Sebou-Bouregreg Water Transfer Project
Sebou-Bouregreg Water Transfer Project
October 2022
SUMMARY
The North-South water transfer project is one of the mega-projects that Morocco plans.
to be carried out in the coming years. It will enable the mobilization of 850 million m3 of water
from the northern rainy country to the semi-arid south. This project, which has been brewing for years,
is still in the study phase.
Officially known as the 'National Water Transfer Scheme from the Basins'
excess to the deficit basins", the interest of the project is simple. In terms of
In terms of precipitation, Morocco is subjected to two very different aspects: the northern part of the country (Rif,
The Middle Atlas, Gharb and Loukkos is regularly watered, especially during the winter,
when the rest of the country is subjected to a regime of more irregular rains.
Several large dams are concerned (Al Wahda, Oued El Makhazine, Mohammed
Ben Abdellah and Al Massira). The project will generate socioeconomic benefits,
notably in terms of job creation and wealth
Card No. 1: The basins of the Laou, Loukkos, and Sebou rivers are surplus.
deficient basins of the Bouregreg, Oum Er Rbia, and Tensift
1
Technically, the project involves the construction of a large water supply system.
artificial means ensuring transport over no less than 500 km allowing for the diversion of a portion
from the northern waters to the south. This supply system consists of a network of
transport of 500 km across Morocco, consisting of canals, pipes, galleries and
pumping stations. will allow to divert part of the waters of the Laou, the Loukkos and
from the Sebou (surplus basins) to supply the deficit basins of Bou Regreg,
from the Oum Er-Rbia and Tensift. The maximum flow rate will be 45 m3/s.
The mega project of the North-South water transfer aims to address the deficits.
in irrigation perimeters and meet a rapidly increasing water demand
in the three beneficiary basins.
The transfer project is indeed a water highway that will require many
artworks, it would be open to the sky or underground depending on the sections and should be
accompanied by several giant pumping stations. This water highway will be
done in three phases consisting of several steps.
The first phase involves supplying drinking water to Marrakech and the cities.
surrounding areas and meet the irrigation needs of Al Haouz with no less than 400
millions of cubic meters that will be mobilized. This operation will also help to reduce
significantly the flooding risks that particularly affect the Gharb regions and
of Loukkos.
For phase 1 (map 2), from the Koudiat Borna intake dam to the dam.
Massira is composed of two sections:
➢ Section 1.1 with a takeoff from the Oued Ouergha (main tributary of
the Sebou river) at the site known as Kodiat Borna, followed by an intake consisting of
canals over 109.1 km, pipelines over 25.9 km and a gallery
underground of 6.8 km. This section arrives in the reservoir of the SMBA dam.
The section includes two pumping stations to overcome a height.
total of 72 m.
➢ Section 1.2 with a connection to the SMBA retention basin and containing a
succession of channels (57.5 km) and pipelines (82.3 km) and finally a
62.4 km gallery arriving at Al Massira. This section includes 4 posts.
pumping to overcome a maximum total height of 326 m.
2
Card No. 2: The initial phases of the transfer project
3
Card No. 3: Details of the upstream transfer project phases of the Sidi Mohammed Ben Abdellah dam
El Dam
Makhazine
Barrage
El Wahda
Dam
Kenitra Driss 1er
Raba
Barrage
S.M.B.
4
II.2 - The phase II of the water transfer project
In the second phase, it is planned to supply the regions of Chaouia, Abda, and Souss,
areas that have significant agricultural potential but are experiencing a deficit
Water significantly disrupts all development efforts.
For phase 2, of the Béni Mansour dam project on the Laou up to point L, it
consists of two sections ::
➢ -Section 2.1: with a connection to the Béni Mansour dam projected in the
Laou basin followed by an underground gallery of 53.3 km. This gallery
restore the water in the Loukkos basin upstream of the dam reservoir
projected from Tfer and whose implementation is located at the end of the retention
existing dam Oued Makhazine.
➢ Section 2.2: with an outlet on the Loukkos river just downstream of the dam
Makhazine River, followed by an underground gallery of 22.3 km. This gallery
and is followed by a channel adduction (33.9 km) and a pipeline (25 km) for
the crossing of the Sebou river in siphon and the flood zone. This
The adduction involves two pumping stations at a total height of 19.
m.
