological contacts, the tectonic lines, the attitudes of
layers, in addition to the soil compartmentalization of the road.
The rock outcrops and the groundwater table will also be recorded and mapped.
with indications of possible orientations. The occurrences of talus, colluvium, half-
steep slopes and gorges should have their extensions mapped with the
possible accuracy, while providing indications about their thicknesses,
natures, spatial orientation, depth of rocky substrate, within accuracy
achieved by the surveys conducted.
Compressible soil zones, in addition to being demarcated, will also be affected through symbolism.
indication of their thicknesses and characteristics provided by the surveys carried out.
Based still on the photointerpretative studies and mappings carried out, a will be made the
final cartography of occurrences considered interesting for use.
a) Geographical situation;
b) Climate;
c) Soils and vegetation;
e) Geological aspects:
stratigraphic;
tectonic
- lithological;
f) Hydrogeological aspects
3.2.4. RECOMMENDATIONS
The Geological Study should conclude with the conclusions and recommendations resulting from the
work completed.
4 PRESENTATION
The presentation of the Geological Study, at the end of this phase, will be done through the Report.
Preliminary Engineering Project to which it corresponds, and must contain:
PRELIMINARY REPORT
Report/
Memory − Report containing the conclusions of this Phase;
1 A4
Descriptive − Recommendations for the continuation of the Study
Preliminary
The presentation of the Geological Study, at the end of the Definitive Phase, will be made through the
Basic Report of the Engineering Project to which it corresponds, containing:
BASIC REPORT
APPENDIX B3
IS-203 - SERVICE INSTRUCTION FOR HYDROLOGICAL STUDIES
1 OBJECTIVE
Define and specify the services included in the Hydrological Studies in Projects of
Road Engineering, Basic Project and Executive Project.
a) Preliminary Phase;
b) Definitive Phase.
3 EXECUTION OF STUDIES
The Hydrological Studies in the Preliminary Phase have the following objectives:
It should cover:
– collection of rainfall data from the stations located in the area and presented in
map indicating the entity responsible for collection and the respective
observation periods;
b) stream gauging
collecting elements for the preparation of flow charts of average water heights,
monthly maximums and minimums of the main rivers in the region;
– flow diagrams of maximum, average, and minimum monthly heights and/or others
necessary;
In the Definitive Phase, the studies conducted in the previous phase will be consolidated, involving
the following activities:
d) histograms with the monthly distributions of the minimum number of rainy days,
averages and maximums.
a) table containing the extreme values of daily average flow rates (m/s),
3
in case of
availability of millimeter scales in the watercourses in a location near the construction site
from art to be designed.
b) table containing the quotas of the maximum full observed in the region, in case of none
to have millimeter rulers available.
a) Recurrence period
The recurrence periods will be fixed by the types of works classified below:
Sewers;
Bridges;
Bridges.
Surface drainage 5 to 10
Subsurface drainage 1
Sewer 10, 25, and 50 (like an orifice)
Footbridge 50
Bridge 100
b) Concentration time
The concentration time of the basins should be evaluated using methodology and models.
usual, and that present compatible results and that consider:
– Basin area;
Vegetation cover;
Land use;
Others.
c) Deflation coefficient
The deflator coefficients should be set only after analyzing the use of
areas of rise, particularly in cases of violent modification of
permeability of the basins.
The methodology to be followed in the determination of the discharges of the basins will depend on:
a) from the availability of river flow data and the number of years of observation;
b) on the size of the basin and the importance of understanding the shape of the hydrogram;
When there is no riverflow data available, the following methods are recommended:
Without rainfall data, basin area < 10 km2 Rational and corrected rational
Without rainfall data, basin area > 10 km2 Hydrogram or similar
With hydrometric data from 10 to 15 years Statisticians
constant of the Manual of Basic Hydrology for Drainage Structures, from DNER,
now in the review process at the IPR.
4 PRESENTATION
The presentation of the Hydrological Study, at the end of this phase, will be made through the
Preliminary Report of the Engineering Project to which it corresponds, containing:
PRELIMINARY REPORT
The presentation of the Definitive Phase of the Hydrological Study will be made through the Report
Basic Project of the Engineering corresponding to it, containing:
BASIC REPORT
ANNEX B4
IS-204 - SERVICE INSTRUCTION FOR TOPOGRAPHICAL STUDIES FOR
BASIC ENGINEERING PROJECTS
1 OBJECTIVE
IS-226 Aerial Photography Coverage for Road Engineering Projects - Single Phase
The topographic survey by conventional process will have the sequence indicated to
to follow
IS-204 - Service Instruction for Topographic Studies for Basic Engineering Project
Basic Guidelines for the Preparation of Road Studies and Projects 260
The execution of this network will be carried out as recommended by Service Instruction IS-227:
Aerophotogrammetric Restitution and Field Support for Engineering Projects
Bus Station - Single Phase:
These lines will be tied to the basic topographic network and obtained using
theodolites and steel tapes.
The allowed tolerance for angular error of the exploration line will be established by the
expression:
e = 10 N
In which:
e = tolerance, in minutes;
N = number of vertices.
The axis will be marked every 20 meters and at all notable points such as: PI,
topographical accidents, intersections with roads, riverbanks and streams. In all
The installed stakes will have witness stakes made of wood.
of good quality, about 60 cm in length, provided with a notched inscription to
oil, from top to bottom, the corresponding number.
All the stakes corresponding to the PIs, as well as the stakes every 2 km of the
long tangents will be tied by "safety points", located more than 20 m away
of the highway axis.
The tying process will normally consist of eight milestones. They will be
organized notebooks of bindings and recorded the elements of the points
tied up.
The distance measurements will be made with a steel tape, according to the horizontal for the purpose of
location of the exploration line stakes, however, it is recommended to use
statistical process for reading the distances between PI, in order to verify the
measures taken.
IS-204 - Service Instruction for Topographic Studies for Basic Engineering Project
Basic Guidelines for the Preparation of Highway Studies and Projects 261
The leveling and counter-leveling of all the stakes of the exploration lines will be
made with the use of precision levels. The control of leveling and
the counter level will be by tying this leveling with the basic line of RRNN.
The tolerance in leveling services will be 2 cm/km and the accumulated difference
the maximum will be less than or equal to that obtained by the formula:
e = 12.5 n
In what:
n = kilometers;
e = millimeters
Along with leveling the axis, all notable points will be leveled and counter-leveled.
the crossings of existing watercourses, when noted, in the notebook of
leveling, the water mirror elevation, leveling date and maximum flood elevation.
The survey of cross sections will be done at the exploration line stakes.
by one of the following methods:
a) statimetry;
ruler;
The spacing between sections will vary according to the region, but ensuring
always your characterization. The maximum spacing allowed between two sections
successive will be 100 m and the length will be the necessary to define the project.
The notebooks of cross sections will mention: houses, quarries, bottom of ravines,
riverbanks, dividing fences and other accidents affected by the sections.
A registration of geographical accidents and other notable points will be made due to its
importance will influence the project, such as: existing highways, transmission line,
water networks, industries, houses, and others.
IS-204 - Service Instruction for Topographic Studies for Basic Engineering Project
Basic Guidelines for the Preparation of Road Studies and Projects 262
Total stations can be used for the optimization of work, in light of the
possibility of dispensing with field notebooks, storing a large amount of
data and eliminate annotation errors, very common in surveying services of
field.
These devices combine, in a single unit, the measurement of angles and distances.
presenting advantages over traditional equipment regarding collection,
storage, processing, import, and export of data collected in the field.
They have an active sensor, as it receives data from a beam of radiation in the range of
infrared, generated by itself, which reaches prisms placed over the target object,
returning by reflection and exciting the sensors of the same generating source.
The calibration of electronic distance measuring devices must be carried out, both for
theodolites and levels, as for Total Stations using the ABNT Standard
13.133.
4 PRESENTATION
The presentation of the Topographic Studies will be through the Basic Project Report.
of Engineering to which it corresponds, comprising the following volumes:
IS-204 - Service Instruction for Topographic Studies for Basic Engineering Project
Basic Guidelines for the Preparation of Road Studies and Projects 263
BASIC REPORT
IS-204 - Service Instruction for Topographic Studies for Basic Engineering Project
Basic Guidelines for the Preparation of Road Studies and Projects 264
ANNEX B5
IS-205 - SERVICE INSTRUCTION FOR TOPOGRAPHIC STUDIES FOR
EXECUTIVE ENGINEERING PROJECTS
1 OBJECTIVE
2 STUDY PHASE
The execution of these studies at this stage will be carried out by conventional process of
topography, and it will refer to the basic topographic network established in the Basic Project phase:
c) Cross sections;
watercourses, etc.
g) Topographic registration of the right-of-way.
The various services included in the Topographic Studies will be carried out according to the
following specifications:
IS-205 - Service Instruction for Topographic Studies for Engineering Executive Project
Basic Guidelines for the Development of Road Studies and Projects 265
The location of the axis will be based on the implantation of its notable points (PI, PC, PT,
TS, SC, CS and ST, topographical accidents, intersections with other highways, margins of
rivers, long tangents, etc.), and direct polar coordinates of the vertices of the polygon
secondary (PS) of the basic topographic network.
Once the notable points of the project's geometric axis are materialized, the placement will be
made using theodolites and linear measurements through steel tape.
The implementation of the axis will consist of two distinct phases:
The axis will be marked every 20 meters. At all installed markers, there will be
witness stakes installed, made of good quality wood, with about
60 cm in length, provided with a notch and inscribed in oil, from top to bottom, the
corresponding number, always located to the left of the staking, in the direction
increasing in number and with the number facing the stake.
Curves with a radius smaller than 600 m will be marked every 10 m. All the
corresponding stakes for PI, PC, PT, TS, and ST, as well as the stakes every 2 km
the long tangents will be secured by "safety points", located more than 20
I am in the axis of the highway.
Distance measurements will be made with a steel tape, according to the horizontal for the purpose of
location of the stakes of the rental line, however, it is recommended to use a
statistical process for reading the distances between PPII, in order to verify the measurements
made.
The curves will be materialized in the field, using a theodolite and the process to be
the employee will be the one from the deflections on the tangents.
The implementation of the reference network at the level must follow the following guidelines:
a) A network of RRNN will be implemented, tied to the RN network of the IBGE that will serve as
support for leveling and counter-leveling of the located axis;
IS-205 - Service Instruction for Topographic Studies for Executive Engineering Project
Basic Guidelines for the Development of Road Studies and Projects 266
The leveling error tolerance will be 2 cm/km and the maximum accumulated difference
will be less than or equal to that obtained by the formula:
e = 12.5 n
Where:
n = km;
e = mm.
Along with leveling the axis, the notable points will also be leveled and counter-leveled.
the crossings of existing watercourses, when they will be noted, in the notebook of
leveling, the water mirror elevation, on the date of leveling, and the maximum elevation
flooding. Likewise, the bottom of the waterways will be leveled in order to allow for the
drawing of the longitudinal profile of the crossing, for use in the design of the artworks.
Cross sections will be taken in all the paddocks along the located axis, with the
employment level and, in justified cases, the ruler.
The following points of the platform will be leveled at a minimum: axis, edges, start, and end.
shoulders, steps between the pavement and the shoulders, bottom of the ditches,
wheel tracks, cut and fill crests, base of cuts and fills.
The sections will be raised asymmetrically, in relation to the axis and in such a way as to
cover the limits of the future domain strip. At points where there is a need for
special studies, the sections will be extended to a considered sufficient extent
for these studies. Whenever necessary, the spacing of the cross sections
will be reduced to 10 meters.
IS-205 - Service Instruction for Topographic Studies for Executive Engineering Project
Basic Guidelines for the Preparation of Highway Studies and Projects 267
In the tangents, the sections will be raised in the direction perpendicular to the located axis and in the
curves in the direction of the bisector of the angle formed by the anterior and posterior sections
section that is being raised.
The determination of the direction of each section provides for the use of a cross brace or prism of
refraction. A bubble level will be used to check the position of the horizontal ruler.
The notebooks of cross sections will mention: houses, quarries, bottom of ravines,
riverbanks, dividing fences, and other accidents affected by the sections.
Total Stations can be used for the optimization of the work, in light of the
possibility of dispensing with field notebooks, storing large amounts of
data and eliminate annotation errors, which are very common in surveying services
field.
These devices combine, in a single unit, the measurement of angles and distances.
presenting advantages over traditional equipment regarding collection,
storage, processing, import and export of data collected in the field.
They have an active sensor, as they receive and record data from a beam of
radiations in the infrared range, generated by itself, that reach placed prisms
about the target object, returning by reflection and exciting the sensors of the same source
generator.
The calibration of electronic distance measuring devices will be carried out, both for theodolites and
levels, as for Total Stations, through the use of the ABNT Standard 13.133.
In the case of using GPS tracking for the determination of coordinates and
Leveling, geodetic precision receivers, either single or dual, shall be used.
frequency, with tracking in static differential mode with tracking time of, in
minimum, 30 minutes or 'fast-static' with a tracking time of at least 10 minutes.
IS-205 - Service Instruction for Topographic Studies for Executive Engineering Project
Basic Guidelines for the Preparation of Road Studies and Projects 268
All access points and intersections will be raised with a view to the preparation of
Project of Intersections, Returns and Accesses, according to the provisions of the Instruction of
ServiceIS-213 - Executive Project Phase.
Conduct review studies of the contribution basin areas with the help of
aerial photographs and field topographic surveys.
All current works of art existing in the section will be registered, informing the
bed leveling, NA, thresholds, coping walls, slope crests, longitudinal section
of those indicated, as well as, noted: position, type, dimension, operational study and
conservation.
Likewise, the special works of art will be lifted through an expedited process.
transpostas pelo eixo locado e anotados os dados principais, tais como: comprimento,
width, longitudinal and transverse section sketch, state of conservation, system
estrutural, etc. Ainda, será feito levantamento batimétrico de 5 m em 5 m, do eixo das
artworks and raised the profile of the riverbed over a 100 m stretch on each side
of the axis.
The new special artworks will have the sites topographically surveyed and
bathymetrically, in the same manner as previously recommended. Raise the sections
longitudinal valleys, with the purpose of designing the ditches.
Simultaneously with the lease or shortly thereafter, proceed with the survey
cadastral of all areas cut or affected by the right of way, determined
by the project axis. To note in dedicated notebooks the names of the owners,
construções existentes e natureza das benfeitorias abrangidas pela faixa. Oportunidade
information will be collected from the residents of the affected properties and the
legal situation of the property title.
IS-205 - Service Instruction for Topographic Studies for Engineering Executive Project
Basic Guidelines for the Preparation of Highway Studies and Projects 269
The topographic survey of the occurrences will be assisted by auxiliary polygons and will be
raised sections, to enable the drawing with contour lines spaced 5 m apart.
All occurrences will be tied to the project's location axis and organized.
specific notebooks for the survey, with a binding sketch of these
occurrences.
c) cross-sectional surveys;
In special cases where the situation demands greater detail for the projects of
environmental rehabilitation will carry out conventional planialtimetric surveys of the
degraded area, related to the project staking.
4 PRESENTATION
The presentation of the Topographic Studies will be made through the Final Report of the Project
of Engineering, to which it corresponds, encompassing the following volumes:
IS-205 - Service Instruction for Topographic Studies for Executive Engineering Project
Diretrizes Básicas para Elaboração de Estudos e Projetos Rodoviários 270
FINAL REPORT
Report of
1 Text - Summary of Studies - Graphs and Tables A4
Project
Memory
3 Descriptive and justificative report of the studies conducted A4
Justification
IS-205 - Service Instruction for Topographic Studies for Engineering Executive Project
Basic Guidelines for the Preparation of Road Studies and Projects 271
ANNEX B6
IS-206 - SERVICE INSTRUCTION FOR GEOTECHNICAL STUDIES
1 OBJECTIVE
2 STAGES OF STUDIES
The Geotechnical Studies in the Basic Design Phase will consist of:
a) Study of subgrade;
Along the axis of the selected layout, and based on its Geometric Project (Basic),
surveys will be conducted on the roadbed, at the highest points of the cuts,
located at intervals of approximately 1000 m, reaching compatible depth
with the possible grade quota on site. The samples collected at each hole, in the various
Material horizons will be subjected to characterization, compaction, and ISC testing.
In the event that it is impossible to collect samples at the highest points of the cuts,
surveys will be conducted near the PP, until reaching the depth of the level of
grade, submitting the collected samples to characterization, compaction, and tests.
ISC.
At least one probing will be conducted in the central sections of the gorges.
selected lines, with the aim of defining the depth of the rock, thickness of
soil layer, classification of materials, following the same procedure in the
steep slopes, colluvial areas and talus.
The surveys in the cuts for NA verification will consist of at least 3 holes, one in
each point of passage (PP) and the other in the middle of the cut, all to the depth of
1.50 m below the level of the subgrade.
In this Basic Project Phase, the preliminary study of occurrences will include:
c) Laboratory tests.
Five to ten drilling holes on the outskirts and in the central part of the designated area.
conveniently located to the necessary or compatible depth with the
extraction methods adopted; In each drilling hole and for each layer, it will be
a sufficient sample has been collected for the characterization tests,
compression and ISC.
Os outros materiais próprios para uso, serão identificados pela denominação corrente no
place, such as: clay, gravel, pebbles, and others;
A sketch of the arrangement of the drilling holes will be made, noting the distances.
approximately between them and the occurrence position, in relation to the highway in
study
In the case of rock occurrences, the preliminary inspection and sampling must follow the
recommended in the DNER-PRO 257/99 Standard: Studies and Sampling of Rocks in
Stones for Road Purposes.
IS-206 - Service Instruction for Geotechnical Studies
Basic Guidelines for the Preparation of Road Studies and Projects 273
In the case of lateritic materials, tests will be carried out to determine the relationship.
silica-sesquioxides.
The Geotechnical Study in the Executive Project Phase will consist of the activities detailed
next.
With the material collected from the surveys, the following tests will be carried out:
a) Characterization;
b) Compression;
c) ISC;
The characterization tests will be conducted on all drilling holes and the others.
in alternating holes.
The surveys of the subsoil should be included in the profile of the located axis.
The choice in the field of loan areas will be made based on the indications of the
earthmoving project.
In areas where lateral loans are anticipated, the test holes will be
located, in principle, on the axis of loans, being the longitudinal distance between the
drilling holes of 100 m and the depth equal to that planned for the loan.
Where concentrated loans are anticipated, at least five holes will be made,
distributed throughout the loan area, with a depth equal to that planned for the
loan. For loan boxes larger than 10,000 m, a mesh will be made 2
with a mesh of 50 m on each side, with a maximum spacing of 70 m between the holes.
Samples will be collected from all the holes at different horizons and submitted to the
following essays:
b) Physical indices;
c) Compression;
In the lateral borrow pits, the compaction tests and ISC will be performed every 200 m.
200 m.
Throughout the entire duration of the project, tests will be conducted for the determination of the
apparent specific mass 'in situ' in order to obtain elements to define the factor of
fill/cut contraction.
In the study of the occurrence of materials for paving, the following are distinguished:
− Quarries, sand pits, gravel pits, clay pits, and deposits of earth materials.
In occurrences of gravel pits, sand pits, sandbanks, and other granular materials, judged
exploitable in the preliminary design phase, definitive studies will be carried out that will consist of
de:
b) Laboratory tests;
The surveys will be conducted through the launching of a grid with a mesh of
30 m on each side, within the limits of the selected occurrence, at whose numbered vertices
the exploratory drilling will be done.
In the occurrences of earthen materials, at each hole in the 30 m grid, for each
A layer of material will undergo a simple sieving granulometry test.
of liquidity limit, plasticity limit and sand equivalent, and in holes
alternates, compaction tests, ISC and in situ density.
In the case of layers thicker than 1.00 m, the following will be carried out
aforementioned tests, for each meter of depth of this layer.
The minimum number of samples to be researched in an occurrence will be nine, after the
rejection of spurious values, with deviations far above the standard deviation.
In the case of river sands, the sampling surveys will be taken from the
places of occurrence exploration;
In the occurrences of stone materials (quarries), the following tests will be conducted:
b) Adhesion;
c) Durability;
In the study of stone materials, follow what is recommended by the ABNT-NBR 06490 standard.
for recognition and sampling for the purpose of characterizing occurrences of
rocks.
a) Granulometry;
In the case of lateritic materials, tests will be carried out to determine the relationship
silica-sesquioxides.
Whenever there is doubt about the bearing capacity of the foundation soils of
there will be a need to develop a special geotechnical study that defines the
natural ground support capacity.
e) Granulometry;
f) Liquidity limit;
g) Plasticity limit;
i) Densification;
Rapid triaxial.
When justified, simple compressive strength tests and quick triaxial tests.
they can be replaced by vane shear tests.
Technical and economic comparisons should be made for the various solutions of
fills over compressible soils, including comparing the fill solutions with
concrete structures.
The surveys for the foundations of the special artworks will be carried out according to
following methodology:
b) preliminary surveys, in order to define the structural type to be adopted in the work;
c) definitive surveys.
The preliminary and final surveys will be conducted in accordance with what is prescribed by the
Basic Implementation Manual, DNER/IPR - 1996.
The section in the project, considering the stability of slopes, should be divided into
homogeneous subsegments and in each one of them should be investigated, by sampling, the
behavior of slopes of cuts over 5 m high. The same care should be taken
to be applied in the studies of loan locations and pawnbrokers.
4 PRESENTATION
The presentation of the geotechnical studies at this stage of the basic project will be made through
of the Basic Engineering Project report to which it corresponds, and must contain:
BASIC REPORT
In the Executive Design Phase, the Geotechnical Studies will be presented in the Report.
Final of the Engineering Project to which it corresponds, encompassing the following
volumes:
FINAL REPORT
FORMAT
VOLUME TITLE
Printing
Minutes
Definitive
Project Report
− Text containing the conception of the study and summary of
obtained results;
− Spreadsheets and graphs with statistical analyses of
1 A4 A4
surveys and experiments conducted
− Results of soil mixture tests
− Results of potential mixture dosages
asphalt and cement concrete
Execution Project
− Cross section of the pavement
− Sketch indicating the characteristics and location
the occurrences of materials
2 A3 A3
− Diagram with the representation of layers and types
of materials indicated for the pavement layers
− Representation in the profile of the geometric project of the
geological-geotechnical characteristics of the materials
excavate (in the case of road construction).
Justifying Memorandum
3 − Justification of the detailing of the alternatives A4 A4
approved preliminary project
Geotechnical Studies
− Surface evaluation data of the pavement
existing
− Data from the pavement deflectometric survey
existing
− Data from the longitudinal irregularity survey
of the existing pavement
3A A4 A4
− Summary sheet of all the performed trials
− Reports of the final surveys at the locations of
landfill foundations
− Final survey bulletins at the locations of
special works of art
− Reports from the preliminary surveys in the locations of
possible slope stability studies
ANNEX B7
IS-207 - SERVICE INSTRUCTION FOR PRELIMINARY STUDIES OF
ENGINEERING FOR HIGHWAYS (ALIGNMENT STUDIES)
1 Objective
Define and specify the services included in the Preliminary Engineering Studies in
Feasibility Studies, and in Road Engineering Projects, Basic Design and
Executive Project.
2 STAGES OF STUDIES
a) Preliminary;
b) Definitive.
The Preliminary Phase corresponds to the collection, compilation, and analysis of data and elements.
available, as well as the identification and study of routing alternatives, and of
operational schemes and a brief preliminary estimate of the implementation costs.
The Definitive Phase encompasses the analysis and evaluation of alternatives and the definition of their
geometric conceptions.
3 ELABORATION OF STUDIES
c) Define certain basic solutions for the smooth preparation of the work more
detailed in subsequent studies;
d) Estimate the approximate costs of construction and expropriation for the purposes of
economic and financial evaluation.
IS-207 - Service Instruction for Preliminary Engineering Studies for Highways (route studies)
Basic Guidelines for the Preparation of Road Studies and Projects 280
This phase of the work aims to provide all the elements and data related to the area in
studies, necessary or valuable for the proper development of the subsequent stages
of the studies.
