Inventory Management and EOQ Calculations
Inventory Management and EOQ Calculations
Fo
01
1 33
24
35
46
65
68
72
84
90
101
126
144
2 Materials Cost
1. About 50 items are required every day for a machine. A fixed cost of 50 per order is incurred for
placing an order. The inventory carrying cost per item amounts to 0.02 per day. The lead period is
32 days. What will be the Economic Order Quantity?
(a) 125 (b) 9552 (c) 500 (d) 26
2. Anuradha Company has a Mumbai Plant that manufactures OTG. One component is an XY chip.
Expected demand is for 10,000 of these chips in the year 2009. Anuradha estimates the ordering
cost per purchase order to be ₹ 250. The carrying cost for one unit of XY in stock is ₹ 5 per annum.
Compute the number of deliveries of XY in March, 2009.
(a) 10 (b) 31.64 or 32 (c) 500 (d) 26
3. The average annual consumption of a material is 18,250 units at a price of ₹36.50 per unit. The
storage cost is 20% on an average inventory and the cost of placing an order is ₹ 50. How much
quantity is to be purchased at a time?
(a) 1000 (b) 2000 (c) 750 (d) 500
4. The purchase committee of A Ltd. has been entrusted to review the material procurement policy
of the company. The chief marketing manager has appraised the committee that the company at
present produces a single product X by using two raw materials A and B in the ratio of 3:2. Material
A is perishable in nature and has to be used within 10 days from Goods received note (GRN) date
otherwise material becomes obsolete. Material B is durable in nature and can be used even after
one year. Material A is purchased from the local market within 1 to 2 days of placing order. Material
B, on the other hand, is purchased from neighbouring state and it takes 2 to 4 days to receive the
material in the store.
The purchase price of per kilogram of raw material A and B is ₹ 30 and ₹ 44 respectively exclusive
of taxes. To place an order, the company has to incur an administrative cost of ₹ 1,200. Carrying
cost for Material A and B is 15% and 5% respectively. At present material A is purchased in a lot
of 15,000 kg. to avail 10% discount on market price. GST applicable for both the materials is 18%
and the input tax credit is availed.
The sales department has provided an estimate that the company could sell 30,000 kg. in January
2024 and also projected the same trend for the entire year.
The ratio of input and output is 5:3. Company works for 25 days in a month and production is carried
out evenly.
The following queries/ calculations to be kept ready for purchase committee’s reference:
(1) For the month of January 2024, what would be the quantity of the materials to be requisitioned
for both material A and B:
(a) 9,000 kg & 6,000 kg respectively
1 CA/CS Nimeet Piti | | |
(b) 18,000 kg & 12,000 kg respectively
(c) 27.000 kg & 18,000 kg respectively
(d) 30,000 kg & 20,000 kg respectively.
(2) The economic order quantity (EOQ) for both the material A & B:
(a) 13,856 kg & 16,181 kg respectively
(b) 16,197 kg. & 17,327 kg respectively
(c) 16,181 kg & 17,165 kg respectively
(d) 13,197 kg & 17,165 kg respectively
(4) Calculate saving/ loss in purchase of Material A if the purchase order quantity is equal to EOQ
(a) Profit of ₹ 3,21,201, (b) Loss of ₹ 3,21,201.
(c) Profit of ₹ 2,52,500. (d) Loss of ₹ 2.52,500.
5. Tropic Pvt Ltd was engaged in the business of manufacturing Product P. The product P required 2
units of Material R. The company intends to sell 24,000 units of Product P and does not wish to
retain any closing stock. However, the opening stock of Product P is 4,000 units. Raw Material R has
to be procured after considering the opening stock of R amounting to 10,000 units. The technical
team further confirms that the yield in the course of manufacture of Product P is 80% of the input.
The company presently procures its annual requirement of materials on a quarterly basis from its
regular supplier enjoying a discount of 2.5% on the invoice price of the material of ₹ 20 per unit.
Every time the company places orders for Material R, it incurs 125 for each of the order placed.
The company also has taken a rented warehouse for storing material R and the annual cost of
storage is ₹ 10 per unit. The company appointed Mr. Ta Chartered Accountant to review the cost
of inventory and provide measures of improvement of cost. After reviewing the material purchase
and consumption pattern, Mr. T suggested that the implementation of Wilson's EOQ would be
beneficial to the company. He emphasized that the change in the quantity ordered would result in
reduction of inventory carrying costs.
1. The annual requirement of Material R to meet the target sales of 24,000 units of Product P is:
(a) 48,000 units (b) 60,000 units
(c) 40,000 units (d) 50,000 units
2. The ordering quantity as per the current inventory policy and the proposed Wilson's Economic
order quantity of Material R are:
(a) Order Quatity as per the current inventory policy 10,000 units & Economic Order Quantity
1,000 units
(b) Order Quantity as per the current inventory policy 15,000 units & Economic Order Quantity
1,225 units
(c) Order Quantity as per the current inventory policy 12,000 units & Economic Order Quantity
1,095 units
(d) Order Quantity as per the current inventory policy 12,500 units & Economic Order Quantity -
1,118 units
3. The net savings to inventory cost on migration from the current inventory policy to the Wilson's
Economic Order Quantity policy would be:
(a) Savings from EOQ as compared to current discount policy - ₹ 26,820
(b) Savings from EOQ as compared to current discount policy -₹ 20,500
(c) Savings from EOQ as compared to current discount policy -₹33,253
(d) Savings from EOQ as compared to current discount policy -₹25,546
5. The savings in labour cost achieved by implementation of incentive scheme over the overtime
payments amounts to:
(a) ₹ 9,600 (b) ₹ 5,600 (c) ₹ 8,000 (d) ₹ 3,200
A 20% shortage in material on receipt is expected considering the nature of the raw material.
The payment to the supplier was made within 21 days of the purchases.
1. If Axe Traders pays the supplier within 30 days of purchase, then, what is the total amount of
cash discount received from the supplier and how it is treated to calculate material cost?
(a) ₹ 25,000 & it will not be deducted from the material cost
(b) ₹ 26,550 & it will be deducted from the material cost
(c) ₹ 26,550 & it will not be deducted from the material cost
(d) ₹ 22,500 & it will not be deducted from the material cost
2. What will be the amount of other expenses and how it is treated in material cost?
(a) ₹ 6,154.40 & it will be added with the material cost
(b) ₹ 6,280.00 & it will be added with the material cost
(c) ₹ 5,344.40 & it will be added with the material cost
(d) ₹ 5,453.47 & it will not be added with the material cost
3. What is the amount of GST and how will it be treated in cost sheet of Axe Traders?
(a) ₹ 40,500 & it will not be added with material cost
(b) ₹ 40,500 & it will be added with material cost
(c) ₹ 45,000 & it will not be added with material cost
(d) ₹ 45,000 & it will be added with material cost
5. The number of good units and cost per unit of the materials received are:
(a) 5,000 units & ₹ 62.80 (b) 5,000 units & ₹ 54.70
(c) 4,000 units & ₹ 78.50 (d) 4,000 units & ₹ 68.38
7. ABC Ltd is a manufacturer of specialized components & needs to maintain an efficient inventory
system for its raw materials. The company has the following data regarding one of its essential raw
materials
annual demand: 36000 units
• ordering cost per order: ₹ 600
• carrying cost per unit per annum: ₹ 15
• Re-order level: 4500 units
• Lead time: 5 days
• Daily usage: 100 units
• maximum Stock level: 6000 units
Based on this information calculate:
1. What is the EOQ for ABC Ltd?
a) 1700 b) 1697 c) 1694 d) 1691
2. (a) 10
2 × 10,000 × ` 250
EOQ = = 1,000 chips
`5
Annual Demand 10,000
Number of deliveries = =
EOQ 1,000
= 10
2 × Annualconsumption × Ordercost
Material A =
Carrying cost per unit p.a.
30,000
= × 10days = 12,000 kg.
25
(b) Maximum Stock Level for Material A:
Re-order Quantity + Re-order level (Min consumption* x Min. lead time)
Where, Re-order Quantity = 15,000 kg.
Re-order level = Max. Consumption* x Max. Lead time
30,000
Maximum stock Level = 15,000 kg. + 2,400 kg. - × 1days
25
Stock required for 10 days consumption is lower than the maximum stock level
calculated through the formula. Therefore, Maximum Stock Level will be 12,000 kg.
(*Since, production is processed evenly throughout the month hence material
consumption will also be even.)
5. 1.(c) 40,000
Annual Demand of finished goods 24,000
Less: Opening Stock (4,000)
Annual Demand of finished goods to manufacture 20,000
× Kgs required per unit 2 kgs
Annual demand of raw material 40,000
yield 80%
Annual demand of raw material 50,000
(-) Opening Stock of raw material; (10,000)
Annual demand of raw material to buy 40,000
2.(a) Order Quatity as per the current inventory policy units 10,000 units & Economic
Order Quantity 1,000
Current order size : Quaterly basis
40,000 kgs – 4 Quarters
40,000
per quarter : = 10,000 kgs.
4
4.(b) ₹ 6,400
Time allowed: 180 + 20 = 200 hrs (given)
Time taken – 125 F.G. - 1 hr
5.(b) ₹ 5,600
Total Labour cost under the current scheme
Basic : 180 hrs × 200 /hr = 36,000
Overtime : 20 hrs × 400 /hr = 8,000
44,000
Earnings as per rowan:
Time saved
Earnings = hours worked × rate/hr + × Time taken rate/ hr
Time allowed
6. i.(a) ` 25,000 & it will not be deducted from the material cost
List Price 2,50,000
(-) Trade discount 10% of List Price (25,000)
Net Price 2,25,000
Cash Discount 10% of 2,25,000 = 22,500 to be deducted.
2 × 36000 × 600
= 1697 units
15
8. 1.(d) 89.8
Annual demand of FG (x) – 3000 × 4 Qtr = 12000 units
(-) Opening Stock 500 units
A.D. of FG to manufacture 11500
× Kgs required of raw material (y) 2 kgs
Total raw material required 23000 kgs
(-) Opening stock (1000 kgs)
Raw materials to buy 22000 kgs
2 × AD ×OCPO
EOQ =
CCpupa
2 × 22000 ×1000
700 =
CCpupa
3. The cost accountant of Y Ltd. has computed labour turnover rates for the quarter ended 31st
March, 2009 as 5% under 'Replacement method' If the number of workers replaced during that
quarter is 30, find out the number of average workers on payroll.
(a) 6 (b) 600
(c) 60 (d) 6000
4. A worker takes 15 hours to complete a piece of work for which time allowed is 20 hours. His wage
rate is ₹ 5 per hour. Following additional information are also available:
Material cost of work ₹ 50
Factory overheads 100% of wages
Calculate the factory cost of work under the following methods of wage payments:
(i) Rowan Plan (ii) Halsey Plan
(a) Rowan – 103.75 & Halsey 108.5 (b) Rowan – 93.75 & Halsey 87.5
(c) Rowan – 83.75 & Halsey 77.5 (d) Rowan – 94.75 & Halsey 85.5
5. The labour turnover rates for the quarter ended 30th June, 2024 are computed as 14%, 8% and
6% under Flux method, Replacement method and Separation method respectively. If the number
of workers replaced during 1st quarter of the financial year 2024-25 is 36, COMPUTE the
following:
(i) The number of workers recruited and joined; and
(ii) The number of workers left and discharged.
6. If the amount of wages under Halsey plan is ₹ 420, total time allowed is 8 hours and the
guaranteed time rate is ₹ 60 per hour. What is the total time saved by the worker?
(a) 2 hours (b) 3 hours
(c) 6 hours (d) 3.5 hours
7. Phalsa Ltd. pays its workers on time-basis because their services cannot be tangibly measured.
The company's normal working week includes 5 days of 8 hours each. Sometimes, the workers
needs to work late at night which was 3 nights of 3 hours each for the current week. The average
output produced per worker for the week is 120 units.
Information regarding incentive rate is as follows:
Rate of Payment Day shift: ₹ 320 per hour
Night shift: ₹ 450 per hour
However, this time-basis payment made workers lazy, making their expected output lower. As
workers started doing more of the night shifts for higher earnings with minimal impact on the
outputs, the company decided to shift on to a system of payments on output basis.
8. Suppose the units of a product are produced at the rate of 4 units per useful direct labour hour.
Direct labour idle time is 10% of hours paid for. Sales of 1,000 units are budgeted and finished
goods stock is expected to rise by 100 units. The budgeted direct labour hours for the production
would be:
(a) 306
9. The board of the J Ltd. has been appraised by the General Manager (HR) that the employee
attrition rate in the company has increased. The following facts has been presented by the
GM(HR):
(1) Training period of the new recruits is 50,000 hours. During this period their productivity is
60% of the experienced workers. Time required by an experienced worker is 10 hours per
unit.
(2) 20% of the output during training period was defective. Cost of rectification of a defective
unit was 25.
(3) Potential productive hours lost due to delay in recruitment were 1,00,000 hours.
(4) Selling price per unit is 180 and P/V ratio is 20%.
(5) Settlement cost of the workers leaving the organization was 1,83,480.
(6) Recruitment cost was 1,56,340
(7) Training cost was 1,13,180
You being an associate finance to GM(HR), has been asked the following questions:
(1) How much quantity of output is lost due to labour turnover?
(a) 10,000 units (b) 8,000 units
(c) 12,000 units (d) 12,600 units
(2) How much loss in the form of contribution, the company incurred due to labour turnover?
(a) ₹ 4,32,000 (b) ₹ 4,20,000
(c) ₹ 4,36,000 (d) ₹ 4,28,000
(4) Calculate the profit lost by the company due to increased labour turnover.
(a) ₹ 7,50,000 (b) ₹ 15,00,000
(c) ₹ 5,00,000 (d) ₹ 9,00,000
(5) How much quantity of output is lost due to inexperience of the new worker?
(a) 1,000 units (b) 2,600 units
(c) 2,000 units (d) 12,600 units
In Division A (Halsey system), the standard time to complete a job is 5 hours, and the hourly rate
is ₹100. An employee named Ravi completes the job in 4 hours. Under the Halsey scheme, the
worker is entitled to 50% of the time saved, which directly influences Ravi's total earnings.
In Division B (Rowan system), the standard time to complete a job is 6 hours, and the hourly rate
is also ₹100. An employee named Sita completes the job in 5 hours. The Rowan scheme provides a
proportionate increase in wages based on the time saved relative to the standard time, affecting
Sita's total earnings. Employee Turnover has also been a point of concern for Green
Manufacturing Ltd. In Division A, the employee turnover ratio stands at 20%, while Division B has
a lower employee turnover ratio of 15%. Management is evaluating whether the incentive schemes
are influencing worker retention and overall productivity.
11. ABC Manufacturing Ltd. employs 500 workers. Over the past year, 80 employees left the company
(30 were separations, and 50 were replacements). The company has also been analyzing labor
efficiency using both the Halsey and Rowan plans to incentivize workers.
• Total wages paid under the time-rate system: ₹2,00,000.
• The standard time to produce 100 units is 50 hours.
• Worker A took 40 hours to complete 100 units.
• Time rate: ₹50 per hour.
3. If Worker A is paid under the Halsey Plan with a 50% bonus, what is Worker A’s total
earnings for producing 100 units?
(a) ₹2,250 (b) ₹2,500
(c) ₹2,750 (d) ₹3,000
4. If Worker A is paid under the Rowan Plan, what will be his total earnings for producing
100 units?
