Detailed First Floor Estimation Report

Uploaded by

g1.eventplanners
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
8 views3 pages

Detailed First Floor Estimation Report

Uploaded by

g1.eventplanners
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

DETAILED ESTIMATION FIRST FLOOR

[Link] Description Of Work Nos Length Breadth Depth Quantity Unit


R.C.C mix 1:1.5:3 using
20mm Metal & [Link] for
1 all structural elements
Excluding Shuttering,
steel work
a Column:
Column C1 8 0.75 0.75 15.00 67.50
Column C2 10 0.75 1.50 15.00 168.75
Column C3 6 0.75 1.50 15.00 101.25
b Lintel Beam
Cross Wall
Cross Wall Wall 1 71.00 0.75 0.50 26.63
Cross Wall Wall 1 60.00 0.75 0.50 22.50
Long wall:
Long wall Wall 8 14.00 0.75 0.50 42.00
Staircase
Slab 1 25.00 3.00 0.50 37.50
c Roof Beam
Beam RB1 1 255.00 0.75 1.25 239.06
Beam RB2 1 120.00 0.75 1.50 135.00
d Roof Slab
All 1 1402.00 0.50 701.00
1541.19 [Link]
Say 43.65 m³
2 Shuttering work
Lintel Beam and
Sunshade:
Cross Wall
Cross Wall Wall 1 71.00 2.50 - 177.50
Cross Wall Wall 1 60.00 2.50 - 150.00
Long wall:
Long wall Wall 8 14.00 2.50 - 280.00
Staircase
Slab 1 25.00 3.00 - 75.00
Roof Beam
Beam RB1 1 255.00 3.25 - 828.75
Beam RB2 1 120.00 3.75 - 450.00
Roof Slab
Slab 1 1402.00 - 1402.00
Column:
Column C1 8 3.50 - 15.00 420.00
Column C2 10 4.50 - 15.00 675.00
Column C3 6 4.50 - 15.00 405.00
4863.25 [Link]
Say 451.97 m²
Fabrication Of Steel
including Material,
7
Barbending labour etc.,
Complete
R.C.C Qty Column 1 337.50 9.56 100.00 955.82
R.C.C Qty Lintel Beam 1 92.00 2.61 100.00 260.55
R.C.C Qty Staircase 1 38.00 1.08 100.00 107.62
R.C.C Qty Roof Beam 1 374.00 10.59 100.00 1059.19
R.C.C Qty Slab 1 701.00 19.85 101.00 2005.13
4388.30 Kg
4.39 Ton

Superstructure wall using


Brick with 9" thick in CM
8
1:6 for All Walls
complete.
Cross Wall
Cross Wall Wall 1 71.00 0.75 9.50 505.88
Cross Wall Wall 1 60.00 0.75 9.50 427.50
Long wall:
Long wall Wall 8 14.00 0.75 9.50 798.00
Deduction:-
Door Rs 6 8.00 0.75 9.50 342.00
1389.38 [Link]
Say 39.35 m³

Rolling Shutter with


9 necessary fitting etc.
completed.
Door Rs 6 8.00 - 9.50 456.00
456.00 [Link]
Say 42.38 m²

Ceiling plastering in CM
1:3 for RCC exposed area
10 with good hacking for
slab bottom smooth area

Passage 1 71.00 4.25 - 301.75


Shop 2 14.00 9.75 - 273.00
Shop 4 14.00 10.00 - 560.00
1134.75 [Link]
Say 105.46 m²

Wall Plastering work for


11 internal wall in cm 1:5
with 12mm thick
Shop 2 48.00 - 11.00 1056.00
Shop 4 48.00 - 11.00 2112.00
Deduction:-
Door Rs 6 8.00 - 11.00 528.00
2640.00 [Link]
Say 245.35 m²

Wall Plastering work for


12 External wall in cm 1:5
with 20mm thick
All Around Wall 1 182.00 - 15.00 2730.00
Deduction:-
Door Rs 6 8.00 - 11.00 528.00
2202.00 [Link]
Say 204.65 m²

Vitrified Tile Supply &


13
Fixing
Floor
Passage 1 71.00 4.25 - 301.75
Shop 2 14.00 9.75 - 273.00
Shop 4 14.00 10.00 - 560.00
1134.75 [Link]
Say 105.46 m²

14 Painting Work 1 5976.75 5976.75 [Link]


Say 555.46 m²
15 Electrical Work L.S

16 Plumbing Work L.S

17 Round Off L.S