The data and documents to be collected and compiled in this phase will include, but
will not be limited to the following:
Cadastral maps;
Geographic maps.
Geological maps;
– Elements related to the hydrology of the basins contained in the study area and in
adjacent areas, including millimeter records, flood experience,
land cover characteristics of the basins, etc;
Other data that prove to be of interest for the project in particular, among which
one can mention: structural sufficiency and the condition of conservation of structures, bridges and
overpasses, whose requests may be subject to modification due to
implementation of the project.
IS-207 - Service Instruction for Preliminary Engineering Studies for Highways (alignment studies)
Basic Guidelines for the Preparation of Road Studies and Projects 281
The execution of this phase will comply with the minimum requirements listed in the subsections.
to continue, however, it is necessary to extend or broaden these works when deemed appropriate
necessary or convenient, in order to better meet the objectives of these studies.
Additionally, any additional study contemplated must be developed to a degree
of precision compatible with the preliminary nature of the study, as a whole, without details
inadequate or improper deepening, except when specifically authorized
by the DNIT.
Having identified the above conditions, precisely define the routing alternatives.
viable, of the possible operational schemes or even of the pattern of improvements of
existing roads, simultaneously establishing the needs for artworks
correntes e especiais, com dados básicos de situação, limites e dimensões de pontes e
viaducts, retaining walls, major drainage works, and others of interest.
This task includes, but is not limited to, establishing, based on traffic studies and
two functional plans, the standard and the main basic project characteristics of
the highway and the secondary connections, such as:
b) Width of the roadway, shoulder, and medians; degree of access and its shape
control; maximum super-elevation;
d) Project vehicles;
IS-207 - Service Instruction for Preliminary Engineering Studies for Highways (alignment studies)
Basic Guidelines for Preparing Road Studies and Projects 282
When the Route Study refers to a roadway section that has already been implemented (existing),
preliminary functional plans must be prepared for each of the guidelines
alternatives under consideration regarding the cards or photomosaics available. As far as
if possible, the functional plan should cover the collector-distributor road system and
still the access corridors that will feed the new connection.
These functional plans encompass at this stage the preliminary general design of
functioning of the existing highway and integration with the rest of the road system, as well
such as intersections, branches, artworks (viaducts, bridges, and walkways),
number of lanes, traffic volume projections and other basic information
related to the functioning of the circulation plan.
The solutions of the intersections and interconnections will still be defined conceptually,
inclusive layout; needs and types of traffic channeling; treatment of
entries and exits of branches; guideline speeds for branches, number of lanes of the
ramos; treatment of specific problems; measures for transportation service
collective.
In the preparation of the Functional Plans, the provisions of the Instruction must be observed.
Service IS-231: Preparation of Functional Plan Studies Aimed at Improvement
Capacity and Safety of Highways in Duplication Projects
IS-207 - Service Instruction for Preliminary Engineering Studies for Highways (alignment studies)
Basic Guidelines for the Preparation of Road Studies and Projects 283
After the identification of the alternative routes, following the completion of the work phase
previously, the selection of the routing option that best meets the objectives will be carried out
of the project.
b) Earthworks
This study should carefully consider the alternatives that are presented.
regarding the movement of earthworks, in order to adjust, between
others, the needs for loans and giveaways and the availability of areas
for that, also taking into account the existing urbanization and landscaping plans or
planned, mutual compatibility. It is also necessary to consider the convenience and
possibilidade de deslocamentos longitudinais extensos de volumes de terra para fins
of compensation.
IS-207 - Service Instruction for Preliminary Engineering Studies for Highways (alignment studies)
Basic Guidelines for the Preparation of Road Studies and Projects 284
Finally, based on the studies carried out, prepare a concise guidance framework.
from earthworks, defining the influence on the aspects of disposal and borrowing,
as well as costs. The table should present a summary of the cutting volumes, by
category, and the volumes of fill to compact.
Based on the data obtained and compiled in the previous phase and with the aim of
to obtain as a conclusion of the studies in this discipline, the establishment and definition of
design of the main drainage system, including the configuration and
function of gutters, ditches, transverse and longitudinal drains, bridges and others
devices for capturing and draining rainwater, execute the following
tarefas:
• Rain gauges;
• Indicate, where appropriate, the posts that characterize the region, the
measuring instruments and the observation period.
• Discharge flow;
IS-207 - Service Instruction for Preliminary Engineering Studies for Highways (alignment studies)
Basic Guidelines for the Development of Road Studies and Projects 285
– Analysis of available flow data and calculation of the other elements not
necessary for the project of larger bridges and culverts,
understanding: preparation of flow charts of average and maximum water levels
and monthly minimums and the flow diagrams corresponding to the project flows,
as above determined, and hydraulic characteristics of the watercourses of
larger vehicles crossing or accompanied by the road layout; data verification
obtained based on local flood experience.
Special artwork
It is necessary to proceed with the preliminary definition of the needs for structures, such as:
bridges, viaducts, walkways, large retaining walls, based on the data
geotechnical, hydrological, and geometric data available at this stage. They will be established
still conceptions and basic options for structures and their foundations, as well as
preliminary options between landfill and structure, retaining wall and expropriation, for the
obtaining basic data to define the evaluation costs of the main
alternatives.
e) Domain range
An estimate of the cost of expropriation of the domain strip must be made for
each alternative under analysis. This will be based on a survey of prices of
market for various types of land and constructions within the range
considered, analysis of the market values and field survey of the properties
reached, however, without entering them, nor interrupting or bothering the residents
occupants of the same. It is very important, due to the weight of this item, that the
criteria used to evaluate the costs of the different alternatives are the most
similar and coherent possible.
IS-207 - Service Instruction for Preliminary Engineering Studies for Highways (alignment studies)
Basic Guidelines for the Preparation of Road Studies and Projects 286
f) Paving
Based on the results of the geology and geotechnical studies described above, well
As for the drainage needs and traffic requests, the procedure will be
definition of the type of pavement to be adopted on the various roads and streets, whose construction or
relocation should be included as part of the project.
g) Environmental studies
In this phase, environmental data will be collected regarding the interactions of the alternatives.
of routes selected with the physical medium.
The objectives of these studies are:
– Relief profile;
Drainage.
h) Other items
IS-207 - Service Instruction for Preliminary Engineering Studies for Highways (alignment studies)
Basic Guidelines for the Preparation of Road Studies and Projects 287
From the interaction of future traffic data and geometric conditions, there will be the
definitive functional plan, to be developed integrated with the geometric design.
It will demonstrate in greater detail the preliminary functional plan, especially in
passages of greater complexity, such as in the convergences of various
highways and/or streets, where there is a degree of urbanization, and problems of conception of
accesses and crossings.
The need and locations for access to areas should be defined with greater precision.
urban and the main land uses that generate traffic; confirmed on a permanent basis
determined the nature, the pattern and the configuration of intersections; determined the
the need for marginal roads, or even for small secondary connections or
small road segments essential for the functioning of the circulation plan
designed; necessary operational and administrative measures established,
especially regarding the level of access control and conduct or measures
restrictive and regulatory when crossing urbanized areas; taken
in consideration of the needs for pedestrian flow and to
collective transport, through constructive and operational measures.
All construction measures resulting from the Functional Plan must be included.
in the Basic Project.
The construction costs will include the following items: earthworks; paving,
bridges and viaducts, works of art; drainage devices; curbs, gutters,
walkways; fences and barriers; horizontal and vertical signage; relocation of
public services, other necessary items and eventual ones.
For the construction items for which, given the preliminary nature of the study
if it is not possible to quantify the required services, their costs will be estimated
through the application of percentages on the other construction items. The
The percentages to be used will be based on experience from similar works, if possible.
in the region, and will have prior approval from DNIT.
IS-207 - Service Instruction for Preliminary Engineering Studies for Highways (route studies)
Diretrizes Básicas para Elaboração de Estudos e Projetos Rodoviários 288
The selection of the route alternative to be considered in the project will be made from the
analysis of the technical compatibility of the alternatives with the project's objectives, and of the
assessment of its economic implications.
4 PRESENTATION
The presentation of the Preliminary Engineering Studies (Routing Studies) will be held
through the Preliminary Report of the Engineering Project to which it corresponds, must
counter
PRELIMINARY REPORT
4.2. FINALSTAGE
BASIC PROJECT
IS-207 - Service Instruction for Preliminary Engineering Studies for Highways (alignment studies)
Basic Guidelines for the Development of Road Studies and Projects 289
ANNEX B8
IS-208 - SERVICE INSTRUCTION FOR GEOMETRIC PROJECT
1 OBJECTIVE
Define and specify the services included in the Geometric Project of the Projects of
Road Engineering, Basic Design and Executive Project.
2 PROJECT PHASES
The Geometric Project in this Basic Project Phase will be developed based on the
aerophotogrammetric restitution, or topographic exploration, carried out in accordance with
with aIS-204, from which several lines will be tested, aiming to obtain the one that
find the three-dimensional balance of the project.
The minimum geometric characteristics of these lines of the geometric project, at this stage
will be guided by Traffic Studies, must comply with the recommendations of
Manual of Geometric Design of Rural Roads DNER - 1999.
The development of the lines of the geometric project will also comply with
recommendations from geological and geotechnical studies aiming to minimize the
construction problems.
a) Project in plan;
b) Profile project;
With the plants and notebooks from the topographic survey resulting from the location of the axis, there will be
start the preparation of the Geometric Project in this Executive Project Phase:
a) Planialtimetric project;
b) Determination of the cross-sections of the project;
– tapers.
in plan
– Represent the edges of the platform and the projections of the offset shachuriados in
conventions differentiating cuts and embankments;
In the case of the existence of a 3rd lane, it should be indicated on the plan. There will be
represented as transmission lines within the right of way with
indication of the origin and number of postings;
Represent the bridges, viaducts with the names of the rivers, accesses, intersections,
walkways and installations for the operation of existing and to be constructed highways, with
the names of the localities, indicating the volume number and sheets that contain them
specific projects; the drains will be indicated in type conventions (lines
traces) with the total extension at the foot of the landfill and its slant. Others
devices (safety trays, cut-offs, loan boxes) will be
represented, indicating where they are located and their construction details;
Indicate the landscaping zoning by marking the rest and recreation areas.
parking and tree planting, the details of which will be presented in a chapter
own. The same treatment will be given to the road policing posts and
to the scales;
in profile
Indicate the land line and the project representing this the surface of the grade of the
paving on the platform axis.
The stakes will be numbered for every 1 m and percentages will be indicated.
lengths of the ramps, the length of the horizontal projections of the curves
of vertical agreement (Y), the length of the arrow "e" of the vertical curves,
kilometers and quotas of the PIV, PCV, and PTV of each vertical curve. The artworks
specials and the manholes will be represented by type conventions, indicating
for these last ones, their type and section and the drainage devices by lines in
Convention. The geotechnical profile will be represented with soil classification.
- The profile will also highlight the extensions with particular solutions.
(diverging from the cross-section type) for widening cuts, stepping
or change in the slope of the slopes.
a) The type cross sections of the platform will be raised and drawn, strip of
domain, bridges and tunnels in the various characteristics provided for the highway in
tangent and curve, showing the distribution criterion of the superwidth and the
superelevation along the alignments of horizontal curves.
b) The cross sections will be raised and drawn indicating the natural terrain, the
platform, the positions of the offsets and slopes.
c) Marking of the domain strip asymmetrically in relation to the axis and based on the
offset line considering the eventual construction of other runways.
They will be constituted by intersections, returns, and accesses, marking any potential
alterations of the cross section of the highway, as well as the indication of the location of the
installations for the operation of the highway.
4 PRESENTATION
The geometric project, in its Basic Project Phase, will be presented in the Report.
Basic of the Engineer's Project to which it corresponds, encompassing the following
volumes:
BASIC REPORT
FORMAT
VOLUME TITLE
Printing
Minute
Definitive
In the Executive Design Phase, the geometric project will be presented through the
Final Report of the Engineering Project to which it corresponds, comprising the
following volumes:
FINAL REPORT
FORMAT
VOLUME TÍTULO
Printing
Minute
Definitive
Project Report
1 A4 A4
− Text - project summary created
Execution Project
− Plants and profiles at scales 1:2,000 (H) and 1:200 (V);
− Drawing of cross sections, in plant.
scales 1:200 or 1:100, containing the sections of
2 A1 A3
land, cut slopes and embankment slopes;
− Drawings of the type cross-sections;
− Designs of return projects, accesses, tapers,
in vegetable.
Justificative Memorandum
3 − Descriptive and justificative report of the elaborated project A4 A4
text, graphics and tables
ANNEX B9
IS-209 - SERVICE INSTRUCTION FOR EARTHWORK PROJECT
1 OBJECTIVE
Define and specify the services included in the Earthworks Project in the Projects of
Road Engineering, Basic Project and Executive Project.
This study should carefully evaluate the alternatives that are presented regarding the
movement of earthworks volumes, in order to adjust, among others, the
loan needs and disposal areas available for such, taking into account
still taking into account the existing or planned urbanization and landscaping plans, for
mutual compatibility, in addition to environmental protection. Also consider the
convenience and possibility of extensive longitudinal movements of volumes of
land for compensation purposes.
d) details of the typical cross-sections and specific solutions for slope inclinations,
widening of cuts, terraces, embankment foundations;
The methodological procedures for carrying out these activities are outlined in the
Basic Implementation Manual of DNER - 1996.
maximum native flora and the layer of topsoil that will serve as capping of the
cut and filled areas.
4 PRESENTATION
The Earthworks Project, at this stage, will be presented in the Basic Project Report.
of Engineering to which it corresponds, should contain:
BASIC REPORT
FINAL REPORT
FORMAT
VOLUME TITLE
Impression
Minute
Definitive
Project Report
1 − Text - summary involving the project conception - A4 A4
text, graphics and tables.
Execution Project
− Geotechnical profile indicating the composition of the soil;
− Cubation leaves;
− Earthmoving orientation frame;
− General plan of the situation of loans and puts-
2 fora A1 A3
− Plants of the loan locations;
− Drawings of the typical cross-sections, in cut and
in fill, indicating the slopes of the embankments;
− Drawings of the cross sections by pile, with
platforms and slopes of cut and fill.
− Other drawings that elucidate the project.
Justifying Memory
3 − Descriptive and justification report of the project prepared A4 A4
− Classification of materials to be excavated.
ANNEX B10
IS-210 - SERVICE INSTRUCTION FOR DRAINAGE PROJECT
1 OBJECTIVE
Define and specify the services included in the Drainage Project in the Projects of
Road Engineering.
The Basic Design phase will define the conception of the drainage project, enabling the
choice of the best solution, through the analysis of the basic conditioning elements of
project. At this stage, regarding the drainage works, the following will be defined: number,
nature, probable location, local aspects considered, access conditions,
utilization of materials and labor from the region with types, quantities, and estimates
of costs.
a) hydrological studies: prepared for the Engineering Project, necessary for the
determination of the flow at each point is essential for the establishment of the sections
to adopt and the conditions of drainage.
c) topographic studies developed in its Basic Project phase for the Project of
Engineering should be supplemented in order to define the implementation of the works of
drainage, using specific measures for this purpose.
d) geotechnical studies prepared in its Basic Project phase for the Project of
Engineering should be supplemented in order to define and characterize materials.
foundation conditions of the works to be designed.
Efforts will be made to preserve the existing valleys, limiting suppression to a minimum for
maintain the river network and the springs.
The feasible alternatives will be listed, and all will be pre-dimensioned based on the
current standards and specifications, at which time consideration will be given to the
possibility of reuse and standardization of solutions, materials,
equipment and labor.
Next, the quantities and costs for each solution will be estimated.
Once the alternatives are defined, the choice of the most convenient solution must be aligned.
with technical, economic, aesthetic, and administrative criteria.
The choice of the definitive solution will be made after considering the examinations of the alternatives.
accordance with the mentioned criteria, including drainage systems and devices
defined in the Highway Drainage Manual, from DNER transcribed as follows:
Devices:
Sewers;
b) Surface drainage
Objective: intercept and capture, guiding the safe drainage of incoming waters.
of their adjacent areas and those that fall onto the road body,
guarding security and stability.
Devices:
Cutting gutters;
Landfill gutters;
Water descent;
Water outlets;
Collector boxes;
Gully drains;
Energy dissipaters;
Slope scaling;
Short-rows;
Objective: to protect the pavement from waters that may damage it, originating from
direct infiltrations from rainfall and those coming from aquifers
subterranean water. This drainage is necessary in regions where it is observed
annual rainfall height greater than 1500 mm and on highways with TMD above
of 500 commercial vehicles.
Devices:
- Draining layer;
Transverse drains.
Devices:
Deep drains;
Fishbone drains;
Draining mattress;
– Sub-horizontal drains;
Side valets;
Vertical drains.
Devices:
– Curb cuts;
Wolf mouths;
Manholes.
Detail the solution approved in the previous phase and relate the necessary elements to
construction of the work.
The various structures that make up the drainage project will be dimensioned.
by the established methods and formulas, must necessarily be presented to
calculation memory containing the adopted norms and specifications, the
hypothesis of calculations, the values of the project conditions, the checks of
work and the resulting efforts and rates.
will be determined in a way that is consistent with the corresponding Specification. The
the costs of each service will be determined according to the current methodology in
DNIT;
d) Project execution plan: the conditions for carrying out the work will be defined, such
as deadlines for execution and quantification of equipment and technical personnel,
indication of the construction site and position of installations, deposits, and sources of materials
and access.
The drainage project should be guided by the guidelines in the Project Album.
Type of Drainage Devices, from DNER.
4 PRESENTATION
At this stage, the project presentation will take place through the Basic Project Report of
Engineering to which it corresponds, consisting of explanatory text and drawings of the
proposed solutions, as detailed below:
BASIC REPORT
− Project conception;
Report / Memory
− Table of quantities and codes;
1 Justification of the Project A4
Basic − Discrimination of all services, distances of
transport and quantities.
− Plans and typical drawings of the various devices
of drainage used;
Basic Project of − Schematic plan of the location of the works of
2 A1
Execution drainage;
− Drawings with the Standard Projects of the devices of
drainage.
− List of services to be performed;
− Costs of each service;
Budget and Plan of − Physical schedule;
4 A4
Execution − List of minimum equipment;
− Layout of the construction site, access,
installations, deposits and source of materials.
The Project, in the Executive Project phase, will be presented in the Final Project Report.
of Engineering that corresponds, initially in the form of a draft and after
approval through final printing, comprising the following volumes:
FINAL REPORT
Format
Volume Discrimination
Printing
Minute
definitive
Project Report
− Project conception;
1 − Table of quantities and codes, A4 A4
− Discrimination of all services, distances of
transport and quantities.
Execution Project
− Plants and type designs of the various devices of
used drainage;
2 A1 A3
− Schematic plan of the location of the works of
drainage
− Service notes
Justifying Memorandum
3 − Justification for the detailing of the approved alternatives A4 A4
in the project.
ANNEX B11
IS-211 - SERVICE INSTRUCTION FOR PROJECT OF
PAVING (FLEXIBLE PAVEMENTS)
1 OBJECTIVE
Define and specify the services included in the Paving Project in the Projects of
Road Engineering.
2 PROJECT PHASES
a) statistical study and definition of the subsoil support index along the various
homogeneous subsegments.
4 PRESENTATION
At this stage, the presentation of the project will be made through the Basic Project Report of
Engineering to which it corresponds, consisting of explanatory text and drawings of the solutions
proposals, as detailed below:
BASIC REPORT
− Project conception;
− Table of quantities and codes;
Report / Memory − Discrimination of all services; distances of
1 Justification of the Project transport and quantities; A4
Basic − Summary table of preliminary study trials
the occurrences of materials;
− Specific and complementary specifications.
− Drawings of cross sections type, in cut and
in landfill;
Basic Project − Sketch of each occurrence of materials with
2 A1
Execution binding of the preliminary drilling holes,
indicating the location in the section, with tying
needs regarding the axis of the highway;
− List of services to be performed;
− Cost of each service;
Budget and Plan of − Physical schedule;
4 A4
Execution − List of minimum equipment;
− "Layout" of the construction site, accesses,
installations, deposits and source of materials.
The Project, in the Executive Design Phase, will be presented in the Final Project Report.
of Engineering to which it corresponds, encompassing the following volumes:
Final Report
Format
Volume Discriminação
Impression
Minute
definitive
Project Report
− Project conception;
1 A4 A4
− Discrimination of all services, quantities, and distances
of transport.
Execution Project
− Summary table containing the quantities and distances of
transport of the various materials that make up the structure of
floor
− Distribution graph of materials and thicknesses of
layers, according to the model recommended by DNIT;
− Cross-section drawings type, in cut and in fill, of the
runway surfaces, shoulders, accesses and areas of
facilities for highway operation;
2 A1 A3
− Detailed plan of each occurrence with contour lines of 1
I am 1 m, indicating the location in the section, with tying.
needs in relation to the axis of the highway, through at least
two benchmarks; positions of the drilling holes with the
usable depth marked next to each hole, area
of exploration and summary of the physical characteristics of the material;
− Drawing presenting the cross sections in tangent and
in curve and its longitudinal variation along the section;
− Other drawings that clarify the project;
Justifying Memorandum
− Justification for the detailing of the approved alternatives in
3 A1 A3
preliminary project.
− Calculation memory for pavement sizing.
Geotechnical Studies
− Summary tables of essays;
3A A4 A4
− Surveys bulletins of material occurrences;
− Surveys bulletins of the subsoil.
Budget and Execution Plan
− List of services to be performed;
− Cost of services;
4 A4 A4
− Physical and financial schedule;
− List of minimum equipment;
− List of necessary personnel.
ANNEX B12
IS-212 - SERVICE INSTRUCTION FOR STRUCTURAL EVALUATION AND DESIGN
REHABILITATION OF FLEXIBLE AND SEMI-RIGID PAVEMENTS
1 OBJECTIVE
Define and specify the Structural Assessment and Rehabilitation Project services.
Flexible and Semi-Rigid Pavement existing in the Feasibility Studies and Projects of
Road Engineering.
The Structural Assessment and the Recovery Project of the existing Pavement will be
executed in two phases:
IS-212S
-ervcieInsrtucoitnfoS
rrtucutraE
lvaulaoitnandDesginoR
fehabatilotnoF
felxbielandSem-iRgidiPavemenst
Basic Guidelines for the Preparation of Road Studies and Projects 307
b) Cross-section of the pavement, indicating the type and thicknesses of the layers
projected and existing and the nature of the subsoil;
The surveys and other field studies conducted in the homogeneous segments
they will be in such a number that allows the safe application of statistical processes for
analysis of the same.
Methodology Title
The measurements will be carried out at stations defined on the pavement, along the stretch.
spaced from each other, alternately, on the right and left side of the track.
When it comes to a highway with more than one lane, the measurements will be determined in
each one of these.
In the case of the existence of additional lanes on slopes, carry out specific measurements for
such segments.
IS-212S
-ervcieInsrtucoitnfoS
rrtucutraA
lsesmenatndRehabatilotnProejcotF
felxbielandSem-iRgidiPavemenst
Basic Guidelines for the Preparation of Road Studies and Projects 308
In the course of the interpretation of deflection basins, through back-analysis processes, the
the designer may justify the obtaining of various project parameters, based on
for modern knowledge about pavement mechanics, making it simpler and
sure the geotechnical studies.
The inventory of surface conditions should be simultaneous with the measurement of deflections.
in the same stations as those, using the following methodologies:
Methodology Title
The measure of the longitudinal irregularity of the pavement will be expressed through the
QI indices - Irregularity Quotient and IRI - International Roughness Index,
using the methodology indicated below:
Methodology Title
IS-212S
-ervcieInsrtucoitnfoS
rrtucutraA
lsesmenatndRehabatilotnDesginoF
felxbielandSem-iRgidiPavemenst
Basic Guidelines for the Preparation of Highway Studies and Projects 309
[Link]. GEOTECHNICAL INVESTIGATIONS OF THE PAVEMENT
Geotechnical investigations will be carried out after determining the deflections and
inventory of surface conditions, in such a way that each segment of
homogeneous behavior should be covered, at least, with a drilling hole.