(a) ₹2,400 (b) ₹2,500
(c) ₹2,600 (d) ₹2,700
=
(No. of workers in the beginning of the period + No. of workers at the end of the period)
2
( 400 + 500 ) = 450
=
2
=
(No. of workers left during the period No. of workers replaced during the period) × 100
(Average no. of workers during the period)
( 45 + 40 )
= × 100 = 18.8%
450
2. (a) 28.8
A. Wage rate per hour = 0.50
B. Standard time allowed = 3 hours per dozen
C. Actual production = 20 dozens
D. Standard time allowed for 20 dozens [B x C] 3 hours x 20 dozens = 60 hours
E. Actual time taken to produce 20 dozens = 48 hours
F. Time saved [D - E] = 60 - 48 = 12 hours
Earnings =
Under Rowan Plan
Time taken
(Actual Time Taken x Time Rate ) + Time saved x x time rate
Time allowed
48
= ( 48 hours x 0.50 ) + 12 x x 0.50
60
= (48 hours x 0.50) + (12 x (48/60) x 0.50]
= 24 + 4.80
= Rs. 28.80
3. (b) 600
Average number of workers on payroll:
Numberorworkers replaced
Labour turnover rate (Replacement method) = × 100
Averagenumberon payroll
5 30
or, =
100 Average numberon payroll
9. 1.(d) ` 80
Time allowed – 5 hours
Time taken - 4 hours
Time saved - 1 hour
rate /hr - 100/hr
Time saved
Bonus Under rowan : = × Time taken rate / hr
Time allowed
2.(c) ` 117
Time allowed - 6 hours
Time taken - 5 hours
Time saved - 1 hour
Rate/hr - 100
Earnings under rowan,
Time saved
Earnings = hours worked x rate/hr + × Time taken rate / hr
Time allowed
1
= 5 × 100 + × 5 100
6
= 583.33
583.33
Effective hourly rate = = 116.66 or 117
5 hours
2. (b) 6%
no. of workere separated
Separation method = ×100
Average no. of workers
30
= ×100 = 5.88% or 6%
510
3.(a) ` 2,250
Time allowed : 50hrs
Time taken : 40 hrs
4. (a) ` 2,400
Time allowed: 50hrs
Time taken : 40 hrs
Time saved : 10 hrs
rate /hr : 50/hr
Earnings under Rowan:
Time saved
Earnings hrs wkd × rate/hr + × Time taken rate / hr
Time allowed
10
= 40 × 50 + × 40 50
50
= 2,400
1. The following data relate to the overhead expenditure of a contract cleaner at two activity levels:
Square meters cleaned 6,375 7,550
Overheads ₹ 36, 975 ₹ 41, 792.5
What is the estimate of the overheads if 8,100 square meters are to be cleaned?
(a) 44047.5 (b) 44074.5 (c) 44704.5 (d) 47074.5
2. The accountant for Brilliant Tools Ltd applies overhead based on machine hours. The budgeted
overhead and machine hours for the year are ₹ 1,30,000 and 8,000 hours respectively. The actual
overhead and machine hours incurred were ₹ 1,37,500 and 10,000 hours. The cost of goods sold
and inventory data compiled for the year is as follows:
Direct Material. ₹ 25,000
Cost of Goods Sold ₹ 2,25,000
Units: WIP 50,000 and Finished Goods 75,000
What is the amount of over/under absorbed overhead for the year?
(a) Over absorbed by ₹ 25,000
(b) Under absorbed by ₹ 25,000
(c) Over a absorbed by ₹ 32,500
(d) Under absorbed by ₹ 32,500
3. ABC Manufacturing allocates its factory overhead costs based on machine hours. The total
estimated overhead cost for the year is ₹ 6,00,000, and the company expects to use 30,000
machine hours. During the year, job A used 300 machine hours. What amount of overhead costs
should be allocated to this job?
(a) ₹ 4,000 (b) ₹ 6,000
(c) ₹ 10,000 (d) ₹ 8,000
4. Based on the data below, what is the amount of the overhead under-/over- absorbed?
Budgeted overhead - ₹ 5,25,000
Budgeted machine hours - 17,500
Actual machine hours - 17,040
Actual overheads - ₹ 5,20,000
(a) 5,000 under-absorbed (b) 8,800 under-absorbed
(c) 8,800 over-absorbed (d) 5,000 over-absorbed
5. Gaarmentz Ltd. run a sewing factory for medical garments. But, the company suffers from the
limiting factor i.e. labor. Each sewing machine needs 100% attention of one person at a particular
point of time to operate it. The company has 8 number of alike sewing machines on which 8
6. PMP Limited manufactures a single product and absorbs the production overheads at a pre-
determined rate of ₹ 20 per machine hour. At the end of financial year 2024-25, it has been found
that actual production overheads incurred were ₹ 12,00,000. It included ₹ 80,000 on account of
‘written off’ obsolete stores and ₹ 30,000 being the wages paid for the strike period under an
award. The actual machine hours worked during the period were 50,000 hours. The production and
sale were 20,000 units and 18,000 units respectively.
What will be the amount of under-absorbed production overhead to be charged to Cost of Sales ?
(A) ₹ 91,000
(B) ₹ 90,000
(C) ₹ 81,000
(D) ₹ 80,000
7. JMS Limited, a soft drink company, is intending to introduce a new product viz. ‘Herbs Infused
Mineral Water’ to the market. Annual sales of this new product is estimated at 36,000 units with a
selling price of ₹ 75 per unit. The cost estimates for this new product are as follows :
Elements of Cost Amount (₹)
Direct material consumed 9,50,000
Direct labour cost 5,93,750
8. During half year ending inter departmental review meeting of P Ltd., cost variance report was
discussed and the performance of the departments were assessed. The following figures were
presented.
For a period of first six months of the financial year, following information were extracted from
the books:
Actual production overheads ₹ 34,08,000
The above amount is inclusive of the following payments made:
Paid as per court's order ₹ 4,50,000
Expenses of previous year booked in current year ₹ 1,00,000
Paid to workers for strike period under an award ₹4,20,000
Obsolete stores written off ₹ 36,000
Production and sales data for the six months are as under:
Production:
Finished goods 1,10,000 units
Works-in-progress(50% complete in every respect) 80,000 units
Sales:
Finished goods 90,000 units
Machine worked during the period was 3,000 hours.
At the of preparation of revenue budget, it was estimated that a total of 50,40,000 would be required
for budgeted machine hours of 6,000 as production overheads for the entire year.
During the meeting, a data analytic report revealed that 40% of the over/under-absorption was
due to defective production policies and the balance was attributable to increase in costs.
You were also present at the meeting; the chairperson of the meeting has asked you to be ready
with the followings for the performance appraisal of the departmental heads:
(iii) What is the supplementary rate for apportionment of over/under absorbed overheads over
WIP, Finished goods and Cost of sales?
(a) ₹ 0.315 per unit (b) ₹ 0.472 per unit
(c) ₹ 0.787 per unit (d) ₹ 1 per unit
(iv) What is the amount of over/under absorbed overhead apportioned to Work in Progress?
(a) ₹ 9,440 (b) ₹ 42,480
(c) ₹ 18,880 (d) ₹ 70,800
9. Litto Itd. is a manufacturing company which has as a machine shop cost centre that contains three
machines of equal capacities. To operate these three machines nine operators are required i.e. three
operators on each machine. Operators are paid ₹ 20 per hour. The factory works for fourty eight
hours in a week which includes 4 hours set up time. The work is jointly done by operators. The
operators are paid fully for the fourty eight hours. In additions they are paid a bonus of 10 per
cent of productive time. Costs are reported for this company on the basis of thirteen four-weekly
period
✓ The company for the purpose of computing machine hour rate includes the direct wages of
the operator and also recoups the factory overheads allocated to the machines. The following
details of factory overheads applicable to the cost centre are available:
✓ Depreciation 10% per annum on original cost of the machine. Original cost of each machine is
₹ 52,000.
✓ Maintenance and repair per week per machine is ₹ 60.
✓ Consumable stores per week per machine are ₹ 75.
✓ Power: 20 units per hour per machine at the rate of 80 paise per unit. No power is used during
the set-up hours.
Apportionment to the cost centre: Rent per annum ₹ 5,400, Heat and Light per annum ₹ 9,720,
foreman's salary per annum ₹ 12,960 and other miscellaneous expenditure per annum ₹ 18,000.
ii. What is the bonus charges and power expenses for four- week period?
(a) ₹ 1,056 and ₹ 2,816 (b) ₹ 1,562 and ₹ 3,560
(c) ₹ 1,240 and ₹ 3,325 (d) ₹ 860 and ₹ 2,450
10. XYZ Ltd. manufactures two products, A and B, in its factory, which has three departments: two
production departments (Machining and Assembly) and one service department (Maintenance). The
following details are provided for the apportionment and accounting of overheads:
Machining department overheads: ₹ 1,50,000
Assembly department overheads: ₹ 75,000
Maintenance department overheads: ₹ 40,000
Machine hours in the Machining department: 5,000 hours
Labour hours in the Assembly department: 10,000 hours
The overheads of the Maintenance department are to be reapportioned to Machining and Assembly
departments in the ratio 3 : 2.
Additional Information:
Product A uses 1,200 machine hours and 3,000 labour hours.
Product B uses 800 machine hours and 2,000 labour hours.
2. If the profit as per the cost accounts is ₹ 50,000 before reconciliation, what will be the
reconciled profit after adjusting for the under-absorbed overheads?
(a) ₹ 40,000 (b) ₹ 50,000 (c) ₹ 45,000 (d) ₹ 60,000
3. In overhead accounting, what would typically happen if overheads are consistently under-
absorbed?
(a) The company may need to increase its overhead absorption rate
(b) The company should decrease its overhead absorption rate
(c) The company will always show higher profits in cost accounts
(d) There is no need to adjust the overhead absorption rate
1. (a) ₹ 410
1. Variable overheads per square metre:
Extra m² cleaned = 7,550 – 6,375 = 1,175
Extra overhead cost = ₹ 41792.5 - ₹ 36,975 = ₹ 4817.5
4,817.5
Variable overhead per m² = = ₹ 4.10
1,175
2. Fixed overhead:
₹
Total overheads of cleaning 6375 m² 36,975
Variable overheads = 6375 x ₹ 4.10 26,137.5
Fixed overhead (₹ 36,975 - ₹ 26,137.5) 10,837.5
Budgeted Overhead
Predetermined Overhead Rate =
Budgeted hours
130,000
i.e. = ₹ 16.25 per hour.
8,000
Hence, absorbed overhead = 10,000 hrs × 16.25 = ₹ 1,62,500.
Since actual overhead incurred were ₹ 1,37,500
Hence the overhead were over absorbed by 1,62,500 - 1,37,500 = ₹ 25,000.
3. (b) ₹ 6,000
Budgetd Overheads 6, 00, 000
= = 20 /hr
Budgeted hours 30, 000hrs
For Job: 300 m/c hrs × 20/hr = ₹ 6,000
5. (d) ₹119.34
Computation of Comprehensive Machine Hour Rate
Particulars Amount for six months (₹)
Operators' wages paid [(9,594 hrs./ 8 hrs.) ×₹110] 1,31,918
Power consumed 60,125
Supervision and indirect labour 21,450
Insurance (₹4,68,000/2) 2,34,000
Sundry expenses (₹7,15,000/2) 3,57,500
Depreciation [(₹41,60,000×10%)/2] 2,08,000
Repair and maintenance [(5%×₹41,60,000)/2] 1,04,000
Total Overheads for 6 months 11,16,993
Comprehensive Machine Hour Rate 119.34
(9,360 hours/₹11,16,993)
6. (C) ₹ 81,000
Total actual overheads = 12,00,000
Less: Abnormal items (80,000 + 30,000) = 1,10,000
Normal overheads = 10,90,000
Overheads absorbed = 50,000 × 20 = 10,00,000
Under-absorbed = 10,90,000 – 10,00,000 = 90,000
Share for Cost of Sales = 90,000 × (18,000 ÷ 20,000) = 81,000
Hence, under-absorbed overhead charged to Cost of Sales = ₹ 81,000.
` 70,800
Supplementary rate = = ` 0.472 perhour
1,50,000 units
2. (a) ₹ 69,060
Total overhead Cost of Product A.
Product A: 1200/m/c hrs × 34.8/hr +
3000/Lab. Hrs × 9.1 hr ₹ 69,060
2. (a) ₹ 40,000 ₹
Profit as per cost accounts 50,000
Less: Under – absorbed overheads (10,000)
Profit as per financial books 40,000
3. (a) The company may need to increase its overhead absorption rate.
1. From the following information, calculate the Total cost of Product A and B using the ABC analysis:
Product A Product B
Units 5,000 5,000
Number of purchase orders placed 100 220
Number of deliveries received 70 200
Ordering Cost ₹ 4,00,000
Delivery Cost ₹ 1,35,000
(a) A = ₹ 47,500; B = ₹ 1,27,500 (b) A = ₹ 2,67,500; B = ₹ 2,67,500
(c) A = ₹ 1,60,00; B = ₹ 3,75,000 (d) A = ₹ 1,47,500; B = ₹ 1,47,500
2. One of Pintu Company’s cost pools is parts administration. The budgeted overhead cost for that
cost pool was ₹ 4,00,000 and the expected activity was 4,000 part types. The actual overhead cost
for the cost pool was ₹ 4,20,000 at an actual activity of 5,000 part types. The activity rate for
that cost pool was:
(a) ₹ 80 per part type (b) ₹ 100 per part type
(c) ₹ 105 per part type (d) ₹ 84 per part type
3. SunBright Appliances Ltd., founded in 2005, is a growing Indian manufacturer of three types of
home appliances: Air Conditioners (ACs), Washing Machines (WMs), and Refrigerators (RFs). The
company has built a reputation for quality and durability in the mid-range market segment and has
seen stable demand across urban and semi-urban markets. In recent years, it has invested in
modernizing its production facilities with semi-automated machinery and upgraded
ERP systems to support cost control and performance monitoring.
The following information is provided for the current year from the books of Olay Ltd.:
Olay EV Max Olay EV Ultra Olay EV Pro
Average revenue per unit (₹) 84,975 1,15,500 2,17,800
Average cost of goods sold per unit (₹) 82,500 1,10,000 1,98,000
Last year, when the company initially expanded its product line, the sales were not much noticeable
comparative to its earlier category of scooters. The company could only sold 528, 330 and 110 units
of Olay EV Max, Olay EV Ultra and Olay EV Pro respectively against the order received of 616, 396
and 165 units respectively. However, with the increasing awareness about the EVs, more people
started buying EVs and, during the current year, the company’s order and sales jumped to five times
the last year.
For earlier years, Olay Ltd. used gross margin percentage method to evaluate the relative
profitability for all of its EVs.
However, from current year, company plans to use activity-based costing for analysing the
profitability.
The Activity analysis of Olay Ltd. is as under:
Activity Area Cost-allocation base
Customer purchase order processing Purchase orders by customers
Line-item ordering Line-items per purchase order
Store delivery Unit sold
Cartons dispatched to stores Cartons dispatched to a store per Unit
Shelf-stocking at customer store Hours of shelf-stocking
All the support costs for the current year amounts to ` 66,23,760. These support costs are
assigned to all the activity areas.
(i) For the current year, how much is the order received and the units sold for Olay EV Max, Olay
EV Ultra and Olay EV Pro respectively?
(a) Order received- 616, 396 and 165 units; sold- 528, 330 and 110 units of Olay EV Max, Olay EV
Ultra and Olay EV Pro respectively.
(b) Order received- 3,696, 2,376 and 990 units; sold- 3,168, 1,980 and 660 units of Olay EV Max,
Olay EV Ultra and Olay EV Pro respectively.
(c) Order received- 528, 330 and 110 units; sold- 616, 396 and 165 units of Olay EV Max, Olay EV
Ultra and Olay EV Pro respectively.
(d) Order received- 3,080, 1,980 and 825 units; sold- 2,640, 1,650 and 550 units of Olay EV Max,
Olay EV Ultra and Olay EV Pro respectively.
(ii) The total gross-margin percentage and the operating income percentage, for the current year
would be:
(a) Gross-margin - 3.72% and Operating income - 4.96%
(b) Gross-margin - 4.96% and Operating income - 3.72%
(c) Gross-margin - 4.96% and Operating income - 4.96%
(d) Gross-margin - 3.72% and Operating income - 3.72%
(iii) The cost driver rate relating to all the five activity areas would be:
(a) Customer purchase order processing- ` 363.64 per order, Line item ordering- ` 21.24 per line
item order, Store delivery- ` 265.42 per unit sold, Cartons dispatched- ` 4.93 per dispatch and
Shelf-stocking at customer store- ` 77.58 per hour.
(iv) The operating cost of the individual product line, as per the method proposed for the current
year w.r.t. profitability analysis, would be:
(a) Olay EV Max- ` 16,11,013, Olay EV Ultra- ` 23,56,890 and Olay EV Pro- ` 26,56,059
(b) Olay EV Max- ` 23,56,890, Olay EV Ultra- ` 26,56,059 and Olay EV Pro- ` 16,11,013
(c) Olay EV Max- ` 26,56,059, Olay EV Ultra- ` 16,11,013 and Olay EV Pro- ` 23,56,890
(d) Olay EV Max- ` 26,56,059, Olay EV Ultra- ` 23,56,890 and Olay EV Pro- ` 16,11,013
(v) Operating income as a percentage of revenues of each product line, namely Olay EV Max, Olay
EV Ultra and Olay EV Pro, when all the support costs are allocated using an activity-based costing
system would be:
(a) Olay EV Max- 1.73%, Olay EV Ultra- 3.53% and Olay EV Pro7.75%
(b) Olay EV Max- 1.18%, Olay EV Ultra- 1.24% and Olay EV Pro1.34%
(c) Olay EV Max- 2.91%, Olay EV Ultra- 4.76% and Olay EV Pro9.09%
(d) Olay EV Max- 1.78%, Olay EV Ultra- 3.70% and Olay EV Pro8.52%
5. The sales department of A Limited is analysing the customer profitability for its Product Z. It
has decided to analyse the profitability of its five new customers using activity-based costing
method. It buys Product Z at ` 5,400 per unit and sells to retail customers at a listed price of `
6,480 per unit.