Figure No. 1: Synoptic diagram of the initial version of the transfer project
1
II.3 - The Phase III of the water transfer project
III.1 The modifications introduced at the level of the initial version of the project
The initial version of the transfer project has been revised. Thus, and as described above, the
implementation phases that were originally three have been reduced to two phases by eliminating
certain sub-phases as follows:
➢ Removal of sub-phase 1.1, which consists of connecting the Ouergha socket and the
meeting point located in the surroundings of the city of Kenitra. This sub-phase
remove will be replaced by phase 3 which initially connects the dam intake
on duty at the meeting point.
➢ Phase II of the project will be scaled back by eliminating the downstream part of the pipeline.
connection linking the Loukkos outlet to the meeting point. This downstream part
starts at the crossing point of the Sebou river and ends at
meeting point of the three supply pipes.
2
Sections
removed
The adjustments introduced at the level of the initial version of the project are based on a
set of advantages justifying the chosen option, in particular, the use of
measurement of the possible, to the natural transportation offered by watercourses. Among others, one
can list the following strengths:
Presence of the Sebou guard dam.
The first phase of the project involves the construction of the diversion dam at the
Kodiat el Borna site to ensure the supply of section 1 of the supply pipeline.
This role will be performed by the Sebou guard dam. Thus, the water released from the dam
They will continue their journey to the guard dam.
Presence of connection with the Sebou river.
The first phase of the project involves the construction of an upstream intake on the Sebou.
Ouregha (Kodiat el Borna Dam. The second plans the crossing of the Sebou. The
The third plans a withdrawal from the Sebou at the guard dam level.
3
Thus, the three phases are directly linked to the Sebou, which allows for grouping.
the three crossing points with the Sebou in a single point downstream of the Sebou, that is just
upstream of the guard dam.
III.3 - The advantages related to the re-adaptation of the initial version of the project
4
IV.2 Project Implementation Phase of Interconnection
• The first phase involves the interconnection of the Garde dam reservoir.
Sebou with the retention of the SMBA dam on the Bouregreg with a flow rate of 45
m3/s ;
• The second phase involves the interconnection of the reservoir of the SMBA dam to the
Retention of the elevated Imfout dam or Al Massira dam with a flow of 30
m3/s.
Given the very deficient water situation in 2022, an urgent first tranche (Figure no. 3)
connecting the Sebou basin to the Bouregreg basin with a flow rate of 15 m3/s is the solution
retention to secure the AEP of the systems in Rabat, Casablanca and indirectly
Marrakech.
5
IV.3 Summary description of the works
The supply will include the following structures from upstream to downstream:
Pump station SP1 with a flow rate of 15 m3/s and a total dynamic head of approximately 115 m
The overall linear distance retained outside the connection to the retention for this option is 66.5 km.
concerning the two provinces Kenitra and Salé
6
guard dam
Sebou
station
SP1
station
SP2
backflow prevention
SMBA retention
The projected route generally crosses four soil classes over approximately the 66 projected kilometers.
distributed as follows:
• Sands little evolved over 6.15 km or 9% of the total length, non-alluvial contributions.
hydromorphic on the surface characterized by a low degree of alteration,
Humiferous horizons can be quickly identified, often with a poorly defined structure.
(DEHS) ;
• Vertisols over 12.3 km, or 18% of the total length, rich in clay, which swell
they deflate depending on their water content. Vertisols are therefore affected
of withdrawal cracks to drying and pressure phenomena during swelling
what causes the undulation of the surface of the ground. They are difficult to work with but
productive (TIRS) ;
• Humus soils evolve into brown or brown soils over 47.5 km, which is 68% of the total linear distance.
This is the classic form of evolved soil found under deciduous forest in the area.
tempered (RMEL);
8
THE DISTRIBUTION OF SOLE CLASSIFICATIONS CROSSING THE PROJECTED TRACE
6% 9%
18%
HYDROMORPHIC SOILS
Projected layout
9
IV.6 Crossing of irrigated sectors
10
Annexes
11