For this purpose, drilling will be carried out throughout the entire pavement structure.
the runways and shoulders, at the edge of the runway with the shoulder, using
shovel and pickaxe, at least every 2.0 km, or less when there is variation in the type of
pavement structure, for sample collection and implementation of the following
determinations:
The quarries and sand pits will be the subject of research in the region, regarding real prices, both
for commercial gravel (documented proofs) as for the produced gravel, in
regarding compensations for use. In cases of owners who have
mining rights, the royalty price charged for exploration will be researched.
obtained prices will be inserted into the cost compositions of the services, seeking to
portray the market reality for bidding purposes.
The samples collected from the pavement layers will be subjected to tests of
laboratory, using the methodology indicated below.
IS-212S
-ervcieInsrtucoitnfoS
rrtucutraE
lvaulaoitnandRehabatilotnDesginoF
felxbielandSem-iRgidiPavemenst
Basic Guidelines for the Preparation of Road Studies and Projects 310
Granulometric tests will be conducted with sedimentation in the case of the application of
DNIT-PRO 269 method (TECNAPAV), in samples collected from the subgrade, in wells.
alternated.
Surveys will be conducted to check the level of the water table, until the
depth of 1.50 m below the level of the subgrade, one at each point of passage
(PP) and another in the middle of the cut.
a) Division of the section under study grouped into segments of structural behavior and
homogeneous functions;
b) Structural assessment of the pavement, calculating the various design parameters for
each homogeneous segment;
c) Conditions of underground drainage of the existing pavement.
The design parameters, for each homogeneous segment, currently practiced in the
various methods adopted by DNIT include the following:
− Curvature radius;
IS-212S
-ervcieInsrtucoitnfoS
rrtucutraA
lsesmenatndRehabatilotnDesginoF
felxbielandSem-iRgidiPavemenst
Basic Guidelines for the Preparation of Road Studies and Projects 311
− Thicknesses of the layers of the pavement made of granular and stabilized materials
additives (base, subbase and reinforcement of the subgrade);
NOTE: The pavement sizing methods of DNAR and the HDM-4 model
they use characteristic deflections Benkelman. In the case of the use of (FWD)
or another type of deflectometer, the characteristic deflections obtained must
to be converted into characteristic Benkelman deflections.
The pavement rehabilitation project must use the methods approved by DNIT.
it is the designer's responsibility to justify the use of the chosen method. In the case of using others
methods, the designer must justify the reasons for their choice and the non-use of the
approved methods.
Methodology Title
DNER-PRO 159/88 Project for the restoration of flexible and semi-rigid pavements
Tables will be presented, containing all the parameters of the section, such as
deflexão, quociente de irregularidade, percentual de trincamento, percentual de desgaste,
arrows on the wheel tracks, defects in the pavement, according to the prescribed in
DNIT procedure-006/2003-PRO, and the pavement structure according to the
highlighting and mileage of the section, demonstrating the division into segments
homogeneous and the corresponding solutions.
IS-212S
-ervcieInsrtucoitnfoS
rrtucutraA
lsesmenatndRehabatilotnProejcotF
felxbielandSem-iRgidiPavemenst
Basic Guidelines for the Preparation of Road Studies and Projects 312
Present the results and design alternatives of the pavement, including shoulders.
correspondents, indicating materials, methods of execution, and quantities, for
technical-economic assessment of the proposed alternatives.
The linear paving graph for the track and shoulder will contain the sources and the
occurrences of materials, such as quarries, gravel pits, sand pits, plants, and crossings
urban, establishing the anchoring and the mileages coinciding with those
demarcated in the field.
An economic study should be conducted with the aim of choosing the most suitable alternative.
economic, considering the life cycle of the planned interventions and the activities of
Scheduled maintenance. The HDM-4 system may be used for this purpose.
Once the conclusions and recommendations in the Basic Project Phase are approved, the
project, in this Executive Project Phase that will basically consist of the consolidation of
solution chosen in the project outline phase.
a) Existing pavement;
c) Geotechnical studies;
d) Milling;
e) Forecast of corrections;
h) Attack plan.
At this stage, the attack plan and the quantities for the services will be defined.
superficial/deep patches, "pothole fillers", and other issues of similar severity on the track of
rolling, to be materialized soon at the beginning of the rehabilitation works.
IS-212S
-ervcieInsrtucoitnfoS
rrtucutraE
lvaulaoitnandRehabatilotnProejcotF
felxbielandSem-iRgidiPavemenst
Basic Guidelines for the Development of Road Studies and Projects 313
The physical-financial schedule must be detailed in such a way as to present all the
paving stages, highlighting that in cases of recycling or reconstruction of the
base, the upper layers will have to be executed with a slight delay of
time, so that they do not remain unprotected against the action of traffic and of
rainfall precipitation.
Whenever possible, traffic diversions will be indicated for the work on the platform.
road, particularly in flat or slightly undulating regions, taking into account
the costs for the removal of vegetation, placement of the primary covering layer
and the use of motor grader for traffic maintenance.
4 PRESENTATION
At this stage, the project presentation will take place through the Basic Project Report.
Engineering corresponds to, consisting of explanatory text and drawings of the solutions
proposals, as detailed below:
BASIC REPORT
IS-212S
-ervcieInsrtucoitnfoS
rrtucutraA
lsesmenatndRehabatilotnProejcotF
felxbielandSem-iRgidiPavemenst
Basic Guidelines for the Preparation of Road Studies and Projects 314
The project will be presented at this stage through the Final Project Report.
Engineering to which it corresponds, initially in the form of a draft and, after approval,
the definitive printing, comprising the following volumes:
FINAL REPORT
Format
Project Report
− Project conception;
1 A4 A4
− Table of quantities containing code, description of
all services, transport distances, unit and
amount.
Execution Project
− Drawings of the typical cross-sections, in cut and in fill;
2 − Drawing with the longitudinal representation of the layers of A1 A3
pavement, indicating types of materials and thicknesses;
− Schematic layout of material occurrences for
paving.
Justifying Memorandum
3 − Justification for the detailing of the approved alternatives in A4 A4
preliminary design.
Budget and Execution Plan
− List of services to be performed;
− Costs of each service;
4 − Physical schedule; A4 A4
− List of minimum equipment;
− Layout of construction site, access, installations, quarries and
source of materials.
IS-212S
-ervcieInsrtucoitnfoS
rrtucutraE
lvaulaoitnandRehabatilotnProejcotF
felxbielandSem-iRgidiPavemenst
Basic Guidelines for the Preparation of Road Studies and Projects 315
ANNEX B13
IS-213 - SERVICE INSTRUCTION FOR PROJECT OF
INTERSECTIONS, RETURNS AND ACCESS.
1 OBJECTIVE
Define and specify the services included in the Intersections, Returns and Project.
Access in Road Engineering Projects.
The project for intersections, returns, and accesses will be developed in two phases:
This phase includes the project conception, involving the following activities:
a) Justification for the solution adopted in regard to the traffic to be addressed.
The execution of the intersection, returns, and access project, at this stage, will consist of:
Do you understand?
a) Traffic flowchart for the year of opening and for the 10th year of useful life, containing
the VMD (daily average volume) and VHP (project hourly volume), by type of vehicle and
in UCP (unit of passenger cars).
e) Typical cross sections of the platform, including lanes, shoulders, and medians,
at the notable intersection points.
It should be noted that the earthworks, drainage, and current construction projects
special, pavement, signage and landscaping of the intersections must meet the
foreseen in the corresponding Service Instructions.
4 PRESENTATION
The presentation of the intersections, returns, and access project at this stage will take place,
through the Basic Report of the Engineering Project to which it corresponds, and
will understand
BASIC REPORT
BASIC REPORT
In this Executive Project Phase, the Project of Intersections, Returns, and Accesses will be
prepared through the Final Report of the Engineering Project to which it corresponds,
understanding the following volumes:
FINAL REPORT
Format
Volume Discriminação
Print
Minute
definitive
Project Report
− Text with the project conception;
1 − Quantity and code chart; A4 A4
− Discrimination of all services; transportation distances and
quantities.
Execution Project
− Plants containing the design conception in plan and profile and the
traffic flowchart.
Plants presenting the projects:
• Geometric;
• Earthworks;
• Paving;
2 • Drainage; A1 A3
• special works of art;
• Complementary works;
• Signaling;
• Landscaping;
• Lighting (occasional);
− Service notes on earthworks, paving, drainage and
signaling.
Justifying Memory
3 A4 A4
− Justification for the detailing of the approved alternatives
Budget and Execution Plan
− List of services to be performed;
− Costs of each service;
4 − Physical schedule; A4 A4
− List of minimum equipment;
− Layout of the construction site, access, installations, deposits and
source of materials.
ANNEX B14
IS-214 - SERVICE INSTRUCTION FOR PROJECT
OF SPECIAL WORKS OF ART
1 OBJECTIVE
Define and specify the services included in the Special Works Project.
Road Engineering Projects.
This Service Instruction applies to the preparation of bridge and viaduct projects.
in reinforced and prestressed concrete.
2 PROJECT PHASES
a) Preliminary Phase;
a) Local information of such nature that indicates the purpose of the work,
situation in the road system, access conditions, regional characteristics and
the availability of materials and labor, and allow for the definition of the location of
implementation of the artwork, the adoption of the appropriate structural type, the implementation
secure foundations and the proper assessment of specific local actions in the structure.
b) Information about the highway project to be used in the preparation of the project.
structure, in such a way that the physical, geometric, and operational characteristics, and,
mainly the width of the cross-section of the artwork should be determined in
compliance with the designed route, incorporating the main elements of the layout,
in order not to reduce capacity.
a) Topographic elements
Longitudinal profile of the terrain along the axis of the layout, with graded elevation.
desenhado em escala de 1:100 ou 1:200, especificando as amarrações ao
highlighting and RRNN of the highway project and locations, in total length
that allows for the definition of the work and access embankments;
– Topographic plan of the section where the work will be implemented, presented in the
scale 1:100 or 1:200, with contour lines every meter, containing the axis of
tracing, existing interferences, such as boundary limits, transmission lines, and
a concern regarding the obstacle to be overcome, covering sufficient area
for the definition of the work and accesses; the bindings to be specified must be
highlighting and RRNN of the highway project, and its definitions are still determined
locations.
b) Hydrological elements:
Indication of the quotas, times, and durations of occurrences, of maximum fullness and
maximum drought of the watercourse;
Calculation memory for determining the flow section required for the work
art, with indication of the maximum speed of the waters in the location;
Indication of the possibility of deposits occurring in the bed, banks, and erosion
at the bottom or along the banks of the watercourse, as well as the tendency to digress from
riverbed and eventual transport of floating materials during flood periods;
News about the possibility of aggressive waters occurring, both under the
toxic aspect as under the aspect of destructive action;
c) Geotechnical elements:
Location plan of the surveys, referred to the located axis of the highway;
- Geological profiles - geotechnical and individual for all boreholes, indicating the
nature and thickness of the various layers crossed, depths in
relation to the RRNN of the highway, penetration resistance index, and water levels;
d) Complementary elements:
- Nomenclature of the highway, segment, subsection, and stake or kilometer where it
will implement the work and names of the obstacles to be overcome;
Description of the local aspects that will be relevant to the project, such as: proximity
from urban centers, templates to obey, need for sidewalks to
pedestrians and special guardrails, bike or cart lane, drainage,
pipeline passages, lighting poles, landscaping aspects to
consider and any other special reports necessary;
Means of access to the region where the work will be located and to the site;
Information about the possibility of utilizing the workforce from the region,
discriminating types, available quantities and normal salaries;
Conditions for obtaining water and chemical analysis;
Information about the support possibilities in the region, such as: energy,
housing, communications, transportation, banks and others.
a) Highway class, according to the Highway Engineering Design Manual, from DNIT.
e) Choice of the solution, opting for the one that best meets the technical criteria,
economic and administrative requirements and operational requirements for the highway. Consider the
architectural and landscape aspects of the work;
f) Structural calculation memory of the adopted solution defining the main sections and
elements of relevance in the structure, including resistance checks and
approximate amount of armor;
Topographic elements
• situation map of the influence area of the work;
• site plan and profile of the construction site, containing the structure, the
accesses, grades, staking and occurrences such as, roads, rivers, lakes, with
respective templates and quotas;
• site of the work, with contour lines spaced to allow for the perfect
characterization of the slopes of cuts, fills;
Hydrological elements: normal level and maximum flood level and flow section
calculated.
Surface drainage: rainwater drainage scheme over the deck and access.
This phase will include the detailing of the project developed in the previous phase, and
approved, through the determination and preparation of the following necessary elements for
execution of the work:
a) Structural calculations;
b) Drawings;
c) Specifications;
d) Quantitative;
They will be executed in accordance with the current rules and specifications, including:
f) Verification of the work rates of all materials and their compatibility with the
specifications;
g) Demonstration of the compatibility of the foundations with the nature of the soil.
When structural calculations are performed with the help of computers, provide
in detail, information about the program used, input data and results
obtained.
3.3.2. DRAWINGS
All necessary elements for the execution of the work must be presented.
consistent with the calculations.
They must include the dimensions of all structural component elements, the dimensions
necessary for the geometric definition of the work (elevations, plans, longitudinal sections and
transverse elements, structural and architectural details, and location of the work in plan and profile,
class regarding mobile loads, the quality of concrete, work rates of
foundation land or loads on piles, provisional openings for phases of
construction and removal of forms, and permanent ones for routine and permanent inspection, as well
such as the forecast of locations for the assembly of jacks, for the replacement of devices
support. They should also be included in the form drawings, whenever necessary, the
counter arrows, auxiliary supports for shoring and any other details that
they can contribute to the perfect execution of the services.
They should indicate the type of steel, the relative arrangement of the parts in the structure, and the dimensions of
Each sheet should contain a general list of the armors of all elements.
structural presented; this list must include the unit and total lengths of
each position, the total weights of the various gauges and the weight of the entire armor
represented in the drawing.
They should indicate the planned construction system, concreting plans, joints
mandatory and optional, plans and prestressing tables, shoring drawings
conveniently sized according to the proposed concreting plan,
indicating the sequence of execution and disassembly, as well as the deformations
foreseen.
3.3.3. SPECIFICATIONS-QUANTITATIVES
In the event that there is no General Specification for the service, it must be presented.
Complementary Specification, in the manner of the General Specifications.
The quantities of the services to be performed and all the materials to be used
they must be detailed, itemized, and calculated based on the definitions
from the Corresponding Specification.
In the preparation of the budget, all services to be provided will be defined and itemized.
executed, the quantities and the corresponding costs, determined in accordance with the
methodology of DNIT, and the provisions of the specifications are respected.
The execution plan of the work will be defined through explanatory text and preparation of
following documents:
a) Physical schedule, with deadlines and favorable dates for the start of services;
4 PRESENTATION
The presentation of the work in this phase will be done through the Preliminary Report of
Engineering Project to which it corresponds, and it will comprise the following volume:
PRELIMINARY REPORT
The presentation of the Special Art Works project, at this stage, will take place through
Basic Report of the Engineering Project to which it corresponds, and will include:
BASIC REPORT
The project presentation at this stage will be through the Final Project Report of
Engineering to which it corresponds, and will include the following volumes:
FINAL REPORT
FORMAT
Volume DISCRIMINATION/ SUBJECTS
Printing
Minute
definitive
Project Report
− Informative text of the project, summary of the studies,
1 specifications, quantities and all elements A4 A4
necessary for the bidding of the work. It will contain elements
topographic, hydrological, and geotechnical.
Project for the Execution of the Work
ANNEX B15
IS-215 SERVICE INSTRUCTION FOR SIGNAGE PROJECT
1 OBJECTIVE
Define and specify the services included in the preparation of the Signage Project in
Road Engineering Projects. This project involves Rural Highways and Urban Roads.
3 PROJECT DEVELOPMENT
This project will follow the recommendations of the DNIT Road Signage Manual
1999 Traffic Signaling Manual - DENATRAN, and will consist of the
establishment of signaling devices along the road sections in the phase
of the project, including branches, intercepted paths, that meet the regulatory requirements
and the circulation established by the functional plan. Also consider the messages
educational ones and those related to the operation process of the road.
Where applicable, this project will be aligned with the recommendations presented in
IS-233: Development of the Engineering Project for PACS Type Improvements, with the
objective of obtaining a uniform conception for the subject.
c) Dynamic signaling project through traffic lights and variable message panels
(PMV).
The horizontal signaling project will consist of longitudinal and transverse markings.
and by markings on the pavement, supplemented by auxiliary safety devices
of traffic.
The horizontal signaling project will contain the specifications of all materials to
employment and services to be performed, as well as presenting tables with the quantities by
type of device, material and service and comply with the following standards:
The vertical signage project will contain indications, location, dimensions, and types of
support, covering the following types of plates:
a) Warning;
b) Regulation;
c) Indication (localities);
d) Guidance (services);
e) Educational.
It will present the type of support for each panel, that is, if hung on portals,
semipoles or posts (with arms projected or not) and plates on columns. These
supports must be properly sized and detailed as part of
project. Consider details such as the type of plate fixation on the support, foundation of
portico and semi-porticos or, if applicable, fixation on central or lateral walls, or others
devices.
All the plates will be designed with the aim of determining dimensions and assisting in
constructive process.
The letter heights (depending on the road speed) and the box types will be informed.
uppercase or lowercase.
The project will present, for budgeting purposes, the corresponding quantities related to the
areas of panels, according to the type of reflective film, number of panels to be
installed and from the support.
3.3.3. SIGNALIZATION PROJECT WITH TRAFFIC LIGHTS AND VARIABLE MESSAGE PANELS (VMS)
Phase diagram and stages, showing the release over time of the various
movements;
– Electrical cabling and data transmission project, with the floor plan and
connection diagram;
After the identification of the alternative routes, following the completion of the work phase
previously, the selection of the routing option that best meets the objectives will be carried out
of the project.
b) Earthworks
This study should carefully consider the alternatives that are presented.
regarding the movement of earthworks, in order to adjust, between
others, the needs for loans and giveaways and the availability of areas
for that, also taking into account the existing urbanization and landscaping plans or
planned, mutual compatibility. It is also necessary to consider the convenience and
possibilidade de deslocamentos longitudinais extensos de volumes de terra para fins
of compensation.
IS-207 - Service Instruction for Preliminary Engineering Studies for Highways (alignment studies)
Basic Guidelines for Developing Highway Studies and Projects 331
FINAL REPORT
Format
Volume Discrimination
Printing
Minute
definitive
Project Report
− Text containing the project description;
1 − Quantity table; A4 A4
− Discrimination of all services, transportation distances
and quantities.
Execution Project
− Plant containing the location and types of devices
signage along the roads, intersections, and accesses in
project
− Plant containing structural details for assembly and fixing
of arches, signs, horizontal signage details,
2 etc; A1 A3
− Project for electrical wiring and data transmission
dynamic signaling, covering the floor plan and diagram
of connections;
− Summary charts and service notes containing the location,
model, type, and quantity of the various elements of
signaling.
Justification Memo
3 − Justification of the indicated solutions; A4 A4
− Calculation memory.
Budget and Execution Plan
− List of services to be performed;
− Cost of each device and services;
4 − Physical schedule with favorable deadline and start date A4 A4
of the services;
− List of minimum equipment;
− Schedule for the use of equipment;
The presentation of the signaling project in linear diagrams or will not be allowed.
diagrams. The location and situation of the signaling elements will be recorded on the
drawings of the geometric project or the topographic survey, in reproductions
simplified (without contour lines, for example), for clarity purposes.
ANNEX B16
IS-216 - SERVICE INSTRUCTION FOR LANDSCAPING PROJECT
1 OBJECTIVE
Proceed with the qualitative assessment of the potentialities and difficulties related to
the landscaping treatment of the highway for each alternative defined in the studies of
traced, based on which the concept of the landscaping project is established.
Indication of the most suitable locations for service and fuel stations,
motels, restaurants, and other commercial establishments.
j) special treatments;
The design concept of the landscaping project, established based on the pedological survey and
Survey of the landscape resources in the area will be the proposed landscape solution.
for the adopted alternative, through type segments, taking into account the
recommended measures for mitigating the environmental impacts related to
specific studies.
The solutions approved in the previous phase must be detailed and include:
a) Topographic survey;
b) Landscaping project.
The topographic survey used for the geometric and design project may be adopted.
intersections, complemented with the following indications:
c) locations planned for service and refueling stations, motels, restaurants, and others
commercial establishments;
Based on the studies developed and approved in the Basic Project phase and
topographical survey carried out, the landscaping project will be developed, which
will consist of:
e) projects for rest and/or recreation areas, parking lots, squares, viewpoints,
belvederes, installations and civil works to support the operational services of
passenger transport and users and buildings for administration
bus station and other public bodies present in the domain strip;
f) indication of the most suitable locations for service and refueling stations,
motels, restaurants, and other commercial establishments;
g) special treatments;
i) budget;
4 PRESENTATION
At this stage, the project presentation will be made through the Basic Project Report.
The engineering it corresponds to will consist of the following volumes:
BASIC REPORT
The project presentation at the Executive Design phase will be carried out through the Report.
Final, of the project to which it corresponds, composed of the following volumes:
FINAL REPORT
FORMAT
Volume Description / Matter
Impression
Minute
definitive
Project Report
⎯ Project design for the approved alternative;
⎯ List of plant species to be used, sources of acquisition,
planting and conservation technique, with information contained in the
1 environmental reports; A4 A4
⎯ Quantity table containing code, description of the
species and all transportation services and distances;
⎯ Technical specifications of the materials to be used in the
construction works.
Execution Project
⎯ General site plan of the locations of the preliminary projects
landscaping treatment, tied to the milestone markers,
notable points such as cities, beaches, rivers,
springs;
⎯ Division into sections for tree planting, vegetation to be
preserved, areas chosen for rest and/or recreation, deposits
the excavations for loans, intersections, suitable locations
for tax posts, service and supply posts (1/10000);
⎯ Drawings with the detailing of the solutions;
⎯ General plan for afforestation and vegetation covering of the area of
domain and bordering areas (scale 1/500);
2 A1 A3
⎯ Detail plant of the different types of tree planting such as
forests, wooded areas (scale 1:100);
⎯ Specific plants for the landscaping treatment of intersections and
accesses on the scale 1:500;
⎯ Specific plants for corrective treatment of deposits,
excavations and dumps, scale 1:100;
⎯ Specific plants for corrective treatment of deposits,
excavations and spoil tips (cross-sections), at a scale of 1:100;
⎯ Drawings, plans, cuts, views, and structural details of the
architectural elements, scales: 1/50 or 1/100 (cuts), 1/50 or
1/100 (plants) and 1/25 or 1/10 (details);
⎯ Adopted conventions sheet.
Justificative Memorandum
− Justification for the detailing of the approved alternative in the phase of
3 preliminary project A4 A4
− Calculation memory of the service quantities for bidding of the
work.
Budget and Execution Plan
− List of services to be performed;
− Cost of each service;
− Physical schedule with favorable deadlines and dates for the start of the
4 A4 A4
services;
− Minimum equipment list;
− Equipment usage schedule;
− List of technical staff for the execution of services;
ANNEX B17
IS-217 - SERVICE INSTRUCTION FOR DEVICE PROJECT
OF PROTECTION (DEFENSES AND BARRIERS)
1 OBJECTIVE
Define and specify the services included in the Protection Devices Project
(Defenses and Barriers), in Road Engineering Projects.
2 GENERAL CONSIDERATIONS
2.1. DEFENSES
Defenses are protection devices, rigid and flexible, continuous, with shape,
resistances and dimensions capable of allowing out-of-control vehicles to be
reintroduced to the track, without abrupt reduction in speed, nor loss of direction,
causing minimal damage to the vehicle, its occupants, and the device itself.