The data pertaining to five customers are:
Customers
A B C D E
Units sold 4,500 6,000 9,500 7,500 12,750
Listed Selling Price ₹ 6,480 ₹ 6,480 ₹ 6,480 ₹ 6,480 ₹ 6,480
Actual Selling Price ₹ 6,480 ₹ 6,372 ₹ 5,940 ₹ 6,264 ₹ 5,832
Number of Purchase orders 15 25 30 25 30
Number of Customer visits 2 3 6 2 3
Number of deliveries 10 30 60 40 20
After a detailed analysis and computation, the following activities has been identified and
respective cost has been calculated:
Activity Cost Driver Rate
Order taking ` 4,500 per purchase order
Customer visits ` 3,600 per customer visit
Deliveries ` 7.50 per delivery Km travelled
Product handling ` 22.50 per case sold
Expedited deliveries ` 13,500 per expedited delivery
You have been assigned the following task of computing different cost information for managerial
decision making:
1. How much cost on customer visit is incurred on customer E?
(a) ₹ 7,200 (b) ₹ 10,800
(c) ₹ 21,600 (d) ₹ 3,600
5. Compute the customer-level operating income of each of five retail customers D and E.
(a) ₹ 46,82,550 & 50,65,720 (b) ` 55,72,350 & 46,85,500
(c) ₹ 47,57,400 & 55,72,350 (d) ` 61,88,550 & 50,57,325
A B
Ordering cost 1,25,000 2,75,000
(1250 × 100) (11,250 × 220)
Delivery cost 35,000 1,00,000
(500 × 70) (500 × 200)
Total cost 1,60,000 3,75,000
Working Notes
Cost for each activity cost driver:
Activity Total Cost (₹) No. of Activity Activity Rate
Driver
Machine Setups ₹ 9,00,000 180 setups ₹ 5,000/setup
Quality Inspections ₹ 6,00,000 300 inspections ₹ 2,000/inspection
Material Handling ₹ 7,50,000 500 moves ₹ 1,500/move
Utilities & Maint. ₹ 15,00,000 30,000 hrs ₹ 50/machine hour
4. (i) (d)
Particulars Olay EV Olay EV Olay EV Pro Total
Max (units) Ultra (units) (units) (units)
Previous year order 616 396 165 1,177
received
Current Year order (5 3,080 1,980 825 5,885
times the last year)
Previous year sales 528 330 110 968
Current Year sales (5 2,640 1,650 550 4,840
times the last year)
(ii) (b)
Statement of gross margin percentage and operating income percentage
Particulars Olay EV Max Olay EV Ultra Olay EV Pro Total
Revenues (A) (₹) 22,43,34,000 19,05,75,000 11,97,90,000 53,46,99,000
(2,640×₹84,975) (1,650×₹1,15,500) (550×₹2,17,800)
Less: Cost of goods 21,78,00,000 18,15,00,000 10,89,00,000 50,82,00,000
sold (B) (₹)
(2,640×₹82,500) (1,650×₹1,10,000) (550×₹1,98,000)
Gross Margin (A - B) 65,34,000 90,75,000 1,08,90,000 2,64,99,000
(₹)
Less: Operating 66,23,760
costs (₹)
Operating income (₹) 1,98,75,240
Gross Margin % 4.96%
Operating income % 3.72%
(iv) (d)
Computation of operating cost
Olay EV Max (₹) Olay EV Ultra (₹) Olay EV Pro (₹) Total (₹)
Customer 9,21,136 5,92,159 2,46,733 17,60,027
purchase order
processing
(₹299.07×3,080 orde (₹299.07×1,980 o (₹299.07×825 orders)
rs) rders)
Line item 6,54,192 5,04,662 2,45,322 14,04,176
ordering
(₹21.24×10×3,080 ord (₹21.24×12×1,980 (₹21.24×14×825 orders)
ers) orders)
Store delivery 8,52,007 5,32,505 1,77,502 15,62,013
(₹322.73×2,640 unit (₹322.73×1,650 u (₹322.73×550 unit sold)
sold) nit sold)
Cartons 2,08,243 6,50,760 8,13,450 16,72,453
dispatched
(₹4.93×16 cartons ×2, (₹4.93×80 carton (₹4.93×300 cartons ×550
640 units) s ×1,650 units) units)
Shelf stocking 20,481 76,804 1,28,007 2,25,292
(₹77.58×2,640 delive (₹77.58×1,650 del (₹77.58×550 deliveries ×
ries ×0.1 Av. hrs.) iveries ×0.6 Av. hr 3 Av. hrs)
s.)
Operating cost 26,56,059 23,56,890 16,11,013 66,23,962*
(v) (a)
Operating Income Statement (using the Activity based Costing system)
Olay EV Max Olay EV Ultra Olay EV Pro
Revenues (₹) (A) 22,43,34,000 19,05,75,000 11,97,90,000
(2,640×₹84,975) (1,650×₹1,15,500) (550×₹2,17,800)
5.
Activity Activity Cost Driver Cost Driver Cost Driver
Cost PooL Volume rate
Machine Setup 1,00,000 Setups 20 5000/setup
Quality Inspections 1,50,000 Inspections 30 5000/inspection
Material handling 50,000 Material 5000 10/movement
movements
1.(c) ₹ 45,000
Set up (2 × 5000) ₹ 10,000
Quality Inspections (5 × 5000) ₹ 25000
Material movements (1000 × 10) ₹ 10,000
Total overhead costs ₹ 45,000
2.(b) ₹237.50
Direct costs (100 pu × 500 units) ₹ 50,000
Overheads (as above) ₹ 45,000
Total Costs ₹ 95,000
+ Profit @ 25% total cost ₹ 23,750
Total Sales ₹ 118,750
Units 500
Selling Price per unit ₹ 237.5
3.(c) ₹ 50,000
Set up (2 × 5000) ₹ 10,000
Quality Inspections (5 × 5000) ₹ 25000
Material movements (1500 × 10) ₹ 15,000
Total overhead costs ₹ 50,000
2. Following information is available for the month of March relating to manufacturing of a product:
Particulars Amount (₹)
Cost of Sales 37,51,540
Stock of Raw material as on 01st March 6,50,000
Direct Wages 11,44,000
Hire charges paid for Plant (indirect expenses) 3,24,740
Salary to office staff 1,78,750
Maintenance of office building 13,000
Depreciation on Delivery van 39,000
Warehousing charges 61,750
Stock of Raw material as on 31st March 1,95,000
Realisable value on sale of scrap 32,500
Factory overheads are 20% of the Prime cost.
FIND OUT the value of Raw Material purchased with the help of Statement of Cost.
(a) ₹ 10,40,000
(b) ₹ 14,95,000
(c) ₹ 26,39,000
(d) ₹ 34,91,540
3. M Ltd. is producing a single product and may expand into product diversification in next one to
two years. M Ltd. is amongst a labour-intensive company where. majority of processes are done
manually. Employee cost is a major cost element in the total cost of the company. The company
conventionally uses performance parameters Earnings per manshift (EMS) to measure cost paid
to an employee for a shift of 8 hours, and Output per manshift (OMS) to measure an employee's
output in a shift of 8 hours.
The Chief Manager (Finance) of the company has emailed you few information. related to the last
month. The email contains the following data related to the last month:
During the last month, the company has produced 2,34,000 tonnes of output.
2. What is the total and per shift cost of production for last month:
(a) ₹ 7,87,10,000 and 336.37 respectively
(b) ₹ 7,87,10,000 and 1,681.84 respectively
(c) ₹ 7,87,28,000 and 1,682.22 respectively
(d) ₹ 7,87,28,000 and 336.44 respectively
3. What is the value of administrative cost incurred during the last month:
(a) ₹ 92,400 (b) ₹ 88,000
(c) ₹ 1,48,400 (d) ₹ 1,44,000
4. What is the value of selling and distribution cost and total cost of sales:
(a) ₹ 36,000 & ₹ 7,88,76,400 respectively
(b) ₹ 56,000 & ₹ 7,88,76,400 respectively
(c) ₹ 36,000 & ₹ 7.88,72,000 respectively
(d) ₹ 56,000 & ₹ 7,88,72,000 respectively
4. P Ltd. has gathered cost information from ledgers and other sources for the year ended 31st
December 2023. The information are tabulated below:
SI. Amount (₹) Amount
No. (₹)
(i) Raw materials purchased 5,00,00,000
(ii) Freight inward 9,20,600
(iii) Wages paid to factory workers 25,20,000
(iv) Royalty paid for production 1,80,000
(v) Amount paid for power & fuel 3,50,000
(vi) Job charges paid to job workers 3,10,000
(vii) Stores and spares consumed 1,10,000
(viii) Depreciation on office building 50,000
(ix) Repairs & Maintenance paid for:
- Plant & Machinery 40,000
- Sales office building 20,000 60,000
(x) Insurance premium paid for:
- Plant & Machinery 28,200
- Factory building 18,800 47,000
(xi) Expenses paid for quality control check activities 18,000
(xii) Research & development cost paid for improvement in 20,000
production process
(xiii) Expenses paid for pollution control and engineering & 36,000
maintenance
(xiv) Salary paid to Sales & Marketing mangers 5,60,000
(xv) Salary paid to General Manager 6,40,000
(xvi) Packing cost paid for:
Primary packing necessary to maintain quality 46,000
For re-distribution of finished goods 80,000 1,26,000
(xvii) Fee paid to independent directors 1,20,000
(xviii) Performance bonus paid to sales staffs 1,20,000
(xix) Value of stock as on 1st January, 2023:
- Raw materials 10,00,000
- Work-in-process 8,60,000
5. The analysis of cost sheet of A Ltd. for the last financial year has revealed the following
information for it's product R:
Elements of Cost Variable Cost portion Fixed Cost
Direct Material 30% of cost of goods sold --
Direct Labour 15% of cost of goods sold --
Factory Overhead 10% of cost of goods sold ₹ 2,30,000
General & Administration Overhead 2% of cost of goods sold ₹ 71,000
Selling & Distribution Overhead 4% of cost of sales ₹ 68,000
Last year 5,000 units were sold at ₹ 185 per unit.
You being an associate to cost controller of the A Ltd., is expected to answer the followings:
6. The following information pertains to ABC Limited for the period 1st April, 2024 to 31 st March,
2025
Sl. Particulars Amount
No. (₹)
1 Royalty paid for production 7,76,400
2 Amount paid for power & fuel 2,15,200
3 Packing cost paid for re-distribution of Finished Goods 70,500
4 Repairs & Maintenance paid for :
Plant & Machinery 65,000
Sales office building 80,000
Total 1,45,000
5 Insurance premium paid for Plant & Machinery 1,17,520
6 Research & Development cost paid for improvement in production process 17,800
7 Depreciation on office building 75,500
8 Salary paid to General Manager 15,50,000
9 Salary & bonus paid to Sales & Marketing staff 11,40,500
10 Receipt from sale of scrap and waste generated during production 20,000
11 Value of stock as on 1st April, 2024:
Raw materials 5,00,000
Overhead costs are another crucial aspect of SpeedX Automotive's financial strategy. Factory
overheads amount to 60,000, covering all indirect manufacturing expenses. Administration
overheads are managed efficiently at ₹ 20,000. Selling and distribution overheads are maintained
at 10,000, ensuring that products reach the market effectively. Quality control, vital for
maintaining the company's reputation, is allocated ₹ 5,000, while ₹ 10,000 is dedicated to research
and development, highlighting their focus on innovation. Inventory management is key to SpeedX
Automotive's financial health. The opening stock of raw materials stands at ₹ 50,000. The work-in-
process inventory starts at ₹ 15,000 and is increased to ₹ 35,000, indicating a smooth production
flow.
For finished goods, the company maintains an opening stock worth ₹ 30,000, adjusted to a closing
stock value of ₹ 25,000, showcasing their agile response to market demands. Throughout the period,
SpeedX Automotive's manufacturing expertise is evident as they successfully produce 4,000 units.
Of these, 3,800 units are sold at a price of ₹ 100 per unit. Additional Information: During the
period, the price of raw materials fluctuated. At the beginning of the period, the price was ₹ 10
per unit. Midway through the period, the price increased to ₹ 12 per unit. The company could only
purchase 10,000 units at the lower price of ₹ 10 per unit. Raw material consumed was 14,000 units.
Company follows FIFO method for inventory valuation.
5. What is the cost per unit of goods sold if 3,800 units were sold?
(a) ₹ 91.11
(b) ₹ 94.74
(c) ₹ 84.21
(d) ₹ 97.45
8. ZEN Manufacturing Pvt. Ltd., headquartered in Pune, Maharashtra, is a mid-sized but rapidly
growing enterprise specializing in the production of precision-engineered automobile components
tailored specifically for the electric vehicle (EV) industry. With India’s EV segment witnessing
exponential growth driven by sustainability goals and government incentives, ZEN has emerged as
a trusted Tier-2 supplier to some of the country’s leading electric vehicle manufacturers.
The company operates with a mission to deliver high-quality, durable, and technologically advanced
components that meet stringent safety and efficiency standards. Its operations encompass R&D,
material procurement, in-house manufacturing, and logistics support — all backed by a strong team
of engineers, production planners, and administrative personnel.
Inventory details:
Particulars As on 01-04-2024 (₹) As on 31-03-2025 (₹)
Raw Materials 7,10,000 5,40,000
Work-in-Progress 8,50,000 7,25,000
Finished Goods 16,20,000 11,80,000
1. What is the Prime Cost of ZEN Manufacturing Pvt. Ltd. for the year ended 31st March
2025?
(a) ₹ 2,16,90,000
(b) ₹ 2,18,90,000
(c) ₹ 2,13,10,000
(d) ₹ 2,09,60,000
4. What is the Cost of Goods Sold (COGS) for ZEN Manufacturing Pvt. Ltd. in FY 2024-
25?
(a) ₹ 2,54,20,000
(b) ₹ 2,58,60,000
(c) ₹ 2,95,95,000
(d) ₹ 3,12,80,000
2. (b) ₹ 14,95,000
Statement of Cost
Particulars Amount (₹)
Direct Material Consumed ?
Add: Direct Wages 11,44,000
Prime Cost = Material Consumed + 11,44,000
Add: Factory Overheads (20% of Prime Cost) 0.20 × Prime Cost
Factory Cost = Prime Cost + Factory Overheads
Add: Warehousing Charges 61,750
Less: Realisable value of Scrap (32,500)
Cost of Production = Factory Cost + 61,750 – 32,500
Add: Office & Admin Exp. (Salary + Maintenance) 1,78,750 + 13,000 = 1,91,750
Add: Selling & Distribution Exp. (Depreciation + 39,000
Delivery + Warehouse etc.)
Cost of Sales (Given) 37,51,540
Now, working backwards:
Let Prime Cost = X
Then,
Factory Overheads = 20% of X = 0.2X
Factory Cost = X + 0.2X = 1.2X
Total Cost of Sales = Factory Cost + Office & Selling Exp – Scrap + Warehouse
= 1.2X + (1,91,750 + 61,750 + 39,000) – 32,500
= 1.2X + 2,60,000
Given,
Cost of Sales = 37,51,540
⇒ 1.2X + 2,60,000 = 37,51,540
⇒ 1.2X = 34,91,540
⇒ X = 29,09,617
Direct expenses:
Power 13000 kwh × 8/kwm ₹ 1,04,000
Disesel 2000 Ltrs × 93 / Ltr ₹ 1,86,000
Hiring changes for HEMM ₹ 30,00,000 32,90,000
Prime Cost 7,87,10,0000
Factory overheads: AMC of CCTV @ Factory 18,000
Gross factory cost/Net factory cost/ 7,87,28,000
Cost of production/Cost of goods sold.
1.(d) ₹ 7,87,10,000
refer solution above.
3.(a) ₹ 92,400
General Administration Overheads
hiring charges for cars 66,000
Reimbursement of diesel 22,000
88,000
+ GST on RCM basis @ 5% of 88000 4400
Total General Admini O/H 92,400
7. 1. (c) 40,000
Calculate units at each price:
Units at 10 per unit: 10,000 units
Cost for these units: 1,00,000
Remaining cost for units at ₹ 12 per unit: ₹ 130,000 - ₹ 100,000 = 30,000
Units at ₹ 12 per unit: ₹ 30,000/12 = 2,500 units
Total units purchased: 10,000 + 2,500 = 12,500 units
2. (b) ₹ 315,000
Cost of Production = Prime Cost + Factory Overheads + Quality Control Costs + Research and
Development Costs + Opening WIP – Closing WIP
Prime Cost = Direct Materials Consumed + Direct Labor + Direct Expenses
= (140,000 + 90,000 + 30,000) + 60,000 + 5,000 + 10,000 - 20,000 (WIP adjustment) = 315,000.
