DETAILED ESTIMATION FIRST FLOOR
[Link] Description Of Work Nos Length Breadth Depth Quantity Unit
R.C.C mix 1:1.5:3 using
20mm Metal & [Link] for
1 all structural elements
Excluding Shuttering,
steel work
a Column:
Column C1 8 0.75 0.75 15.00 67.50
Column C2 10 0.75 1.50 15.00 168.75
Column C3 6 0.75 1.50 15.00 101.25
b Lintel Beam
Cross Wall
Cross Wall Wall 1 71.00 0.75 0.50 26.63
Cross Wall Wall 1 60.00 0.75 0.50 22.50
Long wall:
Long wall Wall 8 14.00 0.75 0.50 42.00
Staircase
Slab 1 25.00 3.00 0.50 37.50
c Roof Beam
Beam RB1 1 255.00 0.75 1.25 239.06
Beam RB2 1 120.00 0.75 1.50 135.00
d Roof Slab
All 1 1402.00 0.50 701.00
1541.19 [Link]
Say 43.65 m³
2 Shuttering work
Lintel Beam and
Sunshade:
Cross Wall
Cross Wall Wall 1 71.00 2.50 - 177.50
Cross Wall Wall 1 60.00 2.50 - 150.00
Long wall:
Long wall Wall 8 14.00 2.50 - 280.00
Staircase
Slab 1 25.00 3.00 - 75.00
Roof Beam
Beam RB1 1 255.00 3.25 - 828.75
Beam RB2 1 120.00 3.75 - 450.00
Roof Slab
Slab 1 1402.00 - 1402.00
Column:
Column C1 8 3.50 - 15.00 420.00
Column C2 10 4.50 - 15.00 675.00
Column C3 6 4.50 - 15.00 405.00
4863.25 [Link]
Say 451.97 m²
Fabrication Of Steel
including Material,
7
Barbending labour etc.,
Complete
R.C.C Qty Column 1 337.50 9.56 100.00 955.82
R.C.C Qty Lintel Beam 1 92.00 2.61 100.00 260.55
R.C.C Qty Staircase 1 38.00 1.08 100.00 107.62
R.C.C Qty Roof Beam 1 374.00 10.59 100.00 1059.19
R.C.C Qty Slab 1 701.00 19.85 101.00 2005.13
4388.30 Kg
4.39 Ton
Superstructure wall using
Brick with 9" thick in CM
8
1:6 for All Walls
complete.
Cross Wall
Cross Wall Wall 1 71.00 0.75 9.50 505.88
Cross Wall Wall 1 60.00 0.75 9.50 427.50
Long wall:
Long wall Wall 8 14.00 0.75 9.50 798.00
Deduction:-
Door Rs 6 8.00 0.75 9.50 342.00
1389.38 [Link]
Say 39.35 m³
Rolling Shutter with
9 necessary fitting etc.
completed.
Door Rs 6 8.00 - 9.50 456.00
456.00 [Link]
Say 42.38 m²
Ceiling plastering in CM
1:3 for RCC exposed area
10 with good hacking for
slab bottom smooth area
Passage 1 71.00 4.25 - 301.75
Shop 2 14.00 9.75 - 273.00
Shop 4 14.00 10.00 - 560.00
1134.75 [Link]
Say 105.46 m²
Wall Plastering work for
11 internal wall in cm 1:5
with 12mm thick
Shop 2 48.00 - 11.00 1056.00
Shop 4 48.00 - 11.00 2112.00
Deduction:-
Door Rs 6 8.00 - 11.00 528.00
2640.00 [Link]
Say 245.35 m²
Wall Plastering work for
12 External wall in cm 1:5
with 20mm thick
All Around Wall 1 182.00 - 15.00 2730.00
Deduction:-
Door Rs 6 8.00 - 11.00 528.00
2202.00 [Link]
Say 204.65 m²
Vitrified Tile Supply &
13
Fixing
Floor
Passage 1 71.00 4.25 - 301.75
Shop 2 14.00 9.75 - 273.00
Shop 4 14.00 10.00 - 560.00
1134.75 [Link]
Say 105.46 m²
14 Painting Work 1 5976.75 5976.75 [Link]
Say 555.46 m²
15 Electrical Work L.S
16 Plumbing Work L.S
17 Round Off L.S