The sliding surface, composed of guide, ramp, and wall, has the property of
receive the impact of uncontrolled vehicles slowing down and returning them to the track.
c) Shoulder width;
d) Horizontal curvature;
IS-217 - Service Instruction for Protection Device Project (fenders and barriers)
Basic Guidelines for the Preparation of Road Studies and Projects 338
f) Road conditions;
g) Climate conditions;
h) Experience in accidents;
i) Highway class;
j) Traffic characteristics.
For the purposes of this instruction, it is established that there is a need to place defenses on
places where the obtained necessity index is higher than 50 (in urban roads and in
main highways) and 70 (on secondary highways).
2.2. BARRIERS
The barriers will be indicated for protection in places where defenses cannot be.
achieve the desired goals, as they require external space for deformation
motivated by the impact, this space is unfeasible in some locations, such as in the trays of
bridges and in the separation of lanes of opposite directions, in segments without a median
central.
The Protection Devices Project (Defenses and Barriers) will be developed in two
phases, which follow:
The execution of the protective device project will be carried out in accordance with the
set forth in the Regulations:
IS-217 - Service Instruction for Protection Device Project (docks and barriers)
Basic Guidelines for the Preparation of Road Studies and Projects 339
Norma Title
c) Estimated costs
In the Executive Design phase, the detailing of the proposed solutions will be carried out in
previous phase, through the selection of model projects, the preparation of service notes and
budget assembly and Project Execution of the Work.
5 PRESENTATION
In this phase of the project presentation, it will be done through the Basic Project Report.
de Engenharia a que corresponde, integrando-se aos seguintes volumes:
BASIC REPORT
Project conception;
Report / Memo.
1 Project Justification Device-type; A4
Basic
Set budgets
5.2.
IS-217 - Service Instruction for Protection Device Project (defenses and barriers)
Basic Guidelines for the Development of Road Studies and Projects 340
In the Executive Design phase, the project will be presented in the Final Project Report to
which corresponds, integrating the following volumes:
FINAL REPORT
FORMAT
Volume Discrimination / Subject
Printing
Minute
definitive
Project Report
1 A4 A4
− Text, chapter Defense and Barrier Project.
Execution Project
2 − Template projects containing placement details; A1 A3
− Service notes.
Justificative Memorandum
3 A4 A4
− Calculation memory.
Budget and Execution Plan
list of services to be performed
4 Costs of each service A4 A4
Physical schedules
Minimum equipment list
IS-217 - Service Instruction for Protection Device Project (defenses and barriers)
Basic Guidelines for the Preparation of Highway Studies and Projects 341
ANNEX B18
IS-218 SERVICE INSTRUCTION FOR PROJECT
FENCE EXECUTIVE
1 OBJECTIVE
Define and specify the services included in the Fence Project in the Projects of
Road Engineering.
2 PROJECT PHASE
The Fencing Project will be executed according to the recommendations of the Manual.
Basic Implementation, from DNIT, must comply with the following standards:
Standards Title
In the Executive Project phase, the detailing of the proposed solutions will be carried out.
previous phase, through the selection of model projects, preparation of service notes and
cost estimation and execution project of the work.
4 PRESENTATION
At this stage of the project presentation, it will be done through the Basic Project Report
of Engineering to which it corresponds, integrating into the following volumes:
BASIC REPORT
List of services
4 Budget and Plan Estimated costs A4
of Execution Physical schedules
In the Executive Project phase, the Project will be presented in the Final Project Report to
which corresponds, integrating with the following volumes:
Final Report
FORMAT
Execution Project
2
− Projetos-tipo contendo detalhes de colocação; A3 A3
− Service notes.
Justificative Memory
3
− Descriptive and justificative memorandum. A4 A4
ANNEX B19
IS-219 SERVICE INSTRUCTION FOR EXPROPRIATION PROJECT
1 OBJECTIVE
3.1. GENERALITIES
The expropriation project aims to define and specify the evaluation services.
de imóveis nos trechos urbanos ou rurais, com a finalidade de fornecer os elementos
necessary for the execution of the administrative process of compensation for expropriation
the areas necessary for the implementation of the corresponding road engineering project.
The preparation of the expropriation project will follow the recommendations of the Manual.
Expropriation of DNIT.
For each property belonging to the alternative approved in the preliminary project phase shall
to present a planimetric survey indicating improvements, main land uses,
distinguishing, also, cultures, pastures, unusable stretches and the main accidents.
The planimetric surveys and cadastral maps may or may not take advantage of the
elements obtained for the engineering project of the highway. The elements obtained, in
scale, must have adequate precision to represent and identify the properties that
will be expropriated.
A list containing the areas of the land and the improvements subject to will be presented.
donation and comparative report between the area to be donated and compensated.
The plan of the area to be expropriated must tie the property to the staking.
indicated in the geometric design. In the case of a highway built, the fixing may be
made through the milestone. Consider the following data:
b) Orographic aspects;
c) Existing public services such as: highways, railways, public transport, sewage
sanitary and rainwater, electricity, water supply, telephone, and others;
Along with the physical registration, a survey will be conducted about the property owners.
will be expropriated, indicating the legal status of the property. The information
The raised ones must be included in the Attached Table, Qd. 01 – 3AP, inserted below.
a) Newspapers;
This study aims to determine the compensation value of the lands, improvements,
crops and cultures, by property.
Use information from the registries in the area where the property is located, regarding the value of
last sale of land and characterized by the conditions of freedom
negotiation.
The information resulting from the conducted research must be included in the Attached Table.
Qd.02 – 3AP – I, inserted below.
VALUE ESTIMATE
EXPROPRIATION PROJECT
Highway: VALUE ESTIMATE NO.
Trecho:
Subsection: Qd02 - 3AP- I
Batch:
VALUE ESTIMATE
LAND USE
Improvements to be compensated
LOCAL DATA
EXPROPRIATION PROJECT
Highway: VALUE ESTIMATE
Excerpt:
Subsection:
Batch: Qd02 - 3AP- I
Área = 25.199,99m²
Área = 2,52ha
HIGHWAY:
EXPROPRIATION PROJECT
EXCERPT:
SUB-SECTION: Question 02 - 3 AP - II
LANGUAGE:
4 PRESENTATION
In the Basic Project phase, the presentation of the Expropriation Project will be made in
Basic Engineering Project Report that corresponds, integrating the following
volumes:
BASIC REPORT
In the Executive Project phase, the Expropriation Project will be presented in the Report.
Final of the Engineering Project to which it corresponds, integrating the following volumes:
FINAL REPORT
ANNEX B20
IS-220 SERVICE INSTRUCTION FOR PROJECT BUDGET
1 OBJECTIVE
Define and specify the services necessary for the preparation of the Project Budget in the
Projeto de Engenharia Rodoviária.
2 PHASES OF SERVICES
3 BUDGET PREPARATION
a) Market research;
d) Budget.
The budget of the alternatives in the Basic Design phase will provide elements for analysis.
economic and will consist of determinations of the costs of the main service items. The
costs will be raised according to the methodology outlined in the Manual
Composition of Road Costs, from DNIT, will basically cover those
of earthworks and paving, except as stated in IS-207 Instructions for
service for preliminary engineering studies for highways (studies of
traced) - Preliminary and Definitive Phases.
Prior to the preparation of the budget at this stage, the following will be carried out
atividades:
The budget in the Executive Project phase will follow the methodology outlined in the Manual
Composition of Road Costs of DNIT. Eventually, they may be introduced.
additional elements not provided in the Manual, to meet the peculiarities of
designed segment.
In certain cases, when the market does not have information available, or for
determination by DNIT, unit costs of the services may be determined, with
based on the Road Cost System SICRO, of DNIT.
In calculating this cost, consider the variation in the equipment's useful life, based on the
nature and conditions of the services to be executed.
3.2.2. PRODUCTION
In these calculations, consider the volume of the work and the structure of the company for each project.
specific.
The cost spreadsheets will contain the coding from the Coding System.
of Items Related to Road Construction, from DNIT, and the costs will be calculated
in the recommended units for measuring them in the general specifications,
complementary and particular.
In the transportation cost study, local costs will be determined, as well as,
the costs of commercial transportation necessary for the execution of the work.
4 PRESENTATION
The presentation at this stage will be made through the Basic Engineering Report to which
corresponds to the volume detailed below:
BASIC REPORT
The presentation at this stage will be made through the Final Report, of the Engineering Project to
that corresponds, as indicated below:
FINAL REPORT
The models of the frames will be those recommended in the Cost Composition Manual
Road workers, from DNIT.
ANNEX B21
IS-221 SERVICE INSTRUCTION FOR PROJECT OF
HIGHWAY OPERATION AND MANAGEMENT
1 OBJECTIVE
Provide subsidies for the development of studies and projects necessary for
characterization and quantification of the operation and management systems of the highway for the
granting of the same for exploitation by the private sector.
Therefore, the operation and management project will be developed based on the cash flow.
of the venture, based on the schedule of revenues and expenditures.
2 STAGES OF STUDIES
The studies for the development of the operation and management project will be carried out in
three phases:
3 DEVELOPMENT OF STUDIES
The definition of standards for operational activities will be the responsibility of the class and the TMD.
(average daily traffic) of the highway under study, and will be based on the recommendations of
publicationBasic Procedures for Highway Operation, DNER.
Several operating systems compose the operation of a highway. The main ones, type
special classes, with high traffic demands, should cover all the
systems indicated in this service instruction.
Rural roads, with low daily volumes, will dispense with several activities.
operational, allowing for the adjustment of the exploitation regime to the revenue forecast.
IS-221 - Service Instruction for the Operation and Management Project of the Highway
Basic Guidelines for the Preparation of Road Studies and Projects 355
k) Monitoring system.
The most appropriate efficiency standard for each of the mentioned systems as well
It will depend on the class of the highway and the traffic demand that circulates through it.
The toll collection activity aims to charge the usage fee, having as
basic objective is the economic viability of management, operation, maintenance and
road maintenance. It is carried out at the toll plazas, encompassing the building of
administration and collection cabins.
The service at the toll booths will be structured to impose the minimum of
delay to users, prevent vehicle evasion and provide adequate conditions of
safety for both employees and users and the capital raised.
It will operate on a rotating shift system, 24 hours a day.
The choice of the most suitable system of control and collection at toll plazas,
must analyze various aspects in order to optimize the resources to be collected,
minimize operational costs and delays experienced by users. These aspects are the
following:
b) Closed system: provides for intense access control, that is, entry accesses
Exits to the highway are limited to a restricted number of locations. In all these
places a small toll plaza (blockade toll). Upon entering
on the highway, the vehicle is registered at the toll plaza of the entry access, and the
The fee to be paid is calculated at the highway exit, at the exit toll plaza.
f) Reversible lane: it is more suitable for highways subject to tourist traffic, with
peaks during vacation periods and extended holidays. In other words, the square of
toll would require a very large number of booths in each direction of
circulation, to meet the peaks of going and coming back, which would remain idle at other times
days of the year.
g) Manual collection: it is the most traditional solution. For each collection hook
a collector is used, with the mission of classifying and collecting the toll amount
directly from the drivers, issuing change and the receipt. The performance of this system,
when it involves a fare value that requires change, it is in a range between 180 to 250
vehicles/hour, depending on the composition of the flow at the toll booth being more or
less homogeneous.
The duration of operation of the number of toll lanes and the number
the collector's correspondent should be sized according to the volume of
traffic by time of day, performance of each of the modalities
collection, and the progressive adherence throughout the concession period, by part of the
users, in relation to the semi-automatic and automatic billing systems.
The choice of the most suitable location for the installation of toll plazas should
consider, whenever possible, the following criteria:
− passages that do not present works of art, in order to minimize costs for the
runway widening;
− observe the location of toll plazas planned or in operation in
adjacent segments or on cross highways.
IS-221 - Service Instruction for the Operation and Management Project of the Highway
Basic Guidelines for the Development of Road Studies and Projects 358
The studies for the development of the vehicle weighing project on a highway should
to contemplate two alternative ways to carry out the activities: through posts
fixed and the second through mobile posts.
The fixed station provides more accurate measurement, as all vehicles subject to
supervision is evaluated.
The process is carried out in two stages, making it more agile and avoiding the formation
from queues for weighing. The first is selective weighing, in which the measurement is less
it is necessary, but it presents as an advantage the fact that the vehicles are weighed at a
speed close to that adopted for circulation on the road (approximately 50 km/h),
thus providing a dynamic flow in the weighing process.
Only those vehicles that present some irregularity in the selective weighing,
for being very close to the weight limits, or exceeding them, or still, by
the verification process did not occur satisfactorily, they are then directed to
precision weighing. reduced speed (around 5 km/h to 8 km/h). In case
upon confirming the irregularity, the driver is instructed to park the vehicle and proceed to
checkpoint, for recording violations. Otherwise, you are advised to continue your
journey.
The studies for the development of the weighing system will be carried out in a way
careful, with the purpose of implementing an efficient system that is capable of ensuring the
compliance with the rules regarding the weight limits established in the CTB. During
the development of the work, observe some issues such as:
a) alternative escape routes, especially for the location of fixed posts, due to the
high cost of setting up the installation;
d) the circulation (lines of desire) of heavy vehicle traffic in the area of influence
of the highway under study;
e) intersections and junctions that allow for the connection between highways, or rather,
the redistribution of traffic on the road network;
f) classification of the heavy vehicle fleet according to the number and types of axles;
It is important to highlight this activity, remembering that the damage to public property
caused by vehicles with excess load will require the return of financial resources
much greater compared to those required for the adoption of preventive measures
for the implementation of a cargo vehicle weighing system.
The constant patrolling of the road allows for the detection of any interfering anomaly in the
security and smoothness of vehicular flow, which may cause congestion or even
more serious traffic accidents. The longer the detection of something
occurrence, greater deterioration of the operating conditions of the road and consequently,
greater the effort to be made for the restoration of normal conditions.
The patrol vehicles should also provide assistance for the transport of special cargo.
or extraordinary, as well as initial assistance to users who are victims of mechanical failure
or traffic accidents, until the rescue teams arrive.
Depending on the class of the highway, the inspection activity of the road may be carried out.
with greater or lesser frequency:
a) Rural roads: the inspection may be carried out on a daily basis and even
weekly
An incident is the reflection of the occurrence of some event interfering with the conditions.
operating standards of the roadway, which may result in losses to fluidity, safety and
comfort in the movement of users. Therefore, it is of vital importance to re-establish
the initial conditions of the road, eliminating the causes that caused the incident.
The most common cases of incidents with damage to road traffic, in addition to accidents
of traffic and mechanical breakdowns are:
e) congestion
f) cargo spillage;
g) others.
In these cases, the action of traffic operators becomes imperative to avoid the
occurrence of accidents or more serious developments. Sometimes, it may be
it is necessary to call third-party institutions such as: Fire Department, organisms of
governmental environmental protection, whenever a more specific action is required.
It will be up to the operators of the Operational Control Center - CCO, after diagnosis of
Field by the operators of the inspection vehicles, request these aids.
The incident response system will be carried out by patrol or inspection vehicles.
utility type, crewed by a traffic operator duly trained to act in these
situations. In addition to the utility vehicles, the system should also include water trucks and trucks
from cattle for removal of animals on the track.
The water trucks will be useful in assisting with firefighting or in cleaning the
track, in case of spillage of lubricating loads or others that pose a risk to the
pavement, the structures of bridges and other road devices. Essential the
team training, especially in the transportation of hazardous materials, so as to
prevent the contamination of watercourses or groundwater by chemical products.
For the incident response system project, follow the recommendations of the
publication Basic Procedures for Highway Operation - DNER, regarding the
maximum response time for incidents, depending on the class of the highway.
a) Condition of the vehicles (in the case of trucks, also the accommodation)
of the load on the bodywork);
b) Physical and psychological condition of the drivers;
IS-221 - Service Instruction for Operation and Management Project of the Highway
Basic Guidelines for the Preparation of Road Studies and Projects 361
Since this task is exclusive to the police contingent, it will be included in the program of
exploration of the highway, a set of interventions aimed at promoting the
ideal conditions for the police force to perform their duties well.
Consider the reform of existing police stations, up to the provision of new ones.
communication systems, radars, breathalyzers, vehicles and fuel, as well as
computers and peripherals.
Also anticipate providing logistical support for police inspection actions, not
only in the verification operations, but regarding the overt policing.
It has been found that this type of action inhibits the undesirable behavior of some.
drivers in the direction of their vehicles.
The asset protection and surveillance system aims to ensure the preservation of the heritage.
public, of the road's facilities and devices, and ensure the physical integrity of
employees of the concessionaire and users who are using the highway.
Thus, to contemplate the highway with property surveillance structure, which may
third-party service, to keep efforts focused on conservation and operation of the
highway.
The toll plazas will have a permanent surveillance force that must provide
the necessary assistance to the areas of handling and storage of the collected funds.
The traffic monitoring and control system must perform in such a way
integrated with other systems and in a centralized manner, through the CCO - Central of
Operational Control and as a basic assignment, to permanently monitor the highway in
its entire extent. Thus, when detecting any anomaly or occurrence, the CCO
must be able to trigger the corresponding resource to correct the situation. For
for example, in case of a mechanical failure suffered by the user, the CCO will receive the request,
will activate the corresponding Operational Base in order to provide mechanical assistance
to the user, in the shortest possible time.
The occurrences on the highway can be perceived through the user's request.
(call through a special telephone line), via sensors spread out
along the way (CCTV, fog sensors, for example) or through the
participation of other systems (inspection vehicles or by the highway police).
The interventions may be carried out by the CCO itself (for example, triggering of
variable message panels) or by the support units located on the track (bases
operational and inspection patrol vehicles). Those that are considered essential are those that
to act in emergency situations that interfere with the conditions of fluidity and
road safety, implementing the required signage for these conditions and
promoting the removal of vehicles and accident victims.
The mechanical assistance system provides help to users who experience breakdowns.
mechanical or electrical.
The sizing of human and material resources for the service system
mechanic will be based on the fleet classification (high percentages of vehicles
heavies require a larger number of heavy trailers) and maximum time of
service, that is: the maximum time in which the rescue team must provide assistance
user assistance needed from the detection of the occurrence of the CCO. This
the maximum speed will depend on the class of the road, and its determination must follow
the recommendations contained in the Basic Procedures for Highway Operation
doDNER.
The sizing of human and material resources for the service system
The emergency doctor should follow the recommendations contained in the Rescue Manual.
Accident victims, DNIT.
The communication system with the user is relevant, especially on the highways under
tolls; users are always more demanding because they have paid the amount to
road circulation fee.
The different channels that allow users to communicate with the control team
from the highway are the following:
Call box
Depending on the class of the highway, there may be different ways to provide
information for travelers, such as:
The electronic control system will use several auxiliary equipment in the process of
road monitoring. The advancement of electronics and computing has allowed
considerable developments in this area, providing automation in
operational procedures, eliminating errors and optimizing the performance of the whole
system.
SYSTEM DEVICES
SYSTEM DEVICES
The advent of semi-automatic and automatic billing systems, represented by the use
IAV brings numerous advantages for users and operators, as indicated below:
a) Reduces the impedance caused in traffic flow, since it allows for drainage.
much larger vehicle fleet, especially for automatic cabins (IAV);
c) Reduces the handling of values, arising from the use of other means of
payment.
Considering the data storage potential of the TAGs used in the IAV and the
project to offer an intelligent highway for all users, where vehicles
commercial vehicles operating according to the standards set by the CTB may
to stop the journey not only at toll plazas, but also in
weighing stations, police, state and international inspection posts, with a view
To Mercosur, it is necessary to monitor technological evolution to expand the use of IAV for
the operation of inspection and weighing stations.
IS-221 - Service Instruction for the Operation and Management Project of the Highway
Basic Guidelines for the Preparation of Road Studies and Projects 366
The road management system aims to manage the daily operations of the
requests regarding the highways in question. It consists succinctly of the approval
or not giving users' requests, causing interference in the day-to-day of highways, or
interactions in physical patterns.
Authorization for the holding of events (sports, political, among others) within the
right of way of the highways, including the partial closure of the road;
Some issues involve other agencies, such as the case of the Highway Police.
(excess and special loads, events on the track, among others), from environmental agencies
environment (hazardous loads) and so on. Given the number of those involved, the
highway monitoring should be carried out swiftly, facilitating the processing of
data, so as not to harm the planning phase that such processes usually
require.
User satisfaction based on the adopted quality standard must be, ultimately
analysis, the parameter that will guide the management of the highway.
IS-221 - Service Instruction for the Operation and Management Project of the Highway
Basic Guidelines for the Preparation of Road Studies and Projects 367
The goal of studying traffic accidents is to understand the causes and frequency,
types and severity, enabling the adoption of measures and predicting interventions on the road, both
in the physical and/or operational aspect, which allow to minimize security issues,
or eliminate them. For this activity, several publications from DNER must be followed,
as the Handbook of Analysis and Identification of Critical Segments and the Guide of
Reduction of Accidents Based on Low-Cost Engineering Measures, among
others.
In addition to the data obtained in the previous stages, further actions may be taken.
public opinion surveys (level of education, family income, origin and destination, among
others), desires and preferences, and then outline your profile.
In the highways granted to the private sector, the management work should be carried out by
own dealership, which must constantly assess the quality of its
services.
To identify the viable operational pattern for the highway, it will be necessary
promote adjustments in the quantity and quality of the services initially planned, well
how to define the most appropriate year to start the execution of services throughout the
concession. This iterative work will be developed in conjunction with the team of
economic-financial-feasibility analysis.
4 PRESENTATION
The Highway Operation and Management Project will be presented in the Final Report of
Highway Exploration Program - PER, which corresponds to:
ANNEX B22
IS-222 - SERVICE INSTRUCTION FOR PRESENTATION OF
WORK EXECUTION PLAN
1 OBJECTIVE
Define and specify the services included in the Work Execution Plan, necessary for
implementation of Road Engineering Projects.
The Construction Execution Plan will be prepared in a single phase, the Project Phase.
Executive and will consist of:
b) Timelines;
c) Sizing and layout of the facilities necessary for the execution of services.
Presentation of the rational sequence of the set of activities that should be executed.
of the project, indicating the problems of a climatic, administrative, technical and
segurança; época do início dos trabalhos; período de execução; conseqüência da
location, type of construction and other conditioning factors for construction, including
implications with traffic, in the case of existing highways.
The execution plan for the work, to be drawn up for each construction lot, will take into account
considering the aspects related to climate and rainfall, notably concerning
to the rainy season and number of rainy days per month, logistical support, deadline for the
execution of the works, minimum equipment and attack plan for the services.
Graphical representation of the execution plan (covering all phases, mobilization and
demobilization) and the financial scheme, resulting from the sum of the quantities by
unit prices.
Definition of the locations of the administrative yards and industrial facilities, thus
how, establishment of sizing and preparation of the layout of the facilities,
presenting the work as a whole.
4 PRESENTATION
The Execution Plan of the Works will be presented in the Final Report of the Project.
Engineering to which it corresponds, and will consist of:
FINAL REPORT
ANNEX B23
IS-223 - SERVICE INSTRUCTION FOR EVALUATION AND RE-DIMENSIONING
OF EXISTING SPECIAL WORKS OF ART
1 OBJECTIVE
Define and specify the services included in the Assessment and Resizing of
Special artworks existing in the Feasibility Studies and in the Projects of
Road Engineering.
In the same way, when in a previous stage, both in the preliminary phase and in the
preliminary project, the results obtained from the technical-economic comparisons will define
clearly the abandonment of one or more existing works of art, this activity may
to be suppressed.
The evaluation and resizing of the existing special artworks will be carried out.
in two phases:
a) Data collection;
At this stage, the assessment of the existing special artworks will be carried out, as per
detailed below:
IS-223 - Service Instruction for the Evaluation Project and Performance of Existing Special Works ofArt
Basic Guidelines for the Development of Road Studies and Projects 372
Geotechnical elements;
Hydrological elements.
Execution plants;
Memoirs of calculation;
Adaptation of the project in relation to the crossing.
Execution date;
Analysis of the geometric project in conjunction with the work, related to the curve
horizontal and vertical, shoulders, and others.