3. (a) 320,000
Cost of Goods Sold = Cost of Production + Opening Stock of Finished Goods - Closing Stock of
Finished Goods
= ₹ 315,000 + ₹ 30,000 - ₹ 25,000 = ₹ 320,000
4. (a) 350,000
Cost of Sales = Cost of Goods Sold + Administration Overheads + Selling and Distribution
Overheads
= ₹ 320,000 + ₹ 20,000 + ₹ 10,000 = ₹ 350,000
8. 1. (a) 2,16,90,000
2. (a) ₹ 2,29,50,000
3. (c) ₹ 2,54,20,000
4. (b) ₹ 2,58,60,000
5. (b) ₹ 16,85,000
Working Note:
Sl. Particulars Amount (₹) Amount (₹)
No.
(i) Material Consumed: 1,00,35,000
- Raw materials purchased 96,50,000
- Carriage inward 2,15,000
Add: Opening stock of raw materials 7,10,000
Less: Closing stock of raw materials (5,40,000)
(ii) Direct employee (labour) cost: 80,80,000
- Direct wages 72,80,000
- Employer's Contribution towards PF & ESIS 8,00,000
(iii) Direct expenses: 35,75,000
- Consumable materials 5,25,000
- Electricity & fuel 30,50,000
Prime Cost 2,16,90,000
(iv) Works/ Factory overheads: 11,35,000
- Wages to floor supervisors and store assistants 9,60,000
- Other indirect wages to factory staffs 1,75,000
Gross factory cost 2,28,25,000
Add: Opening value of W-I-P 8,50,000
Less: Closing value of W-I-P (7,25,000)
Factory Cost 2,29,50,000
(v) Research & development cost paid for 11,20,000
improvement in production process
(vi) Production planning office expenses 13,50,000
Cost of Production 2,54,20,000
Add: Opening stock of finished goods 16,20,000
Less: Closing stock of finished goods (11,80,000)
Cost of Goods Sold 2,58,60,000
1. The following information has been obtained from financial accounting and cost accounting
records.
Financial Accounting Cost Accounting
₹ ₹
(i) Factory Overhead 94,750 90,000
(ii) Administrative Overhead 60,000 57,000
(iii) Selling Overhead 55,000 61,000
(iv) Opening Stock 17,500 22,500
(v) Closing Stock 12,500 15,000
Required:
Indicate under-recovery and over-recovery and their effects on cost accounting profit.
[Note: You are not required to prepare reconciliation statement.]
2. Which of the following item is not the cause of differences in Financial and Cost Accounts?
(a) Income tax not treated in Cost Accounts
(b) Dividends credited in Financial Accounts
(c) Losses on the sale of investments not treated in Financial Accounts
(d) Cost Accounts showing notional depreciation on the assets fully depreciated for which book
value is nil
3. A company which operates a batch costing system is fully integrated with the financial accounts.
During a particular period, materials worth ₹30,000 and ₹20,000 were issued to production and
Factory Maintenance respectively. The following control A/cs are being maintained:
i. Store ledger control A/c
ii. Work-in-progress control A/c
iii. Production overhead control A/c
iv. Finished goods control A/c
From the above information, identify which account/accounts will be debited to effectuate the
issuance of materials:
a) (i) and (ii)
b) (ii) and (iii)
c) (iii) and (iv)
d) Only (i)
4. WHICH of the following is the correct journal entry as would appear in the cost books when
1. A company uses batch costing and incurs a setup cost of ₹ 20,000 for a batch of 300 units. If
direct materials cost ₹ 20 per unit and direct labor costs ₹ 10 per unit, what is the total cost of
the batch?
(a) ₹ 25,000 (b) ₹ 29,000
(c) ₹32,000 (d) ₹ 7,000
2. A FMCG company has an annual demand of 50,000 units for its specific product whose setting up
cost per batch is ₹ 10,000 and carrying cost per unit per month is ₹ 1. What is the Economic
Batch Quantity?
(a) 7,071 units (b) 10,000 units
(c) 12,641 units (d) 9,129 units
3. A customer has been ordering 80,000 caps during the year. It is estimated that it costs ₹ 1 as
inventory holding cost per cap per month and that the set up cost per run of cap manufacture is
₹ 3,500. What is optimum run size of cap manufacture?
(a) 6831 units (b) 23664 units
(c) 404 units (d) 548 units
4. Pari Ltd. operates in beverages industry where it manufactures soft-drink in three sizes of Large
(3 litres), Medium (1.5 litres) and Small (600 ml) bottles. The products are processed in batches.
The 5,000 litres capacity processing plant consumes electricity of 90 Kilowatts per hour and a
batch takes 1 hour 45 minutes to complete. Only symmetric size of products can be processed at
a time. The machine set-up takes 15 minutes to get ready for next batch processing. During the
set-up power consumption is only 20%.
(i) The current price of Large, Medium and Small are ₹ 150, ₹ 90 and ` 50 respectively.
(ii) To produce a litre of beverage, 14 litres of raw material-W and 25 ml of Material-C are
required which costs ₹ 0.50 and ` 1,000 per litre respectively.
(iii) 20 direct workers are required. The workers are paid ` 880 for 8 hours shift of work.
(iv) The average packing cost per bottle is ` 3
(v) Power cost is ` 7 per Kilowatt-hour (Kwh)
(vi) Other variable cost is ` 30,000 per batch.
(vii) Fixed cost (Administration and marketing) is ₹ 4,90,00,000.
(viii) The holding cost is 1 per bottle per annum.
The marketing team has surveyed the following demand (bottle) of the product:
Large Medium Small
3,00,000 7,50,000 20,00,000
2× 50,000 ×10,000
= 9128.7 or 9129 units
1 × 12
3.(b) 1,68,00,000
Small size bottles needed 20,00,000
× Qty Per bottle 600 mL
Total Litres needed 12,00,000
1 Ltr beverage – 14 Litres of raw material w.
120,000 Litres 1,68,00,000 Litres of material req.
4. (a) ₹89,03,880
Batch size: 5,000 litres ÷ 3 litres = 1,667 bottles per batch
70 CA/CS Nimeet Piti | | |
Selling price per bottle: ₹150
Revenue per batch
= 1,667 × 150 = ₹2,50,050
Cost per batch
Particulars Working
Raw material W 14 litres × 0.50 × 5,000 = 35,000
Material C 0.025 litre × 1,000 × 5,000 = 1,25,000
Direct labour 20 workers × (880 ÷ 8 × 1.75 hrs) = 3,850
Power 90 kW × 1.75 hrs × 7 = 1,102.5
Set-up power (15 min × 20%) 90 × 0.25 × 7 = 157.5
Packing cost 1,667 × 3 = 5,001
Other variable cost 30,000
Total variable cost per batch ₹2,00,111
Profit per batch (before fixed cost):
₹2,50,050 – ₹2,00,111 = ₹49,939 per batch
Annual demand = 3,00,000 bottles ⇒ 180 batches (3,00,000 ÷ 1,667)
Total profit before fixed cost: ₹49,939 × 180 = ₹89,89,020
Less fixed cost ₹4,90,00,000 × (180 / total batches) negligible for per batch
5. (c) 3,46,592
Given:
• Demand (D) = 20,00,000 bottles
• Setup cost (S) = ₹30,000
• Holding cost (H) = ₹1 per bottle per annum
2𝐷𝐶 2×20,00,000×30,000
EBQ = √ 𝐻
=√ 1
= √1.2 × 1011 = 3,46,410 ≈ 3,46,592
1. A product passes through Process-I. Input raw material issued were 8,000 units. Normal loss
anticipated was 10% of input with realisable value of ₹ 5 per unit. 7,600 units of output were
produced and transferred to next process. If the total cost incurred under Process-I was
₹ 40,000, then amount of abnormal gain/(loss) is:
(a) ₹ 2,000 (b) (₹ 5,000) (c) (₹2,500) (d) ₹ 3,000
2. 1,200 Kg of a material were input to a process in a period. The normal loss is 8% of input
There is no opening or closing work-in-progress. Output in the period was 1,100 Kg. What was the
abnormal gain/loss in the period?
(a) Abnormal gain of 12 Kg (b) Abnormal loss of 12 kg
(c) Abnormal gain of 108 Kg (d) Abnormal gain of 4 kg
3. The following information is available in respect of Process I: Raw material purchased and
introduced 10,000 units @ 5 per unit Raw Material received from store 4000 units @ 6 per unit
Direct Labour 40,000 Overheads 28,000 Output of Process is 13,500 units, Normal wastage 5%
of inputs Scrap value of wastage 4 per unit
The value of Abnormal Gain is:
(a) ` 2062.68
(b) ` 2135.34
(c) ` 2103.70
(d) ` 2093.2
4. A product passes through Process-I and Process-II. Materials issued to Process-I amounted to
₹ 1,60,000. Wages ₹ 70,000 and Manufacturing Overheads ₹ 58,000 were charged to Process
I. Anticipated normal loss was 6% of input. 9,200 units of output were produced and transferred
to Process-II. There was no opening stock. Input of raw material issued to Process-I was 10,000
units. Scrap has a realizable value of ₹ 10 per unit.
What is the value of units transferred to Process-II?
(A) ₹ 2,76,000
(B) ₹ 2,82,000
(C) ₹ 2,88,000
(D) ₹ 2,78,000
7. Arnav Ltd. manufactures chemical solutions used in paint and adhesive products. Chemical
solutions are produced in different processes. Some of the processes are hazardous in nature
which may results in fire accidents.
At the end of the last month, one fire accident occurred in the factory. The fire destroyed some
of the paper files containing records of the process operations for the month.
You being an associate to the Chief Manager (Finance), are assigned to prepare the process
accounts for the month during which the fire occurred. From the documents and files of other
sources, following information could be retrieved:
Opening work-in-process at the beginning of the month was 500 litres, 80% complete for labour
and 60% complete for overheads. Opening work-in- process was valued at ₹ 2,78,000.
Closing work-in-process at the end of the month was 100 litres, 20% complete for labour and 10%
complete for overheads.
Normal loss is 10% of input (fresh) and total losses during the month were 800 litres partly due
to the fire damage.
Output transferred to finished goods was 3,400 litres.
Losses have a scrap value of ₹ 20 per litre.
All raw materials are added at the commencement of the process.
The cost per equivalent unit is ₹ 660 for the month made up as follows:
Raw Material ₹ 300 Labour ₹ 200 Overheads ₹ 160
The company uses FIFO method to value work-in-process and finished goods.
3. Value of raw material added to the process during the month is:
(a) ₹ 10,10,000 (b) ₹ 10,33,600
(c) ₹ 10,18,400 (d) ₹ 10,20,000
8. The following data are available in respect of Process-l for January 2024:
(1) Opening stock, of work in process: 600 units at a total cost of ₹ 4,200.
(2) Degree of completion of Opening work in process:
Material - 100%
Labour - 60%
Overheads - 60%
(3) Input of materials at a total cost of ₹ 55,200 for 9,200 units.
(4) Direct wages incurred ₹ 18,600
(5) Overheads ₹ 8,630.
(6) Units scrapped 200 units. The stage of completion of these units was:
Materials - 100%
Labour - 80%
Overheads - 80%
(7) Closing work in process; 700 units. The stage of completion of these units was:
Material - 100%
Labour - 70%
Overheads - 70%
(8) 8,900 units were completed and transferred to the next process.
(9) Normal loss is 4% of the total input (opening stock plus units put in)
5. What is the cost of the units to be transferred to the next process using the FIFO method?
(a) ₹ 50,900.15 (b) ₹ 80,303.20
(c) ₹ 80,800.36 (d) ₹ 50,300.80
9. Knowing the hectic schedule of a student preparing for the examination, a homemaker managing
work from home or a new parent busy in neonatal care, a freshly qualified professional (Mr. Rishi)
entered into a start-up business of manufacturing frozen foods.
The process majorly involve washing and cutting the vegetables (Process I), blanching, cooling and
mixing of ingredients with spices (Process II), forming, frying and freezing the final product
(Process III).
In Accounts, Mr. Rishi normally transfers the output of one process to another process at cost
but, being a young entrepreneur, he is interested in knowing the profit made at each and every
process.
Thus, it was decided to transfer the output of Process I and II to the next process at cost plus
25%. Further, the output of Process III is also transferred to finished stock at cost plus 33
1/3%.
Following information is extracted from the books of Mr. Rishi for the current year:
Process I Process II Process III Finished
(`) (`) (`) Stock
(`)
Opening stock 8,02,500 14,44,500 21,40,000 24,07,500
Stock in processes is valued at prime cost. The finished stock is valued at the price at which it is
received from Process III.
Mr. Rishi wants you to FIGURE OUT the following to analyse the profit generated at each process:
1. What is the transfer price value at which the output of Process I is trans-ferred to Process II?
(a) ` 1,97,95,000 (b) ` 39,59,000
(c) ` 1,58,36,000 (d) ` 1,69,06,000
2. What is the transfer price value at which the output of Process II is trans-ferred to Process
III?
(a) ` 1,20,97,476 (b) ` 4,07,93,750
(c) ` 2,86,96,274 (d) ` 3,43,47,000
3. What is the transfer price value at which the output of Process III is transferred to Finished
Stock?
(a) ` 5,40,88,500 (b) ` 3,98,91,140
(c) ` 2,94,44,860 (d) ` 6,93,36,000
4. What is the cost value at which the output of Process III is transferred to Finished Stock?
(a) ` 5,40,88,500 (b) ` 3,98,91,140
(c) ` 2,94,44,860 (d) ` 6,93,36,000
3. (a) ₹2,062.68.
Total inputs = 10,000 + 4,000 = 14,000 units
Normal wastage = 5% of 14,000 = 700 units
Expected output after normal wastage = 14,000 − 700 = 13,300 units
Actual output = 13,500 units ⇒ Abnormal gain = 13,500 − 13,300 = 200 units
Total cost of inputs = (10,000×5) + (4,000×6) + 40,000 + 28,000 = ₹1,42,000
Scrap value of normal wastage = 700 × 4 = ₹2,800
Net cost to be borne by good output = 1,42,000 − 2,800 = ₹1,39,200
Cost per good unit = 1,39,200 ÷ 13,500 = ₹10.3111...
Value of abnormal gain = 200 × 10.3111... = ≈ ₹2,062.22
4. (A) ₹ 2,76,000
Choice 'A' is correct as--
Total cost in Process-I = Materials (₹1,60,000) + Wages (₹70,000) + Overheads (₹58,000) =
₹2,88,000
Normal loss = 6% of 10,000 units = 600 units, scrap value = 600 × ₹20 = ₹12,000
Net cost = ₹2,88,000 – ₹12,000 = ₹2,76,000
7. Basic Working:
Particulars Units Particulars Units
To Opening WIP 500 By NL
800
Material introduced 3800 Ab Loss
Trf → 3400
Clg WIP → 100
Normal Loss : 10% of Input = 3800 × 10% = 380 Ltrs
Abnormal Loss : Total Loss – Abnormal Loss = 800 – 380 = 420 Ltrs
9. 1. Process I Account
Option (a) 1,97,95,000
Particulars Cost (₹) Profit (₹) Total (₹) Particulars Cost (₹) Profit (₹) Total (₹)
Opening Stock 8,02,500 - 8,02,500 Process II 1,58,36,000 39,59,000 1,97,95,000
A/c
(Transfer)
Direct 42,80,000 - 42,80,000 Closing 10,70,000 - 10,70,000
Material Stock
Direct Wages 66,87,500 - 66,87,500
Prime Cost 1,17,70,000 - 1,17,70,000
Manufacturing 51,36,000 - 51,36,000
Overheads
Total Cost 1,69,06,000 - 1,69,06,000
Costing P&L - 39,59,000 39,59,000
A/c**
Total 1,69,06,000 39,59,000 2,08,65,000 Total 1,69,06,000 39,59,000 2,08,65,000
2,63,22,000
*Cost of Closing Stock = 3,04,95,000
× 17,12,000 = =14,77,726
*Transfer Price
=(Total Cost−Closing Stock)×(1+25%)
=(3,43,47,000−17,12,000)×1.25
=4,07,93,750
*Profit on Transfer
=(3,43,47,000−17,12,000)×0.25
=81,58,750
Calculations
*Cost of Closing Stock:
3,78,98,274
= × 20,86,500 = 15,64,884
5,05,30,750
***Profit on Transfer:
=(5,40,88,500−20,86,500)×33.33%
=1,73,34,000
1. In a company’s production process, two joint products, A and B, are created simultaneously.
The company operates in the manufacturing sector, focusing on producing goods that require
multiple stages of production, often resulting in the creation of joint products that share common
production costs up until a certain split-off point. For the last month, the following information is
provided relating to the inventory and sales:
Product Sales (units) Opening Stock (units) Closing Stock (units)
A 1,14,000 1,900 5,700
B 76,000 7,600 3,800
Joint production costs for the last month amounted to ₹ 20,90,000. These costs were allocated
between both the joint products, A and B, based on the number of units produced.
This method of apportioning costs ensures that each product is fairly charged for its share of
the overall production expenses. CALCULATE the joint production costs apportioned to product
A for last month?
(a) ₹ 12,12,200
(b) ₹ 12,54,000
(c) ₹ 12,95,800
(d) ₹ 13,58,500
2. A company produces two joint products - X and Y, using the same type of material. The cost data
to produce 200 units of product X and 400 units of product Y are as under :
Material: ₹ 80,000
Labour: ₹ 40,000
Fixed overheads: ₹ 20,000
Sales of product X was 200 units @ ₹ 350 per unit and product Y was 400 units @ ₹ 250 per unit.
Using the Contribution margin method, in what ratio fixed overheads will be apportioned between
Product X and Product Y?
(a) 4 : 8
(b) 3 : 2
(c) 2 : 3
(d) 8 : 4
3. eSalt is the biggest producer of sodium hydroxide in India. This main product of the company has
a strong reactivity with other organic compounds. It is highly versatile and is alkaline in nature.
However, the basic material required for the production of this product is salt along with the
electricity.
During the current year, the management of the company pointed the extensive use of Vinyl which
can be produced by further processing Halogen. Having selling price of ₹ 250 per tonne higher
than that of the Halogen, it was decided not to sell Halogen and further process it into Vinyl. The
incremental processing cost took ₹ 8,01,000 producing 10,012.50 tonnes of Vinyl.
1. For the current year, the amount of base material purchased and the conversion cost up to
the point at which two products i.e. Sodium hydroxide and Halogen are separated would be:
(a) base material ₹ 10,68,000 and conversion cost ₹ 24,03,000
(b) base material ₹ 10,68,000 and conversion cost ₹ 16,02,000
(c) base material ₹ 16,02,000 and conversion cost ₹ 24,03,000
(d) base material ₹ 24,03,000 and conversion cost ₹ 16,02,000
2. Joint cost to be apportioned between Sodium hydroxide and Halogen as per the physical
unit method would be:
(a) Sodium hydroxide ₹ 24,03,000 and Halogen ₹ 10,68,000
(b) Sodium hydroxide ₹ 10,68,000 and Halogen ₹ 16,02,000
(c) Sodium hydroxide ₹ 16,02,000 and Halogen ₹ 24,03,000
(d) Sodium hydroxide ₹ 24,03,000 and Halogen ₹ 16,02,000
3. Joint cost to be apportioned between Sodium hydroxide and Halogen as per the sales value
at split- off point method would be:
(a) Sodium hydroxide ₹ 20,02,500 and Halogen ₹ 20,02,500
(b) Sodium hydroxide ₹ 16,02,000 and Halogen ₹ 24,03,000
(c) Sodium hydroxide ₹ 24,03,000 and Halogen ₹ 16,02,000
(d) Sodium hydroxide ₹ 10,68,000 and Halogen ₹ 20,02,500
5. Considering that the decision relating to further processing Halogen is not approved,
suggest whether this would be in favour of the management by calculating incremental
revenue /loss from further processing Halogen into Vinyl.
(a) Incremental loss would be ₹ 16,02,000, thus the decision of not further processing
Halogen is correct.
(b) Incremental loss would be ₹ 8,01,000, thus the decision of not further processing
Halogen is correct.
(c) Incremental revenue would be ₹ 8,01,000, thus the decision relating to further
processing Halogen needs to be approved.
(d) Incremental revenue would be ₹ 16,02,000, thus the decision relating to further
processing Halogen needs to be approved.
2. (B) 3 : 2
Sales of X = 200 × 350 = 70,000
Sales of Y = 400 × 250 = 1,00,000
Total Sales = 1,70,000
Variable Cost = Material 80,000 + Labour 40,000 = 1,20,000
Per unit variable cost = 1,20,000 ÷ 600 = 200
Variable cost of X = 200 × 200 = 40,000
Variable cost of Y = 400 × 200 = 80,000
Contribution of X = 70,000 – 40,000 = 30,000
Contribution of Y = 1,00,000 – 80,000 = 20,000
Ratio of Contribution = 30,000 : 20,000 = 3 : 2
Hence, fixed overheads are apportioned in the ratio 3 : 2.
40,05,000
For Halogen = 40,050 𝑡𝑜𝑛𝑛𝑒𝑠 × 16,020 𝑡𝑜𝑛𝑛𝑒𝑠 = ₹ 16,02,000
₹ 40,05,000
For Sodium hydroxide = × 24,03,000 = ₹ 17,16,429
₹ 56,07,000
₹ 40,05,000
For Halogen = × 32,04,000 = ₹ 22,88,571
₹ 56,07,000
1. ALC Ltd. is a insurance company. It launched a new term insurance policy Named as Protection
Plus. The total cost for the policy during the year is ₹ 1,60,00,000. Total number of policies sold
are 410 and total insured value of policies is ₹ 920 crore.
What is the cost per rupee of insured value?
(a) ₹ 0.0017 (b) ₹ 0.18
(c) ₹ 575 (d) ₹ 2.24
3. A hotel has 200 rooms (120 Deluxe rooms and 80 Premium rooms). The normal occupancy in
summer is 80% and winter 60%. The period of summer and winter is taken as 8 months and 4
months respectively. Assume 30 days in each month. Room rent of Premium room will be double
of Deluxe room. Hotel is expecting a profit of 20% on total revenue, total cost for the year is
2,66,11,200. Calculate the room rent to be charged for Premium room.
(a) ₹ 450 per room day (b) ₹ 900 per room day
(c) ₹ 380 per room day (d) ₹ 760 per room day
4. Find out the most appropriate unit cost from the following information of ZMD Transport
Services Ltd. dealing in goods carriage:
Total cost ₹ 5,25,000
Kms. Travelled 8,75,000
Tonnes carries 4,000
No. of Drivers 25
No. of trucks 20
Tonnes Km carried 6,55,000
(a) ₹ 0.6 (b) ₹ 0.8
(c) ₹ 21,000 (d) ₹ 131.25
5. A truck carrying 10 tons of goods over 200 kilometres per day for 26 days in a month. The ton
kms applicable is -
(a) 52,000 (b) 20,000
(c) 5200 (d) 260
7. A LMV Pvt. Ltd, operates cab/ car rental service in Delhi/NCR. It provides its service to the
offices of Noida, Gurugram and Faridabad. At present it operates CNG fuelled cars but it is also
considering to upgrade these into Electric vehicle (EV). The following details related with the
owning of CNG & EV propelled cars are as tabulated below:
Particulars CNG Car EV Car
Car purchase price (₹) 9,20,000 15,20,000
Govt. subsidy on purchase of car (₹) -- 1,50,000
Life of the car 15 years 10 years
Residual value (₹) 95,000 1,70,000
Mileage 20 km/kg 240 km per charge
Electricity consumption per Full charge -- 30 Kwh
CNG cost per Kg (₹) 60 --
Power cost per Kwh (₹) -- 7.60
Apart from the above, the following are the additional information:
Particulars
Average distance covered by a car in a month 1,500 km
Driver’s salary (₹) 20,000 p.m
Garage rent per car (₹) 4,500 p.m
Share of Office & Administration cost per car (₹) 1,500 p.m
You have been approached by the management of A LMV Pvt. Ltd. for consultation on the two
options of operating the cab service. The expected questions that may be asked by the
management are as follows:
1. What would be the depreciable value of CNG Car and EV Car respectively?
(a) ₹ 13,50,000 and ₹ 14,40,000
(b) ₹ 15,20,000 and ₹ 8,25,000
(c) ₹ 8,25,000 and ₹ 14,40,000
(d) ₹ 8,25,000 and ₹12,00,000
2. What would be the monthly cost of fuel and electricity for an CNG and EV car respectively?
(a) ₹ 4,500 and ₹ 1,425 (b) ₹ 1,500 and ₹ 4,500
(c) ₹1,525 and ₹ 1,450 (d) ₹ 1,525 and ₹ 1,425
3. What would be the total cost to be incurred for replacement of tyres for CNG and EV car
respectively?
(a) ₹ 222.22 and ₹ 333.33 (b) ₹ 177.78 and ₹ 133.33
(c) ₹ 155.55 and ₹ 133.33 (d) ₹ 177.78 and ₹ 111.11
4. What would be the total cost to be incurred for replacement of battery for CNG and EV car
respectively?
(a) ₹ 5,40,000 and ₹ 12,000 (b) ₹ 12,000 and ₹ 5,40,000
(c) ₹ 2,00,000 and ₹ 12,000 (d) ₹ 1,00,000 and ₹2,00,000
5. What would be the operating cost of vehicle per month per car for both CNG & EV options?
(a) ₹ 36,627.78 and ₹ 43,708.33 (b) ₹ 36,627.78 and ₹ 48,523.26
(c) ₹ 48,523.26 and ₹ 28,510.29 (d) ₹ 48,523.26 and ₹ 28,510.29
Raju is excited to accept the order but it is not physically possible for Raju to complete this project
alone. He decides to hire a helper cum driver who will assist him in this work contract and will also
drive in turns with Raju. Thus, such a long contract will be managed comfortably. This helper will
take ₹ 15,000 per month.
The contract will start from 15th June, 2024 and will run till 14th September, 2024. Throughout
this time period there are only 2 days holidays, both falling in August (1 for Independence Day and
1 for Raksha Bandhan).
1. What would be the amount of profit Raju would have earned if he had no minimum charges
limit of 75% of total capacity on absolute Tonne-km basis? (If the vehicle runs empty then he
would only charge for Diesel expenses).
(a) 3,34,249 (b) 4,43,249
(c) 5,96,977 (d) 4,34,249
2. If payment was made on commercial Tonne-km basis and Raju had no minimum charges limit
of 75%, how much he would have lost due to no minimum requirement?
3. What should be the minimum amount charged on basis of absolute Tonne-km if Raju wants to
earn ₹ 2,70,000?
(a) ₹ 4.58 (b) ₹ 6.13
(c) ₹ 8.39 (d) ₹ 3.21
4. Choose the correct amount of depreciation and interest that should be charged to this work
contract.
(a) 56,983 & 22,588 (b) 36,986 & 22,578
(c) 63,963 & 12,568 (d) 63,953 & 12,558
5. What is the profit as per current rate charged by Raju? (Use absolute Tonne-Km).
(a) 7,34,249 (b) 9,44,863
(c) 5,96,977 (d) 4,34,249
1.6cr
=
920cr.
= ₹ 0.0017
2. (a) 21,60,000
200 rooms
Summer Winter
8 months/240 days 4 months/120 days
Occupancy : 80% occupancy: 60%
Deluxe: 120 rooms × 80% = 96 rooms Deluxe: 120 rooms × 60% = 72 rooms
Premium: 80 rooms × 807. = 64 rooms Premium: 80 rooms × 60% = 48 rooms
73920x = 3,32,64,000
x = 450
Rent of a premium room = 2x = 2 (450) = 900 per room day
5. (b) 0.8
Total cost ₹ 5,25,000
6,55,000
6. (a) 52,000
10tons × 200 kms × 26 days = 52000 ton-kms
7. (b) Marketing and Sales support– ₹28,62,01,000, Operations– ₹22,53,88,500, I.T. Cost–
₹30,71,90,000 and Support functions– ₹15,42,20,500
28,62,01,000
Operations:
18,03,52,500
c. IT Cost 30,71,90,000
d. Postage-and-logistics 4,50,36,000
19,92,56,500
CNG EV
8. 1. C. 5,96,977
Profit if no minimum charges are there, on absolute tonne basis, but he will charge for diesel petrol
when running empty Absolute tonne-kms: (250 kms x 4 tonnes + 150 kms x 3 tonnes) x 90 days =
1,30,500 tonne-kms Vacant moving (Chandigarh to Ludhiana) = 100kms x 90 days = 9,000 kms
Charges for vacant running:
Monthly Charges Calculation
Calculation (₹)
June (80.30×16×100)/8 16,060
July (80.50×31×100)/8 31,194
August (81.25×29×100)/8 29,453
September (80.90×14×100)/8 14,158
Total Charges 90,864
Profit Calculation
Description (₹)
Total revenue (1,30,500×10) 13,05,000
Add: diesel recovery for vacant running 90,864
Less: service & maintenance (80,000×3) (2,40,000)
Less: salary (15,000×3) -45,000
Less: diesel cost (4,54,323)
Less: interest -22,578
Less: depreciation -36,986
Profit 5,96,977
Diesel expenses:
June (80.30 x 16 x 500)/8 80,300
July (80.50 x 31 x 500)/8 1,55,969
August (81.25 x 29 x 500)/8 1,47,266
September (80.90 x 14 x 500)/8 70,788
Total diesel expenses 4,54,322
2. A. ₹ 6,37,500
With minimum limit (₹) Without minimum limit (₹)
Commercial tonne kms 3.75 x 500 x 90 ((4+0+3)/3) x 500 x 90
= 1,68,750 = 1,05,000
revenue 1,68,750 x 10 1,05,000 x 10
= 16,87,500 = 10,50,000
Less: costs (7,98,887) (7,98,887)
Profit/(loss) 8.88,613 2,51,113
Loss arising due to no minimum limit = 8,88,613-2,51,113 = 6,37,500
3. B. ₹ 6.13
Total Revenue = Cost + Profit = 7,98,887+ 2,70,000 = ₹ 10,68,887 Absolute Tonne-Kms = 1,74,375
Rate = 10,68,887/1,74,375 = ₹ 6.13
1. In a period, 5640 kg of material were used at a total standard cost of ₹ 23,124. The material
usage variance was ₹ 246 adverse. What was the standard allowed weight of material for the
period?
(a) 5580 (b) 5520
(c) 5850 (d) 5250
2. The Budgeted fixed overhead for the month of August was ₹75,00,000 with the units of production
estimated at 15,000. However, the actual units produced is 15,600 with no Fixed overhead cost
variance. CALCULATE the actual fixed overhead incurred.
(A) ₹75,00,000
(B) ₹72,11,538
(C) ₹78,00,000
(D) ₹79,00,000
3. A furniture company uses premium wood for sofa. Standard quantity of premium wood per sofa is
5 sq. ft. Standard price per sq. ft. of premium wood is ₹ 10. Actual production of sofa is 1,000.
Premium wood actually used is 5,300 sq. ft. Actual purchase price of premium wood per sq. ft. is
₹ 10. What is material cost variance?
(a) ₹ 3,000 (A) (b) ₹ 4,300 (A)
(c) ₹ 7,300 (A) (d) ₹ 5,300 (F)
4. The wages budget for the last period was based on a standard repair time of 30 minutes per unit
and a standard wage rate of ₹ 50 per hour. The actual data for the last period are as follows:
Number of units = 30,000
Labour rate variance = 7,500 (A)
Labour efficiency variance = Nil
From the information find out the actual rate of wages per unit
(a) ₹ 50 (b) ₹ 25.50
(c) ₹ 50.50 (d) ₹ 25.25
6. The Cost Accountant of AQ Limited has provided the following information for investigation of
variances:
Amount
Material Cost Variance ₹ 4,220 (F)
Material Usage Variance ₹ 18,540 (A)
Material Yield Variance ₹ 8,390 (F)
The Management Accountant is not able to comment on the reason of variances as information is
not sufficient and seeks your help to find out the correct amount of Material Price Variance and
Material Mix Variance. What is the correct amount of Material Price Variance (MPV) and Material
Mix Variance (MMV) ?
(A) MPV ₹ 24,880 (A) and MMV ₹ 27,440 (F)
(B) MPV ₹ 14,320 (A) and MMV ₹ 10,150 (F)
(C) MPV ₹ 14,320 (F) and MMV ₹ 10,150 (A)
(D) MPV ₹ 22,760 (F) and MMV ₹ 26,930 (A)
8.
ABC Pvt Ltd is engaged in the manufacture of a Product Q. The product has the following standard
production requirements determined by the technical team of the company post satisfactory
completion of test run.