IS-223 - Service Instruction for the Evaluation Project and Performance of Existing Special Works ofArt
Basic Guidelines for the Development of Highway Studies and Projects 208
In the development of the activities of this Preliminary Phase, the following must be observed
following aspects:
a) Data related to the history of the VMD and fleet composition, obtained from DNIT;
c) Volumetric and classificatory counts, carried out for at least 3 days, in the
situations where traffic data is not available or is
outdated;
a) Section Registration;
EB-114 - Basic Scope for the Preparation of Basic Engineering Project for Road Pavement Rehabilitation
Basic Guidelines for the Development of Road Studies and Projects 374
4 PRESENTATION
The presentation of the evaluation of the existing special artworks, Project phase
Basic, will be carried out in the Basic Report of the Engineering Project to which it corresponds, and
will consist of:
BASIC REPORT
Volume Report Discrimination Format
− Texto com apresentação da avaliação da situação
Report / Memorandum of existing works;
1 Justification of − Proposed solution; A4
Basic Project − Calculation memory of services;
− Cost estimate of services.
Sketch of each work indicating geometry, embankments
of access and intervening aspects in the decision on
Basic Project of
2 your utilization or not; A3
Execution
Concept of the resizing project
each artwork to be designed.
List of services to be performed;
Budget and Project - Service Costs;
4 A
of Execution Physical Schedules;
Minimum Equipment List
IS-223 - Service Instruction for the Evaluation and Performance Project of Existing Special Works ofArt
Basic Guidelines for the Preparation of Road Studies and Projects 375
ANNEX B24
IS-224 - SERVICE INSTRUCTION FOR EXECUTIVE SIGNALING PROJECT
FROM THE HIGHWAY DURING THE EXECUTION OF WORKS AND SERVICES
1 OBJECTIVE
Define and specify the services contained in the Signaling Project of the Highway During
The Execution of Works and Services in Road Engineering Projects.
2 PROJECT PHASES
The project will be developed in a single phase, the Executive Project Phase, and will consist of
signage that will guide users and the construction team regarding the use of the section
in the segments under construction. This signaling will have as its primary purpose the safety of
traffic, in addition to contributing to the increase in productivity of the construction team.
This signage project will follow the recommendations of the Signage Manual.
Works and Emergencies, from DNER, also observing the Brazilian Traffic Code,
as far as it fits, and it will consist of signaling devices with the following objectives
main:
a) Notify, with the necessary advance notice, the existence of works ahead and the situation in
runway
b) Regulate the speed and other conditions for safe circulation along the
works;
c) Channel and organize the flow of vehicles near the construction site, in order to avoid movements
conflicting, reduce the risks of accidents and minimize congestion;
− Warning signs;
− Regulatory signs;
− Informative signs;
− Horizontal signaling;
IS-224 - Service Instruction for the Signaling Project of the Highway During the Execution of the Work
Basic Guidelines for the Development of Highway Studies and Projects 376
4 PRESENTATION
The signage project for the highway during the execution of the works and services will be
apresentado no Relatório Final do Projeto de Engenharia a que corresponde, e constará
de:
FINAL REPORT
IS-224 - Service Instruction for the Signaling Project of the Highway During Construction
Basic Guidelines for the Preparation of Road Studies and Projects 377
ANNEX B25
IS-225 - SERVICE INSTRUCTION FOR PROJECT OF
PAVING (RIGID PAVEMENT)
1 OBJECTIVE
Define and specify the services contained in the Paving Project, Pavements
Rigid, in Road Engineering Projects.
At this stage, the project conception will be defined, consisting of the sizing.
preliminary and structural solutions of the pavement, subject to technical-economic analysis. The
the pavement project at this stage will also provide the approximate quantities that
allow to quote the different services that compose it.
b) definitive establishment of the materials that will form the pavement structure;
4 PRESENTATION
The presentation of the paving project, with rigid pavement, will be done as follows
form:
At this stage, the presentation of the project will take place through the Basic Project Report.
Engineering it corresponds to, consisting of explanatory text and drawings of the solutions
proposals, as detailed below:
BASIC REPORT
The presentation of the Pavement Project, rigid pavements, in the Project phase
The executive summary will be included in the Final Report of the corresponding Engineering Project.
understanding the following volumes:
FINAL REPORT
Format
Volume Discrimination / Subject
Printing
Minute
Definitive
Project Report
− Project design;
1 A4 A4
− Discrimination of all services, quantities, and distances of
transport
Execution Project
− Summary table containing the quantities and distances of
transport of the various materials that make up the structure of
pavement
− Distribution chart of materials and layer thicknesses,
according to the model recommended by DNIT;
− Cross-section type drawings, in cut and fill, of the
2 runways, shoulders, accesses, and areas of A1 A3
installations for highway operation;
− Detailed plan of each occurrence with 1m contour lines
a 1m, indicating the location in the section, with precise tying
in relation to the highway axis;
− Positions of drilling holes, exploration area, and summary
the physical characteristics of the material;
− Other drawings that elucidate the project
Justifying Memory
− Justification for the detailed alternatives approved in
3 A4 A4
project
− Calculation memory for pavement sizing
Geotechnical Studies
− Summary tables of trials;
3A A4 A4
− Survey bulletins of material occurrences;
− Substratum survey bulletins
Budget and Execution Plan
− List of services to be performed;
4 − Cost of services; A4 A4
− Physical and financial schedule;
− List of minimum equipment
ANNEX B26
IS-226 - SERVICE INSTRUCTION FOR AIRPHOTOGRAPHIC COVERAGE FOR
HIGHWAY ENGINEERING PROJECT
1 OBJECTIVE
Define and specify the services of Aerial Photography Coverage for Projects of
Road Engineering.
2 SERVICE PHASE
The Aerial Photographic Coverage will be executed in a single phase, the Basic Project phase.
being composed of:
a) carrying out flights that allow for the obtaining of vertical photographs of the areas
flown over, in order to allow stereoscopic vision of the entire terrain to be
aerially covered, at a scale of 1:20,000, generically, or in
any other scale if defined in the 'specific indications' of the notice. In
In principle, during the execution of this flight, the width of the strip should not be greater than 1/4 of
its length between two mandatory passing points;
b) paper photographs originating from contact copies of the negatives subject to the flight;
e) photographic copies;
The slides will, in principle, cover the entire length of the section in the width of the lane.
The flights for taking photographs will be carried out with aircraft that have
equipment that ensures to satisfy, at least, the following conditions:
a) Service ceiling: the aircraft used must have a service ceiling compatible.
with the altitude necessary to obtain the photographs at the desired scale.
b) Flight autonomy: the aircraft must have autonomy that ensures the
full use of a 'blue sky' day, for a period no less than 6 hours.
c) It is recommended to use the NAVSTAR GPS - Navigation Satellite Using Time And
Ranging Global: satellite-based system to provide 3D position and
time for receivers on board the aircraft (the system works with 21 satellites
IS-226 - Service Instructions forAerial Photography Coverage for Road Engineering Project
Basic Guidelines for the Preparation of Road Studies and Projects 381
main and 3 reserves, covering a network covering any land point with 4
satellites). Like traditional navigation equipment, the
GPS receiver microprocessor provides pilots with complete information about the
navigation and the positioning of the aircraft. In this procedure, the positioning
The aircraft's position will be provided to air traffic controllers via GPS.
satellite, and no longer by radar network.
d) Aerophotogrammetric equipment: it must include a photogrammetric camera,
properly calibrated, from a reputable manufacturer and that in the general technical consensus, is
considered free of distortion, with high resolution capability, having all the
accessories that allow for the automatic capturing of photographs, along with their
optical axis as close to vertical as possible. The photographs should contain records of
altitude, data, time and numbering.
The flight must be carried out on lines whose directions are parallel to that defined by
ideal guideline of the highway between two mandatory passage points, with maximum detour
regarding this direction of 5º (five degrees).
Incline of the airplane - The negatives should be removed, preferably, with the axis of
aerophotogrammetric camera in the vertical position. Negatives with a will be refused
tilt (angular deviation of the axis of the aerophotogrammetric camera in relation to the line
defined in the technical terms of astronomy as the zenith nadir that passes through the center
optic of the aerophotogrammetric camera at the moment of exposure) greater than 3º for each
photography is an average of 2nd in ten successive photographs.
The rotation of the photographs due to drift should not exceed 3º between two photographs.
successive.
IS-226 - Service Instruction forAerial Photography Coverage for Roadway Engineering Project
Basic Guidelines for the Development of Highway Studies and Projects 382
The speed of the airplane, the aperture of the diaphragm, and the exposure time must be
conjugated in such a way as to allow for the taking of high-quality photographic images
and whose drag is below the tolerated limits for the full use of photography
(smaller than the grain of the photographic emulsion).
The flights should be made at altitudes that allow for the obtaining of photographs in
required scales with maximum variations in flight altitudes of 5% in relation to the plan
average of the land.
The exposures of the negatives during the flight must be obtained during daylight hours.
that there are no clouds or areas affected by excessive shadows, leaving it up to discretion
DNIT rejects photos damaged by these elements.
3.3. MOVIES
3.3.1. REVELATION
It will be done according to the instructions prescribed by the film manufacturer, in a manner
to ensure a 'long life' to the negatives.
3.3.2. NEGATIVES
They should present clear details, uniform density, and be free of 'smoke'.
halos, luminous stripes, static electricity marks, water spots or product stains
chemicals, risks, scratches, and signs of wear.
It will consist of a single strip of negatives, uncut, without splice, being all
the negatives resulting from the exposure of the same chamber. Each end of the roll
The film must have a minimum length corresponding to five exposures before.
from the first and then from the last useful photograph of the roll.
When the same film contains photographs taken over more than one day, those
regarding different days, they should be highlighted on the film roll by interval
corresponding to a minimum of five exhibitions in 'white'.
IS-226 - Service Instruction forAerial Photography Coverage for Road Engineering Project
Basic Guidelines for the Preparation of Road Studies and Projects 383
The photographic paper to be used must be from a reputable manufacturer, semi-matte, of weight
double, and the emulsion allows for the printing of all the details recorded on the negative.
3.4.2. DEVICE
The film used in the execution of the device must be from a reputable manufacturer with the
next characteristic of stability and dimensions: the differences due to contraction and
expansion measures in the device in any direction, after processing and
drying should not exceed 1:1200. Flat, smooth glass can be used.
parallels, as a basis, as long as it meets the aforementioned stability requirement. The
The emulsion should allow for the printing of all the details recorded in the negative.
3.5. SLIDE
The relative photo indices for the contracted services will be presented in a defined form.
by DNIT and reduced scale for1On a scale of contact copies. The assembly of
The photo index will be such that the northwest corner of each photograph is left exposed.
IS-226 - Service Instruction forAerial Photography Coverage for Road Engineering Project
Basic Guidelines for the Preparation of Road Studies and Projects 384
Each photograph will carry a label with its number printed and easily
legible to the naked eye on the photoindex scale.
The photographs that interest more than one board must, necessarily,
appear in the photo indices of each of the boards.
The negatives of the photoindices, just like the positive copies of them, will receive
laboratory treatment that prevents the occurrence of defects due to manipulation
inadequate.
The names of the municipal headquarters and the main geographical features will be announced.
our photoindices.
3.6. MOSAIC
They will be made using all the consecutive photos in semi-matte, assembled
in rigid and thin material, uncontrolled and as follows:
a) The shape and size of each board will be specified by DNIT, according to the
shape and size of the area.
c) The centers of the photographs used in the mosaic will be marked by means of
crosses of 1 cm by 1 cm.
e) Mark an arrow indicating true north, in a shape and location to be defined by the
DNIT.
f) The copies used in the making of the mosaic will be the same ones used in the
photoindex assembly.
g) All known and identifiable toponymy in the photographs will be included in the mosaic, by
letters in a type to be defined by DNIT.
IS-226 - Service Instruction forAerial Photography Coverage for Road Engineering Project
Basic Guidelines for Preparing Road Studies and Projects 385
of the leaves, apply 'masks' with margins, wording, and position to be defined by
DNIT.
When necessary, the contractor will present a photogrammetry quality test for each
film reel. For these tests, slides from a "suit" of negatives will be used,
allowing to verify in a refund device the relative orientation of a pair and if the
transport to the neighboring pair is processed regularly. These devices will be delivered
to DNIT, along with the written opinion of the test results, mentioning the
used device.
4 PRESENTATION
BASIC REPORT
IS-226 - Service Instruction forAerial Photography Coverage for Road Engineering Project
Basic Guidelines for the Preparation of Road Studies and Projects 386
ANNEX B27
IS-227 - SERVICE INSTRUCTION FOR AEROPHOTOGRAMMETRIC REFUND
FIELD SUPPORT FOR ROAD ENGINEERING PROJECT
1 OBJECTIVE
Define and specify the services of Aerophotogrammetric Restitution and Field Support
for Road Engineering Projects.
2 STUDY PHASE
The aerial photogrammetry restitution will be carried out in a single phase, the Project Phase.
Básico.
IS-227 - Service Instruction for Aerophotogrammetric Refund and Field Support for Road Engineering Project
Basic Guidelines for the Development of Road Studies and Projects 387
f) Use of GIS - Geographic Information System that allows for the use of
compression technology in file structures.
a) Sensitivity of the tubular level of the alidade of 20"/2 mm (variation of 20" for a
displacement of the heating bubble by 2 mm;
b) Direct reading of 1" (one second) of arc on the lines, horizontal and vertical;
c) Increase of the image through the objective by at least 28 times. In addition, it will be
employee signaling using heliotropes, or another similar system that ensures
desired aiming and the precision required for the implementation of the polygon
main planimetric.
Distance meters operating in any range of the electromagnetic spectrum will be used.
since they have nominal accuracy above: E = ± (1.5 cm + 4 x 10-6D)
Enable the measurement of the sides of the main polygon (PP) in just one run.
Proceed with the meteorological readings of pressure and temperature (dry and wet) to define
the refractive index. They should be obtained with instruments compatible with the precision
of the measurement system.
These devices combine, in a single unit, the measurement of angles and distances,
presenting advantages over traditional equipment regarding collection,
storage, processing, importation and exportation of data collected in the field.
placed over the target object, returning by reflection and exciting the sensors of the
same generating source.
− The calibration of electronic distance measuring devices must be carried out, both for
theodolites and levels, as for Total Stations through the use of the Standard
13.133.
The topographic area to be mapped for the road project preliminary design has been chosen.
A planar polygon should be implemented on the site within this area.
called principal planimetric polygon (PP) having the following characteristics
techniques:
a) Measurements of the sides of the polygonal (PP) will be approximately 10 km, tolerated
sides greater than 5 km and less than 15 km.
b) The polygonal (PP) must be tied to first-order vertices of the basic network, being
that the starting vertex and the destination vertex must be different.
f) The vertices of the polygonal (PP) should, in principle, be installed within the range.
to be mapped, of the topographic surface and out of the offsets line.
g) The weather conditions (pressure and temperatures: humid and dry) should be
verified and noted in both stations before and immediately after the
readings, with necessary criteria to ensure the required accuracy in the polygon.
h) For the treatment of the sides of the polygon (PP), the altitudes of the vertices may be
determined by trigonometric leveling. The zenith observations should be
reciprocal and simultaneous.
IS-227 - Service Instruction for Aerophotogrammetric Refund and Field Support for Road Engineering Project
Basic Guidelines for the Preparation of Road Studies and Projects 389
The vertices of the polygon (PP) will be monumented. The identification plate of the
vertices should be circular, with a radius of 3 cm, made of brass or bronze, placed on a base
of concrete, with defined dimensions. When convenient, the sheets of
identification will be implemented directly on permanent buildings. A
Registration on the board must contain: Ministry of Transport, protected by law, BR-
no... polygonal (PP) DNIT.
UTM Coordinates;
Executor's name;
Sketch of the location and type of vertex. The best path to the vertex will be indicated.
and a compass, indicating, approximately, the north.
l) Calculation: the vertices of the polygon will have a double coordinate system, namely:
In the final drawing, use the grid of the local topographic coordinate system.
IS-227 - Service Instruction for Aerophotogrammetric Refund and Field Support for Road Engineering Project
Basic Guidelines for the Preparation of Road Studies and Projects 390
a) Sensitivity of the tubular level of the alidade of 20"/2 mm (variation of 20" for a
bubble displacement of 2 mm;
b) Reading of 1" (one second) of arc in the horizontal and vertical lines;
E = ± (2 cm + 5 x 10-6D)
They should allow for the measurement of the sides of the secondary polygon (PS) in just one
lance.
The meteorological readings of pressure and temperatures (wet and dry) to define the index
of refraction, will be obtained with instruments compatible with the precision of the system
measurement.
a) The measures of the sides of the secondary planar polygon (PS) will be 1 km,
however, sides greater than 0.5 km and less than 2 km will be tolerated.
IS-227 - Service Instruction for Photogrammetric Refund and Field Support for Road Engineering Project
Basic Guidelines for the Preparation of Road Studies and Projects 391
– Angular closing error E = 8" n, where n is the number of vertices of the polygon
(PS) which in principle should not be greater than twelve.
f) The vertices of the polygonal (PS) should, in principle, be placed within the range.
to be mapped and out of the offset line.
h) For the treatment of the sides of the polygon (PS), the altitudes of the vertices may be
determined by leveling with trigonometry. The zenith observations should be
reciprocal and simultaneous.
k) Observation record: in the same format described for the polygonal (PP).
c) Addition constant: 0.
IS-227 - Service Instruction for Aerophotogrammetric Refund and Field Support for Road Engineering Project
Basic Guidelines for the Preparation of Road Studies and Projects 392
The topographic area to be mapped for the preparation of the road preliminary project has been chosen,
A geometric leveling line must be implanted on the ground, within the strip.
with the following technical characteristics:
a) Range of the shots: In favorable terrain, the shots can reach up to 200 m,
that is, views of up to 100 m ahead and behind;
b) The bids must be measured using the plumb lines of the level;
d) A preliminary calculation should be made in the field to verify if the results are
within the tolerance;
− Name, BR;
− Degree of Precision;
− Quota;
− Name of Executor;
− Sketch of the location and type RN. Indicate the best route to the RN.
appropriate notebooks where the names of the operators and number of the will also be recorded
instruments used, the date and time of the observations. The records in the notebooks of
fields must not be scratched or erased. Incorrect annotations must be
scratches.
3.5.1. PLANIMETRY
The chosen points for planar support for the restitution must be perfectly
defined and identified in the photograph.
The planimetric and photogrammetric points will be obtained from the polygonal (PP) or from the
polygonal (PS).
The planimetric displacement of the real position of the photographic point in the field
In relation to the nearest basic planimetric support point, it should not exceed 30 cm.
The planimetric displacement of the real position of the aerotriangulated photogrammetric point
after the compensation in relation to the nearest basic planimetric reference point,
must not exceed 50 cm.
3.5.2. ALTIMETRY
Whenever possible, the photogrammetric altimetric points will coincide with the points.
planimetric. Double support section.
c) The photogrammetric altimetric points will be obtained from the level reference of the
basic leveling.
IS-227 - Service Instruction for Aerophotogrammetric Restitution and Field Support for Road Engineering Project
Basic Guidelines for the Preparation of Road Studies and Projects 394
f) The quota assigned to the altimetric photogrammetric point in the field should not exceed ±
30 cm of the geometric transport quota, starting from the highest level reference
next.
g) The quota assigned to the aerial triangulated altimetric photogrammetric point must not exceed
from ± 50 cm to the geometrically transported level, starting from the lowest reference point
next.
b) For the copies (material): plastic film of the polyester type or cronaflex may be used.
f) The contour lines should include the mesh of the flat coordinate system.
adopted in the project. See subsection [Link] - Calculation.
IS-227 - Service Instruction for Aerophotogrammetric Refund and Field Support for Road Engineering Project
Basic Guidelines for the Development of Road Studies and Projects 395
The altimetric representation will be done using contour lines spaced every 5 meters.
They will be quoted vertically in cabinets through photogrammetric equipment, the
following points:
Notable points of highways and railways, on the main streets of the city, if any,
in areas where the contour lines are spaced farther apart from each other
of 8 cm in steriminute;
m) Altimetry - 90% of the altimetric levels plotted on the topographic maps should not have
error greater than ½ of the interval of the contour lines, and the remaining 10% should not have
error greater than the interval between the contour lines.
a) The names of the cities, towns, villages, and waterways in general will be indicated,
railways, geographical accidents, that are necessary. Will still be recorded.
the numbers of federal and state highways, system coordinates, landmarks
planimetric and level references (LR);
b) The channels and ditches, whose average width in the stereominute is 1 mm, will be
represented by two spaced lines, indicating the correct position of the two
margins;
IS-227 - Service Instruction for Aerial Photogrammetry Refund and Field Support for Road Engineering Project
Basic Guidelines for the Development of Highway Studies and Projects 396
Each stereo-minute will contain the title in the size and position assigned to it by the
DNIT. This title should include: the name of DNIT, the name and node of the project, the date of
refund, the date of the photographs taken and the name of the executing company.
These widths of restitution strips will be increased according to the need for
project in the locations of intersections, crossings of urbanized areas, river crossings and
other locations that the preliminary study indicates.
4 PRESENTATION
The presentation of the aerophotogrammetric restitution will be made in the Basic Project Report.
of Engineering to which it corresponds, as indicated below.
BASIC REPORT
IS-227 - Service Instruction for Aerial Photogrammetric Refund and Field Support for Road Engineering Project
Basic Guidelines for the Development of Road Studies and Projects 397
BASIC REPORT
a) The names of cities, towns, small villages, and the hydrology in general should be indicated,
railways, geographical accidents that are necessary. They should still be
registered the numbers of federal and state highways, the coordinates of the system
of coordinates, the planimetric markers and the level references (RRNN).
b) Channels and ditches with an average width of one millimeter should be represented by
two spaced lines, indicating the correct position of the two margins.
c) The contour lines should be drawn with clear solid lines and
different, except in areas of dense vegetation where the ground cannot be seen or
is covered by rocky outcrops or shadows. In these cases, the contour lines
they should be represented by dashed lines. For every five contour lines,
a master curve should be highlighted by a line stronger than the other four
intermediate and should be numbered according to its elevation quota.
d) Each stereominute must contain a title in the size and position that it is
designated by DNIT. This title should include: the name of DNIT, the name and number
of the project, the date of the refund, the date the photographs used were taken and the name
from the executing company;
IS-227 - Service Instruction for Aerophotogrammetric Refund and Field Support for Road Engineering Project
Diretrizes Básicas para Elaboração de Estudos e Projetos Rodoviários 398
APPENDIX B28
IS-228 - SERVICE INSTRUCTION FOR PROJECT OF
Footbridge for pedestrians
1 OBJECTIVE
Define and specify the services included in the Pedestrian Bridge Project in
Road Engineering Projects.
It will consist of the project design, including the execution of preliminary studies for the
location and feasibility of the implementation of the footbridge, and geotechnical studies,
carried out in the project area, and preparation of a plan-altimetric project, containing
dimensioning and geometric treatment of all intervening elements.
The following activities will be carried out:
Assembly of the project conception, which will be directed towards the induction of pedestrians in
use of the walkway. Therefore, it is relevant to address the following points
fundamentals:
b) favorable location of the footbridge, exerting real attraction on the main flow of
pedestrians;
e) consider the provisions of the ABNT NBR 9050 Standard - Accessibility for People
Carriers of Disabilities to Buildings, Furniture Space and Equipment
Urban
The determination of the project location for the footbridge will result from preliminary studies.
supported by a methodology subject to DNIT approval. These studies must,
above all, promote the carrying out of topographic and cadastral surveys, the application
of statistical analysis processes and measurements along the road segment
considered.
3.1.3. DETAILING
The following types of structural construction elements will be adopted in the project.
pedestrian overpass
overlapping walkways
The support structures of the ceiling (substrate of the layers of the flooring) and containment
two lateral thrusts will be executed in concrete or steel. In the internal coating
apply masonry with mortar.