Raw Material Z - 2 units @ ₹ 2 per unit
Skilled labour of - 2.5 hours@ ` 5 per hour
Fixed Overheads - ₹7.5 per unit
The input of Raw material Z has a yield of 80% every time when infused into production. The
actual quantity of Raw material Z consumed for production during the year was 24,000 units. The
(iii) The Standard Hours, Net Actual hours and the idle time are:
(a) Standard Hours 27,500 Net Actual Hours 28,000 hours Idle Time 2,000 hours
(b) Standard Hours - 22,500 Net Actual Hours 28,500 hours Idle Time 1,500 hours
(c) Standard Hours 24,000 Net Actual Hours 29,000 hours Idle Time 1,000 hours
(d) Standard Hours - 25,000 hours Net Actual Hours -28,000 hours Idle Time - 2,000 hours
9.
K Ltd. is a manufacturer of a single product A. 8,000 units of the product A has been produced
in the month of March 2024. At the beginning of the year a total 1,20,000 units of the product-
The actual cost data for the month of March 2024 are as follows:
Fixed ₹ 1,19,000 Variable ₹ 48,000
Semi-Variable ₹ 19,200
The cost department of the company is now preparing a cost variance report for managerial
information and action. You being an accounts officer of the company are asked to calculate the
following information for preparation of the variance report:
i. What is the amount of variable overhead cost variance for the month of March 2024:
(a) ₹ 10,200 (A) (b) ₹ 10,400 (A)
(c) ₹ 10,800 (A) (d) ₹ 10,880 (A)
ii. What is the amount of fixed overhead volume variance for the month of March 2024:
(a) ₹ 9,000 (F) (b) ₹ 9,000 (A)
(c) ₹21,800 (A) (d) ₹ 11,000 (A)
iii. What is the amount of fixed overhead expenditure variance for the month of March 2024:
(a) ₹21,520 (A) (b) ₹ 21,500 (A)
(c) ₹21,400 (A) (d) ₹ 21,480 (A)
iv. What is the amount of fixed overhead calendar variance for the month of March 2024:
(a) ₹ 5,400 (A) (b) ₹ 5,450 (A)
(c) ₹ 5,480 (A) (d) ₹ 5.420 (A)
v. What is the amount of fixed overhead cost variance for the month of March 2024:
(a) ₹ 43,320 (A) (b) ₹ 43,300 (A)
(c) ₹ 43,200 (A) (d) ₹ 43,380 (A)
10. Following is the data of BROS Ltd relating to standard and actual labour
• Standard Data
- Grade 1: Takes 1 hr p.u. @` 20 per hour
- Grade 2: Takes 0.5 hr p.u @` 10 per hour
11. A company manufactures a product with the following standard cost per unit:
• Direct Material: 5 kg @ ₹10 per kg
• Direct Labor: 2 hours @ ₹15 per hour
• Variable Overheads: 2 hours @ ₹8 per hour
The standard output is 1,000 units. The actual production was 900 units, with actual usage of
4,800 kg of material at ₹11 per kg, 1,850 labor hours at ₹16 per hour, and actual variable
overheads of ₹14,800.
12. XYZ Manufacturing Ltd. produces kitchen appliances and implements a standard costing system to
monitor performance. The company has provided the following data for the month of September:
• Budgeted Output: 10,000 units
• Actual Output: 9,000 units
• Budgeted Hours: 20,000 hours
• Actual Hours Worked: 18,500 hours
• Standard Time per Unit: 2 hours
• Actual Time per Unit: 2.05 hours
• Standard Rate per Labor Hour: ₹25
• Actual Rate per Labor Hour: ₹28
XYZ Ltd. management is analysing these ratios to assess the company’s operational performance
for the month.
1. What is XYZ Ltd.'s Capacity Ratio for September?
(A) 0.925 (B) 0.900
(C) 0.9255 (D) 0.9257
3. What is the Labor Rate Variance for XYZ Ltd. for the month of September?
(A) ₹ 55,500 Unfavorable (B) ₹ 64,750 Unfavorable
(C) ₹ 64,750 Favorable (D) ₹ 55,500 favorable
On the basis of analysis of standard costing system, company's management wants to take actions
like supplier negotiation, process optimisation, employee training, etc.
Being the cost manager of the company, you are required to answer the following five
requirements of the management:
14.
XYZ Manufacturing Ltd. is a mid-sized enterprise that has established a strong reputation in the
field of precision engineering. The company specializes in producing high-quality engineering
components that meet the stringent requirements of various industries including automotive,
aerospace, medical devices, and industrial machinery. With a commitment to precision and
excellence, XYZ Manufacturing Ltd. has positioned itself as a reliable supplier of critical
components that demand the highest levels of accuracy and durability.
To maintain stringent control over its production costs and enhance cost efficiency, XYZ
Manufacturing Ltd. operates under a standard costing system. This system plays a pivotal role in
the company's financial and operational management. Standard costing involves setting
predetermined costs for each production element, including materials, labor, and overheads.
These predetermined costs, known as standard costs, serve as benchmarks against which actual
production costs are measured.
Particulars Budgeted Data Actual Data
Units Produced 10,000 units 9,500 units
Fixed Overheads ` 20,00,000 ` 19,50,000 + ₹ 1,00,000 (additional quality control
cost for 1,000 units chosen on sample basis)
Hours Worked 15,000 hours 14,250 hours
Variable ` 50 per hour ` 50 per hour (first 10,000 hours) ` 60 per hour
Overhead Rate (additional hours)
Based on the given information, you are being required to answer the following questions
1. What is the Fixed Overhead Cost Variance for XYZ Manufacturing Ltd. in May 2024?
(a) ₹ 50,000 (A) (b) ₹ 1,00,000 (A)
(c) ₹ 1,50,000 (A) (d) ` 2,00,000 (A)
2. What is the Fixed Overhead Volume Variance for XYZ Manufacturing Ltd. in May 2024?
(a) ₹ 50,000 (F) (b)₹ 50,000 (A)
(c) ` 1,00,000 (F) (d) ₹ 1,00,000 (A)
4. What is the Variable Overhead Expenditure Variance for XYZ Manufacturing Ltd. in May 2024?
(a) ₹ 40,000 (A) (b) 42,500 (A)
(c)` 45,000 (A) (d) ₹ 45,030 (A)
5. What is the Fixed Overhead Expenditure Variance for XYZ Manufacturing Ltd. in May 2024?
(a) ₹ 50,000 (F) (b) ₹ 50,000 (A)
(c) ₹ 1,00,000 (F) (d) ₹ 1,00,000 (A)
15.
A garment manufacturer has been producing and selling T-shirts exclusively for Indian market.
His T-shirts are made of a specific material which is eco-friendly. It means that T-shirts are
bio-degradable in soil after they become unsuitable for use.
This invention has been applauded throughout the country. Owner, Vikas, registered for the
patent rights for his invention so that no one else could use it.
Vikas feels that this invention will also be liked in foreign markets, and thus plans to expand his
business outside India. He feels that US market is the first foreign market he should tap into.
Direct material 90
Direct labour 60
Special service 80
(Used in T-shirt making, 50% fixed)
Fixed overhead 50
Administration overhead (fixed) 20
Total cost per T-shirt 300
(+) Profit margin 200
Selling price in India 500
There is no limitation of any resources in India. Vikas is able to sell 80,000 T-shirts each year.
He is currently working at 80% of his total capacity.
After searching for potential customers in US, Vikas received an inquiry for 30,000 units from
a wholesale distributor in California. As per the inquiry, order will be placed if price per T-shirt
is reasonable and the order has to be satisfied in full.
Vikas decided to send a quote and the order was placed by the foreign client, on the same day.
Vikas, without a second thought accepted the order, but did not feel the need to extend the
manufacturing capacity; therefore, he decided forgo a few Indian clients.
The shipping company, which was booked by Vikas for taking the consignment to US, got delayed
due to bad weather. Stock was held at port for 5 days and on 6th day it was loaded on ship.
Shipping company charged ₹ 2,800/10kg of goods. Insurance was charged flat at ₹ 1,11,000.
There is no custom duty on such exports.
1. Vikas had sufficient funds in his hands but he still raised a short-term working capital loan @
6.5% p.a. for the satisfaction of this foreign order because he found a onetime investment
opportunity which was giving him 9.25% returns. Foreign order was accepted on 1st June and
loan was taken on the same day. Repayment of the loan will be made on 1st September.
Calculate net cash outflow due to this export order. Which of the following is correct?
(a) ₹ 73,91,000 (b) ₹ 75,47,750
(c) ₹ 74,76,500 (d) ₹ 71,06,000
2. What would have been the minimum price that Vikas could have quoted per T-shirt in US
dollars? (exchange rate on 1st June, $1 = ₹ 83.86)
(a) $ 4.23 (b) $ 4.20
(c) $ 4.17 (d) $ 4.05
3. Payment from foreign client was received on 8th October when exchange rate was ₹ 86 for
each US $. Calculate the profit earned from this export order if actual quoted price was
$4.90 per T-shirt. Select the correct amongst following:
16.
ALZO Toys Ltd. is an exciting new player in the toy manufacturing industry, founded with a
passion for creating high-quality, engaging, and educational toys. The company aims to make a
positive impact on the industry and also on the development of young minds through imaginative
play.
The following statement provides a comprehensive analysis of the various cost variances for a
particular period, outlining the differences between the expected costs and the actual
expenditures incurred.
Cost variances (₹)
Direct material price 25,000F
Direct material usage 3,750A
Direct labour rate 5,000A
Direct labour efficiency 3,750A
Variable overhead expenditure 15,000A
Variable overhead efficiency 1,875A
Fixed overhead expenditure 62,500F
The budget for the same period reflected the following data:
Production volume 7,500 units
Direct materials purchased 3,750kg
Direct materials used 3,750kg
Direct material cost ₹ 1,12,500
Direct labour hours 5,625 hours
Direct labour cost ₹ 1,12,500
Variable overhead cost ₹ 56,250
Fixed overhead cost ₹ 1,12,500
Some other information relating to the same period is provided below:
(i) Stocks of raw materials and finished goods are valued at a predetermined standard cost for
easier cost comparison and reporting.
(ii) The actual number of units produced was 7,750.
(iii) The direct materials purchased were 5,000 kg.
From the information given above, you are required to FIGURE OUT the following in actual:
1. Quantity of materials used and direct material cost-
(a) 3,875 kg and ` 1,50,000
(b) 3,875 kg and ` 1,25,000
1. (a) 5580
The usage must have been higher than standard because the usage variance is adverse.
Usage variance is equal to the excess usage multiplied by the standard price per kg of material.
` 23,124
Standard price per kilogram of material : = ` 4.10
` 5640
` 246
Number of kilogram excess usage : = 60kg
` 4.1
Standard usage : 5640 kg – 60 kg = 5580 kg.
2. (A) ₹ 75,00,000.
Fixed Overhead Cost Variance=Budgeted Fixed Overhead−Actual Fixed Overhead Incurred
Given in the problem:
Budgeted Fixed Overhead = ₹ 75,00,000
Fixed Overhead Cost Variance = ₹ 0 (since there is "no Fixed overhead cost variance")
Substituting the values:
₹ 0=₹ 75,00,000−Actual Fixed Overhead Incurred
Actual Fixed Overhead Incurred=₹ 75,00,000
The actual units produced (15,600) and budgeted units (15,000) are irrelevant for the calculation
of the total Fixed Overhead Cost Variance.
3. (a) 3000A
1 sofa - 5 [Link]
4. (c) ` 50.50
1 unit - 30 mins
5.
Standard labour cost ₹
(1,000 hours × R` 0.50) 500
Actual wages paid 360
Actual rate per hour: ` 360/800 hours = ` 0.45
Calculation of Variances
(i) Rate variance = Actual time (Standard rate – Actual rate)
= 800 hours (` 0.50 – ` 0.45) = ` 40 (F)
(ii) Efficiency variance = Standard rate per hour (Standard time – Actual time)
= ` 0.50 (1,000 hrs. – 800 hrs.) = ` 100 (F)
(iii) Total labour cost variance= Standard labour cost – Actual labour cost
= (Standard rate × standard time) – (Actual rate × Actual time)
= (` 50 × 1,000 hrs.) – (` 45 × 800 hrs.)
= ` 500 – ` 360
= ` 140(F).
6.
7.
(b) ` 5.30 Material Price Variance = (Standard Price - Actual Price) x Actual Quantity
600 = (5.50 - AP) x 3,000
AP = 5.50 - 0.20 = `5.3
(iii) (d) Standard Hours - 25,000 hours Net Actual Hours -28,000 hours Idle Time - 2,000
hours
Standard Hours - 25,000 hours Net Actual Hours - 28,000 hours
Idle Time - 2,000 hours.
Actual output = 10,000 units
Standard hours per unit = 2.5
Therefore standard hours = 10,000 x 2.5 = 25,000 hours.
Idle time variance = SR × (Net AH - AH)
5 x (Net AH - 30,000) = 10,000 Adverse
5 Net AH - 1,50,000 = - 10000
5 Net AH = 1,40,000
Net AH = 28,000 hours
Idle time = 2,000 hours
115 CA/CS Nimeet Piti | | |
(iv) (c) Labour Efficiency Variance - 25,000 Adverse, Labour rate Variance 30,000
Favourable
Labour Efficiency Variance – 25,000 Adverse,
Labour rate Variance - 30,000 Favourable
Efficiency Variance = SR × (SH - AH)
= 5 × (25,000 – 30,000)
= 25,000 Adverse
Rate Variance = AH × (SR - AR)
1,20,000
= 30,000 (5 - 4)
30,000
= 30,000 Favourable.
Actual Amt
Fixed - 119,000
+ FC of S. VOH O/H 11,520
(19200 × 60%) 130,520
Calendar variance
(20 - 19) 5450
5450A
Actual amt
VOH P.a. 600,00 Variable 48000
VOH of SVOH 72,000 V of SVOH 7680
(180,000 × 40%) 672000 – 120,000 units (192000 × 40%)
VOH Pu : 5.6 Pu 55680
i) (c) 10,880(A)
refer working above
ii) (c) 21,800(a)
refer working above
iii) (a) 21,520(A)
refer working above
iv) (b) 5,450(A)
refer working above
v) (a) 43,320(A)
refer working above
2.(a) 0.9729
Efficiency ratio = Standard hours for Actual output × 100
Actual hours for Actual output
9000units × 2hrs
= × 100
18500 hrs
= 97.29% or 0.9729
13. 1. (a) Material Mix Variance (Cotton + Polyester) = {(RSQ × SP) – (AQ × SP)}
= {7,08,570- 7,10,000} = 1,430 (A)
Material Yield Variance (Cotton + Polyester) = {(SQ × SP) – (RSQ × SP)}
= {7,51,770 – 7,08,570} = 43,200 (F)
2. (d) Material Price Variance (Cotton + Polyester) = {(AQ × SP) – (AQ × AP)
= {7,10,000 – 6,72,500} = 37,500 (F)
3. (c) Material Cost Variance (Cotton + Polyester) = {(SQ × SP) – (AQ × AP)}
= {7,51,770 – 6,72,500} = 79,270 (F)
Working Note
Material Variances:
Material SQ SQ× SP RSQ RSQ × AQ AQ × SP AP AQ × AP
(WN-1) (₹) (WN-2) SP (₹) (₹) (₹) (₹)
Cotton 9,397 m 4,69,850 8,857 m 4,42,850 9,000 m 4,50,000 48 4,32,000
Polyester 7,048 m 2,81,920 6,643 m 2,65,720 6,500 m 2,60,000 37 2,40,500
16,445 m 7,51,770 15,500 m 7,08,570 15,500 m 7,10,000 6,72,500
5. (a) Labour Cost Variance (Skilled + Unskilled) = {(SH × SR) – (AH × AR)}
= {61,496 – 62,380} = 884 (A)
Working Note
Labour Variances:
Labour SH (WN- SR SH × SR RSH RSH × AH AH × SR AR AH × AR
3) (₹) (₹) (WN-4) SR (₹) (₹) (₹) (₹)
Skilled 1,116 hrs 37.5 41,850 1,144 42,900 1,200 45,000 35.5 42,600
Unskilled 893 hrs 22 19,646 916 20,152 860 18,920 23 19,780
2,009 hrs 61496 2,060 63052 2,060 63920 62380
14.
1. (c) ` 1,50,000 (A)
Fixed Overhead Cost Variance = Absorbed Fixed Overheads - Actual Fixed Overheads
Absorbed Fixed Overheads = (Budgeted Fixed Overheads / Budgeted Production) x Actual
Production = (` 20,00,000 / 10,000 units) x 9,500 units
= ` 19,00,000
Adjusted Actual Fixed Overheads = ` 19,50,000 + ` 1,00,000 = ` 20,50,000
Fixed Overhead Cost Variance = ` 19,00,000 - ` 20,50,000 = ` 1,50,000 (Adverse)
3. (c) 0
Variable Overhead Efficiency Variance = (Standard Hours for Actual Production - Actual Hours
Worked) x Standard Variable Overhead Rate
Standard Hours for Actual Production = 9,500 units x 1.5 hours/unit = 14,250 hours
Variable Overhead Efficiency Variance = (14,250 – 14,250) x ` 50 = 0
2. (a) $ 4.23
Minimum price :-
Variable cost (net) 75,47,750
Add: fixed cost recovery (110 x 10,000 units) 11,00,000
Add: loss of profit (200 x 10,000 units) 20.00.000
Minimum price 1,06,47,750
Minimum price per unit 1,06,47,750/30,000 ₹ 354.925
Minimum price is $ ($1 = ₹ 83.864) $4.23
3. (c) ` 39,94,250
PROFIT EARNED:
SALES ($4.90 x 30,000 x RS. 86) ` 1,26,42,000
(-) Variable cost (net) (75,47,750)
(-) allotted fixed cost (10,000 units x110) (11,00,000)
PROFIT ` 39,94,250
4. (d) ` 50,94,250
CASH INFLOW:
SALES ($4.90 x 30,000 x RS. 86) ` 1,26,42,000
(-) Variable cost (net) (75,47,750)
CASH INFLOW ` 50,94,250
5. (a) ` 19,94,250
Incremental benefits:
SALES ($4.90 x 30,000 x RS. 86) ` 1,26,42,000
(-) Variable cost (net) (75,47,750)
(-) allotted fixed cost (10,000 units x110) (11,00,000)
(-) loss of profit (10,000x200) (20,00,000)
Incremental benefits 19,94,250
3,750 𝑘𝑔
=( ) = 0.5𝐾𝑔
7,500 𝑢𝑛𝑖𝑡𝑠
` 1,12,500
=( ) = 30
3,750 𝑘𝑔
Material usage variance = (Std. qty. for actual output - Actual qty.) × Std. price
3,750A = [(7,750 x 0.5kg) - AQ] x ` 30
- ` 3,750 = ` 1,16,250 - 30AQ
30AQ = ` 1,20,000
AQ = 4,000 kg
Actual quantity of materials used = 4,000 kg
2. (b)
𝐵𝑢𝑑𝑔𝑒𝑡𝑒𝑑 ℎ𝑜𝑢𝑟𝑠
𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑 ℎ𝑜𝑢𝑟𝑠 𝑝𝑒𝑟 𝑢𝑛𝑖𝑡 𝑜𝑓 𝑜𝑢𝑡𝑝𝑢𝑡 = ( )
𝐵𝑢𝑑𝑔𝑒𝑡𝑒𝑑 𝑜𝑢𝑡𝑝𝑢𝑡
5,625 ℎ𝑜𝑢𝑟𝑠
=( ) = 0.75𝐻𝑜𝑢𝑟𝑠
7,500 𝑢𝑛𝑖𝑡𝑠
1,12,500
=( ) = 20
5,625 ℎ𝑜𝑢𝑟𝑠
3.
(b) Labour Cost Variance = [Standard Labour Cost – Actual Labour Cost]
Labour Rate Variance + Labour Efficiency Variance = [Standard Labour Cost – Actual Labour
Cost]
5,000A + 3,750A = (7,750 x 0.75 hours x 20) - Actual Labour Cost
- 5,000 - 3,750 = ` 1,16,250 – Actual Cost
Actual Labour Cost = ` 1,16,250 + ` 8,750
Actual Labour Cost = ` 1,25,000
Total Variable Overhead Variance = [Standard Variable Overhead – Actual Variable Overhead]
Variable Overhead Expenditure Variance + Variable Overhead Efficiency Variance = [Standard
Variable Overhead – Actual Variable Overhead]
15,000A + ` 1,875A = (7,750 x ` 7.50) - Actual Variable Overhead
- ` 15,000 - ` 1,875 = ` 58,125 - Actual Variable Overhead
Actual Variable Overhead = ` 58,125 + ` 16,875
Actual Variable Overhead = ` 75,000
5.
(d) Fixed Overhead Expenditure Variance = Budgeted Fixed Overheads - Actual Fixed
Overheads
62,500 F = ` 1,12,500 - Actual Fixed Overheads
Actual Fixed Overheads = ` 50,000
1. A company’s fixed costs are ₹ 5,00,000, the selling price per unit is ₹ 200, and the variable cost
per unit is ₹ 100. How many units must the company sell to earn the targeted profit of ` 2,00,000?
(a) 2,000 units (b) 5,000 units
(c) 10,000 units (d) 7,000 units
2. Ms. Gauri has the business of selling pens. She has setup this pen retailing for over 10 years with
good profit volume ratio. Her average cost from the retailing is ` 11.25 per unit if she sells 16,000
units and is ` 11 per unit if she sells 20,000 units.
For the current month, she also charged ` 5,000 towards depreciation and the rental payment
due.
The excess of sales revenue over the variable costs is ` 3.333 per unit.
You are required to CALCULATE Break-even Point (in units), Cash Break-even Point (in units) and
Profit Volume Ratio.
(a) Break-even Point - 6,000 units, Cash Break-even Point - 6,000 units and Profit Volume Ratio
- 33.33%
(b) Break-even Point - 6,000 units, Cash Break-even Point - 4,500 units and Profit Volume Ratio
- 25%
(c) Break-even Point - 4,500 units, Cash Break-even Point - 4,500 units and Profit Volume Ratio
- 33.33%
(d) Break-even Point - 4,500 units, Cash Break-even Point - 4,500 units and Profit Volume Ratio
- 25%
3. A company’s sales could decrease by 50% before it starts incurring losses. And, for every Re. 1 of
sales, it can contribute 40 paise towards fixed costs and generating profit. For the current year,
the company’s fixed cost amounts to ` 5,00,000. CALCULATE the Projected sales.
(a) ` 10,00,000 (b) ` 12,50,000
(c) ` 20,83,333 (d) ` 25,00,000
4. A meeting of the heads of departments of the Arnav Ltd. has been called to review the operating
performance of the company in the last financial year. The head of the production department
appraised that during the last year the company could operate at 70% capacity level but in the
coming financial year 95% capacity level can be achieved if an additional amount of ₹ 100 Crore
on capex and working capital is incurred.
The head of the finance department has presented that during the last financial year the company
had a P/V ratio of 40%, margin of safety and the break-even were ₹ 50 crore and
₹ 200 crore respectively.
The following points is required to be calculated on urgent basis to put the same in the meeting.
You being an assistant to the head of finance, has been asked the followings:
1. What will be the revised sales for the coming financial year?
(a) ₹ 322.22 Crore (b) ₹ 311.11 Crore
(c) ₹ 300.00 Crore (d) ₹ 324.24 Crore
2. What will be the revised break-even point for the coming financial year?
(a) ₹ 222.22 Crore (b) ₹ 252.22 Crore
(c) ₹ 244.44 Crore (d) ₹ 255.56 Crore
3. What will be the revised margin of safety for the coming financial year?
(a) ₹ 100 Crore (b) ₹ 58.89 Crore
(c) ₹ 55.56 Crore (d) ₹ 66.66 Crore
4. The profit of the last year and for the coming year are:
(a) ₹ 50 Crore & ₹ 95 Crore respectively
(b) ₹ 20 Crore & ₹ 65 Crore respectively
(c) ₹ 20 Crore & ₹ 30 Crore respectively
(d) ₹ 45 Crore & ₹ 66.66 Crore respectively
5. The total cost of the last year and for the coming year are:
(a) ₹ 230 Crore & ₹ 292.22 (b) ₹ 230 Crore & ₹ 275 Crore
(c) ₹ 220 Crore & ₹ 282.22 Crore (d) ₹ 220 Crore & ₹ 292.22 Crore
5. XYZ Manufacturing Pvt. Ltd is a prominent company in the electric appliances industry, known for
producing a diverse range of high-quality products. The company has built a reputation for
reliability and innovation in the manufacturing of household appliances, including fans, mixers, and
heaters. XYZ Manufacturing Pvt. Ltd is dedicated to delivering products that meet the needs of
its customers while adhering to the highest standards of quality and performance
The company operates a state-of-the-art factory that is fully equipped with advanced machinery
and technology to ensure efficient and consistent production. The factory operates 25 days a
Additional Info: Raw Materials include Copper, Plastic, and Other Materials. The per unit cost of
Copper is 80 more than the cost of Plastic, while the cost of Other Materials is twice that of
Plastic And the total Raw Material Cost per unit is 210 more than the combined cost of Copper &
Plastic.
The Labour Hour Rate is 100 per hour. The total labour hours used in the last month were 36,000
Hours. The Utilities Cost per unit is 100, and the Packaging Cost per unit is 50. Being a finance
manager of the company, you are required to answer the following:
3. If the company wants to achieve a target profit of 5,00,000, what should be the sales
volume (in units)?
(a) 2,000 units (b) 2,727 units
(c) 2,750 units (d) 3,000 units
4. What would be the impact on the break-even point if the variable cost per unit increases by
10%?
5. Calculate the margin of safety in percentage if the company sells 4,000 units if the variable
cost per unit increases by 10%
(a) 44.85% (b) 42.55%
(c) 45.05% (d) 45.75%
6. Miniso Pvt Ltd a company engaged in the business of manufacturing wireless Bluetooth earphones.
The company wishes to track its operating profitability and the margin it needs to maintain to
sustain profitability in the long run Further the company has adopted the marginal costing
technique to identify and define operational levels. In this regard the company has provided the
following information for the current year:
Opening stock of earphones 30,000 units
Selling Price of the earphones ₹ 450 per unit
Variable costs incurred in manufacture ₹ 270 per unit
Units produced during the previous year 1,80,000 units
Expected production for the current year 2,25,000 units
Expected sales for the current year 2,40,000 units
Fixed cost per unit for last year was ₹ 60 per unit
Expected rise in Fixed Cost 10%
Expected Increase in Variable cost 2.5%
3. The total fixed cost for the current year post the cost increase amounts to
(a) 1,08,00,000 (b) 1,48,50,000
(c) 1,18,80,000 (d) 1,44,00,000
7. Gamma Foods Ltd. produces gourmet snacks. The management is considering whether to continue
producing one of its products, Product P, based on its contribution margin. Below are the relevant
details for the last financial year.
Cost Information:
• Selling Price per Unit: ₹100
• Variable Costs per Unit:
- Direct Materials: ₹30
- Direct Labor: ₹20
- Variable Overhead: ₹10
• Total Fixed Costs: ₹ 15,00,000
• Units Produced and Sold: 50,000 units
Additional Information:
• A market analysis indicates that sales could increase by 10% if they offer a special discount
of 15% on the selling price.
• If the special discount is applied, the company believes that it can keep the fixed costs
unchanged but anticipates an increase in variable costs by 5% due to higher production
volume and potential wastage.
1. If Gamma Foods Ltd. decides to discontinue Product P, what would be the impact on total
contribution margin if the product has a current contribution margin of ₹40 per unit and
total fixed costs are unaffected?
(a) Total contribution margin remains the same
(b) Total contribution margin decreases by ₹ 20,00,000 (right answer)
(c) Total contribution margin increases by ₹ 20,00,000
(d) Total contribution margin decreases by ₹ 15,00,000
2. Calculate the break-even point in units for Product P after the special discount is applied
and the variable costs have increased.
(a) 68,182 units (b) 61,225 units
(c) 60,000 units (d) 40,541 units
3. If the sales increase by 10% due to the discount, what will be the total contribution margin
after applying the discount and the new variable costs?
8. Gamma Ltd. manufactures Product A, and the company uses a standard costing system to control
costs. The standard cost per unit of Product A includes:
• Direct Material: ₹6
• Direct Labor: ₹4 (0.5 hours @ ₹8 per hour)
• Variable Overheads: ₹2
• Fixed Overheads: ₹8
• The selling price per unit is ₹20.
The company expected to produce 5,000 units in October, with fixed costs budgeted at ₹40,000.
However, due to inefficiencies in labour, the actual labour hours worked were higher than
expected, resulting in a labour efficiency variance of ₹5,000 adverse.
Gamma Ltd. wants to calculate the new break-even point after incorporating this labour efficiency
variance, and how this variance affects their profit margins.
1. What was Gamma Ltd.’s original break-even point before considering any variances?
(a) 12,500units (b) 4,167 units
(c) 10,000 units (d) 5000 units
2. What is the revised variable cost per unit after considering the labour efficiency variance?
(a) ₹12.50 (b) ₹13.00
(c) ₹14.00 (d) ₹15.00
3. What is the new break-even point after factoring in the labour efficiency variance?
(a) 15,000 units (b) 10,000 units
(c) 12,500 units (d) 14,286 units
4. How much additional profit would Gamma Ltd. lose for each unit sold if it fails to control its
labour efficiency?
(a) ₹2 per unit (b) ₹1 per unit
(c) ₹3 per unit (d) ₹5 per unit
9. Popular company produces various articles for student purposes. It has been in industry since last
25 years. Company had a very humble start but gained popularity over the years due to excellent
quality products which were sold at very competitive prices. Company has huge reserves and feel
that it is also obligated to give back to the society from which it has grown.
Last year management decided to produce and supply special quality school bags, water bottles,
& geometry boxes to NGOs, at no price, as a social responsibility. These articles were simple
The variable costs are ` 100, ` 80, and ` 40 for school bags, water bottles, and geometry boxes,
respectively. These articles are made using a single machine. 0.20 hours of machine operation is
required for manufacturing 1 unit of school bag. Similarly, machine hours required for each units
of water bottle and geometry box is 0.15 hours and 0.10 hours, respectively. Fixed overhead
related to machine is ` 7,40,000 per year. Machine can operate for 8,000 hours in a year.
Company has decided to sell its 80% capacity production in markets. Rest is divided amongst the
2 undergoing social works, equally.
All Schools requests these items in the ratio of [Link], as per their demand by the school students.
Company wants to set a price for these articles to be offered to the schools. Management has
few questions they need the answers to. They assigned the task to their team. Team made rough
calculations but as there were too many people on the team, each came up with different answers.
As a Chartered accountant, you have been approached. Understand the case closely, find the
correct answers and help management to set a price.
1. What is allocated fixed cost per unit of School bags, water bottles, and geometry boxes?
(a) 18.5, 13.875, 9.75 (b) 18.5, 13.875, 9.25
(c) 18.5, 13.785, 9.25 (d) 18.5, 13.785, 9.50
2. If the prices were ` 200, ` 160, and ` 100, what would be the overall break-even point in units
in relation to fixed cost allocated to these supplies?
(a) 308.33 units (b) 500 units
(c) 508.33 units (d) 1,000 units
3. Find out the maximum number of units of each article that can be given at the prices given
in Part (ii).
(a) 61, 92, 154 (b) 200, 300, 500
(c) 101, 152, 254 (d) 100, 150, 250
4. What will be the maximum units that can be supplied to the schools of each article?
(a) 1103, 1645, 2726 (b) 1093, 1655, 2748
(c) 1185, 1777, 2962 (d) 1133, 1675, 2958
10. A garment manufacturer has been producing and selling T-shirts exclusively for Indian market.
His T-shirts are made of a specific material which is eco-friendly. It means that T-shirts are bio-
degradable in soil after it becomes unsuitable for use.
This invention has been applauded throughout the country. Owner, Vikas, registered for the patent
rights for his invention so that no one else could use it.
Vikas feels that this invention will also be liked in foreign markets, and thus plans to expand his
business outside India. He feels that US market is the first foreign market he should tap into.
There is no limitation of any resources in India. Vikas is able to sell 80,000 T-shirts each year. He
is currently working at 80% of his total capacity.
After searching for potential customers in US, Vikas received an inquiry for 30,000 units from a
wholesale distributor in California. As per the inquiry, order will be placed if price per T-shirt is
reasonable and the order has to be satisfied in full.
Vikas decided to send a quote and the order was placed by the foreign client, on the same day.
Vikas, without a second thought accepted the order, but did not feel the need to extend the
manufacturing capacity; therefore, he decided forgo a few Indian clients.
This foreign order also required special packaging. It is spent at 20% of the total prime cost per
T-shirt. The production was done quickly and foreign consignment was transported to custom port
via services from a carriage agency. It charged ₹80,000 for 1 truck, whose capacity was 500 kg, to
transport whole of the consignment. Truck was 20% vacant after loading the consignment. Bill of
lading was filed and a professional fee of ₹25,000 for filing this was paid to a Chartered accountant.
Custom port also charged ₹80 per kg per day to handle the material, storing it in warehouse, and
for loading the goods on ship.