For access to the walkways, solutions that preferably utilize will be adopted.
rampas com inclinação suave, solicitando pouco esforço do pedestre. Será admitida em
certain situations, although not advisable, access by ladder.
[Link]. LIGHTING
[Link]. FLOORS
The meetings of the superstructure of the overhead walkways with the ramps or stairs
access must always occur with a minimum setback of 10 m.
starting from the outer edges of the shoulders, on the sides of the road body platform.
Similarly, the intersections of the accesses with the underlying walkways will occur.
always with the same minimum spacing (indentation) of 10 m from the outer edges
of the shoulders, on both sides of the roadway platform.
The area adjacent to the project site must be fenced with wire, with a height
minimum of 2 m, fixed next to the outer edges of the shoulders, with an extension of
at least 20 m on each side of the longitudinal axis of the work, leading the pedestrian to
crossing the walkway.
overhanging walkways
Superstructure: it should be designed in cantilever, with the pillars embedded in
points of the land at least 1 m away from the outer edges of
berths.
Central median: on duplicated highways, the pedestrian bridge should be developed without
interruptions, continuously and superimposed on the central median, do not
admitting independent sections with access to the same.
Distance between two walkways: the minimum distance to adopt between two
Pedestrian walkways should be 200 m.
The execution project of the work must include the drawings, plans, profiles, and also the
cross-sectional and typical sections, in order to ensure perfect visualization of the solution
structural of the pedestrian bridge project.
At this stage, the detailed project in plan and profile, the sections should be included.
transversal, including sizing and treatment of all elements
geometric, the structural constructive elements, the protective elements for
pedestrian-user, the elements related to sidewalks, curbs, gutters, storm drains,
drains, fences, blocking wires, lighting and signaling elements, and
still the typical sections of pedestrian accesses to the walkway.
4 PRESENTATION
The presentation of the Project, at this stage of the Basic Project, will be made through the
Basic Report of the Engineering Project to which it corresponds, composed of the volumes:
BASIC REPORT
Report /
Memory Descriptive text of the project conception and studies
1 Justification preliminaries for the choice of location and feasibility of the A4
of the Project implementation.
Basic
At this stage, the presentation of the project will be made through the Final Project Report.
Engineering to which it corresponds, consisting of the following volumes:
FINAL REPORT
ANNEX B29
IS-229 - SERVICE INSTRUCTION FOR THE PREPARATION OF STUDIES OF
ECONOMIC VIABILITY OF ROADS (RURAL AREA)
1 OBJECTIVE
Define and specify the services for the execution of Economic Feasibility Studies
Highways (rural area) to be developed in the Technical Feasibility Studies
Highway Economics.
2 STUDY PHASE
They will be carried out throughout the Preliminary and Definitive Phases of the Feasibility Studies
Technical and Economic of Highways, according to the provisions in Basic Scope EB-101-
Preparation of Technical Feasibility Studies and Preparation of Highways.
3 PREPARATION OF STUDIES
The studies to assess the economic feasibility, in this Preliminary Phase, will include the
following services:
Carry out a survey of the area to be served by the highway aiming at:
a) Definition in conjunction with the traffic studies of the traffic zone system a
to be adopted;
b) Analysis of the existing situation (climate, soils, demographic data, activities
economic, local production, productivity, markets;
c) Preliminary analysis of the economic potential of the region, outlines, and characteristics
alternative functions for the highway;
IS-229 - Service Instruction for the Economic Feasibility Study Project of Highways (rural area)
Basic Guidelines for the Preparation of Road Studies and Projects 405
Environmental Studies must characterize the environmental situation of the area of influence of
enterprise in physical, biotic, and anthropic aspects, aiming for knowledge
from the region before the implementation of the project, serving as a reference for
evaluation of the environmental impacts arising from the works and operation of the highway, and of the
environmental liabilities.
The Environmental Diagnosis will identify and analyze the possible impacts.
environmental, and identified the environmental liabilities, of the alternatives, at a preliminary level.
In selecting the alternatives, the privileged areas must be identified and weighed.
by law (Biological and Indigenous Reserves, Conservation Units, etc.)
During the preparation of the environmental studies, activities will also be developed.
following:
c) verification with the competent authorities of the existence of restrictive factors to use
solo only along the highway (urban areas and Conservation Units);
b) Calculation of benefits;
c) Definition and calculation of implementation costs;
IS-229 - Service Instruction for Economic Viability Study Project for Highways (rural area)
Basic Guidelines for the Preparation of Road Studies and Projects 406
Depending on the circumstances and the methodology adopted for traffic projections,
the benefits can be calculated from:
− increase in the value of properties located in the influence zone of the highway;
− increase in revenue;
− social evolution of the community, the redistribution and expansion of the urban population, and
others.
The most commonly used processes for economic evaluation of road projects in areas already
developed are those based directly on the quantification of the reduction in costs
of transportation. In developing regions, economic analysis becomes necessary.
based also on indirect benefits.
The definition of the benefits will depend on the data available in each case and the
relative importance of the functions that the highway will perform: to serve the existing traffic,
compared to the expected results in the opening of new areas, etc. At the same
time, carefully analyze the possibility of double counting benefits to
define them and calculate them.
For example:
a) The benefits from the generated traffic should not be added to the net value of the
increase in local production, since they are equivalent quantities;
b) The benefits resulting from the increase in the value of properties located in the area
of direct influence from the highway, only the benefits of
reduction of operational costs and time for long-distance traffic that have
both the destination and origin were outside this zone;
IS-229 - Service Instruction for the Project of Economic Viability Studies of Highways (rural area)
Basic Guidelines for the Preparation of Road Studies and Projects 407
a) Benefits to users
The benefits will be calculated based on the comparison of the operational costs of
vehicles, travel time, and cost estimates of accidents for each alternative,
in the situation without the road connection or with the proposed improvements. When one
to calculate these benefits, consider the following aspects:
– Explain and justify the assumptions made for accident costs through the
comparison with studies for highways with similar characteristics.
The increase in security is presented as an important factor in the design of new
highways or improvements. However, it is doubtful that the reduction in volume and in
the severity of accidents can be quantified with the level of detail of
other benefits. Both for the calculation of benefits and for costs, one must
study the need and possibility of using 'ghost prices' (shadow
prices):
• Calculate the benefits for the year of opening, intermediate year, and horizon of
project (usually 20 years after the opening of the highway), with the benefits
for the intermediate years estimated by interpolation. In the case of loading
from traffic to the project horizon, ensure the exclusion of benefits
resulting from traffic that exceeds the absolute capacity of the roads;
IS-229 - Service Instruction for Economic Viability Study Project of Highways (rural area)
Basic Guidelines for the Preparation of Road Studies and Projects 408
When calculating the benefits of economic development, take into account the
following aspects:
Benefits derived from the increase in the value of agricultural production. Analyze the
climatic conditions and soil of the region; current production, productivity, and prices;
future demand for local production; other existing plans for the region
(energy infrastructure, irrigation, storage) since the highway
it will probably not be a sufficient condition for development
local.
The investment costs of the economic analyses will be determined in such a way as to
obtain
The necessary investment for each alternative must include the construction costs.
(earthworks, drainage, common and special structures, paving, relocation
IS-229 - Service Instruction for Economic Feasibility Study Project of Highways (rural area)
Basic Guidelines for the Preparation of Road Studies and Projects 409
The final stage of the economic analysis will be the comparison between the benefits of each
alternative and the estimated costs for implementation. It involves the updating of benefits
and some costs, using capital opportunity rate. Calculate the absolute relationship
B/C (Benefit/Cost), the incremental relationships and the internal rate of return.
Present a sensitivity analysis that considers the effect on the final result of the
variations in the main parameters, such as: traffic estimates, the allocated value
the time of users, the opportunity cost of capital, and the construction costs.
The methodology for economic analysis developed by the World Bank in cooperation
with government agencies from various countries, with significant participation from
Brazil gave rise to the HDM System and its derivatives HDM Manager and modernly
HDM-4 Highway Development & Management is accepted as satisfactory for the
objectives of these studies.
4 PRESENTATION
The presentation Economic Feasibility Study of Highways will be made in the Reports
Preliminary and Definitive Studies of Technical and Economic Feasibility of the Highway
to which it corresponds.
IS-229 - Service Instruction for Economic Viability Study Project of Highways (rural area)
Basic Guidelines for the Preparation of Road Studies and Projects 410
ANNEX B30
IS-230 - SERVICE INSTRUCTION FOR STUDIES
TRAFFIC IN URBAN AREAS
1 OBJECTIVE
2 STAGES OF STUDIES
a) Preliminary;
b) Definitive.
a) Data collection;
b) Functional classification of the existing road network;
d) Traffic projections;
– current, obtained from the master plans and other available sources;
The traffic study in the definitive phase will develop according to the conclusions and
recommendations from the study in the preliminary phase, subject to prior approval from DNIT, and if
will consist of the following:
a) collection of existing data on the metropolitan area of interest for the project,
including maps, plans, studies, and traffic data;
d) collection and compilation of any other data deemed valuable for execution
adequate of the studies.
This phase aims to group all urban roads in the metropolitan area into systems,
according to its function, in order to establish the common planning base and establish the
function that the runners under analysis and the proposed connection will have in the system as a
everything, as indicated below:
The work in this phase will consist of the development and study of technical alternatives.
for the proposed connections and accesses. These alternatives may cover both the
variations in the layout as in the physical and operational characteristics of the roads and arteries
of access. They will take into account the road plans and collective transportation studies already
prepared or in preparation and considered existing in the analysis horizon.
3.2.4. DEVELOPMENT OF THE MATHEMATICAL NETWORK RELATED TO THE ROAD NETWORK UNDER STUDY
At this stage, the mathematical network corresponding to the road system will be prepared in
study, specifying the nodes and the connections (links). For each of these links, there will be
researched the physical and operational characteristics necessary for the stages of
network loading.
Use simulation techniques compatible with the complexity of the networks under analysis and
that take into account the drainage capacity in the links studied and the
Characteristic of fixed itineraries of the public transport system, the data for the year-
the base and the projections of the interzonal movements for the project horizon will be
allocated to the networks that incorporate the alternatives under analysis. This will enable vision
approximate future development of networks, the need for modifications, and the
role of proposed long-term improvements.
Analyze and compare the loading results of the different networks, based on the
relations volume/capacity, in traffic flow charts, in average speeds of
route, in the delays caused by the crossings of the nodes, and service levels for the
road networks. Primarily considering technical assessment and comparison.
Probably, as a consequence of these evaluations and comparisons, it will be possible to eliminate most of it.
the alternatives, and leave for later analysis those that are remarkably similar.
Based on the traffic volume projections, the work in this phase aims to determine
the following:
b) number of lanes required for works (including weaving lanes, branches, and
others);
4 PRESENTATION
In this Preliminary Phase, the Traffic Studies must be included in the Preliminary Report.
of the Engineering Project to which it corresponds, consisting of:
PRELIMINARY REPORT
The presentation of the traffic study, at this stage, will be done through Volume 1 of
Basic Engineering Project Report to which it corresponds, as detailed
to follow
FINAL REPORT
ANNEX B31
IS-231 - SERVICE INSTRUCTION FOR THE DEVELOPMENT OF PLAN STUDIES
FUNCTIONAL WITH A VIEW TO IMPROVING CAPACITY AND SAFETY OF
HIGHWAYS IN DUPLICATION PROJECTS
1 OBJECTIVE
The Studies of the Functional Plan aimed at Improving Capacity and Safety
Highways in Duplication Projects must be developed with the aim of
establishment of a model that meets current and future traffic requests to
long of the highway, based on criteria for the hierarchization of road structures that
they behave according to different traffic systems, a direct result of the types and intensities
land use.
The studies subject to this Instruction must be carried out in a single phase, throughout
from the Preliminary Phase of Engineering Projects for Highway Duplication, of
compliance with the Basic Scopes EB-109 and EB-110.
a) On-site recognition;
b) Collection and analysis of existing data;
c) Aerophotogrammetric studies;
d) Guidelines of the Functional Plan;
h) Programming of priorities.
IS-231 - Service Instruction for the Project of Functional Plan Studies Aimed at Improving Capacity and Safety
Highways in Duplication Projects
Basic Guidelines for the Development of Road Studies and Projects 415
The section subject to study must be preliminary and exhaustively observed 'in loco' by
Head of the Functional Plan Team, who should preferably use the highway.
as if it were one of your usual users, under different conditions throughout the
day (or the period of seasonality), aiming to experiment and perceive the real conditions
of operation offered by the highway and the adjacent road system, and to know better
the causes of the conflicts and problems that generated the need for the realization of the
studies.
This phase aims at a better understanding of the problem that is being sought to be solved with the
execution of the Functional Plan.
Elements and data regarding the highway and the area under study should be collected.
available in work, studies or projects already carried out, that may be useful for the
characterization of the problems and for the appropriate treatment and development of
later stages.
The elements and data must be analyzed in light of the resulting knowledge (or
that were confirmed) of the phase described in 3.1, for identification and specification of the
data and supplementary surveys, necessary for the quantifications and
dimensions relevant to the Studies of the Functional Plan.
The basic elements that will serve for the execution of the studies and for the presentation
the solutions should be the results of aerial survey services
that should be available at the right time.
The elements that should be available, preferably in digital form, are the
follows:
In the case of mechanical (manual) development of the drawings, of the set of copies of the
retificação em material poliester cronaflex serão tiradas cópias, as quais serão utilizadas
in field and office work for the plotting of cadastral information and
inventory.
IS-231 - Service Instruction for the Functional Plan Study Project Aimed at Improving Capacity and Safety
Highways in Duplication Projects
Basic Guidelines for the Preparation of Road Studies and Projects 416
The analysis of the conditions of current land use, of future occupation trends of the
areas, the observed traffic patterns and the operational conditions verified in the
ways, will allow a preliminary and comprehensive assessment of the causal relationship between traffic
and the system of occupancy of the areas adjacent to and served by the highway.
This analysis will provide a basis for the detailing of the subsequent procedures.
traffic studies that should be anticipated will be established
in the Basic/Executive Project, and that will be carried out by the designer according to the Instructions
of the Consulting Services Manual for Road Studies and Projects of
DNIT, or instructions formulated by it.
The examination of these elements, coupled with the existing deficiencies, reinforced by the analysis
and the location of critical segments will allow for the identification and description in a panorama
broad and general, of the necessary improvements for the intended increase to be feasible
capacity and safety for the highway, promoted through its duplication.
It is necessary to pay close attention to the differentiation between local traffic volumes (of
small and medium courses), which generally have characteristics of pendular movement, and
that significantly aggravate the operational characteristics of a significant part of the
highways, with special emphasis on the sections that develop within the boundaries
urban
Where these sectors have imposed themselves, as is the case with the mentioned sections, it should be...
to aim at the sorting of the different types and volumes of traffic, through the
hierarchization of different road structures based on the concept of mesh
hierarchized in the region, which will be sought to be translated into a theoretical model.
The application of the developed model to the area under study will allow for the identification and comparison of the
existing structures with hierarchical conditions contained in the model, determining the
guidelines for the necessary adaptations to existing roads (whether they are the road itself
highway or local roads), crossings, existing and/or planned intersections, in the direction
to equip them with conditions compatible with the characteristics of the traffic to be
submitted.
According to the results obtained as stipulated in item 3.4 above, one must-
it will launch, regarding the rectification on the scale 1:2 000, the various alternatives for the Plan
Functional.
On this occasion, in addition to the aspects of hierarchization of the road structures, will be
adequate and/or elaborated the "layouts" of the instructions and proposals for the crossings,
blockages and other devices designed for the road system.
IS-231 - Service Instruction for the Functional Plan Study Project Aiming at Improving Capacity and Safety
Highways in Duplication Projects
Basic Guidelines for the Preparation of Highway Studies and Projects 417
Regarding the access conditions to the riparian areas, possible should be observed
proposed guidelines in programs already implemented aimed at Urban Crossings, which
deverão adaptar-se às condicionantes de melhorias que o segmento deverá possuir. Para
Therefore, the methods of access to the uses related to service will be specified.
road service stations (service posts, restaurants, workshops, bus stops), as well as the
criteria for your location.
Through the analysis of the data collected in each existing access, it will be presented
individualized solution regarding its maintenance or not, or the necessity for its
adequacy and/or reformulation.
As diversas alternativas propostas para o Plano Funcional serão então analisadas, tendo
in view of the choice that can offer the best compatibility in the light of aspects
technical, functional, economic, and operational policy aspects of DNIT.
This last factor relates to certain aspects that may transcend decisions.
purely technical, as is the case with options between the need for large
expropriations or sacrifices of the technical standard.
In order to allow for a comparative analysis of the various alternatives that may be
proposals, quantities will be estimated and costs will be prepared covering the main ones
service items, with the purpose of providing a global idea regarding the cost
of each of them.
In the preparation of costs, prices practiced in the region should be adopted, obtained from
projects prepared and/or recommended by DNIT.
After the analysis, comparison, and selection of the best among the presented alternatives for
The Functional Plan will define the execution priorities of the measures and services.
in the forecasts, recommendations should also be made about the timing of
execution of the same, through technical, economic analyses and evaluations
financial, if applicable.
Such analysis will be substantiated in a general programming to be presented, taking into account
In consideration of all the aspects already discussed, it may be specified, depending on the
IS-231 - Service Instruction for Functional Plan Study Project Aimed at Improving Capacity and Safety
Highways in Duplication Projects
Basic Guidelines for the Development of Road Studies and Projects 418
The presentation of the Functional Plan Studies will be made in the Preliminary Report of the
Duplication Project of the Highway that corresponds.
IS-231 - Service Instruction for Functional Plan Study Project Aimed at Improving Capacity and Safety
Highways in Duplication Projects
Basic Guidelines for the Preparation of Road Studies and Projects 419
ANNEX B32
IS-232 - SERVICE INSTRUCTION FOR PROGRAM DEFINITION STUDIES
FOR CAPACITY AND SAFETY ADJUSTMENT (PACS)
1 OBJECTIVE
Identify and analyze the existing problems in the traffic operating system that
we restrict capacity and/or cause high accident rates in corridors or
urban crossings and the proposal of required solutions as an integral part of projects
of engineering or as special studies in existing roadway.
2 STAGES OF STUDIES
The development of the services will be carried out according to the following sequence:
d) traffic projections;
preliminary studies;
IS-232 - Service Instruction for the Study Project for Program Definition for Capacity and Safety Adjustment (PACS)
Basic Guidelines for the Preparation of Road Studies and Projects 420
traffic research
b) accident data
Raise the critical sections in traffic accidents, as well as rates, indices and
quantities. Obtain the historical series of critical sections in the stretch of highway in
question, verify the completion of work on the subject;
c) complementary data
Obtaining maps and plans that show the road system, with its conditions
the peculiarities;
Planning of land use in the buffer zones of the highway under study;
IS-232 - Service Instruction for Program Definition Study Project for Capacity and Safety Adjustment (PACS)
Basic Guidelines for the Preparation of Road Studies and Projects 421
After analyzing the existing data, the research and surveys will be defined.
necessary complements for the realization of the studies including the following:
a) Traffic counts;
h) Expedited registration of the highway section under study, recording notable points such as
works of art, intersections and junctions, railways, signaling devices and state
of conservation and also, the survey of land use along the stretch
marking relevant locations, schools, health centers, commerce, among others;
n) Volume and route of pedestrians (crossing the road at critical points and bus stops);
IS-232 - Service Instruction for Program Definition Study Project for Capacity and Safety Adjustment (PACS)
Basic Guidelines for the Preparation of Road Studies and Projects 422
u) Direction of circulation;
y) Lighting conditions;
z) Conditions of horizontal and vertical signage; model, cycle, phases, and methods of
control of all traffic light signals;
Type and conditions of the pavement, as well as data on the cross-section, such
such as the width of the track, right-of-way, and number of traffic lanes;
bb) Conditions of the surface texture of the pavement: texture, locations subject to
skidding, aquaplaning, and exudations;
cc) Existence of central median and its width; shoulder, gutter, curb, and sidewalks;
dd) Notable points: schools, shops, hospitals, parking lots, and others;
ee) Intersections and existing junctions in the section of road under study, with the ramps and
access and control devices, such as signaling and others;
Elaborate the single-line diagram of the highway, a schematic drawing in which will be marked
the notable points and registration data.
This stage aims to identify the main problems and observe the causes,
conceiving corrective measures. The analyses carried out based on traffic studies,
they will use universally established methodologies, giving preference to the recommended ones
IS-232 - Service Instruction for the Development of a Program Definition Study for Capacity and Safety Adjustment (PACS)
Basic Guidelines for the Development of Road Studies and Projects 423
a) Seasonal variations throughout the year, the existence of vehicle flow occurrences
atypical, such as holiday periods, public holidays, and festive dates (tourist regions) and
harvest periods (agricultural regions);
d) Obtaining factors that express daily variation, along with annual variation,
also considering the fleet of vehicles. Thus, based on a TMDA (traffic
annual daily average), it will be possible to obtain the hourly volume and the fleet composition for
any time of the year;
e) Identification of the quality of operational conditions throughout the entire day of the
highway, for a period of one year. The office analyses must be confirmed.
for field inspections;
i) Consider the absolute quantities related to each critical section with the objective
to subsidize the other information, creating the collision diagram,
recording types and consequences of the most frequent accidents, among others
information, period (hour, month and day of the week), weather conditions, type of
involved vehicles, and so on;
IS-232 - Service Instruction for the Program Definition Study Project for Adequacy of Capacity and Safety (PACS)
Basic Guidelines for the Development of Road Studies and Projects 424
The diagnosis prepared in the office will be confirmed by the field inspection.
The advantage of early diagnosis is to provide an initial idea about the causes of
accidents. Going to the field is more objective, allowing observation of when and how,
reducing the inspection period and, consequently, the duration of this stage.
The following are some helpful recommendations for the visit phase in
field:
− Observe the traffic circulation, both driving a vehicle and walking on the
segment under study;
− Circular with the vehicle through the section under study several times, some conditions
conditions for the occurrence of accidents are not immediately perceived;
− Choose different locations to study vehicle flow. Details, such as obscuring.
by the light the sun will only be perceived at specific points of the road system;
− Extend the observation periods covering different times (day and night)
and different conditions (good weather or rainy).
b) Operation of the road: respect for signage and traffic rules by drivers,
condition of the signage (vertical, horizontal, and electronic), conflicts between
distinct flows, especially at interchanges and intersections, lateral friction caused by the
local traffic and by the bordering activities in the road flow, operating regimes
undesirable (congestion situations or nearby), lighting efficiency
public, among others.
Once the studies aim for a short-term improvement program, many of the
analyses and conclusions will be based on existing traffic. To reconcile any
recommendations with the other traffic projections made for the project, referring to
to the same or another time horizon (see IS-230: Traffic studies in the area
urban.
Follow the procedures indicated in IS-230, and conduct studies with the aim of
determine future traffic by classifying it based on the vehicle fleet and estimating the
main peak periods.
IS-232 - Service Instruction for the Definition of Program Adjustment Studies for Capacity and Safety (PACS)
Basic Guidelines for the Preparation of Road Studies and Projects 425
IS-232 - Instruction of Service for Project of Study for Definition of Program for Adaptation of Capacity and Safety (PACS)
Basic Guidelines for the Preparation of Road Studies and Projects 426
The objective of this phase is to conceive a range of solutions or minimize the problems.
detected, developing a minimum amount of alternatives, and enabling comparisons
among them.
Prefer low-cost measures, and those that present conditions for implementation.
immediate, highlighting the following:
k) Paving of shoulders.
The alternative solutions will encompass physical and operational measures, such as
related to the following:
IS-232 - Service Instruction for the Definition Study Project of the Program for Capacity and Safety Adequacy (PACS)
Basic Guidelines for the Preparation of Road Studies and Projects 427
e) Runway duplication;
f) Improvement of the radius of curvature;
g) Implementation of superelevation;
j) Others.
These alternatives will be analyzed throughout the study horizon with the aim of
to know how long each solution will maintain initial efficiency, or rather, after how much time
new intervention will be necessary.