1. Vikas had sufficient funds in his hands but he still raised a short-term working capital loan @
6.5% p.a. for the satisfaction of this foreign order because he found a one-time investment
opportunity which was giving him 9.25% returns. Foreign order was accepted on 1st June and
loan was taken on the same day. Repayment of the loan will be made on 1st September. Calculate
net cash outflow due to this export order. Which of the following is correct?
(a) ₹73,91,000
(b) ₹75,47,750
(c) ₹74,76,500
(d) ₹71,06,000
2. What would have been the minimum price that Vikas could have quoted per T-shirt in US dollars?
(exchange rate on 1st June, $1=₹83.86)
(a) $4.23
(b) $4.20
(c) $4.17
(d) $4.05
3. Payment from foreign client was received on 8th October when exchange rate was ₹86 for each
US $. Calculate the profit earned from this export order if actual quoted price was $4.90 per
T-shirt. Select the correct amongst following:
(a) ₹40,65,500
(b) ₹41,51,000
(c) ₹39,94,250
(d) ₹44,36,000
2. (b) Break-even Point - 6,000 units, Cash Break-even Point - 4,500 units and Profit Volume
Ratio – 25%
Step Formula / Work Value
From averages: FC Solve 11.25−11=
𝐹𝐶
−
𝐹𝐶
⟹FC=₹20,000 ₹20,000
16,000 20,000
Variable cost per unit v 𝐹𝐶
v=11−20,000=11−1 ₹10.00
3. (d) 25,00,000
Margin of Safety = 50%
P/V ratio = 40%
Fixed Cost = ` 5,00,000
Fixed Cost 5,00,000
Break − even Sales (BES) = =
𝑃 0.40
𝑅𝑎𝑡𝑖𝑜
𝑣
BES = 12,50,000
Margin of Safety = Projected sales(S) – Break Even Sales (BES)
S = BES + Margin of Safety
S = ` 12,50,000 + (0.50 x S)
Or, S – 0.50S= ` 12,50,000
Or, S = ` 25,00,000
Revised Profit
Current Profit 20 Crs
+ Additional 10 crs
30 crs
Revised P/V ratio
If current SP pu assumed – 100 (100%)
Current VC PV will be – 60 (60%)
Current contribution will be – 40 (40%)
5.(c) 45.05%
Total units sold 4000
(-) Break-even units 2198
Margin of safety units 1802
Mosunits
MOS% = 100
Totalunits
1802
= 100
4000
= 45.05%
1) (c) 1,71,45,000
Refer working above
2) (b) 87,600 units
Refer working above
3) (c) 1,18,80,000 units
Refer working above
4) (c) 15,000 & 50,62,500
Refer working above
5) (b) 152,400 units
Refer working above
iii.(d) ₹ 1,210,000
Revised contribution per unit (refer above) 22 pu
× units sold (50,000 + 10%) 55000
Revised contribution 12,10,000
ii.(b) ₹13.00
Labour efficiency variance = 500A
no. of units produced = 5000
Increase in variable cost p.u. 1
Original variable cost p.u. 12
Revised variable cost p.u. 13
iii.
SP pu 20
Revised VC pu 13
Contribution pu 7
Fixedcosts 40,000
BEP = = = 5714.28 units
Contribution p.u 7
9. (a) ₹ 92,400
General Administration Overheads
Hiring charges for cars 66,000
Reimbursement of diesel 22,000
88,000
+ GST on RCM basis @ 5% of 88000 4400
Total General Admini O/H 92,400
Net amount of interest earned: (Interest earned in 9.25% and paid is 6.50% for 3 months)
76,00,000×(9.25%−6.50%)×3/12=₹52,250
Net cash outflow due to export order:
76,00,000−52,250=₹75,47,750
2. (a) $4.23.
Minimum Price Calculation
Amounts (₹)
Minimum price: - Variable cost (net) 75,47,750
Add: fixed cost recovery (110×10,000 units) 11,00,000
Add: loss of profit (200×10,000 units) 20,00,000
Minimum price 1,06,47,750
Minimum price per unit 1,06,47,750/30,000 ₹354.925
Minimum price in $ ($1=₹83.864) $4.23
3. (c) ₹39,94,250.
Profit Calculation
(₹)
SALES ($4.90×30,000×Rs.86) 1,26,42,000
(-) Variable cost (net) −75,47,750
(-) allotted fixed cost (10,000 units×110) −11,00,000
PROFIT ₹39,94,250
5. (a) ₹19,94,250.
Incremental Benefits Calculation
(₹)
SALES ($4.90×30,000×Rs.86) 1,26,42,000
(-) Variable cost (net) −75,47,750
(-) allotted fixed cost (10,000 units×110) −11,00,000
(-) loss of profit (10,000×200) −20,00,000
Incremental benefits 19,94,250
1. AB Ltd. is currently preparing its production budget for product Z for the forthcoming year. The
sales director has confirmed that he requires 60,000 units of product Z. Opening inventory is
estimated to be 6,500 units and the company wishes to reduce inventory at the end of the year
by 50 %. How many units of product Z will need to be produced?
(a) 63,250 (b) 69,750
(c) 50,250 (d) 56,750
2. A business manufactures a single product and is preparing its production budget for the year
ahead. It is estimated that 2,00,000 units of the product can be sold in the year and the opening
inventory is currently 25,000 units. The inventory level is to be reduced by 40% by the end of
the year. What is production budget in units?
(a) 1,95,000 units (b) 1,90,000 units
(c) 1,84,000 units (d) 1,75,000 units
3. If activity ratio of a company is 104% and its capacity ratio is 96%, find out its efficiency ratio.
(a) 99.84% (b) 92.30%
(c) 108.33% (d) 98%
4. A factory has a capacity utilization ratio of 85% and its activity ratio is 95%.
Which one of the following is the efficiency ratio?
(a) 120% (b) 110%
(c) 112% (d) 90%
5. Standard hours required for doing a work is 100 hours and budgeted hours is 120 hrs while the
same work is actually completed by workers in 110 hrs. You are required to calculate the activity
ratio:
(a) 109.09% (b) 83.33%
(c) 90.90% (d) 110%
8. Healthy & Fit Ltd., manufactures sells a single product captioned as 'Exercise bikes'. The estimated
units to be sold in the last quarter of the year are as under:
Particulars January 2025 February 2025 March 2025
Exercise bikes (in units) 1,500 1,800 1,000
The company's policy is to hold closing stock of finished goods at 20% of the expected sales volume
of the succeeding month.
Each unit of exercise bike requires one unit of main body with resistance system & two units of
pedals. Calculate the number of pedals required to be purchased for January 2025 production.
(A) 1,560 pedals
(B) 1,440 pedals
(C) 3,120 pedals
(D) 2,880 pedals
9. A company prepares its monthly production budget using the following policy:
• 70% of the current month’s sales are to be produced in the same month.
• The company maintains an opening finished goods inventory of 6,000 units for June.
• The desired closing inventory for June is 30% of July’s forecasted sales.
The sales forecasts are as follows:
Month Sales Forecast (Units)
May 20,000
June 24,000
July 30,000
August 18,000
10. A company plans to produce 50,000 units during the budget period. To produce 1 unit of finished
goods, the company requires 5 units of raw material, including an allowance for 5% raw material
wastage during production. The company currently has 90,000 units of raw material in stock and
How many units of raw material should the company plan to purchase during the budget period?
(a) 3,45,000 units
(b) 3,50,000 units
(c) 2,80,000 units
(d) 3,70,000 units
11. PJ Ltd. is currently preparing cash budget for the year 2025. An extract from its sales budget for
the same year shows the following sales values:
(₹ ’000)
March 750
April 900
May 1,000
June 600
40% of its sales are expected to be for cash. Of its credit sales, 80% are expected to be realised
in the next month and the balance in the second month. The value of sales receipts to be shown in
cash budget for May 2025 is (in ₹ ’000):
(a) 840
(b) 922
(c) 948
(d) 1060
12. GHI Ltd. is preparing its budget for the coming year. The company is divided into three
responsibility centers: a cost center (Production), a profit center (Sales), and an investment
center (Regional Office). The following information is available:
• Production department's expected cost: ₹5,00,000 (fixed) and ₹50 per unit (variable)
• Sales department expects to sell 12,000 units at ₹150 per unit.
• The Regional Office is expected to earn a return of 10% on the capital employed of
₹20,00,000.
1. What is the total cost for the production department if 12,000 units are produced?
(a) ₹6,00,000 (b) ₹11,00,000
(c) ₹10,00,000 (d) ₹12,00,000
13. XYZ Limited produces the product P. The cost accountant of the company has to prepare its budget
for a particular year. The following information are made available for this purpose:
The expected sales of the product P is 1,00,000 units during the year at a selling price of ₹50 per
unit. Each unit of product P requires 3 kgs of raw material Q and 4 kgs of raw material R.
The expected stock levels are as follows:
Beginning of year End of year
Finished product P in units 12,000 15,000
Raw material Q in kgs 26,000 20,000
Raw material R in kgs 36,000 42,000
Raw material Q costs ₹2 per kg and R costs ₹3 per kg.
It requires 10 minutes of direct labour time to produce one unit of product P.
Labour cost is ₹50 per hour.
Variable manufacturing overheads are ₹10 per unit.
Fixed manufacturing cost is ₹3,00,000 per year.
Fixed Administration and selling expenses are ₹25,000 per year.
14.
Allure Metallurgy Ltd. is a stainless-steel manufacturing company which manufactures two grades
of stainless-steel products namely SS304 & SS316 made of a common raw material iron procured
at ₹52 per kg from the market. The usage of the raw material is expected to be at a constant rate
over the entire period. The raw material supplier to the company charges ₹24,000 per order but
its delivery is limited to 1,200 tons per annum. There is no alternate source to procure the raw
material. In consideration of the above limitations, the company decided to review its inventory
management policies for the forthcoming year.
The following forecasted information has been extracted from departmental estimates for the
budget year ending on 31st March 2025:
SS304 SS316
Sales (units) 56,000 86,000
Finished Goods stock increase by year end (units) 1,614 1,215
Post Production rejection rate (%) 3 7
Iron usage in kg (per completed unit, net of wastage) 5.5 8
Iron wastage (%) 8 11
1. The minimum number of units of SS304 & SS316 the company shall produce to justify the
sales forecast would be:
(A) 56,000 & 86,000
(B) 57,614 & 87,215
(C) 59,396 & 93,780
(D) 64,561 & 1,05,371
3. Assuming that all the available 1,200 tons of raw material is procured per annum and would
be utilized for production, what would be the raw material needed for production of SS304 in
order to maintain the same production mix arrived in Q-12 above?
(A) 3,26,678 kg
(B) 3,27,209 kg
(C) 3,55,085 kg
(D) 3,55,663 kg
4. Assuming that all the available 1,200 tons of raw material is procured per annum and would
be utilized for production, what would be the raw material needed for production of SS316 in
order to maintain the same production mix arrived in Q-12 above?
(A) 7,50,240 kg
(B) 7,51,460 kg
(C) 8,42,966 kg
(D) 8,44,337 kg
5. Assuming that all the available 1,200 tons of raw material is procured per annum and would
be utilized for production, what would be the raw material needed for production of SS316 in
order to maintain the same production mix arrived in Q-12 above?
(A) 7,50,240 kg
(B) 7,51,460 kg
(C) 8,42,966 kg
(D) 8,44,337 kg
15.
Valley Ltd., a medium-sized manufacturing firm, is reviewing its operational strategy for Q2 of
2025 due to an anticipated rise in market demand for its signature product, ‘X’—a pre-packaged
consumer item. To maintain profitability and manage costs efficiently, the management team is
preparing a detailed budget.
Based on above information, you are required to answer the following (MCQs 6 to 10):
1. The required production of “X” in second quarter will be:
(a) 45,000 bags
(b) 46,000 bags
(c) 61,000 bags
(d) 50,000 bags
2. What is the quantity to be purchased for ‘Y’, ‘Z’ and ‘Empty bags’?
(a) 1,41,000, 3,92,000 and 74,000
(b) 1,15,000, 3,45,000 and 46,000
(c) 1,30,800, 67,000 and 26,600
(d) 1,09,000, 3,35,000 and 37,000
3. What is the cost of quantity purchased for ‘Y’, ‘Z’ and ‘Empty bags’
(a) 1,30,800, 67,000 and 29,600
(b) 1,09,000, 3,35,000 and 37,000
(c) 1,41,000, 3,92,000 and 74,000
(d) 1,15,000, 3,45,000 and 46,000
1. (d) 56,750
Sales budget 60,000
+ Closing stock (65000 × 50%) 3250
- Opening Stock (6,500)
Production Budget 56,750
2. (b) 1,90,000
Sales budget 2,00,000
+ Closing stock (25000 × 40%) 15000
- Opening Stock (25000)
Production Budget 1,90,000
3. (c) 108.33%
Activity ratio = Capacity ratio × Efficiency ratio
104% = 96% × Efficiency ratio
104%
Efficiency ratio = = 108.33%
96%
4. (c) 112%
Activity ratio = Capacity ratio × Efficiency ratio
95% = 85% × Efficiency ratio
95%
= Efficiency ratio = 111.76% or 112%
85%
5. (b) 83.33%
Budgeted hours = 120 hrs
Standard hours for Actual hours = 100 hrs
Actual hours = 110 hrs
Standard hours
Activity ratio = ×100
Budgeted hours
100 hrs
= ×100 = 83.33%
120 hrs
6. (b) ₹ 34,00,000
in total overheads 40,00,000 - 30,00,000 10,00,000
= =
in % activity 75% - 50% 25%
4,00,000 per 10% = Variable overheads.
7. (c) It is probably the least time consuming and least costly approach to budgeting.
Explanation: ZBB is a budgeting method that requires starting from scratch each year, analyzing
every line of business for its needs and costs, and justifying all expenses for each new period. It
can help companies identify and eliminate unnecessary costs, and focus on high-profit initiatives.
However, it can be problematic to explain very item and cost, and may require training for
managers.
9. (d) 19,800
Production = 70% of June sales + 30% of July sales (Closing inventory) – Opening inventory
= 24,000 x 70% + 30,000 x 30% - 6,000 = 19,800 units
2.(b) ₹7,00,000
Sales (12,000 units 150 pu) ₹ 18,00,000
(-) Total Cost ₹ (11,00,000)
Budgeted Profit ₹ 7,00,000
13. Part 1, 2, 3
Sales =1,00,000
Clg FG =15,000
− Op FG =(12,000)
Prod'n budget =1,03,000
× kgs req.
Q (3 kgs) R (4 kgs)
Consumption budget 3,09,000 4,12,000
+ Closing RM 20,000 42,000
− Op RM -26,000 -36,000
Purchase budget 3,03,000 4,18,000
× Purchase price ₹2/kg ₹3/kg
6,06,000 12,54,000
Q1 1,03,000=A - refer working above
Q2 4,18,000=B - refer working above
Q3 6,06,000=E - refer working above
Q4. (D) ₹36.33
Q5. (A)
Sales: 1,00,000 units×₹50 =50,00,000
VC:1,00,000 units×₹36.33 =36,33,333
Contribution =13,66,667
(-) Fixed Costs:
Manufacturing Costs =(3,00,000)
Admin & Sales =(25,000)
Profit =₹10,41,667
4. (D) 8,44,337 kg
Available kgs = 1200 × 100 = 12,00,000 kgs
Kgs allocated to SS-304 = 3,55,663 kgs
∴ Kgs allocated to SS-316 = 8,44,337 kgs
5. (B) 7,51,460 kg
Particulars SS-304 SS-316
Kgs allocated 3,55,663 8,44,337
(-) Wastage 8% 11%
Net kgs (after wastage) 3,27,210 7,51,460
⇐ Kgs required per unit 5.5 kgs 8 kgs
Production (Gross) 59,493 units 93,933 units
(-) Rejection % 3% 7%
Production (Net) 57,708 units 87,358 units
15.
1. (b) 46,000 bags
2. (d) 1,09,000, 3,35,000 and 37,000
3. (a) 1,30,800, 67,000 and 29,600
4. (c) ₹ 6.50
5. (d) ₹ 47,500
Working Note:
(i) Production Budget of ‘X’ for the Second Quarter
Particulars Bags (Nos.)
Budgeted Sales 50,000
Add: Desired Closing stock 11,000
Total Requirements 61,000
Less: Opening stock 15,000
Required Production 46,000
(ii) Raw–Materials Purchase Budget in Quantity as well as in ₹ for 46,000 Bags of ‘X’
Particulars ‘Y’ Kgs. ‘Z’ Kgs. Empty Bags
Production Requirements 2.5 7.5 1.0