The procedure adopted for analyzing the operational conditions in the current situation will be
followed to determine parameters for the study horizon. The methodology
employed in the diagnostic phase will allow comparison based on the same
indicators.
Stage that considers the set of measures and includes the one deemed most appropriate and
viable for implementation.
The solution to the problem may come from a single measure or from a set of them.
choice of the most viable intervention, some issues should be considered, such as
like:
d) Positive and negative impacts on the wild and urban environment and on
local urban planning
e) Duration period of the measures, or the time during which they will remain effective.
Most of the time, it is not possible to reconcile relevant issues, such as mobility and
accessibility. The first refers to road circulation itself, with emphasis
especially in the fluency, safety, and comfort of users, while the second refers to the
IS-232 - Service Instruction for the Definition of Program Studies Project for Capacity and Safety Adjustment (PACS)
Basic Guidelines for the Preparation of Road Studies and Projects 428
ease of entry and exit in the roadway system under study results in very high impedance
large on the first, resulting from the lateral friction caused by the maneuvers of
entry and exit, and the fact of exposing the route to the operational conditions of the system
external roadway, through the exit accesses.
The choice of the solution will be the result of the analyses carried out, such as in the case
the small-scale urban crossings, where long-distance road traffic
should be prioritized, emphasizing the aspect of mobility, to the detriment of the
accessibility. On the other hand, in highly densely populated urban areas, in which the
vehicular flows towards these areas are predominant, the accessibility function
it must be treated specially to the detriment of mobility.
The functional plan covering each problematic location or stretch will be developed.
in detail, being sufficient to demonstrate the physical and operational feasibility of
proposed improvements. It will provide the conceptual basis for the subsequent development of
engineering project of the recommended solutions, at which point estimates will be made of the
costs. Once the plans with the proposed solutions are developed, they will be verified regarding
capacity of the planned services to accommodate both existing traffic and traffic
designed for the project horizon adopted.
The functional plan should illustrate the proposed improvements and include geometry, signaling,
traffic channeling, graphical representation of improvements in service level,
synchronization of traffic lights, implementation of a barrier or electronic speed bump and any
another recommendation necessary for the effectiveness of the proposed measures.
It will be prepared in agreement with the local authorities responsible for conservation.
of the road system and the operation of traffic, in order to achieve a unit of
efforts aimed at solving problems.
After the approval of the selected solution, in accordance with what is stated in item
previous (3.6 - Selection of the Most Suitable Alternative) will be detailed
as recommended in the following methodology:
4 PRESENTATION
The presentation of the PACS should be made in the Basic and Final Reports of the Project.
Engineering for the Rehabilitation of Roads with Low-Cost Improvements, and Project
from Engineering for Road Rehabilitation with Improvements for Adjustment of
Capacity and Safety, to which it corresponds.
IS-232 - Service Instruction for the Project of Studies for the Definition of the Program for Capacity and Safety Adjustment (PACS)
Basic Guidelines for the Preparation of Road Studies and Projects 429
ANNEX B33
IS-233 - SERVICE INSTRUCTION FOR THE PREPARATION OF THE PROJECT OF
ENGINEERING OF PACS TYPE IMPROVEMENTS
1 OBJECTIVE
2 PROJECT PHASES
The final improvement project of the PACS type will be developed in two phases, design phase
Basic in the Executive Project phase, involving:
a) physical improvements;
b) operational improvements;
c) improvements in public transportation;
d) institutional changes.
a) Lane duplication;
f) Regulatory signage;
h) Sense of direction;
Prohibited conversion;
Examples of improvements:
c) Terminals;
− Other measures.
The institutional changes will recommend the procedures and involve others.
organizations or institutions, such as the local municipal government. One can cite, as an example,
the need for a review of planning for the use of land adjacent to the highway, through the
review of authorized accesses, with the purpose of minimizing lateral friction in the flow of
via, or still the need for intervention in the local road system.
Scope Project
Basic
EB-104 Basic Engineering Project for Road Rehabilitation with Low-Cost Improvements
4 PRESENTATION
The presentation of the Engineering Projects for the implementation of the PACS measures will-
It will be in the Preliminary Reports of the Basic and Executive Engineering Projects
for Pavement Rehabilitation with Improvements for Capacity Adjustment
Security.
ANNEX B34
IS-234 - SERVICE INSTRUCTION FOR PROJECT DEVELOPMENT
GEOMETRIC OF HIGHWAYS - URBAN AREA
1 OBJECTIVE
Define and specify the services included in the preparation of the Geometric Design Project.
Highways in Urban Areas.
a) Basic Project;
b) Executive Project.
3 PROJECT DEVELOPMENT
Based on the plans and notebooks of the topographic studies carried out or in the
aerophotogrammetric restitution and, furthermore, using any and all elements, such as
drawings, plans, useful for the work, subject of this instruction, will be executed
the following tasks.
Independent drawings will be prepared showing the typical cross sections, with
all its defined elements, all types of clues included in the project. A
description of the basic characteristics to be defined and elements that will be included in the
drawings as well as the presentation scale.
3.2.2. PLANTS
Based on the information and analyses developed in the preliminary studies, such as
hydrology, drainage, geotechnics, intersection layouts, public services, and others,
Floor plans will be developed indicating all elements of the project.
planimetric.
3.2.3. PROFILES
Longitudinal profiles of all the roads will be graphically elaborated, including the
main alignment, branches, marginal and local roads to be built, relocated or
modified as part of the project.
Definition, based on data and/or conclusions from geotechnical studies, of traffic and
other relevant or applicable, of the basic characteristics of the cross-section of the
types of tracks included in the project. The basic characteristics to be defined include,
but are not limited to:
b) Shoulder widths;
e) Maximum superelevation;
j) Other applicable.
− Drainage structures;
− Other necessary or required data for the complete interpretation of the drawings.
3.3.2. PLANTS
For the project in plan, containing the complete planimetric definition of the project, it will be
a scale of 1:500 has been adopted. However, a minimum scale of 1:2,000 will be acceptable.
for areas without adjacent urban development. The project will be represented on
as plantas topográficas utilizadas e indicará, claramente, todos os dispositivos de
traffic channeling. The plan drawings must indicate at least the following
elements of the planimetric project:
d) Location, stakes and coordinates of the notable points of the horizontal alignment
all tracks and alignments of the fences/walls (PC's, PT's, ST's, TS's, PI's);
external tangents;
– other applicable;
f) Necessary and sufficient planar dimensions for the definition of the works;
h) Coordinates and equality of stakes for all intersections, beginnings and endings of
axes in plan;
change of axis;
defenses;
- fences;
valet
If considered convenient and aiming for greater clarity in the presentation, it will be permitted.
the presentation and planimetric detailing of the elements mentioned above in
drawings aside.
In this case, the drawings will be grouped according to the relevant subject (e.g.
drainage plans, location plans for complementary works). However,
should always be designed in plans whose background includes the geometric project of
via.
For the purposes of the previous paragraph, the indication of any will not be considered sufficient.
two elements above in the profiles, cross sections or linear diagrams
especially prepared, neither in schemes nor in isolated details, without these
sufficient and clear reference to identified elements in the project plans
geometric.
3.3.3. PROFILES
The longitudinal profiles will be developed and designed on the horizontal scale equal to that of
project in plan and with a vertical distortion of 10:1. The graphical representation of the profiles
It will consist of the drawing showing the same section of the road(s) in plan view, being
the sections shown in plan and profile must be exactly coincident. In
longitudinal profile drawings shall contain, at least, the following data and indications:
a) Longitudinal profile of the original terrain in the horizontal projection of the axis that defines the
geometric alignment in plan;
b) Finished grade line at the point of application of the grade, as defined in the sections
transversal types;
c) Graphic location and indication of the stake and elevation of the PIV's, PCV's, PTV's, etc.;
– design speed of vertical curves as a function of the coefficient K and the criterion
of the visibility adopted;
IS-234 - Service Instruction for Geometric Design of Highways - Urban Area
Basic Guidelines for the Development of Road Studies and Projects 438
- levels of the free edges of the pavement when the profile of this is not parallel to
profile of the greide line, presented at the same stakes where the quotas of
grades are indicated;
e) Location and boundaries of current and special works of art, existing and proposed,
about and on the finished grade line, with appropriate identification and indication of
dimensions and more thresholds quotes, surface, and others, in the horizontal projection
of the axis that defines the geometric alignment in plan;
f) Altimetric location of public services that interfere with the layout and their
proposed relocations, with indication of the respective horizontal projection quotas of
axis that defines the alignment in plan;
i) Sill profile of the larger drainage lines parallel to the horizontal axis of the
For this purpose, it is understood that the larger drainage lines are those whose
dimensioning may influence the vertical design of the road(s);
j) Profile and/or water sheet quotas in parallel and transverse drainage works
larger scale. The quotas will be indicated on the horizontal projection of the axis of the road and in the case
of parallel drainage works, at intervals compatible with the provided data
from the hydraulic studies. These data will reflect the criteria used in the study
hydrological.
If it is deemed convenient and aiming for greater clarity in the presentation, it will be
the presentation and altimetric detailing of the above-related elements is permitted
In separate drawings, as long as they always include the basic profile data of the
original land and the finished grade.
Cross sections, for the purposes of this instruction, can be divided into two types, the
to know
a) Common cross-sections
IS-234 - Service Instruction for Geometric Design of Highways - Urban Area
Basic Guidelines for the Preparation of Road Studies and Projects 439
– Indication of:
• axis referred to in the section and its stake;
• areas of the sections in cut and/or fill, to be used in the calculation of the
earthworks volumes;
– Lateral finishing of the sections and adaptation to the adjacent terrain. The sections
common transversals to be prepared must take into account all of the
design elements that affect earthworks, such as: existence or non-existence of
superelevation, ditches, shoulders. Where necessary, the distance between sections
should be reduced.
The purpose of the special cross sections is to illustrate the proposed solutions
in places where the project characteristics require special consideration. Among
others, some of the conditions that may require special sections are
numbered as follows:
Structures and/or complementary works, such as: retaining walls, channels, lines
transmission, containment of adjacent buildings;
The section title should contain the necessary data for correct interpretation.
(stake on the axis, angle in relation to the perpendicular). Eventually, it will be indicated in
plant the situation of the section. The minimum scale for the sections will be 1:200.
4 PRESENTATION
In this Phase, the presentation of the project will be made through the Basic Project Report of
Engineering to which it corresponds, consisting of explanatory text and drawings of the
proposed solutions, as outlined below:
BASIC REPORT
The Geometric Project in the Executive Design Phase will be presented in the Final Report.
of the Engineering Project to which it corresponds, comprising the following volumes:
FINAL REPORT
Format
Volume Discrimination/Subjects Minute Printing
definitive
Project Report
1 A4 A4
- Τproject geometric design
Execution Project
Convention sheet used in the drawings and inclusion of
title page, index page, conventions page, page of
location and articulation sheet of the plants;
-Technical characteristics of the project;
- Plants and profiles at scales 1:5000 (H) and 1:500 (V),
containing:
The profile design of the terrain along the project axis;
2 A4 A3
Project profile design;
The constructive elements of the vertical project;
Indication of the location of special artworks and
currents
Typical cross-section drawings at scales 1:100
1:200;
Interferences with public service networks and possible
rearrangements.
Justifying Memorandum
3 Descriptive and justificatory report of the
A4
prepared
A4
project
APPENDIX B35
IS-235 SERVICE INSTRUCTION FOR PROJECT OF
Urban Road Lighting
1 OBJECTIVE
Define and specify the services included in Urban Street Lighting Projects.
This Instruction applies uniquely and specifically to the Lighting Project of the Streets
Urban, the interconnections, the accesses whose geometric complexity implies in
potential dangers for nighttime operation and other specific locations such as squares of
toll.
2 PROJECT PHASE
The Urban Street Lighting Project will be developed after the final determination and
definitive of all geometric characteristics of the interconnections and access, and of the
other locations to be illuminated, according to aIS-208: Service instruction for
geometric project.
For the execution of the lighting project, a specific study must be carried out to
each interconnection or access, however, the resulting project should present
homogeneous and uniform characteristics for all areas to be illuminated and
obeying where applicable the instructions and project standards (lighting levels,
for example) and constructive (types of boxes, cables, ducts, and others) of the utility company
local.
The project will be presented in special plans, consisting of the geometric design of
various clues and special detail drawings, as applicable.
For the development of the lighting project, the following elements will be determined:
a) location and spacing of the poles - based on the levels of lighting and
required uniformity relations, considering the aspects of maintenance, network
of supply, economy, and security (the placement of poles will not be allowed
on the outer part of curved branches, among others);
b) mounting heights - a function of efficiency and economy, levels of illumination and
required uniformity relations, maintenance, blinding characteristics of
lamps, and others;
In choosing the type of lamp, observe the chromatic homogeneity between the lighting.
the interconnected roads and within the road itself.
– branches and accesses: gradually varying the level of illumination of the main road
up to the level of the interconnected street(s) or road(s);
c) Uniformity relations
E/ E min < 3
In what:
E: Average horizontal illumination (lux).
interest in the sale of the equipment does not interfere with the quality of the project, in
efficiency, and whether it will be suitable for local characteristics and objectives.
4 PRESENTATION
The presentation of the Urban Lighting Project will be done in the Final Report
of the Engineering Project to which it corresponds, consisting of:
FINAL REPORT
Format
Volume Discrimination/Subjects Minute Printing
definitive
Project Report
1 A4 A4
-Text, chapter Lighting Project.
Execution Project
Plants at an appropriate scale, containing, in addition to the project
planimetric of the road(s), the location of the poles and networks of
distribution.
Drawings and details, indicating:
Type and details of the light fixtures and bulbs;
2 A1 A3
Type and construction details of assembly and anchoring
two posts;
The detailing of the interferences; Others of value in
correct and complete definition of the project, related to
niches, boxes, ducts, cables, circuits, and others.
-Service notes.
Justifying Memorandum
3 A4 A4
Calculation memory
Cost Estimate
4 A4 A4
Costs
ANNEX B36
IS-236 - SERVICE INSTRUCTION FOR TRAFFIC STUDIES OF THE PROJECT
EXECUTIVE OF ENGINEERING FOR THE CONSTRUCTION OF LOCAL ROADS
1 OBJECTIVE
The present instruction aims to define and specify the services contained in the
Traffic Studies in Executive Engineering Projects for Highway Construction
Neighbors.
2 STUDY PHASE
The Traffic Studies will be conducted in a single phase, the Preliminary Phase and of
Basic Project.
3 Preparation of studies
a) Traffic volume;
b) Origin and destination;
c) Weighing.
The section must be identified based on the latest version of the Plan.
Nacional de Viação – PNV.
IS-236 - Service Instruction for Traffic Study Project for Executive Engineering Projects for Construction of
Local Highways
Basic Guidelines for the Preparation of Road Studies and Projects 446
Based on the results of the processing of the existing data, the following will be done:
a) traffic allocation;
4 PRESENTATION
The Traffic Studies will be presented in the Basic Report of the Executive Project of
Engineering to which it corresponds, thus discriminated.
BASIC REPORT
IS-236 - Service Instruction for Traffic Study Project for Executive Engineering Projects for Construction of
Local Roads
Basic Guidelines for the Preparation of Road Studies and Projects 447
ANNEX B37
IS-237 - SERVICE INSTRUCTION FOR PROJECT LAYOUT STUDIES
EXECUTIVE OF ENGINEERING FOR THE CONSTRUCTION OF LOCAL ROADS
1 OBJECTIVE
Define and specify the services included in the Route Studies for Projects
Engineering Executives for the Construction of Rural Highways.
2 STUDY PHASE
The Route Studies should take place over a single phase, Phase
Preliminary and Basic Project.
3 PREPARATION OF STUDIES
c) Comparative evaluation.
b) Geological elements;
Once the above conditions have been identified, they must be identified based on the elements
available plan-altimetric topographic data, the routing alternatives of the schemes
IS-237 - Service Instruction for Routing Study Projects for Executive Engineering Projects for Construction
Local Highways
Basic Guidelines for Preparing Road Studies and Projects 448
possible operational ones or still from the standard of improvements of existing roads,
simultaneously establishing the needs for current and special artworks,
with basic data on the situation, limits, and dimensions of bridges and viaducts, walls of
support, larger drainage works, and others of interest.
The standard and the main aspects should be established based on Traffic Studies.
characteristics of the alternatives, such as:
b) Width of the roadway, shoulder and medians; level of access and its form
of control; maximum super elevation;
d) Project vehicles;
The initially identified routing alternatives should be compared with each other.
for the purpose of selecting the most viable. The comparison will cover basic technical aspects.
(traced, topography), functional (access control, intersections, elevation increase of
service), economic (brief preliminary analysis of alternatives among themselves and the situation
existing, comparing implementation costs with benefits in the form of reductions in
operational costs, in travel times, in number of accidents, without intending
in this phase very detailed analysis), environmental (improvements to the urban environment),
financial (investment possibilities) and others necessary.
As a consequence of the comparative evaluation of the alternatives, it will be possible to select the
alternative tracing to be designed.
The activities that make up the Layout Study must be developed accordingly.
with the Service Instruction.
Service Instruction Activity
Preliminary Engineering Studies for Highways - Study of
IS-207
Draft) - Preliminary and Definitive Phases
4 PRESENTATION
The presentation of the Route Study will take place in the Basic Report of the Executive Project.
of Engineering to which it corresponds, thus broken down:
BASIC REPORT
Volume Species Subject Format
− Descriptive and justificatory memorandum of the studies conducted;
Report/
− Conclusions and recommendations;
Memory
1 Justification − Planimetry and altimetry elements. A4
of Project
Basic
IS-237 - Service Instruction for Study Plan Projects for Executive Engineering Projects for Construction
Local Roads
Basic Guidelines for the Preparation of Road Studies and Projects 449
ANNEX B38
IS-238 - SERVICE INSTRUCTION FOR TOPOGRAPHIC STUDIES
FOR ENGINEERING EXECUTIVE PROJECTS FOR
CONSTRUCTION OF LOCAL ROADS
1 OBJECTIVE
2 STUDY PHASE
These Topographic Studies will be carried out over a single phase, Phase of
Executive Project.
3 EXECUTION OF STUDIES
The surveying services will be carried out by conventional methods. The tasks to
will consist of:
a) Location of the selected route in the Preliminary Phase and Basic Project of the Project
Executive;
c) Cross sections;
watercourses;
h) Topographic registration of the domain strip.
The various services outlined in the topographic study will be carried out according to the
following methodology:
IS-238 - Service Instruction for Topographic Study Projects for Engineering Executive Projects for Construction
Local Highways
Basic Guidelines for the Development of Road Studies and Projects 450
The rental of the axis will be executed using a theodolite and linear measurements.
will be obtained using steel measuring tapes.
The axis will be marked every 20 m at all notable points, such as: PC, PT,
TS, SC, CS, and ST, topographic accidents, intersections with roads, riverbanks and
creeks. In all the installed enclosures, witness stakes will be placed.
made of good quality wood measuring about 60 cm in length, equipped with
in the engraving, where the corresponding number will be written with oil paint, from top to bottom.
These stakes will always be located to the left of the stakeout in the direction
increasing in its numbering and with the number facing the stake. The curves of radius
less than 300 meters will be marked at intervals of 10 meters. All the markers
corresponding to the PC, PT, TS, and ST, as well as the stakes every 2 km of the tangents
long ones will be tied by "safety points", located more than 20 m from the axis of the
road. The tying process will consist of at least four markers of
legal wood.
The distance measurements will be made with a steel tape, according to the horizontal for the purpose of
location of the stakeout points, however it is recommended to use a
statistical process for reading the distances between Pls, in order to achieve greater accuracy
in the calculation of the coordinates of these points.
The curves will be materialized in the field, using a theodolite and the process to be
the employee will be the one of the deflections over the tangents.
The leveling and counter-leveling of all the pegs of the location axis will be done.
with the use of precision levels. For leveling and counter-leveling control,
stable level references (RRNN) will be implemented, spaced every five hundred
metros, duly referred to in the plans, to the staking of the location. These
references (RRNN) will be implemented outside the offset lines and will consist of
IS-238 - Service Instruction for Topographic Study Projects for Executive Engineering Projects for Construction of
Local Highways
Basic Guidelines for the Preparation of Road Studies and Projects 451
The counterbalancing will be closed at each (RN), within the tolerance allowed by the standards.
for DNIT. The tolerance for leveling services will be 2 cm per kilometer and the
the maximum accumulated difference will be less than or equal to that obtained by the formula:
Together with the leveling of the axis, all will be leveled and counter-leveled.
notable points of crossing existing watercourses, when it will be noted in the
benchmark notebook, the water mirror level on the leveling date and the level of
maximum flood.
Also, the bottom of the watercourses will be leveled in order to allow for the design of the profile.
longitudinal of the crossing, to be used in the design of the artworks.
Cross sections will be raised in all paddocks of the located axis, with the
use of rulers or levels.
The sections will be raised symmetrically in relation to the axis and in a way to cover
the limits of the future right of way. In points where there is a need for studies
specials, the sections will be extended to a length considered sufficient to
those studies.
The determination of the direction of each section will be done using a crossbar. It will be
always employed bubble level, when checking the position of the horizontal ruler.
IS-238 - Service Instruction for Topographic Study Project for Executive Engineering Projects for Construction
Local Roads
Basic Guidelines for the Development of Road Studies and Projects 452
c) Survey of existing special and current artworks and location of new ones
to be built - all existing current works of art will be registered
in the section informing about leveling of the bed, NA, thresholds, retaining walls, crests
of slopes, longitudinal section of the thalweg, as well as their position will be noted,
type, dimension, operating condition and conservation.
The special works of art cut by the located axis will be swiftly raised, and
the main data will be recorded, such as: length, width, section sketch
longitudinal and transversal, state of conservation, structural system.
A bathymetric survey will be carried out every 5 meters from the axis of the works of art and two
parallel sections located 20 m upstream and downstream of the axis. Furthermore, it will be
raised the riverbed profile for a distance of 100 m on each side of the axis.
The new special artworks will have their locations raised typographically and
bathymetrically in the same guidelines previously recommended. Surveys will also be conducted
the longitudinal sections of the watercourses, in order to design the culverts of the gully.
The topographic survey of the occurrences will be carried out with the help of auxiliary polygons.
sections will be raised in order to allow their design with curves of
spaced levels of 5 m. All occurrences will be tied at the axis of the location of
project. Specific notebooks will be organized for this type of survey, with
sketch of tying these occurrences.
IS-238 - Service Instruction for Topographic Study Projects for Executive Engineering Projects for Construction of
Local Roads
Basic Guidelines for the Preparation of Road Studies and Projects 453
These devices combine, in a single unit, the measurement of angles and distances.
presenting advantages over traditional equipment regarding collection,
storage, processing, importation and exportation of data collected in the field.
They have an active sensor, as it receives and records data from a beam of radiation.
in the infrared range, generated by itself, which reaches prisms placed on the
target object, returning by reflection and exciting the sensors of the same generating source.
The calibration of electronic distance measuring devices must be carried out, both for
theodolites and levels, as for total stations using the ABNT Standard
13.133.
In the case of using GPS tracking for the determination of coordinates and
leveling, precision geodetic receivers with single or dual channels should be used
frequency, with tracking in static differential mode with a tracking time of,
at least 30 minutes or fast-static with a tracking time of at least 10 minutes.
4 PRESENTATION
The Topographic Studies will be presented in the Final Report of the Executive Project.
according to the following volumes:
IS-238 - Service Instruction for Topographic Study Projects for Executive Engineering Projects for Construction
Local Roads
Basic Guidelines for the Preparation of Road Studies and Projects 454
FINAL REPORT
IS-238 - Service Instruction for Topographic Study Projects for Executive Engineering Projects for Construction
Local Roads
Basic Guidelines for the Development of Road Studies and Projects 455
ANEXO B39
IS-239 - INSTRUCTION MANUAL FOR HYDROLOGICAL STUDIES
FOR EXECUTIVE ENGINEERING PROJECT FOR
CONSTRUCTION OF LOCAL ROADS
1 OBJECTIVE
The present Instruction aims to define and specify the services contained in
Hydrological Studies in Engineering Executive Projects for Construction of
Local Roads.
The Hydrological Studies will be developed in a single phase, the Preliminar [Link] of
Basic Project of the Executive Project.
3 DEVELOPMENT OF STUDIES
Data collection
a) Precipitation data, pluviographs, and river flow data available in the region.
b) Data that allows for the definition of the dimensions of the basins.
IS-239 - Service Instruction for Hydrological Study Projects for Executive Engineering Projects for Construction of
Local Highways
Basic Guidelines for the Development of Road Studies and Projects 456
a) Recurrence period:
The recurrence periods set for the types of works classified below will be
following:
Type of work Período de recorrência (anos)
b) Concentration time
The concentration time of the basins should be evaluated using methodology and models.
usual ones that present compatible results and that consider:
Basin area;
Land use;
Others.
c) Coefficient of impermeability
The impermeability coefficients should be determined only after analyzing the usage.
the areas of upriver, particularly in cases of violent modification of the
impermeability of the basins.
IS-239 - Service Instruction for Hydrological Study Projects for Executive Engineering Projects for Construction of
Local Roads
Basic Guidelines for the Development of Highway Studies and Projects 457
Basins with areas smaller than 10 km2 must have their discharge determined by
rational method.
The basins with areas greater than 10 km2 must have the discharge determined by
método de hidrograma ou similares.
For the two families of basins, the discharge must be verified by the equation of
continuity associated with Manning's formula.
4 PRESENTATION
The Hydrological Studies will be presented in the Basic Report of the Executive Project of
Engineering that corresponds, as detailed below:
BASIC REPORT
IS-239 - Service Instruction for Hydrological Study Projects for Engineering Executive Projects for Construction
Local Highways
Basic Guidelines for the Preparation of Road Studies and Projects 458
ANNEX B40
IS-240 - SERVICE INSTRUCTION FOR GEOTECHNICAL STUDIES
FOR ENGINEERING EXECUTIVE PROJECT FOR
CONSTRUCTION OF LOCAL ROADS
1 OBJECTIVE
2 STAGES OF STUDIES
3 PREPARATION OF STUDIES
Along the rental of the selected route, testing and collection will be carried out with
sampling for characterization of the geotechnical profile of the terrain. The borings
will be carried out at intervals of 100 m and in the intervals, when there are any
material variation. In virgin section, they will be made along the located axis, and in section
already implanted will be done on the right edge, axis and left edge, alternately. With the
The material collected from the surveys will undergo the following tests:
b) Physical indexes
Compression
d) ISC;
e) In situ density.
The first two tests will be carried out in all drilling holes and the last three,
in alternate holes.
The surveys of the subsoil should be included in the profile of the located axis.
IS-240 - Service Instruction for Geotechnical Study Projects for Executive Engineering Projects for Construction
Local Roads
Basic Guidelines for the Preparation of Road Studies and Projects 459
Investigation of the leveled locations in order to proceed with the selection, in the field, of the areas.
of loans based on the indications of the earthworks project (IS-243). In the
places where lateral loans are anticipated, there will be no need for execution
of tests, using those performed for the subgrade study. Where provided for
concentrated loans will be made, at least, five holes, distributed by
loan area, with a depth equal to that anticipated for the loan.
Samples will be collected in all boreholes, at the various horizons, which will
will undergo the following tests:
a) Granulometry
b) Physical Indices
c) Compression
a) The surveys;
b) Laboratory tests;
c) Volume estimates.
In the occurrences of materials selected for the primary coating layer will be
the following tests were carried out:
− Physical indices;
− Equivalent of sand;
The investigation of the material from the occurrences will be carried out through the launch of
60 m side reticular mesh, within the limits of the selected occurrence, in which
At the vertices, drilling holes will be made. In each hole of the 60 m grid, for each
layer of material, will be carried out:
b) Liquidity limit;
c) Plasticity limit;
IS-240 - Service Instruction for Geotechnical Study Projects for Engineering Executive Projects for Construction of
Local Roads
Basic Guidelines for the Preparation of Road Studies and Projects 460
d) Sand equivalent;
e) Compression;
f) ISC;
g) In situ density.
In the case of layers with more than 1.00 meter thickness, they will be executed.
the above-mentioned tests, for each meter of depth of this layer, should be
make a minimum of nine samples per occurrence.
In the study of stone materials, what is recommended by the Standard (NBR-6490) will be followed.
by ABNT), for recognition and sampling for the purpose of characterization of the
occurrences of rocks.
It is admitted and tolerated, in this case, to avoid the use of rotary probes, that the
the volumetric calculation of rock occurrences should be done, indirectly, based on the volumetric calculation of the
The measurement of the material may be carried out by listening to the mine bar, however,
it is necessary to launch a lattice with sides of 50 m. It is accepted and tolerated that
Let the mass below the quarry cover be considered as rock.
a) Granulometry;
Whenever there is doubt about the load-bearing capacity of the foundation soils
landfills, there will be a need to develop a special geotechnical study that defines
the bearing capacity of the natural ground, where it will be concluded about the possibility of:
IS-240 - Service Instruction for Geotechnical Study Projects for Executive Engineering Projects for Construction of
Local Roads
Basic Guidelines for the Development of Road Studies and Projects 461
The surveys for the foundations of the special artworks will consist of surveys.
definitive, which will be executed as prescribed by the Implementation Manual
Basic, from DNIT.
4 PRESENTATION
The Geotechnical Studies will be presented in the Final Report of the Executive Project.
Engineering to which it corresponds, should consist of:
FINAL REPORT
IS-240 - Service Instruction for Geotechnical Study Projects for Executive Engineering Projects for Construction
Local Roads
Basic Guidelines for the Development of Road Studies and Projects 462
ANNEX B41
IS-241 - SERVICE INSTRUCTION FOR GEOMETRIC PROJECT
IN ENGINEERING EXECUTIVE PROJECTS
FOR THE CONSTRUCTION OF LOCAL ROADS
1 OBJECTIVE
Define and specify the services contained in the Geometric Project in the Projects.
Engineering Executives for the Construction of Local Highways.
The geometric project will be executed in a single phase, the Executive Design Phase.
tapers
IN PLANT
c) safety points of the line with the attachments, representing them through
side sketches;
d) edges of the platform and projections of the shaded offsets in conventions,
differentiating cuts and embankments;
IS-241 - Service Instruction for Geometric Projects in Executive Engineering Projects for the Construction of Local Roads
Basic Guidelines for the Preparation of Road Studies and Projects 463
g) accesses, existing intersections and to be built, with the names of the localities and
indicators of the number of volume and the sheets that contain your projects
specifics;
h) indicated drains in type conventions (dashed lines) with total length and
indicated hidden footprints at the foot of the embankment.
j) domain range represented on all boards indicating the limits and their
ordered in relation to the axis.
3.1.2. IN PROFILE
a) indication of the land line and project representing the surface of the grade of
earthworks on the axis of the platform;
b) the percentages of the ramps and lengths, the lengths of the projections
horizontal lines of vertical concordance curves (V), kilometers and elevations of the PIV, PCV
the PTV of each vertical curve and the length of the arrow "e" of the vertical curves.
− Typical cross sections of the platform, right of way, and bridges in the various
expected characteristics for the highway;
− Cross sections indicating the natural terrain, the platform, the position of the offsets
and the slopes;
− Marking the domain strip symmetrically in relation to the axis and according to
offset line;
− Detailing of special projects consisting of returns and level accesses,
marking of tables, etc.
IS-241 - Service Instruction for Geometric Projects in Executive Engineering Projects for the Construction of Local Roads
Basic Guidelines for the Preparation of Road Studies and Projects 464
4 PRESENTATION
The Geometric Project will be presented in the Final Report of the Executive Project
Engineering to which it corresponds, must consist of:
FINAL REPORT
FORMAT
VOLUME DISCRIMINATION/ SUBJECTS
Printing
Minute
definitive
Project Report
1 A4 A4
⎯ Text containing a description of the studies conducted.
Execution Project
− Convention sheet;
− Plants and profiles at scales 1:2000 (H) and 1:200 (V),
containing:
− Profile drawing of the terrain along the project axis;
− Project profile design;
2 − Constituent elements of the vertical project; A1 A3
− Indication of the location of special works of art and
currents;
− Drawings of typical cross sections at the scales 1:100
e 1:200;
− Slope of cutting and embankment slopes.
Justification Memo
3 − Justification of the procedures performed. A4 A4
IS-241 - Service Instruction for Geometric Projects in Executive Engineering Projects for the Construction of Rural Roads
Basic Guidelines for the Preparation of Road Studies and Projects 465
ANNEX B42
IS-242 - SERVICE INSTRUCTION FOR DRAINAGE PROJECT
IN THE EXECUTIVE ENGINEERING PROJECTS FOR
CONSTRUCTION OF LOCAL ROADS
1 OBJECTIVE
Define and specify the services contained in the Drainage Project in the Projects.
Engineering Executives for the Construction of Local Roads.
The drainage project will be developed in a single phase, the Design Phase
Executive:
a) Design of the structures that will make up the surface drainage project and
subsuperficial.
The surface drainage system aims to capture and intercept the waters that
they fall onto the roadway and lead them to a safe drainage location, without
compromises the stability of the massif.
To meet this purpose, the surface drainage project will encompass the
the following devices:
Cutting board;
c) Embankment bench;
d) Water inlet;
water descent;
f) Collector box;
g) Shock absorber;
IS-242 - Service Instruction for Drainage Project in the Executive Engineering Projects for the Construction of Rural Highways
Basic Guidelines for the Preparation of Highway Studies and Projects 466
The drainage system aims to allow the passage of water that drains through
natural terrain from one side to the other of the road and as an additional device,
supplement of surface drainage when indicated as a grade culvert.
The culverts to be used in the rural road projects will be of the following types:
a) Concrete tubes;
b) Metal tubes;
c) Concrete cells.
The deep drainage system aims to intercept and lower the groundwater table.
subterranean, in order to prevent the progressive degradation of the support of the layers of
Embankments; their use, type, and location must be justified in the project.
The activities to be carried out for the development of the Drainage Project
they must comply with the existing methodology in the Service Instruction:
4 PRESENTATION
The Drainage Project will be presented through the Final Report of the Executive Project
of Engineering to which it corresponds:
IS-242 - Service Instruction for Drainage Project in Executive Engineering Projects for the Construction of Rural Highways
Basic Guidelines for the Preparation of Road Studies and Projects 467
FINAL REPORT
FORMAT
VOLUME DISCRIMINATION/ SUBJECTS
Printing
Minute
Definitive
Project Report
− Project conception;
1 − Frame of quantities and codes; A4 A4
− Discrimination of all services, transportation distances
and quantities.
Execution Project
⎯ Plants and standard projects of various devices of
drainage used;
2 ⎯ Schematic plan of the location of the drainage works; A1 A3
⎯ Service notes.
Justification Memo
3 A4 A4
⎯ Justification for the detailed solutions proposed
Budget and Execution Plan
⎯ List of services to be executed;
⎯ Costs of each service;
4 ⎯ Physical schedule; A4 A4
⎯ List of minimum equipment;
⎯ Layout of the construction site, access installations, quarries and
source of materials.
IS-242 - Service Instruction for Drainage Project in Executive Engineering Projects for the Construction of Local Roads
Basic Guidelines for the Preparation of Road Studies and Projects 468
ANNEX B43
IS-243 - SERVICE INSTRUCTION FOR EARTHWORK PROJECT
IN THE EXECUTIVE ENGINEERING PROJECTS FOR
CONSTRUCTION OF LOCAL ROADS
1 OBJECTIVE
The present Instruction aims to define and specify the services listed in
Earthworks Project in Engineering Executive Projects for Construction of
County Roads.
The earthworks project will be developed in a single phase, the Design Phase
Executive.
d) Framework for guidance and distribution of primary coating layer, indicating the
origins and destinations of the materials to be used.
In the development of these activities, the recommendations of the Instruction must be followed.
of Service:
4 PRESENTATION
The presentation of the Earthworks Project will be made in the Final Project Report.
Engineering Executive corresponding to the breakdown:
IS-243 - Service Instruction for Earthworks Project in Executive Engineering Projects for Road Construction
Local neighbors
Basic Guidelines for the Preparation of Highway Studies and Projects 469
FINAL REPORT
FORMAT
VOLUME DISCRIMINATION/ SUBJECTS
Impression
Minute
definitive
Project Report
− Project conception;
1 − Table of quantities and codes; A4 A4
− Discrimination of all services, transport distances and
quantities.
Execution Project
− Cubic leaves;
− Distribution board of materials;
− Earthworks orientation frame;
− Guidance chart for layer materials
primary coating;
− General plant showing the situation of the loans, botafora
and occurrences of materials for the coating layer
primary
2 − Plants of loan locations and material occurrences A1 A3
regarding your situation in relation to the highway, the position of the
drilling holes and the summary of the study results
geotechnical studies conducted;
− Drawing of the type cross sections, in excavation and embankment,
showing the slopes of the slopes, considering the layer
of the primary coating;
− Other drawings that clarify the project;
− Earthwork service notes;
− Primary coating layer service notes.
Justifying Memorandum
3 A4 A4
− Justification for the detailing of the proposed solutions
Service Notes and Volume Calculation
3C A4 A4
Budget and Execution Plan
− List of services to be performed;
− Classification of materials to be excavated;
− Costs of each service;
4 A4 A4
− Physical schedule;
− List of minimum equipment;
− Layout of construction site, accesses, installations, quarries and
source of materials.
IS-243 - Service Instruction for Earthworks Project in Engineering Executive Projects for Highway Construction
Neighbors
Basic Guidelines for the Preparation of Highway Studies and Projects 470
ANNEX B44
IS-244 - SERVICE INSTRUCTION FOR ARTWORK PROJECTS
SPECIAL IN THE ENGINEERING PROJECTS OF LOCAL ROADS
1 Objective
Define and specify the services contained in the Project of Special Works of Art in the
Executive Engineering Projects for the Construction of Local Roads.
At this stage, the structural design of the works to be designed will be defined, according to the
exposed methodology:
Starting from the conception of the project, established in the previous phase, the...
projects of special artworks containing:
a) definition of the type of work to be designed (wood, wooden superstructure with infrastructure-
structure in concrete, or purely concrete;
b) choice of the type of foundation based on geotechnical studies, on the type of work
to design and in the local conditions;
c) structural calculation;
d) preparation of the project layout drawing on plan and profile in 1:100 scale;
IS-244 - Service Instruction for Artworks Projects in Executive Engineering Projects for Road Construction
Local residents
Basic Guidelines for the Preparation of Road Studies and Projects 471
e) preparation of floor plans, elevations, and longitudinal and transverse sections and
structural and architectural details;
f) descriptive memory as aspects related to the execution of the work and the landfills
access.
The structural project will comply with ABNT standards and DNIT instructions.
especially the Service Instruction:
4 PRESENTATION
The presentation of the project, in its Preliminary Phase and Basic Project, will be made through
of the Basic Report of the Engineering Project to which it corresponds, as detailed
next.
BASIC REPORT
Report/
Memory Descriptive and justificatory report of the studies
1 Justification completed. A4 A4
of the Project Structural design of the works
Basic
The presentation of the Project, in its Executive Design Phase, will be made through the
Final Report of the Executive Engineering Project to which it corresponds, initially under the
draft form and later in the form of final printing, containing texts,
drawings and plans as specified below:
IS-244 - Service Instruction for Artwork Projects in Executive Engineering Projects for Road Construction
Local
Basic Guidelines for the Preparation of Road Studies and Projects 472
FINAL REPORT
FORMAT
VOLUME DISCRIMINATION/MATTERS
Printing
Minute
definitive
Project Report
− Informative text of the project, summary of the studies,
1 specifications, quantities, and all necessary elements A4 A4
in the bidding for the work. It will contain topographical, hydrological elements
geotechnics.
Project for the Execution of the Work
− Drawings, plans, profiles, and cross sections and typicals, for
for visualization and clarification purposes, of the structural solution of the
2 work of art, containing details of the foundations, infrastructure and A1 A1
mesostructure, formwork, molds, reinforcement elements
geometric, safety elements, drainage, and lighting.
Justificative Memo
3 A4 A4
− Memorial of the project developed
Calculation Memory of the Structures
3B A4 A4
Budget and Work Execution Plan
− Demonstrative charts of construction costs;
4 − Physical schedule; A4 A4
− Minimum equipment list;
− Equipment usage schedule;
IS-244 - Service Instruction for Artwork Projects in the Executive Engineering Projects for Road Construction
Neighborhoods
Basic Guidelines for the Preparation of Road Studies and Projects 473
ANNEX B45
IS-245 - SERVICE INSTRUCTION FOR FENCE PROJECTS
ENGINEERING EXECUTIVES FOR THE CONSTRUCTION OF LOCAL ROADS
1 OBJECTIVE
Define and specify the services included in the Fencing Project in the Executive Projects
from Engineering for the Construction of Local Roads.
The fence project will be executed in a single phase, the Executive Design Phase.
a) Type projects;
b) Service notes.
The fence project will be developed taking into account the available resources.
existing materials in the region, in order to reduce its implementation cost.
4 PRESENTATION
The presentation of the Fencing Project will take place in the Final Report of the Executive Project.
Engineering to which it corresponds, according to the breakdown below:
FINAL REPORT
IS-245 - Service Instruction for Fence Project in the Executive Engineering Projects for the Construction of Rural Highways
Basic Guidelines for the Preparation of Road Studies and Projects 474
ANNEX B46
IS-246 SERVICE INSTRUCTION FOR THE ELABORATION OF THE COMPONENT
ENVIRONMENTAL ASPECTS OF HIGHWAY ENGINEERING PROJECTS
1 OBJECTIVE
With the existence of the EIA/RIMA and PBA, the preparation of the Environmental Component of the Projects of
The designer must carry out the work seeking obedience to the precepts of
sustainable development and principles established in the Environmental Policy of DNIT,
which aims to ensure the continuous improvement of its environmental management.
a) Fase Preliminar;
a) Specific legislation;
b) Recommendations / conditions from environmental agencies;
− Manual for Land Use Management in the Domain and Adjacent Strips
Federal Highways
− Instructions for Environmental Protection of the Domain and Marginal Strips of Highways
Federals;
− Guidelines and Procedures for Resettlement of Affected Populations in Works
Bus stations;
− Environmental Regulatory Framework for Road Projects.
The Preliminary Environmental Diagnosis must characterize the environmental situation of the area of
influence of the enterprise on physical, biotic, and anthropic aspects, aiming for a
knowledge of the region prior to the implementation of the enterprise, serving as a reference
for the assessment of the environmental impacts arising from the works and operation of the highway, and of the
environmental liabilities.
Regarding the biotic environment, a characterization of the flora and fauna must be carried out.
especially of the forest remnants, and other forms of natural vegetation that
may be impacted by the enterprise, and the identification of legally designated areas
existing protected areas in the region, with information on the distance between them and the
enterprise.
It must be verified, with the competent authorities, the existence of areas to be protected, and of
restrictive factors for land use for road activities (urban areas, areas
legally protected.
The Preliminary Environmental Diagnosis should be developed at the level of bibliographies and,
government sources of environmental data, satellite photos, thematic maps, etc.
complemented by field inspections for the perfect environmental characterization of
área de influência do projeto (física, biótica e antrópica).
The Preliminary Phase of the Environmental Component of Road Engineering Projects will be
consolidated by the Preliminary Environmental Assessment Report - PEAR, which will allow the
decision-making for the optimization of technical and locational alternatives, as well as,
the initiative of DNIT, along with the Licensing Environmental Authority for the purpose of requesting the
Preliminary License-LP of the Enterprise.
Considering the dual purpose of the RPAA, as stated above, its content will be
consisting of:
It must detail, at the level of Basic Project, the environmental situation of the influence area.
according to physical, biotic, and anthropic aspects, aiming for a more comprehensive knowledge
detailed description of the region before the implementation of the enterprise, serving as a reference
for assessing environmental liabilities, and for evaluating impacts
environmental.
For the purpose of applying this Instruction, Environmental Liability is defined as all
the occurrence resulting from construction, restoration, or maintenance failure of the highway,
caused by third parties, or by adverse weather conditions, capable of acting as a factor
of damage or environmental degradation to the area of direct influence, to the roadway or to
user.
Special attention should be given to the interferences with urban areas and areas
legally protected and, in particular, to the sources intended for human consumption,
facing the possibility of accidents involving road transportation of hazardous products.
The identification, analysis, and evaluation of positive and negative environmental impacts must
focus on the changes in the environment resulting from the insertion of
project, considering the phases of implementation and operation.
The discussion and analysis of these correlations, developed both together and individually for
Each diagnosed issue will lead to a listing of the identified and active impacts.
in the area of influence.
This listing should be submitted to several discussion and analysis sessions within
a multidisciplinary approach, aiming to define the classification of impacts, determining
among them, the most significant occurrences, concerning the locations and the phases of
undertaking.
b) Biotic Medium.
Fire Hazard.
Increase in Poaching.
Change in the Current Level and in the Trend of Accident Rate Evolution.
The Environmental Forecast is established from the development of current and future scenarios.
of the territory of the area of influence, based on the environmental diagnosis of it and
in the assessment of the significant impacts arising from the works and the road operation
planned, considering the possibility of not implementing them.
a) Current Scenario that portrays the environmental picture diagnosed in the area of influence, in
especially the current quality of life, which will be subject to environmental transformations.
b) Trend Scenario that constitutes the forecast of the current scenario, without considering the
implementation of the planned venture, but only the transformations
natural events that the region will be prone to.
c) Succession scenario that constitutes the forecast of the transformed territory in relation to
implementation of planned road activities, without the application of any
environmental protection measures, except for those contained in the project of
engineering.
d) Target Scenario that constitutes the environmental framework possible to be achieved in
coexistence with the transformative activities and results of the application of a
basic environmental plan, which will ensure the environmental sustainability of the territory.
The Basic Environmental Assessment Report - RBAA must contain the characterization of
the undertaking and the entrepreneur, the justification for its execution, the diagnosis
environmental of its area of influence, the identification of environmental impacts and the
proposed mitigating measures.
The characterization of the enterprise, the entrepreneur, and the justification for the execution
of the enterprise, must be established according to the provisions in the Instruction of
Environmental Service ISA-03: Environmental Impact Studies - EIA, of the Normative Body
Environmental for Road Enterprises.
c) Single line diagram, with identification of all registered areas, including the areas
legally protected, transpositions of urban areas, rivers, streams and eventual
sources of water for human consumption, as well as other "Points"
Notable interferers.
– Summary descriptive text, addressing the Environmental Programs and distinguishing them
integrating programs of the PCA and the Institutional Programs, discussing
its specific purposes and respective implementation schedules,
referenced to the execution schedule of the work.
Interface Spreadsheet, according to the model contained in the Basic Guidelines for
Environmental Road Activities, currently being developed by the IPR, which contains the
listing of the relevant Environmental Programs and their corresponding
the various items of the Engineering Project.
Project Elements:
NOTE: The data regarding the calculation of quantities and budgeting must be
dealt with in the corresponding volume of the Engineering Project.
In the case where the bidding for the work is based on the Executive Project of
Engineering, the Final Environmental Assessment Report - RFAA should provide
additional information that allows DNIT to request from the Environmental Authority
Installer License of Installation - LI, of the Enterprise.
4 PRESENTATION
4 - BIBLIOGRAPHY
Basic Guidelines for the Preparation of Road Studies and Projects 483
Basic Guidelines for the Preparation of Road Studies and Projects 484
4 BIBLIOGRAPHY
BRAZIL. Law 8666, of June 21, 1993. Regulations for article 37, item XXI, of
Federal Constitution establishes rules for bidding and contracts of Public Administration
and provides other measures. Available at: [Link] Accessed on: February 2.
2005.
PEREIRA, Francisco de Mattos de Britto. The Evolution of DNER studies and projects.
Rio de Janeiro: DNER. Planning Directorate. Studies and Projects Division, 1970.